Learn More: www.wauwatosaschools.org/referendum REFERENDUM CONSTRUCTION UPDATE Wilson/WSTEM Elementary School February 2021 RECENTLY COMPLETED WORK • Steel stud framing in the administration area is complete. • All slab on metal deck has been poured. • Exterior building sheathing is complete. • The performance platform slab on grade is complete. CONSTRUCTION QUESTIONS? Please contact Dan Nash, Site Superintendent, or Ryan Kaplanek, Project Manager, at 262-542-9000. CURRENT & UPCOMING WORK • Exterior sheathing is ongoing. • Mechanical, Plumbing and Electrical (MEP) overhead rough-in is ongoing. • Remaining slab on metal deck and slab on grade pours to take place in the upcoming weeks. • Roofing activities are ongoing. • Brick install is upcoming. Administration Wing Steel Stud Framing Building South East Elevation Student Commons Community Room When complete, Wilson/WSTEM will stand roughly 45’ high at its tallest point. The worlds littlest skyscraper, the Newby-McMahon Building, stands at a whopping 40’ tall. That means, despite being an elementary school and not a high rise, Wilson/WSTEM is taller than a skyscraper! DID YOU KNOW?