Stantec Consulting Limited 40 Highfield Park Drive, Suite 102 Dartmouth NS B3A 0A3 Tel: (902) 468-7777 Fax: (902) 468-9009 June 12, 2012 File: 121411939.200.300 Chignecto-Central Regional School Board 60 Lorne Street Truro, NS B2N 3K3 Attention: Ms. Jackie Fahey Email: [email protected]Dear Ms. Fahey: Reference: Building Investigation – Highland Consolidated Middle School, Westville, Nova Scotia Stantec Consulting Ltd. (Stantec) was retained by the Chignecto-Central Regional School Board (CCRSB) to conduct an investigation for potential vapour and water pathways in the building envelope at the Highland Consolidated Middle School (HCMS), located in Westville, Nova Scotia. The assessment was mainly visual, however some bulk sampling was performed to identify mould. A boroscope was used, where applicable, to observe areas that were not visually accessible, such as; flutes, roof deck cavities and wall cavities. Don Hartt and David Ayers of Stantec were on site on May 24, 2012, to conduct the investigation. The visit was prompted by a recent building assessment that focused on identifying potential pathways for vapours/odours from roofing materials to migrate into classrooms. Several potential building envelope deficiencies were observed during this assessment. LIMITATIONS The information and observations contained within this report are based on visual assessments of the readily accessible interior surfaces of the building ( i.e., walls, ceilings, floors). Information obtained during the assessment may not be extrapolated to areas of the building not observed during the assessment. RESULTS & DISCUSSION The findings from the visual investigation of the readily accessible interior surfaces of the building are presented in Table 1. Table 1 Building Investigation Findings – Highland Consolidated Middle School, May 24, 2012 Location Observations Room 201 Black tar compound observed in flute area at the exterior wall joint. The tar compound was on the back side of a foam air-flow stopper and on the wood stud at the parapet Not all flutes were observed to have a foam air-flow stopper Northern Stairwell Black tar compound observed at the end of the flute at the exterior wall Draft observed in northeastern exterior wall corner at the roof deck Water staining was observed on wood stud at parapet Vertical crack continuous to the exterior (outdoors) was observed in southeastern corner of the concrete block wall Room 203 Water staining observed on wood stud at parapet
19
Embed
Reference: Building Investigation Highland … and...Table 1 Building Investigation Findings – Highland Consolidated Middle School, May 24, 2012 Location Observations Room 204 Exterior
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Stantec Consulting Limited 40 Highfield Park Drive, Suite 102 Dartmouth NS B3A 0A3 Tel: (902) 468-7777 Fax: (902) 468-9009
June 12, 2012 File: 121411939.200.300
Chignecto-Central Regional School Board 60 Lorne Street Truro, NS B2N 3K3 Attention: Ms. Jackie Fahey Email: [email protected]
Dear Ms. Fahey:
Reference: Building Investigation – Highland Consolidated Middle School, Westville, Nova Scotia
Stantec Consulting Ltd. (Stantec) was retained by the Chignecto-Central Regional School Board (CCRSB) to
conduct an investigation for potential vapour and water pathways in the building envelope at the Highland
Consolidated Middle School (HCMS), located in Westville, Nova Scotia. The assessment was mainly visual,
however some bulk sampling was performed to identify mould. A boroscope was used, where applicable, to
observe areas that were not visually accessible, such as; flutes, roof deck cavities and wall cavities.
Don Hartt and David Ayers of Stantec were on site on May 24, 2012, to conduct the investigation. The visit
was prompted by a recent building assessment that focused on identifying potential pathways for
vapours/odours from roofing materials to migrate into classrooms. Several potential building envelope
deficiencies were observed during this assessment.
LIMITATIONS
The information and observations contained within this report are based on visual assessments of the readily
accessible interior surfaces of the building (i.e., walls, ceilings, floors). Information obtained during the
assessment may not be extrapolated to areas of the building not observed during the assessment.
RESULTS & DISCUSSION
The findings from the visual investigation of the readily accessible interior surfaces of the building are
presented in Table 1.
Table 1 Building Investigation Findings – Highland Consolidated Middle School, May 24, 2012
Location Observations
Room 201 Black tar compound observed in flute area at the exterior wall joint. The tar compound
was on the back side of a foam air-flow stopper and on the wood stud at the parapet
Not all flutes were observed to have a foam air-flow stopper
Northern Stairwell
Black tar compound observed at the end of the flute at the exterior wall
Draft observed in northeastern exterior wall corner at the roof deck
Water staining was observed on wood stud at parapet
Vertical crack continuous to the exterior (outdoors) was observed in southeastern corner of the concrete block wall
Room 203 Water staining observed on wood stud at parapet
June 12, 2012
Ms. Jackie Fahey
Page 2 of 5
Reference: Building Investigation – Highland Consolidated Middle School, Westville, Nova Scotia
Table 1 Building Investigation Findings – Highland Consolidated Middle School, May 24, 2012
Location Observations
Room 204 Exterior drywall wall removed to expose envelope. Apparent mould observed on
plywood wall. Water staining observed on plywood wall
Room 206
Fiberglass insulation is being used to fill gap between structural steel I-beam and metal roof deck along exterior wall. Flashing was used to conceal gap
Portion of drywall wall at window base removed from previous mould abatement exposing wall cavity. Area was re-insulated and sealed with poly. No water-staining noted
Room 208
T-bar suspended ceiling observed in room with fiberglass/vinyl ceiling tiles
Black tar compound observed leaking through holes in flutes and from I-beam along the perimeter
There is a gap between the roof deck and the wood studded support at the parapet which is exposing the thermal layer of the roof membrane
Room 220
Fiberglass insulation is being used to fill gap between structural steel I-beam and metal roof deck along exterior wall. Black tar compound was observed on the wood studs at the parapet
Black tar compound observed in flute area at the exterior wall joint. The tar compound was on the back side of a foam air-flow stopper and on the wood stud at the parapet
Not all flutes were observed to have a foam air-flow stopper
Room 218
Rusted steel I-beam observed along perimeter
Building maintenance staff had recently removed a portion of exterior drywall wall to expose the envelope and window framing
Apparent mould (black staining) was observed on the window header, window base and plywood wall.
Bulk samples were taken from would for mould analysis (MBS#1 and MBS#2)
A tape-lift sample was taken from the plywood wall for mould analysis (TMS#1)
Drywall removed from the wall was placed by building maintenance staff in clear garbage bags. A bulk sample from apparent mould on the drywall paper backing was taken for mould analysis (MBS#3)
The window header was observed to be water soaked and rotted
Apparent mould and water staining was observed to be impacting building materials at the floor level and possibly into room spaces below
Room 216
Building maintenance staff had recently removed a portion of exterior drywall wall to expose the envelope and window framing
Apparent mould (black staining) was observed on the window header and plywood wall.
A strong draft was observed in the wall cavity at the roof deck
A gap in the envelope to the exterior of the building was observed at the concrete block/sheet metal siding
Deficiencies in the roof system were evident by the presence of water stains on wood at the parapet in
various locations of the HCMS. This information together with drafts noted at the roof deck/wall joint provide
evidence that pathways for vapour and water to enter the building envelope exist.
During the building investigation, apparent mould was exposed within the wall cavity of Room 218. The
drywall had been removed by building maintenance staff prior to Stantec’s site visit. The mould impacted area
consisted of the interior surfaces of the exterior wood framed wall that supported corrugated sheet metal
siding, including window frames. The deficiencies with regard to the exterior envelope that led to water
intrusion in Room 218 were observed in other areas of the building where the sheet metal siding was
installed.
June 12, 2012
Ms. Jackie Fahey
Page 3 of 5
Reference: Building Investigation – Highland Consolidated Middle School, Westville, Nova Scotia
Bulk samples for mould were taken at the HCMS during the investigation. The results of the bulk sample
testing for mould are summarized in Table 2.
Table 2 Mould Bulk & Tape-lift Sample Test Results – Highland Consolidated Middle School, May 24, 2012
TMS#1 Upper floor, Room 218 Cladosporium sp. colonies Active mould growth 1 Aspergillus/Penicillium-like spores may include those of Acremonium, Paecilomyces and Trichoderma
Bulk samples were submitted to Mycotaxon Consulting Limited, located in Halifax, Nova Scotia. Mycotaxon
produces data that is of sufficient quality for Canada Mortgage and Housing Corporation (CMHC), Health
Canada and Public Works and Government Services (PWGSC) for the analysis of mould and biological
contaminants. Mycotaxon Consulting Limited is a participant in the American Industrial Hygiene Association’s
Photo 1: Room 201. Flute ending at exterior wall with foam stopper. Flashing covering I-beam. Not all flutes containing foam stopper.
Photo 2: Room 201. Flute ending at exterior wall with foam stopper. Flashing covering I-beam. Tar compound observed on back of foam stopper.
Project No: 121411939.200.300
Photo 3: Room 201. Flute ending at exterior wall supported by I-beam. Tar compound observed on wood butted up against flute at parapet.
Photo 4: North stairwell plenum exterior wall. Water staining observed on wood at parapet.
Project No: 121411939.200.300
Photo 5: Room 208. Showing end of parallel chord roof truss and metal roof deck at parapet. Water stained wood observed along with tar compound.
Photo 6: Room 208. Showing metal roof deck meeting parapet. Water staining on wood and steel I-beam observed. Above wood roof thermal membrane is visible.
Project No: 121411939.200.300
Photo 7: North stairwell exterior wall. Large cracks observed in corners. Ceiling tiles with water stains observed.
Photo 8: Room 220. Exterior wall showing wall roof joint. Fiberglass insulation sealing cavity at parapet between roof deck and steel I-beam support.
Project No: 121411939.200.300
Photo 9: Room 208. Tar compound dripping from holes in metal roof deck.
Photo 10: Room 218. Showing wood rot and apparent mould at window header and on exterior plywood wall. Also observed rusted I-beam.
Project No: 121411939.200.300
Photo 11: Room 218. Showing wood rot and apparent mould at window header and on exterior plywood wall. Also observed rusted I-beam.
Photo 12: Room 218. Showing apparent mould on exterior plywood wall at exterior wall/floor joint. No pooling at base indicating moisture is seeping below floor.
Project No: 121411939.200.300
Photo 13: Room 218. Showing wood rot and apparent mould at window header and on exterior plywood wall. Also observed rusted I-beam.
Photo 14: Room 218. Showing apparent mould at window base and on exterior plywood wall.
Project No: 121411939.200.300
Photo 15: Room 216. Showing apparent mould on window header and exterior plywood wall.
Photo 16: Room 216. Showing apparent mould on window header and exterior plywood wall. Strong draft coming from concrete block cavity at parapet.
Project No: 121411939.200.300
Photo 17: Showing gap in envelope between concrete block/brick façade and sheet metal siding with wood frame.
Photo 18: Room 216. Showing building materials affected by water damage/intrusion around window base.
Project No: 121411939.200.300
Photo 19: Room 216. Showing building materials affected by water damage/intrusion around window base.
Photo 22: Room 214. Showing window base that has been abated for mould and re-insulated by the CRSB.
Project No: 121411939.200.300
Photo 23: Room 218. Water impacted drywall removed from exterior wall with apparent mould. Wrapped in light gauge plastic bag.
Photo 24: Photo taken from outside window in Room 218 showing detailing around roof curb flashing/parapet.
MYCOTAXON CONSULTING LTD. 3 Rockwood Avenue Halifax, Nova Scotia Canada B3N 1X4 Phone: 902-475-1456 Fax: 902-475-1982 Mr. Don Hartt Stantec Consulting Ltd. Suite 102 40 Highfield Park Dr. Dartmouth, N.S. B3A 0A5
May 28, 2012 Dear Mr. Hartt: Herewith are the results of the microscopic examination of the bulk and tape samples from your project 121411939 Task 200.300, which were received by this laboratory on May 25, 2012. SAMPLE GENERA MBS 1 active growth Cladosporium sp. colonies MBS 2 active growth Cladosporium sp. colonies MBS 3 active growth Stachybotrys sp. colonies heavy Aspergillus/Penicillium-like spores TMS 1 active growth Cladosporium sp. colonies Note: 1. Aspergillus/Penicillium-like spores may include those of Acremonium, Paecilomyces, and Trichoderma I hope this is helpful. If you have any questions concerning this report, please do not hesitate to contact me. Sincerely yours, Mycotaxon Consulting Ltd. Per: Thomas G. Rand, Ph.D. Mycology