REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY REVIEWS REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY REVIEWS A Pre-Construction Best Management Practice Presenters: Troy Pyles, PE, Project Director Jim Barger, Deputy Director of Review Services Vanir Construction Management, Inc. NWCCC Conference - November 8, 2006
31

REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

May 05, 2018

Download

Documents

trandan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

REDUCING PROJECT COSTS THROUGH EFFECTIVE

CONSTRUCTABILITY REVIEWS

REDUCING PROJECT COSTS THROUGH EFFECTIVE

CONSTRUCTABILITY REVIEWS

A Pre-Construction Best Management Practice

Presenters:Troy Pyles, PE, Project DirectorJim Barger, Deputy Director of Review ServicesVanir Construction Management, Inc.

NWCCC Conference - November 8, 2006

Page 2: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 2

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Experience has shown that the ability to reduce project cost is much greater early in the life of a project

• Much of the opportunity is past once the project is out for bid.

• Constructability review during the design phase is a key to project success.

OVERVIEW

Page 3: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 3

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

Page 4: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 4

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• A structured review of the project and design documents to ensure:– Feasibility of construction– Design as represented in the plans and

specifications is biddable and constructible

WHAT IS A CONSTRUCTABILITY REVIEW?

Page 5: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 5

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Site Constraints– Access– Lay down areas– Availability of

utilities– Height restrictions

TWO TYPES OF REVIEWS

• Schedule Constraints– Duration– Allowable work hours– Sequencing– Time of year– Weather impacts

Feasibility Review – Early In Design

Page 6: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 6

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Resource Constraints– Materials– Labor– Equipment

TWO TYPES OF REVIEWS

Feasibility Review (cont.)

Page 7: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 7

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Bidable & Buildable• Looking for

– errors – omissions – ambiguities – conflicts

• Coordination

Detailed Document Review – Later In Design

TWO TYPES OF REVIEWS

• Complete instructions• Inclusion of:

– Permit requirements– Geotechnical study

recommendations– LEED analysis– Hazmat report

Sometimes referred to as a Bidability Review

Page 8: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 8

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Constructability Review– Looks at how the design is represented to the contractor– Is the contractor provided complete and unambiguous

instructions on what to build?

CLARIFICATION

• Design / Peer Review– Looks at the design per se– Is the design correct per engineering, architectural,

regulatory, and code standards & requirements?

• Coordination Review– Coordination of disciplines only

Page 9: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 9

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

A design is a unique, one time endeavor requiring scores of individuals making hundreds of decisions on thousands of building components. It does not have the benefit of product testing. A perfect design will not result.

A third party review will help!

WHY DO CONSTRUCTABILITY REVIEWS?

Page 10: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 10

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

WHY DO CONSTRUCTABILITY REVIEWS?

Page 11: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 11

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

WHY DO CONSTRUCTABILITY REVIEWS?

Page 12: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 12

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

Primary Benefits

• Reduces RFIs• Reduces change orders• Reduces likelihood of impact claims• Reduces impossible and impracticable

requirements

WHY DO CONSTRUCTABILITY REVIEWS?

Savings = $6 to $27 for each $1 invested in the review

Page 13: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 13

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

Primary Benefits (cont.)

• Cleaner contract documents =– More attractive project– More bids– Lower bids – less contingency

WHY DO CONSTRUCTABILITY REVIEWS?

More Savings!!

Page 14: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 14

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

Side Benefits• Less RFIs and Changes =

– More management on construction– Better relationships– Better attitudes

• Better quality• Better schedules• VE suggestions

WHY DO CONSTRUCTABILITY REVIEWS?

Page 15: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 15

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

REVIEW FORMATS

• Workshop– Better for VE– May catch big issues

• Independent Study– More detailed– Will find more issues

Page 16: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 16

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Compile documents• Team orientation• Site visit• Document review• A/E Review and Respond• Reconciliation Meeting• Back Check• Final Report

REVIEW PROCESS

Page 17: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 17

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Three sizes of generators• Leland Stanford’s tree• Overhead power line interference• Backflow preventer• Wrong soil elevation• Conflicting permits

EXAMPLE CONSTRUCTABILITY ISSUES

Page 18: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 18

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Civil pad elevations• Civil utility plans/plumbing site plans• Civil utility plans/landscape plans• Structural beams/HVAC ducts• Structural top of steel elevations• Structural/architectural• Gridlines & dimensions

EXAMPLE CONSTRUCTABILITY ISSUES

Page 19: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 19

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Site visit critical– As-builts poor– Designer & constructor perspectives differ

• Say it once – Say it right• Need to budget & schedule the review• Don’t hide the results

LESSONS LEARNED

Page 20: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 20

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Back check to get maximum value• Need qualified reviewers• Need a developed Review Methodology• Review with “eyes of a contractor”• Review team needs all disciplines

LESSONS LEARNED (con’t)

Page 21: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 21

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Benefits designer• Quality of documents is decreasing

– Less principal involvement– Cut and paste details– Workload too high

• There is no industry standard definition of “constructability review”

LESSONS LEARNED (con’t)

Page 22: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 22

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Why do a constructability review? I’m already paying the designer for good plans and specs.

FAQs

Page 23: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 23

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Should owner pay to have the designer make the corrections?

FAQs

Page 24: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 24

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• How much does a constructability review cost?

FAQs

Page 25: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 25

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• How long does a constructability review take?

FAQs

Page 26: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 26

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Can’t you just do a quick review and find all the big problems?

FAQs

Page 27: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 27

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• When is the best time to do a review?FAQs

Page 28: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 28

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Our change order rate is only 10%, so why should we do constructability reviews?

FAQs

Page 29: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 29

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• Do you spell it “constructability” or “constructibility”?

FAQs

Page 30: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 30

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

• While there will never be a perfect set of plans and specs, a constructability review will help improve the quality.

• A constructability review should be viewed as an investment, not an expense.

CONCLUSIONS

Page 31: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience

Vanir Construction Management Inc. 31

Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews

QUESTIONS