Reduced cost bases Transportation & Installation merging Deep water MPP Umbilical and Structures Installation Moho Nord, Offshore Congo 12 th February 2017
36

Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of.....

Mar 16, 2018

Download

Documents

LêHạnh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

Reduced cost bases

Transportation & Installation merging

Deep water MPP Umbilical and Structures Installation

Moho Nord, Offshore Congo

12th February 2017

Page 2: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

Page 3: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

3

OCEAN INSTALLERAt a glance

Page 4: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

4

MOHO NORD DEVELOPMENT

Client: TOTAL

Ownership: TOTAL (~53.5%) – OperatorChevron (~31.5%)Société Nationale des Pétroles du Congo (~15%)

Location: 75km SW of Pointe Noire – Congo

Water Depth: 750 – 1,200m

Subsea Infrastructure:• 28 Subsea wellheads tied back to FPUs• 17 additional wells from new TLP

Production capacity: 140,000 b/d

Moho Phase 1 Bis Scope:• Extension of Moho Bilondo subsea development• Tied back to Alima FPU

Ocean Installer won the MPI Contract

Total © Total ©

Total ©

Total ©

Page 5: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

5

TOTAL

OVERVIEW

MOHO NORD CPI

2 x 45Te Transformers

175Te Pump Control Module

70Te SUT

12,5m LongTopside end

6,3km MPP Power & Control Umbilical

Support & Leveling Structure

252 Te Multi Phase Pump Module

Dummy Multi Phase Pump Module

20 x Flying Leads

Page 6: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

6

MOHO NORD INSTALLATION VESSELVessels – CSV Normand Vision

Long-term charter from Solstad

Ordered and developed in cooperationbetween OI, Solstad and Vard

Class leading asset design

Tailored for installation offlexible risers and flowlines

Length: 156,7m

Breadth: 27m

VLS: 150t

Crane capacity: 400t

Bunks: 140

Under deck carousel: 3000 ton

On deck carousel: 1800 ton

.

8 OFF VESSELS WITH SAME DESIGN

Skandi Acergy

Skandi Artic (DSV)

Aker Wayfarer

Lewek Connector

Normand Oceanic

Skandi Vitoria

Skandi Niteroi

Page 7: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

7

Key Sites

GEOGRAPHICAL OVERVIEW

RosythUmbilical

TotalParis

StordMobilisation

StavangerPM&E

Pointe NoireCongo

Moho NordSite

BergenStructures

Page 8: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

Page 9: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

2014 2015 2016 2017

Project AwardJuly 2015

ITTDec 2014

Tender Phase7 months

Task 5 Here

Timeline

KEY PROJECT MILESTONES

Page 10: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

10

Deck area

NORMAND VISION

Deck area 2100 m2

3000Te Underdeck Carousel

Page 11: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

11

EQUIPMENT OVERVIEWInstallation & Tooling

Installation

• 2 x I/O Transformers• PCM• MPP Umbilical• MPP module• 20 x Flying leads

Project equipment

• Project side VLS• Project rigging & tools• Horizontal connection system• Survey• Precommissioning

Page 12: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

12

Deck Overview

DECK PLAN

Plan view of deckready for transitfrom Rosyth

Page 13: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

13

One trip:• Vessel Mobilisation (personnel, rigging, installation aids and side

VLS)• Ocean Installer – Project Mobilisationo Stord

• One Subsea – Norwayo Loadout MPP moduleo Loadout PCM & Transformers

• Oceaneering – UKo Transit to Rosytho Loadout umbilical

• Moho Nord Field - Congoo Transit to Congoo Installation activities

Installation Approach

ONE TRIP APPROACH

Page 14: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

Page 15: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

2014 2015 2016 2017

ProjectDemobJan 2017

Project MobOct 2016

Project AwardJuly 2015

ITTDec 2014

Tender Phase7 months

Engineering Phase15 months

InstallationPhase3 months

Task 5 Here

Timeline

KEY PROJECT MILESTONES

ProjectHAZID

Jan 2016

ProjectHAZOP

May 2016

Page 16: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

16

CONGO OPERATIONS & PLANNINGLocal support team

Congo services

• Rope Access team on Alima• Provisions• Liftco, rigging• Precom supplies• Pointe Noire project operational office• External and covered storage facilities• Local harbour, Normand Vision Pointe Noire• Welders, on Normand Vision• Burners, on Normand Vision• Translators• Agency

Page 17: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

17

General field overview

MPP STATION

Ca. 5,7km

INSTALLATION SITES

FPU Alima

Page 18: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

18

FPU Alima

Location: Moho Nord Field – Congo

Moored on fixed heading (12 Mooring lines)

L: 188.5m

B: 34m

Slot 5: Umbilical Pull-in

M41C: PCM Installation

M51A: Transformer Installation (2x)

INSTALLATION SITES

Page 19: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

Page 20: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

20

PCM INSTALLATIONOverview – PCM Lift

Crane Curve – Sealift Mode

Radius – 19m

Available Lifting Height – 38.5 m

Capacity – 265 Te

Utilisation (Dyn.) – Approx 75%

Page 21: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

21

DYNAMIC ANALYTICAL ANALYSISRelease of Load

LOSE CA. 60Te DURING ROTATION

LOSE CA. 100Te ON CONTACT OF LOWER SUPPORT

CA. 9DEG DYNAMIC ROLL ON VESSEL

Page 22: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

22

PCM INSTALLATIONWeather Criteria – Head Seas

Relative Vertical Motion [m]

TP [s]

HS [m]6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

2,1 0,4 0,6 0,9 1,2 1,9 2,1 2,5 2,9 3,9 5,4 5,7 6,1 8,5 7,5 5,1

1,8 0,3 0,6 0,8 1,0 1,5 1,7 2,1 2,4 3,4 4,5 5,8 5,4 4,8 4,1 3,9

1,5 0,3 0,4 0,6 0,8 1,2 1,4 1,8 2,2 3,2 3,8 4,4 4,6 4,4 3,5 2,7

1,1 0,2 0,3 0,5 0,6 0,9 1,0 1,3 1,7 2,8 3,6 3,4 3,4 2,9 3,3 2,0

Acceptable for 1.7m of Relative Vertical Motion

Acceptable for 2.5m of Relative Vertical Motion

Acceptable for 3.5m of Relative Vertical Motion

Not Acceptable

Page 23: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

23

PCM INSTALLATIONKey Challenge is tolerances Vrs Motion

Page 24: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

24

PCM INSTALLATIONCLEARANCE

Page 25: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

25

PCM INSTALLATIONOverboarding Sequence

Page 26: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

26

PCM INSTALLATIONWeather Criteria – Head Seas

Page 27: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

27

PCM INSTALLATIONWeather Criteria +/-30deg

Page 28: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

28

SIMULATIONS

• Real time simulation

• Vessel crew

• Operational experience

• Crane and Moored FPU simulation

• Crane Controls as per vessel

• Tugger functionality as per vessel

DP System

Page 29: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

29

INSTALLATIONPCM operations

Page 30: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

Page 31: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

31

Product loadout

UMBILICAL OPERATIONS

Page 32: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

32

Handling operations

UMBILICAL OPERATIONS

Topside Endloadout fromhandoverlocation

Transpoolingproduct loading intounderdeck carousel

SUT lift fromhandoverlocation

SUT landed onseafastening.Product stored inunderdeckcarousel

Page 33: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

33

The MPP umbilical is to be installed betweenthe MPP location and FPU Alima.

Main umbilical data:Length: 6260mOD: 230.5mmWeight: 101.1kg/mMBR: 6.7m (load controlled)MBR: 4.8m (discplacement controlled)

Introduction

MPP UMBILICAL INSTALLATION

Page 34: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

34

Sim Vrs Installation

MPP UMBILICAL INSTALLATION

Page 35: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

35

MOHO NORD MPI PROJECTOverview

Total split Project Overall SURF SOW

SOW tailored to a Mid Size Deep Water ConstructionVessel such as Normand Vision

Optimization of the execution plan (Transport &Installation in one phase)

Very competitive pricing of relevant SOW

Adding to our strong and successful track record inSURF projects

Systematic and meticulous approach to new countriesentry

Safe, on time, on budget project execution

Sucessful for Total and Ocean Installer

SAME CAN BE DONE FOR DEEP WATER SOW’s IN EGYPT

Page 36: Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases Transportation & Installation merging ... • Precommissioning. 12 ... Optimization of the execution

36CONTACTS

Technical

Iarla Lewis

Project Technical Manager