-
Guillaume VERY Student Engineer 5th Year Civil Engineering
Specialty
Reconstruction of the grandstand Leo Lagrange stadium of
Besanon
Christian Mataigne
Saida Mouhoubi
Project Graduation
September 2006
-
1VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Author:
Guillaume VERY Engineering student 5th years, specializing in
Civil Engineering National Institute of Applied Sciences of
Strasbourg
Tutors:
Saida Mouhoubi Professor and lecturer INSA Strasbourg
24, Boulevard de la Victoire 67084 Strasbourg
Christian Mataigne Project Engineer, responsible for structural
studies Betic Ingrop
47 Clemenceau Avenue BP 1041 25001 Besanon Cedex
-
2VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Summary Summary
.......................................................................................................................................
2 Thanks
...........................................................................................................................................
3 Introducing Betic Ingrop
...............................................................................................................
4
1. The group Ingrop
...........................................................................................................................................
4 a) Historical
......................................................................................................................................................................
4 b) The organization
..........................................................................................................................................................
4 c) Actual
...........................................................................................................................................................................
4 d) Key figures
...................................................................................................................................................................
5 e) Ingrop in France and around the world
......................................................................................................................
5 f) The various crafts Ingrop
............................................................................................................................................
5
2. Betic in Ingrop group
......................................................................................................................................
7 CHAPTER I Introduction
................................................................................................................
9
1. Project Overview
..............................................................................................................................................
9 a) Stakeholders and the budget
.......................................................................................................................................
9 b) Award of the contract
.................................................................................................................................................
10 c) Part of Operation
.......................................................................................................................................................
10 d) Architectural and urban party
.....................................................................................................................................
10 e) Project Description
....................................................................................................................................................
11
2. Problematic
..............................................................................................................................................
13 CHAPTER II Tribune concrete
......................................................................................................
14
1. Calculation assumptions
..............................................................................................................................
14 a) Rules of calculation
...................................................................................................................................................
14 b) Loads
........................................................................................................................................................................
14 c) Ranking ERP and structural fire
.................................................................................................................................
14
2. Description of the supporting structure
.........................................................................................................
15 a) Foundations, paving
..................................................................................................................................................
15 b) Vertical structure
........................................................................................................................................................
16 c) Horizontal structure
....................................................................................................................................................
17
3. Detailed study of the porticos
........................................................................................................................
17 a) Reinforcement beams racks
.....................................................................................................................................
18 b) Checking posts
..........................................................................................................................................................
24
4. Detailed study of the bleachers
.....................................................................................................................
24 a) Form
..........................................................................................................................................................................
24 b) Specifications
............................................................................................................................................................
25 c) Reinforcement
...........................................................................................................................................................
26 d) Structural fire
.............................................................................................................................................................
34 e) Dynamic
....................................................................................................................................................................
35
CHAPTER III Metal roof
...............................................................................................................
37 1. Calculation assumptions
..............................................................................................................................
37
a) Rules of calculation
...................................................................................................................................................
37 b) Loads applied to the structure
....................................................................................................................................
37
2. Calculation with the Robot program
.............................................................................................................
39 a) Evolution of the static system
....................................................................................................................................
40 b) Estimated by manual calculation of certain profile sections
.......................................................................................
44 c) Design parameters
....................................................................................................................................................
47 d) Main results
...............................................................................................................................................................
48
3. Description of the supporting structure
.........................................................................................................
50 a) Main frame
................................................................................................................................................................
50 b) Calculating the anchor metal mast on concrete pole
..................................................................................................
54 c) Metal sheet
................................................................................................................................................................
56
4. Modal analysis
..............................................................................................................................................
57 CHAPTER IV Complete Building
..................................................................................................
59
1. Modeling
.......................................................................................................................................................
59 a) Model Comparison
....................................................................................................................................................
59 b) Modeling bleachers
....................................................................................................................................................
60
2. Results of the modal analysis
.......................................................................................................................
61 CHAPTER V Conclusion
..............................................................................................................
63 Bibliography
.................................................................................................................................
64
-
3VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Thanks
This work was carried out from April to August 2006 within the
agency Ingrop of Besancon.
I wish to extend my sincere thanks to the company Ingrop and
especially in the East regional entity Ingrop Great for accepting
me in project graduation this through Mr. Claude Heyd (Regional
Director Great Eastern) and Herv Michiels (Director of the Agency
of Besancon, Development Director) who welcomed me in the agency
Besancon.
I also thank for their time, patience and sympathy all the
Ingrop staff (project managers, engineers, designers and
secretaries) and the people I worked with during my graduation
project (the firm architecture and Denu Paradon and techniques
Besanon services). I was sensitive to the quality of their
hospitality and professionalism.
I would also like to express my sincere gratitude to Mrs. Saida
Mouhoubi (Professor and Lecturer at INSA Strasbourg) for being my
main contact at INSA Strasbourg and also to Mr. Christian Mataigne
(Project Engineer, responsible for structural studies of concrete,
wood and steel) for kindly ensure accountability within Ingrop my
graduation project. Indeed, these two people have always been
anxious to answer my questions and my expectations, and their
advice and their help has guided me throughout my work.
A big thank you also to the teaching staff of the INSA
Strasbourg for the quality of education that has been bestowed upon
us, and my classmates for the atmosphere and friendliness in which
we studied during the three years.
Finally, I would like to extend special thanks to my parents, my
grandparents, my brother and Aurlie for the support they have shown
me throughout this period.
-
4VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Introducing Betic Ingrop
1. LegroupeIngrop :
a) History:
Ingrop was born in 1992 from the combination INTER G and ESA,
both companies technical engineering. Here is a brief recalling the
important dates of the birth of Ingrop group:
1945: creation of the company INTER G, specializing in the field
of thermoelectric plants, hotels, hospitals and trams.
1984 takeover of INTER G by the manufacturer group GTM (Grands
Travaux de Marseille) to expand its core business in hand.
1984 founding by GTM ESA in order to create an art complex
structures and technical studies department works, which over the
years has developed in the areas of project management of large
linear infrastructure Building and industrial plant.
1992: Birth of Ingrop group merging INTER G and STPs. End of
2000: 1,100 employees Ingrop account March 2001: GTM is absorbed by
VINCI, managers take the initiative to Ingrop redemption of
their company through an LMBO (Leverage Management By Out), with
the support of Crdit Lyonnais.
December 2005: Crdit Lyonnais sold its stake to the Ingrop
capital for the benefit of the management team and a hundred
frames.
b) The organization:
Ingrop is now an independent engineering simplified joint stock
company with capital of 5
million, divided into regional units, and managed by a board of
three persons whose decisions are endorsed by the Supervisory Board
representing the shareholders. Ingrop is wholly owned by more than
160 senior executives and by a Mutual Fund Company (CIPF), open to
all employees.
Figure 0.1: Distribution of shares in the company.
c) Staff:
Figure 0.2: Actual 31/12/05.
-
5VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
d) Key figures:
Figure 0.3: turnovers since 2001.
Backlog at the end of 2005 stood at 186M, more than 17 months of
activity.
e) Ingrop in France and worldwide:
Figure 0.4: implantations Ingrop in France and worldwide. f) The
various crafts Ingrop:
Building and equipment:
Ingrop often occurs alongside programmists, architects and urban
planners, managers of public facilities and large industrial. Its
teams design and build in the following areas:
Y Housing and urban renewal. Y Socio-cultural. Y Sports and
Recreation. Are Teaching and Research. Y Health. Y Buildings
tertiary. Y Industrial buildings.
Some current projects: Centre Hospitalier Universitaire de
Prigueux, House of the Alsace region, Strasbourg, Les Terrasses du
Port in Marseille (shopping center), Extension of hall A
-
6VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Bordeaux Airport, renovation of the Petit Palais in Paris,
Mother-Child Faencerie Nantes Hospital Pasteur in Nice 2
hospital.
Infrastructure: The creation of infrastructure is one of the
core businesses of Ingrop. It draws on a wide beam expert, flexible
multidisciplinary teams, implementing proven methodologies and
focus on compliance of quality, time and cost. Serving the State,
local authorities, businesses, Ingrop deploys its experience in all
areas of transportation infrastructure:
Y Collection, purification and distribution of water. Y River
hydraulics and waterways. Y Dams and transfer. Y Ports, marine and
offshore works. Y Roads and highways. Y Railways, TGV. Y bridges,
viaducts and tunnels. Y Road Equipment and tunnels. Y VRD and large
platforms.
Some current projects: Lyon-Turin rail link, renovation of the
tunnel of the Thorn, express link Cholet-Bressuire bridge Nouatre
the Vienna bridge crossing in Algiers (Algeria), Viaduct Monk in
Loire-Atlantique, LGV is section B.
Public transport:
For years, Ingrop developing its transport activity in common.
It carries many of consulting and engineering, in France and abroad
for the benefit of utilities, operators and managers of transport
networks, builders or contractors working in the field of systems
transport and its environmental integration. The range of skills
continues to grow: According to traffic studies, socio-economic
studies and transport infrastructure studies Ingrop develops
operating systems (ticketing, centralized management, ...) while
addressing the ancillary works such as multimodal hubs. References
illustrate the diversity of interventions in this business:
Y Metros. Y Tramways. Y Bus own site.
Some current projects: Bordeaux tramway, Grenoble tramway, tram
Douai, tram Morelia (Mexico), tramway of Granada (Spain), garage
workshop tramway Barcelona.
Water and environment: Independent industry groups that build or
operate the water and sanitation infrastructure, building on its
extensive network of regional offices that allow it to provide
local service, and strong experience in the full range of
engineering construction and project management, Ingrop develops
its activities in the sectors of water and environment:
Y Managing water resources. Y River Hydraulics, improvements of
rivers and canals rivers. Hydraulic Y Urban, drinking water,
wastewater and stormwater, sewage. Y Shoreline. Y Industrial
Environment. Y Management and treatment of waste.
-
7VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Some current projects: Dam Vessy (Switzerland), Marine
Structures and port facilities in Saint-Malo, Inga Dam (DRC) gas
pipeline between Egypt and Israel, digital terrain model of
floodplains in PACA, stabilization the bed and banks of the Rhone
(Switzerland), spatial lido of Ste to Marseillan.
Industry:
Through its multidisciplinary expertise and locations close to
customers, Ingrop meets the needs of industry by jointly optimizing
processes, buildings and utilities. Ingrop deploys a specific
expertise in response to increasingly stringent constraints on
industrial plants: environmental issues, health and safety,
classified facilities, validation and regulatory compliance. Its
services business is exercised in various sectors of the
industry:
Y Life Sciences. Y Fine Chemicals, chemical, oil and gas. Y
Infrastructures for telecommunications. Y automotive and tire
industry. Y Aircraft, Airports, space. Y Mechanical industry,
steel, metallurgy. Y Food industry. Y Waste treatment and
industrial environment.
Some current projects: painting robots for applying for PSA, C35
(string A330 / A340 paint) Airbus building, boiler SANOFI-AVANTIS
factory Peugeot Citroen in Trnava (Slovakia).
Figure 0.5: Distribution of activity by Ingrop trades.
The building and infrastructure is the main Ingrop activity.
2. BeticdanslegroupeIngrop :
Betic (Bureau of Technical Studies and Construction Engineering)
was, since its creation in
April 1977 by Jacques Ovigne, an office independent technical
studies (the largest engineering office Besanon), consisting of
fourteen engineers and technicians. It is now a 100% subsidiary of
Ingrop since 9 November 2004 Betic is attached to the entity Ingrop
Grand Est, gathering the Strasbourg offices (regional office),
Metz, Nancy and therefore Besancon. The mission of this new agency
Betic Ingrop Besanon is to develop the Group's business in the
Franche-Comt region and in the department of Cte d'Or and
especially in the building sector. Betic Ingrop with expertise in
structural and civil engineering, light work, electricity, fluids,
environmental engineering, electromechanical equipment and fire
safety ensures missions project management, execution of studies
and feasibility studies.
Current research projects: construction of 25 homes on the site
of Maroon Suns in Besanon (25), rehabilitation of Voltaire College
of Besancon (25) extension and rehabilitation center
-
8VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
Hospitalier de Belfort (90) Remodeling of the Rock pension Gray
(70), deconstruction and reconstruction of the grandstand Leo
Lagrange stadium Besanon (25), extending the stamping plant in
Bourgeois Besanon (25).
Figure 0.6: diagram of Ingrop Grand East.
-
9VERY Guillaume, INSA Strasbourg, Specialty Engineering, Project
Report graduation.
CHAPTER I Introduction
1. Prsentationgnraleduprojet :
Figure I.1: Perspective view of the podium (made
competition).
a) Stakeholders and the budget:
Client: City of Besanon (Technical Services Branch
Buildings).
Architect: Architecture and Denu Paradon (Strasbourg), BET Betic
Ingrop firm.
Control Office: SOCOTEC.
Safety Coordinator: ACE BTP.
Programmiste: GPCI (Project Management Construction and
Industry). User: Besanon, BRC (Besanon Racing Club). Budget:
5 million before tax.
-
10VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
b) Award of the contract:
The team consists of project management architecture firm Denu
and Paradon and engineering
firm status Betic Ingrop every body has obtained the contract
for project management for the demolition and reconstruction of the
tribune of honor of Leo Lagrange stadium Besanon after an
architectural competition and engineering in accordance with the
Public Procurement Code. The competition focused on rebuilding the
grandstand but it was nevertheless asked to reflect on the overall
design of a stadium with a capacity of 12,000 seats and the general
organization and composition of the urban neighborhood.
c) Part of Operation:
This project falls within the broader framework of the complete
restructuring of the stadium
whose capacity will be brought home to end about 12,000 seats
(four grandstands 3500 seats in the grandstand (West), 5000 places
for the East Stand, 1500 seats for the North and 3350 seats for the
south stand) platform and the design will meet the requirements of
the League 2 of the Professional Football League (LFP). It is also
integrated with an urbanization project area: widening the avenue
Lo Lagrange (alignment 20m) to incorporate transmission constraints
own site, creating an urban front built along this avenue and
creation of a highway north / south (see rendering contest
attached).
These projects on a larger scale are not part of the contract
won by the team of project management.
d) Architectural and urban party:
Between Avenue Lo Lagrange in the North and the South Street
Trpillot, sports area made
the football stadium of Besanon, the athletics stadium and
tennis courts has changed significantly over time. The general
organization of the stadium pose operational problems, and the site
now offers a confusing area with poorly defined boundaries picture,
a patchwork resulting from the interweaving of older areas with
sports facilities. The planned interventions were first to improve
the internal operation of the stadium and increase both its
capabilities and its reception quality objective. Also, they offer
an opportunity to rethink this 'piece of city' to incorporate this
sector in a comprehensive urban project including the Palais des
Sports, pool Mallarme and other equipment, including urban
development project related to the course of the future MRT (Public
Transport in Clean Site) will be the theme. Programmed steps,
rebuilding the football stadium will soon initiate a comprehensive
redevelopment of the site of the sports area.
Even more than the programmatic requirements, including the
12,000-seat gauge desired term, the existing site configuration
which governs the scope of the planned intervention. The site is
very constrained, flexibility is limited due to the nesting of
components: close to the athletics track with a football stadium
must be separated presence tennis south prohibiting all in a least
First, any recomposition South front along Avenue Trpillot,
multiple access ... Major constraint for example, 'pinch' the site
in the North East at the corner of the field of honor and Avenue Lo
Lagrange, an effect that will be enhanced by the enlargement of the
avenue to 20m by the realization of the North Stand. A context that
actually offers little freedom to the designer.
-
11VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
This diagnosis led the project management team to provide a
flexible, scalable project, based on the idea of a reconstruction
by use and by the plant, a 'Sports Park' organized around a
prominent built feature, which will be the new stand.
The grandstand (West):
In the proposed project, the new platform is the unifying
element of all the sports area, and constitutes the 'Landmark',
'major urban signal perceptible distance architectural landmark in
the cityscape. These seven arrows shot into the sky from Besanon
are part of revaluation of all of the city entrance area.
The proposed the VIP project is a cover wing-shaped, hanging
from a cable-stayed structure whose masts, height ranging from 35
to 40m, are arranged irregularly.
Very spectacular, all offering dynamic, changing approach in the
views. At night or on game nights,
the seven masts illuminated with the colors of the city exalt
atmosphere demonstrations.
The choice of such a structure is motivated by the desire to
form a coherent whole with the south stand; both buildings have
formal correspondence, the south stand itself being designed by a
system of tubular towers.
To the east and north, future forums could be designed later by
a similar system, but restricts the height of the masts in order to
establish a formal hierarchy, the grandstand to remain the dominant
element.
Inside, the 3488 grandstand seats in the highest levels of
comfort and visibility. At the top, the wind cuts glass house the
public.
The public reception areas are particularly cared for, and the
ambulatory of the first level, and the reception area for partners
and VIP, offering a 360 degree view of the entire site.
e) Project Description:
The new west grandstand will have a capacity of 3488 seats and
covered; it includes all the
facilities and equipment needed to operate the club in Ligue 2
of the Professional Football League (LFP). For this section, refer
to the APS drawings attached. This platform has two levels of
steps:
the lower plate totaling 1874 seats including 32 seats PMR
(Disability Access), accessible from the inner court, a vast area
located at 1.
the top plate totaling 1614 seats including 210 VIP seats,
accessible by two bridges and vomitories located halfway up the
level 1.
The ground floor of the building located below the first level
tier includes all the necessary premises in sporting activities
(sports field).
The first floor, located in the second level tier is occupied by
the inner court, the refreshment area and shop. The audience
reached by two monumental stairs at the ends north and south of the
grandstand. Access to the bleachers is from this floor, directly to
the stands of the lower plate, or via two bridges and two
vomitories mid-storey height for the stands of the upper plate.
-
12VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
The second and top floor is occupied by the VIP area, accessible
by the public and separated by a lift stairs. This space provides
direct access to the protocol platform.
In general, all the services provided in this project is the
respect of the operation of the program established by GPCI.
The sports field (level 0): The sports field is organized in a
pattern of four distinct areas:
The Y sealed area: it welcomes all players and sports players.
Traffic flows are entirely independent of the operation of the rest
of the equipment. The sealed area is organized around a central
hall generously sized, Through access to the land serving fluidly
whole area. Access to land is split, to separate the two teams.
Y Annexes and local sports facilities mutualisables: These
premises are used outside of
time games, and can be made available to the athletics stadium.
They have an entry in the north of the grandstand near the porter's
lodge, and access to the football field. The weight room and warm,
the pool and sauna also have direct access from the sealed
area.
Y spaces and organization techniques dedicated to stakeholders
annexes, contains
technical spaces and storage, as well as local dedicated
stewards. It has access to the South gable. The local security DRC
has direct access to the outside.
Y VIP hall and press space: the VIP hall is located south of the
grandstand. It provides
access to the VIP lounge is by stairs or by elevator. The press
area is directly accessible from the lobby. It includes the
interview room and the press room. It has access to the sealed
area, allowing either to call sports or to conduct interviews in
the sports hall.
The inner court and the bar (level 1):
The inner court is used to manage access to the high and low
platform and the press box. It hosts the bar and spaces boutiques,
infirmary and a comfort station RMC. It is a vast space generously
sized, to manage all flows, especially before and after games. It
is well ventilated by a perforated facade upper west. To the east,
the view of the land is clear, to maintain visual contact with the
stage. The bar has been set to provide maximum linear. It is an
enclosed area that will be treated frost. The public toilets were
placed in the inter-level, accessible from the bearings of
stairways gable North and South. Only health PMR are held on the
square.
Grandstand:
The low profile platform has been optimized following a
blueprint of visibility. It consists of ten rows of bleachers size
40 x 80cm, between altitudes 2.33m + and + 6,33m. Access is
provided at the top by four vomitories wide 3UP Unit (Person), and
completed at the bottom by two side stairs. Its capacity is 1874
seats, including 32 PMR. The high platform has a height greater
step. It consists of ten rows of bleachers size 54 x 80cm, between
altitudes 9,16m + and + 14,20m. Cabin access is in bottom, by means
of two corridors accessible from the court, serving two double
vomitories 3UP of each. VIP and protocol platform is generously
sized. It has a depth and spacing of the upper seats. It consists
of six rows of bleachers 60 x 90cm, following the same slope as the
rest of the upper gallery. It has a terraced area
-
13VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
to the VIP lounge. Cabin access is directly from the show, and
is complemented by two controlled gates on the lower corridor of
the grandstand access. However, it is possible and feasible, to
pass the size of 54 x 80cm bleachers in ten rows (like the rest of
the gallery), which would increase the number of seats for VIPs, as
desired by the master authority.
The VIP lounge (top level):
The VIP lounge located on the top level (+ 14,20m). It grows in
length, providing maximum view of the playing field. At the rear,
it also opens the athletics stadium. The VIP lounge access is by an
airlock, bringing the arrival of the stairs and the elevator, and
also serving the PC security and local entertainment-center in the
south of the platform. The office and its annexes were integrated
into the local volume of the show. The disposal of the latter is by
the stands, accessible by both side doors. A secondary staircase
leads an additional issue.
2. Issue:
Alongside specific to this type of work technical requirements,
compliance with financial constraints imposed at the outset as a
major issue of the operation. Indeed, this project is in an
unfavorable political and popular part because the football team
Besanon (Besanon Racing Club), currently CFA Group B (Amateur
Championship, 4th division), finished thirteenth of his
championship season last. These results are not really consistent
with the ambitions Besanon has placed in the restructuring of Leo
Lagrange stadium in view of the approval for the Ligue 2 (second
division). Therefore, the city, through its technical services, has
made available for this project to rebuild the grandstand a budget
of 5 million excluding non-extendable and non-negotiable fees. Note
that a project had been abandoned for reasons of exceeding the
budget. He anticipated at the time the complete construction of a
stadium with a capacity of 20000 places. It is for these reasons
that from the preliminary design phase (APS), an optimization of
the structure work (which alone accounts for half the cost of the
operation) was necessary, first by the uniqueness and peculiarities
of the work to be performed and also to avoid drift a financial
point of view.
My graduation project is therefore in this light. He was
committed to my mission, under the responsibility of Mr. Christian
Mataigne (Project Engineer, responsible for structural studies of
concrete, wood and steel), define, from the architect's plans and
working closely with the last, a support structure and to estimate
the price. For this, the work was divided into several steps. The
first was to model and size the metal roof for. Then the second job
was to study the concrete structure of the platform to find a more
streamlined operation diagram and best use possible. Finally, a
dynamic study of the entire building will verify the natural modes
of vibration of the structure and analyze the potential
interactions between the stands of concrete and metal roofing.
-
14VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
CHAPTER II
Tribune concrete
1. Hypothsesdecalcul :
a) Rules of calculation:
Calculations are made of reinforced concrete according to DTU P
18-702 Rules BAEL revised 99 91 - Rules technical design and
costing, and reinforced concrete structures using the method of
limits in February 2000 states Operating expenses acting on the
elements are calculated according to the NF P 06-001 Basis of
constructions Operating expenses buildings in June 1986.
b) Loads:
Dead Load:
Dead loads resulting from the self weight of the concrete
structure and the various materials used (coverings, partitions,
specific hardware).
Operating expense: Operating expenses considered are those
defined by the program and, failing that, those required by the
standard. We note mainly:
Y Tribunes (seats), main corridors, vomitoria, stairways,
corridors, refreshments, VIP lounge, gym, media room, storage,
public health, technical premises: q = 5 kN / m 2.
Y Room Video, PC Security Office (VIP lounge), shop, local
security, local facilitator, conference room (
-
15VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
All activities PA + N + X is an establishment open to the public
one, which employs 3,500 people, first class (over 1,500
employees). The concrete structure will have stability and CF
degree (fire) 1:30.
2. Description of the supporting structure:
The goal was to find a carrier simplest and purest possible
structure. This in order to achieve maximum savings and also to
allow the simplest implementation and most repetitive possible, in
order to reduce delays (structurally concrete GO-01 in the
appendix).
a) Foundations and paving:
The site has been the subject of a geotechnical study by the
research department of Geology,
Geophysics and Geotechnics B3G2. The findings of this study
are:
The land is substantially planar and horizontal. Geologically,
the nearest basement consists of limestone Bathonian. Polls have
recognized from the surface, the following layers:
Y 0.5 to 3m thick generally clay embankments, poor mechanical
properties (ultimate pressure: Pl
-
16VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Given the possible presence of karst cavities, it will be
essential to the vertical and horizontal continuity of bedrock
check under each support by destructive surveys of drill-type
wagon. The level of full body will be established to 70cm under the
pavement. The embankments under paving include a blocking layer
40cm 0-200 and subgrade 30cm-run from 0 to 31.5. The floors will be
designed unarmed guy with coatings placed on screed. Additional
surveys with pressuremeter results should be made to verify that
the design of the paving.
Paving (15cm thick)
Flooring (5cm thick) Subgrade-run 0 to 31.5 (30cm thick)
0-blocking layer 200 (40cm thick)
Sill recovery
Natural terrain
Pile head
Figure II.1: Schematic diagram of the foundations.
b) Vertical structure:
Bored pile cased (800mm diameter)
The supporting structure consists of a vertical reinforced
concrete portals disposed along the
transverse axis, numbered from A to K, a frame according to
9.5m. Given the length of the building (about 100m), two joints are
put in place. To facilitate the implementation of these expansion
joints, gantries rows E and G were split (E / E 'and G / G') with a
spacing of 2 m, which can handle either side of the door gasket
-to- wrong.
We are 13 and 10 gantry defining spans of slab spans of 9.5m and
2m 2 console. Gantries include the following (see section on the
plane structure):
Pole 60 x 60 rear panel on two levels (ground floor and level 1)
on the e file. An intermediate pole 40 x 40 beams overlap the scope
of the DRC on the e file. This post does
not go upstairs. Pole 40 x 210 on two levels (ground floor and
level 1) on the line 8 This post gets the rack beam
of the upper plate. Pole 40 x 276 on the ground floor in the
lane 0 This post gets the beam rack of the bottom tray. A floor
beam 40 x 80 for the recovery of high slab floor. A beam rack 40 x
115 on the ground floor with a span of 10m (to the axis poles)
showing the
steps of the lower plate. A beam rack height adjustable 40 x 100
to 40 x 175 on the first floor with a range of 11,6m (to
the axis poles) showing the steps of the upper plate.
Porticos queues A and K (gable) and B and J have a slightly
different configuration due to the presence of monumental stairs
and lack of floor level 1. Trailing post will be checked with a
length corresponding buckling 2 floor heights. Porticos show floors
and bleachers. They also provide lateral stability
-
17VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
building through the bending strength of the posts 40 and 40 x
210 x 276 and beams 115 and racks 40 x 100 to 40 x 175 The gantry
also show horizontal forces induced at floor level by the anchoring
of the structure metal awning. The longitudinal bracing is provided
by a set of sails shuttered 20cm thick located:
On the edge of monumental stairs (at 1 and DRC). On the edge of
the platform TV (at 1). On the ground floor, along the flow-field
cloakroom on the line 8. In DRC faade, row 0.
The seven metal poles supporting the canopy forming the roof
will be extended into the building through concrete columns
elliptical diameter 180 x 120 They will transmit the loads exerted
on the roof to the foundation.
The two joints define blocks having the following
dimensions:
40m in length for 2 power ends. 19,4m long for the central
block.
These joints are not extended in the roof. The influence of the
expansion of the concrete structure of the frame will therefore be
checked by simulating a moving support.
c) Horizontal structure:
The floors are made of solid slabs cast in place, possibly from
slabs. They will be based on
longitudinal beams, possibly prefabricated bearing a portal to
another. The high slab from Level 1 (floor VIP lounge) will have to
take this particular horizontal forces brought by the masts of the
frame. This panel will thus work as a beam bent in the horizontal
plane approached by point forces at each mast and supported
horizontally on each portal.
The flowsheet practically excludes the use of hollow-core
slabs.
3. Etudedtailledesportiques :
This study was carried out using a 3-dimensional model of the
entire building as the Robot
program (Study module in a shell). The purpose of this model was
to determine the stresses in the skeleton into account the
interaction and transmission of forces between the metal roof and
the concrete structure of the rostrum. To obtain directly diagrams
internal forces, porticos were modeled by bars. The choice of bars
for gantry induced necessarily simplifications and geometric
approximations on other structural elements (floors, walls) as a
bar is defined by its mean fiber, so it is difficult to liaisonner
a veil on the bracket a pole, for example. It would have been
possible to make a more accurate model by adding rigid connections,
but the simplifications made not having a great influence on the
desired results, it was not necessary to complicate the model. It
should be noted that the dimensions of the beams and posts have
racks permit the use of the module plates, though the results given
by the software to the plates are difficult to use.
-
18VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
tj
e ed
0
f fC
a) Reinforcement beams racks:
The racks beams are made of reinforced concrete cast in place.
For reasons of simplicity, we
neglect the normal efforts in the racks beams. Indeed, these
elements are always compressed, this assumption on the side of
safety increases since the reinforcement sections (without buckling
phenomenon). Furthermore it is assumed that the beams will be
carried out with a cover of concrete, that is to say we do not take
into account the participation of the concrete to balance the shear
( = K = 0 0,3f )
Material characteristics: Concrete: B25
c 28
= 25MPa = 14,17MPa
Steels: HA feE500 f = 500 MPa f = 434,8MPa
Settings section: Is defined by beams racks, the two component
beams and gantries supporting the bleachers (but not only). Partly
tribune high beam rests on the pole 210 x 40 x 60 door to the post
60 of the back cover also supports the low-floor VIP lounge
(between the line and the line 8 th), and ends in console . Partly
forum low, the beam carries the pole to pole 276 x 40 210 x 40
(between the line and the line 0 8).
b = 40cm h = d = 90cm 100cm
b = 40cm h = 100 and d = 90 to 206cm 185,4cm
b = 40cm h = 175cm d = 157,5cm
High beam rack forum
b = 40cm H = 80cm d = 72cm
b = 40cm h = 115cm d = 103,5cm
Low beam rack forum
File 4 File 3 File 2 File 1
Figure II.2: description and parameters of beam sections
component type gantry.
-
19VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
d
u
u
A
S
S
sA d
C
u u
hu u
f
t
High beam rack forum:
Stresses: M (ULS) 1812,22kN.m = M (ULS) -1220,04kN.m = V (ULS) =
624,51kN
Calculation of reinforcement Asmini section:
m = Mjd(ULS) u b d2 For h = 175cm and Md(ULS) = 1812,22kN.m: mu=
0.129 For h = 175cm and Md(ULS) = -1220,04kN.m: mu= 0.087
= 1.25[1 1-2m ] For h = 175cm and Md(ULS) = 1812,22kN.m: = 0.173
For h = 175cm and Md(ULS) = -1220,04kN.m: = 0.114
= 0,8 For h = 175cm and Md(ULS) = 1812,22kN.m: hasu= 0.138 For h
= 175cm and Md(ULS) = -1220,04kN.m: hasu= 0.091 A = A
d b fCD S u
ed
For h = 175cm and Md (ULS) = 1812,22kN.m: S = 28,4cm2 For h =
175cm and Md (ULS) = -1220,04kN.m: A S
= 18.7cm2
Choice longitudinal reinforcement: 6HA25 (2 beds)
A = 29,45cm2
6HA20 (2 beds)
A = 18,85cm2
t= F 0,9ded V (ULS)
= 9,87cm / cm2
Choice transverse reinforcement: 2 frames HA8 all 19cm.
Checking the tensile stress in concrete:
V =d(ULS) = 0,99MPa u b d
ULIM
F = 0.2 c 28
= 3,33MPa
b
Surface reinforcement: HA10.
Beam rack platform upper tapered:
Stresses:
-
20VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
d
M (ULS) -1220,04kN.m = M (ULS) -460,51kN.m = V (ULS) =
589,83kN
-
20VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
f
u
u
AA
S
S
sA d
C
u u
hu u
f
t
Calculation of reinforcement Asmini section:
m = Mjd(ULS) u b d2 For h = 206cm and Md(ULS) = -1220,04kN.m:
mu= 0.063 For h = 100cm and Md(ULS) = -460,51kN.m: mu= 0.100
= 1.25[1
1-2m ] For h = 206cm and Md(ULS) = -1220,04kN.m: = 0.081 For h =
100cm and Md(ULS) = -460,51kN.m: = 0.132
= 0,8 For h = 206cm and Md(ULS) = -1220,04kN.m: hasu= 0.065 For
h = 100cm and Md(ULS) = -460,51kN.m: hasu= 0.106
A = A
d b fCD S u
ed
For h = 206cm and Md (ULS) = -1220,04kN.m: S = 15,6cm2 For h =
100cm and Md (ULS) = -460,51kN.m: S = 12,43cm2
Choice longitudinal reinforcement: 6HA20 (2 beds)
A = 18,85cm2
3HA25 (1 bed)
A = 14,73cm2
t= F 0,9ded V
(ULS)
= 4,78cm / cm2
Choice transverse reinforcement: 2 frames HA8 all 9cm.
Checking the tensile stress in concrete:
V =d(ULS) = 1,64MPa u b d ULIM
F = 0.2 c 28
= 3,33MPa
b
Surface reinforcement: HA10.
-
21VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
d
d
d
d
f C
u u
Figure II.3: purifies stop bars beam rack high platform from the
diagram bending moment envelope.
Low beam rack forum:
Stresses: M (ULS) -1114,89kN.m = M (ULS) = 618,72kN.m M (ULS)
-273,93kN.m = M (ULS) 757,86kN.m = V (ULS) = 475,07kN V (ULS) =
461,31kN
Calculation of reinforcement Asmini section:
m = Mjd(ULS) u b d2 For h = 115cm and Md(ULS) = -1114,89kN.m:
mu= 0.183 For h = 115cm and Md(ULS) = 678,72kN.m: mu= 0.102 For h =
80cm and Md(ULS) = -273,93kN.m: mu= 0.093 For h = 80cm and Md(ULS)
= 757,86kN.m: mu= 0.258
= 1.25[1 1-2m ] For h = 115cm and Md(ULS) = -1114,89kN.m: u=
0.256 For h = 115cm and Md(ULS) = 678,72kN.m: u= 0.135 For h = 80cm
and Md(ULS) = -273,93kN.m: u= 0.122 For h = 80cm and Md(ULS) =
757,86kN.m: u= 0.380
-
22VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
AA
A
S
S
S
S
sA d
hu u
f
t
= 0,8
For h = 115cm and Md(ULS) = -1114,89kN.m: hasu= 0.205 For h =
115cm and Md(ULS) = 678,72kN.m: hasu= 0.108 For h = 80cm and
Md(ULS) = -273,93kN.m: hasu= 0.098 For h = 80cm and Md(ULS) =
757,86kN.m: hasu= 0.304
A = A
d b fCD S u
ed
For h = 115cm and Md (ULS) = -1114,89kN.m: S = 27,60cm2 For h =
115cm and Md (ULS) = 678,72kN.m: S = 14,53cm2 For h = 80cm and Md
(ULS) = -273,93kN.m: A S
= 9,20cm2
For h = 80cm and Md (ULS) = 757,86kN.m: S = 28,55cm2
Choice longitudinal reinforcement: 6HA25 (2 beds)
A = 29,45cm2
3HA20 and 3HA16
A = 15,45cm2
3HA20 A = 29,45cm2
6HA25 (2 beds)
A = 29,45cm2
t= F 0,9ded V (ULS)
= 6,11cm / cm2
Choice executives: HA8 every 12cm.
Checking the tensile stress in concrete:
V =d(ULS) = 1,14MPa u b d
ULIM
F = 0.2 c 28
= 3,33MPa for h = 115cm and Vd(ULS) = 475,07kN
V =d(ULS) = 1,60MPa u b d
ULIM
b
F = 0.2 c 28
= 3,33MPa for h = 115cm and Vd(ULS) = 461,31kN
b
Surface reinforcement: HA10.
-
23VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
A AA t
Figure II.4: purifies stop bars beam rack low platform from the
diagram bending moment envelope.
Reinforcement beams racks is complex. Indeed, a study should be
made on the disposal of the latter. Always for the sake of rapid
implementation and thus economy, emphasis should be placed on a
prefabrication of reinforcement cages with on-site assembly,
minimizing the introduction of reinforcement bracket. We decide to
make the rack beam high tribune two reinforcement cages. Both beds
3HA20 part of variable inertia will be stopped and realized the
anchor using splints (2 times 3HA20) which will be implemented on
site. These elements are very important for the resistance of the
section, it must at all costs prevent wrong installation so it was
decided to voluntarily increase the length, which is usually twice
the length of a bar anchor HA20 , 30cm on each side in order to
take into account the tolerances of implementation. This provision
also increases the effective length to achieve sewing.
As
Sides
At Figure II.5: Distribution splints.
Checking the sewing: We made the choice to insert three sides
between the two frames beds which reduces the reinforcement sewing
since shear can occur in two planes.
So we must have:
n =
S(l
2
anchorage
30 +)= S( 44 30 +)= 9,42cm2 2
From where n = 5
(Because we arranged two frames HA8)
To achieve the seam must be separated five times two frames
1.20m HA8 is every 20cm.
-
24VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
b) Check posts:
The posts 210 x 40 and 276 x 40 are solicited compound bend.
They must therefore be
determined by taking into account the interaction between the
normal force and bending moment. Their generous dimensions allow to
resume the internal forces with small sections of reinforcement.
However, these elements provide bracing in the transverse direction
(effect of swings), and a reduction in their section might tend to
weaken the dynamic behavior of the skeleton.
4. Etudedtailledesgradins :
a) Form:
The goal is to find an optimized shape for the stands which is
both resistant (static and dynamic), both economical and also
allowing easy implementation to reduce the time of construction.
Several forms of step were investigated, but only one was chosen.
The stands are made of precast reinforced concrete face for casting
mold base. Each member include a step with a gradient of 1% to the
flow of water, an edge and running against a rounded with dropout
and heel (II.2 see Figure below). The concrete thickness is at
least 15cm. These items will be self-supporting, they will receive
a sealing resin. The stands are placed on racks beams starting from
the top item, the operation of each element resting on the heel of
the previous element (see Figure II.10). The junctions will be
keyed on-bead over the entire length so as to obtain the required
mechanical continuity bracing building. Marches and marches against
the law will be keyed racks with continuity of reinforcement. The
keyways will be realized through a concrete shrinkage
compensated.
Figure II.6: typical cross section of a step.
In fact, there are three types of step. The tiers of the bottom
portion 40 have dimensions of 80cm X, while those of the upper part
have dimensions of 54 x 60 x 80cm or 90cm (partly for VIP).
Nevertheless, it will be considered that the steps of dimension 40
x 80cm they are the worst (lever arm weakest).
-
25VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
G1 1 G2 2 G3 3
AAA
1
2
3
1 2 3
zzz
G
G
G
z = zG
b) Features:
It seeks to identify the characteristics (area and inertia) of
the selected section. To do this we
decompose the complex into three rectangular section.
Figure II.7: decomposition of section three.
Calculate the area of the section:
= 15 = 65 975cm2
= 15 = 70 1050cm2
= 15 10 = 150cm2
A = A + A + A
= 2175cm2
Figure II.8: position of the center of gravity of the
section.
Determination of the position of the center of gravity:
= 62,5cm
= 35cm
= 7.5cm
from where
z A + z A + z A
G A
= 45,4cm
-
26VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
G1 1 G2 2 G3 3
Gy + Dz
3
1
2
3
Gz 1
e e
tt
t
G
G
G
t = t G
I 1 G G
I
I3
2
3
G
G
G
G
y
2
1 1
y 2 2 y 3 3
I = 2 2 G G
I = 3 3 G G
z 1
2 2 2 z 3 3
f fC
= 57,5cm
= 17.5cm
= 5cm
from where
there A + y A + y A
G A
= 34,1cm
Calculation of inertia:
3
B =1 h1 y1 12
= 18281,25cm4
3
dz = z - Z = 17,1cm
B =2 h2 y 2 12
B =3 h3 y 3 12
= 42875cm4
= 2812,5cm4
dz = z - Z
dz = z - Z
= -10,4cm
= -37,9cm
where I = (I ) + (I + Dz
2 A ) + (I + Dz 2 A ) = 1063973cm4
I B =1 h = 343281cm4 dy = y - Y = 23,4cm
z1 12 3
1 G1 G
b h 2 z 12
3
= 18281,25cm4
dy = y - Y = -16,6cm
b h z 3 12
= 1250cm4 dy = y - Y = -29,1cm
where I = (I + Dy 2 A ) + (I + Dy
2 A ) + (I + Dy
2 A ) = 1313043cm4
c) Reinforcement:
We can now perform calculations to identify concrete steps for
the rebar and sections required
to achieve the principle of reinforcement.
Calculation in flexion (final phase):
Material characteristics: Concrete: B25
c 28
= 25MPa = 14,17MPa
Steels: HA feE500 f = 500 MPa f = 434,8MPa
-
27VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
pppp
1
2
3
4
Modeling:
Figures II.9: modeling.
Loads: Q = 5 kN / m2
(According to the program established by GPCI, standard NFP
06-001 provides 4 kN / m)
= 0.55 0.15 25 = 2,0625kN / m = 0.15 0.74 25 = 2,625kN / m =
0.10 0.15 25 = 0,375kN / m = 0.65 0.15 25 = 2,4375kN / m
q = 5 0.8 = 4 kN / m
g = 2.0625 + 2.625 + 0.375 + 2.4375
= 5,25kN / m
2 2
Calculation of forces: 2
M (ULS) = (1.35g + 1.5Q) L
= 147,64kN.m
d 8 2
M (ELS) = (g + q) L = 104,35kN.m d 8
V (ULS) = (1.35g + 1.5Q) L
= 62,17kN
d 2
-
28VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
S
sA d
m =
u u
hu u
A S u
t
-
+
+
+
Figure II.10: diagram of internal forces to ULS and SLS (shear
and bending moment).
Calculation of reinforcement Asmini section:
Little detrimental cracking (calculated to the ultimate limit
state): The steps will be covered by a resin (polyurethane or
methyl methacrylate, for example). But after searching for
different commercial products, it was found that no indication of
the quality of the carrier resin (in terms of cracking) was given.
Therefore in order to ensure the sustainability and not crack
sealing, it was decided to make a calculation of the bleachers at
the serviceability limit state (in harmful or very harmful
cracking). So the calculation somewhat detrimental cracking is
actually a calculation of principle, but may still be useful if
another method of sealing was chosen. Moreover, the three
calculations (little detrimental cracking, very harmful and
detrimental) compare an economic point of view the
reinforcement.
M (ULS)
u b d2 f = 0.178
= 1.25[1 -
CD
1 - 2m ] = 0.247 = 0,8 = 0.197 = A b d fCD
f
= 6,03cm2
ed
Choice longitudinal reinforcement: 6HA12 (2 beds) or A =
6,78cm2
(We decided to have the
longitudinal reinforcement in the entire width of the heel of 2
beds).
t= F 0,9ded V (ULS)
= 39,34cm / cm2
Choice executives: HA6 every 25cm.
-
29VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
= Checking the tensile stress in concrete:
V (ULS) d = 0,66MPa u b d
u lim
F = 0.2 c 28
= 3,33MPa
b
Surface reinforcement: HA8.
-
30VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
3
d
d
S
sA d
ftj
S
m =
S
t
=
Figure II.11: principle of reinforcement in no detrimental
cracking.
Detrimental cracking (calculated limit state service): = = f
min2, max{0.5 f; 110 f }
= 250 MPa S e
e tj = 1.6
(Steels HA)
= 0.6 + 0.06 f
c 28
= 2,1MPa
m = M (ELS)
= 0.107 S b d2 / n
2 (1 - / 3) S 2 (1 - )
A = M (ELS)
from where = 0.388
= 7,67cm2
S (1 - / 3) d
Choice longitudinal reinforcement: 6HA14 (2 beds) or A =
9,24cm2
(We decided to have the longitudinal reinforcement in the entire
width of the heel of 2 beds).
t= F 0,9ded V (ULS)
= 39,34cm / cm2
Choice executives: HA6 every 25cm.
Checking the tensile stress in concrete: V (ULS) d = 0,66MPa u b
d
u lim
F = 0.2 c 28
= 3,33MPa
b
Surface reinforcement: HA10 (3cm per meter of wall length
measured perpendicular to their direction).
-
31VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Figure II.12: principle of reinforcement of harmful
cracking.
-
30VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
3
d
d
S
sA d
ftj
S
m =
S
t
=
Very detrimental cracking (calculated limit state service): = =
0.8 0,8 min2 f, max{0.5 f; 110 f }
= 200 MPa S e
e tj = 1.6
(Steels HA)
= 0.6 + 0.06 f
c 28
= 2,1MPa
m = M (ELS)
= 0.134 S b d2 / n
2 (1 - / 3) S 2 (1 - )
A = M (ELS)
from where = 0.423
= 9,72cm2
S (1 - / 3) d
Choice longitudinal reinforcement: 6HA16 (2 beds) or A =
12,10cm2 (We decided to have the
longitudinal reinforcement in the entire width of the heel of 2
beds).
t= F 0,9ded V (ULS)
= 39,34cm / cm2
Choice executives: HA8 every 20cm.
Checking the tensile stress in concrete: V (ULS) d = 0,58MPa u b
d
u lim
F = 0.2 c 28
= 3,33MPa
b
Armatures of skin: HA10 and HA12 (5cm by meter of length of wall
measured perpendicular to their direction).
Figure II.13: principle of reinforcement in very detrimental
cracking.
Calculate torsional (construction phase):
Installation of the prefabricated girder no i + 1: It seeks to
implement these steps without the use of props. Prefabricated
bleachers will be installed from the top and going down the table
compression step No. i + 1 basis on the heel of the step n i. When
precast step No. i + 1 is set, check that the No. i is stable, that
is to say, it does not spill and must also verify that the
calculated reinforcements previously allow it to withstand the
torsion applied thereto. It should be noted that such a calculation
is almost never done in phase APS. For this operation, the
-
31VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
aim is to minimize the maximum cost and time of implementation,
it could be appropriate to carry out an approach to the
construction phase from the first draft.
-
32VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Q C
pppp
1
2
3
4
3
Modeling:
Figure II.14: modeling the construction phase.
Loads: = 4kN (Construction hoist defined by extrapolation of the
Technical Specification
processes common to the floors, Title II and III) = 0.55 0.15 25
= 2,0625kN / m = 0.15 0.74 25 = 2,625kN / m = 0.10 0.15 25 =
0,375kN / m = 0.65 0.15 25 = 2,4375kN / m
Check that the moment which tends to reverse the step is less
than the time which tends to stabilize:
M = Q
0.1 + 0.15 + p 9.5 0.1 + 0.15 = 0,92kN.m
R C 2
2 2 2
R = p1 2
= 2.0625 = 1,03kN /
m 2 M = 2.0625 9.5 0.55 + 0.15 = 3,43kN.m
S M> M
-
33VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
2 2 2 S R
-
34VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
C
d m =
u u
hu u
A S u
Q 0.175 0.15 + 0.55
2
= 1,12kN
2 1,03 = 1.12 x = 1,09m
2
+ +
Figure II.15: diagram of the bearing pressure at the heel of the
prefabricated No. i. Flexion:
Figure II.16: modeling flexion during the construction
phase.
Loads:
g = 2.0625 2 + 2.625 + 0.375 = 5,06kN / m 2
Calculation of forces: M (ULS) = L (GL 1.35 + 1.5 2 Q
)= 93,31kN.m
d 8 C
V (ULS) = 1.5 QC+ 1.35 Gl = 35,45kN
d 2
+
M (ULS) u b d2 f
Figure II.17: bending moment diagram at ULS.
= 0.112
= 1.25[1 -
CD
1 - 2m ] = 0.149 = 0,8 = 0.119 = A b d fCD
f
-
35VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
sA dt
= 3,65cm2
t= F 0,9ded V (ULS)
ed = 68,99cm / cm2
-
36VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
=
C
3
Checking the tensile stress in concrete:
V (ULS) d = 0,38MPa u b d
u lim
F = 0.2 c 28
= 3,33MPa
b
Torsion:
Q = C
Figure II.18: modeling of twist during the construction phase. =
0.1 + 0.15 0,7kN.m 2
c / m = p
= 0.1 + 0.15 0,05kN.m / m
2 2
Figure II.19: diagram torques.
For the torsion can not be considered a section whose height is
more than three times its width, so: h = 15 3 = 45cm
-
37VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Figure II.20: definition of resistant section in torsion.
-
38VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
T
T
t
A s
f
f
T
u
A s
T
s
s
u b
= 0
V
u S
l
t ed
f
= 1.5 0.35 = 0,525kN.m
= 15 = 2.5cm 0 6
= 53125mm2 u = 1.1m
u t 2b = 0.2 MPa
Check that: 2+ 2 = 0.382+ 0.202 0.18 2 u lim
= 11.11
t and
t S
A = l e= u 2
= A T u 2 f = 0,125cm2
t= u 2 f
ed
= 0,001cm2/ Cm
For f c 28
40MPa : A t B = 0.4 0
= 0,0023cm2/ Cm
tmin ed ( A ) A =
t U = 0.25 cm 2
l min tmin
A 2 S+
A l = 2,56cm2 + 4HA12 2HA8
3 4
6,78cm2
max{0,0023cm2/ Cm; 0,014cm2/ Cm} 0,025cm2/ Cm
The section of reinforced concrete so resistant to twisting.
d) Fire stability:
In the stands, structural fire and CF degree (fire) 1:30 is
required. To check the fire stability of these elements, simplified
rules (Chapter 7.51) DTU P 92-701 Calculation Rules FB - Prediction
by calculating the fire behavior of concrete structures in October
1987 will be used. The stands are beams to heel:
Minimum (2 1h1 /) value required Actual value Heel width b [cm]
24 25 Heel height h0[Cm] 12 15 Beam width b0[Cm] 12 15
-
39VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Number of lower beds 2 2 Coating 5.5 5.6 Number of bars per bed
2 3
One realizes, after applying the simplified rules, that the
steps are stable fire at least 1:30, which is in line with fire
regulations and classification of ERP platform.
-
40VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
V
e) Dynamic:
The aim is to ensure that when the crowd jumps in the stands,
the resonant frequency of the latter is higher than the frequency
of the action of the crowd seeking the following in order to ensure
user comfort.
Hypothesis:
It is considered that the step is a beam of constant cross
section and mass evenly distributed. The formula for calculating
the period of the first five modes as follows:
T = L2
Along with:
p g EI
T = 2 [s] : Period. f
= 0.636
: Coefficient depending on the mode (mode 1: the worst fashion
period giving the
Thus the greater the smaller frequency).
= 0.636
L = 9,50m : Length of the beam. E = E f =
11000
c 28
Third = 32164,2MPa : Modulus of elasticity instant.
g = 9,81m / s : Acceleration of gravity. p = 5.25 + 4 = 9,25kN /
m : Applied load. I [cm4] Moment of inertia of the beam (the
reduced section of inertia).
Calculate the moment of inertia:
For the calculation of inertia, a question arises, should we use
to calculate the time (and thus frequency) geometric inertia of the
section or the inertia of the cracked section. The inertia of the
fractured section is significantly smaller (about twice) the
inertia of the geometric section. So it will give the largest and
therefore the smallest frequency period, which puts us on the side
of safety.
-
41VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Figure II.19: scheme of calculating the inertia of the reduced
section.
-
42VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
S 0
S
AN
AN
AN
I3
0
t 0
t 0
t 0
Re d / AN = 0 :b y y0
- N A (d - y )= 0
= B y0 AN 3
0
A + n
2
(d - y )2 Little detrimental cracking:
= 11,40cm I = 305067,89cm4 T = 0,178s
from where f = 35Hz
Detrimental cracking: = 13,08cm
I = 398182,73cm4 T = 0,156s
from where f = 40Hz
Very detrimental cracking: = 14,72cm
I = 499404,98cm4 T = 0,139s
from where f = 45Hz
The natural frequencies of the beam slightly detrimental
cracking, very detrimental and harmful being considerably above 3Hz
(hopping frequency and stroke of a human being, used for dynamic
calculations gateways), so there is no risk of a dynamic viewpoint
of precast bleachers.
-
43VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
pn
n =
n
CHAPTER III Metal roofing
1. Hypothsesdecalcul :
a) Rules of calculation:
Calculations are made of steel construction according to DTU P
22-701 Rules CM - Design rules for steel structures December 1966
Regarding climatic loads (snow and wind), charges are calculated
according to DTU P 06 Rules 65 -002 NV - Rules defining the effects
of snow and wind on buildings and annexes of April 2000.
b) Loads applied to the structure:
Dead Load:
We can decompose dead loads in two loads: the weight of the
metal forming the roof structure and the load induced by hedges
(galvanized steel tray supporting a complex seal comprising an
insulating rockwool high density and sealing PVC membrane),
dressing on the underside (flat panels prepainted galvanized steel
riveted on a secondary frame suspended from the roof) and any
technical equipment (lighting, sound) that could be suspended: g =
50 daN / m2
= 0,50kN / m2
Operating expense:
The roof was not available except for any needed repairs, no
operating expenses are planned. Snow load:
The building is located in Besancon in the Doubs (25), the site
is classified in zone 2A (following the NV65 Rules). The altitude
of 282m asl. We can therefore calculate the snow load that will
apply on the roof:
= 45daN / m2
= 0,45kN / m2
200 A = 282m 500m
therefore p A + - 200
n0 10
where p
= 53daN / m2
= 0,53kN / m2
Wind Load:
Effect of wind on the roof are determined by applying the NV65
and especially the chapters on openwork construction and insulated
roof dimensions and proportions equivalent to the draft rules,
which is a priori detrimental (ie the side of safety ) compared to
wind tunnel tests that are also not expected results. The Doubs
(25) is classified as zone 1 NV65 rules, hence:
Basic dynamic pressure: q = 50 daN / m2
-
44VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
= 0,50kN / m2: Zone 1.
-
45VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
kS
k
b
0 S H
0 e
i
i 0
i
i 0
i
i
Site effect:
= 1.00 : Normal site (zone 1).
Effect of height above the ground:
H = 2.5 18 + The building height is between 19 and 20m so: k H H
+ 60 H
= 1.18 .
Aspect ratio:
= H h = has has b b Considering that the two parts of the roof
cantilevered overhang are actually elements of a building
with an open wall.
= H = has
has
19 99.8
= 0.19
0.5
therefore 0
= 1.00 (Figure III-R-NV 5 of Regulation 65)
Dynamic pressure corrected: q = q k k = 59daN / m2
Calculation of internal and external factors:
= 1.00 and 0
(Roof angle): c = -0.45 (Figure III-R-NV 6 of Regulation 65)
Door overhang 2.50m: c = 0.8: when this part is in the wind
(wind from left to right). c = 0.6(1.8 - 1,3 )= 0.3 When this part
is the wind (wind from right to left). Door overhang of 10m: c =
0.8: when this part is in the wind (wind from right to left). c =
0.6(1.8 - 1,3 )= 0.3 When this part is the wind (wind from left to
right). Inside the VIP lounge: c = 0.3 : When the wind is in
pressure. c = -0.3 : When the wind is in depression.
For masts: The focus here is on the part of the mast sticking
out of the building and extends to the point of attachment of the
tie-struts. One must calculate a drag coefficient, it is assumed
for simplicity that the masts have constant diameter of 1m (this
puts us safe).
It first calculates the size ratio.
h = d
H is the height of the mast part windward (10m) and the diameter
of the mast (1m).
= 10 = 10 1
-
46VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
0
1.20 (this coefficient is obtained from Figure III-R-NV 10 of
Regulation 65).
-
47VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
c 0 0
c0
t0 0
t t
The drag coefficient is: t C = with CT0 is the overall drag
coefficient function
of the form (category VI: smooth circular cylinder without rib
and having a polished specular and long lasting) and which is in
our case
= .90 To .30 d q = 0.68
car
0.5
-
48VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
composing the structure, checking deformations and
movements.
-
40VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
a) Evolution of the static system:
The static system of metal roofing has evolved through four
variants, the latter being of course
the structure used for the calculation and the future roof
sheltering the rostrum. These variants are the result of an
optimization approach while retaining the positive aspects and
strengths of previous variants. These solutions are not independent
of each other but are steps that have led to a satisfactory
structure.
Note: sheet is defined by the entire roof deck (ties, purlins,
bracing) and all media for suspending the aquifer height (masts,
anchors, tie-struts and girders, depending on the elements used in
each variant), possibly see chapter 3 (general description of the
structure).
First alternative:
Ties (elements
working in tension)
Tablecloth
Completely metal mast
Figure III.2: first variant of the static system.
Initially, the idea is, as desired by the architect to achieve a
wing suspended height of the masts, seven in number and arranged
irregularly. A first model was made on this basis. However, given
the length of the elements connecting the roof poles (about 20m),
and in order to avoid problems related to buckling, it was
initially decided that they do work in tension (tie ). Furthermore,
the positioning of the poles causes uneven manner a real problem.
Indeed, the difficulty lies in the design of the web. The question
is: should we have ties with regular spacings or does it stall the
pace of spacing of ties on one variable, between the masts.
Regular spacings
Solution 1
Irregular distances
Solution 2
Figure III.3: solutions for the design of the web.
-
41VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Solution 1 Solution 2
Description Regular grid Irregular frame Benefits One length of
failures Bonded sheet to 7 masts 7
sleepers (cross beams) Disadvantages
No cross attachable on masts Adding additional elements linking
the water masts (headers)
Failures of different lengths
The first idea was to choose a regular pattern, as is
traditionally done for metal roofs. It was therefore added
additional elements linking the water masts (headers). Down under
loads (dead weight, dead load and snow) the ties are in tension and
transmit much of the efforts to masts. Charges under upward (wind)
the tie are neglected and the forces are transmitted by the masts
trimmers working in console.
Since the elements connecting the poles to the roof and bracing
are used as tie rods (elements working in tension), the calculation
is nonlinear.
Option 1 Web weight [t] 169.5 Media Weight [t] 332 Total weight
[t] 501.5 Ratio [kg / m] 138.1
Second alternative:
Ties (elements working in tension)
Tablecloth
Completely metal mast
Ties (elements working in tension) inserted into the facades of
the VIP
lounge Figure III.4: second variant of the static system.
The effect of the wind tends to raise the roof, a second
alternative should be considered. The latter consists of the
addition of tie rods in the water, finding support on the slab of
the VIP area and which aims to reduce the bending forces seeking
trimmers. These ties are hidden, for architectural reasons, in
external joinery supports the glass facades of the VIP lounge.
Indeed, the architect does not want these elements are visible.
However, this solution is bad because it involves considerable
efforts parasites which significantly increase the stresses in the
members connecting the roof poles. Such parasitic forces are mainly
the fact that the tie rods are not added in front of the tie rods
on a main cross-section.
-
42VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Since the elements connecting the poles to the roof and bracing
are used as tie rods (elements working in tension), the calculation
is nonlinear.
Alternative Web weight [t] 169.5 Media Weight [t] 350 Total
weight [t] 519.5 Ratio [kg / m] 157.4
After analyzing the results of the first two variants, it turned
out that the forces (normal forces and bending particular times)
seeking masts are so important that they have unrealistic
dimensional metal sections conventional commercial or PRS (
Engineered Welded profiles).
Third alternative: Pullers-Struts (elements working in
tension and compression)
Mast part made of metal
Part made of
concrete mast
Tablecloth
Figure III.5: third variant of the static system.
The third variant is, somehow, a bit of a return to the first,
except that this time, the members connecting the roof to the mast
are no longer used only in tension, but tension and compression
(tie-struts). Indeed, any compressive forces that might seek the
elements connecting the roof poles are actually not excessive and
therefore will not cause buckling problem. However, after analyzing
the results, efforts in the masts are so important that they still
can not be made of metal profiles conventional commercial or PRS
(cylindrical-conical shape). Therefore by virtue of their stress
exclusively by normal forces and bending moments along the y axis
predominant (relative to the z axis), it has even been devised to
achieve SRP and the H collapse rather than have them form
cylindroconical: this in order to use the material where it is
needed. Also in order to reduce the cost of the structure, the
option was taken to hold the portion of masts within the forum
reinforced concrete and let metal from the floor of the VIP lounge.
The architect wished to remain in the VIP lounge metal material to
give the illusion of a mast from the ground, crossing the wing
formed by the roof and rushing the sky. In addition, the VIP lounge
is almost entirely glass, the illusion seems even more likely.
Since braces work only traction, the calculation is
nonlinear.
-
43VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Option 3 Web weight [t] 152.3 Media Weight [t] 246 Total weight
[t] 398.3 Ratio [kg / m] 120.7
At this stage, the solution is satisfactory from a strictly
technical point of view and architectural. However, the cost of
such a structure appears excessive. That is why we must find a
radical solution of the economic point of view.
Fourth alternative:
Pullers-Struts (elements working in
tension and compression)
Mast part made of metal
Tablecloth
Part made of
concrete mast
Pullers-Struts (elements working in tension and compression)
Related
porticos concrete after the concrete frame structure
Figure III.6: latest evolution of the static system.
The last variant is the future structure. The elements linking
the roof poles are used both in tension and in compression
(tie-braces), the tie-struts resting on the concrete structure
constituting the platform were added back. The position of these
tie-struts is punctuated by concrete porches, and their role is to
relieve the masts and limit efforts in key tie-struts. Part of the
poles inside the gallery (below the slab of the VIP lounge) is made
concrete in the interests of economy. The web has also evolved
since the idea of designing the web based on a regular grid has
been abandoned in favor of the solution of irregular frame (which
eliminates the headers).
Since braces work only traction, the calculation is
nonlinear.
Option 4 Web weight [t] 135.1 Media Weight [t] 142.4 Total
weight [t] 277.5 Ratio [kg / m] 92.5
The solution this time is satisfactory to all points of view. It
is true that architecturally mind wing suspended height is a little
lost, but nevertheless the addition of rear tie-paced struts on the
concrete structure brings another aspect to the project, however,
not denatured.
-
44VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
t z
qd SQd d
q d SQ d d
s
It
l
b) Estimated by manual calculation of certain profile
sections:
Failures:
We choose to scale the longer outages (6,47m length) and having
a wheelbase is 2.50m. We choose to make isostatic.
Q = g + = 0.5 + 0.53 = 1,03kN / m2 = Q = 2.50 2,55kN / m 5 L Q4
f =
The
384 EI 5 Q
From where I d 200 L4
5 Q
E 384 L L4
200
d
E 384 L
200
= 856,45cm4 choice: IPE 200.
Verification:
Q = g + = 0.5 + 0.53 = 1,03kN / m2 Q = 2.50 + G IPE
200 = 2,774kN / m
5 L Q4 f = The 384 EI 5 Q
From where I d 200 L4
5 Q
E 384 L L4
200
d
E 384 L
200
= 931,68cm4 choice: IPE 200.
M (ULS) = [1.35(g 2.50 + G
IPE 200
)+1.5(q 2.50)] L2
= 20,81kN.m
d adm
= M 275MPad(ULS)
I v
8 M (ULS)
d I = 158MPa v
Spill: 2 2
= I Ez h (D - 1) BC : Constraint not spill d 5.2 l
E = 210000MPa I = 1943cm4 I = 142,4cm4 h = 200cm
= L = 3,235m (Placing a link fault at mid-length) d 2 B = 1.00 C
=
-
45VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
2
dd e
(Averaged over the length constant load) D = 1 + lde
= 1.7
where
Bh = 406MPa the IPE section 200 does not spill because >
-
46VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
d
e
=
k
e
Braces:
Braces are only called in tension, tubular sections are chosen.
Longer bracing 8,179m measure. N (ULS) = -70,39kN (Tensile)
adm = N 275MPad(ULS)
A A Nd(ULS)
A 2,56cm2
Choice x 3.2mm round tube 33,7mm.
adm
We must check the arrow on each brace bent half-length (either
4,09m). 4
f = 5 L G 384
EI
L 200
along with G = 0,0199kN / m
f L 200
f = 1cm
The 2cm = 200
Main-braces tie rods: The main tie-struts are biased either in
traction or compression, tubular sections are chosen. Longer main
tie-braces measure 17,708m. Because of their length and because it
can be compressed, they must be checked to buckling. N (ULS) =
112,07kN
(Compression)
N (ULS) = -1069,27kN (Tensile)
adm = N 275MPad(ULS)
A A Nd(ULS)
A 38,88cm2
choice: Round tube 273 x 10
= Nd(ULS) = A 13,57MPa
adm
k = 275MPa
k = 0.5 + 0.65 2E
o
e + k
0.5 + 0.65
2 o
e k
e
k
k 2 : Euler critical stress
= L = 190.2 i
where
2E = = 57,29MPa
2 therefore k = 6.50 k =
88,21MPa : No problem buckling
Tie rods, struts Rear:
The tie-back braces are biased either in traction or
compression, tubular sections are chosen. Longer
-
47VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d
d
tie-back braces measure 12,43m. Because of their length and
because it can be compressed, they must be checked to buckling. N
(ULS) = 203,28kN (Compression) N (ULS) = -623,97kN (Tensile)
-
48VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
e
=
k
e
adm = N 275MPad(ULS)
A A Nd(ULS)
A 22,69cm2
choice: 193.7 x 10 round tube
= Nd(ULS) = A 35,23MPa
adm
k = 275MPa
k = 0.5 + 0.65 2E
o
e + k
0.5 + 0.65
2 o
e k
e
k
k 2 : Euler critical stress
= L = 191.2 i
where
2E = = 56,69MPa
2 therefore k = 5.90 k = 207,86MPa : No problem buckling
-
49VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
c) Design parameters:
When modeling in ROBOT, we must define the types of bars. This
allows to dimension the bars
when calculating the structure. Once the latter created
geometrically, enter the parameters that will allow to size bars:
resistance (choice of material and its resistance), buckling
(definition of buckling parameters) and dumping (parameter
definition buckling). This calls for a reflection, in fact, you
have to have an idea when creating a model of support elements and
the interactions between these conditions.
Figure III.7: design parameters of the elements of the roof.
-
50VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
d) Main results:
In this part, the results are presented as Figure to illustrate
the structure of the deformations
depending on the different load cases. Tables show the forces
that are transmitted by the metallic structure forming the roof to
the concrete structure. The next section describes and explains the
principle structure of the roof.
Figure III.8: perspective views of the steel structure.
Figure III.9: sign convention and notation for the forces
transmitted to the metal poles concrete structure.
-
51VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Figure III.10: forces transmitted metal poles with concrete
poles.
Figure III.11: efforts transmitted to tie-back braces the
concrete structure.
Figure III.12: displacements under different load cases.
-
50VERY Guillaume, INSA Strasbourg, Specialty Engineering,
Project Report graduation.
Comments:
The most sought poles are masts ends (No. 1 and No. 7). Bending
poles along the y axis is predominant compared to that along z.
Cases of wind V1, V2 (left right wind pressure and depression), V5
and V6 (longitudinal wind pressure and depression) tend to relieve
the structure and thus reduce efforts in the masts. The greatest
displacement occurs under constant load (dead weight and burden of
roof). The ends of the roof are deformed more than the rest, this
is explained by the fact that it has a double door overhang that
amplifies the deformation. Cases of V3 and V4 wind (wind right left
overpressure and depression) reduces the deformation of the canopy
by reducing travel. After analyzing the displacements obtained
under each load case, it is necessary to establish an arrow against
the roof in order to have a minimum slope after deformation of 3%
for the evacuation of water (according to the standard). We can
then consider the influence of the arrow against the calculation of
the elements of the structure. The displacements obtained under
different load cases are to be analyzed in more detail, because
taken as they appear in the table above, could lead to the
conclusion that the structure is too flexible and that the
deformations are excessive. Indeed, the maximum movement of the
canopy door overhang can be decomposed into two parts that are
added, the first is the deformation under load of the awning and
corresponds to a second displacement caused by the bending of mast.
It is therefore essential to define a criterion flexibility to the
awning and not strictly enforce the normative standard.
3. Carrier Descriptiongnraledelastructure :
The metal roof made of a steel tray seal carrier is supported by
a metal structure shaped sheet
composed (see map of the roof structure in the appendix): a
network fault-profile trade section adapted to the range (IPE 160,
IPE 180, IPE 200) and
spaced 2.5m. a system of sleepers PRS tapered resting on two
supports and having a door overhang of 2.5m
to the rear, a central span 17,5m and door overhang 10m towards
forward. This sheet is based on a main frame with beams type wells
PRS assembled frame and suspended by major tie-struts with metal
poles and anchored by tie-struts back into the concrete structure.
These structural elements are described in detail in the following
chapters. Coverage covers an area of 30m wide by 110m long. It has
a residual slope after deformation of 3%. The evacuation of
rainwater will be through a valley located 5m from the rear side
and 25 meters from the front side. The position of the mast, in the
transverse direction, oscillates about a mean line in the th