Bridge Development Update Rebecca Curtis, PE Michigan Department of Transportation Bridge Management Engineer 2014 Michigan Bridge Conference
70

Rebecca Curtis, PE Michigan Department of Transportation ...

Feb 03, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Development Update

Rebecca Curtis, PEMichigan Department of TransportationBridge Management Engineer

2014 Michigan Bridge Conference

Page 2: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Development Update

Load Rating Plan of Corrective Action Update Technical Assistance for Load Ratings Metric 14 MiBridge Update Scour Management Questions

Page 3: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

What are the major points of the Load Rating PCA?

Tiered Deadlines for Load Ratings Three Tiers Deadlines every two years Continuing Compliance Checks (Metric 13)

Page 4: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

Tier 1

Bridges without load ratings as of January 1st, 2011 Due on December 31st, 2012

Page 5: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

Tier 2

Local Agency Tier 2 is comprised of bridges in poor condition

Load Ratings must be reviewed or updated to account for the poor condition

Tier 2 Load Ratings are due on December 31st, 2014

Page 6: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

Tier 3

Local Agency Tier 3 is comprised of bridges with load rating inconsistencies Proper rating method based on year of construction or

reconstruction Load posting inconsistencies

Tier 3 Load Ratings are due on December 31st, 2016

Page 7: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

Page 8: Rebecca Curtis, PE Michigan Department of Transportation ...

Load Rating Plan of Corrective Action

Page 9: Rebecca Curtis, PE Michigan Department of Transportation ...

Technical Assistance for Load Rating

Bridge Load Rating Program Support with MTU Center for Technology and Training

2013 Accomplishments User Needs Survey Camelback bridge tutorial, CMP culvert spreadsheet,

SHV analysis Over 68 technical assistance cases Processed 68 license requests

Page 10: Rebecca Curtis, PE Michigan Department of Transportation ...

Technical Assistance for Load Rating

2014 Plans 3 bridge rating workshops 4+ Webinars (starts April 3rd) The Basics Theory and Policy Output Reports Concrete Box Culverts

Update CMP culvert spreadsheet Continued technical support and license facilitation

Page 11: Rebecca Curtis, PE Michigan Department of Transportation ...

AASHTOWare Bridge Design & Rating

User Group Meeting for software formerly known as Virtis/Opis

Basic and/or advanced training included

August 12th and 13th

Park Place Hotel, Traverse City

Page 12: Rebecca Curtis, PE Michigan Department of Transportation ...

Metric 14 – Inspection Procedures, Post or Restrict Metric 14

Rating less than 100% legal loads and still open Posting recommended Rating less than 3 Tons and open without restrictions

At this time last year, there were 183 bridges with postings recommended

Page 13: Rebecca Curtis, PE Michigan Department of Transportation ...

Metric 14 – Inspection Procedures, Post or Restrict MDOT will check data monthly for possible Metric

14 compliance issues Safety issues must be addressed as soon as

possible Inventory must be addressed within 180 days for

Local Agency structures

Page 14: Rebecca Curtis, PE Michigan Department of Transportation ...

MiBridge Update

MBIS and MBRS were combined into one system National Bridge Element Inspection is in place Highlights of future planned development Add remaining element level inspection items Compliance dashboard Request for Action dashboard Call for Projects dashboard Performance Report dashboard

Page 15: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

FHWA Stewardship Agreement Goal Mitigate or reduce the number of interstate scour

critical bridges, using risked-based selection procedures, by 5 percent each year.

MDOT 426 scour critical bridges

Local agencies 1331 scour critical bridges

Page 16: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

Page 17: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

Interactive Risk Assessment Spreadsheet Created to prioritize mitigation efforts Data-driven risk assessment Adds weighted factors to water crossing bridges to

quantify vulnerability and criticality Provided local agency focused version to CRAM

Page 18: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

Page 19: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

MDOT Scour Committee is working to update guidance on design, coding, and plans of action for scour critical bridges Updating coding guidance (Item 113) Will reflect changes in HEC-23

Page 20: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

Scour countermeasures can be used to mitigate existingpiers so they are no longer scour critical

Source: FHWA

Page 21: Rebecca Curtis, PE Michigan Department of Transportation ...

Scour Management

Scour countermeasures can be considered in the design of abutments to mitigate local (abutment) scour

Source: FHWA

Page 22: Rebecca Curtis, PE Michigan Department of Transportation ...

Questions?

Rebecca Curtis, PEMichigan Department of TransportationBridge Management Engineer

2014 Michigan Bridge Conference

Page 23: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Field Services Update

Michigan Bridge ConferenceMarch 19, 2014

Page 24: Rebecca Curtis, PE Michigan Department of Transportation ...

Outline 2013 FHWA 23 Metrics Audit ABC Workshop Steel Fabrication Timeline Temporary Earth Retaining Structure Workshop Bulb T Beams Lodge Freeway Retaining Walls Bridge Approach Details Bridge Deck BOHIM (revised) 2013 BFSA Advisories

Vertical underclearance Revised MDOT Construction Manual

Page 25: Rebecca Curtis, PE Michigan Department of Transportation ...

FHWA 23 Metrics 2013 Audit 13 of 23 Metrics determined to be fully compliant Plans of Corrective action required for:

METRIC 6 – Inspection Frequency, Routine, LOW Risk

METRIC 7 – Inspection Frequency, Routine, HIGH Risk

METRIC 10 – Inspection Frequency, Fracture Critical METRIC 11 – Inspection Frequency – Frequency

Criteria METRIC 13 – Inspection Procedures, Load Rating METRIC 14 – Inspection Procedures, Post or Restrict METRIC 15 – Inspection Procedures, Bridge Files METRIC 16 – Inspection Procedures, Fracture

Critical Members METRIC 20 – Inspection Procedures, QC/QA METRIC 21 – Inspection Procedures, Critical

Findings

Page 26: Rebecca Curtis, PE Michigan Department of Transportation ...

FHWA 23 Metrics 2013 Audit METRICs 6, 7, 10, and 11 – MDOT will develop

and implement a statewide policy to require all inspection reports to be entered into to the bridge management database within thirty (30) days of completing the field portion of the inspection for all types of inspections.

This will allow MDOT to start the process of verifying timeliness earlier and as a result reduce the number of inspection that are more than (1) month late and eliminate inspections that are more than (4) months late . This policy exceeds FHWA’s regulation 23 CFR 650.313(b) of 90/180 days to update the condition ratings.

Page 27: Rebecca Curtis, PE Michigan Department of Transportation ...

FHWA 23 Metrics 2013 Audit METRICs 13, 14 and 15 – Currently part of

the Load Rating corrective action plan.

Metrics 16, 20 and 21 – PCA involves development and implementation of Michigan Bridge Inspection Reference Manual, which MDOT Bridge Field Services is in the process of creating. Draft sections are complete pending reviews from Region Bridge Engineers. Local agency will also be engaged in reviews.

Page 28: Rebecca Curtis, PE Michigan Department of Transportation ...

Accelerated Bridge Construction Workshop Workshop held December 9th, 2013

175 participants (MDOT, local agencies, consultants, industry)

Presentations from contractors, consultants, states (Utah) and ABC experts

Focus on specialized work such as structural moves and prefabricated elements

Future workshops will be coordinated.

Page 29: Rebecca Curtis, PE Michigan Department of Transportation ...

Accelerated Bridge Construction Workshop Requires change in philosophy – must think

like a contractor during design Consider equipment capacities

Page 30: Rebecca Curtis, PE Michigan Department of Transportation ...

Accelerated Bridge Construction Workshop Consider methods to accelerate construction

Page 31: Rebecca Curtis, PE Michigan Department of Transportation ...

Accelerated Bridge Construction Workshop MDOT publications

New section 7.01.19 of the Bridge Design Manual

Bridge Slide Special Provision

Page 32: Rebecca Curtis, PE Michigan Department of Transportation ...

Steel Fabrication Timelines Plate Girders with flange thicknesses less than

3 inches, and rolled beams = 26 weeks after award

Provide sufficient time in letting for fabrication of steel beams Up to 3 months for rolling, and material delivery

from mill to fabricator Up to 1 month for RFI and shop drawing review

and approval Up to 2 months for fabrication and delivery to

project site

Page 33: Rebecca Curtis, PE Michigan Department of Transportation ...

Steel Fabrication Timelines Variables that effect fabrication timelines

Fabricator chosen by contractor may have less work or greater production capacity

Some fabricators make book their production schedules in late winter/early spring

Mill order and other milestones may take equal time whether it includes one or both stages

The relationship of the contractor and fabricator

Page 34: Rebecca Curtis, PE Michigan Department of Transportation ...

Steel Fabrication Timelines New BOHIM to be released, which will

included MITA and fabricator input

Information will also be included in the Construction Manual Wiki

Please consider interim completion, or interim open to traffic dates in your progress schedule when building steel beam bridges

Page 35: Rebecca Curtis, PE Michigan Department of Transportation ...

Cofferdam Reviews Working with Geotechnical Services to

ensure all cofferdam and temporary sheeting plans and calculations are reviewed, and provide comments to field office.

Developing and Temporary Earth Retaining Structures design and construction workshop, and prequalcategory

Page 36: Rebecca Curtis, PE Michigan Department of Transportation ...

Cofferdam Reviews

Page 37: Rebecca Curtis, PE Michigan Department of Transportation ...

Cofferdam Reviews

Page 38: Rebecca Curtis, PE Michigan Department of Transportation ...

Bulb-T Beam Implementation

MDOT Bridge Committee currently working through implementation plan for prestressed Bulb-T beam

Many states including Texas, Nebraska, Washington, Indiana and Wisconsin already use prestressed Bulb-T’s

Page 39: Rebecca Curtis, PE Michigan Department of Transportation ...

Bulb-T Beam Implementation

Page 40: Rebecca Curtis, PE Michigan Department of Transportation ...

Bulb-T Beam Implementation

Benefits High load carrying capacity More efficient fabrication Improved stability during handling and

transport Shallower depths per span length –

increased underclearance Reduction in overall costs

Page 41: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 @ US-23 First use of spliced bulb-T on MDOT project Single span, 181 ft long Temporarily supported, Post-Tensioned

with closure pour (UHPC) Post-Tensioning SP from Muskegon project,

with Bulb-T fabrication SP

Page 42: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB

Page 43: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB90” Indiana Bulb Tee beams7,500 psi concrete strengthEight lines of beamsLongest Beam is 181’-8”Shortest beam is 161’-10”Longest segments is 139’ (89 tons)Five PT ducts with 12 strands in each

duct (12-0.6” strands)Duct diameter is 3 3/8” (corrugated plasticduct)2,600 kips of PT force per beam.

Page 44: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB

Stage 1

Page 45: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB

Stage 2

Page 46: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB

Stage 3

Page 47: Rebecca Curtis, PE Michigan Department of Transportation ...

Spliced Bulb-T, I-96 EB over US-23 SB

Stage 3

Page 48: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 49: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 50: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 51: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 52: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 53: Rebecca Curtis, PE Michigan Department of Transportation ...

Lodge Freeway Retaining Walls

Page 54: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Approach Details (Sleeper Slabs)

Page 55: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Approach Details (Sleeper Slabs)

Page 56: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Approach Details (Sleeper Slabs)

Page 57: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Approach Details (Sleeper Slabs) 12” minimum (36” max) Agg base or

Open Graded Drainage Course (OGDC) under sleeper slab

6” x 1’6” cut below backwall/abutment connection for joint waterproofing and drain installation

Geotextile separator used only with OGDC

Page 58: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Approach Details (Sleeper Slabs) Agg base compacted to 98%, OGDC

compacted per Special Provision 30’ cut to prevent settlement of slab during

construction 20’ approach typical

Independent backwalls may have shorter approaches based on expansion over the wall.

Site restriction may require shorter approaches.

Page 59: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Deck BOHIM Revised

Page 60: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Deck BOHIM Revised Emphasized debris clean-up prior to pour Epoxy coated steel touch-up Bridge deck pour sequence Bridge deck haunches Change in night casting pay items

No adjustments to “super concrete, night casting” or “Super Conc, Form Finish and Cure, Night Casting

Page 61: Rebecca Curtis, PE Michigan Department of Transportation ...

Bridge Deck BOHIM Revised Texturing and curing bridge decks

Exemptions to two hour limit on placement of burlap

Reference to 104.01.A to change this as necessary in cold weather conditions to accommodate additional curing time

Cold weather protection clarification

Page 62: Rebecca Curtis, PE Michigan Department of Transportation ...

Rigid Overlays Concerns regarding thickness of Silica Fume

Modified Concrete(SFMC) overlays More than 6” becomes troublesome and

creates risk of cracking Working with CFS Materials to create

alternatives to SFMC. Anticipated (design) depths

< 4” = SFMC 4”-6” = Grade D slag cement with 26A > 6” = Grade D slag cement with 6AA

Page 63: Rebecca Curtis, PE Michigan Department of Transportation ...

BFS Advisories

Page 64: Rebecca Curtis, PE Michigan Department of Transportation ...

BFS 2013-03 Vertical Under-Clearance Superstructure/Bridge replacement Roadway grade changes Beam repairs

Page 65: Rebecca Curtis, PE Michigan Department of Transportation ...

BFS 2013-03 Vertical Under-Clearance Clearance signs to be present for all

vehicular structures with under-clearance of 16’0” or less.

Measurements taken 2’ off edge of pavement

Sign will indicate 2” less than actual measurement to accommodate live load deflections

Page 66: Rebecca Curtis, PE Michigan Department of Transportation ...

BFS 2013-03 Vertical Under-Clearance Measurement included in Contractor

Staking Form 1190 Structure Clearance

Measurements to be completed Form 1120 Final Inspection/Acceptance

and Certification Report indicates clearance measurements taken

Contact Statewide Signs for assistance

Page 67: Rebecca Curtis, PE Michigan Department of Transportation ...

Revised MDOT Construction Manual Division 7 has been re-written from the

ground up Construction Manual to be released in

Wiki format in April 2014 Sample of Section 704:

http://mdotwiki.state.mi.us/construction/index.php/704_-_Steel_Sheet_Piling_and_Cofferdams

Page 68: Rebecca Curtis, PE Michigan Department of Transportation ...

Zilwaukee Bridge

SB complete NB to begin March

25, 2014

Page 69: Rebecca Curtis, PE Michigan Department of Transportation ...

US-131 over Muskegon River

To begin summer 2014

Page 70: Rebecca Curtis, PE Michigan Department of Transportation ...

Thank you

Questions?