Real Time Fulfilment Planning at Flipkart Scale

Jagadeesh Huliyar [email protected]

The Fifth Elephant 201629th July 2016

Page 2: Real Time Fulfilment Planning

What is it?➔ Flipkart stores and sells

millions of unique items through its Fulfillment Centers (FCs) and Sellers.

➔ These items need to be picked from FCs or Seller Locations and delivered to End Customers.

➔ Real Time Fulfilment Planner is responsible for planning the schedule for these activities.

Page 3: Real Time Fulfilment Planning

What exactly happens

Page 4: Real Time Fulfilment Planning

DecisionsAre there any decisions to be made?

When should pick start in the FC? What is the order or batch for pick?

When should other activities be performed? Should items be held somewhere?

Which transport connection and mode should be taken?

Which route should be taken during transportation?

Do we really need to take these decisions? What happens if we process as and when order are placed or as and when shipments arrive at a particular location?

Page 5: Real Time Fulfilment Planning

Transportation Schedule

Page 6: Real Time Fulfilment Planning

Downstream Capacity

Page 7: Real Time Fulfilment Planning

Storage Usage

➔ Hour 1 ◆ Operation-1 processes 75 small units. ◆ Operation-2 will be able to process 50 small units and remaining 25 will remain in storage.

➔ Hour 2 ◆ Operation-1 processes 50 large units. ◆ Operation-2 can processes these 50 large units plus 25 small present in storage.

➔ This average processing over two hours is 62 units and at the end of two hours storage is empty.

Page 8: Real Time Fulfilment Planning

Transportation Batching and Routing

Page 9: Real Time Fulfilment Planning

Priority, Breach Cost and Capacity Consumption

Case 1 Case 2

Supply 2 units 2 units

Demand 2 COD and 2 Prepaid. 2 COD and 2 Prepaid.

Service Type All Regular COD are NDD. Pre-paid are Regular

Consumption COD = 2 units. Prepaid = 1 unit

COD = 2 units. Prepaid = 1 unit

Breach Cost Regular = 20 rupeesNDD = 70 rupees

Regular = 20 rupeesNDD = 70 rupees

Decision 2 Prepaid 1 COD

Page 10: Real Time Fulfilment Planning

Priority, Breach Cost and Capacity Consumption

➔ Consumption Factory vary as per Stage of processing◆ Sortation Station

● Size◆ FC

● Proximity to packing stations● Packaging Type

◆ Delivery Centre● Payment Type● Address Type

➔ Breach cost or Profit on timely delivery ◆ Service Type ◆ Customer Type

Page 11: Real Time Fulfilment Planning

Gigantic Graph

➔ Items : Different dimensions, Volume and Weight → Different restrictions and shipping costs.

➔ Constraints◆ Transport Connection Time◆ Priority of Shipments◆ SLA

Need to do all this at Lowest Possible Cost

Page 12: Real Time Fulfilment Planning

Variability➔ Demand Variability

◆ Destination Mix Variability◆ Product Mix Variability◆ Seller Mix Variability ◆ Service Mix Variability

➔ Supply Variability◆ Dependency on temporary work

force◆ Unreliable Transport Capacity◆ Network and infrastructure issues◆ Changing rules and regulations

Page 13: Real Time Fulfilment Planning

ModellingPlanned Storage

Unplanned Storage

Operations

Capacity

Lead Time

Page 14: Real Time Fulfilment Planning

Graph - Capacity and Lead Time

Page 15: Real Time Fulfilment Planning

Capacity Modelling with Storage

Page 16: Real Time Fulfilment Planning

Graph

Page 17: Real Time Fulfilment Planning

Plan Creation

➔ Computation Graph Creation➔ Start and Terminal Nodes Identification➔ Feasible Set ➔ Optimisation Function➔ Allocation➔ Learning➔ Usage of Learning➔ Repeat➔ Terminating Conditions➔ Match

Page 18: Real Time Fulfilment Planning

Scalability➔ Nodes - Millions➔ Edges - Tens of millions➔ Need to distribute the

computation

Page 19: Real Time Fulfilment Planning

Bulk synchronous parallel and Pregel➔ BSP system consists of

◆ Local Memory Transactions.◆ Message routing across Components.◆ Synchronisation

➔ Pregel - Inspired by BSP◆ Graph is divided into Partitions

◆ Algorithm is modelled as Computation

at Vertex and Message Passing across Vertices.

◆ Sequence of supersteps

Page 20: Real Time Fulfilment Planning

Example

Page 21: Real Time Fulfilment Planning

Giraph

Page 22: Real Time Fulfilment Planning

Giraph Job Lifetime

Page 23: Real Time Fulfilment Planning

Real Time Fulfillment Plan➔ Vertices - Time Slots in a Facility or Transport➔ Edges - Movement of Shipments from one Time Slot in a Facility/Transport to

another Time Slot in a Facility/Transport➔ Input - Requests Received and Forecast grouped by Dimensions➔ Messages - Allocation groups and Learnings (Bottlenecked Dimensions and

Variable Capacity Requirement)➔ Output - Set of Plans : Dimension Group : Time Slot : Number of Shipments

Page 24: Real Time Fulfilment Planning

Simulated Annealing - Global Optima and Local Optima➔ Starting with an initial solution. Learn better

allocation strategies. Move to a better neighbouring solution.

➔ It can lead to situations where you're stuck at a sub-optimal place.

➔ Simulated annealing injects right amount of randomness into things to escape local maxima.

Page 25: Real Time Fulfilment Planning

Local PlanningOnce Global Plan is ready there are some local decisions to be taken. These do not affect the Global Plan and are hence taken independently

➔ Pick Path Optimisation➔ Sorting Configuration➔ Last Mile Vehicle Routing Problem

Page 26: Real Time Fulfilment Planning

References➔ Distributed multi-agent optimization

◆ http://www.cds.caltech.edu/~murray/preprints/ttm11-ifac_s.pdf➔ Apache Giraph

◆ http://www.slideshare.net/ClaudioMartella/giraph-at-hadoop-summit-2014◆ http://giraph.apache.org/◆ http://www.apress.com/9781484212523

➔ BSP◆ https://en.wikipedia.org/wiki/Bulk_synchronous_parallel

➔ Reactive Search and Intelligent Optimization◆ REACTIVE SEARCH AND INTELLIGENT OPTIMIZATION Roberto Battiti, Mauro Brunato, and Franco Mascia

➔ Flow shop scheduling◆ http://faculty.ksu.edu.sa/ialharkan/IE428/Chapter_4.pdf◆ https://en.wikipedia.org/wiki/Flow_shop_scheduling

➔ Ant colony optimization◆ http://www.scholarpedia.org/article/Ant_colony_optimization◆ M. Dorigo, M. Birattari & T. Stützle, 2006 Ant Colony Optimization: Artificial Ants as a Computational Intelligence

Technique. TR/IRIDIA/2006-023➔ Simulated Annealing

◆ https://en.wikipedia.org/wiki/Simulated_annealing➔ Images have been picked by searching Google Images