Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22 nd March 2017, Dublin
52

Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Aug 26, 2018

Download

Documents

vannhu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Re-decking Hogarth Flyover

Jack Rose

Yunus Hussein

Engineers Ireland: Structures & Construction Seminar

22nd March 2017, Dublin

Page 2: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 2

Agenda

• LoHAC overview

• Background

• Risk management

• Design phase

• Construction phase

• Completion & re-opening

Page 3: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 3

• Four geographic Framework

Area

• NW, NE, S, C

• One contractor per

Framework Area appointed –

Design & Construction

Capability

• 8 years in length

• Based on NEC

• NW Value approx £50M p.a.

TfL London Highways Alliance Contract (LoHAC) Project Set-Up

Page 4: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 4

• Two ways to procure work:

Cyclic and reactive activities paid under an annual lump sum payment; core services.

Individual work ordered items under schedule of rates – Tasks.

• Payment options:

Lump sum

Re-measure

Target cost

• ‘Find and Fix’ by contractor or Employer inspection and contractor fix.

• Design by Client, build by contractor or design and build by the

contractor:

Feasibility design under a time charge

Detailed design by contractor using a % design fee based on construction costs

• Open book.

• Flexibility and room to grow.

TfL London Highways Alliance Contract (LoHAC) Project Set-Up

Page 5: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 5

Location

Page 6: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 6

Location

Page 7: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 7

• Single lane

• 20mph speed

restriction

• 2.0m width

restriction

Location

Page 8: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 8

• Built as temporary structure in 1971 o Designed by Sir Bruce White, Wolfe Barry and Partners

• 250m long, 17-span flyover, concrete-steel o Span lengths varying between 8m to 18m

• 40+ years service life o In excess of its original intended use

• Strategic importance o 10 500 vehicles carried per day

Background

Page 9: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 9

Background - context

Page 10: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 10

• Capacity assessment undertaken in 2013 Rapid

evaluation vs 3T weight limit

• Structure History o Maintenance regime unsuccessful in maintaining condition;

o Concrete repair scheme proposed at late stage; but

o Safety concerns prevented implementation of repair programme

Inadequate

Parapets

Structure Condition

Page 11: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 11

• Inspect & Assess

• Determine the current condition

• 3T Live Load

• A minimum requirement Hogarth Flyover

• Interim measures/risk management to BD 79

• In the event of a 3T live load being unavailable

• Develop Solution for strengthening/replacement

• In the event of a 3T live load being unavailable

Client Brief

Page 12: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 12

Risk Management

Page 13: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 13

• 2013 assessment

• 3T Live Load

• CA re-assessment

• DL only at delaminated areas

• SOLUTION REQUIRED

• Hidden strength in concrete slab

• Risk assessed

• Commenced monitoring to BD 79

• Red, Amber, Green (RAG) & Black

trigger levels

• Weekly night closure for top & underside

inspections

• Emergency Preparedness Plan in case of

Black status – communications protocol,

diversion routes

Condition Monitoring

Page 14: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 14

Delamination & spalling over 50% of panel

area AND spalling more than 10mm past 2nd

layer of bottom rebar.

Delamination present over more than 20% of

panel area.

Minor spalls; some exposed reinforcement.

No spalling or delamination present.

Condition of Element (examples) Actions

Close Flyover until emergency

strengthening installed.

Weekly monitoring; Prepare to

install emergency strengthening.

Monthly monitoring; Programme

emergency strengthening.

Quarterly monitoring

Condition Monitoring

Page 15: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 15

• Pre-October 2013

• Semi-critical areas

• Spalling >25mm

• Rebar de-bonding over lengths >1m

Condition Deterioration

Page 16: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 16

• October 2013

• Critical areas

• Spalling >40mm

• Bottom rebar fully exposed

• Rebar not bonded to concrete over lengths >1m

Delaminating

Concrete

Condition Deterioraton

Page 17: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

6th November 2015 Hogarth Flyover Deck Replacement Page 17

Critical spans pre-October 2013 Critical spans after full delamination

survey during closure, October 2013

Condition Deterioration

Page 18: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 18

• Propping of category ‘Black’ areas & continued monitoring

• Further development of TfL business case for capital funding

• ECI development of construction methodology to identify constraints and

timings

• Programme changes to 6 week closure during school holiday period in

summer 2014

Post October 2013 Delamination Survey

Page 19: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 19

• Stakeholders

o Hounslow Council

o Vegetation on Hogarth Roundabout Chiswick Society

o Noise Local residents

o Dust Residents and road users

o Lighting Road user safety concern

• Demolition

o Safe methods & areas of work

• Site Compound & working space

o Site contained within live roundabout & adjacent to live roads.

Logistics on cranage, materials storage & removal of demolition

materials

• Traffic management closures

o Highly visible & on news daily

Constraints

Page 20: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 20

Design Phase

Page 21: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 21

Superstructure &

substructure capacity

Lighting

requirements

Live

carriageways

Residential

areas Commercial

businesses

Trees

Solution Development

Page 22: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 22

Option Construction Cost

TM1a -

Night-time flyover closure, working along structure £ 4.7M

TM1b -

Night-time flyover closure, working from both ends of

structure

£ 5.1M

TM2a –

Full closure of flyover, precast deck panels with in-situ

deck at west end

£ 3.6M

TM2b –

Full closure of flyover, precast deck panels £ 3.7M

Deck Replacement Options

Page 23: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 23

New Deck Details

Page 24: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 24

Methodology - Demolition

Page 25: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 25

In situ stitch

Methodology – New Panel Installation

Page 26: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 26

Noise & Air Quality Monitoring

Page 27: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 27

• Carriageway qualities and junction density

• Crime data

• Ambient lighting

• Recommendations

Remove all luminaries and associated infrastructure over

Flyover

Install new lighting on off ramp for eye adaptation onto A4

carriageway

Lighting

Page 28: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 28

Construction

Phase

Page 29: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 29

• LoHAC procured on an NEC Term Services contract

• Hogarth Flyover procurement moved from Lump Sum (option A) to

Target Cost (option C)

o First time on LoHAC this has been implemented

o Shared risk via pain/gain mechanism

o Driven by TfL’s desire for cost certainty

o Delivered an approximate 15% reduction in the estimate to £3.1M outturn cost

• Supply chain

o Responsive & committed suppliers during preliminary and optioneering phase of the

project

Procurement Challenges

Page 30: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 30

Crane mat installation

Advanced Works

Page 31: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 31

Precast factory visit

Advanced Works

Page 32: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 32

Demolition

Page 33: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 33

Steelwork Assessment, Repairs & Painting

Page 34: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 34

Deck Installation

Page 35: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 35

Deck Installation

Page 36: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 36

In Situ Deck

Page 37: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 37

Waterproofing Installation

Page 38: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 38

Parapet Installation

Page 39: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 39

Surfacing, Kerbs & Drainage

Page 40: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 40

Final Inspection

Page 41: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 41

Completion &

Re-opening

Page 42: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 42

0

+12 days

+22 days

+31 days

+42 days

~40 years old

Completion & Re-Opening

Page 43: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 43

Collaborative working between TfL, CA & Stakeholders central to

successful and timely delivery of project – re-opened 10 hours early

Re-Opening

Page 44: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 44

Project Profile

Page 45: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 45

Drive Through

Page 46: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Final Thoughts

Page 46

CIRIA C764

Hidden Defects

in Bridges

Page 47: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 47

Thank you

Jack Rose

Yunus Hussein

Page 48: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 48

Hogarth Roundabout Restoration

Page 49: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 49

Precast deck

Main longitudinal

beam

In situ deck

Rubber

bearing strip

Beam buffers

Pier

Angle

Background – Typical Deck Detail

Page 50: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 50

Superstructure analysis

Longitudinally fixed at Span 8

Idealisation over pier

Pier

Superstructure Analysis

Page 51: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 51

– Crash decks

Hung crash deck for spans over

carriageway

Self supported crash deck elsewhere for

full access

Methodology – Crash Decks

Page 52: Re-decking Hogarth Flyover - Engineers Ireland · Re-decking Hogarth Flyover Jack Rose Yunus Hussein Engineers Ireland: Structures & Construction Seminar 22nd March 2017, Dublin

Page 52

It does happen…