http://itconfidence2013.wordpress.com Software Rates vs Price of Function Points 2° ° °International Conference on IT Data collection, Analysis and Benchmarking Tokyo (Japan) - October 22, 2014 Rafael de la Fuente Founder and CEO of LEDAmc Raúl Fernández SW Productivity Consultant Insert here a picture An Updated Cost Analysis
32
Embed
R.D.Fernandez et al - Software rates vs price of function points
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
http://itconfidence2013.wordpress.com
Software Rates vs Price of Function Points
2°°°°International Conference on IT Data collection, Analysis and Benchmarking
Tokyo (Japan) - October 22, 2014
Rafael de la Fuente
Founder and CEO of LEDAmc
Raúl Fernández
SW Productivity Consultant
Insert here a picture
An Updated Cost Analysis
2IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com
Software Rates vs Price of Function Points: A cost analysis
Goals of the presentation
Nowadays, in Software Development Contracts the key elements determining the price are: the Rate and the Effort.
The possibility to measure the quantity of software produced (the size in
Function Points) allows us to assess whether there is a logical connection between the price of the projects and the software actually produced.
The main goal of this presentation is to show what happens with the FP price in several scenarios:
�G1. Implementing estimation models.
�G2. Implementing productivity models.
�G3. Introducing new competitors in a productivity model.
�G4. De-localizing providers.
3IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com
• Background
• Objective
• 2014 vs 2012 benchmarking
• Case studies
• Conclusions
Agenda
4IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com
BackgroundOver the last seven years, LEDAmc has managed the productivity of more than 12,000
development projects of 10 significant clients in Spain (mostly telecommunication and
financial companies). They were mainly small enhancement projects.
The main goal of the measures is to control large contracts of Adaptive Maintenances,
which involves the highest percentage of our clients’ development budget.
In 2012 LEDAmc developed a benchmarking study with some of these projects (we
selected 3,405). The purpose of the study was to analyze the relationship between the
rates of the different software providers and the price of the Function Point that they
were offering their clients. This study was presented:
•In the UKSMA conference in October 2012
•An updated study, in the IT Confidence Conference in Rio, in October 2013.
5IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com
BackgroundThe basic numbers of the 2012 sample were:
•10 Clients
•14 Providers
•3,405 Projects
•196,356 UFP
•2,168,192 Hours
•69,926,907 Million Euros
And the main conclusions were:
�Pressure to lower rates ends up in lower productivity and higher FP price.
�There is not a logical relationship between Rates and FP Price.
�The performance of the providers changes dramatically among clients.
�Clients with only one development provider have the highest FP Price.
6IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com