http://itconfidence2013.wordpress.com Software Rates vs Price of Function Points 2° ° °International Conference on IT Data collection, Analysis and Benchmarking Tokyo (Japan) - October 22, 2014 Rafael de la Fuente Founder and CEO of LEDAmc Raúl Fernández SW Productivity Consultant Insert here a picture An Updated Cost Analysis
32
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: R.D.Fernandez et al  - Software rates vs price of function points

http://itconfidence2013.wordpress.com

Software Rates vs Price of Function Points

2°°°°International Conference on IT Data collection, Analysis and Benchmarking

Tokyo (Japan) - October 22, 2014

Rafael de la Fuente

Founder and CEO of LEDAmc

Raúl Fernández

SW Productivity Consultant

Insert here a picture

An Updated Cost Analysis

Page 2: R.D.Fernandez et al  - Software rates vs price of function points

2IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Software Rates vs Price of Function Points: A cost analysis

Goals of the presentation

Nowadays, in Software Development Contracts the key elements determining the price are: the Rate and the Effort.

The possibility to measure the quantity of software produced (the size in

Function Points) allows us to assess whether there is a logical connection between the price of the projects and the software actually produced.

The main goal of this presentation is to show what happens with the FP price in several scenarios:

�G1. Implementing estimation models.

�G2. Implementing productivity models.

�G3. Introducing new competitors in a productivity model.

�G4. De-localizing providers.

Page 3: R.D.Fernandez et al  - Software rates vs price of function points

3IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

• Background

• Objective

• 2014 vs 2012 benchmarking

• Case studies

• Conclusions

Agenda

Page 4: R.D.Fernandez et al  - Software rates vs price of function points

4IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

BackgroundOver the last seven years, LEDAmc has managed the productivity of more than 12,000

development projects of 10 significant clients in Spain (mostly telecommunication and

financial companies). They were mainly small enhancement projects.

The main goal of the measures is to control large contracts of Adaptive Maintenances,

which involves the highest percentage of our clients’ development budget.

In 2012 LEDAmc developed a benchmarking study with some of these projects (we

selected 3,405). The purpose of the study was to analyze the relationship between the

rates of the different software providers and the price of the Function Point that they

were offering their clients. This study was presented:

•In the UKSMA conference in October 2012

•An updated study, in the IT Confidence Conference in Rio, in October 2013.

Page 5: R.D.Fernandez et al  - Software rates vs price of function points

5IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

BackgroundThe basic numbers of the 2012 sample were:

•10 Clients

•14 Providers

•3,405 Projects

•196,356 UFP

•2,168,192 Hours

•69,926,907 Million Euros

And the main conclusions were:

�Pressure to lower rates ends up in lower productivity and higher FP price.

�There is not a logical relationship between Rates and FP Price.

�The performance of the providers changes dramatically among clients.

�Clients with only one development provider have the highest FP Price.

Page 6: R.D.Fernandez et al  - Software rates vs price of function points

6IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Background

CLIENT-PROVIDER

0

1 0

2 0

3 0

4 0

5 0

6 0

7 0

8 0

9 0

1 0 0

1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 2 5 2 6 2 7 2 8 2 9 3 0 3 1

Pressure to lower rates ends up in lower productivity and higher FP price.

Page 7: R.D.Fernandez et al  - Software rates vs price of function points

7IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Background

0

1 0

2 0

3 0

4 0

5 0

6 0

7 0

8 0

9 0

1 0 0

1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 2 5 2 6 2 7 2 8 2 9 3 0 3 1

The same provider for different clients, offers significant differences in FP price.

CLIENT-PROVIDER

Page 8: R.D.Fernandez et al  - Software rates vs price of function points

8IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Background

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

The price of the FP with only one provider is higher.

CLIENT-PROVIDER

MULTI-PROVIDER CLIENTS

ONE-PROVIDER CLIENTS

Page 9: R.D.Fernandez et al  - Software rates vs price of function points

9IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

ObjectiveLEDAmc has been continuously working for most of those clients, implementing Software

Development Productivity Models over the last two years.

Our productivity benchmarking data base has grown: It has more data for the same

clients and new clients have been included.

The main goal of this presentation is to show what has happened in these two years with

clients who have worked hard to improve their software development productivity.

�We will first explain the general evolution of the Function Point Price for those clients,

comparing 2012 and 2014 benchmarks.

�Afterwards, we will focus on three case studies that are especially significant.

�Finally, we will draw conclusions on the economics of software management, based on

our results.

Page 10: R.D.Fernandez et al  - Software rates vs price of function points

10IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

2014 vs 2012 benchmarkingThe 2014 sample were:

•Clients that were in the 2012 study and have implemented some estimation or

productivity control

•4 Clients

•12 Providers

•883 Projects

•44,897 UFP

•415,768 Man Hours

•15,428,772 Million Euros

What has happened with the FP price?

Page 11: R.D.Fernandez et al  - Software rates vs price of function points

11IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2014 vs 2012 benchmarking

CLIENT-PROVIDER

The rates have remained almost the same.

Page 12: R.D.Fernandez et al  - Software rates vs price of function points

12IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2014 vs 2012 benchmarking

The FP price is more homogeneous in 2014 than 2012.

CLIENT-PROVIDER

Page 13: R.D.Fernandez et al  - Software rates vs price of function points

13IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

2014 vs 2012 benchmarking

Apparently there is no relation between FP price and rate…

CLIENT-PROVIDER

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Rates vs FP Price in 2014

Page 14: R.D.Fernandez et al  - Software rates vs price of function points

14IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2014 vs 2012 benchmarking

.. but if we group the data by client, the results look different.

CLIENT A CLIENT B CLIENT C CLIENT D

Rates vs FP Price in 2014

Page 15: R.D.Fernandez et al  - Software rates vs price of function points

15IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2014 vs 2012 benchmarking

There are big differences in the FP price for the same provider with different clients.

CLIENT A CLIENT B CLIENT C CLIENT D

Rates vs FP Price in 2014

P1 P1P2 P2P3 P3 P3

Page 16: R.D.Fernandez et al  - Software rates vs price of function points

16IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

2014 vs 2012 benchmarking

Conclusions

The results are homogeneous on a client basis because they have implemented

estimation or productivity control models that allow them control the FP price.

Because there is no transparency in software development and the public FP price does

not exist in the market, the FP price stills remains very different among the clients.

The natural differences of the systems architectures and processes should not imply

such FP price differences.

… now we will present some case studies highlighting the change that has been

produced for these clients who have introduced control systems.

Page 17: R.D.Fernandez et al  - Software rates vs price of function points

17IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

� High FP price

� Only one provider

� No estimation control

Case Study 1 Competition among providers + Estimation Model

INITIAL SITUATION OF THE CLIENT (2012)

Page 18: R.D.Fernandez et al  - Software rates vs price of function points

18IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

� During 2013, the implementation of a centralized mechanism of estimation control has

allowed to objectively contrast the costs offered by providers with corporate cost

strategies.

� It includes functional sizing, as well as other sizing methods (for parametrization,

technical changes, test support,..)

� Benchmarking studies helped establish a cost strategy and a target price for FP .

� Introducing a new development provider fosters competitiveness among providers and

helps establish a FP price within market values.

Case Study 1 Competition among providers + Estimation Model

INPUTS (2013)

Page 19: R.D.Fernandez et al  - Software rates vs price of function points

19IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

TOTAL 1 2PROV 1 PROV 2

INPUTS (2013)

Case studies

1. The rate was only

reduced by 5%

2. New development

provider worked with

a similar rate

21

Case Study 1 Competition among providers + Estimation Model

Page 20: R.D.Fernandez et al  - Software rates vs price of function points

20IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

TOTAL 1 2PROV 1 PROV 2

INPUTS (2013)

Case studies

TOTAL 1 2

� The FP price was

reduced by 44 %

� Similar FP Price

among providers

1. The rate was only

reduced by 5%

2. New development

provider worked with

a similar rate

Case Study 1 Competition among providers + Estimation Model

21

PROV 1 PROV 2

Page 21: R.D.Fernandez et al  - Software rates vs price of function points

21IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

� A good estimating process was used for all projects

� 44% reduction in FP price

� More than 10 Million euros saved

� FP Price within market values

� Two competing providers in 2013 – Four in 2014

FINAL SITUATION (2014)

Case Study 1 Competition among providers + Estimation Model

Page 22: R.D.Fernandez et al  - Software rates vs price of function points

22IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Case studies

� Specialized providers

� On-site development

� High rates and very low FP price

� Estimation and productivity control implemented

INITIAL SITUATION OF THE CLIENT (2012)

Case Study 2 De-localization of providers

Page 23: R.D.Fernandez et al  - Software rates vs price of function points

23IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

� The client strategy was to proceed to the de-localization of the providers to a

typical outsourced model introducing new development providers with lower rates.

� The client also decided to create an in-house development team in order to

preserve and extend the know-how.

Case Study 2 De-localization of providers

INPUTS (2013)

Page 24: R.D.Fernandez et al  - Software rates vs price of function points

24IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

TOTAL 1 2 3 4

1. New provider with

lower rate

2. In-house development

rate

1 2

INPUTS (2013)

Case Study 2 De-localization of providers

PROV 1 PROV 2 PROV 3 PROV 4

Page 25: R.D.Fernandez et al  - Software rates vs price of function points

25IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

TOTAL 1 2 3 4

Case studies

TOTAL 1 2 3 4

1. New provider with

lower rate

2. In-house development

rate

1 2

� Logical behavior of FP

price

� In-house

developments at lower

FP cost than in

outsourced scenario

INPUTS (2013)

Case Study 2 De-localization of providers

PROV 1 PROV 2 PROV 3 PROV 4

PROV 1 PROV 2 PROV 3 PROV 4

Page 26: R.D.Fernandez et al  - Software rates vs price of function points

26IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Case studies

Case Study 2 De-localization of providers

� FP price controlled

� Outsourcing process controlled

2014 situation

FINAL SITUATION (2014)

Page 27: R.D.Fernandez et al  - Software rates vs price of function points

27IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Case studies

� Ratio of the rates: 1.1

� Ratio of the FP Price: 2.3

INITIAL SITUATION OF THE CLIENT (2012)

Case Study 3 Controlling large maintenance contracts

Page 28: R.D.Fernandez et al  - Software rates vs price of function points

28IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Case studies

� During 2012 the client implemented a productivity control for maintenance

development.

� An annual productivity SLA for all the providers was established.

� The client also implemented a productivity and quality providers ranking.

� Every two months the client presented to the providers their position in the ranking.

Case Study 3 Controlling large maintenance contracts

INPUTS (2013)

Page 29: R.D.Fernandez et al  - Software rates vs price of function points

29IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

TOTAL 1 2 3 4 5 6

Case studies

� Renegotiation of rates

Ratio 2012: 1.1

Ratio 2014: 1.0

INPUTS (2013)

Case Study 3 Controlling large maintenance contracts

Page 30: R.D.Fernandez et al  - Software rates vs price of function points

30IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

TOTAL 1 2 3 4 5 6

TOTAL 1 2 3 4 5 6

Case studies

� Renegotiation of rates

Ratio 2012: 1.1

Ratio 2014: 1.0

� FP cost control

Ratio 2012: 2.3

Ratio 2014: 1.7

INPUTS (2013)

Case Study 3 Controlling large maintenance contracts

Page 31: R.D.Fernandez et al  - Software rates vs price of function points

31IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Case studies

Case Study 3 Controlling large maintenance contracts

� Uniformity of FP price

� 9.5 million euros saved

2014 situation

FINAL SITUATION (2014)

Page 32: R.D.Fernandez et al  - Software rates vs price of function points

32IT Confidence 2014 – October 22, 2014 http://itconfidence2014.wordpress.com

Conclusions

1. It is relatively easy to influence FP price. The main levers are:

>>> A centralized estimation control

>>> A development productivity control

>>> Several providers in competition

2. Working on those key elements the results are much better than working only

on the rates:

>>> The behavior of the unit cost of production (FP price) is more homogeneous.

>>> The cost of the development process can be controlled.

3. Diversification of providers with joint management results in a better uniformity

of the FP price.