RBS6000 Integration and Commissioning MOP 1 (92) Prepared (also subject responsible if other) No. ENO/O/I Ashwin Ramachandran Approved Checked Date Rev Reference ENO/O/IC Grace Tan Hong Lee 25-08-2010 A RBS6000 Integration and Commissioning MOP Contents 1 Overview............................................2 2 Preparation.........................................2 2.1 Laptop with the below software installed.....2 2.2 Cable and accessories........................2 2.3 Node B Scripts and License...................3 2.4 Test Phone...................................3 3 Node B Commissioning Process Summary................4 4 Node B Commissioning................................4 4.1 Format DUW...................................4 4.2 Transfer the Basic software package to NodeB. ............................................ 10 4.3 Restart Node B with basic software..........13 4.4 Run Cabinet Equipment Wizard................18 4.5 Run OAM Wizard..............................24 4.6 Run Site Equipment Configuration............32 4.7 Run Iub Transport script....................39 4.8 Activating Integration Unlock...............41 4.9 Run HS/EUL script...........................42 4.10 Changing the RUW power to 60 Watts..........45 4.11 Installation of the License Key File........45 4.12 Creation of Configuration Version...........48 4.13 Integration Template........................51 5 Unlocking the Utran Cells and Test Calls...........51 6 Operation and Maintenance scenarios................51 6.1 Changing DUW................................51 6.1.1 Remove the faulty DUW.......................52 6.1.2 Install the new DUW and power up............52 6.1.3 Load the basic software into the new DUW....52 6.1.4 Restore the CV..............................62 6.1.5 Install the License / Do integration unlock. 70
92

RBS6000 Integration and Commissioning MOP

Nov 27, 2015

Download

Documents

rbs integration
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 1 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

RBS6000 Integration and Commissioning MOP

Contents

1 Overview.................................................................................................2

2 Preparation.............................................................................................22.1 Laptop with the below software installed...................................22.2 Cable and accessories..............................................................22.3 Node B Scripts and License......................................................32.4 Test Phone................................................................................3

3 Node B Commissioning Process Summary........................................4

4 Node B Commissioning........................................................................44.1 Format DUW..............................................................................44.2 Transfer the Basic software package to NodeB......................104.3 Restart Node B with basic software.........................................134.4 Run Cabinet Equipment Wizard..............................................184.5 Run OAM Wizard.....................................................................244.6 Run Site Equipment Configuration..........................................324.7 Run Iub Transport script..........................................................394.8 Activating Integration Unlock...................................................414.9 Run HS/EUL script...................................................................424.10 Changing the RUW power to 60 Watts....................................454.11 Installation of the License Key File..........................................454.12 Creation of Configuration Version...........................................484.13 Integration Template................................................................51

5 Unlocking the Utran Cells and Test Calls.........................................51

6 Operation and Maintenance scenarios..............................................516.1 Changing DUW........................................................................516.1.1 Remove the faulty DUW..........................................................526.1.2 Install the new DUW and power up.........................................526.1.3 Load the basic software into the new DUW.............................526.1.4 Restore the CV........................................................................626.1.5 Install the License / Do integration unlock...............................706.2 Changing RUW........................................................................72

7 Conclusion...........................................................................................72

Page 2: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 2 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

1 Overview

This document describes in detail the integration and commissioning procedure for RBS6000. The procedure is applicable for RBS6102, RBS6102 and RBS6101.

2 Preparation

This section mentions the software and test tools required to do the RBS integration.

2.1 Laptop with the below software installed

1. Tera Term Version 4.61

2. Filezilla 3.2.2.1(FTP Client) or any other FTP client

3. FileZilla Server Version 0.9.31(FTP Server)

4. RBS Element Manager P7

5. Java1.6.0_14jre-6u14-windows-i586-s

6. RBS 6000 Basic Software P7.1.6

2.2 Cable and accessories

1. Serial to RJ45 cable

2. USB to Serial Adaptor

3. LAN cable

Page 3: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 3 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

2.3 Node B Scripts and License

Total of 7 integration scripts are used during the RBS integration.

1_Cabinet.xml

2_OAM.xml

3_Site_Equipment.xml

4_Iub_Scripts.mo

5_HS_EUL_Parameters.mo

The license file/integration unlock is mandatory. Without the license/ file or integration unlock the

5_ HS_EUL_Parameters.mo cannot be run successfully.

2.4 Test Phone

Any phone which is capable of the displaying the cell information(eg: TEMS, Phones with Netmon)

Page 4: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 4 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

3 Node B Commissioning Process Summary

1. Format DUW

2. Install Basic package P7.1.6

3. Restart the Node B in the basic software

4. Run Cabinet Equipment Wizard

5. Run OAM Wizard

6. Run Site Equipment wizard

7. Run Iub_Scripts.mo Script

8. Activate integration unlock

9. Run HS_EUL_Parameters.mo Script

10. Changing the RUW power to 60 Watts

11. Installing the license key file

12. Creating a Configuration Version.

4 Node B Commissioning

This section explains in detail the steps mentioned in the previous section.

4.1 Format DUW

Connect the serial cable to the LMT A port of DUW and run Tera Term software.

Make sure that you see the command prompt $

Page 5: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 5 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 6: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 6 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Put the Node B in BackUp mode, by issuing the following command.

reload—

We can check the directories within the NodeB by issuing

vols

Page 7: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 7 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Since the /c2 is not automatically mounted, we will have to manually mount the drive by issuing the following command.

mount_c2

Page 8: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 8 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Now we will proceed with the formatting of the hard drives /c2 and /d. The commands to dothe format is given below.

formathd /c2 formathd /d

Page 9: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 9 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the format is done, reload the RBS. After this is done, we again move to the back up mode to start the configuration. This is done by issuing a reload – command

The next step is to proceed with setting the IP address in the nodeB. The command issued is

ifconfig le0 169.254.1.1 netmask 255.255.0.0

Page 10: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 10 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Set the IP address in your laptop to 169.254.1.2.

Make sure that you set the Default gateway IP address in the laptop without which the integration scripts will fail.

4.2 Transfer the Basic software package to NodeB.

Open an FTP client such as Filezilla and connect to the RBS IP address 169.254.1.1 through LMT B port of DUW

Page 11: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 11 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Make sure you select the root directory ‘/’ at the RBS side.

Transfer /c2 and /d directories to the RBS as shown below.

Page 12: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 12 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 13: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 13 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the transfer is completed make sure the size of /c2 is 129M and /d is 39M. This can be done by issuing the vols command

4.3 Restart Node B with basic software

Now we have to restart the RBS with the basic software. The command to be issued is reload. Wait till the RBS restart is completed

Page 14: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 14 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 15: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 15 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

We login to the RBS using the element manager software. The local maintenance IP address of the RBS 6201 is always 169.254.1.1.

Page 16: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 16 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Checking the Finger print

This section shows a series of screenshots on how to check the finger print of the RBS. The finger print is used to generate the license key file for the RBS.

Page 17: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 17 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 18: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 18 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.4 Run Cabinet Equipment Wizard

The RBS is configured with the cabinet type when we run the Cabinet equipment wizard. Also some basic sector and IP definitions are done in the Cabinet equipment configuration. The script to be run is 1_Cabinet.xml.

From the tools menu, select Cabinet Equipment configuration. We can choose the wizard or the scripts option. Since cabinet equipment configuration is quite simple, we will be running the wizard manually. Please follow the screenshots below.

Page 19: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 19 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Click Next

Page 20: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 20 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Since we are running the wizard manually click Next. The RBS will proceed with a restart and it is a normal behaviour. Wait for the restart to complete.

Page 21: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 21 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the restart is completed, you will see a screen as mentioned below. Click Next

In the next screen you will select the RBS cabinet type, key in the cabinet information and select the Radio Building blocks for the sectors. We will be using the radio building block RBB12_1A. In this example we will be configuring two sectors. Click next once done.

Page 22: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 22 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

In the next page you will see the power supply and the battery configuration. Key in the number of PSU’s and the battery backup in Ampere Hour if applicable. Click next once done.

Page 23: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 23 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next page shows the Local maintenance IP address and the subnet mask. The default IP address for the RBS is 169.254.1.1 and netmask is 255.255.0.0. Click next once done.

Please confirm the parameters and select the option to restart the RBS after cabinet equipment configuration.

Page 24: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 24 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Observe in the Teraterm that the RBS is starting up in the Initial CV

Page 25: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 25 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.5 Run OAM Wizard

Now that the Cabinet equipment configuration is completed, we will run the 2_OAM_Script.xml through the OAM Access Configuration Wizard. This will configure OAM IP address, the OAM VLAN, the OAM Gateway , OAM Subnet mask, the Iub IP address(User Plane/ Control Plane IP), the Iub VLAN, the Iub Gateway and the Iub subnet mask. In addition to this we will also define the server IP addresses specific to Singtel.

To run the OAM wizard, from the tools menu select OAM access configuration.

Page 26: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 26 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

You will see the screen below.

Since we will be using the 2_OAM_Script.xml select Use Configuration file and browse the file from the folder where the OAM file is stored.

Page 27: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 27 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the current configuration is loaded, click next.

Page 28: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 28 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The following screens show the parameters that have been defined through our scripts.

This screen shows the Local Maintenance IP address and the subnet mask.

The next screen shows the OAM IP, OAM VLAN, OAM Gateway and OAM subnet mask configuration. Also we select the Transmission type (TNB). TNB is used for Optical Gigabit Ethernet through SFP and is required for IPRAN sites.

Page 29: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 29 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

This screen shows the Iub IP address, Iub VLan, Iub Gateway,Iub Subnet mask and the IP Sync Ref IP addresses.

The next screen shows the next HOP IP address which s required for OAM access. The next hop IP address will be the OAM Gateway IP address.

Page 30: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 30 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the Server configuration inside the Singtel network and they are standard values. Click next once done.

Page 31: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 31 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the NTP servers for the time setting in the RBS.

The next screen shows the Network Synchronization available. We have configured two IP Sync Ref’s in the RBS. Therefore we will see 2 entries here.

Confirm the parameters that have been entered in the OAM script. Click Finish

Page 32: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 32 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 33: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 33 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.6 Run Site Equipment Configuration

The next step is to run the Site Equipment configuration. We will be running 3_Site_Equipment_script.xml.

The site equipment configuration defines the site name, number of carriers/sector, defines the external equipment such as ASC, and the feeder cable settings.

To invoke the Site equipment configuration, go to Tools Site Equipment configuration.

Page 34: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 34 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Select the Site equipment file 3_Site_Equipment.xml and

Click next

This screen shows the Site name and the logical name.

Page 35: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 35 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the SAU and the PSU configuration. SAU is currently used only for the 6102 sites.

Page 36: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 36 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the Sector Data info including the latitude and longitude.

The next screen shows the Carrier configuration on per sector basis.

Page 37: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 37 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the ASC configuration.

Page 38: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 38 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen defined the band at which the RU’s will operate.

Page 39: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 39 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The next screen shows the Antenna feeder configuration.

The following screen shows the parameter numhscoderesources and numeulresources. Set the parameters according to the requirement.

Page 40: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 40 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Confirm the parameters in the next screen by clicking Finish.

Once the Site Equipment configuration is done, you will see the following screen.

Page 41: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 41 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.7 Run Iub Transport script

Now we will proceed to run the 6_Iub_script.mo. This will define the Iub link towards the RNC

From the tools menu select Run Command file

From the screen below select the Iub script by clicking Browse.

Page 42: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 42 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Make sure you select “Halt on Errors” and Verbose logging” before clicking the Start button.

Page 43: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 43 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once completed you will see the following messages.

4.8 Activating Integration Unlock

We assume that during RBS integration, we do not have the License Key file. In the event of not having the LKF, we can activate a feature called “Integration Unlock”. This feature is conceptually similar to the “Emergency Unlock” feature. All the RBS software and hardware licenses will be available for a maximum period of 7 days. The advantage of the feature is that we need to touch the Emergency Unlock feature this reserving it for emergency purposed and at the same time have the same functionality.

The command to activate integration unlock (to be done at Teraterm) is

$ license iu activate

The command to check the status of Integration unlock (to be done at Teraterm) is

$ license iu status

Please see the screenshots below for details.

Page 44: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 44 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.9 Run HS/EUL script

This script is required for the HS/EUL features to work properly. It is an .mo script and to run it go to Tools Run Command file

Page 45: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 45 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Browse for the HS/EUL script.

Page 46: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 46 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Click on “Halt on Errors” and “Verbose Logging” and click Start. You should

Page 47: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 47 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.10 Changing the RUW power to 60 Watts

Most of Singtel RBS sites require that the each carrier supports 30 Watts. Since we have configured 2 carriers per RUW, we will have to set the total power of RUW to 60 Watts. Thus each carrier will have a power of 30 Watts.

We will have to set the power for all the RUW’s in the RBS.

From the MOM view in the Element Managed, browse to the following path

ManagedElement -> Equipment->RbsSubrack->RbsSlot-> AuxPlugInUnit>RruDeviceGroup->TpaDeviceSet->TpaDevice

In the MO properties window set

maxTotalOutputPower = 60

Click on Apply to confirm the settings.

4.11 Installation of the License Key File

After obtaining the License Key File, we will be proceed with LKF installation.

Open the FTP server software in your laptop(such as Filezilla Server)

Click on the Users icon

Page 48: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 48 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Select the folder where the license key file is installed.

Once the selection of the folder is done, click OK

Page 49: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 49 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

In the Element Manager go to Licensing View. Go to MO properties and select “Update LicenseKey File”.

Page 50: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 50 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Now in the following page, key in the following details of the FTP Server(our Laptop). Username, Password, IP address and the License File Name. It is shown in the screen shot below.

Once all the details are keyed in clock on “Execute”.

4.12 Creation of Configuration Version.

Before proceeding with the creation of CV make sure that there are no alarms in the RBS.

Page 51: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 51 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

To create the CV, go to Software view in the Element Manager.

Go to the CV tab.

Page 52: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 52 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Click on Create CV. You will see the following window.

Once the CV name and the operator comments are keyed in click Create.

Make sure that the created CV is visible in the CV list. If it is not click refresh. Set the CV to startable and restart the RBS with the CV.

Page 53: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 53 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

4.13 Integration Template

The integration scripts for RBS6000 (template) are mentioned below.

1_Cabinet.xml 2_OAM.xml 3_Site.xml 4_Iub_Transport.mo

5_HS_EUL_Scripts.mo

5 Unlocking the Utran Cells and Test Calls

Now that we have completed the RBS integration, call the RNC engineer to unlock the utrancells from the RNC side so that we can proceed with test calls.

Make sure the calls are tested in all the carriers of the RBS.

The performance monitoring is to be done for at least 15 minutes from the RNC side.

If there are no further alarms, the RBS engineer can leave the site.

6 Operation and Maintenance scenarios

6.1 Changing DUW

This section describes the procedure to replace the DUW board in case of a board fault.

The process summary to replace the DUW is as follows.

1) Remove the faulty DUW

2) Install the new DUW and power up

3) Load the basic software into the new DUW

4) Restore the CV

Page 54: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 54 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

5) Load the license/do Integration Unlock

6.1.1 Remove the faulty DUW

Carefully remove all the cables including the power cable from the DUW

6.1.2 Install the new DUW and power up

Slot in the new DUW and connect all the cables including the power cables.

6.1.3 Load the basic software into the new DUW

Now we need to transfer the basic software into the new DUW. This step is same as the step mentioned during the initial phases of RBS integration.

We need to transfer /c2 and /d into the new DUW. Let us look into this process step by step.

Connect the serial cable to the LMT A port of the DUW. Now open Teraterm in the laptop and connect to the RBS.

After logging in to the RBS using the serial port, go to the back up mode by typing

reload –

Page 55: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 55 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

We can check the directories within the NodeB by issuing

vols

Since the /c2 is not automatically mounted, we will have to manually mount the drive by issuing the following command.

mount_c2

Page 56: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 56 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Now we will proceed with the formatting of the hard drives /c2 and /d. The commands to format are given below.

formathd /c2 formathd /d

Page 57: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 57 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the format is done, reload the RBS. After this is done, we again move to the back up mode to start the configuration. This is done by issuing a reload – command

The next step is to proceed with setting the IP address in the nodeB. The command issued is

ifconfig le0 169.254.1.1 netmask 255.255.0.0

Page 58: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 58 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Set the IP address in your laptop to 169.254.1.2.

Make sure that you set the Default gateway IP address in the laptop without which the integration scripts will fail.

Now we need to transfer the basic software /c2 and /d to the DUW.

Open an FTP client such as Filezilla and connect to the RBS IP address 169.254.1.1

Page 59: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 59 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Make sure you select the root directory ‘/’ at the RBS side.

Transfer /c2 and /d directories to the RBS as shown below.

Page 60: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 60 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 61: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 61 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the transfer is completed make sure the size of /c2 is 129M and /d is /39M. This can be done by issuing the vols command

Now we have to restart the RBS with the basic software. The command to be issued is reload. Wait till the RBS restart is completed

Page 62: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 62 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 63: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 63 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

We login to the RBS using the element manager software. The local maintenance IP address of the RBS 6201 is always 169.254.1.1.

Page 64: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 64 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

6.1.4 Restore the CV

Now that we have transferred the basic software, we should restore the previously working CV in the RBS. The CV back up is stored as a zip file in the FTP server.

Unzip the CV backup.

Page 65: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 65 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

We will see that the CV directory has two sub directories inside called “cv” and “misc”

Page 66: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 66 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Rename the “cv” directory with the actual CV name

Now go to the misc directory. We are interested in 3 files. They are autoconfig.xml, uplist.xml and ipaddress2.xml

We will have to edit the file autoconfig.xml. We open the file in a text editor and see that the parameter “Setting Mode” is set as “As Configured”

Page 67: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 67 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Change the value of “Setting Mode” to “On”

Now we are ready to transfer to transfer the following to the DUW.

a. The CV directory(earlier named as cv) to /d/configuration/cv in DUW

Page 68: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 68 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

b. The 3 files in misc directory(autoconfig.xml, uplist.xml and ipaddress2.xml) to be transferred to /c/systemfiles/cello/cma/backuprestore/restorefiles/

Note: restorefiles is not created automatically and hence we need to create it in the RBS.

Page 69: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 69 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Once the transfer is completed, do a reload on Teraterm.

Page 70: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 70 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

Page 71: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 71 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

After the restart is completed, do a cv ls on the Teraterm to check whether our CV has been transferred. Also note that a system created CV starting EF_CXP is created. It is a CV created by the system at emergency restore.

Now we have to restart the RBS with the desired CV. This can be done by typing the command.

cv set <CV NAME>

Page 72: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 72 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

6.1.5 Install the License / Do integration unlock

Note that if there are more than 1 RUW in the RBS, the finger print will still remain the same. In this case we can install the license as mentioned in the RBS integration section.

In case there is only 1 RUW in the RBS, the finger print of the RBS will change. In that case we will have to activate the integration unlock so that the site can be put back to service as soon as possible. We should install the actual license before the actual expiry of the Integration Unlock(valid for 7 days).

The command to activate integration unlock is

$ license iu activate

Page 73: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 73 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

The command to check the Integration unlock status is

$ license iu status

Make sure that after restoring the CV, there are no new alarms in the RBS

Page 74: RBS6000 Integration and Commissioning MOP

RBS6000 Integration and Commissioning MOP 74 (74)

Prepared (also subject responsible if other) No.

ENO/O/I Ashwin RamachandranApproved Checked Date Rev Reference

ENO/O/IC Grace Tan Hong Lee 25-08-2010 A

6.2 Changing RUW

Replacing a faulty RUW is straightforward. We should lock the faulty RUW and take out the

old RUW. Now we should install the new RUW and power it up. After the power up is completed, we should do the unlock of the new RUW.

Make sure that no new alarms are observed after replacing the RUW.

7 Conclusion

Depending on site situation, actual practice may differ from the recommended process in this document. Any variation as such, will be informed in later revision