RBS 6102 Done by: Ali Noureddine [email protected] +96176618788 Comissioning 4+4+4 900/1800 Using OMT R48S
16

RBS Installation

Jul 13, 2016

Download

Documents

Brian Mapira

RBS Installation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: RBS Installation

RBS 6102

Done by: Ali Noureddine

[email protected]

+96176618788

Comissioning 4+4+4 900/1800

Using OMT R48S

Page 2: RBS Installation

Digital Unit for GSM (DUG)

Prepared for the future

• Supports multistandard

• Main Unit

Capacity

• Up to 12 TRX

• Half the size of predecessor

• Multiple digital units (TG-sync)

Page 3: RBS Installation

Opening OMT

Page 4: RBS Installation

Press on Configuration and create IDB

Page 5: RBS Installation

Dialogue box will for create IDB.

Page 6: RBS Installation

Chose the type of RBS 6102RUG.

Page 7: RBS Installation

Antenna sector setup press new

Page 8: RBS Installation

Chose the frequency and type of

combining

Page 9: RBS Installation

Press OK

Page 10: RBS Installation

Press another new for the 1800 band

Page 11: RBS Installation

Click OK

Page 12: RBS Installation

Two sectors will be generated

Page 13: RBS Installation

Repeat it three times

Page 14: RBS Installation

Then press OK.

Page 15: RBS Installation

Finalizing the RBS

• Last steps is to put the RBS in maintenance mode.

• Connect the laptop to RBS.

• Connect OMT to RBS.

• Install the IDB

• Remove the maintenance mode.

• Call NMC for confirmation.

Page 16: RBS Installation

• Done by: Ali Noureddine

[email protected]