Top Banner
Item Code Description CARRIAGE Chapter # : 01 Rate (British System) Rate (Metric System) Unit Unit Composite Composite COMPOSITE SCHEDULE OF RATES 2008 NWFP Labour Labour Remarks Spec. No 01-01-a 50 Meter 50 m 58.84 0.00 0.00 58.84 a) Cement carried in containers other than bags will be paid according to this item Carriage of 100 cft / 5 tonne of all materials by truck or other means : 1st 50 meter 01-01-b 50 Meter 50 m 9.29 0.00 0.00 9.29 b) Word, pipes and specials, covers GI , CI , AC, RCC,PCC, PVC and steel pipes and specials. Carriage of 100 cft / 5 tonne of all materials by truck or other means : 2nd 50 meter 01-01-c 50 Meter 50 m 6.20 0.00 0.00 6.20 c) Reduce the rate in case of carriage of 1000 NO. Tiles by:- Carriage of 100 cft / 5 tonne of all materials by truck or other means : 3rd to 5th 50 meter 01-01-d 250 Meter 250 m 28.91 0.00 0.00 28.91 33% for 12"x6"x1" size Carriage of 100 cft / 5 tonne of all materials by truck or other means : 250 to 1000 meter 01-01-e 1 KM km 103.24 0.00 0.00 103.24 25% for 12"x6"x1.5" size Carriage of 100 cft / 5 tonne of all materials by truck or other means : 1st kilometer 01-01-f 1 KM km 24.02 0.00 0.00 24.02 20% for 12"x6"x1.25" size Carriage of 100 cft / 5 tonne of all materials by truck or other means : 2nd - 5th kilometer 01-01-g 1 KM km 20.23 0.00 0.00 20.23 Carriage of 100 cft / 5 tonne of all materials by truck or other means : 6th to 10th kilometer 01-01-h 1 KM km 16.63 0.00 0.00 16.63 Carriage of 100 cft / 5 tonne of all materials by truck or other means : 11th & subsequent kilometer 01-02-a 50 Meter 50 m 37.07 0.00 0.00 37.07 Reduce the rate by 33% for our tile size 9"x4.5"x1.5" Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 1st 50 meter 01-02-b 50 Meter 50 m 5.85 0.00 0.00 5.85 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 2nd 50 meter 01-02-c 50 Meter 50 m 3.90 0.00 0.00 3.90 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 3rd to 5th 50 meter 01-02-d 50 Meter 250 m 18.21 0.00 0.00 18.21 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 250 - 1000 meter 01-02-e 1 KM km 65.04 0.00 0.00 65.04 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 1st kilometer 01-02-f 1 KM km 15.13 0.00 0.00 15.13 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 2nd - 5th kilometer 01-02-g 1 KM km 12.75 0.00 0.00 12.75 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 6th - 10th kilometer 01-02-h 1 KM km 10.47 0.00 0.00 10.47 Carriage of 1000 Nos. bricks or load upto 3 tonne by truck etc : 11th & subsequent kilometer 01-03-a Tonne/50 Meter tonne/50m 11.77 0.00 0.00 11.77 Carriage of cement(bag), bitumen/lubricants (drum) by truck or other means : 1st 50 meter 01-03-b Tonne/50 Meter tonne/50m 1.86 0.00 0.00 1.86 Carriage of cement (bag) bitumen/lubricant (drum) by truck or other means : 2nd 50 meter Page 1 of 144 NWFP CSR 2008 - Approved 25-Aug-2008
144
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Rate nwfp 2008

Item Code Description

CARRIAGEChapter #

:

01

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

01-01-a 50 Meter 50 m 58.84 0.00 0.00 58.84a) Cement carried in

containers other than

bags will be paid

according to this item

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 1st 50 meter

01-01-b 50 Meter 50 m 9.29 0.00 0.00 9.29b) Word, pipes and

specials, covers GI ,

CI , AC, RCC,PCC,

PVC and steel pipes

and specials.

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 2nd 50 meter

01-01-c 50 Meter 50 m 6.20 0.00 0.00 6.20c) Reduce the rate in

case of carriage of

1000 NO. Tiles by:-

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 3rd to 5th 50 meter

01-01-d 250 Meter 250 m 28.91 0.00 0.00 28.9133% for 12"x6"x1"

size

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 250 to 1000 meter

01-01-e 1 KM km 103.24 0.00 0.00 103.2425% for 12"x6"x1.5"

size

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 1st kilometer

01-01-f 1 KM km 24.02 0.00 0.00 24.0220% for

12"x6"x1.25" size

Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 2nd - 5th kilometer

01-01-g 1 KM km 20.23 0.00 0.00 20.23Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 6th to 10th kilometer

01-01-h 1 KM km 16.63 0.00 0.00 16.63Carriage of 100 cft / 5 tonne of all materials by truck or

other means : 11th & subsequent kilometer

01-02-a 50 Meter 50 m 37.07 0.00 0.00 37.07Reduce the rate by

33% for our tile size

9"x4.5"x1.5"

Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 1st 50 meter

01-02-b 50 Meter 50 m 5.85 0.00 0.00 5.85Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 2nd 50 meter

01-02-c 50 Meter 50 m 3.90 0.00 0.00 3.90Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 3rd to 5th 50 meter

01-02-d 50 Meter 250 m 18.21 0.00 0.00 18.21Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 250 - 1000 meter

01-02-e 1 KM km 65.04 0.00 0.00 65.04Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 1st kilometer

01-02-f 1 KM km 15.13 0.00 0.00 15.13Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 2nd - 5th kilometer

01-02-g 1 KM km 12.75 0.00 0.00 12.75Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 6th - 10th kilometer

01-02-h 1 KM km 10.47 0.00 0.00 10.47Carriage of 1000 Nos. bricks or load upto 3 tonne by truck

etc : 11th & subsequent kilometer

01-03-a Tonne/50

Meter

tonne/50m 11.77 0.00 0.00 11.77Carriage of cement(bag), bitumen/lubricants (drum) by

truck or other means : 1st 50 meter

01-03-b Tonne/50

Meter

tonne/50m 1.86 0.00 0.00 1.86Carriage of cement (bag) bitumen/lubricant (drum) by truck

or other means : 2nd 50 meter

Page 1 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 2: Rate nwfp 2008

Item Code Description

CARRIAGEChapter #

:

01

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

01-03-c Tonne/50

Meter

tonne/50m 1.24 0.00 0.00 1.24Carriage of cement (bag), bitumen/lubricant (drum) by

truck or other means : 3rd to 5th 50 meter

01-03-d Tonne/25

0 Meter

t/250m 5.78 0.00 0.00 5.78Carriage of cement(bag), bitumen/lubricant (drum) by truck

or other means : 250 to 1000 meter

01-03-e Tonne/1

Km

tonne/km 20.65 0.00 0.00 20.65Carriage of cement(bags), bitumen/lubricant (drum) by

truck or other means : 1st kilometer

01-03-f Tonne/1

Km

tonne/km 4.80 0.00 0.00 4.80Carriage of cement(bag), bitumen/lubricant (drum) by truck

or other means : 2nd - 5th kilometer

01-03-g Tonne/1

Km

tonne/km 4.05 0.00 0.00 4.05Carriage of cement(bag), bitumen/lubricant (drum) by truck

or other means : 6th - 10th kilometer

01-03-h Tonne/1

Km

tonne/km 3.33 0.00 0.00 3.33Carriage of cement(bag), bitumen/lubricant (drum) by truck

or other means : 11th & subsequent km

01-04-a 50 Meter 50 m 35.31 0.00 0.00 35.31Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 1st 50 meter

01-04-b 50 Meter 50 m 5.58 0.00 0.00 5.58Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 2nd 50 meter

01-04-c 50 Meter 50 m 3.72 0.00 0.00 3.72Carriage of 100cft of sarkanda, pichi, frash etc by road or

boat : 3rd to 5th kilometer

01-04-d 250 Meter 250 m 17.34 0.00 0.00 17.34Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 250 to 1000 meter

01-04-e 1 KM km 61.94 0.00 0.00 61.94Carriage of 100cft of sarkanda, pichi, frash etc by road or

boat : 1st kilometer

01-04-f 1 KM km 14.41 0.00 0.00 14.41Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 2nd - 5th kilometer

01-04-g 1 KM km 12.14 0.00 0.00 12.14Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 6th - 10th kilometer

01-04-h 1 KM km 9.98 0.00 0.00 9.98Carriage of 100cft of sarkanda, pilchi, frash etc by road or

boat : 11th & subsequent kilometer

01-05-a 50 Meter 50 m 2.94 0.00 0.00 2.94For consignment

weighing over 250

kg, the rate shall be

increased on pro-rate

basis.

Carriage of small consignments upto 250kg 1st 50 meter

01-05-b 50 Meter 50 m 0.46 0.00 0.00 0.46Carriage of small consigmnments upto 250 kg 2nd 50

meter

01-05-c 50 Meter 50 m 0.31 0.00 0.00 0.31Carriage of small consignments upto 250 kg 3rd to 5th 50

meters

01-05-d 250 Meter 250 m 1.45 0.00 0.00 1.45Carriage of small consignments upto 250 kg 250 - 1000

meter

01-05-e 1 KM km 5.16 0.00 0.00 5.16Carriage of small consignments upto 250 kg 1st kilometer

01-05-f 1 KM km 1.20 0.00 0.00 1.20Carriage of small consignments upto 250 kg 2nd to 5th

kilometer

Page 2 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 3: Rate nwfp 2008

Item Code Description

CARRIAGEChapter #

:

01

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

01-05-g 1 KM km 1.01 0.00 0.00 1.01Carriage of small consignments upto 250 kg 6th to 10th

kilometer

01-05-h 1 KM km 0.83 0.00 0.00 0.83Carriage of small consignments upto 250 kg 11th &

subsequent kilometer

01-06-a 1 KM km 27.90 27.90 27.90 27.90Carriage of consignments (odd job) Coolie load

01-06-b 1 KM km 18.15 0.00 0.00 18.15Carriage of consignments (odd job) Donkey load

01-06-c 1 KM km 13.61 0.00 0.00 13.61Carriage of consignments (odd job) Cart Load

01-06-d 1 KM km 18.15 0.00 0.00 18.15Carriage of consignments (odd job) Camel load

01-07-a Day Day 5,526.67 0.00 0.00 5,526.67a) This item shall be

allowed with prior

concurrence of

Superintending

Engineer b) The rate

includes pay of driver

and cleaner only. The

cost of repairs shall

be borne by the owner

and the cost of POL,

loading/unloading

shall be paid by the

borrower .

Hire Charges of Truck

01-07-b Day Day 4,964.73 0.00 0.00 4,964.73Hire charges of Tractor with trolley

01-07-c Day Day 4,005.24 0.00 0.00 4,005.24Hire charges of Tractor without trolley

01-08-a Each Each 418.50 418.50 418.50 418.50Hand shunting loaded railway wagons Upto 500 meter

01-08-b Each Each 627.75 627.75 627.75 627.75Hand shunting loaded railway wagons Upto 1 kilometer

01-08-c Each Each 767.25 767.25 767.25 767.25Hand shunting loaded railway wagons Upto 2 kilometer

01-08-d Each Each 348.75 348.75 348.75 348.75Hand shunting loaded railway wagons 3rd & subsequent

kilometer

01-09-a Each Each 209.25 209.25 209.25 209.25Hand shunting empty railway wagons Upto 500 meter

01-09-b Each Each 313.88 313.88 313.88 313.88Hand shunting empty railway wagons Upto 1 kilometer

01-09-c Each Each 383.63 383.63 383.63 383.63Hand shunting empty railway wagons Upto 2 kilometer

01-09-d Each Each 174.38 174.38 174.38 174.38Hand shunting empty railway wagons 3rd & subsequent

kilometer

Page 3 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 4: Rate nwfp 2008

Item Code Description

LOADING, UNLOADING AND STACKINGChapter #

:

02

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

02-01 100 cft m3 279.00 98.53 279.00 98.53Load into or unload from railway wagons within 50m

shingle, sand, ballast, tiles, etc, laid & stacked

02-02-a 1000 No. 1000 No. 348.75 348.75 348.75 348.75Load into or unload from railway wagons within 50m laid

& stacked : Bricks 10" size

02-02-b 1000 No. 1000 No. 279.00 279.00 279.00 279.00Load into or unload from railway wagons within 50m laid

& stacked : Bricks 9" or smaller size

02-03 100 No. 100 No. 348.75 348.75 348.75 348.75Load into or unload from railway wagons, cement in bags

and stacking within 50m.

02-04 1000 No. 1000 No. 312.48 312.48 312.48 312.48Load into or unload from railway wagons, empty cement

bags and stacking

02-05 tonne tonne 69.75 69.75 69.75 69.75Load into or unload from railway wagons and stacking

white lime in bags

02-06 tonne tonne 167.40 167.40 167.40 167.40Load into or unload from railway wagons structural steel,

RS joists, rails, rail fastenings etc

02-07 Each Each 22.32 22.32 22.32 22.32Load into or unload from 45 gallon drums full, into or from

railway wagons,lead upto 50m

02-08 Each Each 19.53 19.53 19.53 19.53Except cement in Jute

or paper bags

Loading or unloading packages of all sorts upto 50 kg.

02-09-a 100 No. 100 No. 697.50 697.50 697.50 697.50Load or unload sleepers other than wooden, incl stacking,

lead upto 50 m : Broad gauge

02-09-b 100 No. 100 No. 348.75 348.75 348.75 348.75Load or unload sleepers other than wooden, including

stacking, lead upto 50 m : Metre gauge &

02-10 tonne tonne 92.07 92.07 92.07 92.07Load or unload timber logs or shuttering into or from

railway wagons, including stacking within 50m

02-11 tonne tonne 209.25 209.25 209.25 209.25Loading or unloading bhoosa in railway wagons lead upto

50 m.

02-12 tonne tonne 139.50 139.50 139.50 139.50Load or unload timber scrap or wooden plugs into or from

railway wagons & stacking within 50m

02-13 100 cft m3 103.23 36.46 103.23 36.46Load or unload pitching stone/spawl from railway wagons

of any guage including clearing 1.5m away

02-14 100 cft m3 133.92 47.29 133.92 47.29Loading or unloading building stone including clearing

away 1.5m from rails

02-15-a 1000 ltr 1000 ltr 83.70 83.70 83.70 83.70The rate include

checking and

weighing the tins

Unloading oil,bitumen or tar etc : Crude Oil (to be pumped

from tank wagon into tank)

02-15-b 1000 ltr 1000 ltr 83.70 83.70 83.70 83.70Unloading oil,bitumen or tar etc Crude oil (drained by

gravity)

02-15-c Ton Ton 15.90 15.90 15.90 15.90Unloading oil,bitumen or tar etc Crude oil materials from

railway wagons

02-15-d tonne tonne 139.50 139.50 139.50 139.50Unloading oil, bitumen or tar etc : Fuel Oil from tank into

empty drums including stacking within 50 m

02-15-e 100 No. 100 No. 175.77 175.77 175.77 175.77Unloading oil,bitumen or tar etc Petrol (2 gallon tin)

Page 4 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 5: Rate nwfp 2008

Item Code Description

LOADING, UNLOADING AND STACKINGChapter #

:

02

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

02-15-f 100 No. 100 No. 348.75 348.75 348.75 348.75Unloading oil, bitumen or tar etc Kerosine oil (4 gallon tin)

02-15-g 100 No. 100 No. 90.75 0.00 0.00 90.75Unloading oil,bitumen or tar etc Tar & Bitumen in drums

with carriage upto 1 km

02-16-a 100 cft m3 139.50 49.26 139.50 49.26Removing and stacking within 50m. lead Stone, spawl,

brick bats, shingle, sand, lime etc

02-16-b 1000 No. 1000 No. 404.55 404.55 404.55 404.55Removing and stacking within 50m. lead Bricks

02-16-c 100 No. 100 No. 223.20 223.20 223.20 223.20Removing and stacking within 50m. lead Broad gauge

wooden sleepers

02-16-d 100 No. 100 No. 127.50 127.50 127.50 127.50Removing and stacking within 50m. lead Metre gauge or

narrow guage wooden sleepers

02-16-e tonne tonne 64.17 64.17 64.17 64.17Removing and stacking within 50m. lead Rails, girders,

pipes, cement etc.

02-16-f 100 No. 100 No. 744.93 744.93 744.93 744.93Removing and stacking within 50m. lead Bridge and

crossing timbers, etc.

02-17 tonne tonne 178.56 178.56 178.56 178.56Load into wagons girders, rails, MS bars, pipes etc.

including 50m lead & stacking inside wagons

02-18 tonne tonne 69.75 69.75 69.75 69.75Unload from wagons girders, rails, MS bars, girder etc.

including 50m lead but excluding stacking

02-19 100 No. 100 No. 558.00 558.00 558.00 558.00Load into wagons wooden baord guage sleepers including

50m lead & stacking

02-20 100 No. 100 No. 279.00 279.00 279.00 279.00Unload wooden broad gauge sleepers from wagons

including 50m lead and stacking

02-21 100 No. 100 No. 306.90 306.90 306.90 306.90Loading metre gauge or narrow guage wooden sleepers

including 50m lead & stack inside wagons

02-22 100 No. 100 No. 147.87 147.87 147.87 147.87Unloading metre gauge or narrow guage wooden sleepers

including 50m lead but excluding stacking

02-23 100 No. 100 No. 279.00 279.00 279.00 279.00Loading bridge and crossing timber including 50m lead &

stacking

02-24 100 No. 100 No. 139.50 139.50 139.50 139.50Unloading bridge and crossing timbers including 50m lead

but excluding stacking

02-25 tonne tonne 139.50 139.50 139.50 139.50Load or unload bitumen, asphalt, tar in drums, into or from

railway wagons, lead upto 50m

Page 5 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 6: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-01-a 1000 Cft m3 1,046.25 36.95 1,046.25 36.95Earth excavation undressed upto single throw of kassi

phaorah or shovel etc : in ashes, sand, soft soil or silt

clearance

03-01-b 1000 Cft m3 1,255.50 44.34 1,255.50 44.34Earth excavation undressed upto single throw of kassi

phaorah or shove etc : in ordinary soil,

03-02 1000 Cft m3 1,534.50 54.19 1,534.50 54.19Earth excavation in ashes, sand & soft soil or silt clearance,

undressed lead upto 25m.

03-03-a 1000 Cft m3 1,953.00 68.97 1,953.00 68.97The rate is aplicable

where the earth of the

bed tobe removed is

of the type of

ordinary soil. When it

is silt or soft soil, it

will be paid per item

No 03-01-a, 03-01-b

or 03-02 above,

whichever is

applicable. The XEN

will specify drains of

each category

Bed clearance and dressing slopes of drains including

removing of weeds and roots etc. Excavated material

undressed within 25m

03-03-b 1000 Cft m3 2,159.46 76.26 2,159.46 76.26Bed clearance and dressing slopes of drains including

removing of weeds and roots etc. Excavated material

dressed within 25m lead

03-04-a 1000 Cft m3 1,953.00 68.97 1,953.00 68.97Borrowpit excavation undressed lead upto 50m in Ordinary

soil

03-04-b 1000 Cft m3 2,399.40 84.73 2,399.40 84.73Borrowpit excavation undressed lead upto 50m in Hard soil

03-04-c 1000 Cft m3 4,743.00 167.50 4,743.00 167.50Borrowpit excavation undressed lead upto 50m in

shingle/gravel formation

03-05-a 1000 Cft m3 7,039.72 19.46 551.18 248.61The rate includes hire

charges of machinery,

cost of fuel,

lubricants, pay of

driver and cleaner.

The rate also include

clearing and grubbing

where necessary.

Embankment formation in ordinary soil & compaction by

mechanical means at optimum moistures content to 95% to

100% max. modified. AASHTO dry density (borrow area)

03-05-b 1000 Cft m3 6,917.98 19.27 545.60 244.31Embankment formation in ordinary soil & compaction by

mechanical means at optimum moistures content to 90%

max. modified AASHTO dry density (borrow area)

03-05-c 1000 Cft m3 6,796.24 19.07 540.02 240.01Embankment formation in ordinary soil & compaction by

mechanical means at optimum moistures content to 85%

max. modified AASHTO dry density (borrow area)

03-06-a 1000 Cft m3 1,426.00 50.36 1,426.00 50.36Earth fill in lawns including dressing & compaction with

earth available from cutting/excavation

Page 6 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 7: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-06-b 1000 Cft m3 2,650.50 93.60 2,650.50 93.60Earth fill in lawns including dressing & compaction with

suitable earth borrowed.

03-07-a 1000 Cft m3 2,015.00 71.16 2,015.00 71.16Earth excavation in open cut upto 1.5m depth for drains etc

& disposal : in Ordinary Soil

03-07-b 1000 Cft m3 2,518.75 88.95 2,518.75 88.95Earth excavation in open cut upto 1.5m depth for drains etc

& disposal : in Hard Soil

03-07-c 1000 Cft m3 2,619.50 92.51 2,619.50 92.51Earth excavation in open cut upto 1.5m depth for drains etc

& disposal : in Very hard Soil

03-07-d 1000 Cft m3 2,921.75 103.18 2,921.75 103.18Earth excavation in open cut upto 1.5m depth for drains etc

& disposal : in Gravel & shingle

03-08-a 1000 Cft m3 2,790.00 98.53 2,790.00 98.53Earth excavation in open cut 1.5m - 3m depth for

S.W.Drains etc & disposal : in Ordinary Soil

03-08-b 1000 Cft m3 3,152.70 111.34 3,152.70 111.34Earth excavation in open cut 1.5m - 3m depth for

S.W.Drains etc & disposal : in Hard Soil

03-08-c 1000 Cft m3 3,627.00 128.09 3,627.00 128.09Earth excavation in open cut 1.5m - 3m depth for

S.W.Drains etc & disposal : in Very Hard Soil

03-08-d 1000 Cft m3 6,249.60 220.70 6,249.60 220.70Earth excavation in open cut 1.5m - 3m depth for drains etc

& disposal : in Gravel & shingle

03-09-a 1000 Cft m3 5,301.00 187.20 5,301.00 187.20Excavation in shingle or gravel formation & rock not

requiring blast, undressed, 50m lead : Dry

03-09-b 1000 Cft m3 6,138.00 216.76 6,138.00 216.76Excavation in shingle or gravel formation & rock not

requiring blast, undressed, 50m lead : Wet

03-09-c 1000 Cft m3 7,812.00 275.88 7,812.00 275.88Excavation in shingle or gravel formation & rock not req.

blast, undressed, 50m lead : in Flowing Water

03-10-a 1000 Cft m3 2,263.00 79.92 2,263.00 79.92Earth excavation in irrigation channels/drains & disposal

upto 25m. & dressing : in Ordinary Soil

03-10-b 1000 Cft m3 2,709.40 95.68 2,709.40 95.68Earth excavation in irrigation channels/drains & disposal

upto 25m. & dressing : in Hard Soil

03-10-c 1000 Cft m3 3,183.70 112.43 3,183.70 112.43Earth excavation in irrigation channels/drains & disposal

upto 25m. & dressing : in Very Hard Soil

03-10-d 1000 Cft m3 5,921.00 209.10 5,921.00 209.10Earth excavation in irrigation channels/drains & disposal

upto 25m. & dressing : in Shingle/Gravel

03-11-a 1000 Cft m3 7,564.00 267.12 7,564.00 267.12Tools and plants shall

be the liability of the

contractor.

Rock Excavation, dressing & disposal up to 50m Soft

Rock, slate, shale, schist or lateriate

03-11-b 1000 Cft m3 9,675.07 303.21 8,586.07 341.67Rock Excavation, dressing & disposal up to 50m Medium

hard rock, requiring occasional blasting

03-12-a 1000 Cft m3 6,498.50 191.03 5,409.50 229.49a) Tools and plants

required shall be the

liabilities of the

contractor.

Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade I

Page 7 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 8: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-12-b 1000 Cft m3 7,751.50 209.65 5,936.50 273.74b) Reduce the rate by

8 % if the excavated

section is not dressed

or levelled to design

section.

Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade II

03-12-c 1000 Cft m3 9,315.75 252.07 7,137.75 328.98Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade III

03-12-d 1000 Cft m3 10,500.25 281.08 7,959.25 370.81Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade IV

03-12-e 1000 Cft m3 11,692.50 310.36 8,788.50 412.92Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade V

03-12-f 1000 Cft m3 12,722.00 333.90 9,455.00 449.27Excavation in hard rock requiring blasting and disposal

upto 25m & dressing : Grade VI

03-13-a 1000 Cft m3 10,819.00 382.07 10,819.00 382.07a) Tools and plants

required shall be the

liabilities of the

contractor.

Excavation in hard rock requiring blasting but blasting

prohibited, dispose & dress within 25 m : Grade I

03-13-b 1000 Cft m3 11,873.00 419.29 11,873.00 419.29b) Reduce the rate by

8 % if the excavated

section is not dressed

or levelled to design

section.

Excavation in hard rock requiring blasting where blasting

prohibited, dispose & dress within 25 m : Grade II

03-13-c 1000 Cft m3 14,275.50 504.14 14,275.50 504.14Excavation in hard rock requiring blasting where blasting

prohibited, dispose & dress within 25 m: Grade III

03-13-d 1000 Cft m3 15,918.50 562.16 15,918.50 562.16Excavation in hard rock requiring blasting where blasting

prohibited, dispose & dress within 25 m: Grade IV

03-13-e 1000 Cft m3 17,577.00 620.73 17,577.00 620.73Excavation in hard rock requiring blasting where blasting

prohibited, dispose & dress within 25 m: Grade V

03-13-f 1000 Cft m3 18,910.00 667.80 18,910.00 667.80Excavation in hard rock requiring blasting where blasting

prohibited, dispose & dress within 25 m: Grade VI

03-14-a 1000 Cft m3 697.50 24.63 697.50 24.63Rehandling of earthwork Lead upto a single throw of kassi,

shovel, phaorah

03-14-b 1000 Cft m3 976.50 34.48 976.50 34.48Rehandling of earthwork upto a lead of 25 m.

03-15 1000 Cft m3 2,790.00 98.53 2,790.00 98.53Rehandling of gravel work or excavated rock, lead upto

25m.

03-16-a 1000 Cft m3 1,426.00 50.36 1,426.00 50.36Filling, watering and ramming earth under floor with

surplus earth from foundation, etc

03-16-b 1000 Cft m3 2,960.50 104.55 2,960.50 104.55Filling, watering and ramming earth under floor with earth

excavated from outside lead upto 50m

Page 8 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 9: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-17-a 1000 Cft m3 83.70 2.96 83.70 2.96This rate shall be

aplicable upto 250m

total distance,

including the lead

covered in the item of

earth work.

Extra for every 25 m extra lead or part thereof for

earthwork soft, ordinary, hard & very hard

03-17-b 1000 Cft m3 111.60 3.94 111.60 3.94Extra for every 25 m extra lead or part thereof for gravel,

shingle or rock.

03-18-a 1000 Cft m3 1,980.90 69.95 1,980.90 69.95This rate will be paid

in addition to the rate

of earth work, without

deducting the lead

covered in the item of

earth work

Transportation of earth all types beyond 250 m and upto

500 m.

03-18-b 1000 Cft m3 306.90 10.84 306.90 10.84Transportation of earth all types for every 100m extra lead

beyond 500m upto 1.5 km.

03-18-c 1000 Cft m3 279.00 9.85 279.00 9.85Transportation of earth all types for every 500m extra lead

beyond 1.5 km. upto 8 km.

03-18-d 1000 Cft m3 195.30 6.90 195.30 6.90Transportation of earth all types for every 1 km extra lead

or part thereof beyond 8 km.

03-19-a 1000 Cft m3 95.48 3.37 95.48 3.37Dressing & levelling earth to designed sections Ashes,

sand, silt or soft soil upto cut or fill 6 inches

03-19-b 1000 Cft m3 188.48 6.66 188.48 6.66Dressing & levelling earth to designed sections Ordinary or

hard soil upto cut or fill 6 inches

03-19-c 1000 Cft m3 449.50 15.87 449.50 15.87Dressing & levelling earth to designed section Gravel work

or soft rock not requiring blasting upto cut or fill 6 inches

03-20 1 Chain m 105.40 3.46 105.40 3.46This rate is in

addition to pavement

for dressed earth work

Dowel dressing

03-21 1000 Sft m2 387.50 4.17 387.50 4.17a) To be paid only

when exclusively

dressing is done and

no earh work is

carried out in

embankment or

cutting.

Dressing slopes of banks or ground surface

03-22 1000 Sft m2 418.50 4.50 418.50 4.50b) The surface area

dressed is to be taken

for measurement (ii)

The item is aplicable

where the dressing is

done by the

contractor other than

the one who executed

the work

Dressing of earthwork (done by machinery or otherwise &

left undressed) to designed section

Page 9 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 10: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-23-a 1000 Cft m3 2,542.00 89.77 2,542.00 89.77Excavation in foundation of building, bridges etc complete

: in sand, ashes or loose soil

03-23-b 1000 Cft m3 2,976.00 105.10 2,976.00 105.10Excavation in foundation of building, bridges etc complete

: in ordinary soil

03-23-c 1000 Cft m3 3,332.50 117.69 3,332.50 117.69Excavation in foundation of building, bridges etc complete

: in hard soil or soft murum

03-23-d 1000 Cft m3 3,782.00 133.56 3,782.00 133.56Excavation in foundation of building, bridges etc complete

: in shingle/gravel

03-24 1000 Cft m3 29,226.89 674.37 19,096.00 1,032.14Tools and plants

required shall be the

liability of the

contractors.

Cutting hard rock such as granite, ballast, hard lime etc

with chisels/hammers for small foundation

03-25 1000 Cft m3 619.85 15.05 426.25 21.89Composite rate

includes material, i.e

plank, etc

Extra for excavaton requiring shoring

03-26-a 1000 Cft m3 273.42 9.66 273.42 9.66The rate does not

include hire charges

of the Roller to be

supplied by the

Department or

through other

agencies.

Mixing & moistening of earthwork to OMC in layers for

compaction etc complete

03-26-b-01 1000 Cft m3 759.50 26.82 759.50 26.82Compaction by rolling with animal driven roller or hand

rammed : Soft or sandy soil

03-26-b-02 1000 Cft m3 914.50 32.30 914.50 32.30Compaction by rolling with animal driven roller or hand

rammed : Ordinary soil

03-26-b-03 1000 Cft m3 1,275.03 45.03 1,275.03 45.03Compaction by rolling with animal driven roller or hand

rammed : Hard soil

03-26-b-04 1000 Cft m3 2,251.53 79.51 2,251.53 79.51Compaction by rolling with animal driven roller or hand

rammed : Admixture of shingle

03-26-c 1000 Cft m3 418.50 14.78 418.50 14.78Ramming earthwork (all types of soil)

03-26-d 1000 Cft m3 558.00 19.71 558.00 19.71Ramming earthwork behind retaining wall

03-27-a 1000 Cft m3 5,129.59 5.44 154.07 181.15The rate alslo inlcude

hire charges of

machinery, cost of

fuel, lubricant, pay of

driver and cleaner etc

Compaction of earth with power road roller 95% to 100%

max. mod. AASHTO dry density

03-27-b 1000 Cft m3 5,129.59 5.44 154.07 181.15Compaction of earth with power road roller 90% max.

mod. AASHTO dry density

03-27-c 1000 Cft m3 5,129.59 5.44 154.07 181.15Compaction of earth with power road roller 85% max.

mod. AASHTO dry density

03-28 1000 Cft m3 976.50 34.48 976.50 34.48That will support a

man's weight.

Extra for wet earthwork

Page 10 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 11: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-29 1000 Cft m3 2,837.00 78.82 2,232.00 100.19That will not support

a man's weight

Extra for slush or daldal including dewatering

03-30 1000 Cft m3 1,743.75 61.58 1,743.75 61.58Extra for puddling.

03-31 1 Rft m 2.79 9.15 2.79 9.15Earthwork on small rain water drains, along canal banks,

roads, drains, etc complete

03-32 1000 Cft m3 2,511.00 88.68 2,511.00 88.68Filling and Compacting Soil, Earth and Boulders behind

retaining walls

03-33 2500 Rft km 434.00 568.54 434.00 568.54Dag belling for layout

of borrow pit, to be

done by contractor at

their own cost.

Dag belling 75 mm deep.

03-34 1000 Sft m2 1,116.00 12.01 1,116.00 12.01Turfing slopes of banks or lawns with grass sods including

ploughing, laying, setting & watering

03-35-a 1000 Cft m3 1,255.50 44.34 1,255.50 44.34Berm cutting : Lead upto single throw of phaorah or

shovel, without dressing

03-35-b 1000 Cft m3 1,953.00 68.97 1,953.00 68.97Berm cutting : Upto 25 m lead (including dressing)

03-36-a Mile km 3,968.00 2,465.72 3,968.00 2,465.72Berm trimming both sides of channels Upto 1 m depth

03-36-b Mile km 5,254.50 3,265.15 5,254.50 3,265.15Berm trimming both sides of channels Over 1m to 1.5m

depth

03-36-c Mile km 8,354.50 5,191.49 8,354.50 5,191.49Berm trimming both sides of channels Over 1.5m to 2.5m

depth

03-37-a Acre ha 1,798.00 4,442.86 1,798.00 4,442.86Area ploughed bo be

measured

Ploughing and levelling borrow pits Upto 1m depth

03-37-b Acre ha 2,659.80 6,572.37 2,659.80 6,572.37Ploughing and levelling borrow pits Exceeding 1m depth

03-38-a-01 Chain 50 m 434.00 711.76 434.00 711.76Making boundary or service roads complete in unploughed

land : From 3 m to 6 m wide

03-38-a-02 Chain 50 m 589.00 965.96 589.00 965.96Making boundary or service roads complete in unploughed

land : Over 6 m to 12 m wide

03-38-b-01 Chain 50 m 504.99 828.18 504.99 828.18Making boundary or service roads complete in ploughed

land : From 3 m to 6m wide

03-38-b-02 Chain 50 m 724.78 1,188.64 724.78 1,188.64Making boundary or service roads complete in ploughed

land : Over 6 m to 12 m wide

03-39-a 1000 Cft m3 2,092.50 73.90 2,092.50 73.90For ordinary soilEarthwork by boats, Digging and loading into boats, upto

25m lead

03-39-b 1000 Cft m3 1,674.00 59.12 1,674.00 59.12Earthwork by boats, including hire of boats Carriage by

boats upto 250m.

03-39-c 1000 Cft m3 111.60 3.94 111.60 3.94Earthwork by boats, including hiring of boats Extra for

every additional 50m beyond 250m

03-39-d 1000 Cft m3 976.50 34.48 976.50 34.48Earthwork by boats, Unloading earth from boats

03-40 1000 Cft m3 837.00 29.56 837.00 29.56Unloading earth from BG trucks and clearing 1.5m from

rail

Page 11 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 12: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-41 1000 Cft m3 1,953.00 68.97 1,953.00 68.97Earthwork by tramway, digging and loading in trucks, upto

25m lead

03-42 1000 Cft m3 1,255.50 44.34 1,255.50 44.34Unloading earth from BG trucks and spreading upto 5m

from rail

03-43 1000 Cft m3 11,780.00 416.01 11,780.00 416.01The rate include a)

Removal of top crust

of earth overburden.

b) Royalty to the

government or cost to

the private owner

Supplying clean and screened river or pit sand within 150m

including removal of loose earth or overburden.

03-44-a 1000 Cft m3 2,511.00 88.68 2,511.00 88.68a) The rate does not

include back filling

after laying of sewer,

which is payable

seperately b) If the

timbering and

shuttering is not

actually done at site,

the composite rate

may be reduced by 5

%

Excavation in open cut for sewers & manhole except

shingle, gravel & rock : Upto 2m

03-44-b 1000 Cft m3 3,348.00 118.23 3,348.00 118.23Excavation in open cut for sewers & manholes except

shingle, gravel & rock : 2m to 5m

03-44-c 1000 Cft m3 4,464.00 157.64 4,464.00 157.64Excavation in open cut for sewers & manholes except

shingle, gravel & rock : Below 5m depth

03-45-a 1000 Cft m3 6,963.61 135.20 3,828.50 245.92The rate does not

include back filling

after laying of sewer,

which is payable

seperately.

Trench Excavation in open cutting below water level for

sewers & manholes : Upto 1.25m depth

03-45-b 1000 Cft m3 9,164.42 165.86 4,696.50 323.64Trench Excavation in open cutting below water level for

sewers & manholes : 1.25m to 2.5m depth

03-45-c 1000 Cft m3 15,104.35 239.20 6,773.50 533.41Trench Excavation in open cutting below water level for

sewers & manholes : Exceeding 2.5m depth

03-46 1000 Cft m3 2,042.90 72.14 2,042.90 72.14The rate does not

include back filling

after laying of pipe

line, which is payable

separately.

Excavation of trench in all kinds of soils except cutting in

rock for pilelines upto 1.5m depth

03-48-a Each Each 697.50 697.50 697.50 697.50Uprooting stump and removing within 50 m upto 2 m girth

03-48-b Each Each 1,114.69 976.50 976.50 1,114.69Uprooting stump and removing within 50 m above 2 m

girth

03-48-c Each Each 1,164.71 697.50 697.50 1,164.71Uprooting stump and removing within 50 m upto 2 m girth

including sand filling and trinches

Page 12 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 13: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-48-d Each Each 1,819.85 976.50 976.50 1,819.85Uprooting stump and removing within 50 m above 2 m

girth including sand filling and trinches

03-49-a Decare Decare 1,501.02 1,501.02 1,501.02 1,501.02Jungle clearance and removing within 50m Light Jungle

03-49-b Decare Decare 3,002.04 3,002.04 3,002.04 3,002.04Jungle clearance and removing within 50m Thick Jungle

03-50 1000 Sft m2 362.70 3.90 362.70 3.90Uprooting sarkanda growth & disposal within 50m

03-51 ha ha 5,359.90 5,359.90 5,359.90 5,359.90Ploughing 3 times

03-52 1000 Sft m2 2,945.00 31.69 2,945.00 31.69Levelling, dressing and making lawns

03-53 1000 Sft m2 9,600.00 31.69 2,945.00 103.30Turfing of lawn with Dacca Grass

03-54 1000 Cft m3 1,422.90 50.25 1,422.90 50.25Clearance of shingle, gravel including sand, soft soil and

silt deposits in channel bed upto 25m

03-55-a 100 Ft m 13,950.00 457.68 13,950.00 457.68Clearance of choked up syphon including dewatering Upto

1.25m dia

03-55-b 100 Ft m 25,110.00 823.82 25,110.00 823.82Clearance of choked up syphon including dewatering

Exceeding 1.25m dia

03-56 1000 Sft m2 1,328.17 2.59 241.06 14.29Clearing & Grubbing

03-57-a No No 259.67 18.69 18.69 259.67Removal of Tree : Girth 150mm - 300mm including

removal of stump & backfilling with sand

03-57-b No No 519.35 37.39 37.39 519.35Removal of Tree : Girth 300mm - 600mm including

removal of stump & backfilling with sand

03-57-c No No 1,276.14 112.16 112.16 1,276.14Removal of Tree : Girth over 600mm including removal of

stump & backfilling with sand

03-58 1000 Sft m2 1,132.54 2.31 215.11 12.19Compaction of Natural Ground

03-59-a 1000 Cft m3 5,572.00 5.58 157.91 196.77Roadway Excavation in Surplus / Unsuitable Common

Material

03-59-b 1000 Cft m3 11,737.61 74.40 2,106.76 414.51Roadway Excavation in Surplus / Unsuitable Rock (Hard)

Material requiring blasting.

03-59-c 1000 Cft m3 9,765.11 43.20 1,223.26 344.85Roadway Excavation in Surplus / Unsuitable Rock

(Medium) Material requiring blasting

03-60-a 1000 Cft m3 4,880.60 92.06 2,606.98 172.36Structural Excavation in Common Material

03-60-b 1000 Cft m3 24,289.44 371.99 10,533.71 857.77Structural Excavation in Rock Material requiring blasting

03-60-c 1000 Cft m3 21,773.58 139.50 3,950.08 768.93Structural backfill using Common Material available at

site.

03-60-d 1000 Cft m3 30,608.66 34.88 987.66 1,080.94Structural Backfill using Granular Material brought from

outside

03-61-a 1000 Cft m3 6,298.37 5.58 157.91 222.42Formation of Embankment from Roadway Excavation in

Common Material including compaction by power roller.

03-61-b 1000 Cft m3 13,817.39 74.40 2,106.76 487.96Formation of Embankment from Roadway Excavation in

Rock Material requiring blasting and compaction of

embankment by power roller.

03-61-c 1000 Cft m3 12,200.79 5.59 158.19 430.87Formation of Embankment from Borrow Excavation in

Common Material including compaction by power roller.

Page 13 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 14: Rate nwfp 2008

Item Code Description

EARTHWORK (EXCAVATION AND EMBANKMENT)Chapter #

:

03

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

03-61-d 1000 Cft m3 6,419.45 9.85 279.00 226.70Formation of Embankment from Roadway Excavation in

granular Material including compaction by power roller.

03-62-a 1000 Sft m2 2,107.01 2.31 215.11 22.67Subgrade Preparation in Earth Cut

03-62-b 1000 Sft m2 5,156.16 6.95 645.61 55.48Subgrade Preparation in Rock Cut

03-62-c 1000 Sft m2 3,010.30 4.63 430.22 32.39Subgrade Preparation on Existing Road

03-63-a 1000 Cft m3 1,347.51 2.46 69.75 47.59Earthwork by mechanical means in drains and irrigation

channels in DRY soil dressed to designed section, grades

profile/with excavated material, disposed off within 50 feet

(15.2 m) lead and dressed as directed.

03-63-b 1000 Cft m3 1,443.34 2.46 69.75 50.97Earthwork by mechanical means in drains and irrigation

channels in DRY & WET soil dressed to designed section,

grades profile/with excavated material, disposed off within

50 feet (15.2 m) lead and dressed as directed.

03-63-c 1000 Cft m3 1,708.95 3.65 103.23 60.35Earthwork by mechanical means in drains and irrigation

channels in WET & SLUSH soil dressed to designed

section, grades profile/with excavated material, disposed

off within 50 feet (15.2 m) lead and dressed as directed.

03-63-d 1000 Cft m3 1,949.79 3.65 103.23 68.86Earthwork by mechanical means in drains and irrigation

channels in SLUSH soil dressed to designed section,

grades profile/with excavated material, disposed off within

50 feet (15.2 m) lead and dressed as directed.

03-63-e 1000 Cft m3 1,865.64 4.93 139.50 65.88Earthwork by mechanical means in drains and irrigation

channels in DRY & WET to that of SLUSH (1:2) soil

dressed to designed section, grades profile/with excavated

material, disposed off within 50 feet (15.2 m) lead and

dressed as directed.

03-63-f 1000 Cft m3 1,559.31 2.46 69.75 55.07Earthwork by mechanical means in drains and irrigation

channels in BORROW AREA soil dressed to designed

section, grades profile/with excavated material, disposed

off within 50 feet (15.2 m) lead and dressed as directed.

03-63-g 1000 Cft m3 2,608.01 9.85 279.00 92.10Earthwork by mechanical means in drains and irrigation

channels in UNDER WATER soil dressed to designed

section, grades profile/with excavated material, disposed

off within 50 feet (15.2 m) lead and dressed as directed.

Page 14 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 15: Rate nwfp 2008

Item Code Description

DISMANTLING (DEMOLITION)Chapter #

:

04

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

04-01 100 Cft m3 237.15 83.75 237.15 83.75Dismantling dry stone masonry

04-02 100 Cft m3 348.75 123.16 348.75 123.16Dismantling stone masonry in mud mortar

04-03 100 Cft m3 837.00 295.58 837.00 295.58Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively.

Dismantling stone masonry in lime or cement mortar

04-04-a 100 Cft m3 418.50 147.79 418.50 147.79Dismantling dry stone or spawl pitching

04-04-b 100 Cft m3 558.00 197.06 558.00 197.06Dismantling stone or spawl pitching (mud grouted)

04-05 100 Cft m3 697.50 246.32 697.50 246.32Dismantling stone or spawl pitching and apron in silted

condition

04-06 100 Cft m3 837.00 295.58 837.00 295.58Dismantling stone pitching, cement or lime grouted

04-07-a 100 Cft m3 558.00 197.06 558.00 197.06Dismantling stone in Wooden crates

04-07-b 100 Cft m3 697.50 246.32 697.50 246.32Dismantling stone in Wire crates

04-08 100 Cft m3 465.00 164.21 465.00 164.21Dismantling stone ware drain including base concrete

04-09 100 Cft m3 139.50 49.26 139.50 49.26Dismantling mud/pise walling

04-10 100 Cft m3 348.75 123.16 348.75 123.16Dismantling sun dried brick masonry

04-11 100 Cft m3 237.15 83.75 237.15 83.75Dismantling dry brick masonry

04-12 100 Cft m3 488.25 172.42 488.25 172.42Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-12,

04-13, 04-14 and

04-15

Dismantling brick work in mud mortar

04-13 100 Cft m3 1,185.75 418.74 1,185.75 418.74Dismantling brick work in lime or cement mortar

04-14 100 Cft m3 1,046.25 369.48 1,046.25 369.48Dismantling cement block masonry

04-15 100 Cft m3 279.00 98.53 279.00 98.53Dismantling Dhajji walling

04-16 100 Cft m3 558.00 197.06 558.00 197.06Dismantling mud concrete

04-17 100 Cft m3 767.25 270.95 767.25 270.95Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-17,

04-19, and 04-20

Dismantling lime concrete

04-18 100 Cft m3 2,929.50 1,034.54 2,929.50 1,034.54Dismantling lime or cement concrete, under water

04-19-a 100 Cft m3 1,534.50 541.90 1,534.50 541.90Dismantling : Plain Cement Concrete 1:4:8

04-19-b 100 Cft m3 2,511.00 886.75 2,511.00 886.75Dismantling : Plain Cement Concrete 1:3:6

Page 15 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 16: Rate nwfp 2008

Item Code Description

DISMANTLING (DEMOLITION)Chapter #

:

04

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

04-19-c 100 Cft m3 3,069.00 1,083.81 3,069.00 1,083.81Dismantling : Plain Cement Concrete 1:2:4

04-19-d 100 Cft m3 837.00 295.58 837.00 295.58Dismantling : Cement Concrete with brick aggregate

04-19-e 100 Sft m2 379.16 40.80 379.16 40.80Dismantling : DPC of cement concrete 1.5" thick and

clearing the site

04-20 100 Cft m3 5,022.00 1,773.50 5,022.00 1,773.50Dismantling RCC, separating reinforcement, cleaning &

straightening the same

04-21 100 Sft m2 167.40 18.01 167.40 18.01Dismantling sirki sarkanda or thached roofing supported on

battens or ballies

04-22-a 100 Sft m2 418.50 45.03 418.50 45.03Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-22-a,

04-22-b, 04-26, 04-27

and 04-30

Dismantling 1st class tile roofing

04-22-b 100 Sft m2 344.84 37.11 344.84 37.11Dismantling 2nd class tile roofing

04-23 100 Sft m2 263.50 28.35 263.50 28.35Dismantling from any height, asbestos sheets & ridge

coping

04-24 100 Sft m2 229.40 24.68 229.40 24.68Dismantling roof of wooden planks & battens from any

height

04-25 100 Sft m2 851.14 91.58 851.14 91.58Dismantling wooden ceiling above 20' height in difficult

position including lifting along live wire

04-26 100 Sft m2 558.00 60.04 558.00 60.04Dismantling jack arch roofing, including removing joists

04-27 100 Sft m2 697.50 75.05 697.50 75.05Dismantling RB roof complete with mud and mud plaster

including reinforcement complete

04-28-a 100 Sft m2 259.16 27.89 259.16 27.89Stripping and stacking: Slate or tiles from the truss roofing

04-28-b 100 Sft m2 338.52 36.42 338.52 36.42Stripping and stacking: GI sheet roofing

04-29 100 Sft m2 658.75 70.88 658.75 70.88Extra for dismantling CI sheet roof above 20 ft. in dificult

position including lifting along live wire

04-30 100 Sft m2 558.00 60.04 558.00 60.04Dismantling slates or tiles including battens, purlins and

planking

04-31 100 Sft m2 237.15 25.52 237.15 25.52Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-31 and

04-32

Dismantling brick or flagged flooring without concrete

foundation

04-32 100 Sft m2 348.75 37.53 348.75 37.53Dismantling plank or wooden block flooring etc

Page 16 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 17: Rate nwfp 2008

Item Code Description

DISMANTLING (DEMOLITION)Chapter #

:

04

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

04-33-a 100 Rft m 3,487.50 114.42 3,487.50 114.42a) The rate does not

include the cost of

excavation and

refilling of trench, or

the demoliation of

any masonry or brick

work.

Disjointing RCC pipes inside trench & removing pipes &

stacking outside : 6" to 12" diameter

04-33-b 100 Rft m 4,882.50 160.19 4,882.50 160.19b) Bends, elbows,

sluice valves, etc

should not be paid for

extra if fixed in the

length of pipe line

that is being

dismantled.

Disjointing RCC pipes inside trench & removing pipes &

stacking outside : 13" to 24" diameter

04-33-c 100 Rft m 6,277.50 205.95 6,277.50 205.95Disjointing RCC pipes inside trench & removing pipes &

stacking outside : 25" to 36" diameter

04-33-d 100 Rft m 8,370.00 274.61 8,370.00 274.61Disjointing RCC pipes inside trench & removing pipes &

stacking outside : Over 36" diameter

04-34 Each Each 159.65 159.65 159.65 159.65Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-34 to

04-37

Removing door with chowkat

04-35 Each Each 116.25 116.25 116.25 116.25Removing windows and sky lights with chowkat

04-36 Each Each 58.13 58.13 58.13 58.13Removing ventilators and wooden sunshades

04-37-a Each Each 69.75 69.75 69.75 69.75Dismantling: Woden beams up to 12' in length

04-37-b Each Each 139.50 139.50 139.50 139.50Dismantling: Wooden beams from 12.1' to 23' length

04-37-c 600 Sft m2 1,102.11 19.76 1,102.11 19.76Dismantling: Wooden partiton Jaffry Work etc

04-37-d 5 Cwt 100 kg 1,263.25 492.67 1,263.25 492.67Dismantling: Wooden trusses

04-37-e 50 Rft m 868.00 56.96 868.00 56.96Dismantling: Wooden palisade fencing

04-38 5 Cwt 100 kg 1,426.00 556.14 1,426.00 556.14Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-38 and

04-39

Dismantling iron work of trusses, sheds, water tanks, etc

excluding cutting of rivets

04-39 12 Cwt 100 kg 1,395.00 228.78 1,395.00 228.78Dismantling rolled steel beams or iron rails etc.

04-40 Each Each 527.00 527.00 527.00 527.00Dismantling iron latrine

04-41 Each/25m

m D

Ea/25mm D 7.75 7.75 7.75 7.75Dismantling tees, bends or sluice valves upto 12" i/d

Page 17 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 18: Rate nwfp 2008

Item Code Description

DISMANTLING (DEMOLITION)Chapter #

:

04

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

04-42-a Each Each 3,968.00 3,968.00 3,968.00 3,968.00Dismantling water column : BG

04-42-b Each Each 2,697.00 2,697.00 2,697.00 2,697.00Dismantling water column : MG or NG

04-43 230 Rft m 558.00 7.96 558.00 7.96Dismantling all type of wire fencing, including rolling wire

into bundles and collecting material

04-44 100 Sft m2 111.60 12.01 111.60 12.01Dismantling wire netting of tennis courts and frame work

04-45 100 Sft m2 209.25 22.52 209.25 22.52Dismantling cloth ceiling and supporting timber

04-46 100 Cft m3 558.00 197.06 558.00 197.06Dismantling and removing road metalling

04-47 100 Sft m2 3,660.48 393.87 3,660.48 393.87Dismantling & removing road pavement etc including

screening & stacking of by-products upto 50m.

04-48-a 500 Sft m2 279.00 6.00 279.00 6.00Add extra 13%, 32%

and 51% on labour

rates only for 2nd,

3rd, 4th and

subsequent floors

respectively against

item No 04-46 to

04-49

Removing from walls: Mud plaster

04-48-b 250 Sft m2 279.00 12.01 279.00 12.01Removing from walls: Cement or lime plaster

04-49-a 100 Sft m2 69.75 7.51 69.75 7.51Scraping : White wash or colour wash

04-49-b 100 Sft m2 209.25 22.52 209.25 22.52Scraping : Ordinary distemper, oil bound distemper or

paint off wall

04-50 100 Sft m2 868.00 93.40 868.00 93.40Dismantling glazed or accoustics tiles etc

04-51 100 Cft m3 948.32 334.90 948.32 334.90Scraping boulders.

04-52 100 Cft m3 976.50 344.85 976.50 344.85Cleaning mortar of old stones to be used in masonry

04-53 Point Point 30.69 30.69 30.69 30.69Dismantling light, fan and call bell point including casing,

capping/strip open type complete

04-54 Point Point 25.73 25.73 25.73 25.73Dismantling plug point & making good damaged surface

(building portion)

04-55-a 1 Rft m 5.97 19.60 5.97 19.60Dismantle GI/MS conduit/GI flexible/PVC pipes or

conduit wiring of all sizes : On surface

04-55-b 1 Rft m 9.64 31.63 9.64 31.63Dismantle GI/MS conduit/GI flexible/PVC pipes or

conduit wiring of all sizes : Recessed in wall

Page 18 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 19: Rate nwfp 2008

Item Code Description

MORTARChapter #

:

05

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

05-01 100 Cft m3 6,973.08 369.48 1,046.25 2,462.52Lime Sand Mortar 1 : 2 (one Lime: 2 Sand)

05-02 100 Cft m3 5,979.45 369.48 1,046.25 2,111.63Lime Sand Mortar 1 : 3 (one Lime: 3 Sand)

05-03 100 Cft m3 6,297.47 369.48 1,046.25 2,223.93Lime Surkhi Mortar 1 : 1-1/2 (one Lime: 1-1/2 Surkhi)

05-04 100 Cft m3 5,566.76 369.48 1,046.25 1,965.88Lime Surkhi Mortar 1 : 2 (one Lime: 2 Surkhi)

05-05 100 Cft m3 4,645.70 369.48 1,046.25 1,640.62Lime Surkhi Mortar 1 : 3 (one Lime: 3 Surkhi)

05-06 100 Cft m3 5,785.15 369.48 1,046.25 2,043.01Lime Sand And Surkhi Mortar 1 : 1 : 1 (one Lime: 1 Sand

And : 1 Surkhi)

05-07 100 Cft m3 4,981.94 369.48 1,046.25 1,759.36Lime Sand And Surkhi Mortar 1 : 2 : 1 (one Lime: 2 Sand

And : 1 Surkhi)

05-09 100 Cft m3 15,025.53 369.48 1,046.25 5,306.22Lime, Cement And Sand Mortar 1 : 1 : 3 (one Lime: One

Cement And : 3 Sand)

05-10 100 Cft m3 12,998.36 369.48 1,046.25 4,590.33Lime, Cement And Sand Mortar 1 : 1 : 4 (one Lime: One

Cement And : 4 Sand)

05-11 100 Cft m3 11,559.54 369.48 1,046.25 4,082.22Lime, Cement And Sand Mortar 1 : 1 : 5 (one Lime: One

Cement And : 5 Sand)

05-12 100 Cft m3 10,484.42 369.48 1,046.25 3,702.54Lime, Cement And Sand Mortar 1 : 1 : 6 (one Lime: One

Cement And : 6 Sand)

05-13 100 Cft m3 9,695.38 369.48 1,046.25 3,423.90Lime, Cement And Sand Mortar 1 : 1 : 7 (one Lime: One

Cement And : 7sand)

05-14 100 Cft m3 8,853.13 369.48 1,046.25 3,126.46Lime, Cement And Sand Mortar 1 : 1 : 8 (one Lime: One

Cement And : 8 Sand)

05-15 100 Cft m3 8,440.58 369.48 1,046.25 2,980.77Lime, Cement And Sand Mortar 1 : 1 : 9 (one Lime: One

Cement And : 9 Sand)

05-16 100 Cft m3 8,019.10 369.48 1,046.25 2,831.92Lime, Cement And Sand Mortar 1 : 1 : 10 (one Lime: One

Cement And : 10 Sand)

05-17 100 Cft m3 9,908.16 369.48 1,046.25 3,499.04Cement, Lime And Sand Mortar 1 : 2 : 6 (one Cement: 2

Lime And : 6 Sand)

05-18 100 Cft m3 8,803.66 369.48 1,046.25 3,108.99Cement, Lime And Sand Mortar 1 : 2 : 9 (one Cement: 2

Lime And : 9 Sand)

05-19 100 Cft m3 27,152.81 295.58 837.00 9,588.93Cement Sand Mortar 1 : 1 (one Cement: One Sand)

05-20 100 Cft m3 22,536.10 295.58 837.00 7,958.56Cement Sand Mortar 1 : 1-1/2 (one Cement: 1-1/2 Sand)

05-21 100 Cft m3 19,574.08 295.58 837.00 6,912.53Cement Sand Mortar 1 : 2 (one Cement: 2 Sand)

05-22 100 Cft m3 17,046.04 295.58 837.00 6,019.76Cement Sand Mortar 1 : 2-1/2 (one Cement: 2-1/2 Sand)

05-23 100 Cft m3 14,988.09 295.58 837.00 5,293.00Cement Sand Mortar 1 : 3 (one Cement: 3 Sand)

05-24 100 Cft m3 12,400.31 295.58 837.00 4,379.13Cement Sand Mortar 1 : 4 (one Cement: 4 Sand)

05-25 100 Cft m3 10,928.58 295.58 837.00 3,859.40Cement Sand Mortar 1 : 5 (one Cement: 5 Sand)

05-26 100 Cft m3 9,639.57 295.58 837.00 3,404.18Cement Sand Mortar 1 : 6 (one Cement: 6 Sand)

05-27 100 Cft m3 8,804.18 295.58 837.00 3,109.17Cement Sand Mortar 1 : 7 (one Cement: 7 Sand)

05-28 100 Cft m3 8,091.13 295.58 837.00 2,857.36Cement Sand Mortar 1 : 8 (one Cement: 8 Sand)

05-29 100 Cft m3 1,500.30 517.27 1,464.75 529.83Clay Mortar.

05-30 100 Cft m3 2,861.55 517.27 1,464.75 1,010.55Clay Mortar Mixed With Chipped Bhoosa Or Straw.

Page 19 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 20: Rate nwfp 2008

Item Code Description

MORTARChapter #

:

05

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

05-31 200 Cft m3 5,351.30 270.95 1,534.50 944.90Clay Mortar Mixed With Cow-dung 1 : 1 (1 Clay: 1 Cow

Dung).

05-32 100 Cft m3 18,155.99 295.58 837.00 6,411.73White Cement And Sand Mortar1 : 3 (1 White Cement 3

Sand)

05-33 100 Cft m3 73,087.27 295.58 837.00 25,810.55Coloured Cement Mortar Made By Mixing White Cement

And Pigment Of Approved Shade (1 White Cement Mixed

With Pigment Of Approved Shade: 2 Sand)

05-34 100 Cft m3 23,919.19 295.58 837.00 8,446.99White Cement And Sand Mortar1 : 2 (1 White Cement 2

Sand)

05-35 100 Cft m3 73,087.27 295.58 837.00 25,810.55Coloured Cement Mortar Made By Mixing Grey Cement

And Pigment Of Approved Shade (1 Grey Cement Mixed

With Pigment Of Approved Shade: 2 Sand)

Page 20 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 21: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-01 100 Cft m3 3,016.82 445.78 1,262.32 1,065.38The stone ballast,

crushed bajri, round

shingle from nallah,

or brick ballast may

be used according to

their comparative

cheaper rates in

various areas of the

province.

Mud concrete in foundation using brick ballast or stone

ballast 1.5" gauge to 2" guage

06-02 100 Cft m3 2,301.10 295.58 837.00 812.63dittoDry rammed shingle brick ballast or stone ballast 1.5" to 2"

guage

06-03-a 100 Cft m3 9,181.33 593.90 1,681.75 3,242.36Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:3:6)

06-03-b 100 Cft m3 7,518.79 593.90 1,681.75 2,655.24Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:4:8)

06-03-c 100 Cft m3 7,022.69 593.90 1,681.75 2,480.04Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:5:10)

06-03-d 100 Cft m3 6,513.28 593.90 1,681.75 2,300.15Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:6:12)

06-03-e 100 Cft m3 5,842.94 593.90 1,681.75 2,063.42Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:6:18)

06-03-f 100 Cft m3 5,638.45 593.90 1,681.75 1,991.20Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah

shingle well graded and cleaned) in foundation & plinth

(Ratio 1:7:20)

06-04-a 100 Cft m3 837.00 295.58 837.00 295.58The stone ballast,

crushed bajri, round

shingle from nallah,

or brick ballast may

be used according to

their comparative

cheaper rates in

various areas of the

province.

Extra on Item 3 above, for sedimentation tank or filter beds

in PHE works (in bed)

06-04-b 100 Cft m3 1,255.50 443.38 1,255.50 443.38Extra on Item 3 above, for sedimentation tank or filter beds

in PHE works (On slope)

06-05-a 100 Cft m3 17,800.29 551.65 1,562.09 6,286.12Plain Cement Conrete including placing, compacting,

finishing & curing (Ratio 1:1:2)

06-05-b 100 Cft m3 17,738.58 551.65 1,562.09 6,264.33Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:1.5:1.5)

Page 21 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 22: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-05-c 100 Cft m3 14,014.20 551.65 1,562.09 4,949.07Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:1.5:3)

06-05-d 100 Cft m3 13,399.52 551.65 1,562.09 4,732.00Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:2:3)

06-05-e 100 Cft m3 11,916.06 551.65 1,562.09 4,208.12Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:3:3)

06-05-f 100 Cft m3 11,969.30 551.65 1,562.09 4,226.92Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:2:4)

06-05-g 100 Cft m3 10,357.58 551.65 1,562.09 3,657.75Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:2:6)

06-05-h 100 Cft m3 10,055.08 551.65 1,562.09 3,550.92Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:3:6)

06-05-i 100 Cft m3 8,402.22 551.65 1,562.09 2,967.22Plain Cement Concrete including placing, compacting,

finishing & curing (Ratio 1:4:8)

06-06-a-01 100 Cft m3 20,251.36 1,115.56 3,158.90 7,151.711) The rate include

rendering floor

surface smooth, and

the plustering done

for making up all

surfaces after

removing centering.

RCC in roof slab, beam, column & other structural

members, insitu or precast. Type A (1:1:2)

06-06-a-02 100 Cft m3 17,171.91 1,115.56 3,158.90 6,064.212) Plustering done

after soffit of R.C.C

roof slab meant for

human habitaion

buildings shall be

paid extra

RCC in roof slab, beam, column & other structural

members, insitu or precast. Type B (1:1.5:3)

06-06-a-03 100 Cft m3 15,127.01 1,115.56 3,158.90 5,342.063) This item shall not

be aplicable to factory

made units.

RCC in roof slab, beam, column & other structural

members, insitu or precast. Type C (1:2:4)

06-06-b-01 100 Cft m3 19,252.29 1,094.76 3,100.00 6,798.89RCC in raft foundation slab, base slab of column & ret.

wall etc, not including in 06-06. Type A (1:1:2)

06-06-b-02 100 Cft m3 16,258.75 1,094.76 3,100.00 5,741.73RCC in raft foundation slab, base slab of column & ret.

wall etc, not including in 06-06 Type B (1:1.5:3)

06-06-b-03 100 Cft m3 13,508.42 1,094.76 3,100.00 4,770.46RCC in raft foundation slab, base slab of column & ret.

wall etc, not including in 06-06. Type C(1:2:4)

06-06-c-01 100 Cft m3 23,004.84 1,302.76 3,689.00 8,124.09RCC including Precast/Prestressed in slab, beam, column,

lintel, girder, etc. Type A (1:1:2)

06-06-c-02 100 Cft m3 19,925.38 1,302.76 3,689.00 7,036.59RCC including Precast/Prestressed in slab, beam. column,

lintels, girder, etc. Type B (1:1.5:3)

06-06-c-03 100 Cft m3 17,173.85 1,302.76 3,689.00 6,064.89RCC including Precast/Prestressed slab, column, beam,

lintel, girder etc. Type C (1:2:4).

06-06-e 100 Cft m3 1,185.75 418.74 1,185.75 418.74Add extra labour for RCC in 2nd & subsequent storeys

Page 22 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 23: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-07-a Cwt Tonne 5,178.12 4,271.47 217.00 101,927.17The rate includes

wastage, overlap and

chairs, etc

Supply & fabricate M.S. reinforcement for cement concrete

(Plain bars)

06-07-b Cwt Tonne 5,957.36 4,271.47 217.00 117,265.89Supply & fabricate M.S. reinforcement for cement concrete

(Hot rolled deformed bars Grade 60)

06-07-c Cwt Tonne 5,347.52 4,271.47 217.00 105,261.67Supply & fabricate M.S. reinforcement for cement concrete

(Hot rolled deformed bars Grade 40)

06-08 Cwt Tonne 10,273.84 8,542.94 434.00 202,232.33The rate includes

wastage & allowance

for stressing of

cables.

Supplying & fixing high tensile steel wire in prestressing

cables in precast girders

06-09 100 Cft m3 12,615.17 914.12 2,588.50 4,455.01Precast cement concrete solid or face blocks 1:2:4,

including cost of templates.

06-10 100 Cft m3 11,299.44 1,976.03 5,595.50 3,990.36Precast cem. concrete hollow blocks 1:2:4, including cost

of templates & constructing wall thereof

06-11 100 Sft m2 4,054.93 248.50 2,309.50 436.31Provide & fix ornamental cement jali 1:2:4 2" thick without

steel.

06-12-a 100 Cft m3 1,116.00 394.11 1,116.00 394.11Extra labour for laying concrete (plain or reinforced) From

20' upto 40' height

06-12-b 100 Cft m3 558.00 197.06 558.00 197.06Extra labour for laying concrete (plain or reinforced) For

every extra10' height

06-13 100 Cft m3 279.00 98.53 279.00 98.53Extra labour for work of weirs, rails or bridges, syphons &

concreting in superstructure

06-14 Each Each 581.15 217.00 217.00 581.15RCC spout, 2.5'x6"x5", including fixing in position

06-15 Each Each 607.60 607.60 607.60 607.60Making holes upto 3" dia, 18" depth in cement concrete or

stone masonry walls and repairing

06-16 100 Cft m3 4,076.50 1,439.60 4,076.50 1,439.60Extra labour for skipping concrete in wells

06-17-a 100 Sft m2 294.50 31.69 294.50 31.69Nicking cement concrete surface.

06-17-b 100 Sft m2 97.18 10.46 97.18 10.46Nicking lime concrete surface.

06-18-a 100 Sft m2 217.00 23.35 217.00 23.35Prepare, water and ramming surface for laying concrete (for

Headworks only) Horizontal floor

06-18-b 100 Sft m2 364.25 39.19 364.25 39.19Prepare, water and ramming surface for laying concrete (for

Headworks only) Glacis and crest

06-18-c 100 Sft m2 108.50 11.67 108.50 11.67Prepare, water and ramming surface for laying concrete (for

Headworks only) inverted filters

06-19 1 RFT m 51.11 14.83 4.52 167.67Providing and fixing 6" wide GI sheet 18 SWG. stopper to

expansion joint.

06-20 1 RFT m 11.85 9.15 2.79 38.87Fill expansion joints with bitumen, sand & saw dust in

Ratio 1:2:2

06-21-a 1 RFT m 40.38 91.54 27.90 132.49Filling expansion joints with bitumen

06-21-b 1 RFT m 27.90 91.54 27.90 91.54Laying Asphaltic Mixture in Expansion Joints

Page 23 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 24: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-22-a-01 100 Sft m2 2,755.24 108.74 1,010.60 296.46Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 1 coat bitumen (1.5" thick)

06-22-a-02 100 Sft m2 3,140.99 108.74 1,010.60 337.97Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 1 coat bitumen (2" thick)

06-22-a-03 100 Sft m2 4,040.47 115.08 1,069.50 434.75Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 1 coat bitumen (3" thick)

06-22-b-01 100 Sft m2 2,798.77 86.56 804.45 301.15Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 2 coats bitumen (1.5" thick)

06-22-b-02 100 Sft m2 3,390.67 108.74 1,010.60 364.84Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 2 coats bitumen (2" thick)

06-22-b-03 100 Sft m2 4,225.37 108.11 1,004.71 454.65Damp proof course of cem. conc. 1:2:4 including bitumen

coat, 1 layer polythene & 2 coats bitumen (3" thick)

06-23-a-01 100 Sft m2 1,810.45 99.23 922.25 194.80Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:4 (0.5" thick)

06-23-a-02 100 Sft m2 1,992.92 99.23 922.25 214.44Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:4 (0.75" thick)

06-23-a-03 100 Sft m2 1,887.89 99.23 922.25 203.14Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:3 (0.5" thick)

06-23-a-04 100 Sft m2 2,108.23 99.23 922.25 226.85Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:3 (0.75" thick)

06-23-a-05 100 Sft m2 2,003.20 99.23 922.25 215.54Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:2 (0.5" thick)

06-23-a-06 100 Sft m2 2,301.95 99.23 922.25 247.69Damp proof course in c/s plaster, 1 layer polythene, 1 coat

bitumen Ratio 1:2 (0.75" thick)

06-23-b-01 100 Sft m2 2,061.47 99.23 922.25 221.81Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:4 (0.5" thick)

06-23-b-02 100 Sft m2 2,242.60 99.23 922.25 241.30Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:4 (0.75" thick)

06-23-b-03 100 Sft m2 2,137.57 99.23 922.25 230.00Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:3 (0.5" thick)

06-23-b-04 100 Sft m2 2,357.92 99.23 922.25 253.71Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:3 (0.75" thick)

06-23-b-05 100 Sft m2 2,252.89 99.23 922.25 242.41Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:2 (0.5" thick)

06-23-b-06 100 Sft m2 2,551.64 99.23 922.25 274.56Damp proof course in c/s plaster, 1 layer polythene, 2 coats

bitumen Ratio 1:2 (0.75" thick)

06-24-a-01 100 Sft m2 1,820.49 99.23 922.25 195.89V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:4 (0.5" thick)

06-24-a-02 100 Sft m2 1,992.92 99.23 922.25 214.44V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:4 (0.75" thick)

06-24-a-03 100 Sft m2 1,900.96 99.23 922.25 204.54V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:3 (0.5" thick)

Page 24 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 25: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-24-a-04 100 Sft m2 2,108.23 99.23 922.25 226.85V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:3 (0.75" thick)

06-24-a-05 100 Sft m2 2,003.20 99.23 922.25 215.54V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:2 (0.5" thick)

06-24-a-06 100 Sft m2 2,301.95 99.23 922.25 247.69V. Damp proof c/s plaster, 1 layer polythene 1 coat

bitumen Ratio 1:2 (0.75" thick)

06-24-b-01 100 Sft m2 2,070.18 99.23 922.25 222.75V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:4 (0.5" thick)

06-24-b-02 100 Sft m2 2,242.60 99.23 922.25 241.30V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:4 (0.75" thick)

06-24-b-03 100 Sft m2 2,155.00 99.23 922.25 231.88V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:3 (0.5" thick)

06-24-b-04 100 Sft m2 2,357.92 99.23 922.25 253.71V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:3 (0.75" thick)

06-24-b-05 100 Sft m2 2,252.89 99.23 922.25 242.41V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:2 (0.5" thick)

06-24-b-06 100 Sft m2 2,551.64 99.23 922.25 274.56V. Damp proof c/s plaster, 1 layer polythene 2 coats

bitumen Ratio 1:2 (0.75" thick)

06-25 100 Cft m3 3,720.00 1,313.71 3,720.00 1,313.71Grouting concrete between the grooves of gates including

shuttering

06-26 1000 Sft m2 1,472.50 15.84 1,472.50 15.84Chisel dressing concrete surface on sides of grooves

06-27 100 Sft m2 3,373.11 362.95 3,373.11 362.95Laying and ramming dry ballast or kankar

06-28 100 No No 4,466.17 44.66 4,466.17 44.66Hoisting & placing in position RCC shelves

06-29-a 100 Cft m3 837.00 295.58 837.00 295.58Breaking brick ballast, screening & stacking 2" ring

06-29-b 100 Cft m3 976.50 344.85 976.50 344.85Breaking brick ballast, screening & stacking 1.5" ring

06-29-c 100 Cft m3 1,116.00 394.11 1,116.00 394.11Breaking brick ballast, screening & stacking 1" ring

06-29-d 100 Cft m3 1,255.50 443.38 1,255.50 443.38Breaking brick ballast, screening & stacking. Jhama ballast

3/4" ring

06-30 100 Rft m 5,730.51 29.22 890.51 188.01Supply & fix broken glasses on court yard walls, including

1:3:6 cement concrete coping

06-31 100 Cft m3 789.57 278.83 789.57 278.83This does not include

the chages for

working of crushers ,

but manual labour

for charges of stone to

crusher within 100 m

and also stacking the

product after crushing

within 100 m.

Crushing stone ballast by machine

06-32-a 100 Cft m3 976.50 344.85 976.50 344.85Breaking stone ballast screened & stacked 2" ring

06-32-b 100 Cft m3 1,116.00 394.11 1,116.00 394.11Breaking stone ballast screened & stacked 1.5" ring

06-32-c 100 Cft m3 1,255.50 443.38 1,255.50 443.38Breaking stone ballast screened & stacked 1" ring

Page 25 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 26: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-32-d 100 Cft m3 1,674.00 591.17 1,674.00 591.17Breaking stone ballast screened & stacked 0.5" ring

06-32-e 100 Cft m3 2,790.00 985.28 2,790.00 985.28Breaking stone ballast screened & stacked 1/8" to 1/4" ring

06-33 100 Cft m3 279.00 98.53 279.00 98.53Screening and stacking stone ballast, shingle or bajri etc

06-34 100 Cft m3 279.00 98.53 279.00 98.53Washing ballast, bajri or shingle

06-35 Each Each 198.40 198.40 198.40 198.40Erecting and carting sun shades of precast RCC (upto 5"x

2.5")

06-36-a 100 Cft m3 6,375.84 623.57 1,765.76 2,251.61PCC 1:3:6 in mass concrete less formwork using 50%

boulders

06-36-b 100 Cft m3 7,049.67 622.59 1,762.97 2,489.57PCC 1:3:6 in mass concrete less formwork using 40%

boulders

06-36-c 100 Cft m3 7,735.63 622.59 1,762.97 2,731.81PCC 1:3:6 in mass concrete less formwork using 30%

boulders

06-37-a 100 Cft m3 5,447.42 622.59 1,762.97 1,923.74PCC 1:4:8 in mass concrete less formwork using 50%

boulders

06-37-b 100 Cft m3 5,942.31 622.59 1,762.97 2,098.51PCC 1:4:8 in mass concrete less formwork using 40%

boulders

06-37-c 100 Cft m3 6,437.20 622.59 1,762.97 2,273.28PCC 1:4:8 in mass concrete less formwork using 30%

boulders

06-38-a 100 Sft m2 2,539.47 250.17 2,325.00 273.25Errecting & removing formwork to concrete in any shape /

position (Horizontal)

06-38-b 100 Sft m2 2,849.33 280.19 2,604.00 306.59Errecting & removing formwork to concrete in any shape /

position (Vertical)

06-39-a 100 Sft m2 6,367.00 30.85 286.75 685.09Errection and removal of steel Form work for RCC or Plain

Concrete horizontal

06-39-b 100 Sft m2 6,276.45 25.02 232.50 675.35Errection and removal of steel Form work for RCC or Plain

Concrete vertical

06-40-a 100 Cft m3 12,549.56 848.44 2,402.50 4,431.84Class A1 concrete in reinforcement/non reinforcement

concrete structure with minimum cylinder compressive

strength 3000 psi on 28 days other than concrete in water

and piles with consistency range in slump 25-75 mm with

water cement ratio 0.58

06-40-b 100 Cft m3 13,469.16 848.44 2,402.50 4,756.59Class A2 cement concrete for concrete place under water

with minimum cylinder compressive strength 3500 psi on

28 days with consistency range in slump 100-150 mm with

water cement ratio 0.58

06-40-c 100 Cft m3 15,073.62 848.44 2,402.50 5,323.20Class A3 cement concrete for concrete in pile with

minimum cylinder compressive strenght 4000 psi on 28

days other than concrete in water and piles with

consistency range in slump 100-150 mm with water cement

ratio 0.58

Page 26 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 27: Rate nwfp 2008

Item Code Description

CONCRETEChapter #

:

06

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

06-40-d 100 Cft m3 11,332.30 848.44 2,402.50 4,001.97Class B concrete for concrete in pile specified works only

with minimum cylinder compressive strenght 2418 psi on

28 days and consistency range in slump 25-75 mm with

water cement ratio 0.65

06-40-e 100 Cft m3 12,158.73 848.44 2,402.50 4,293.82Class C concrete for concrete for cribbing or otherwise

specified in special provision with minimum cylinder

compressive strength 3000 psi on 28 days and consistency

range in slump 25-75 mm with water cement ratio 0.58

06-40-f 100 Cft m3 15,900.05 848.44 2,402.50 5,615.06Class D1 concrete for concrete in pre-stressed & post

tensioned with minimum cylinder compressive strength

4978.12 psi on 28 days and consistency range in slump

50-100 mm with water cement ratio 0.40

06-40-g 100 Cft m3 17,162.08 848.44 2,402.50 6,060.74Class D2 concrete for concrete in pre-stressed & post

tensioned with minimum cylinder compressive strength

6045 psi on 28 days and consistency range in slump

50-100 mm with water cement ratio 0.40

06-40-h 100 Cft m3 18,398.14 848.44 2,402.50 6,497.25Class D3 concrete for concrete in pre-stressed & post

tensioned with minimum cylinder compressive strength

7112 psi on 28 days and consistency range in slump

50-100 mm with water cement ratio 0.40

06-40-i 100 Cft m3 14,731.19 848.44 2,402.50 5,202.28Class Y concrete for concrete use as filler in steel grid,

Bridge floor, in then reinforced section etc with minimum

cylinder compressive strength 2575 psi on 28 days and

consistency range in slump 50-100 mm with water cement

ratio 0.58

06-40-j 100 Cft m3 9,157.93 848.44 2,402.50 3,234.10Lean concrete for use as thin layer under neath footings

with cylinder compressive strength of 1423 psi on 28 days.

Page 27 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 28: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-01-a 100 Cft m3 7,764.89 618.43 1,751.19 2,742.15Pacca brickwork in mud mortar in buildings in foundation

and plinth

07-01-b 100 Cft m3 8,437.98 821.94 2,327.48 2,979.85Pacca brickwork in mud mortar in buildings in ground

floor

07-02-a 100 Cft m3 523.05 150.53 426.25 184.71Add extra labour on Item 07-01 for brickwork in First floor

07-02-b 100 Cft m3 1,096.55 353.06 999.75 387.24Add extra labour on Item 07-01 for brickwork in Second

floor

07-02-c 100 Cft m3 1,670.05 555.59 1,573.25 589.77Add extra labour on Item 07-01 for brickwork in Third

floor

07-02-d 100 Cft m3 2,243.55 758.12 2,146.75 792.30Add extra labour on Item 07-01 for brickwork in Fourth &

subsequent floors.

07-03-a 100 Cft m3 8,447.20 859.38 2,433.50 2,983.10Pacca brick work in mud mortar other than building Upto

20 ft. height

07-03-b 100 Cft m3 426.25 150.53 426.25 150.53Pacca brick work in mud mortar other than building Extra

labour for each 5 ft. addl. height or part

07-04-a-01 100 Cft m3 11,784.57 818.00 2,316.32 4,161.69Pacca brick work in foundation and plinth in Cement, sand

mortar 1:2

07-04-a-02 100 Cft m3 10,946.64 818.00 2,316.32 3,865.77Pacca brick work in foundation and plinth in Cement, sand

mortar 1:3

07-04-a-03 100 Cft m3 10,443.89 818.00 2,316.32 3,688.23Pacca brick work in foundation and plinth in Cement, sand

mortar 1:4

07-04-a-04 100 Cft m3 10,082.10 818.00 2,316.32 3,560.46Pacca brick work in foundation and plinth in Cement, sand

mortar 1:5

07-04-a-05 100 Cft m3 9,874.10 818.00 2,316.32 3,487.01Pacca brick work in foundation and plinth in Cement, sand

mortar 1:6

07-04-a-06 100 Cft m3 9,693.08 818.00 2,316.32 3,423.08Pacca brick work in foundation and plinth in Cement, sand

mortar 1:7

07-04-a-07 100 Cft m3 9,547.24 818.00 2,316.32 3,371.58Pacca brick work in foundation and plinth in Cement, sand

mortar 1:8

07-04-b-01 100 Cft m3 10,134.13 818.00 2,316.32 3,578.84Pacca brick work in foundation and plinth in Lime, cement,

sand mortar 1:1:6

07-04-b-02 100 Cft m3 9,947.96 818.00 2,316.32 3,513.09Pacca brick work in foundation and plinth in Lime, cement,

sand mortar 1:1:7

07-04-b-03 100 Cft m3 10,512.20 1,069.80 3,029.32 3,712.35Pacca brick work in foundation and plinth in Lime, cement,

sand mortar 1:1:8

07-04-b-04 100 Cft m3 9,673.60 818.00 2,316.32 3,416.20Pacca brick work in foundation and plinth in Lime, cement,

sand mortar 1:1:9

07-04-b-05 100 Cft m3 9,579.54 818.00 2,316.32 3,382.99Pacca brick work in foundation and plinth in Lime, cement,

sand mortar 1:1:10

07-04-c 100 Cft m3 9,474.23 818.00 2,316.32 3,345.80Pacca brick work in foundation and plinth in Lime, sand

mortar 1:2

Page 28 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 29: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-04-c-01 100 Cft m3 9,309.72 818.00 2,316.32 3,287.70Pacca brick work in foundation and plinth in lime, sand,

surkhi 1:1:1

07-04-c-02 100 Cft m3 9,775.97 818.00 2,316.32 3,452.35Pacca brick work in foundation and plinth in lime, coarse

cinder.

07-04-c-03 100 Cft m3 9,515.82 818.00 2,316.32 3,360.48Pacca brick work in foundation and plinth in lime, surkhi

mortar 2:3

07-04-c-04 100 Cft m3 9,304.86 818.00 2,316.32 3,285.98Pacca brick work in foundation and plinth in lime, surkhi

mortar 1:2

07-04-c-05 100 Cft m3 9,039.38 818.00 2,316.32 3,192.23Pacca brick work in foundation and plinth in lime, surkhi

mortar 1:3

07-05-a-01 100 Cft m3 12,535.47 1,048.99 2,970.42 4,426.86Pacca brick work in ground floor Cement, sand mortar 1:2

07-05-a-02 100 Cft m3 11,697.54 1,048.99 2,970.42 4,130.95Pacca brick work in ground floor Cement, sand mortar 1:3

07-05-a-03 100 Cft m3 11,194.79 1,048.99 2,970.42 3,953.41Pacca brick work in ground floor Cement, sand mortar 1:4

07-05-a-04 100 Cft m3 10,859.62 1,048.99 2,970.42 3,835.04Pacca brick work in ground floor Cement, sand mortar 1:5

07-05-a-05 100 Cft m3 10,625.00 1,048.99 2,970.42 3,752.19Pacca brick work in ground floor Cement, sand mortar 1:6

07-05-a-06 100 Cft m3 10,443.99 1,048.99 2,970.42 3,688.26Pacca brick work in ground floor Cement, sand mortar 1:7

07-05-a-07 100 Cft m3 10,298.14 1,048.99 2,970.42 3,636.76Pacca brick work in ground floor Cement, sand mortar 1:8

07-05-b-01 100 Cft m3 10,952.64 1,069.80 3,029.32 3,867.89Pacca brick work in ground floor Lime, cement, sand

mortar 1:1:6

07-05-b-02 100 Cft m3 10,757.76 1,069.80 3,029.32 3,799.07Pacca brick work in ground floor Lime, cement, sand

mortar 1:1:7

07-05-b-03 100 Cft m3 10,609.00 1,069.80 3,029.32 3,746.54Pacca brick work in ground floor Lime, cement, sand

mortar 1:1:8

07-05-b-04 100 Cft m3 10,483.40 1,069.80 3,029.32 3,702.18Pacca brick work in ground floor Lime, cement, sand

mortar 1:1:9

07-05-b-05 100 Cft m3 10,389.34 1,069.80 3,029.32 3,668.96Pacca brick work in ground floor Lime, cement, sand

mortar 1:1:10

07-05-c 100 Cft m3 10,284.03 1,069.80 3,029.32 3,631.77Pacca brick work in ground floor Lime, sand mortar 1:2

07-05-c-01 100 Cft m3 10,022.72 1,069.80 3,029.32 3,539.49Pacca brick work in foundation and plinth in lime, sand,

surkhi 1:1:1.

07-05-c-02 100 Cft m3 10,488.97 1,069.80 3,029.32 3,704.15Pacca brick work in Ground floor lime, coarse cinder.

07-05-c-03 100 Cft m3 10,228.82 1,069.80 3,029.32 3,612.28Pacca brick work in Ground floor lime, surkhi mortar 2:3

07-05-c-04 100 Cft m3 10,017.86 1,069.80 3,029.32 3,537.78Pacca brick work in Ground floor lime, surkhi mortar 1:2

07-05-c-05 100 Cft m3 9,752.38 1,069.80 3,029.32 3,444.02Pacca brick work in Ground floor lime, surkhi mortar 1:3

07-06-a 100 Cft m3 523.05 150.53 426.25 184.71Add extra labour on item No.07-05 for brick work in First

floor

07-06-b 100 Cft m3 1,096.55 353.06 999.75 387.24Add extra labour on item No.07-05 for brick work in in

Second floor

07-06-c 100 Cft m3 1,670.05 555.59 1,573.25 589.77Add extra labour on item No.07-05 for brick work in Third

floor

Page 29 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 30: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-06-d 100 Cft m3 2,677.55 911.38 2,580.75 945.57Add extra labour on item No.07-05 for brick work in in

Fourth & subsequent floors.

07-07-a-01 100 Cft m3 12,293.05 963.39 2,728.00 4,341.25Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:2

07-07-a-02 100 Cft m3 11,594.63 1,012.65 2,867.50 4,094.61Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:3

07-07-a-03 100 Cft m3 10,952.37 963.39 2,728.00 3,867.80Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:4

07-07-a-04 100 Cft m3 10,617.20 963.39 2,728.00 3,749.43Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:5

07-07-a-05 100 Cft m3 10,382.58 963.39 2,728.00 3,666.58Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:6

07-07-a-06 100 Cft m3 10,201.57 963.39 2,728.00 3,602.65Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:7

07-07-a-07 100 Cft m3 10,055.72 963.39 2,728.00 3,551.15Pacca brick work other than building upto 10 ft. height :

Cement, sand mortar 1:8

07-07-b-01 100 Cft m3 10,642.61 963.39 2,728.00 3,758.41Pacca brick work other than building upto 10 ft. height :

Lime, cement, sand mortar 1:1:6

07-07-b-02 100 Cft m3 10,456.97 963.39 2,728.00 3,692.85Pacca brick work other than building upto 10 ft. height :

Lime, cement, sand mortar 1:1:7

07-07-b-03 100 Cft m3 10,307.68 963.39 2,728.00 3,640.13Pacca brick work other than building upto 10 ft. height :

Lime, cement, sand mortar 1:1:8

07-07-b-04 100 Cft m3 10,182.08 963.39 2,728.00 3,595.77Pacca brick work other than building upto 10 ft. height :

Lime, cement, sand mortar 1:1:9

07-07-b-05 100 Cft m3 10,088.02 963.39 2,728.00 3,562.55Pacca brick work other than building upto 10 ft. height :

Lime, cement, sand mortar 1:1:10

07-07-c 100 Cft m3 9,982.71 963.39 2,728.00 3,525.36Pacca brick work other than building upto 10 ft. height :

Lime, sand mortar 1:2

07-07-c-01 100 Cft m3 11,073.76 1,406.76 3,983.50 3,910.67Pacca brick work in other than building upto 10 ft height in

lime, sand, surkhi 1:1:1

07-07-c-02 100 Cft m3 10,284.45 963.39 2,728.00 3,631.92Pacca brick work in other than building upto 10 ft height in

lime, coarse cinder 1:1

07-07-c-03 100 Cft m3 10,024.30 963.39 2,728.00 3,540.05Pacca brick work in other than building upto 10 ft height in

lime, surkhi mortar 2:3

07-07-c-04 100 Cft m3 9,394.84 815.59 2,309.50 3,317.76Pacca brick work in other than building upto 10 ft height in

lime, surkhi mortar 1:2

07-07-c-05 100 Cft m3 9,849.18 1,069.80 3,029.32 3,478.21Pacca brick work in other than building upto 10 ft height in

lime, surkhi mortar 1:3

07-08 100 Cft m3 445.61 150.53 426.25 157.37Add extra labour on item No. 07-07 for every 10 ft.

additional height, or part thereof

07-09 100 Cft m3 1,195.40 405.06 1,147.00 422.15Extra labour for arch work in brick masonry, including

labour for centring and decentring

Page 30 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 31: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-10 100 Cft m3 1,032.70 260.00 736.25 364.69Extra for pacca brick work in steining of wells or any other

circular masonry.

07-11 100 Cft m3 868.00 306.53 868.00 306.53Extra labour for profile & flared walls

07-12-a 100 Cft m3 573.50 202.53 573.50 202.53Extra labour for pacca brick work in pier/abutment From

10 ft.to 20 ft. height.

07-12-b 100 Cft m3 1,007.50 355.80 1,007.50 355.80Extra labour for pacca brick work in pier/abutment

Exceeding 20 ft height.

07-13 100 Sft m2 573.50 61.71 573.50 61.71This item is to be

executed only on the

written orders of

Superintending

Engineer.

Extra for face work (half brick thick) using special bricks

instead of first class bricks.

07-14 100 Cft m3 17,535.59 2,632.01 7,453.02 6,192.64Reinforced brick work in lintel of openings, laid in 1:3

cement mortar complete

07-15-a 100 No 100 No 1,906.50 1,906.50 1,906.50 1,906.50Extra for dressing or chamfering bricks for Special

architectural bricks

07-15-b 100 No 100 No 1,317.50 1,317.50 1,317.50 1,317.50Extra for dressing or chamfering bricks for all other

purposes.

07-16-a 100 Sft m2 2,791.98 125.22 1,163.74 300.42Perf. pacca brick wall 1/2 brick thick in ground floor : Mud

mortar

07-16-b-01 100 Sft m2 4,106.12 163.28 1,517.45 441.82Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:2

07-16-b-02 100 Sft m2 3,896.31 163.28 1,517.45 419.24Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:3

07-16-b-03 100 Sft m2 3,770.95 163.28 1,517.45 405.75Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:4

07-16-b-04 100 Sft m2 3,687.16 163.28 1,517.45 396.74Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:5

07-16-b-05 100 Sft m2 3,628.17 163.28 1,517.45 390.39Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:6

07-16-b-06 100 Sft m2 3,583.59 163.28 1,517.45 385.59Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:7

07-16-b-07 100 Sft m2 3,549.28 163.31 1,517.73 381.90Perf. pacca brick wall 1/2 brick thick in ground floor :

Cement, sand mortar 1:8

07-16-c-01 100 Sft m2 3,570.82 163.28 1,517.45 384.22Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, cement, sand mortar 1:1:6

07-16-c-02 100 Sft m2 3,528.51 163.28 1,517.45 379.67Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, cement, sand mortar 1:1:7

07-16-c-03 100 Sft m2 3,489.51 163.28 1,517.45 375.47Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, cement, sand mortar 1:1:8

07-16-c-04 100 Sft m2 3,455.02 163.28 1,517.45 371.76Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, cement, sand mortar 1:1:9

Page 31 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 32: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-16-c-05 100 Sft m2 3,435.02 163.28 1,517.45 369.61Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, cement, sand mortar 1:1:10

07-16-d 100 Sft m2 3,403.09 163.28 1,517.45 366.17Perf. pacca brick wall 1/2 brick thick in ground floor :

Lime, sand mortar 1:2

07-17-a 100 Sft m2 232.49 22.93 213.13 25.02Add extra labour on item No. 07-16 for pacca brick work

in First floor

07-17-b 100 Sft m2 519.23 53.79 499.88 55.87Add extra labour on item No. 07-16 for pacca brick work

in Second floor

07-17-c 100 Sft m2 810.83 84.64 786.63 87.24Add extra labour on item No. 07-16 for pacca brick work

in Third floor

07-17-d 100 Sft m2 1,324.26 138.84 1,290.38 142.49Add extra labour on item No. 07-16 for pacca brick work

in Fourth & subsequent floors.

07-18-a 100 Sft m2 4,849.26 187.83 1,745.61 521.78Perf. pacca brick wall 1 brick thick in ground floor : Mud

mortar

07-18-b-01 100 Sft m2 7,070.98 241.03 2,240.06 760.84Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:2

07-18-b-02 100 Sft m2 6,652.02 241.03 2,240.06 715.76Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:3

07-18-b-03 100 Sft m2 6,400.65 241.03 2,240.06 688.71Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:4

07-18-b-04 100 Sft m2 6,233.06 241.03 2,240.06 670.68Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:5

07-18-b-05 100 Sft m2 6,115.08 241.03 2,240.06 657.98Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:6

07-18-b-06 100 Sft m2 6,023.65 241.03 2,240.06 648.14Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:7

07-18-b-07 100 Sft m2 5,952.39 241.03 2,240.06 640.48Perf. pacca brick wall 1 brick thick in ground floor :

Cement, sand mortar 1:8

07-18-c-01 100 Sft m2 6,245.77 241.03 2,240.06 672.04Perf. pacca brick wall 1 brick thick in ground floor : Lime,

cement, sand mortar 1:1:6

07-18-c-02 100 Sft m2 6,150.77 241.03 2,240.06 661.82Perf. pacca brick wall 1 brick thick in ground floor : Lime,

cement, sand mortar 1:1:7

07-18-c-03 100 Sft m2 6,084.41 241.03 2,240.06 654.68Perf. pacca brick wall 1 brick thick in ground floor : Lime,

cement, sand mortar 1:1:8

07-18-c-04 100 Sft m2 6,015.50 241.03 2,240.06 647.27Perf. pacca brick wall 1 brick thick in ground floor : Lime,

cement, sand mortar 1:1:9

07-18-c-05 100 Sft m2 5,969.68 241.03 2,240.06 642.34Perf. pacca brick wall 1 brick thick in ground floor : Lime,

cement, sand mortar 1:1:10

07-18-d 100 Sft m2 5,890.47 241.03 2,240.06 633.81Perf. pacca brick wall 1 brick thick in ground floor : Lime,

sand mortar 1:2

07-19-a 100 Sft m2 321.16 34.56 321.16 34.56Add extra labour on item No. 07-18 for perf. pacca brick

work in First floor

Page 32 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 33: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-19-b 100 Sft m2 999.75 107.57 999.75 107.57Add extra labour on item No. 07-18 for perf. pacca brick

work in Second floor

07-19-c 100 Sft m2 1,790.25 192.63 1,790.25 192.63Add extra labour on item No. 07-18 for perf. pacca brick

work in Third floor

07-19-d 100 Sft m2 2,580.75 277.69 2,580.75 277.69Add extra labour on item No. 07-18 for perf. pacca brck

work in Fourth & subsequent floors

07-20-a 100 Cft m3 14,336.00 1,067.39 3,022.50 5,062.72Fire brick masonry in fire-clay mortar Upto 20 ft. height

including all charges

07-20-b 100 Cft m3 474.65 150.53 426.25 167.62Fire brick masonry in fire-clay mortar. Extra for every 5 ft.

additional height, or part thereof

07-21-a 100 Sft m2 4,467.48 112.65 1,046.96 480.701st class brick wall laid in 1:3 c/s mortar reinfd 4.5" thick

wall with hoop iron bonding 6" apart

07-21-b 100 Sft m2 4,460.23 112.65 1,046.96 479.921st class brick wall laid in 1:3 c/s mortar reinfd 4.5" thick

wall with hoop iron bonding 12" apart

07-21-c 100 Sft m2 3,183.34 87.80 816.01 342.531st class brick wall laid in 1:3 c/s mortar reinfd 3" thick

wall with hoop iron bonding 6" apart

07-21-d 100 Sft m2 3,195.54 89.89 835.45 343.841st class brick wall laid in 1:3 c/s mortar reinfd 3" thick

wall with hoop iron banding 12" apart

07-22 100 Cft m3 8,005.60 1,160.44 3,286.00 2,827.16Ghilafi work (1.5 brick thick wall)

07-23 100 Cft m3 7,130.45 405.06 1,147.00 2,518.10Dry brick pitching

07-24 100 Cft m3 5,329.85 681.49 1,929.75 1,882.22Sun dried bricks in mud mortar

07-25 100 Cft m3 1,969.10 306.53 868.00 695.38Pise wall (mud walling)

07-26-a 100 Rft m 3,494.50 52.12 1,588.75 114.65Eave brick moulded in 1:3 c/s mortar 3" thick drip course

cornice

07-26-b 100 Rft m 4,426.61 59.24 1,805.75 145.23Eave brick moulded in 1:3 c/s mortar 4.5" thick drip course

cornice

07-26-c 100 Rft m 4,181.73 50.09 1,526.75 137.20Eave brick moulded in 1:3 c/s mortar 4.5" thick eave brick

with back brick

07-27-a 100 Rft m 2,900.20 59.24 1,805.75 95.15Laying dressed or moulded brick cornices in c/s mortar,

plaster or paint (1 brick)

07-27-b 100 Rft m 6,044.21 87.72 2,673.75 198.30Laying dressed or moulded brick cornices c/s mortar,

plaster or paint (2 brick)

07-27-c 100 Rft m 9,327.30 116.93 3,564.07 306.01Laying dressed or moulded brick cornices c/s mortar,

plaster or paint (3 brick)

07-27-d 100 Rft m 12,512.69 146.97 4,479.50 410.52Laying dressed or moulded brick cornices c/s mortar,

plaster or paint (4 brick)

07-28 1000 No. 1000 No. 279.00 279.00 279.00 279.00Cleaning bricks dismantled from kacha pacca masonry

07-29 1000 No. 1000 No. 589.00 589.00 589.00 589.00Scraping bricks dismantled from pacca masonry

07-30 100 Cft m3 1,552.23 31.12 88.13 548.17Supplying and filling sand under floor or plugging in wells

07-31 100 Rft m 5,153.87 143.41 4,371.00 169.09Provide & lay 2" thick & 15" projected tile band, laid in

1:2 c/s mortar

Page 33 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 34: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-32-a 100 Sft m2 3,844.50 126.59 1,176.45 413.67This item is to be

executed only on the

written orders of

Superintending

Engineer.

First class brick tiles clad by laying tiles in stretcher course,

in cement sand mortar 1:3

07-32-b 100 Sft m2 3,691.52 126.59 1,176.45 397.21First class brick tiles clad by laying tiles in stretcher course,

in cement sand mortar 1:4

07-33 100 Sft m2 3,468.53 373.21 3,468.53 373.21Chamfering sides of head regulators and masonry walls to

increase width

07-34 Each Each 21.59 17.36 17.36 21.59Replacing kallar eaten bricks

07-35 Each Each 217.00 217.00 217.00 217.00Repairing corners of bridges & other hydraulic masonry

works

07-36 100 Rft m 2,592.72 85.06 2,592.72 85.06Payable in addition to

brickwork

Extra labour for drains of bath rooms etc

07-37 Each Each 112.84 112.84 112.84 112.84Payable in addition to

brickwork

Maroo corners

07-38-a 100Cft m3 15,277.82 1,094.43 3,099.07 5,395.32Masonry with Facing/Machine/Special Bricks in cement

sand mortar 1:2 upto 10 ft. height

07-38-b 100Cft m3 14,370.18 1,069.80 3,029.32 5,074.79Masonry using Facing/Machine/Special bricks in cement

sand mortar 1:3 upto 10 ft. height

07-38-c 100Cft m3 13,867.29 1,069.80 3,029.32 4,897.19Masonry using Facing/Machine/Special bricks in cement

sand mortar 1:4 upto 10 ft. height

07-39 100Cft m3 158.35 53.70 152.05 55.92Add extra labour on Item 07-38 for every 10 ft additional

height or part thereof

07-40 100Cft m3 17,880.16 1,883.53 5,333.55 6,314.32Masonry with Machine/Special Bricks in 1:3 c/s mortar in

circular core wall of Overhead Reservoir

07-41-a 100Cft m3 10,656.00 558.33 1,581.00 3,763.13Hollow Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-41-b 100Cft m3 10,240.37 558.33 1,581.00 3,616.36Hollow Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-41-c 100Cft m3 9,985.66 558.33 1,581.00 3,526.41Hollow Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of

1900 psi.

07-41-d 100Cft m3 9,818.08 558.33 1,581.00 3,467.22Hollow Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

Page 34 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 35: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-41-e 100Cft m3 9,714.50 558.33 1,581.00 3,430.65Hollow Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-41-f 100Cft m3 9,610.92 558.33 1,581.00 3,394.07Hollow Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-41-g 100Cft m3 9,536.87 558.33 1,581.00 3,367.92Hollow Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using Hollow Block 16"x8"x8" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-a 100Cft m3 12,519.66 646.02 1,829.31 4,421.28Hollow Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-b 100Cft m3 12,016.91 646.02 1,829.31 4,243.74Hollow Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-c 100Cft m3 11,715.25 646.02 1,829.31 4,137.21Hollow Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-d 100Cft m3 11,514.15 646.02 1,829.31 4,066.19Hollow Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of

1900 psi.

07-42-e 100Cft m3 11,371.37 646.02 1,829.31 4,015.77Hollow Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-f 100Cft m3 11,264.77 646.02 1,829.31 3,978.12Hollow Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

07-42-g 100Cft m3 11,178.98 646.02 1,829.31 3,947.82Hollow Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using Hollow Block 16"x8"x6" factory

manufactured with 1.5" wall thickness and strenght of 1900

psi.

Page 35 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 36: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-43-a 100Cft m3 15,226.04 746.29 2,113.27 5,377.03Hollow Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-b 100Cft m3 14,640.16 746.29 2,113.27 5,170.13Hollow Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-c 100Cft m3 14,287.56 746.29 2,113.27 5,045.61Hollow Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-d 100Cft m3 14,052.95 746.29 2,113.27 4,962.76Hollow Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-e 100Cft m3 13,889.72 746.29 2,113.27 4,905.11Hollow Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-f 100Cft m3 13,762.67 746.29 2,113.27 4,860.25Hollow Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-43-g 100Cft m3 13,659.45 746.29 2,113.27 4,823.79Hollow Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using Hollow Block 16"x8"x4" factory

manufactured with 1.25" wall thickness and strenght of

1900 psi.

07-44-a 100Cft m3 11,067.40 558.33 1,581.00 3,908.42Solid Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-44-b 100Cft m3 10,651.76 558.33 1,581.00 3,761.64Solid Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-44-c 100Cft m3 10,397.06 558.33 1,581.00 3,671.69Solid Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-44-d 100Cft m3 10,229.47 558.33 1,581.00 3,612.51Solid Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-44-e 100Cft m3 10,125.90 558.33 1,581.00 3,575.93Solid Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

Page 36 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 37: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-44-f 100Cft m3 10,022.32 558.33 1,581.00 3,539.35Solid Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-44-g 100Cft m3 9,948.27 558.33 1,581.00 3,513.20Solid Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using 16"x8"x8" factory manufactured

solid blocks with strength of 2100 psi.

07-45-a 100Cft m3 13,064.16 646.02 1,829.31 4,613.57Solid Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-b 100Cft m3 12,561.41 646.02 1,829.31 4,436.02Solid Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-c 100Cft m3 12,259.75 646.02 1,829.31 4,329.49Solid Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-d 100Cft m3 12,058.65 646.02 1,829.31 4,258.48Solid Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-e 100Cft m3 11,915.87 646.02 1,829.31 4,208.05Solid Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-f 100Cft m3 11,809.27 646.02 1,829.31 4,170.41Solid Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-45-g 100Cft m3 11,723.48 646.02 1,829.31 4,140.11Solid Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using 16"x8"x6" factory manufactured

solid blocks with strength of 1900 psi.

07-46-a 100Cft m3 16,002.86 746.29 2,113.27 5,651.36Solid Block Masonry in walls upto 20 feet height in 1:2

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

07-46-b 100Cft m3 15,416.98 746.29 2,113.27 5,444.46Solid Block Masonry in walls upto 20 feet height in 1:3

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

07-46-c 100Cft m3 15,064.38 746.29 2,113.27 5,319.94Solid Block Masonry in walls upto 20 feet height in 1:4

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

07-46-d 100Cft m3 14,829.76 746.29 2,113.27 5,237.09Solid Block Masonry in walls upto 20 feet height in 1:5

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

07-46-e 100Cft m3 14,666.54 746.29 2,113.27 5,179.44Solid Block Masonry in walls upto 20 feet height in 1:6

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

Page 37 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 38: Rate nwfp 2008

Item Code Description

BRICK MASONRYChapter #

:

07

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

07-46-f 100Cft m3 14,539.49 746.29 2,113.27 5,134.58Solid Block Masonry in walls upto 20 feet height in 1:7

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

07-46-g 100Cft m3 14,436.27 746.29 2,113.27 5,098.13Solid Block Masonry in walls upto 20 feet height in 1:8

cement sand mortar using 16"x8"x4" factory manufactured

solid blocks with strength of 1800 psi.

Page 38 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 39: Rate nwfp 2008

Item Code Description

STONE MASONRYChapter #

:

08

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

08-01-a 100 Cft m3 4,519.70 711.59 2,015.00 1,596.12Random rubble masonry in foundn. & plinth Dry masonry.

08-01-b 100 Cft m3 5,404.60 889.49 2,518.75 1,908.62Random rubble masonry in foundn. & plinth in mud mortar

08-01-c-01 100 Cft m3 8,246.50 1,373.92 3,890.50 2,912.23Random rubble masonry (Un coursed) in foundn. & plinth

in lime, sand mortar 1:2

08-01-c-02 100 Cft m3 8,137.60 1,373.92 3,890.50 2,873.77Random rubble masonry (Un coursed) in foundn. & plinth

in lime, sand mortar, Surkhi Ratio 1:1:1

08-01-c-03 100 Cft m3 8,028.70 1,373.92 3,890.50 2,835.31Random rubble masonry (Un coursed) in foundn. & plinth

in lime, Surkhi Ratio 1:2

08-01-d-01 100 Cft m3 10,764.81 1,373.92 3,890.50 3,801.56Random rubble masonry in foundn. & plinth in cement,

sand mortar : Ratio 1:3

08-01-d-02 100 Cft m3 10,010.68 1,373.92 3,890.50 3,535.24Random rubble masonry in foundn. & plinth in cement,

sand mortar : Ratio 1:4

08-01-d-03 100 Cft m3 9,147.55 1,373.92 3,890.50 3,230.43Random rubble masonry in foundn. & plinth in cement,

sand mortar : Ratio 1:6

08-01-d-04 100 Cft m3 8,670.00 1,373.92 3,890.50 3,061.78Random rubble masonry in foundn. & plinth in cement,

sand mortar : Ratio 1:8

08-02-a 100 Cft m3 5,108.70 919.59 2,604.00 1,804.12Coursed rubble masonry in foundn. & plinth dry masonry.

08-02-b 100 Cft m3 6,497.35 1,275.39 3,611.50 2,294.52Coursed rubble masonry in foundn. & plinth in mud mortar

08-02-c-01 100 Cft m3 8,551.54 1,554.55 4,402.00 3,019.95Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in lime, sand mortar 1:2

08-02-c-02 100 Cft m3 8,699.65 1,554.55 4,402.00 3,072.26Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in lime, sand mortar, Surkhi Ratio 1:1:1

08-02-c-03 100 Cft m3 8,602.94 1,554.55 4,402.00 3,038.10Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in lime, Surkhi Ratio 1:2

08-02-d-01 100 Cft m3 11,035.83 1,554.55 4,402.00 3,897.27Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in cement,sand mortar : Ratio 1:3

08-02-d-02 100 Cft m3 10,365.49 1,554.55 4,402.00 3,660.54Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in cement,sand mortar : Ratio 1:4

08-02-d-03 100 Cft m3 9,594.96 1,554.55 4,402.00 3,388.43Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in cement,sand mortar : Ratio 1:6

08-02-d-04 100 Cft m3 9,176.30 1,554.55 4,402.00 3,240.58Coursed rubble masonry (Hammer Dressed) in foundn. &

plinth in cement,sand mortar : Ratio 1:8

08-03-a 100 Cft m3 4,814.20 815.59 2,309.50 1,700.12Random rubble masonry in ground floor Dry masonry.

08-03-b 100 Cft m3 5,908.35 1,067.39 3,022.50 2,086.52Random rubble masonry in ground floor in mud mortar

08-03-c-01 100 Cft m3 8,610.75 1,502.55 4,254.75 3,040.86Random rubble masonry in ground floor in lime, sand

mortar 1:2

08-03-c-02 100 Cft m3 8,501.85 1,502.55 4,254.75 3,002.40Random rubble masonry in ground floor in lime, sand

mortar, Surkhi Ratio 1:1:1

08-03-c-03 100 Cft m3 8,392.95 1,502.55 4,254.75 2,963.95Random rubble masonry in ground floor in lime, Surkhi

Ratio 1:2

08-03-d-01 100 Cft m3 11,129.06 1,502.55 4,254.75 3,930.19Random rubble masonry in ground floor in cement,sand

mortar : Ratio 1:3

Page 39 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 40: Rate nwfp 2008

Item Code Description

STONE MASONRYChapter #

:

08

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

08-03-d-02 100 Cft m3 10,374.93 1,502.55 4,254.75 3,663.88Random rubble masonry in ground floor in cement,sand

mortar : Ratio 1:4

08-03-d-03 100 Cft m3 9,511.80 1,502.55 4,254.75 3,359.06Random rubble masonry in ground floor in cement,sand

mortar : Ratio 1:6

08-03-d-04 100 Cft m3 9,034.25 1,502.55 4,254.75 3,190.42Random rubble masonry in ground floor in cement,sand

mortar : Ratio 1:8

08-04-a 100 Cft m3 5,542.70 1,072.86 3,038.00 1,957.39Coursed rubble masonry in ground floor Dry masonry.

08-04-b 100 Cft m3 7,659.85 1,685.92 4,774.00 2,705.05Coursed rubble masonry in ground floor in mud mortar

08-04-c-01 100 Cft m3 9,131.46 1,759.82 4,983.25 3,224.75Coursed rubble masonry in ground floor in lime, sand

mortar 1:2

08-04-c-02 100 Cft m3 9,280.90 1,759.82 4,983.25 3,277.52Coursed rubble masonry in ground floor in lime, sand

mortar, Surkhi Ratio 1:1:1

08-04-c-03 100 Cft m3 9,183.58 1,759.82 4,983.25 3,243.16Coursed rubble masonry in ground floor in lime, Surkhi

Ratio 1:2

08-04-d-01 100 Cft m3 11,617.08 1,759.82 4,983.25 4,102.54Coursed rubble masonry in ground floor in cement,sand

mortar : Ratio 1:3

08-04-d-02 100 Cft m3 10,946.74 1,759.82 4,983.25 3,865.81Coursed rubble masonry in ground floor in cement,sand

mortar : Ratio 1:4

08-04-d-03 100 Cft m3 10,178.87 1,759.82 4,983.25 3,594.64Coursed rubble masonry in ground floor in cement,sand

mortar : Ratio 1:6

08-04-d-04 100 Cft m3 9,770.86 1,759.82 4,983.25 3,450.55Coursed rubble masonry in ground floor in cement,sand

mortar : Ratio 1:8

08-05-a-01 100 Cft m3 20,195.73 4,926.40 13,950.00 7,132.06Ashlar block masonry in ground floor in lime, sand mortar

1:2

08-05-a-02 100 Cft m3 20,123.13 4,926.40 13,950.00 7,106.42Ashlar block masonry in ground floor in lime, sand mortar,

Surkhi Ratio 1:1:1

08-05-a-03 100 Cft m3 20,050.53 4,926.40 13,950.00 7,080.78Ashlar block masonry in ground floor in lime, Surkhi

Ratio 1:2

08-05-b-01 100 Cft m3 21,874.61 4,926.40 13,950.00 7,724.95Ashlar block masonry in ground floor in cement,sand

mortar : Ratio 1:3

08-05-b-02 100 Cft m3 21,371.85 4,926.40 13,950.00 7,547.40Ashlar block masonry in ground floor in cement,sand

mortar : Ratio 1:4

08-05-b-03 100 Cft m3 20,802.06 4,926.40 13,950.00 7,346.19Ashlar block masonry in ground floor in cement,sand

mortar : Ratio 1:6

08-06-a-01 100 Cft m3 34,625.51 9,666.69 27,373.00 12,227.89Ashlar fine masonry in ground floor in lime, sand mortar

1:2

08-06-a-02 100 Cft m3 34,589.21 9,666.69 27,373.00 12,215.08Ashlar fine masonry in ground floor in lime, sand mortar,

Surkhi Ratio 1:1:1

08-06-a-03 100 Cft m3 34,552.91 9,666.69 27,373.00 12,202.26Ashlar fine masonry in ground floor in lime, Surkhi Ratio

1:2

08-06-b-01 100 Cft m3 35,464.95 9,666.69 27,373.00 12,524.34Ashlar fine masonry in ground floor in cement,sand mortar

: Ratio 1:3

Page 40 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 41: Rate nwfp 2008

Item Code Description

STONE MASONRYChapter #

:

08

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

08-06-b-02 100 Cft m3 35,213.57 9,666.69 27,373.00 12,435.57Ashlar fine masonry in ground floor in cement,sand mortar

: Ratio 1:4

08-06-b-03 100 Cft m3 34,932.90 9,666.69 27,373.00 12,336.45Ashlar fine masonry in ground floor in cement,sand mortar

: Ratio 1:6

08-07-a 100 Cft m3 612.25 216.21 612.25 216.21Extra labour on items 08-03-a-01 to 08-06-b-03 for work in

First floor

08-07-b 100 Cft m3 1,432.20 505.78 1,432.20 505.78Extra labour on items 08-03-a-01 to 08-06-b-03 for work in

Second floor

08-07-c 100 Cft m3 2,266.10 800.27 2,266.10 800.27Extra labour on items 08-03-a-01 to 08-06-b-03 for work in

Third floor

08-07-d 100 Cft m3 3,623.90 1,279.77 3,623.90 1,279.77Extra labour on items 08-03-a-01 to 08-06-b-03 for work in

Fourth & subsequent floors

08-08 100 Cft m3 573.50 202.53 573.50 202.53Extra labour on items 08-03-a-01 to 08-06-b-03 for every

5' additional height, other than building

08-09 100 Cft m3 2,294.00 810.12 2,294.00 810.12Extra labour for arch work in stone masonry including

centring & decentring etc.

08-10-a 100 Cft m3 11,780.00 4,160.07 11,780.00 4,160.07Extra labour for coping & caps etc

08-10-b 100 Cft m3 11,780.00 4,160.07 11,780.00 4,160.07Extra labour for cornice & string course

08-11-a 100 Sft m2 3,642.50 391.93 3,642.50 391.93a) This rate of

dressing shall be paid

only when supply of

undressed stone is

made

Dressing stones : Hammer dressed

08-11-b 100 Sft m2 7,006.00 753.85 7,006.00 753.85b) In case of masonry,

dressing is already

included and this rate

shall not be added

thereto

Dressing stones : Rough tooled dressed

08-11-c 100 Sft m2 8,463.00 910.62 8,463.00 910.62c) Only dressed

surface of stone shall

be measured

Dressing stones : Chisel dressed

08-11-d 100 Sft m2 18,476.00 1,988.02 18,476.00 1,988.02Dressing stones : Fine dressed

08-12 100 Sft m2 11,663.75 588.40 5,468.40 1,255.02Dhajji walling 5"x5" thick deodar framing with stone laid

in 1:6 c/s mortar & 1:4 c/s plaster

08-13 100 Cft m3 21,864.60 6,798.43 19,251.00 7,721.42Provide & fix stone blocks from 2 cft. to 6 cft. each,

including lift upto 20 ft.

08-14 100 Cft m3 12,130.60 3,360.90 9,517.00 4,283.88Providing and fixing stone blocks, under 2 cft. each,

including lift upto 20 ft.

08-15 100 Cft m3 3,529.30 208.00 589.00 1,246.36Provide & lay stone/boulder dry hand packed as filling

behind retaining walls or in pitching

Page 41 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 42: Rate nwfp 2008

Item Code Description

ROOFINGChapter #

:

09

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

09-01 100 Sft m2 9,201.08 448.97 4,172.60 990.04Add extra 13%, 32%

and 51% on labour

rates only are 6%,

15% and 23% on

composite rates for

2nd, 3rd, 4th and

subsequent floors

respectively.

First class tile roofing including earth, mud plaster, gobri

leeping, cement plaster etc complete

09-02 100 Sft m2 6,993.54 338.56 3,146.50 752.50dittoSecond class tile roofing consisting of 4" earth and 1" mud

plaster with gobri leeping etc

09-03 100 Sft m2 567.83 15.11 140.43 61.10dittoCovering mud roof with coal tar and fine sand

09-04-a 100 Sft m2 2,017.29 46.70 434.00 217.06dittoFilling spaces in between wooden battens over beams,

filled with deodar wood pieces

09-04-b 100 Sft m2 895.33 65.61 609.77 96.34Filling spaces in between RCC battens, filled with PCC

block 1:3:6

09-04-c 100 Sft m2 466.46 18.88 175.46 50.19Filling spaces in between spacers filled with bricks

09-05 100 Sft m2 5,091.50 139.26 1,294.25 547.85Add extra 13%, 32%

and 51% on labour

rates only are 6%,

15% and 23% on

composite rates for

2nd, 3rd, 4th and

subsequent floors

respectively.

Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1"

mud plaster on top of RC roof slab

09-06-a 100 Sft m2 11,416.48 493.67 4,588.00 1,228.41a) For steel part and

its erection etc. Item

No 25-10 and 25-14

be reffered b) Add

extra 13%, 32% and

51% on labour rates

only are 6%, 15% and

23% on composite

rates for 2nd, 3rd, 4th

and subsequent floors

respectively.

Jack arch roof 4.5" thick laid in 1:5 c/s mortar a) cement

concrete in haunches 1:6:12

09-06-b 100 Sft m2 12,415.70 493.67 4,588.00 1,335.93Jack arch roof 4.5" thick laid in 1:5 c/s mortar b) cement

concrete in haunches 1:3:6

Page 42 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 43: Rate nwfp 2008

Item Code Description

ROOFINGChapter #

:

09

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

09-07-a 100 Sft m2 10,246.29 401.11 3,727.75 1,102.50a) For steel part and

its erection etc. Item

No 25-10 and 25-14

be reffered b) Add

extra 13%, 32% and

51% on labour rates

only are 6%, 15% and

23% on composite

rates for 2nd, 3rd, 4th

and subsequent floors

respectively.

Jack arch roofing 4.5"thick laid in 1:5 c/s mortar complete.

Cement concrete in haunches 1:6:12

09-07-b 100 Sft m2 11,149.43 401.11 3,727.75 1,199.68Jack arch roofing 4.5"thick laid in 1:5 cement mortar,

including complete. Cement concrete in haunches 1:3:6

09-08 100 Sft m2 1,178.00 126.75 1,178.00 126.75dittoExtra for vaulted jack arch roofing

09-09 100 Sft m2 7,348.03 395.27 3,673.50 790.65Jack arch roofing of shingle & cement concrete 1:3:6, 4.5"

at crown & 1/2" cem. plaster complete

09-10-a 100 Sft m2 984.23 41.23 383.16 105.90Add extra 13%, 32%

and 51% on labour

rates only are 6%,

15% and 23% on

composite rates for

2nd, 3rd, 4th and

subsequent floors

respectively.

Earth filling over roof including watering, ramming etc 3"

thick earth filling and 1" mud plaster

09-10-b 100 Sft m2 1,085.67 43.03 399.90 116.82Earth filling over roof including watering, ramming etc 4"

thick earth filling and 1" mud plaster

09-11 100 Sft m2 111.92 9.41 87.42 12.04ditto1/8" thick gobri leeping on roofs or floors

09-12 100 Sft m2 1,095.78 30.02 279.00 117.912 coats of bitumen laid hot using 34 lbs. for %sft over roof

& blinded with sand at 1 cft per % sft

09-13-a 100 Sft m2 10,450.23 93.40 868.00 1,124.44Add extra 13%, 32%

and 51% on labour

rates only are 6%,

15% and 23% on

composite rates for

2nd, 3rd, 4th and

subsequent floors

respectively.

Supply & fix corrugated GI sheet with GI bolts, nuts,

limpet etc. complete : 20 BWG

09-13-b 100 Sft m2 9,172.47 93.40 868.00 986.96Supply & fix corrugated GI sheet with GI bolts, nuts,

limpet etc. complete : 22 BWG

09-13-c 100 Sft m2 7,734.99 93.40 868.00 832.29Supply & fix corrugated GI sheet with GI bolts, nuts,

limpet etc. complete : 24 BWG

09-14 1 Rft m 70.18 165.87 50.56 230.24dittoKhassi parnalas in c/s mortar 1:2, 12" outside width

finished smooth with a floating coat

09-15 Each Each 363.00 187.55 187.55 363.00dittoKhuras on roof 2'x2'x6"

Page 43 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 44: Rate nwfp 2008

Item Code Description

ROOFINGChapter #

:

09

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

09-16 Each Each 579.83 187.55 187.55 579.83dittoBottom khuras of brick masonry in c/s mortar

1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8

09-17-a 1 RFT m 118.01 136.43 41.59 387.19dittoPlain GI sheets 22 SWG rain water down pipe a) 4"

diameter down pipe

09-17-b 1 RFT m 132.38 136.43 41.59 434.32Plain GI sheets 22 SWG rain water down pipe b) 5"

diameter down pipe

09-18 100 Sft m2 9,496.63 595.82 5,537.36 1,021.84dittoPlain galvanized iron sheet flashing, 22 guage

09-19-a 1 RFT m 290.05 96.53 29.42 951.62dittoCast iron rain water down pipe fixed in position excluding

heads & shoes : 4" dia

09-19-b 1 RFT m 231.60 96.53 29.42 759.84Cast iron rain water down pipe fixed in position excluding

heads & shoes : 3" dia

09-20 Each Each 500.35 122.76 122.76 500.35dittoHeads for cast iron rain water down pipe fixed in place

including cost of clamp holdfast and painting

09-21 Each Each 445.79 68.20 68.20 445.79dittoShoes, bends or offsets for cast iron ran water down pipe,

including fixing & painting

09-22 Each Each 287.54 145.70 145.70 287.54dittoPlain GI sheet spouts fixed in position, including paint

09-23 100 Sft m2 15,498.70 343.57 3,193.00 1,667.66dittoLaying 1/2" thick deodar ceiling complete, including

sawing, planing & fixing

09-24-a 100 Sft m2 10,506.83 240.58 2,235.88 1,130.53Flat sheet roof with GI plain sheets, including batten rolls,

screws, clips etc : 22 BWG

09-24-b 100 Sft m2 9,602.68 240.58 2,235.88 1,033.25Flat sheet roof with GI plain sheets, including batten rolls,

screws, clips etc : 24 BWG

09-25 100 Sft m2 13,996.59 123.42 1,147.00 1,506.03Asbestos cement corrugated sheet roofing including

overlaps, GI hooks, bolts, nuts etc

09-26 100 Sft m2 189.10 20.35 189.10 20.35Extra labour for erection of GI sheets, flat sheet or asbestos

sheet roofing above 20' height

09-27 100 RFT m 7,595.56 47.29 1,441.50 249.20Fixing asbestos cement sheet ridges and valleys 1/4" thick

09-28-a 1 RFT m 358.72 173.64 52.93 1,176.89Plain GI sheet ridging including fixture complete 6" lap &

18" overall of 22 gauge GI sheet ridging

09-28-b 1 RFT m 351.19 173.64 52.93 1,152.20Plain GI sheet ridging including fixture complete 9" lap &

24" overall, of 24 gauge GI sheet ridging

09-28-c 1 RFT m 391.12 173.64 52.93 1,283.21Plain GI sheet ridging including fixture complete 12" lap &

30 overall, of 22 gauge GI sheet ridging

09-29 1 RFT m 170.03 86.82 26.46 557.83Plain 22 gauge GI sheet gutter semi circular 8" diameter

09-30 Each Each 217.00 217.00 217.00 217.00Fixing water spouse or parnala.

09-31 Each Each 1,174.08 868.00 868.00 1,174.08Making masonry ventilators in c/s mortar 1:4

09-32 1 RFT m 7.27 20.53 6.26 23.84Making drip course 2"x1/2" under RCC slab edges in outer

opening, in c/s mortar 1:2

09-33 100 Sft m2 14,027.29 187.79 1,745.30 1,509.34Supply and laying of twin GI sheet 20 SWG painted with

bitumen & polythene fim complete

09-34-a 1 Sft m2 64.58 142.29 13.22 694.84Provide & lay roof insulation complete with Thermopore

sheet 1/2" thick

Page 44 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 45: Rate nwfp 2008

Item Code Description

ROOFINGChapter #

:

09

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

09-34-b 1 Sft m2 77.22 142.29 13.22 830.91Provide & lay roof insulation complete with Thermopore

sheet 3/4" thick

09-34-c 1 Sft m2 89.32 142.29 13.22 961.11Provide & lay roof insulation complete with Thermopore

sheet 1" thick

09-35 1 RFT m 210.10 94.08 28.67 689.31Providing and fixing AC rain water down pipe 4" dia, with

shoe, tee, bend & clamp etc

09-36-a 1 RFT m 37.09 51.07 15.57 121.68Rate shall be increase

by 1.5 times for stone

masonry or PCC and

2 times for RCC

Making jharries in existing brick masonry For slabs upto 6"

thick

09-36-b 1 RFT m 45.08 138.25 42.14 147.90Making jharries in existing brick masonry For slabs

exceeding 6" to 12" thick

09-37-a Each Each 183.25 161.20 161.20 183.25dittoMaking recess in existing brick masonry a) upto 1.0' height

of girder or beam

09-37-b Each Each 78.10 65.88 65.88 78.10Making recess in existing brick masonry b) for every 6"

additional height or part thereof

09-38 Each Each 168.33 168.33 168.33 168.33Hoisting RS Beams & wooden beams and placing in

position

09-39 Each Each 28.64 28.64 28.64 28.64Hoisting and placing in position sahl ballies, over roof

09-40-a Each Each 23.96 23.96 23.96 23.96Hoist precast RCC/pre-stressed conc. battens a) From 5' to

6' long

09-40-b Each Each 35.65 35.65 35.65 35.65Hoist precast RCC/pre-stressed conc. battens b) Over 6' to

7' long

09-40-c Each Each 47.34 47.34 47.34 47.34Hoist precast RCC/pre-stressed conc. battens c) Over 7' to

8' long

09-40-d Each Each 57.04 57.04 57.04 57.04Hoist precast RCC/pre-stressed conc. battens d) Over 8' to

9' long

09-40-e Each Each 71.30 71.30 71.30 71.30Hoist precast RCC/pre-stressed conc. battens e) Exceeding

9' length

09-41-a Each Each 71.30 71.30 71.30 71.30Applicable only ot

roof troughs (inverted

tees and trough) for

heights of first storey

only

Hoisting and placing in position RCC troughs Upto 10' in

length

09-41-b Each Each 95.26 95.26 95.26 95.26Hoisting and placing in position RCC troughs Upto 11' in

length

09-41-c Each Each 118.64 118.64 118.64 118.64Hoisting and placing in position RCC troughs Upto 12' in

length

09-41-d Each Each 128.90 128.90 128.90 128.90Hoisting and placing in position RCC troughs Upto 13' in

length

09-41-e Each Each 142.60 142.60 142.60 142.60Hoisting and placing in position RCC troughs Upto 14' in

length

Page 45 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 46: Rate nwfp 2008

Item Code Description

ROOFINGChapter #

:

09

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

09-41-f Each Each 156.86 156.86 156.86 156.86Hoisting and placing in position RCC troughs Upto 15' in

length

09-41-g Each Each 178.25 178.25 178.25 178.25Hoisting and placing in position RCC troughs Upto 16' in

length

09-41-h Each Each 203.05 203.05 203.05 203.05Hoisting and placing in position RCC troughs Upto 17' in

length

09-41-i Each Each 237.86 237.86 237.86 237.86Hoisting and placing in position RCC troughs Upto 18' in

length

09-41-j Each Each 285.20 285.20 285.20 285.20Hoisting and placing in position RCC troughs Upto 19' in

length

09-41-k Each Each 356.50 356.50 356.50 356.50Hoisting and placing in position RCC troughs Upto 20' in

length

09-42-a Each Each 56.54 56.54 56.54 56.54Hoist & place in position RCC inverted battens Upto 10'

span

09-42-b Each Each 113.09 113.09 113.09 113.09Hoist & place in position RCC inverted battens Upto 12'

span

09-42-c Each Each 141.79 141.79 141.79 141.79Hoist & place in position RCC inverted battens Upto 13'

span

09-42-d Each Each 170.50 170.50 170.50 170.50Hoist & place in position RCC inverted battens Upto 14'

span

09-42-e Each Each 187.55 187.55 187.55 187.55Hoist & place in position RCC inverted battens Upto 15'

span

09-42-f Each Each 213.13 213.13 213.13 213.13Hoist & place in position RCC inverted battens Upto 16'

span

09-42-g Each Each 284.73 284.73 284.73 284.73Hoist & place in position RCC inverted battens Upto 18'

span

09-42-h Each Each 426.25 426.25 426.25 426.25Hoist & place in position RCC inverted battens Upto 20'

span

09-43 Each Each 492.26 303.80 303.80 492.26RCC spout including fixing in position, with top and

bottom khuras

09-44 100 Sft m2 27,309.69 299.27 2,781.37 2,938.52P/F Burnt Brick Tile Roofing over Tee Iron and Steel

Girder, in 1:6 c/s mortar (12' max span)

09-45 1 Sft m2 159.54 263.50 24.49 1,716.69Providing and Laying Prestressed Roof of Slab/Girder, 2"

thick PCC 1:2:4 with chicken mesh, polythene, mud, tar

Page 46 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 47: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-01 100 Sft m2 4,659.00 136.76 1,271.00 501.31Laying murum flooring complete as per specs

10-02 100 Sft m2 1,015.28 45.45 422.38 109.24Earth flooring 6" thick consolidated layer of moistened

earth, including ramming

10-03-a 100 Cft m3 2,136.36 588.29 1,665.85 754.45Provide, lay, water & ram clean coarse sand under floor /

brick paving, complete

10-03-b 100 Cft m3 6,344.60 1,177.07 3,333.09 2,240.58Provide, lay, water & ram brick ballast 1.5" to 2" guage

mixed with 25% sand for floor foundations

10-04 100 Sft m2 1,720.46 86.73 806.00 185.12Mud floor of 6" thick consolidated layer of moist earth &

finished off with 1" mud plaster

10-05 100 Sft m2 2,187.07 63.21 587.45 235.33Dry brick paving laid flat,sand grouted, including prep. of

bed, by 1/2" thick mud plaster

10-06 100 Sft m2 3,183.61 89.26 829.56 342.56Dry brick on edge paving, sand grouted, including prep. of

bed, by 1/2" thick mud plaster

10-07 100 Sft m2 942.67 61.71 573.50 101.43Grouting 4.5" dry brick work with cement sand mortar 1:5

10-08 100 Sft m2 3,190.09 107.57 999.75 343.25Flat brick flooring laid in 1:6 c/s mortar over a bed of 3/4"

thick cement mortar 1:6

10-09 100 Sft m2 4,410.36 138.43 1,286.50 474.55Brick on edge flooring, laid in 1:6 c/s mortar, over a bed of

3/4" thick cement mortar 1:6

10-10 100 Sft m2 2,940.83 107.57 999.75 316.43Brick tiles (12"x6"x2") laid in 1:6 c/s mortar, over a bed of

3/4" thick c/s mortar 1:6

10-11 100 Sft m2 3,619.27 123.42 1,147.00 389.43Brick tiles (9"x4.5"x1.5") laid flat in 1:3 c/s mortar over a

bed of 3/4" thick cement mortar 1:6

10-12 100 Sft m2 14,392.72 165.01 1,533.57 1,548.66Cement tiles (8"x8"x3/4") laid flat in 1:2 c/s mortar, over

3/4" thick bed of c/s mortar 1:2

10-13-a 100 Sft m2 7,858.72 165.01 1,533.57 845.60Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick

bed of c/s mortar 1:2 : 12" x 12" x 1"

10-13-b 100 Sft m2 6,827.80 165.01 1,533.57 734.67Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick

bed of c/s mortar 1:2 : 9" x 9" x 3/4"

10-13-c 100 Sft m2 6,842.32 165.01 1,533.57 736.23Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick

bed of c/s mortar 1:2 : 6" x 6" x 3/4"

10-14 100 Sft m2 7,132.72 165.01 1,533.57 767.48Coloured cement tile (8"x8"x3/4") of dark shade laid flat in

1:2 c/s mortar over 3/4" mortar bed

10-15-a 100 Sft m2 1,912.91 97.23 903.65 205.83If glass strips are used

for paneling, it shall

be paid extra as per

item No. 10-43

Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels : 1" thick

10-15-b 100 Sft m2 2,379.02 113.74 1,057.10 255.98Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels: 1.5" thick

10-15-c 100 Sft m2 2,551.33 113.74 1,057.10 274.52Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels: 1.5" thick

10-15-d 100 Sft m2 2,909.00 113.74 1,057.10 313.01Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels : 1.75" thick

Page 47 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 48: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-15-e 100 Sft m2 3,217.91 128.75 1,196.60 346.25Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels : 2" thick

10-15-f 100 Sft m2 4,049.52 186.79 1,736.00 435.73Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels: 2.25" thick

10-15-g 100 Sft m2 4,327.26 194.30 1,805.75 465.61Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels: 2.5" thick

10-15-h 100 Sft m2 4,899.76 233.49 2,170.00 527.21Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels: 2.75" thick

10-15-i 100 Sft m2 5,006.85 217.65 2,022.75 538.74Provide & lay topping of concrete 1:2:4, including surface

finishing & dividing in panels : 3" thick

10-16-a 100 Sft m2 3,229.95 205.14 1,906.50 347.54dittoProvide & laying conglomerate floor (two coat work) with

top layer of 1/2" thick wearing surface of one part of

cement 2 parts of stone chips passing 3/16" sieve over

bottom layer of cement concrete (1:3:6) including surface

finishing & dividing in panels: 1.5" thick

10-16-b 100 Sft m2 2,760.30 141.76 1,317.50 297.01Provide & laying conglomerate floor (two coat work) with

top layer of 1/2" thick wearing surface of one part of

cement 2 parts of stone chips passing 3/16" sieve over

bottom layer of cement concrete (1:3:6) including surface

finishing & dividing in panels: 1.75" thick

10-16-c 100 Sft m2 3,022.29 156.77 1,457.00 325.20Provide & laying conglomerate floor (two coat work) with

top layer of 1/2" thick wearing surface of one part of

cement 2 parts of stone chips passing 3/16" sieve over

bottom layer of cement concrete (1:3:6) including surface

finishing & dividing in panels : 2" thick

10-17 100 Sft m2 849.76 46.70 434.00 91.43Add extra in cement concrete floor topping if finished with

pigment and polishing

10-18 100 Sft m2 209.25 22.52 209.25 22.52Applicable to item No

10-08 to 10-16, 10-19

to 10-25 and 10-30 to

10-35

Extra labour for each storey above ground for mosaic,

conglomerate, tiles, stone & wood floor

10-19-a 100 Sft m2 3,910.17 280.36 2,605.55 420.73Flag stone flooring in lime mortar 1:2, over 3/4" bedding :

2" thick

10-19-b 100 Sft m2 3,960.37 261.44 2,429.78 426.14Flag stone flooring in lime mortar 1:2, over 3/4" bedding :

3" thick

10-20-a 100 Sft m2 7,318.92 91.73 852.50 787.52Asphalt floor, including base preparation, remelting, setting

out & finish : 1" thick topping

10-20-b 100 Sft m2 3,975.66 79.89 742.45 427.78Asphalt floor, including base preparation, remelting, setting

out & finish : 1/2" thick topping

10-20-c 100 Sft m2 2,139.59 56.00 520.49 230.22Asphalt floor, including base preparation, remelting, setting

out & finish : 1/4" thick topping

Page 48 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 49: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-21-a 100 Sft m2 5,946.40 366.92 3,410.00 639.83If glass strips are used

for paneling, it shall

be paid extra as per

item No. 10-43

1.375" thick mosaic flooring, including rubbing and

polishing complete : Using grey cement

10-21-b 100 Sft m2 5,664.35 366.92 3,410.00 609.481.375" thick mosaic flooring, including rubbing and

polishing complete : Using white cement

10-22-a 100 Sft m2 5,793.79 375.92 3,493.70 623.41ditto1.5" thick mosaic flooring, including rubbing & polishing

complete : Using grey cement

10-22-b 100 Sft m2 5,978.92 375.92 3,493.70 643.331.5" thick mosaic flooring, including rubbing & polishing

complete : Using white cement

10-23 100 Sft m2 5,393.92 206.31 1,917.35 580.39Laying floor of mosaic marble chips tiles of approved

shade including finishing complete

10-24 100 Sft m2 7,072.88 261.84 2,433.50 761.04Lay floor of white glazed tile 1/4" thick in white cement

1:2 over 3/4" thick cement mortar 1:2

10-25 100 Sft m2 7,095.15 261.84 2,433.50 763.44Lay floor of approved coloured glazed tiles 1/4" thick laid

in white cement & pigment complete

10-26-a 100 Sft m2 10,733.10 527.02 4,898.00 1,154.88Provide & lay marble fine dressed stone flooring on surface

in white cement complete: 3/4" thick (Badel, Silky black,

Sunny white, Sunny Grey or eq)

10-26-b 100 Sft m2 13,909.35 527.02 4,898.00 1,496.65Provide & lay marble fine dressed stone flooring on surface

in white cement complete: 1" thick (Badel, Silky black,

Sunny white, Sunny Grey or eq)

10-26-c 100 Sft m2 9,589.65 527.02 4,898.00 1,031.85Provide & lay marble fine dressed stone flooring on surface

in white cement complete: 1/2" thick (Badel, Silky black,

Sunny white, Sunny Grey or eq)

10-26-d 100 Sft m2 13,222.80 527.02 4,898.00 1,422.77Providing and Laying marble fine dressed stone 4-5 feet

and 12" wide 1" thick for stairs steps.

10-26-e 100 Sft m2 13,222.80 527.02 4,898.00 1,422.77Providing and Laying marble fine dressed stone 7x1.5 feet

and

1" thick for stairs steps.

10-26-f 100 Rft m 3,902.04 14.90 454.15 128.02Providing and fixing glazed tile colour printed border 2"

wide

10-26-g 100 Rft m 3,902.04 14.90 454.15 128.02Providing and fixing glazed tile colour printed border 3"

wide

10-26-h 100 Rft m 3,902.04 14.90 454.15 128.02Providing and fixing glazed tile colour printed border 4"

wide

10-27 100 Sft m2 2,475.85 261.84 2,433.50 266.40Reduce the rate by 35

% and 40 % for

labour and composite

rate respectively if

polishing is not done.

Rubbing and polishing old grit/mosaic floor, including

repairing voids, uneven surface, complete

Page 49 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 50: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-28 100 Sft m2 997.36 91.56 850.95 107.32Reduce the rate by 35

% and 40 % for

labour and composite

rate respectively if

polishing is not done.

Rubbing & polishing grit floor, including repairing voids,

uneen surface, complete

10-29 100 Sft m2 232.56 11.27 104.78 25.02Cleaning and washing mosaic or marble floor with caustic

soda mixture

10-30 100 Sft m2 28,503.04 783.87 7,285.00 3,066.93Shisham wood boarding or strip flooring 3/4" thick

including 2 coats of bitumen laid hot complete

10-31 100 Sft m2 38,336.09 560.38 5,208.00 4,124.96Deodar wood boarding or strip flooring 3/4" thick

including 2 coats of bitumen laid hot complete

10-32 100 Sft m2 39,106.29 783.87 7,285.00 4,207.84Teak wood boarding or strip flooring 1/2" thick including 2

coats of bitumen laid hot complete

10-33 100 Sft m2 24,480.02 560.38 5,208.00 2,634.05Shisham wood block flooring 1" thick out to required size,

fixed on a layer of bitumen base

10-34 100 Sft m2 58,802.31 783.87 7,285.00 6,327.13Teak wood block 1" thick cut to required size, fixed on a

layer of asphalt bitumen laid on base

10-35-a 100 Sft m2 13,958.29 216.81 2,015.00 1,501.91Laying wooden paving of hard wood on edge in coal tar &

asphalt : Shisham wood

10-35-b 100 Sft m2 9,873.93 216.81 2,015.00 1,062.43Laying wooden paving of hard wood on edge in coal tar &

asphalt : Kikar wood

10-36-a 100 Sft m2 8,185.77 180.02 1,673.07 880.79Tile skirting laid in 1:2 c/s mortar over 3/4" thick cement

mortar 1:2 complete : Cement tiles

10-36-b 100 Sft m2 10,897.31 209.31 1,945.25 1,172.55Tile skirting laid in 1:2 c/s mortar over 3/4" thick cement

mortar 1:2 complete : Mosaic tiles

10-37-a 100 Sft m2 2,576.21 213.38 1,983.07 277.20Provide grey cement skirting 3/8" thick complete 1:2

cement, sand mortar

10-37-b 100 Sft m2 2,473.97 213.38 1,983.07 266.20Provide grey cement skirting 3/8" thick complete 1:3

cement, sand mortar

10-37-c 100 Sft m2 821.23 16.68 155.00 88.36Provide grey cement skirting 3/8" thick complete Extra if

skirting or dado is finished with pigment

10-38-a 100 Sft m2 7,351.88 291.86 2,712.50 791.06Glazed tile 1/4" thick dado jointed in white cement

complete : White Plain tiles

10-38-b 100 Sft m2 7,264.76 291.86 2,712.50 781.69Glazed tile 1/4" thick dado jointed in white cement

complete : Coloured Plain tiles

10-38-c 100 Sft m2 7,351.88 291.86 2,712.50 791.06Glazed tile 1/4" thick dado jointed in white cement

complete : Printed tiles

10-39 100 Sft m2 7,472.88 291.86 2,712.50 804.08Glazed tile dado 1/4" thick in pigment over 1:2 c/s mortar

3/4" thick including finishing complete

10-40-a-01 100 Sft m2 5,128.37 373.59 3,472.00 551.81Mosaic dado or skirting complete as per specs Using grey

cement : 3/8" thick

10-40-a-02 100 Sft m2 5,513.88 373.59 3,472.00 593.29Mosaic dado or skirting complete as per specs Using grey

cement : 1/2" thick

Page 50 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 51: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-40-b-01 100 Sft m2 5,110.34 373.59 3,472.00 549.87Mosaic dado or skirting complete as per specs Using white

cement : 3/8" thick including grinding and polishing

10-40-b-02 100 Sft m2 5,572.56 373.59 3,472.00 599.61Mosaic dado or skirting complete as per specs Using white

cement : 1/2" thick including grinding and polishing

10-41-a 100 Sft m2 4,601.77 170.12 1,581.00 495.15Provide & lay marble fine dressed and polished stone dado

or skirting in white cement complete : 3/8" thick (Badel,

Silky black, Sunny white, Sunny Grey or eq)

10-41-b 100 Sft m2 5,691.98 170.12 1,581.00 612.46Provide & lay marble fine dressed and polished stone dado

or skirting in white cement complete : 1/2" thick (Badel,

Silky black, Sunny white, Sunny Grey or eq)

10-42 100 Sft m2 12,744.33 123.10 1,144.06 1,371.29The cost of base for

rubber floor is not

included in the rate

and is payable

separately

Rubber flooring, consisting of 12"x12"x1/8" rubber tiles

laid on firm foundation

10-43-a 100 Rft m 418.91 1.24 37.76 13.74Provide & fix glass strip 1.5" wide for dividing the floors

into panels : 5mm thick

10-43-b 100 Rft m 418.91 1.24 37.76 13.74Provide & fix glass strip 1.5" wide for dividing the floors

into panels : 3mm thick

10-43-c 100 Rft m 291.86 1.24 37.76 9.58Providing and Fixing marble strip 1.5 inch wide 3/8 inch

thick for dividing the floor into panels

10-43-d 100 Rft m 482.43 1.24 37.76 15.83Providing and Fixing marble strip 2" wide and 3/8" thick

for dividing the floor into panels

10-44 100 Sft m2 13,741.20 128.42 1,193.50 1,478.55P/F Vinyl Tiles or Vinyl Sheet flooring over firm

foundation

10-45 100 Sft m2 5,669.11 120.08 1,116.00 610.00P/F Precast Concrete 7000 psi TUFF Tiles over bed of 2"

thick sand & 4" thick brick ballast comp

10-46-a 100 Sft m2 11,396.01 250.17 2,325.00 1,226.21P/F Ceramic Floor Tiles (Emco, National or eq) Size : 12"

x 12"

10-46-b 100 Sft m2 17,446.01 250.17 2,325.00 1,877.19P/F Ceramic Floor Tiles (Emco, National or eq) Size 20" x

20"

10-47 100 Sft m2 3,733.73 138.43 1,286.50 401.75Burnt brick (1st class) pavement on edge grouted with sand

including preparation of bed

10-48-a 100 Sft m2 8,276.83 261.84 2,433.50 890.59Porceline tile floor 1/4" thick laid cement 1:2 or 3/4" thick

cement mortar 1:2 (Local Master Tiles)

10-48-b 100 Sft m2 10,454.83 261.84 2,433.50 1,124.94Porceline tile floor 1/4" thick laid cement 1:2 over 3/4"

thick cement mortar 1:2 (Imported Tiles)

10-48-c 100 Sft m2 20,013.83 261.84 2,433.50 2,153.49Granitto tile floor 1/4" thick laid cement 1:2 or 3/4" thick

cement mortar 1:2 (Imported Tiles UAE) 24"x24"

10-48-d 100 Sft m2 17,334.89 261.84 2,433.50 1,865.23Granitto tile floor 1/4" thick laid cement 1:2 or 3/4" thick

cement mortar 1:2 (Imported Tiles UAE) 16"x16"

Page 51 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 52: Rate nwfp 2008

Item Code Description

FLOORINGChapter #

:

10

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

10-49-a 100 Sft m2 28,440.35 306.88 2,852.00 3,060.18Providing and Laying marble fine dressed stone flooring

on surface in white cement complete using indian green

marble 12"x12"x3/4" thick

10-49-b 100 Sft m2 10,048.35 306.88 2,852.00 1,081.20Providing and Laying marble fine dressed stone flooring

on surface in white cement complete using Trevera marble

12"x12"x3/4" thick

10-49-c 100 Sft m2 12,105.35 306.88 2,852.00 1,302.54Providing and Laying marble fine dressed stone flooring

on surface in white cement complete using Botocina

marble 12"x12"x3/4" thick

10-49-d 100 Sft m2 11,500.35 306.88 2,852.00 1,237.44Providing and Laying marble fine dressed stone flooring

on surface in white cement complete using

Veroona/Lasbela marble 12"x12"x3/4" thick

10-50 100 Sft m2 1,616.75 60.04 558.00 173.96Chemical polishing of marble floor/Dado

10-51 1 Sft m2 106.40 233.49 21.70 1,144.86Replaced coloured glass panes of sizes upto 4 mm

thickness with iron, nails and putty including removing

broken ones if required in all floors.

Page 52 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 53: Rate nwfp 2008

Item Code Description

SURFACE RENDERINGChapter #

:

11

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

11-01-a 100 Sft m2 396.36 27.29 253.58 42.65Mud plaster on walls (excluding gobri leeping) upto 20'

height : 1/2" thick

11-01-b 100 Sft m2 632.14 37.29 346.58 68.02Mud plaster on walls (excluding gobri leeping) upto 20'

height : 1" thick

11-02-a 100 Sft m2 370.63 24.52 227.85 39.88Add extra 13%, 32%

and 51% above the

labour rates only or

6%, 15% and 23% on

composite rates for

2nd, 3rd, 4th and

subsequent floors

respectively.

Mud plaster on floor / roof (excluding gobri leeping) upto

20' height : 1/2" thick

11-02-b 100 Sft m2 714.60 46.16 429.04 76.89Mud plaster on floor / roof (excluding gobri leeping) upto

20' height : 1" thick

11-03-a 100 Sft m2 929.41 85.06 790.50 100.00Cement lime plaster 1:7:12 (c/l/s) upto 20' height 1/4" thick

11-03-b 100 Sft m2 1,068.56 85.06 790.50 114.98Cement lime plaster 1:7:12 (c/l/s) upto 20' height 1/2" thick

11-04-a 100 Sft m2 1,212.23 85.06 790.50 130.44Cement Neru plaster 1:2 (c/s) upto 20' height 1/4" thick

11-04-b 100 Sft m2 1,512.00 85.06 790.50 162.69Cement Neru plaster 1:2 (c/s) upto 20' height 1/2" thick

11-05 100 Sft m2 3,436.96 192.46 1,788.70 369.822" stucco cement plaster 1:2:4 (c/s/shingle) upto 20' height

11-06-a 100 Sft m2 1,761.14 62.61 581.87 189.50Provide/lay machine sprayed plaster 1/2" thick using

cement & zero guage chips : Ratio 1:1

11-06-b 100 Sft m2 1,681.14 63.21 587.45 180.89Provide/lay machine sprayed plaster 1/2" thick using

cement & zero guage chips : Ratio 1:1.5

11-06-c 100 Sft m2 1,649.94 64.51 599.54 177.53Provide/lay machine sprayed plaster 1/2" thick using

cement & zero guage chips : Ratio 1:2

11-07-a 100 Sft m2 1,250.66 85.06 790.50 134.57The rate be allowed

only on written orders

of Superintending

Engineer

Cement plaster 1:2, upto 20' height 3/8" thick

11-07-b 100 Sft m2 1,383.64 85.06 790.50 148.88Cement plaster 1:2, upto 20' height 1/2" thick

11-07-c 100 Sft m2 1,923.47 108.41 1,007.50 206.97Cement plaster 1:2, upto 20' height 3/4" thick

11-08-a 100 Sft m2 1,116.29 85.06 790.50 120.11dittoCement plaster 1:3 upto 20' height 3/8" thick

11-08-b 100 Sft m2 1,223.44 85.06 790.50 131.64Cement plaster 1:3 upto 20' height 1/2" thick

11-08-c 100 Sft m2 1,659.09 108.41 1,007.50 178.52Cement plaster 1:3 upto 20' height 3/4" thick

11-09-a 100 Sft m2 1,083.08 85.06 790.50 116.54Cement plaster 1:4 upto 20' height 3/8" thick

11-09-b 100 Sft m2 1,160.76 85.06 790.50 124.90Cement plaster 1:4 upto 20' height 1/2" thick

11-09-c 100 Sft m2 1,586.00 108.41 1,007.50 170.65Cement plaster 1:4 upto 20' height 3/4" thick

Page 53 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 54: Rate nwfp 2008

Item Code Description

SURFACE RENDERINGChapter #

:

11

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

11-10-a 100 Sft m2 1,360.82 108.41 1,007.50 146.42i) This item shall be

applicable to building

meant for human

habitation only, such

as building like

residence, offices,

educational

institutions and

hospitals etc. It shall

no admissible on

godowns, bins,

agricultural, poultry

etc.

Cement plaster 3/8" thick under soffit of RCC roof slabs

only upto 20' height : (1:2)

11-10-b 100 Sft m2 1,353.91 108.41 1,007.50 145.68ii) The thickness of

the plaster will not be

more than 3/8" thick.

Cement plaster 3/8" thick under soffit of RCC roof slabs

only upto 20' height : (1:3)

11-10-c 100 Sft m2 1,239.82 108.41 1,007.50 133.40Cement plaster 3/8" thick under soffit of RCC roof slabs

only upto 20' height : (1:4)

11-11-a 100 Sft m2 1,052.59 85.06 790.50 113.26Cement plaster 1:5, upto 20' height 3/8" thick

11-11-b 100 Sft m2 1,135.59 85.06 790.50 122.19Cement plaster 1:5, upto 20' height 1/2" thick

11-11-c 100 Sft m2 1,531.67 108.41 1,007.50 164.81Cement Plaster 1:5, upto 20' height 3/4" thick

11-12-a 100 Sft m2 1,009.03 85.06 790.50 108.57Cement plaster 1:6, upto 20' height 3/8" thick

11-12-b 100 Sft m2 1,078.96 85.06 790.50 116.10Cement plaster 1:6, upto 20' height 1/2" thick

11-12-c 100 Sft m2 1,440.20 108.41 1,007.50 154.97Cement plaster 1:6, upto 20' height 3/4" thick

11-13 100 Sft m2 718.00 58.04 539.40 77.26Applying floating coat of cement 1/32" thick

11-14 100 Sft m2 679.74 61.71 573.50 73.14Lime pointing flush upto 20' height, including racking

joints in lime sand mortar 1:2

11-15 100 Sft m2 1,043.99 100.90 937.75 112.33Lime pointing struck joints on walls, upto 20' height

including racking joints, in lime sand mortar 1:2

11-16-a 100 Sft m2 1,132.45 85.06 790.50 121.85Cement pointing flush, upto 20' height Ratio 1:2

11-16-b 100 Sft m2 1,056.70 85.06 790.50 113.70Cement pointing flush, upto 20' height Ratio 1:3

11-17-a 100 Sft m2 915.45 61.71 573.50 98.50Cement pointing 1:2 flush, on floor

11-18-a 100 Sft m2 1,279.70 100.90 937.75 137.70Cement pointing struck joints, on walls, upto 20' height :

Ratio 1:2

11-18-b 100 Sft m2 1,203.95 100.90 937.75 129.55Cement pointing struck joints, on walls, upto 20' height :

Ratio 1:3

11-19-a 100 Sft m2 933.77 85.89 798.25 100.47Pointing flush on stone work, upto 20' height in lime sand

mortar 1:2 (lime, sand)

11-19-b 100 Sft m2 1,064.45 85.89 798.25 114.53Pointing flush on stone work, upto 20' height in cement

sand mortar 1:3

11-19-c-01 100 Sft m2 1,662.27 164.28 1,526.75 178.86Pointing flush on stone work, upto 20' height On stone

work raised : in lime sand mortar 1:2

Page 54 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 55: Rate nwfp 2008

Item Code Description

SURFACE RENDERINGChapter #

:

11

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

11-19-c-02 100 Sft m2 1,792.95 164.28 1,526.75 192.92Pointing flush on stone work, upto 20' height On stone

work raised : in c/s mortar 1:3

11-20 100 Sft m2 348.75 37.53 348.75 37.53Racking and washing joints of stone masonry (old work)

11-21 100 Sft m2 209.25 22.52 209.25 22.52Racking and washing joints of brick masonry (old work)

11-22 100 Sft m2 125.34 9.34 86.80 13.49Priming coat of chalk under distemper

11-23-a-01 100 Sft m2 342.53 23.35 217.00 36.86Distempering New surface : One coat

11-23-a-02 100 Sft m2 371.18 23.35 217.00 39.94Distempering New surface : Two coats

11-23-a-03 100 Sft m2 390.71 23.35 217.00 42.04Distempering New surface : Three coats

11-23-b-01 100 Sft m2 141.96 6.54 60.76 15.27Distempering Old surface : One coat

11-23-b-02 100 Sft m2 190.80 9.34 86.80 20.53Distempering Old surface : Two coats

11-24-a-01 100 Sft m2 75.54 5.00 46.50 8.13Colour washing: New surface : One coat

11-24-a-02 100 Sft m2 166.90 12.84 119.35 17.96Colour washing: New surface : Two coats

11-24-b-01 100 Sft m2 74.96 5.67 52.70 8.07Colour washing: Old surface : One coat

11-24-b-02 100 Sft m2 127.94 9.87 91.76 13.77Colour washing: Old surface : Two coats

11-25-a-01 100 Sft m2 53.56 4.67 43.40 5.76White washing: New surface : One coat

11-25-a-02 100 Sft m2 137.08 13.11 121.83 14.75White washing: New surface : Two coats

11-25-a-03 100 Sft m2 179.89 16.78 155.93 19.36White washing: New surface : Three coats

11-25-b-01 100 Sft m2 71.16 5.67 52.70 7.66White washing: Old surface : One coat

11-25-b-02 100 Sft m2 104.59 9.87 91.76 11.25White washing: Old surface : Two coats

11-26-a 100 Sft m2 95.59 9.41 87.42 10.29Gobri leeping: On walls

11-26-b 100 Sft m2 105.39 9.41 87.42 11.34Gobri leeping: Over roofs

11-27 100 Sft m2 206.15 22.18 206.15 22.18Payable with fresh

masonry when the

face of the work is

not to be

plastered/pointed.

Striking joints of burnt brick in lime or cement mortar

11-28 100 Sft m2 140.43 15.11 140.43 15.11Extra for lime, mud or cement plaster & pointing from 20'

& above for each additional 10' height

11-29 100 Sft m2 588.26 31.69 294.50 63.30Caulking joints of sleeper wall, with sand and coaltar

11-30 100 Sft m2 375.57 31.69 294.50 40.41Caulking joints of sleepers, with mud and chopped straw

11-31 100 Sft m2 221.95 5.00 46.50 23.88Extra cost of labour & material for red oxide pigment in

cement pointing to match bricks

11-32-a 100 Sft m2 1,050.10 75.88 705.25 112.99Provide grooved c/s plaster 1:3 over existing plastered &

roughened surface 3/8" thick

11-32-b 100 Sft m2 1,137.46 75.88 705.25 122.39Provide grooved c/s plaster 1:3 over existing plastered &

roughened surface 1/2" thick

11-32-c 100 Sft m2 6,382.92 564.55 5,246.75 686.80Providing ornamental plaster 3/4" thick with (1:3) cement

sand mortar on walls, columns chajja and slabs finished

smooth including all charges for Labour and Material.

Page 55 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 56: Rate nwfp 2008

Item Code Description

SURFACE RENDERINGChapter #

:

11

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

11-32-d 100 Sft m2 6,688.56 509.18 4,732.15 719.69Providing ornamental moulding of approved design in

column with base/top and nosing and shade of lintle or

pediments in cement mortar(1:3) 1-1/8" thick(1 feet under

coat x 1/8" finish layer) including all charges for

curing/finishing complete

11-33 1 RFT m 18.81 13.89 4.23 61.70Provide & fit expanded metal edge bead for corners, with

nails on both sides of edges

11-34-a Each Each 317.90 136.40 136.40 317.90Petty repairs to Fire Place

11-34-b Each Each 401.00 195.30 195.30 401.00Petty repairs to Verandah

11-34-c Each Each 438.90 136.40 136.40 438.90Petty repairs to Room upto 100 sft area

11-34-d Each Each 648.25 224.75 224.75 648.25Petty repairs to Room exceeding 100 sft area

11-35 m3 / coat m3 / coat 0.93 0.93 0.93 0.93The will be taken

from the floor, roof or

ground underneath as

the case may be, on

the side towards

which the work is to

be done

Extra labour for white washing, priming etc. from 20'

height & above for every extra 10' height

11-36 100 Sft m2 8,016.65 216.81 2,015.00 862.59Providing and fixing of clad stones over 1/2" c/s mortar 1:1

incl curing etc.

11-37 100 Sft m2 11,461.87 130.92 1,216.75 1,233.30The rate of plastering

over walls is not

included in this rate

and is to be paid

separately.

Supply & apply acrylic wall coating 10 to 12mm thick of

approved quality over plastered surface

11-38 100 Sft m2 12,078.37 272.69 2,534.25 1,299.63P/F Ceramic Exterior Finish Tiles over 1/2" cement sand

mortar 1:1 including curing complete

11-39-a 100 Sft m2 5,606.05 218.48 2,030.50 603.21Providing and fixing Chakwal tiles red colour in 1:3

cement mortar complete.

11-39-b 100 Sft m2 6,090.05 218.48 2,030.50 655.29Providing and fixing Chakwal tiles white colour in 1:3

cement mortar complete.

Page 56 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 57: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-01-a Cft m3 3,172.66 12,863.38 364.25 112,041.54Plain wood work sawn, wrought, planed & fixed in

position, including nails & screws : Deodar wood

12-01-b Cft m3 1,771.11 18,063.47 511.50 62,546.22Plain wood work sawn, wrought, planed & fixed in

position, including nails & screws : Shisham wood

12-02-a Cft m3 3,047.12 9,327.32 264.12 107,608.13Plain woodwork for regulation karries or needles etc.

complete as per specs : Deodar wood

12-02-b Cft m3 1,657.35 14,943.42 423.15 58,528.82Plain woodwork for regulation karries or needles etc.

complete as per specs : Shisham wood

12-03-a 1 Sft m2 1,145.97 1,465.28 136.18 12,330.621st class teak wood wrought joinery in doors & windows,

panelled or glazed complete : 2" thick

12-03-b 1 Sft m2 1,070.34 1,465.28 136.18 11,516.891st class teak wood wrought joinery in doors & windows,

panelled or glazed complete : 1.75" thick

12-03-c 1 Sft m2 994.71 1,465.28 136.18 10,703.101st class teak wood wrought joinery in doors & windows,

panelled or glazed complete : 1.5" thick

12-04-a-01 1 Sft m2 601.51 909.71 84.55 6,472.28a) This also includes

the cost of woods

required for extra

thickness of

chowkats.

1st class teak wood wrought joinery Teak wood frame

1.75" thick w/o spring/hinge

12-04-a-02 1 Sft m2 613.51 909.71 84.55 6,601.401st class teak wood wrought joinery Teak wood frame

1.75" thick w/o spring/hinge

12-04-b-01 1 Sft m2 522.78 909.71 84.55 5,625.091st Class Teak Wood Wrought Joinery : Teak Wood

framing 1.5" thick w/ wire guaze w/o springs

12-04-b-02 1 Sft m2 536.51 909.71 84.55 5,772.881st Class Teak Wood wrought joinery : Teak Wood

framing 1.5" thick w/ wire guaze w/ springs

12-04-c 1 Sft m2 189.79 326.61 30.35 2,042.161st class teak wood wrought joinery GI wire guaze 22

SWG, fixed to chowkat

12-04-d 1 Sft m2 445.04 489.92 45.53 4,788.661st class teak wood wrought joinery GI wire guaze 22

SWG, fixed on teak wood frame

12-05 1 Sft m2 189.79 326.61 30.35 2,042.16Provide & fix exp. metal 1/2"-3/4" mesh, 16 guage fixed to

chowkat, with 1" teak wood cover strips

12-06 1 Sft m2 189.79 326.61 30.35 2,042.16Provide & fix expanded metal 1/2" to 3/4", 16 guage fixed

to chowkat with 1" cover moulding

12-07-a 1 Sft m2 724.33 899.42 83.59 7,793.83First class deodar wood wrought joinery in doors and

windows etc. complete : 2" thick

12-07-b 1 Sft m2 637.91 899.42 83.59 6,863.86First class deodar wood wrought joinery in doors and

windows etc. complete : 1-3/4" thick

12-07-c 1 Sft m2 601.39 729.66 67.81 6,470.91First class deodar wood wrought joinery in doors and

windows etc. complete : 1.5" thick

12-08-a 1 Sft m2 733.84 1,047.01 97.31 7,896.15Deodar wood framed, braced & battened doors & windows

: 2.25" thick, 1.25" battens & 1" planks

12-08-b 1 Sft m2 600.24 803.97 74.72 6,458.58Deodar wood framed, braced & battened doors & windows

: 1.75" thick, 1" battens & 3/4" planks

Page 57 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 58: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-09 1 Sft m2 445.69 602.97 56.04 4,795.621" thick battened doors & windows fitted in position,

complete with iron fittings

12-10 1 Sft m2 733.32 897.44 83.40 7,890.51Deodar wood battened ledged & braced doors & windows

2.25" thick complete

12-11-a 1 Sft m2 315.91 416.95 38.75 3,399.15Deodar wood doors framed with braces & 22 SWG GI

sheet facing on one side complete

12-11-b 1 Sft m2 320.54 416.95 38.75 3,449.02Deodar wood doors framed with braces & 22 SWG GI

sheet facing on both sides complete

12-12-a 1 Sft m2 204.13 294.47 27.37 2,196.43Partal wood doors framed with braces & 22 SWG GI sheet

facing on one side complete

12-12-b 1 Sft m2 155.38 416.95 38.75 1,671.89Partal wood doors framed with braces & 22 SWG GI sheet

facing on both sides complete

12-13-a-01 1 Sft m2 373.71 770.66 71.62 4,021.08First class deodar wood wrought joinery work Deodar

wood frame 1-3/4" thick w/o springs

12-13-a-02 1 Sft m2 387.56 770.66 71.62 4,170.16First class deodar wood wrought joinery work Deodar

wood frame 13/4" thick with springs

12-13-b-01 1 Sft m2 337.72 770.66 71.62 3,633.88First class deodar wood wrought joinery work Deodar

wood frame 1.5" thick w/o springs

12-13-b-02 1 Sft m2 351.58 770.66 71.62 3,782.95First class deodar wood wrought joinery work Deodar

wood frame 1" thick with springs

12-13-c 1 Sft m2 131.04 326.61 30.35 1,409.95First class deodar wood wrought joinery work GI wire

guaze fixed to chowkat with 3/4" strip

12-13-d 1 Sft m2 114.90 326.61 30.35 1,236.36First class deodar wood wrought joinery work GI wire

guaze fixed to chowkat with 1/2" strip

12-14 1 Sft m2 391.72 694.92 64.58 4,214.89Making and fixing trellis doors & windows of deodar wood

complete.

12-15-a 1 Sft m2 100.54 222.21 20.65 1,081.79Provide & fix MS chowkat of doors, windows etc MS

angle iron 1.5"x1.5"x1/4" welded with MS flat

12-15-b 1 Sft m2 107.31 223.39 20.76 1,154.60Provide & fix MS chowkat of doors, windows etc MS tee

iron 1.5"x 1.5"x 1/4" welded with MS flat

12-16 1 Sft m2 61.65 222.37 20.67 663.30Extra for providing & fixing iron double spring hinges with

brass fittings including finger plate etc

12-17-a Each Each 219.82 43.40 43.40 219.82P/F brass spring hinges to wire gauzed door.

12-17-b Each Each 755.40 89.90 89.90 755.40P/F hydraulic Door Closer (Best Quality)

12-18-a-01 Each Each 140.27 43.71 43.71 140.27Providing and fixing sliding bolt to doors Iron sliding bolts

: 10" long

12-18-a-02 Each Each 194.72 43.71 43.71 194.72Providing and fixing sliding bolt to doors Iron sliding bolts

: 12" long

12-18-b-01 Each Each 791.08 361.77 361.77 791.08Providing and fixing sliding bolt to doors CP sliding bolts :

10" long

12-18-b-02 Each Each 533.52 43.71 43.71 533.52Providing and fixing sliding bolt to doors CP sliding bolts :

12" long

Page 58 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 59: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-18-c-01 Each Each 594.02 43.71 43.71 594.02Providing and fixing sliding bolt to doors Brass sliding

bolts : 10" long

12-18-c-02 Each Each 654.52 43.71 43.71 654.52Providing and fixing sliding bolt to doors Brass sliding

bolts : 12" long

12-19-a 1 Sft m2 8.66 10.42 0.97 93.18Extra for brass fittings to doors & windows Deodar

panelled, panelled+glazed or fully glazed

12-19-b 1 Sft m2 8.31 11.28 1.05 89.45Extra for brass fittings to doors & windows Deodar wood

wire guazed shutters

12-20-a-01 Each Each 913.55 187.55 187.55 913.55Extra for providing/fixing approved quality Rim locks :

Imported

12-20-a-02 Each Each 611.05 187.55 187.55 611.05Extra for providing/fixing approved quality Rim locks :

Local

12-20-b-01 Each Each 737.65 132.65 132.65 737.65Extra for providing/fixing approved quality Rim locks :

Imported

12-20-b-02 Each Each 495.65 132.65 132.65 495.65Extra for providing/fixing approved quality Rim locks :

Local

12-21-a 1 Sft m2 183.92 163.31 15.18 1,979.02Provide & fix exp. metal 1/2"-3/4"mesh 16 gauge Fixed to

chowkat with 1" deodar wood strip etc

12-21-b 1 Sft m2 282.26 133.42 12.40 3,037.12Provide & fix exp. metal 1/2"-3/4"mesh 16 gauge Fixed

with 1" cover mould & screws including frame

12-22-a 1 Sft m2 954.76 1,468.20 136.45 10,273.21Provide & fix deodar wood almirah 9"-12" depth including

boxing with back, shelves, shutters etc

12-22-b 1 Sft m2 539.58 1,045.53 97.17 5,805.91Provide & fix deodar wood almirah 9"-12" depth With

shelves, shutters etc w/o boxing & back

12-23-a 1 Sft m2 608.06 1,570.80 145.99 6,542.75Provide & fix wooden box type wardrobe 22" deep Partal

wood boxing & deodar wood shelves etc

12-23-b 1 Sft m2 687.93 1,570.80 145.99 7,402.09Provide & fix wooden box type wardrobe 22" deep Deodar

wood boxing & deodar shelves etc

12-24-a 1 Sft m2 297.09 279.95 26.02 3,196.69Provide & fix chowkat for doors, windows & CS windows,

including holdfast etc : Teak wood

12-24-b 1 Sft m2 102.44 223.37 20.76 1,102.30Provide & fix chowkat for doors, windows & CS windows,

including holdfast etc : Shisham wood

12-24-c 1 Sft m2 183.61 139.98 13.01 1,975.62Provide & fix chowkat for doors, windows & CS windows,

including holdfast etc : Deodar wood

12-25-a 100 Sft m2 26,475.85 283.53 2,635.00 2,848.80Make & fix deodar planking in eave boards etc planed on

both sides complete : 1" thick

12-25-b 100 Sft m2 20,716.21 283.53 2,635.00 2,229.06Make & fix deodar planking in eave boards etc planed on

both sides complete : 3/4" thick

12-25-c 100 Sft m2 14,980.81 283.53 2,635.00 1,611.94Make & fix deodar planking in eave boards etc planed on

both sides complete : 1/2" thick

12-26-a 100 Sft m2 26,366.91 283.53 2,635.00 2,837.08Make & fix deodar wood shelves, incl brackets 1" thick

12-26-b 100 Sft m2 37,872.98 283.53 2,635.00 4,075.13Make & fix deodar wood shelves, incl brackets 1.5" thick

Page 59 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 60: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-26-c 100 Sft m2 49,379.05 283.53 2,635.00 5,313.19Make & fix deodar wood shelves, incl brackets 2" thick

12-27-a 1 No each 85.09 36.42 36.42 85.09Make & fix cleats for doors & windows including hinges

and screws.

12-27-b 1 No no 83.25 36.42 36.42 83.25Make & fix cleats with brass hooks for roof ventilators

12-27-c Each Each 100.35 21.70 21.70 100.35Make & fix Door stops of 1.5" dia rubber block

12-27-d Each Each 56.29 26.04 26.04 56.29Make & fix GI hook with clamps for doors

12-28-a 1 RFT m 898.83 409.47 124.81 2,948.93Teak wood railing of any shape & design including bends,

corners, polishing etc complete

12-28-b 1 RFT m 412.16 409.47 124.81 1,352.23Shisham wood railing of any shape & design including

bends, corners, polishing etc complete

12-29 1 RFT m 242.60 167.51 51.06 795.93Deodar wood dado or picture rail 3"x1.5" as per approved

design, including moulding etc. complete

12-30-a 100 Sft m2 837.00 90.06 837.00 90.06Sawing wood by hand : Soft wood (deodar, kail or chir)

12-30-b 100 Sft m2 1,674.00 180.12 1,674.00 180.12Sawing wood by hand : Hard wood (shisham, kikar, teak or

sahl)

12-31-a 100 Sft m2 452.14 48.65 452.14 48.65Sawing wood by machine : Soft Wood

12-31-b 100 Sft m2 488.28 52.54 488.28 52.54Sawing wood by machine : Hard Wood

12-32 100 Sft m2 32,138.51 361.91 3,363.50 3,458.10Making and fixing sun-shade of deodar wood including

fixing brackets

12-33 1 SFT m2 112.73 435.48 40.47 1,212.99Making and fixing 1" thick kail or chir wooden notice

board with frame

12-34 Each Each 6,339.46 307.61 307.61 6,339.46Making deodar punkha pole 10'x6"x6"

12-35 1 RFT m 14.47 47.46 14.47 47.46Dismantling and refixing eave boards

12-36 1 RFT m 1,862.59 478.02 145.70 6,110.85Wooden stair-cases complete 2'-3' wide frame 1.5" thick

planks of deodar wood including hand rails

12-37-a-01 100 Sft m2 5,897.36 93.40 868.00 634.56Providing and fixing partition including framework : Sheet

on one side of frame : Hard board

12-37-a-02 100 Sft m2 6,230.11 93.40 868.00 670.36Providing and fixing partition including framework : Sheet

on one side of frame : Ply wood 1/4" thick

12-37-a-03 100 Sft m2 8,745.10 93.40 868.00 940.97Providing and fixing partition including framework : Sheet

on one side of frame : Masonite

12-37-b-01 100 Sft m2 7,431.72 171.78 1,596.50 799.65Providing and fixing partition including framework :

Sheets on both sides of frame : Hard board

12-37-b-02 100 Sft m2 8,056.08 171.78 1,596.50 866.83Providing and fixing partition including framework :

Sheets on both sides of frame : Ply wood 1/4"

12-37-b-03 100 Sft m2 12,668.00 171.78 1,596.50 1,363.08Providing and fixing partition including framework :

Sheets on both sides of frame : Masonite

12-38-a 100 Sft m2 7,323.36 246.83 2,294.00 787.99Providing and fixing ceiling, including frame work : Hard

board

12-38-b 100 Sft m2 9,747.60 246.83 2,294.00 1,048.84Providing and fixing ceiling, including frame work : Chip

Board

Page 60 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 61: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-38-c 100 Sft m2 7,621.63 246.83 2,294.00 820.09Providing and fixing ceiling, including frame work : Ply

wood 1/4" thick

12-38-d 100 Sft m2 10,715.60 246.83 2,294.00 1,153.00Providing and fixing ceiling, including frame work :

Masonite

12-39-a-01 100 Sft m2 12,390.05 186.79 1,736.00 1,333.17Provide & fix, thermorpore false ceiling complete Deodar

wood frame panelling : 3/4" thick

12-39-a-02 100 Sft m2 14,350.25 186.79 1,736.00 1,544.09Provide & fix, thermorpore false ceiling complete Deodar

wood frame panelling : 1" thick

12-39-b-01 100 Sft m2 8,572.50 186.79 1,736.00 922.40Provide & fix, thermorpore false ceiling complete Partal

wood frame panelling : 3/4" thick

12-39-b-02 100 Sft m2 9,398.33 186.79 1,736.00 1,011.26Provide & fix, thermorpore false ceiling complete Partal

wood frame panelling : 1" thick

12-40 100 Sft m2 29,660.59 155.44 1,444.60 3,191.48Supply and Fixing accoustic miller fibre tile ceiling fixed

with aluminium tee hung by GI wire fixed in roof

12-41-a Each Each 364.25 364.25 364.25 364.25Fixing Door including chowkats

12-41-b Each Each 182.13 182.13 182.13 182.13Fixing Windows including chowkats

12-42-a 1 Sft m2 40.97 148.91 13.84 440.85Glazing with panes (16-18 oz) including cost of putty

12-42-b 1 Sft m2 62.07 208.48 19.38 667.82Glazing with panes (16-18 oz) using deodar wooden fillets

& putty

12-42-c 1 Sft m2 62.07 208.48 19.38 667.82Glazing with panes (24-26 oz) using putty & deodar

wooden fillets

12-43-a 100 Sft m2 390.38 20.85 193.75 42.00Cutting to required size & fixing glass panes with putty.

12-43-b 1 Sft m2 15.64 40.30 3.75 168.30Cutting to required size & fixing glass panes Using deodar

wood fillets & putty

12-44-a 1 Sft m2 102.77 251.93 23.41 1,105.85Glazing with plate glass 6 mm thick including cost of

deodar wood fillet & putty : Upto 0.75 m2

12-44-b 1 Sft m2 101.87 251.92 23.41 1,096.08Glazing with plate glass 6 mm thick including cost of

deodar wood fillet & putty : 0.75m2 to 2.25 m2

12-45-a 1 Sft m2 609.05 1,119.88 104.08 6,553.341.5" thick deodar doors & windows, chowkat of MS angle

iron 1.5"x1.5"x1/4" welded with MS flat

12-45-b 1 Sft m2 590.47 1,232.95 114.59 6,353.491.5" thick deodar doors & windows, chowkat of MS tee

iron 1.5"x 1.5"x 1/4" welded with MS flat

12-46-a 1 Sft m2 471.92 952.63 88.53 5,077.811.5" thick hollow flush door/window, chowkat of MS angle

iron 1.5"x1.5"x1/4" welded with MS flat

12-46-b 1 Sft m2 432.50 941.78 87.53 4,653.751.5" thick hollow flush door/window, chowkat of MS tee

iron 1.5"x 1.5"x 1/4" welded with MS flat

12-47 1 Sft m2 445.52 1,573.06 146.20 4,793.83Panelled door of MS sheet with forged door leaves of MS

sheet 22 SWG etc complete

12-48 1 RFT m 34.97 75.50 23.01 114.7224 SWG aluminium kick plate 4" high, on bottom rail of

flush doors of commercial ply

12-49 1 RFT m 100.52 75.02 22.87 329.80Curtain railing to doors & windows comprising TOSO-elite

Japanese railing or equiv. including paint

Page 61 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 62: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-50 1 Sft m2 166.45 248.79 23.12 1,790.98MS flat 1/2"x1/8" grill in windows of approved design

including painting 3 coats, complete

12-51 1 Sft m2 140.67 345.65 32.12 1,513.62Provide & fix GI wire gauze 22 SWG, 12x12 mesh per sq.

in, fixed to steel window complete

12-52-a 1 Sft m2 416.17 188.52 17.52 4,478.04Hollow flush door 1.5"-2" thick including iron mongery

excluding chowkat & lock : Teak veneered

12-52-b 1 Sft m2 384.71 188.52 17.52 4,139.53Hollow flush door 1.5"-2" thick including iron mongery

excluding chowkat & lock : Shisham veneered

12-52-c 1 Sft m2 404.04 188.32 17.50 4,347.43Hollow flush door 1.5"-2" thick including iron mongery

excluding chowkat & lock : Deodar veneered

12-52-d 1 Sft m2 367.76 188.53 17.52 3,957.06Hollow flush door 1.5"-2" thick including iron mongery

excluding chowkat & lock : Commercial veneered

12-53-a-01 1 Sft m2 283.43 315.58 29.33 3,049.70Supply and Fixing aluminium door/window, Economy

model Sliding window

12-53-a-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Economy

model Hinges window

12-53-a-03 1 Sft m2 470.87 315.58 29.33 5,066.56Supply and Fixing aluminium door/window, Economy

model Fixed louver in door frame

12-53-a-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium door/window, Economy

model Fixed louver in 2" frame

12-53-b-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Deluxe 3"

sect. Sliding window

12-53-b-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Deluxe 3"

sect. Hinges window

12-53-b-03 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium door/window, Deluxe 3"

sect. Fixed glazing

12-53-b-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium door/window, Deluxe 3"

sect. Fixed arch

12-53-b-05 1 Sft m2 410.37 315.58 29.33 4,415.63Supply and Fixing aluminium door/window, Deluxe 3"

sect. Fixed louvers

12-53-b-06 1 Sft m2 443.70 315.58 29.33 4,774.23Supply and Fixing aluminium door/window, Deluxe 3"

sect. Sliding door

12-53-b-07 1 Sft m2 423.67 315.58 29.33 4,558.65Supply and Fixing aluminium door/window, Deluxe 3"

sect. Swing door single action (short handle)

12-53-b-08 1 Sft m2 434.47 315.58 29.33 4,674.85Supply and Fixing aluminium door/window, Deluxe 3"

sect. Swing door single action (long handle)

12-53-b-09 1 Sft m2 423.67 315.58 29.33 4,558.65Supply and Fixing aluminium door/window, Deluxe 3"

sect. Swing door double action (short handle)

12-53-b-10 1 Sft m2 396.49 315.58 29.33 4,266.27Supply and Fixing aluminium door/window, Deluxe 3"

sect. Swing door double action (short handle)

12-53-c-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Sliding window

Page 62 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 63: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-53-c-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Hinges window

12-53-c-03 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Fixed glazing

12-53-c-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Fixed arch

12-53-c-05 1 Sft m2 443.68 315.58 29.33 4,774.01Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Sliding door

12-53-c-06 1 Sft m2 410.37 315.58 29.33 4,415.63Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Swing door single action (short handle)

12-53-c-07 1 Sft m2 423.58 315.58 29.33 4,557.69Supply and Fixing aluminium door/window, Deluxe 3.5"

sect. Swing door single action (long handle)

12-53-d-01 1 Sft m2 474.56 315.58 29.33 5,106.21Supply and Fixing aluminium door/window, Premium 4"

sect. Sliding window

12-53-d-02 1 Sft m2 467.47 315.58 29.33 5,029.98Supply and Fixing aluminium door/window, Premium 4"

sect. Hinges window

12-53-d-03 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium door/window, Premium 4"

sect. Fixed glazing

12-53-d-04 1 Sft m2 391.12 315.58 29.33 4,208.45Supply and Fixing aluminium door/window, Premium 4"

sect. Fixed arch

12-53-d-05 1 Sft m2 485.20 315.58 29.33 5,220.72Supply and Fixing aluminium door/window, Premium 4"

sect. Sliding door

12-53-d-06 1 Sft m2 410.37 315.58 29.33 4,415.63Supply and Fixing aluminium door/window, Premium 4"

sect. Swing door single action (short handle)

12-53-d-07 1 Sft m2 423.67 315.58 29.33 4,558.65Supply and Fixing aluminium door/window, Premium 4"

sect. Swing door single action (long handle)

12-53-d-08 1 Sft m2 580.82 315.58 29.33 6,249.66Supply and Fixing aluminium door/window, Premium 4"

sect. Swing door double action (short handle)

12-53-d-09 1 Sft m2 594.41 315.58 29.33 6,395.87Supply and Fixing aluminium door/window, Premium 4"

sect. Swing door double action (long handle)

12-53-e-01 1 Sft m2 308.70 66.71 6.20 3,321.61Supply and Fixing aluminium door/window. Other items :

Fly screen shutter for Deluxe model

12-53-e-02 1 Sft m2 272.40 66.71 6.20 2,931.02Supply and Fixing aluminium door/window. Other items :

Fly screen shutter for Premium model

12-53-e-03 1 Sft m2 369.20 66.71 6.20 3,972.59Supply and Fixing aluminium door/window. Other items :

Fly screen shutter with separate outer frame

12-54-a-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Economy

model Sliding window

12-54-a-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Economy

model Hinges window

12-54-a-03 1 Sft m2 505.46 315.58 29.33 5,438.73Supply and Fixing aluminium bronze/black. Economy

model Fixed louver in door frame

Page 63 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 64: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-54-a-04 1 Sft m2 505.46 315.58 29.33 5,438.73Supply and Fixing aluminium bronze/black. Economy

model Fixed louver in 2" frame

12-54-b-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Sliding window

12-54-b-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Hinges window

12-54-b-03 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Fixed glazing

12-54-b-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Fixed arch

12-54-b-05 1 Sft m2 505.46 315.58 29.33 5,438.73Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Fixed louvers

12-54-b-06 1 Sft m2 478.29 315.58 29.33 5,146.35Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Sliding door

12-54-b-07 1 Sft m2 444.96 315.58 29.33 4,787.75Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Swing door single action (short handle)

12-54-b-08 1 Sft m2 396.49 315.58 29.33 4,266.27Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Swing door single action (long handle)

12-54-b-09 1 Sft m2 620.50 315.58 29.33 6,676.60Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Swing door double action (short handle)

12-54-b-10 1 Sft m2 581.76 315.58 29.33 6,259.78Supply and Fixing aluminium bronze/black. Deluxe 3"

sect. Swing door double action (long handle)

12-54-c-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Sliding window

12-54-c-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Hinges window

12-54-c-03 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Fixed glazing

12-54-c-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Fixed arch

12-54-c-05 1 Sft m2 478.29 315.58 29.33 5,146.35Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Sliding door

12-54-c-06 1 Sft m2 444.96 315.58 29.33 4,787.75Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Swing door single action (short handle)

12-54-c-07 1 Sft m2 423.67 315.58 29.33 4,558.65Supply and Fixing aluminium bronze/black. Deluxe 3.5"

sect. Swing door single action (long handle)

12-54-d-01 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Premium 4"

sect. Sliding window

12-54-d-02 1 Sft m2 416.53 315.58 29.33 4,481.85Supply and Fixing aluminium bronze/black. Premium 4"

sect. Hinges window

12-54-d-03 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Premium 4"

sect. Fixed glazing

Page 64 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 65: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-54-d-04 1 Sft m2 356.03 315.58 29.33 3,830.87Supply and Fixing aluminium bronze/black. Premium 4"

sect. Fixed arch

12-54-d-05 1 Sft m2 478.29 315.58 29.33 5,146.35Supply and Fixing aluminium bronze/black. Premium 4"

sect. Sliding door

12-54-d-06 1 Sft m2 444.96 315.58 29.33 4,787.75Supply and Fixing aluminium bronze/black. Premium 4"

sect. Swing door single action (short handle)

12-54-d-07 1 Sft m2 423.67 315.58 29.33 4,558.65Supply and Fixing aluminium bronze/black. Premium 4"

sect. Swing door single action (long handle)

12-54-d-08 1 Sft m2 615.41 315.58 29.33 6,621.78Supply and Fixing aluminium bronze/black. Premium 4"

sect. Swing door double action (short handle)

12-54-d-09 1 Sft m2 594.12 315.58 29.33 6,392.68Supply and Fixing aluminium bronze/black. Premium 4"

sect. Swing door double action (long handle)

12-54-e-01 1 Sft m2 308.70 66.71 6.20 3,321.61Supply and Fixing aluminium bronze/black. Other items :

Fly screen shutter for Deluxe model

12-54-e-02 1 Sft m2 272.40 66.71 6.20 2,931.02Supply and Fixing aluminium bronze/black. Other items :

Fly screen shutter for Premium model

12-54-e-03 1 Sft m2 248.20 66.71 6.20 2,670.63Supply and Fixing aluminium bronze/black. Other items :

Fly screen shutter with separate outer frame

12-55-a 1 Sft m2 105.72 500.54 46.52 1,137.60Wall Panelling over 0.5" thick chipboard & wood frame

(2"x0.75") 2'x2' grid : Sheesham Ply

12-55-b 1 Sft m2 135.87 375.06 34.86 1,461.94Wall Panelling over 0.5" thick chipboard & wood frame

(2"x0.75") 2'x2'grid : Lamination Sheet

12-55-c 1 Sft m2 96.69 500.42 46.51 1,040.33Wall Panelling over 0.5" thick chipboard & wood frame

(2"x0.75") 2'x2' grid : Commercial Ply

12-56-a 1 RFT m 161.18 101.53 30.95 528.82Supply and Fixing MS Sheet 16 guage(10x20 feet) box

type chowkats including fixing in position with all charges

for Hold fast, Hinges and Painting etc

12-56-b 1 RFT m2 319.81 444.75 41.33 3,441.11Wood plastic composite door patio door leap delux (laker

coated)

12-56-c 1 RFT m2 341.13 444.75 41.33 3,670.51Wood plastic composite door patio door leap premium

grade ( UV coated )

12-56-d 1 Sft m2 710.63 384.59 35.74 7,646.33Wood plastic composite door patio door with frame and

beading deluxe grade (laker coated)

12-56-e 1 Sft m2 710.63 384.59 35.74 7,646.33Wood plastic composite patio door with frame and beading

premium grade(UV coated)

12-57-a 1 Sft m2 551.94 384.59 35.74 5,941.10Wood plastic composite door bukhara flush door steppe

type

12-57-b 1 Sft m2 829.90 384.59 35.74 8,933.00Wood plastic composite door rock type single side door

12-57-c 1 Sft m2 934.63 384.59 35.74 10,056.62Wood plastic composite door rock type double side door

12-58-a 1 Sft m2 934.63 384.59 35.74 10,056.62Wood plastic composite door image type single side door

12-59-a 1 Sft m2 934.63 384.59 35.74 10,056.62Wood plastic composite door carving type single side door

12-60-a 1 Sft m2 681.02 168.71 15.68 7,327.74Composite windows deluxe grade (laker coated)

Page 65 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 66: Rate nwfp 2008

Item Code Description

WOOD WORK, WOODEN/ALUMINIUM JOINERYChapter #

:

12

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

12-60-b 1 Sft m2 734.46 168.11 15.62 7,902.00Composite windows premium grade (UV coated)

12-61-a 1 Sft m2 276.95 200.00 18.58 2,980.00Wood Plastic Fly Screen Delux Grade

12-61-b 1 Sft m2 276.95 200.00 18.58 2,980.00Wood Plastic Screen Premium Grade

12-62-a 1 Sft m2 642.87 1,167.46 108.50 6,917.24Kitchen Floor Cabinet as per MES Design/Specification..

12-62-b 1 Sft m2 518.16 933.97 86.80 5,575.46Kitchen Wall Cabinet as per MES Design/Specification.

12-62-c Each each 5,735.14 1,302.00 1,302.00 5,735.14Providing and Fixing Sink Cabinet as per MES

Design/Specification.

Page 66 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 67: Rate nwfp 2008

Item Code Description

PAINTING AND VARNISHINGChapter #

:

13

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

13-01 100 Sft m2 116.45 6.67 62.00 12.53Cleaning painted woodwork with oil & water

13-02 100 Sft m2 119.47 6.67 62.00 12.86Oiling woodwork with boiled linseed oil

13-03 100 Sft m2 139.50 15.01 139.50 15.01Brushing & scraping blisters of old paints from woodwork

13-04 100 Sft m2 558.00 60.04 558.00 60.04Scraping, brushing and removing old paint, from metal

surface

13-05-a-01 100 Sft m2 561.11 30.82 286.44 60.38Painting old corrugated surfaces, pent roofing etc. with oil

paint : First coat

13-05-a-02 100 Sft m2 437.10 23.35 217.00 47.03Painting old corrugated surfaces, pent roofing etc. with oil

paint : Each subsequent coat

13-05-b-01 100 Sft m2 336.65 18.68 173.60 36.22Painting old surfaces : Sashes, fanlights, doors or windows

: First coat

13-05-b-02 100 Sft m2 283.32 15.88 147.56 30.49Painting old surfaces : Sashes, fanlights, doors or windows

: Each subsequent coat

13-05-c-01 100 Sft m2 561.11 30.82 286.44 60.38Painting old surfaces : Doors / windows any type First coat

13-05-c-02 100 Sft m2 437.10 23.35 217.00 47.03Painting old surfaces : Doors / windows any type Each

subsequent coat

13-05-d-01 100 Sft m2 336.65 18.68 173.60 36.22Painting old surfaces : Guard bars, gratings, railing &

similar open work : First coat

13-05-d-02 100 Sft m2 283.32 15.88 147.56 30.49Painting old surfaces : Guard bars, gratings, railing &

similar work : Each subsequent coat

13-05-e-01 100 Rft m 285.92 4.84 147.56 9.38Painting old surfaces : Fillets, framing, skirting pipes, etc.

less than 6" girth : First coat

13-05-e-02 100 Rft m 215.24 3.42 104.16 7.06Painting old surfaces : Fillets, framing, skirting pipes, etc.

less than 6" girth : Each subseq. coat

13-05-f-01 100 No. 100 No. 1,156.67 658.75 658.75 1,156.67Painting old surfaces : Small detached articles Not

exceeding 1 sft : First coat

13-05-f-02 100 No. 100 No. 840.74 511.50 511.50 840.74Painting old surfaces : Small detached articles Not

exceeding 1 sft : Each subsequent coat

13-05-g-01 100 No. 100 No. 2,267.96 1,317.50 1,317.50 2,267.96Painting old surfaces : Small detached articles 1sft-3sft area

: First coat

13-05-g-02 100 No. 100 No. 1,306.88 728.50 728.50 1,306.88Painting old surfaces : Small detached articles 1sft-3sft area

: Each subsequent coat

13-06-a-01 100 Sft m2 714.27 35.29 327.98 76.86Prepare & Paint new corrugated surface, pent roofing etc :

Priming coat

13-06-a-02 100 Sft m2 501.29 18.25 169.57 53.94Prepare & Paint new corrugated surface, pent roofing etc :

Each subsequent coat of paint

13-06-b-01 100 Sft m2 442.06 20.95 194.68 47.57Prepare & Paint new surface, sashes, doors & windows etc

: Priming coat

13-06-b-02 100 Sft m2 311.86 11.21 104.16 33.56Prepare & Paint new surface, sashes, doors & windows etc

: Each subsequent coat of paint

13-06-c-01 100 Sft m2 714.27 35.29 327.98 76.86Prepare & Paint new surface, doors & windows Priming

coat

Page 67 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 68: Rate nwfp 2008

Item Code Description

PAINTING AND VARNISHINGChapter #

:

13

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

13-06-c-02 100 Sft m2 501.29 18.25 169.57 53.94Prepare & Paint new surface, doors & windows Each

subsequent coat of paint

13-06-d-01 100 Sft m2 411.21 20.95 194.68 44.25Prepare & Paint new surfaces of guard bars, railing &

similar open work : Priming coat

13-06-d-02 100 Sft m2 281.00 11.21 104.16 30.24Prepare & Paint new surfaces of guard bars, railing &

similar work : Each subsequent coat

13-06-e-01 100 Rft m 328.52 4.84 147.56 10.78Prepare & Paint new surface of fillets, framing, skirtings

etc : Priming coat

13-06-e-02 100 Rft m 218.15 2.28 69.44 7.16Prepare & Paint new surface of fillets, framing, skirtings

etc : Each subsequent coat of paint

13-06-f-01 100 No. 100 No. 1,366.11 651.00 651.00 1,366.11Prepare & Paint new surface of small detached articles upto

1 sft : Priming coat

13-06-f-02 100 No. 100 No. 906.35 327.67 327.67 906.35Prepare & Paint new surface of small detached articles upto

1 sft : Each subsequent coat

13-06-g-01 100 No. 100 No. 2,700.65 1,309.75 1,309.75 2,700.65Prepare & paint surf. of small detached articles 1sft - 3sft

area : Priming coat

13-06-g-02 100 No. 100 No. 1,624.88 581.25 581.25 1,624.88Prepare & paint surf. of small detached articles 1sft - 3sft

area : Subsequent coat of paint

13-06-h 100 Sft m2 114.60 3.80 35.34 12.33Extra for knotting & stopping to prime coat on new surface

of wood

13-06-i 100 Sft m2 2,575.50 93.40 868.00 277.12Providing and applying 3 coats of approved type of Plastic

emulsion paint to Plastic surface as per manufucture

specification.

13-07-a 2000 Sft m2 8,641.00 23.35 4,340.00 46.49Khanki mixture, applied hot to barrage gates First coat

13-07-b 2000 Sft m2 6,471.59 17.65 3,279.80 34.82Khanki mixture, applied hot to barrage gates Second coat

13-08-a 100 Sft m2 3,872.10 300.20 2,790.00 416.64French polishing complete: On new work

13-08-b 100 Sft m2 1,950.74 150.10 1,395.00 209.90French polishing complete: On old work

13-09-a 100 Sft m2 482.62 18.68 173.60 51.93Varnishing wood work, including cleaning & preparing

surface : First coat

13-09-b 100 Sft m2 323.79 9.34 86.80 34.84Varnishing wood work, including cleaning & preparing

surface : Second coat

13-09-c 100 Sft m2 282.09 9.34 86.80 30.35Varnishing wood work, including cleaning & preparing

surface : Third coat

13-10-a 100 Sft m2 661.40 9.34 86.80 71.17Bitumen coating to plastered / cement concrete surface : 20

Ibs. per 100 sft.

13-10-b 100 Sft m2 947.60 56.04 520.80 101.96Bitumen coating to plastered / cement concrete surface : 14

Ibs. per 100 sft.

13-10-c 100 Sft m2 675.39 37.36 347.20 72.67Bitumen coating to plastered / cement concrete surface : 10

Ibs. per 100 sft.

13-11 Each Each 6.16 5.15 5.15 6.16Writing letters or figures

13-12-a 100 Sft m2 703.48 11.01 102.30 75.69Coaltar paint applied hot: First coat

13-12-b 100 Sft m2 400.94 6.67 62.00 43.14Coaltar paint applied hot: Second coat

Page 68 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 69: Rate nwfp 2008

Item Code Description

PAINTING AND VARNISHINGChapter #

:

13

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

13-13-a 100 Sft m2 626.95 20.91 194.37 67.46Solignum paint applied hot: First coat

13-13-b 100 Sft m2 799.51 10.77 100.13 86.03Solignum paint applied hot: Second coat

13-14-a 100 Sft m2 471.58 20.91 194.37 50.74Creosote paint applied hot: First coat

13-14-b 100 Sft m2 285.93 10.77 100.13 30.77Creosote paint applied hot: Second coat

13-15 100 Sft m2 561.09 38.36 356.50 60.37Burning off or rubbing down with pumice stone, old paint

from wood work

13-16 100 Sft m2 187.90 15.01 139.50 20.22Removing with caustic soda,old paint from wood work

13-17 Each Each 65.13 26.50 26.50 65.13Painting distance marks with white ground and black

letterin on both faces

13-18 100 RFT m 6,873.51 191.01 5,821.95 225.51Painting two feet wide gauges, reading to 1/10th of a foot.

13-19 100 RFT m 3,310.64 95.50 2,910.98 108.62Painting sounding rods and other guages, reading to 1/10th

of a foot

13-20 100 RFT m 9,230.92 285.58 8,704.57 302.85Painting levelling staves

13-21-a Each Each 317.13 217.00 217.00 317.13The ratio in the rate

of 1st coat to 2nd coat

is 60 % to 40 % in the

labour as well as

composite rate

Painting & lettering (2 coats) on both sides with syn.

enamel paint : Mile/km posts

13-21-b Each Each 39.72 27.17 27.17 39.72Painting & lettering (2 coats) on both sides with syn.

enamel paint : Furlong or 1/10 km posts

13-21-c Each Each 386.57 286.44 286.44 386.57Painting & lettering (2 coats) on both sides with syn.

enamel paint : Sign posts

13-22 100 Sft m2 279.00 30.02 279.00 30.02Removing paint or varnish from wall

13-23-a 100 Sft m2 76.09 0.38 3.49 8.19Scraing of Khanki paint from barrage gates

13-23-b 100 Sft m2 142.35 7.51 69.75 15.32Scraping of Aluminium paint from barrage headworks

13-24 letter letter 18.95 13.89 13.89 18.95Painting letters with shade

13-25 100 Sft m2 491.10 45.03 418.50 52.84Scraping rust from old rails or girders

13-26 100 Sft m2 630.60 60.04 558.00 67.85Chiselling old paint from brick work

13-27 100 Sft m2 351.60 30.02 279.00 37.83Cleaning glasses with chalk and spirit etc

13-28 100 Sft m2 146.84 15.01 139.50 15.80Cleaning and oiling rafter or rolled steel beams

13-29 Each Each 300.27 279.00 279.00 300.27Cleaning and painting punkha poles, including fixing

hooks

13-30-a 100 Sft m2 793.33 37.36 347.20 85.36Preparing surface and painting with emulsion paint : First

coat

13-30-b 100 Sft m2 336.83 18.68 173.60 36.24Preparing surface and painting with emulsion paint : 2nd &

each subsequent coat.

13-31 100 Sft m2 3,431.76 61.71 573.50 369.26Pavement Marking using Reflective Chlorinated Rubber

Paint with Glass Beads as per specification

13-33 Job Job 129.87 41.23 41.23 129.87Repainting of ceiling fan (all sizes & types) incl painting of

blades, canopy etc with syn. enamel

Page 69 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 70: Rate nwfp 2008

Item Code Description

PAINTING AND VARNISHINGChapter #

:

13

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

13-34 Job Job 348.25 286.75 286.75 348.25Repainting of iron poles with cross arms, with bitumen or

other approved paint

13-35-a 100 RFT m 370.47 5.89 179.57 12.15Repainting of pipes and specials of GI, MS or PVC conduit

etc : Upto 1.5" i/d

13-35-b 100 RFT m 631.35 8.84 269.36 20.71Repainting of pipes and specials of GI, MS or PVC conduit

etc : From 1.5" to 2" i/d

13-35-c 100 RFT m 777.41 11.78 359.15 25.51Repainting of pipes and specials of GI, MS or PVC conduit

etc : From 2" to 4" i/d

13-36 Job Job 88.04 44.17 44.17 88.04Repainting main switches & branch distribution boards of

all sizes & types with approved paint

13-37 100/coat m2 50.22 5.40 50.22 5.40The height will be

taken from the floor,

road or ground

underneath, as the

case may be, on side

towards which the

work is to be done.

Extra labour for painting, varnishing etc from 20' height &

above, for every additional 10'

13-38-a 100/coat m2 811.04 46.70 434.00 87.27Preparing surface & painting with snowcem / weathershield

paint : First coat

13-38-b 100/coat m2 422.10 23.35 217.00 45.42Preparing surface & painting with snowcem / weathershield

paint : 2nd & subsequent coats

Page 70 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 71: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-01-a Each Each 1,682.89 265.98 265.98 1,682.89Providing and Fixing glazed earthen ware WC European

type excluding cost of seat & cover : White

14-01-b Each Each 1,842.61 265.98 265.98 1,842.61Providing and Fixing glazed earthen ware WC European

type excluding cost of seat & cover : Coloured

14-02-a Each Each 367.96 4.96 4.96 367.96Providing and Fixing double seat & cover only : Bakelite

14-02-b Each Each 307.46 4.96 4.96 307.46Providing and Fixing double seat & cover only : Plastic

14-03-a Each Each 1,288.45 241.80 241.80 1,288.45Providing and Fixing glazed earthen ware WC squatting

type with built-in foot rests : White

14-03-b Each Each 1,669.60 241.80 241.80 1,669.60Providing and Fixing glazed earthen ware WC squatting

type with built-in foot rests : Coloured

14-04 Each Each 943.60 241.80 241.80 943.60Providing and Fixing white glazed earthernware WC

squatting type with separate foot rests

14-05-a-01 Each Each 1,611.05 322.40 322.40 1,611.05Providing and Fixing glazed earthen ware WHB complete

Size 22"x16" : White with pedestal

14-05-a-02 Each Each 1,792.55 322.40 322.40 1,792.55Providing and Fixing glazed earthen ware WHB complete

Size 22"x16" : Coloured with pedestal

14-05-a-03 Each Each 992.00 241.80 241.80 992.00Providing and Fixing glazed earthen ware WHB complete

Size 22"x16" : White without pedestal

14-05-a-04 Each Each 1,052.50 241.80 241.80 1,052.50Providing and Fixing glazed earthen ware WHB complete

Size 22"x16' : Coloured without pedestal

14-05-b-01 Each Each 2,161.60 322.40 322.40 2,161.60Providing and Fixing glazed earthen ware WHB complete

Size 25"x18" : White with pedestal

14-05-b-02 Each Each 2,241.46 322.40 322.40 2,241.46Providing and Fixing glazed earthen ware WHB complete

Size 25"x18" : Coloured with pedestal

14-05-b-03 Each Each 1,113.00 241.80 241.80 1,113.00Providing and Fixing glazed earthen ware WHB complete

Size 25"x18" : White without pedestal

14-05-b-04 Each Each 1,173.50 241.80 241.80 1,173.50Providing and Fixing glazed earthen ware WHB complete

Size 25"x18" : Coloured without pedestal

14-06-a Each Each 2,524.60 322.40 322.40 2,524.60Providing and Fixing stainless steel sink with drain board

size 48"x24", including set of brackets, waste pipe etc

14-06-b Each each 2,161.60 322.40 322.40 2,161.60Providing and fixing stainless steel sink with drain board

size 18"x36" including set of brackets, waste pipe etc

14-06-c Each each 4,146.00 322.40 322.40 4,146.00Providing and fixing stainless steel sink with drain board

size 18"x48" including set of brackets, waste pipe etc

14-06-d Each each 5,219.27 322.40 322.40 5,219.27Providing and fixing stainless steel sink with drain board

size 20"x60" including set of brackets, waste pipe etc

14-06-e Each each 8,514.10 322.40 322.40 8,514.10Providing and fixing stainless steel sink with drain board

size 20"x72" including set of brackets, waste pipe etc

14-07 Each Each 1,545.70 372.00 372.00 1,545.70Providing and Fixing terrazzo concrete sink 25"x18", with

drain board of mosaic, including set of brackets etc

14-08-a Each Each 1,133.10 322.40 322.40 1,133.10Providing and Fixing glazed earthen ware sink including

set of brackets, waste pipe etc : 25"x18"

Page 71 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 72: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-08-b Each Each 951.60 322.40 322.40 951.60Providing and Fixing glazed earthen ware sink including

set of brackets, waste pipe etc : 25"x18"

14-09 Each Each 866.90 322.40 322.40 866.90Providing and Fixing white glazed earthernware flat back

urinal

14-10-a Each Each 1,484.00 322.40 322.40 1,484.00Providing and Fixing glazed earthen ware low down

flushing cistern 3 gallons capacity : White

14-10-b Each Each 1,544.50 322.40 322.40 1,544.50Providing and Fixing glazed earthen ware low down

flushing cistern 3 gallons capacity : Coloured

14-11 Each Each 2,306.80 322.40 322.40 2,306.80Providing and Fixing white enamelled CI low down

flushing cistern (3 gallons capacity) including CP water

connection

14-12-a Each Each 2,185.80 322.40 322.40 2,185.80Providing and Fixing cast iron high level flushing cistern,

including high level flushing cistern including CP : 3

gallons

14-12-b Each Each 975.80 322.40 322.40 975.80Providing and Fixing cast iron high level flushing cistern,

including high level flushing cistern including CP : 1

gallon

14-13 Each Each 337.22 34.72 34.72 337.22Providing and Fixing CP soap dish.

14-14-a Each Each 185.97 34.72 34.72 185.97Providing and Fixing glazed earthen ware soap dish White

14-14-b Each Each 216.22 34.72 34.72 216.22Providing and Fixing glazed earthen ware soap dish

Coloured

14-15 Each Each 204.12 34.72 34.72 204.12Providing and Fixing CP toilet paper holder

14-16-a Each Each 240.42 34.72 34.72 240.42Providing and Fixing CP towel rail : 24" long, 3/4" dia

14-16-b Each Each 216.22 34.72 34.72 216.22Providing and Fixing CP towel rail : 20" long, 1/2" dia

14-17 Each Each 645.25 100.75 100.75 645.25Providing and Fixing best quality 5mm mirror 22"x16" size

14-18-a Each Each 463.18 39.68 39.68 463.18Providing and Fixing best quality 5mm glass shelf 24"x5"

With chromium plated brackets & railing

14-18-b Each Each 317.38 14.88 14.88 317.38Providing and Fixing best quality 5mm glass shelf 24"x5"

Glass shelf only, w/o chromium plated brackets

14-19-a Each Each 342.18 39.68 39.68 342.18Providing and Fixing glazed earthen ware shelf 24"x5"

with CP brackets & railing of : 24" length, 3/4" dia

14-19-b Each Each 402.68 39.68 39.68 402.68Providing and Fixing glazed earthen ware shelf 24"x5"

with CP brackets & railing of : 20" length, 1/2" dia

14-20-a Each Each 119.42 34.72 34.72 119.42Providing and Fixing Plastic soap dish.

14-20-b Each Each 137.57 34.72 34.72 137.57Providing and Fixing Plastic toilet paper holder.

14-20-c Each Each 119.42 34.72 34.72 119.42Providing and Fixing Plastic towel rail.

14-20-d Each Each 131.52 34.72 34.72 131.52Providing and Fixing Plastic shelf 24"x5" with

14-21-a Each Each 579.22 34.72 34.72 579.22Providing and Fixing CP pillar-cock, heavy type : 3/4"

14-21-b Each Each 417.08 34.72 34.72 417.08Providing and Fixing CP pillar-cock, heavy type : 1/2"

14-22-a Each Each 579.22 34.72 34.72 579.22Providing and Fixing CP stop-cock, heavy type : 3/4"

14-22-b Each Each 325.12 34.72 34.72 325.12Providing and Fixing CP stop-cock, heavy type : 1/2"

Page 72 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 73: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-23 Each Each 359.12 39.68 39.68 359.12Providing and Fixing underground stop-cock 1/2" with CP

cover

14-24-a Each Each 325.12 34.72 34.72 325.12Providing and Fixing CP bib-cock, heavy type : 3/4"

14-24-b Each Each 325.12 34.72 34.72 325.12Providing and Fixing CP bib-cock, heavy type : 1/2"

14-25 Each Each 325.12 34.72 34.72 325.12Providing and Fixing 1/2" CP tee stop cock

14-26-a Each Each 325.12 34.72 34.72 325.12Providing and Fixing CP shower rose : 1/2"x4"

14-26-b Each Each 373.52 34.72 34.72 373.52Providing and Fixing CP shower rose : 3/4"x6"

14-27 Each Each 2,696.72 34.72 34.72 2,696.72Providing and Fixing CP mixing valve for WHB, sink or

shower

14-28-a Each Each 644.68 39.68 39.68 644.68Reduce the composite

rate by 10 % incase

brase peet / gate valve

are used.

Providing and Fixing gun metal peet / gate valve (screwed)

1¬" dia

14-28-b Each Each 765.68 39.68 39.68 765.68Providing and Fixing gun metal peet / gate valve (screwed)

1«" dia

14-28-c Each Each 886.68 39.68 39.68 886.68Providing and Fixing gun metal peet / gate valve (screwed)

2" dia

14-28-d Each Each 2,399.18 39.68 39.68 2,399.18Providing and Fixing gun metal peet / gate valve (screwed)

2«" dia

14-28-e Each Each 3,064.68 39.68 39.68 3,064.68Providing and Fixing gun metal peet / gate valve (screwed)

3" dia

14-29-a Each Each 579.22 34.72 34.72 579.22Providing and Fixing CP or brass oxidized swan-neck cock

1/2" dia : Single way

14-29-b Each Each 947.18 39.68 39.68 947.18Providing and Fixing CP or brass oxidized swan-neck cock

1/2" dia : Double way

14-29-c Each Each 1,259.60 49.60 49.60 1,259.60Providing and Fixing CP or brass oxidized swan-neck cock

1/2" dia : Three way

14-30-a Each Each 234.37 34.72 34.72 234.37Providing and Fixing brass union 1/2" dia

14-30-b Each Each 288.82 34.72 34.72 288.82Providing and Fixing brass union 3/4" dia

14-31-a Each Each 222.70 77.50 77.50 222.70Providing and Fixing CI floor trap including CI grating &

concrete chamber all round : 4"x2"

14-31-b Each Each 501.00 77.50 77.50 501.00Providing and Fixing CI floor trap including CI grating &

concrete chamber all round : 4"x3"

14-32-a Each Each 747.35 69.75 69.75 747.35Providing and Fixing 'P' trap including GI grating & PCC

chamber 4" of cast iron

14-32-b Each Each 124.20 69.75 69.75 124.20Providing and Fixing 'P' trap including GI grating & PCC

chamber 4" glazed

14-33 Each Each 418.75 116.25 116.25 418.75Providing and Fixing 4" gully trap with PCC, including

masonry chamber 1'x1' and PVC grating 6"x6"

14-34-a-01 1 RFT m 451.55 77.52 23.63 1,481.48Providing and fitting CI soil pipe with : Lead & yarn

caulked joint : 4" dia.

Page 73 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 74: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-34-a-02 1 RFT m 301.40 38.76 11.81 988.85Providing and fitting CI soil pipe with : Lead & yarn

caulked joint : 2" dia.

14-34-b-01 1 RFT m 436.80 77.52 23.63 1,433.06Providing and fitting CI soil pipe with : Cement caulked

joint : 4" dia

14-34-b-02 1 RFT m 286.64 38.76 11.81 940.44Providing and fitting CI soil pipe with : Cement caulked

joint : 2" dia

14-35-a 1 RFT m 75.63 19.38 5.91 248.13Providing and Fixing AC soil pipe with cement caulked

joint including all specials : 1¬" i/d

14-35-b 1 RFT m 92.38 23.26 7.09 303.10Providing and Fixing AC soil pipe with cement caulked

joint including all specials : 3¬" i/d

14-35-c 1 RFT m 126.44 38.76 11.81 414.83Providing and Fixing AC soil pipe with cement caulked

joint including all specials : 4" i/d

14-35-d 1 RFT m 180.66 62.02 18.90 592.71Providing and Fixing AC soil pipe with cement caulked

joint including all specials : 6" i/d

14-36-a Each Each 363.07 96.88 96.88 363.08Increase the

composite rate by 3

%, in case of plug

type.

Providing and Fixing CI specials, such as tees, bends etc

Lead caulked joint

14-36-b Each Each 314.67 96.88 96.88 314.67Providing and Fixing CI specials, such as tees, bends etc

Cement caulked joint

14-37-a Each Each 1,260.06 50.06 50.06 1,260.06Supply and Fixing CI manhole cover with frame etc

complete 12" dia

14-37-b Each Each 1,713.81 50.06 50.06 1,713.81Supply and Fixing CI manhole cover with frame etc

complete 18" dia

14-37-c Each Each 2,712.06 50.06 50.06 2,712.06Supply and Fixing CI manhole cover with frame etc

complete 24" dia

14-37-d Each each 2,122.75 217.00 217.00 2,122.75Providing & Fixing Steel manhole cover with frame

18"x18" full heavy duty

14-38 1 RFT m 142.81 226.98 69.18 468.55Providing and Fixing RCC pipe 4" dia, including laying &

jointing in trenches

14-39-a Each Each 252.52 34.72 34.72 252.52Providing and Fixing brass stop/bib cock : 1/2" dia

14-39-b Each Each 349.32 34.72 34.72 349.32Providing and Fixing brass stop/bib cock : 3/4" dia

14-40 Each Each 209.25 209.25 209.25 209.25Hoisting & Placing in position precast RC latrine seat

14-41-a Each Each 221.18 39.68 39.68 221.18Providing and Fixing CP waste coupling : 1.25"

14-41-b Each Each 245.38 39.68 39.68 245.38Providing and Fixing CP waste coupling : 1.5"

14-42-a Each Each 74.09 1.49 1.49 74.09Providing and Fixing rubber plug with chain : 1.25"

14-42-b Each Each 86.19 1.49 1.49 86.19Providing and Fixing rubber plug with chain : 1.5"

14-43-a Each Each 83.12 34.72 34.72 83.12Providing and Fixing waste pipe of PVC : 1.25"

14-43-b Each Each 119.42 34.72 34.72 119.42Providing and Fixing waste pipe of PVC : 1.5"

14-44-a Each Each 67.15 24.80 24.80 67.15Providing and Fixing flushing bend of PVC : 1.25"

14-44-b Each Each 97.40 24.80 24.80 97.40Providing and Fixing flushing bend of PVC : 1.5"

Page 74 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 75: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-45-a Each Each 947.18 39.68 39.68 947.18Providing and Fixing CP bottle trough with waste pipe :

1.25" i/d

14-45-b Each Each 1,249.68 39.68 39.68 1,249.68Providing and Fixing CP bottle trough with waste pipe :

1.5" i/d

14-46-a Each Each 112.28 39.68 39.68 112.28Providing and Fixing angle iron brackets for : WHB and

cistern

14-46-b Each Each 124.38 39.68 39.68 124.38Providing and Fixing angle iron brackets for : Sink

14-47-a Each Each 45.13 14.88 14.88 45.13Providing and Fixing 1/2" dia connection including check

nuts etc Plastic rubber connection

14-47-b Each Each 54.81 14.88 14.88 54.81Providing and Fixing 1/2" dia connection including check

nuts etc Copper connection

14-47-c Each Each 147.98 14.88 14.88 147.98Providing and Fixing 1/2" dia connection including check

nuts etc CP connection

14-48-a Each Each 179.92 34.72 34.72 179.92Providing and Fixing brass ball float valve 1/2" dia

14-48-b Each Each 198.07 34.72 34.72 198.07Providing and Fixing brass ball float valve 3/4" dia

14-48-c Each Each 337.22 34.72 34.72 337.22Providing and Fixing brass ball float valve 1" dia

14-48-d Each Each 415.87 34.72 34.72 415.87Providing and Fixing brass ball float valve 1.25" dia

14-48-e Each Each 700.22 34.72 34.72 700.22Providing and Fixing brass ball float valve 1.5" dia

14-48-f Each Each 942.22 34.72 34.72 942.22Providing and Fixing brass ball float valve 2" dia

14-49-a 1 RFT m 318.21 317.92 96.90 1,044.00Providing and Fixing 4" dia MS high pressure seamwelded

pipe & specials complete : 2" dia

14-49-b 1 RFT m 261.93 254.34 77.52 859.34Providing and Fixing 4" dia MS high pressure seamwelded

pipe & specials complete : 1" dia

14-50-a Each Each 10,067.50 387.50 387.50 10,067.50Providing and Fixing Audco type valve : 4" dia

14-50-b Each Each 5,600.00 155.00 155.00 5,600.00Providing and Fixing Audco type valve : 2" dia

14-50-c Each Each 1,931.25 116.25 116.25 1,931.25Providing and Fixing Audco type valve : 1" dia

14-51-a Each Each 1,309.80 124.00 124.00 1,309.80Providing and Fixing pressure regulator : No. 103

14-51-b Each Each 1,092.00 124.00 124.00 1,092.00Providing and Fixing pressure regulator : No. 043

14-51-c Each Each 704.80 124.00 124.00 704.80Providing and Fixing pressure regulator : People type

14-52-a Each Each 10,672.50 387.50 387.50 10,672.50Providing and Fixing high pressure flange type valve : 4"

dia

14-52-b Each Each 4,874.00 155.00 155.00 4,874.00Providing and Fixing high pressure flange type valve : 2"

dia

14-52-c Each Each 1,892.50 77.50 77.50 1,892.50Providing and Fixing high pressure flange type valve : 1"

dia

14-53 Each Each 24.56 14.88 14.88 24.56Providing and Fixing nipple or bush 1/4" to 3/8" i/d

14-54-a Each Each 803.50 77.50 77.50 803.50Providing and Fixing eclipse cock : 1" dia

14-54-b Each Each 779.30 77.50 77.50 779.30Providing and Fixing eclipse cock : 3/4" dia

14-55-a 1 RFT m 188.34 101.52 30.94 617.91Providing and Fixing GI pipe(light) & including specials

complete 2" dia

Page 75 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 76: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-55-b 1 RFT m 156.06 101.52 30.94 512.00Providing and Fixing GI pipe(light) & including specials

complete 1.5" dia

14-55-c 1 RFT m 129.80 101.52 30.94 425.85Providing and Fixing GI pipe(light) & including specials

complete 1.25" dia

14-55-d 1 RFT m 95.05 58.98 17.98 311.85Providing and Fixing GI pipe(light) & including specials

complete 1" dia

14-55-e 1 RFT m 72.67 58.70 17.89 238.41Providing and Fixing GI pipe(light) & including specials

complete 3/4" dia

14-55-f 1 RFT m 53.83 50.76 15.47 176.60Providing and Fixing GI pipe(light) & including specials

complete 1/2" dia

14-56-a Each Each 206.00 12.40 12.40 206.00Providing and Fixing oxidized gas cock : 1" dia.

14-56-b Each Each 133.40 12.40 12.40 133.40Providing and Fixing oxidized gas cock : 3/4" dia.

14-56-c Each Each 109.20 12.40 12.40 109.20Providing and Fixing oxidized gas cock : 1/2" dia.

14-57-a Each Each 117.43 2.48 2.48 117.43Providing and Fixing brass gas cock : 1/2" dia

14-57-b Each Each 196.08 2.48 2.48 196.08Providing and Fixing brass gas cock : 3/4" dia

14-58-a Each Each 93.53 14.88 14.88 93.53Providing and Fixing 1/4" CP or oxidized gas cock Single

way

14-58-b Each Each 115.55 24.80 24.80 115.55Providing and Fixing 1/4" CP or oxidized gas cock Two

way

14-58-c Each Each 148.58 39.68 39.68 148.58Providing and Fixing 1/4" CP or oxidized gas cock Three

way

14-59-a Each Each 1,101.00 496.00 496.00 1,101.00Providing and Fixing approved best quality light burners

Single

14-59-b Each Each 2,129.50 496.00 496.00 2,129.50Providing and Fixing approved best quality light burners

Double

14-60-a Each Each 3,521.00 496.00 496.00 3,521.00Providing and Fixing approved best quality gas room

heaters Single pannel

14-60-b Each Each 4,126.00 496.00 496.00 4,126.00Providing and Fixing approved best quality gas room

heaters Double pannel

14-61-a Each Each 5,699.00 496.00 496.00 5,699.00Providing and Fixing approved best quality cooking range

with 2 burners & oven

14-61-b Each Each 6,667.00 496.00 496.00 6,667.00Providing and Fixing approved best quality cooking range

with 2 burners, oven & rostary

14-61-c Each Each 9,208.00 496.00 496.00 9,208.00Providing and Fixing approved best quality cooking range

with 3 burners, oven & hot case

14-61-d Each Each 13,806.00 496.00 496.00 13,806.00Providing and Fixing approved best quality cooking range

with 3 burners, oven, hot case & roastary

14-61-e Each Each 19,009.00 496.00 496.00 19,009.00Providing and Fixing approved best quality cooking range

with 5 burners, oven, hot case & roastary

14-62-a Each Each 9,692.00 496.00 496.00 9,692.00Providing and Fixing approved best quality gas water

heaters 20 gallons capacity

Page 76 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 77: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-62-b Each Each 11,386.00 496.00 496.00 11,386.00Providing and Fixing approved best quality gas water

heaters 30 gallons capacity

14-62-c Each Each 13,806.00 496.00 496.00 13,806.00Providing and Fixing approved best quality gas water

heaters 50 gallons capacity

14-63-a Each Each 340.30 62.00 62.00 340.30Providing and Fixing gas cross burners : 6" Size

14-63-b Each Each 400.80 62.00 62.00 400.80Providing and Fixing gas cross burners : 9" Size

14-63-c Each Each 485.50 62.00 62.00 485.50Providing and Fixing gas cross burners : 12" Size

14-64-a Each Each 572.30 148.80 148.80 572.30Providing and Fixing gas nozzle star burner with injector

12" nozzle

14-64-b Each Each 729.60 148.80 148.80 729.60Providing and Fixing gas nozzle star burner with injector

18" nozzle

14-64-c Each Each 790.10 148.80 148.80 790.10Providing and Fixing gas nozzle star burner with injector

24" nozzle

14-64-d Each Each 1,177.30 148.80 148.80 1,177.30Providing and Fixing gas nozzle star burner with injector

32" nozzle

14-65 Each Each 158.50 49.60 49.60 158.50Providing and Fixing flue pipe for gas room heater any

type/make

14-66 Each Each 4,383.80 148.80 148.80 4,383.80Providing and Fixing gas twin burners with stand complete

Imperial make

14-67 Pair Pair 304.00 62.00 62.00 304.00Providing and Fixing angle iron frame wall type brackets

for gas room heater

14-68-a Each Each 1,028.80 387.50 387.50 1,028.80Providing and Fixing gas tandoor complete : 24" nozzle

14-68-b Each Each 1,609.75 581.25 581.25 1,609.75Providing and Fixing gas tandoor complete : 32" nozzle

14-68-c Each Each 2,384.15 581.25 581.25 2,384.15Providing and Fixing gas tandoor complete : 48" nozzle

14-69-a-01 Each Each 11,115.00 775.00 775.00 11,115.00P/F Fibre Glass Water Tank (Shalimar/Spectrum) 300

gallons

14-69-a-02 Each Each 13,948.04 775.00 775.00 13,948.04P/F Fibre Glass Water Tank (Sepctrum/Shalimar) 400

gallons

14-69-b-01 Each Each 8,574.00 775.00 775.00 8,574.00P/F Polyethylene Water Tank (Super Tuff) 200 gallons

(Horizontal)

14-69-b-02 Each Each 15,426.34 1,581.00 1,581.00 15,426.34Supplying and Fixing Polyethylene Water Tank (Super

Tuff) 400 gallons (Vertical)

14-69-b-03 Each Each 18,454.06 1,581.00 1,581.00 18,454.06P/F Polyethylene Water Tank (Super Tuff) 500 gallons

(Vertical)

14-69-b-04 Each Each 35,095.69 2,108.00 2,108.00 35,095.69P/F Polyethylene Water Tank (Super Tuff) 1000 gallons

(Vertical)

14-69-b-05 Each Each 50,207.31 3,162.00 3,162.00 50,207.31P/F Polyethylene Water Tank (Super Tuff) 1500 gallons

(Vertical)

14-70-a 1 RFT m 339.30 77.52 23.63 1,113.19Providing and Fixing of pipe type B nikasi system

including testing in all respect 110 mm (using dadex, or eq)

14-70-b 1 RFT m 188.36 77.52 23.63 617.99Providing and Fixing of pipe type B nikasi system

including testing in all respect 75 mm (using dadex, or eq)

Page 77 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 78: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-71-a 1 RFT m 81.02 50.76 15.47 265.83Providing and Fixing of poly dex high pressure PPR(green

including testing ect complete 25 mm(including all special

ect)

14-71-b 1 RFT m 73.96 50.76 15.47 242.64Providing and Fixing of poly dex high pressure PPR(green

including testing ect complete 20 mm(including all special

ect)

14-72-a 20 Rft m 25.83 1.94 11.81 4.24Providing of plumbing tape insulation on G.I pipe

complete 1/2" dia

14-72-b 20 Rft m 32.84 1.94 11.81 5.39Providing of plumbing tape insulation on G.I pipe

complete 3/4" dia

14-72-c 20 Rft m 39.85 1.94 11.81 6.54Providing of plumbing tape insulation on G.I pipe

complete 1" dia

14-72-d 20 Rft m 46.86 1.94 11.81 7.69Providing of plumbing tape insulation on G.I pipe

complete 1.5" dia

14-72-e 20 Rft m 53.87 1.94 11.81 8.84Providing of plumbing tape insulation on G.I pipe

complete 2" dia

14-72-f 20 Rft m 60.88 1.94 11.81 9.99Providing of plumbing tape insulation on G.I pipe

complete 2.5" dia

14-73-a 20 Rft m 636.00 5.09 31.00 104.33Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 1/2" dia

14-73-b 20 Rft m 678.35 5.09 31.00 111.28Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 3/4" dia

14-73-c 20 Rft m 817.50 5.09 31.00 134.10Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 1" dia

14-73-d 20 Rft m 896.15 5.09 31.00 147.01Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 1.5" dia

14-73-e 20 Rft m 926.40 5.09 31.00 151.97Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 2" dia

14-73-f 20 Rft m 1,071.60 5.09 31.00 175.79Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 2.5" dia

14-73-g 20 Rft m 1,228.90 5.09 31.00 201.59Providing of thermal insulation of high density (64kg/m3)

fiber glass pipe insulation faced with aluminium foil for

chilled/hot water piping complete 3" dia

14-74-a Each each 13,624.50 496.00 496.00 13,624.50Providing and Fixing Gas water Geyser "Singer" 30 gallons

SG 35 DLX with imported (American) Thermostat

Page 78 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 79: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-74-b Each each 14,713.50 496.00 496.00 14,713.50Providing and Fixing Gas water Geyser "Singer" 35 gallons

SG 35 DLX with imported (American) Thermostat

14-75-a Each each 14,347.55 124.00 124.00 14,347.55Providing & Fixing "Singer" Cooking Range Model 307 (3

Burners Black), Bigger size

14-75-b Each each 12,792.70 124.00 124.00 12,792.70Providing & Fixing "Singer" Cooking Range Model 308 (3

Burners Black), Smaller size

14-76 Each each 16,241.20 124.00 124.00 16,241.20Providing & Fixing "Singer" Cooking Range Model 310 (3

Burners White)

14-77 Each each 18,032.00 124.00 124.00 18,032.00Providing & Fixing "Singer" Cooking Range Model 312 (5

Burners), (Automatic)

14-78 Each each 809.55 77.50 77.50 809.55Supply and Fixing low level plastic flushing cistern.

14-79-a Each each 6,831.22 306.90 306.90 6,831.22Supply and fixing of 0.5 HP Monoblock water pump

1.25"x1" single phase upto 72 ft head (Deen Pump Type

SE) i/c all accessories.

14-79-b Each each 8,380.02 306.90 306.90 8,380.02Supply and fixing of 1.0 HP Monoblock water pump

1.25"x1" single phase upto 90 ft head (Deen Pump Type

SE) i/c all accessories.

14-79-c Each each 9,316.56 306.90 306.90 9,316.56Supply and fixing of 1.0 HP Monoblock water pump

1.25"x1" single phase upto 88 ft head (Deen Pump Type

DE-S2) i/c all accessories.

14-79-d Each each 9,671.09 306.90 306.90 9,671.09Supply and fixing of 1.5 HP Monoblock water pump

1.25"x1" single phase upto 130 ft head (Deen Pump Type

DE-S2) i/c all accessories.

14-80-a Each each 13,597.54 306.90 306.90 13,597.54Supply and fixing of 2.0 HP Monoblock water pump

1.5"x1.25" 3 stage model DE-S3 (DEENS' PUMPS) single

phase for 150 ft head with all accessories.

14-80-b Each each 14,551.02 306.90 306.90 14,551.02Supply and fixing of 2.0 HP Monoblock water pump

1.5"x1.5" 4 stage model DE-S4 (DEENS' PUMPS) single

phase for 190 ft head with all accessories.

14-80-c Each each 14,964.84 306.90 306.90 14,964.84Supply and fixing of 2.0 HP Monoblock water pump

2"x2" size 1 stage SE model (DEENS' PUMPS) single

phase for 65 ft head with all accessories and fittings.

14-81-a Each each 16,641.90 306.90 306.90 16,641.90Supply and fixing of 3.0 HP Monoblock water pump

1.5"x1.5" size 5 stage DE-S5 model (DEENS' PUMPS)

single phase for 220 ft head with all accessories

14-81-b Each each 20,345.71 306.90 306.90 20,345.71Supply and fixing of 3.0 HP Monoblock water pump

1.5"x1.25" size 6 stage DE-S6 model (DEENS' PUMPS)

single phase for 260 ft head with all accessories

14-81-c Each each 21,402.04 306.90 306.90 21,402.04Supply and fixing of 4.0 HP Monoblock water pump

1.5"x1.25" size 7 stage DN-S7 model (DEENS' PUMPS)

single phase for 300 ft head with all accessories

Page 79 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 80: Rate nwfp 2008

Item Code Description

PLUMBING, SANITARY INSTALLATION AND GAS FITTINGSChapter #

:

14

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

14-81-d Each each 21,372.83 542.50 542.50 21,372.83Supply and fixing of 3.0 HP Monoblock water pump

2.5"x2" size 2 stage DE-S2 model (DEENS' PUMPS)

single phase for 100 ft head with all accessories

14-81-e Each each 20,513.66 306.90 306.90 20,513.66Supply and fixing of 4.0 HP Monoblock water pump

1.5"x2" size 3 stage DN-S3 model (DEENS' PUMPS)

single phase for 130 ft head with all accessories

14-81-f Each each 21,716.05 542.50 542.50 21,716.05Supply and fixing of 4.0 HP Monoblock water pump

1.5"x2" size 4 stage DN-S4 model (DEENS' PUMPS)

single phase for 160 ft head with all accessories

14-81-g Each each 20,585.17 306.90 306.90 20,585.17Supply and fixing of 3.0 HP Monoblock water pump

3"x3" size 1 stage P.P model (DEENS' PUMPS) single

phase for 60 ft head with all accessories

14-81-h Each each 23,284.68 306.90 306.90 23,284.68Supply and fixing of 4.0 HP Monoblock water pump

3"x2.5" size 1stage P.P model (DEENS' PUMPS) single

phase for 60 ft head with all accessories

14-82-a Each each 9,334.55 1,100.50 1,100.50 9,334.55Supply and fixing of 1.0 HP Deep well water pump 1"x1"

size 1stage Jet S-1 model (DEENS' PUMPS) single phase

for 60 ft suction and upto 60 ft head with all accessories

14-82-b Each each 12,593.08 1,100.50 1,100.50 12,593.08Supply and fixing of 2.0 HP Deep well water pump 1"x1"

size 2 stage Jet S-2 model (DEENS' PUMPS) single phase

for 80 ft suction and upto 80 ft head with all accessories

14-82-c Each each 15,255.08 1,100.50 1,100.50 15,255.08Supply and fixing of 3.0 HP Deep well water pump 1"x1"

size 3 stage Jet S-3 model (DEENS' PUMPS) single phase

for 120 ft suction and upto 120 ft head with all accessories

14-82-d Each each 17,999.36 1,100.50 1,100.50 17,999.36Supply and fixing of 4.0 HP Deep well water pump 1"x1"

size 4 stage Jet S-4 model (DEENS' PUMPS) single phase

for 160 ft suction and upto 160 ft head with all accessories

14-83 Each each 27,426.00 806.00 806.00 27,426.00Providing & Fixing Solar Geysers 35 gallons capacity (a

product of Enercon, National Energy Conservation Centre

Islamabad)

Page 80 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 81: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-01-a-01 1 RFT m 26.37 23.57 7.18 86.50Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 1/2" i/d

15-01-a-02 1 RFT m 32.64 23.57 7.18 107.08Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 3/4" i/d

15-01-a-03 1 RFT m 40.05 23.57 7.18 131.40Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 1" i/d

15-01-a-04 1 RFT m 45.73 23.57 7.18 150.04Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 1.25" i/d

15-01-a-05 1 RFT m 51.27 23.57 7.18 168.20Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 1.5" i/d

15-01-a-06 1 RFT m 68.81 23.57 7.18 225.75Supply and Erection MS conduit pipe for wiring purpose

comp. On surface including clamps etc: 2" i/d

15-01-b-01 1 RFT m 46.36 58.92 17.96 152.11Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 1/2" i/d

15-01-b-02 1 RFT m 52.63 58.92 17.96 172.68Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 3/4" i/d

15-01-b-03 1 RFT m 60.05 58.92 17.96 197.01Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 1" i/d

15-01-b-04 1 RFT m 65.73 58.92 17.96 215.65Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 1.25" i/d

15-01-b-05 1 RFT m 71.26 58.92 17.96 233.80Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 1.5" i/d

15-01-b-06 1 RFT m 85.47 58.92 17.96 280.40Supply and Erection MS conduit pipe for wiring purpose

comp. Recessed in walls including chase etc : 2" i/d

15-02-a-01 1 RFT m 18.23 11.78 3.59 59.81Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 1/2" i/d

15-02-a-02 1 RFT m 9.70 11.78 3.59 31.81Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 3/4" i/d

15-02-a-03 1 RFT m 22.92 11.78 3.59 75.20Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 1" i/d

15-02-a-04 1 RFT m 36.29 17.39 5.30 119.06Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 1.25" i/d

15-02-a-05 1 RFT m 34.74 23.57 7.18 113.98Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 1.5" i/d

15-02-a-06 1 RFT m 30.62 15.02 4.58 100.47Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 2" i/d

15-02-a-07 1 RFT m 53.25 17.97 5.48 174.70Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 3" i/d

15-02-a-08 1 RFT m 63.33 23.19 7.07 207.76Supply and Erection PVC pipe for wiring purpose

complete On surface including clamps etc: 4" i/d

15-02-b-01 1 RFT m 25.41 35.35 10.77 83.38Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 1/2" i/d

Page 81 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 82: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-02-b-02 1 RFT m 35.40 35.35 10.77 116.13Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 3/4" i/d

15-02-b-03 1 RFT m 39.84 35.35 10.77 130.72Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 1" i/d

15-02-b-04 1 RFT m 53.76 35.35 10.77 176.36Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 1.25" i/d

15-02-b-05 1 RFT m 51.85 47.13 14.37 170.10Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 1.5" i/d

15-02-b-06 1 RFT m 54.48 58.92 17.96 178.74Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 2" i/d

15-02-b-07 1 RFT m 78.54 70.70 21.55 257.69Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 3" i/d

15-02-b-08 1 RFT m 93.52 88.37 26.94 306.83Supply and Erection PVC pipe for wiring purpose

complete Recessed in walls including chase etc : 4" i/d

15-03-a 1 RFT m 32.92 13.61 4.15 108.02Supply and Erection GI flexible pipe for wiring purpose

complete 1/2" i/d

15-03-b 1 RFT m 48.06 19.70 6.00 157.67Supply and Erection GI flexible pipe for wiring purpose

complete 3/4" i/d

15-03-c 1 RFT m 67.51 22.99 7.01 221.48Supply and Erection GI flexible pipe for wiring purpose

complete 1" i/d

15-03-d 1 RFT m 87.28 24.92 7.59 286.34Supply and Erection GI flexible pipe for wiring purpose

complete 1.25" i/d

15-03-e 1 RFT m 102.03 24.92 7.59 334.76Supply and Erection GI flexible pipe for wiring purpose

complete 1.5" i/d

15-03-f 1 RFT m 128.27 40.81 12.44 420.84Supply and Erection GI flexible pipe for wiring purpose

complete 2" i/d

15-03-g 1 RFT m 202.80 42.11 12.83 665.37Supply and Erection GI flexible pipe for wiring purpose

complete 3" i/d

15-04-a 1 RFT m 5.39 6.09 1.85 17.67Additional width

required to

accommodate wire

will be provided by

erection of additional

strips.

Supply and Erection Sahl wood strip batten for wiring

complete 1/2" i/d

15-04-b 1 RFT m 8.41 6.09 1.85 27.59Supply and Erection Sahl wood strip batten for wiring

complete 3/4" i/d

15-04-c 1 RFT m 4.09 6.09 1.85 13.43Supply and Erection Sahl wood strip batten for wiring

complete 1" i/d

15-05-a 1 RFT m 7.32 8.21 2.50 24.01Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 3/0.029"

15-05-b 1 RFT m 9.54 8.25 2.51 31.31Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 3/0.036"

Page 82 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 83: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-05-c 1 RFT m 12.76 7.73 2.36 41.87Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 7/0.029"

15-05-d 1 RFT m 14.89 7.73 2.36 48.86Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 7/0.036"

15-05-e 1 RFT m 25.81 19.33 5.89 84.67Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 7/0.044"

15-05-f 1 RFT m 50.14 28.99 8.84 164.52Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 7/0.064"

15-05-g 1 RFT m 118.01 48.32 14.73 387.19Supply and Erection single core PVC insulated copper

conductor 250/440 V grade cable : 19/0.064"

15-06-a 1 RFT m 8.91 13.53 4.12 29.25Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 3/0.029"

15-06-b 1 RFT m 11.13 13.53 4.12 36.51Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 3/0.036"

15-06-c 1 RFT m 14.67 15.46 4.71 48.13Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 7/0.029"

15-06-d 1 RFT m 31.27 15.46 4.71 102.60Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 7/0.036"

15-06-e 1 RFT m 29.41 25.12 7.66 96.50Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 7/0.044"

15-06-f 1 RFT m 57.90 38.66 11.78 189.95Supply and Erection single core PVC insulated+sheathed

copper conductor 250/440 V grade cable : 7/0.064"

15-07-a 1 RFT m 70.81 38.66 11.78 232.31Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 7/0.064"

15-07-b 1 RFT m 62.45 65.70 20.03 204.89Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 19/0.052"

15-07-c 1 RFT m 108.56 65.70 20.03 356.17Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 19/0.064"

15-07-d 1 RFT m 203.44 96.65 29.46 667.47Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 19/0.083"

15-07-e 1 RFT m 311.96 241.63 73.65 1,023.48Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 37/0.072"

15-07-f 1 RFT m 372.82 241.63 73.65 1,223.17Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 37/0.083"

15-07-g 1 RFT m 534.03 241.63 73.65 1,752.06Supply and Erection single core PVC insulated & sheathed

copper conductor, 660/1100V cable : 37/0.103"

15-08-a 1 RFT m 12.17 9.66 2.94 39.91Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 3/0.029"

15-08-b 1 RFT m 17.33 9.66 2.94 56.86Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 3/0.036"

15-08-c 1 RFT m 24.78 13.53 4.12 81.29Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 7/0.029"

Page 83 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 84: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-08-d 1 RFT m 40.31 13.53 4.12 132.26Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 7/0.036"

15-08-e 1 RFT m 50.24 13.53 4.12 164.82Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 7/0.044"

15-08-f 1 RFT m 89.33 13.53 4.12 293.08Supply and Erection twin core PVC insulated & sheathed

copper conductor 250/440 V grade cable : 7/0.064"

15-09-a Each Each 86.53 44.17 44.17 86.53Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 4"x4"

15-09-b Each Each 125.45 58.90 58.90 125.45Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 7"x4"

15-09-c Each Each 152.27 73.63 73.63 152.27Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 9"x4"

15-09-d Each Each 233.55 88.35 88.35 233.55Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 8"x10"

15-09-e Each Each 311.72 106.02 106.02 311.72Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 10"x12"

15-09-f Each Each 395.94 123.69 123.69 395.94Supply and Erection MS sheet box of 16 SWG, 4"deep

with 3/16" thick bakelite sheet top etc. complete : 12"x14"

15-10-a Each Each 14.89 8.84 8.84 14.89Supply and Erection Sahl wood board, 1.75" deep : 3" dia

15-10-b Each Each 33.76 26.50 26.50 33.76Supply and Erection Sahl wood board, 1.75" deep : 4"x4"

15-10-c Each Each 68.86 26.50 26.50 68.86Supply and Erection Sahl wood board, 1.75" deep : 7"x4"

15-10-d Each Each 84.58 26.50 26.50 84.58Supply and Erection Sahl wood board, 1.75" deep : 8"x10"

15-10-e Each Each 102.05 29.45 29.45 102.05Supply and Erection Sahl wood board, 1.75" deep :

10"x12"

15-10-f Each Each 114.15 29.45 29.45 114.15Supply and Erection Sahl wood board, 1.75" deep :

12"x14"

15-11-a-01 Each Each 870.05 265.05 265.05 870.05Reduce the labour

and composite rates

by 20 % in case, base

frame is already

installed.

Supply and Erection of iron/aluminium clad, 500V main

switch Double pole : 15/20 Amp.

15-11-a-02 Each Each 991.05 265.05 265.05 991.05Supply and Erection of iron/aluminium clad, 500V main

switch Double pole : 30/35 Amp.

15-11-a-03 Each Each 3,290.05 265.05 265.05 3,290.05Supply and Erection iron/aluminium clad 500 volts main

switch Double Pole : 60/65 Amp

15-11-a-04 Each Each 4,500.05 265.05 265.05 4,500.05Supply and Erection iron/aluminium clad 500 volts main

switch Double Pole : 100 Amp

15-11-b-01 Each Each 991.05 265.05 265.05 991.05Supply and Erection of iron/aluminium clad, 500V main

switch Triple pole with neutral link : 15/20 Amp.

15-11-b-02 Each Each 1,233.05 265.05 265.05 1,233.05Supply and Erection of iron/aluminium clad, 500V main

switch Triple pole with neutral link : 30/35 Amp.

Page 84 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 85: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-11-b-03 Each Each 1,805.40 353.40 353.40 1,805.40Supply and Erection of iron/aluminium clad, 500V main

switch Triple pole with neutral link : 60/65 Amp.

15-11-b-04 Each Each 2,388.64 441.75 441.75 2,388.64Supply and Erection of iron/aluminium clad, 500V main

switch Triple pole with neutral link : 100 Amp.

15-12-a Each Each 3,777.25 147.25 147.25 3,777.25Reduce the labour

and composite rates

by 20 % in case, base

frame is already

installed.

Supply and Erection or iron/aluminium clad, 500V main

switch with triple pole, complete : 60 Amp.

15-12-b Each Each 4,382.25 147.25 147.25 4,382.25Supply and Erection or iron/aluminium clad, 500V main

switch with triple pole, complete : 100 Amp.

15-12-c Each Each 5,075.60 235.60 235.60 5,075.60Supply and Erection or iron/aluminium clad, 500V main

switch with triple pole, complete : 200 Amp.

15-12-d Each Each 6,043.60 235.60 235.60 6,043.60Supply and Erection or iron/aluminium clad, 500V main

switch with triple pole, complete : 300 Amp.

15-12-e Each Each 8,463.60 235.60 235.60 8,463.60Supply and Erection or iron/aluminium clad, 500V main

switch with triple pole, complete : 500 Amp.

15-13 Each Each 189.62 5.89 5.89 189.62Reduce the labour

and composite rates

by 20 % in case, base

frame is already

installed.

Supply and Erection plain pendent lamp holder, complete

with bakelite lamp holder & flexible twin wire of 2m

15-14 Each Each 53.39 11.04 11.04 53.39Supply and Erection 9" long swan neck plain

brass/steel/brass oxidised bracket lamp holder, complete

15-15 Each Each 53.81 23.56 23.56 53.81Supply and Erection wall/pole type bracket with double

cover water tight reflector, flexible wire & brass holder

15-16 Each Each 81.28 14.73 14.73 81.28Supply and Erection call bell 220/250V, fixed on Sahl

wood board 7"x4"

15-17 Each Each 58.38 4.42 4.42 58.38Supply and Erection bell push or bed switch, with 5m. twin

flexible wire 23/0.0076"

15-18-a Each Each 26.99 8.84 8.84 26.99Supply and Erection switches 10/15 Amp : Open type

15-18-b Each Each 26.99 8.84 8.84 26.99Supply and Erection switches 10/15 Amp : Recessed type

15-19-a Each Each 38.92 14.73 14.73 38.92Supply and Erection 3 pin 10/15 Amp. wall socket : Open

type

15-19-b Each Each 38.92 14.73 14.73 38.92Supply and Erection 3 pin 10/15 Amp. wall socket :

Recessed

15-20-a Each Each 159.93 14.73 14.73 159.93Supply and Erection 3 pin switch & plug combined

recessed type : 5 Amp

15-20-b Each Each 196.23 14.73 14.73 196.23Supply and Erection 3 pin switch & plug combined

recessed type : 10/15 Amp

15-21 Each Each 57.08 14.73 14.73 57.08Supply and Erection 3 pin 10/15 Amp. wall socket with

shoe open type

Page 85 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 86: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-22-a Each Each 31.56 7.36 7.36 31.56Supply and Erection button holder/angle holder Bakelite

large size

15-22-b Each Each 43.66 7.36 7.36 43.66Supply and Erection button holder/angle holder Brass

15-23-a Each Each 44.97 14.73 14.73 44.97Supply and Erection porcelain fuses (china made) with

plastic sheet base on angle iron board : 10/15 Amp.

15-23-b Each Each 51.03 14.73 14.73 51.03Supply and Erection porcelain fuses (china made) with

plastic sheet base on angle iron board : 30 Amp.

15-23-c Each Each 87.32 14.73 14.73 87.32Supply and Erection porcelain fuses (china made) with

plastic sheet base on angle iron board : 60 Amp.

15-23-d Each Each 147.82 14.73 14.73 147.82Supply and Erection porcelain fuses (china made) with

plastic sheet base on angle iron baord : 100 Amp.

15-23-e Each Each 256.73 14.73 14.73 256.73Supply and Erection porcelain fuses (china made) with

plastic sheet base on angle iron board : 200 Amp.

15-24-a Set Set 875.65 58.90 58.90 875.65Supply and Erection tube light, including rod, choke etc

complete Double rod (80 watts) with 2 chokes & 2 starters

15-24-b Set Set 477.36 44.17 44.17 477.36Supply and Erection tube light, including rod, choke etc

complete Single rod (40 watts) with 1 choke & 1 starter

15-24-c Each Each 165.49 32.40 32.40 165.49Supply and Erection tube light, including rod, choke etc

complete Round tube (10 watt) 1 choke + 1 starter w/o

cover

15-25 Each Each 63.13 14.73 14.73 63.13Supply and Erection girder clamp hook, 5/8" dia.for

hanging ceiling fans

15-26-a Each Each 304.32 44.17 44.17 304.33Supply and Erection circuit breaker (imported) on sahl

wood board complete : 2/5/15 Amp.

15-26-b Each Each 322.48 44.17 44.17 322.48Supply and Erection circuit breaker (imported) on sahl

wood board complete : 20/25/30 Amp.

15-27 1 RFT m 57.63 17.39 5.30 189.07Supply and Erection stay for house service pipe, erected

with straining screws and 7/14 SWG stay wire

15-28 1 RFT m 223.09 23.19 7.07 731.93Supply and Erection of house service pipe Henley or pole,

type 2" dia. erected to install insulated wire etc

15-29 Each Each 535.03 14.73 14.73 535.03Supply and Erection shackle/pin insulator, medium size

15-30 kg kg 777.73 7.36 7.36 777.73Supply and Erection bare copper conductor wire, No. 2 to

16 SWG, including binding wire No. 16 SWG

15-31 kg kg 104.16 7.36 7.36 104.16Supply and Erection GI wire of sizes, including binding

wire No. 16 SWG for support of rubber wire, pole to pole

15-32-a 1 RFT m 40.32 13.53 4.12 132.27Wiring overhead line in 2 single core, PVC insulated cable

with GI wire #8 SWG : 3/0.029"

15-32-b 1 RFT m 51.50 13.53 4.12 168.95Wiring overhead line in 2 single core, PVC insulated cable

with GI wire #8 SWG : 7/0.029"

15-32-c 1 RFT m 55.76 13.53 4.12 182.92Wiring overhead line in 2 single core, PVC insulated cable

with GI wire #8 SWG : 7/0.036"

Page 86 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 87: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-32-d 1 RFT m 73.46 23.19 7.07 241.02Wiring overhead line in 2 single core, PVC insulated cable

with GI wire #8 SWG : 7/0.044"

15-33 Each Each 605.64 132.52 132.52 605.64Supply and Erection street light pole bracket 1.25" GI pipe

2m. long, complete with 2 pole clamps

15-34 Each Each 6,285.60 235.60 235.60 6,285.60Supply and Fixing dust & weather proof street light fitting

with reflector, 400W mercury vapour lamp etc comp.

15-35-a Each Each 1,506.10 235.60 235.60 1,506.10Supply and Erection pole mounted street light complete for

fitting 125/250 W mercury lamp : GEC make

15-35-b Each Each 3,018.60 235.60 235.60 3,018.60Supply and Erection pole mounted street light complete for

fitting 125/250 W mercury lamp : Philips make

15-36-a Each Each 542.90 58.90 58.90 542.90Supply and Fixing 125 W mercury vapour lamp with choke

15-36-b Each Each 936.15 58.90 58.90 936.15Supply and Fixing 250 W mercury vapour lamp with choke

15-36-c Each Each 2,781.40 58.90 58.90 2,781.40Supply and Fixing 400 W mercury vapour lamp with choke

15-37 Each Each 1,571.40 58.90 58.90 1,571.40Supply and Fixing mercury sodium lamp 360 Sunlux 400

W complete with choke

15-38 Each Each 482.40 58.90 58.90 482.40Supply and Fixing mercury blended lamp 160 W

15-39 Each Each 15,634.00 3,534.00 3,534.00 15,634.00a) Increase/Reduce

composite rate of

addition/reduction in

height of pole above

ground level b) The

item does not cover

cost of excavation,

which is payable

separately.

Supply and Erection MS angle lattice structure pole 36'

long 14"sq at base & 8"sq. at top for elec. distribution

15-40-a-01 Each Each 17,158.00 883.50 883.50 17,158.00The item does not

cover cost of

excavation, which is

payable separately.

Supply and Fixing GI tubular street light pole, 8' of 5" dia,

7' 4" dia, 5' of 3" dia, Single arm of 5' of 1.5" dia

15-40-a-02 Each Each 17,763.00 883.50 883.50 17,763.00Supply and Fixing GI tubular street light pole, 8' of 5" dia,

7' 4" dia, 5' of 3" dia, Double arm of 5' of 1.5" dia

15-40-b-01 Each Each 14,133.00 883.50 883.50 14,133.00Supply and Fixing GI tubular street light pole, 8' of 4" dia,

7' 3" dia, 5' of 2" dia, Single arm of 5' of 1.5" dia

15-40-b-02 Each Each 14,738.00 883.50 883.50 14,738.00Supply and Fixing GI tubular street light pole, 8' of 4" dia,

7' 3" dia, 5' of 2" dia, Double arm of 5' of 1.5" dia

15-40-b-03 Each each 22,361.65 136.40 136.40 22,361.65Providing street light poles of 40 ft height without arms

including fixing complete.

15-41 Job Job 3,874.33 1,178.00 1,178.00 3,874.33The item does not

cover cost of

excavation, which is

payable separately.

Earthing of iron clad/aluminium switches etc with GI wire

#8 SWG in GI pipe 0.5" dia

15-42 Each Each 2,956.50 294.50 294.50 2,956.50Supply and Erection 2'x2'x1/8" copper plate including

rivetting to copper tape & placing in mixture of salt etc

Page 87 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 88: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-43-a 1 RFT m 119.98 13.53 4.12 393.62Supply and Erection copper tape, including copper stapple

& copper nails etc : Size 1.5"x1/8"

15-43-b 1 RFT m 156.59 13.53 4.12 513.75Supply and Erection copper tape, including copper stapple

& copper nails etc : Size 2"x1/8"

15-44 Job Job 2,309.25 736.25 736.25 2,309.25Supply and Erection 1" dia & 1m long lightening

conductor copper rod with 5 spikes ball & base etc.

15-45 Each Each 553.55 17.67 17.67 553.55Wiring of light/fan/call-bell point in 3/0.029 PVC insulated

& sheathed cable on sahl wood strip

15-46 Each Each 391.14 17.67 17.67 391.14Wiring of 2/3-pin 5-Amp plug point in 3/0.029 PVC

insulated & sheathed cable on sahl wood

15-47-a 1 RFT m 25.44 12.08 3.68 83.48Wiring of main & sub-main in 2 single core PVC insulated

& sheathed cable : 3/0.029

15-47-b 1 RFT m 48.31 12.08 3.68 158.51Wiring of main & sub-main in 2 single core PVC insulated

& sheathed cable : 7/0.029

15-47-c 1 RFT m 104.39 19.32 5.89 342.48Wiring of main & sub-main in 2 single core PVC insulated

& sheathed cable : 7/0.044

15-47-d 1 RFT m 187.29 34.78 10.60 614.47Wiring of main & sub-main in 2 single core PVC insulated

& sheathed cable : 7/0.064

15-48-a 1 RFT m 11.01 8.21 2.50 36.12Wiring of sub main/earthing in 1 single core PVC insulated

& sheathed cable : 3/0.029

15-48-b 1 RFT m 16.45 7.73 2.36 53.97Wiring of sub main/earthing in 1 single core PVC insulated

& sheathed cable : 7/0.029

15-48-c 1 RFT m 28.54 7.73 2.36 93.65Wiring of sub main/earthing in 1 single core PVC insulated

& sheathed cable : 7/0.044

15-48-d 1 RFT m 51.70 13.53 4.12 169.63Wiring of sub main/earthing in 1 single core PVC insulated

& sheathed cable : 7/0.064

15-49 Each Each 934.39 28.27 28.27 934.39Wiring of light point in 3/0.029 PVC insulated sheathed

cable on sahl wood strip batten

15-50 Each Each 783.50 26.50 26.50 783.50Wiring of light/fan/call-bell point in 3/0.029 PVC insulated

bare cable in PVC pipe recessed

15-51 Each Each 415.34 12.96 12.96 415.34Wiring of 2/3-pin 5-Amp. plug point in 3/0.029 PVC

insulated bare cable in PVC pipe recessed

15-52 Each Each 1,409.15 40.05 40.05 1,409.15Wiring of light point in 3/0.029 PVC insulated bare cable

in PVC pipe recessed in wall comp.

15-53 Each Each 6,441.45 471.20 471.20 6,441.45Special earthing of iron/metal clad switches etc with copper

wire No. 8 SWG in GI pipe 1/2" dia

15-54 Each Each 233.34 29.45 29.45 233.34Supply and Erection enclosed switch of bakelite DP

(China) 15/30 Amp. fixed on wooden board complete

15-55-a Each Each 326.06 23.56 23.56 326.06Supply and erection of fancy wall type bracket with brass

holder & fancy shade : Single

15-55-b Each Each 519.66 23.56 23.56 519.66Supply and erection of fancy wall type bracket with brass

holder & fancy shade : Double

Page 88 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 89: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-56-a Each Each 164.97 29.45 29.45 164.97Supply and Erection white round globe with holder, gallery

& 100 Watt bulb complete : 6" dia.

15-56-b Each Each 225.47 29.45 29.45 225.47Supply and Erection white round globe with holder, gallery

& 100 Watt bulb complete : 8" dia.

15-56-c Each Each 346.47 29.45 29.45 346.47Supply and Erection white round globe with holder, gallery

& 100 Watt bulb complete : 10" dia.

15-57-a Each Each 225.47 29.45 29.45 225.47Supply and Erection white flat globe with holder, gallery &

100 W bulb complete : 8" dia

15-57-b Each Each 346.47 29.45 29.45 346.47Supply and Erection white flat globe with holder, gallery &

100 W bulb complete : 10" dia

15-57-c Each Each 527.97 29.45 29.45 527.97Supply and Erection white flat globe with holder, gallery &

100 W bulb complete : 12" dia

15-58 Each Each 634.45 29.45 29.45 634.45Supply and Erection white round globe 6" dia with angle

type bakelite gallery, holder & 60-W bulb complete

15-59 Each Each 319.05 58.90 58.90 319.05Supply and Erection 1' long strip light fitting comp. with

cover of opalescent perspex in plain finish 10-Watt

15-60 Each Each 860.13 73.63 73.63 860.13Supply and Erection double fluorescent tube light fitting 2

No. 4' long, 40-W with 2 chokes & starters complete

15-61-a Each Each 494.50 58.90 58.90 494.50Supply and Erection fluorescent tube light fitting including

4' rod, choke, starter, flexible wire etc : Single

15-61-b Each Each 845.40 58.90 58.90 845.40Supply and Erection fluorescent tube light fitting including

4' rod, choke, starter, flexible wire etc : Double

15-62 Each Each 467.67 44.17 44.17 467.67Supply and Erection porch-light fitting round/square type

with gallery, holder & 40 W bulb

15-63-a Each Each 724.40 58.90 58.90 724.40Supply and Erection gate-light fitting complete with holder

& 160-Watt mercury blended lamp: Small

15-63-b Each Each 845.40 58.90 58.90 845.40Supply and Erection gate-light fitting complete with holder

& 160-Watt mercury blended lamp: Medium

15-63-c Each Each 966.40 58.90 58.90 966.40Supply and Erection gate-light fitting complete with holder

& 160-Watt mercury blended lamp: Large

15-64-a Each Each 1,296.75 147.25 147.25 1,296.75The rate does not

include cost of GI

pipe and excavation

and are to be paid

separatively

Supply and Erection garden-light fitting with holder and

160 W mercury blended lamp & choke : 18" dia

15-64-b Each Each 1,478.25 147.25 147.25 1,478.25Supply and Erection garden-light fitting with holder and

160 W mercury blended lamp & choke : 19" dia

15-64-c Each Each 1,962.25 147.25 147.25 1,962.25Supply and Erection garden-light fitting with holder and

160 W mercury blended lamp & choke : 22" dia

Page 89 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 90: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-65-a Each Each 1,690.00 147.25 147.25 1,690.00The rate does not

include cost of GI

pipe and excavation

and are to be paid

separatively

Supply and Erection garden-light fitting with porcelain

holder 125 W mercury vapour lamp & choke : 18" dia

15-65-b Each Each 1,871.50 147.25 147.25 1,871.50Supply and Erection garden-light fitting with porcelain

holder 125 W mercury vapour lamp & choke : 19" dia

15-65-c Each Each 2,355.50 147.25 147.25 2,355.50Supply and Erection garden-light fitting with porcelain

holder 125 W mercury vapour lamp & choke : 22" dia

15-66-a Each Each 1,962.25 147.25 147.25 1,962.25Supply and Erection flood-light fitting with holder,

complete 14" dia with 500-W lamp

15-66-b Each Each 3,232.75 147.25 147.25 3,232.75Supply and Erection flood-light fitting with holder,

complete 19«" dia with 1000-W lamp

15-67 Each Each 142.80 88.35 88.35 142.80Making hole in wall with necessary masonry work for

exhaust fan any size complete

15-68-a Each Each 1,525.63 73.63 73.63 1,525.63Asia, Breeze, Climax,

Millat, National &

Pak fans are the

approved makes.

Supply and Erection best quality AC ceiling fan complete

with GI rod, canopy, blades & regulator : 36" sweep

15-68-b Each Each 2,009.63 73.63 73.63 2,009.63Supply and Erection best quality AC ceiling fan complete

with GI rod, canopy, blades & regulator : 48" sweep

15-68-c Each Each 2,433.13 73.63 73.63 2,433.13Supply and Erection best quality AC ceiling fan complete

with GI rod, canopy, blades & regulator : 56" sweep

15-69-a Each Each 1,329.40 58.90 58.90 1,329.40Asia, Breeze, Climax,

Millat, National &

Pak fans are the

approved makes.

Supply and Erection best quality exhaust fan complete with

shutter & regulator : 12"sweep

15-69-b Each Each 1,571.40 58.90 58.90 1,571.40Supply and Erection best quality exhaust fan complete with

shutter & regulator : 16"sweep

15-69-c Each Each 1,825.50 58.90 58.90 1,825.50Supply and Erection best quality exhaust fan complete with

shutter & regulator : 18"sweep

15-70-a Each Each 2,716.10 235.60 235.60 2,716.10Supply and Erection transpower auto circuit breaker

3-phase, 400V fungus moisture proofing : 30 Amp.

15-70-b Each Each 3,260.60 235.60 235.60 3,260.60Supply and Erection transpower auto circuit breaker

3-phase, 400V fungus moisture proofing : 60 Amp.

15-70-c Each Each 5,724.77 279.77 279.77 5,724.77Supply and Erection transpower auto circuit breaker

3-phase, 400V fungus moisture proofing : 100 Amp.

15-71-a Each Each 370.88 44.17 44.17 370.88Supply and Erection single phase imported auto circuit

breaker 6 Amp.

15-71-b Each Each 467.67 44.17 44.17 467.67Supply and Erection single phase imported auto circuit

breaker 15 Amp.

15-71-c Each Each 588.67 44.17 44.17 588.67Supply and Erection single phase imported auto circuit

breaker 20 Amp.

Page 90 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 91: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-71-d Each Each 600.78 44.17 44.17 600.78Supply and Erection single phase imported auto circuit

breaker 30 Amp.

15-72-a Each Each 4,365.35 511.50 511.50 4,365.35Supply and Erection of bus bars for 500 volts 3 phase AC

S/W 4 copper bars 40 Amp with bar size 1 1/2" X 1/8"

15-72-b Each Each 4,380.48 511.50 511.50 4,380.48Supply and Erection of bus bars 500 volts 3 phase AC

supply with 4 copper bars - 100 Amp with bar size1 1 1/2"

X 1/8"

15-72-c Each Each 5,218.70 899.00 899.00 5,218.70Supply and Erection of bus bars 500 volts 3 phase AC

supply with 4 copper bars - 200 Amp with bar size 2"X

1/8"

15-72-d Each Each 5,427.58 1,092.75 1,092.75 5,427.58Supply and Erection of bus bars 500 volts 3 phase AC

supply with 4 copper bars - 300 Amp with bar zise 2" X

3/16"

15-72-e Each Each 8,040.95 1,271.00 1,271.00 8,040.95Supply and Erection of bus bars 500 volts 3 phase AC

supply with 4 copper bars - 500 Amp with zise 2" X 1/4"

15-73-a Each Each 338.42 111.91 111.91 338.42Supply and Erection of bracket of channel 3" X 1 1/2" X

1/4" section 2' long for 2 lines

15-73-b Each Each 553.00 141.36 141.36 553.00Supply and Erection of bracket of MS channel 3" X 1 1/2"

X 1/4" Section:- 4' long for 4 lines

15-74 1 RFT m 48.34 14.26 4.35 158.59Supply and Erection of anchor rod honley type for poles

i/e clamps & 7/13 SWG stay wire straning screws PCC

1:3:6

15-75-a Each Each 9,821.50 1,472.50 1,472.50 9,821.50Supply and Erection cubical type factory fabricated

floor/wall mounting steel main board comp. : On surface

15-75-b Each Each 10,057.10 1,708.10 1,708.10 10,057.10Supply and Erection cubical type factory fabricated

floor/wall mounting steel main board comp. : Recessed

15-76-a Each each 1,939.00 124.00 124.00 1,939.00Flouresent tube lights fitting 2.5x2.5 feet square type

suitable for fixing in recess or direct on complete with 4

Nos 2 ft 20 watts tubes, chokes, starters, holders complete

in all respect in steel body.

15-76-b each each 1,576.00 124.00 124.00 1,576.00Supply and Fixing of fluoresent tube fitting rectanglular

box types housing made of 22 SWG stave enamelled steel

sheet having spring load inner frame attachement with

acrylic or polythene complete with 2 No 4 ft 40 watts

15-77-a each each 1,523.36 196.85 196.85 1,523.36Supply and Fixing electric AC exhuast/fresh air

circulation(double way) 220/230 single phase plastic frame

body and blade complete 8"x8"

15-77-b each each 1,666.41 196.85 196.85 1,666.41Supply and Fixing electric AC exhuast/fresh air

circulation(double way) 220/230 single phase plastic frame

body and blade complete 10"x10"

15-77-c each each 4,998.18 73.78 73.78 4,998.18Supply and fixing electric AC exhaust/fresh air

circulation(Double way) 220/230 single phase plastic frame

body and blade complete 12"x12"

Page 91 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 92: Rate nwfp 2008

Item Code Description

ELECTRIC INSTALLATIONSChapter #

:

15

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

15-78 each each 1,853.70 99.20 99.20 1,853.70Supply and Fixing bracket fan pak made complete

15-79-a 1 RFT m 19.48 14.88 4.54 63.91Supply and Fixing PVC conduit for surface wiring (dura

duct) 1/2" including all charges for nail screws etc

15-79-b 1 RFT m 22.63 14.88 4.54 74.23PVC conduit for surface wiring (dura duct) 1" including all

charges for nail screws etc complete

15-79-c 1 RFT m 24.99 14.88 4.54 81.97PVC conduit for surface wiring (dura duct) 1.5" including

all charges for nail screws etc complete

15-79-d 1 RFT m 29.70 14.88 4.54 97.46PVC conduit for surface wiring (dura duct) 2" including all

charges for nail screws etc complete

15-80 each each 134.30 49.60 49.60 134.30Supply and Fixing dimmer switch complete

15-81 each each 152.45 49.60 49.60 152.45Supply and Fixing 20 Amp power plug

15-82 each each 170.60 49.60 49.60 170.60Supply and Fixing Asia porcelin power plug 30 Amp

15-83 each each 128.25 49.60 49.60 128.25Supply and fixing light plug 10 Amp

15-84 each each 65.75 29.45 29.45 65.75Supply and fitting of capacitor 2.2 uf for ceiling fans

15-85 each each 145.71 36.81 36.81 145.71Supply and fitting of ball bearing of size 6201, 6202 or

6203 for ceiling fans

15-86 each each 34.31 6.48 6.48 34.31Supply and erection of cut out, bakelite open type

15-87 each each 40.36 6.48 6.48 40.36Supply and erection of cut out bakelite Recessed type cut

out

15-88 each each 39.62 10.58 10.58 39.62Supply and erection of kit kat 500 volts 15/20 Amp

15-89 each each 40.90 11.86 11.86 40.90Supply and erection of kit kat 500 volts 30/35 Amp

15-90 each each 60.56 17.00 17.00 60.56Supply and erection of kit kat 500 volts 60/65 Amp

15-91 each each 97.81 20.37 20.37 97.81Supply and erection of kit kat 500 volts 100 Amp

15-92 each each 139.68 23.52 23.52 139.68Supply and erection of kit kat 500 volts 200 Amp

15-93 each each 288.51 23.52 23.52 288.51Supply and erection of kit kat 500 volts 300 Amp

15-94 each each 359.47 29.14 29.14 359.47Supply and erection of kit kat 500 volts 400 Amp

15-95-a Each each 41,831.26 449.50 449.50 41,831.26Providing & Fixing Honda Generator EP 2500ex, 2.2 KVA

Petrol driven.

15-95-b Each each 44,856.26 449.50 449.50 44,856.26Providing & Fixing Honda Generator EP 2500ex, 2.2 KVA

Petrol-cum-Gas driven

15-95-c Each each 69,056.26 449.50 449.50 69,056.26Providing & Fixing Honda Generator EP 2800ex, 3.1 KVA

Petrol-cum-Gas driven.

15-95-d Each each 66,031.26 449.50 449.50 66,031.26Providing & Fixing Honda Generator EP 2800ex, 3.1 KVA

Petrol driven.

Page 92 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 93: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-01 100 Cft m3 8,232.46 784.83 2,222.39 2,907.27The nominal

thickness of bricks

shall be taken for the

purpose of

measurement and

payment.

Providing and Laying sub-base course of brick on edge

4.5" thick including compaction to required camber &

grade

16-02 100 Cft m3 2,692.68 295.58 837.00 950.91To be used only when

brick aggregate is

cheaper than stone

aggregate.

Providing and Laying sub-base course of brick aggregate,

including compaction to required camber, grade & density

16-03-a 100 Cft m3 1,795.34 155.24 439.58 634.02a) The carriage of the

whole distance to side

of work shall be

calculated on the

basis of the rates of

the actual means of

transport used in

carriage that is i.e

road and rail is the

case may be. b) It

shall be payable from

the nearest approved

quarry.

Granular Sub Base Course using Pit Run Gravel

16-03-b 100 Cft m3 2,363.58 93.93 265.98 834.69c) The quantity of pit

run or bed run gravel

in crush stone

aggregate for payment

of carriage shall be

taken as per actual

volume but not more

than 120 Cft.

Granular Sub Base Using Crushed Stone Aggregate

16-04-a 100 Cft m3 2,730.36 93.93 265.98 964.22Aggregate Base Course

16-04-b 100 Cft m3 2,763.98 93.93 265.98 976.09Water Bound Macadam Base Course

16-05 100 Rft m 2,546.50 27.97 852.50 83.55Providing and Laying road edging of 3" wide & 9" deep

brick on end, complete

16-06 100 Sft m2 796.27 0.77 7.20 85.68Bitumenous Prime Coat

16-07 100 Sft m2 375.85 2.17 20.16 40.44Bitumenous Tack Coat

16-08-a 100 Sft m2 1,412.06 1.47 13.69 151.94Single bitumenous Surface Treatment

16-08-b 100 Sft m2 2,945.69 2.24 20.83 316.96Double bitumenous Surface Treatment

16-08-c 100 Sft m2 3,559.60 3.71 34.44 383.01Triple bitumenous Surface Treatment

16-09-a 100 Sft m2 910.74 3.77 35.03 98.00Resurfacing of road complete with per 100sft : 22 Ibs.

bitumen, 2.5"cft bajri/crush aggregate

16-09-b 100 Sft m2 847.17 5.28 49.03 91.16Resurfacing of road complete with per 100sft : 20 Ibs.

bitumen, 2"cft bajri/crush aggregate

Page 93 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 94: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-10 100 Sft m2 139.50 15.01 139.50 15.01Scarifying/Dismantling old road surface, including removal

of debris within one chain (NHA specified)

16-11-a 100 Sft m2 2,017.78 16.11 149.73 217.11Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 1"

Thick, without prime coat or tack coat

16-11-b 100 Sft m2 2,961.46 23.08 214.52 318.65Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 1.5"

Thick

16-11-c 100 Sft m2 3,925.46 30.05 279.31 422.38Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 2"

Thick

16-12-a 100 Cft m3 29,778.15 114.70 324.78 10,516.06Asphaltic Base Course (Asphalt Batch Plant Hot Mixed)

16-12-b 100 Cft m3 34,188.40 114.70 324.78 12,073.53Asphaltic Wearing Course (Asphalt Batch Plant Hot

Mixed)

16-12-c Mile t/km 5.35 0.00 0.00 5.35Carriage of asphalt concrete from asphalt batch plant to the

site of work by dump trucks.

16-13 100 Rft m 42,116.53 292.50 8,915.34 1,381.78The rate includes the

cost of steel, its

fabrication, laying in

position and

fastening, including

cost of binding wire

and removal of rust

from the bars, etc

Providing RCC railing on bridges (3 feet high)

16-14 100

Rft/3rows

m/3rows 62,183.38 138.68 4,227.94 2,039.61Providing and fixing GI pipe railing (3 feet high)

16-15-a Each Each 2,135.84 951.70 951.70 2,135.84The rate is for

complete item of

work according to

standard design

including cement

concrete foundation

block and painting

letters etc.

P&E at site : RCC km stone

16-15-b Each Each 396.58 228.16 228.16 396.58P&E at site : RCC 1/10th km stone.

16-15-c Each Each 755.32 140.43 140.43 755.32P&E at site : RCC boundry pillar.

16-16-a 100 Sft m2 72,206.77 827.35 7,689.08 7,769.45The cost of pedestal,

PCC and excavation

is included in the rate.

Road signs (not exceeding 1 m2) without reflection sheet &

lettering : Supply and Fixing at site with PCC 1:3:6 upto

max 3' depth

16-16-b 100 Sft m2 66,179.77 687.94 6,393.51 7,120.94Road signs (not exceeding 1 m2) without reflection sheet &

lettering : Supply to the C&W store/site of work

16-17-a 100 Sft m2 58,678.16 949.49 8,824.27 6,313.77The cost of pedestal,

PCC and excavation

is included in the rate.

Road sign (any size) double pedestal 4"x2"x0.25" 11' long

without reflection sheet & lettering: Supply and Fixing at

site with PCC 1:3:6 max 3' depth

16-17-b 100 Sft m2 49,707.84 1,058.25 9,835.06 5,348.56Road sign (any size) double pedestal 4"x2"x0.25" 11' long

without reflection sheet & lettering: Supply to the C&W

store/site of work

Page 94 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 95: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-18-a 100 Sft m2 49,436.80 111.56 1,036.80 5,319.40a) The rate does not

include the cost of

road signs b) The

work with sub-items a

and b shall only be

carried out on the

written permission of

the SE.

Supply and Fixing reflective sheet on MS/aluminium road

signs etc including lettering : Diamond grade

16-18-b 100 Sft m2 27,656.80 111.56 1,036.80 2,975.87Supply and Fixing reflective sheet on MS/aluminium road

signs etc including lettering : High intensity grade

16-18-c 100 Sft m2 7,086.80 111.56 1,036.80 762.54Supply and Fixing reflective sheet on MS/aluminium road

signs etc including lettering : Engineering grade

16-19-a-01 Each Each 521.00 279.00 279.00 521.00Supply and Fixing aluminium alloy road studs as per specs

Large, strip 146x30mm, 171 beads: Uni-direction

16-19-a-02 Each Each 763.00 279.00 279.00 763.00Supply and Fixing aluminium alloy road studs as per specs

Large, strip 146x30mm, 171 beads: Bi-direction

16-19-b-01 Each Each 490.75 279.00 279.00 490.75Supply and Fixing aluminium alloy road studs as per specs

Medium, strip 114x18mm, 74 beads: Uni-direction

16-19-b-02 Each Each 702.50 279.00 279.00 702.50Supply and Fixing aluminium alloy road studs as per specs

Medium, strip 114x18mm, 74 beads: Bi-direction

16-19-c-01 Each Each 430.25 279.00 279.00 430.25Supply and Fixing aluminium alloy road studs as per specs

Small, strip 75x14mm, 43 beads: Uni-directional

16-19-c-02 Each Each 581.50 279.00 279.00 581.50Supply and Fixing aluminium alloy road studs as per specs

Small, strip 75x14mm, 43 beads: Bi-directional

16-19-c-03 Each each 502.50 139.50 139.50 502.50Supply & Fixing Cat Eye single as specified

16-20 Cwt kg 5,791.81 19.91 1,015.75 113.52The cost of RCC base

for the foundation is

not included in the

rate which is payable

separately.

Providing and Fixing gantry of structural steel sections as

per design / drawings including foundation complete

16-21 100 Cft m3 7,554.78 405.06 1,147.00 2,667.95The nominal

thickness of bricks

shall be taken for the

purpose of

measurement and

payment.

Providing and Laying dry brick pavement/soling in streets

etc including prep, water, compaction & sand cushion

16-22 100 Cft m3 1,409.09 1.48 4.18 497.62For different

thicknesses, rate is to

be calculated on

pro-rate basis.

Supply & spreading 1"-1.5" guage shingle on road surface

including compaction

16-23-a 100 Rft m 43,635.39 285.10 8,689.92 1,431.61Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

460mm

16-23-b 100 Rft m 62,843.36 356.49 10,865.78 2,061.79Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

610mm

Page 95 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 96: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-23-c 100 Rft m 91,205.55 427.80 13,039.29 2,992.31Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

760mm

16-23-d 100 Rft m 107,377.73 499.04 15,210.86 3,522.89Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

910mm

16-23-e 100 Rft m 148,203.11 570.36 17,384.59 4,862.31Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

1070mm

16-23-f 100 Rft m 189,024.64 641.78 19,561.37 6,201.59Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

1220mm

16-23-g 100 Rft m 259,215.36 712.99 21,731.90 8,504.44Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia:

1520mm

16-24 100 Cft m3 3,507.28 92.06 260.70 1,238.59Granular Material in Bed to RCC Pipe Culvert

16-25-a 100 Rft m 160,823.70 2,976.77 90,732.04 5,276.37a) The bore hole dia

shall not be less than

200mm and the

method of execution

of pre-construction

boring shall be done

with casing and

appropriate to soil

encountered.

Confirmatory Boring including SPT's, samples, lab test

bore-hole logs & Report : Alluvial Soils

16-25-b 100 Rft m 179,268.95 2,976.77 90,732.04 5,881.53b) Preparation and

submission of

bore-logs based on

soil classification

with SPT's values as

per BS-1377 is

included in the rate.

Confirmatory Boring including SPT's, samples, lab test,

bore-hole logs, report : in Gravelly Soil

16-26-a Job Job 377,898.63 0.00 0.00 377,898.59Rates includes all

material, equipment,

instruments and

temporary work

required to construct

test pile, load test and

load settlement

readings and

preparation of graphs

of the test pile.

Pile Load Testing : Max Load up to 240 tonne

16-26-b Job Job 408,148.63 0.00 0.00 408,148.59Pile Load Testing : Max Load 240 - 300 tonne

16-26-c Job Job 438,398.63 0.00 0.00 438,398.59Pile Load Testing : Max Load 300 - 360 tonne

16-26-d Job Job 468,648.63 0.00 0.00 468,648.59Pile Load Testing : Max Load 360 - 600 tonne

16-27-a 100 Rft m 70,091.67 0.00 0.00 2,299.60Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia

up to 760mm

16-27-b 100 Rft m 88,536.91 0.00 0.00 2,904.75Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia

760 - 1220 mm

Page 96 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 97: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-27-c 100 Cft m 110,670.23 0.00 0.00 3,630.91Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia

1220 - 2000 mm

16-28-a 100 Rft m 88,536.91 0.00 0.00 2,904.75Boring for Cast-in-place RCC Piles in Gravelly Soils : Dia

up to 660mm

16-28-b 100 Rft m 140,183.34 0.00 0.00 4,599.19Boring for Cast-in-place RCC Piles in Gravelly Soils : Dia

660 - 910 mm

16-29 Cwt kg 6,481.65 6.86 349.99 127.04Supply fabricate & install welded MS lining in piles of

thickness as per specs/drwg

16-30-a Cubic

Inch

cm3 21.77 0.15 2.41 1.33Supply and Fixing Neoprene Bearing Pad as per specs &

design

16-30-b Cwt kg 6,674.33 16.36 834.64 130.82Supply and Fixing Steel Bearing Pads as per specs &

design

16-34 100 Rft m 3,146.94 16.74 510.23 103.25Supply and Fixing spirally wound sheath of 50mm dia. for

pre-stressing of cables in precast conc. girders

16-35 Set Set 688.70 83.70 83.70 688.70Supply and Fixing stressing anchorages for high tensile

steel wire cables in precast girders

16-36 Ft m 294.90 725.57 221.15 967.53Launching girders in place, including lifting & handli any

number of time including temporary works comp

16-37 Each Each 837.30 474.30 474.30 837.30Stressing Cable of High Tensile Steel Wire Strands

16-38 100 Rft m 1,841.45 13.02 396.84 60.42Inject Cement Grout in Sheath Pipe after stressing

16-39 Each Each 142.63 83.05 83.05 142.63Cut off projecting wire ends of cables & make good

anchorage recess with 1:2:4 cem. conc.

16-40 Cwt kg 5,657.95 17.29 881.89 110.90Supply and place in position MS expansion joint

assemblies as specified & as per drawing

16-41 Each Each 297.30 85.25 85.25 297.30Supply and place in position galvanised steel 3" dia drain

scuppers in deck slab as per specs/drwg

16-42 Each Each 250.57 43.40 43.40 250.57Providing and Fixing rain water outlet of AC pipe

16-43 100 Cft m3 2,308.96 766.26 2,169.81 815.40Supply and Fixing polystrene fill in expansion joints &

under diaphragms at transoms.

16-44 100 Rft m 12,709.06 102.32 3,118.60 416.96Providing and Laying expansion joint of neoprene strip

4"x1/4" and plastic bitumen

16-46 100 Rft m 1,942.75 39.92 1,216.75 63.74Repair to cracks to reinforced or plain cement concrete

work by grouting with cement gun in (1:2) cement sand

mortar including cutting the chase of required size.

16-47 100 Sft m2 279.00 30.02 279.00 30.02Dismantling bitumen carpet of any description from

existing roads surface including its removal and disposal

within 3 chains lead as desired.

16-48 100 Sft m2 3,425.23 70.88 658.72 368.55Removing the existing worn out bitumanious surface

having pot holes and ruts in patches of regular shape

brushing and re-carpeting with 1" thick (consolidated)

asphalt macadam as per specifications.

Page 97 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 98: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-49 100 Sft m2 3,215.98 48.36 449.47 346.04Providing and Laying 1" thick(consolidated) asphalt

macadam with liquid asphalt (cut backs) of any approved

grade with premixed sand seal coat, as specified.

16-50 100 Sft m2 4,449.94 73.13 679.64 478.81Removing the existing worn out bitumanious surface pot

holes and ruts in patches of regular shape brushing and

re-carpeting with 2" thick(consolidated) asphalt macadam

as per specificaiton complete

16-51 100 Sft m2 4,240.69 50.61 470.39 456.30Providing and Laying 2" thick (consolidated) asphalt

macadam with liquid asphalt(cut backs) of approved grade

with precoated bajri seal coat as specified.

16-52 100 Sft m2 6,322.03 93.03 864.62 680.25Removing of existing worn out bitumanious surface pot

holes and ruts in patches and re-carpeting with 3"

thick(consolidated) asphalt macadam as per

specifiedcomplete including disposal of excavated stuff

within one chain

16-53 100 Sft m2 6,112.78 70.52 655.37 657.73Providing and Laying 3" thick (consolidated) asphalt

macadam with liquid asphalt(cut backs) of approved grade

with precoated bajri seal coat as specified.

16-54 100 Sft m2 2,054.67 2.04 18.94 221.08Surface dressing with bituman 80/100 or any other

approved grade on a primary coat of liquid asphalt (cut

backs) of any approved grade primer at 22lbs&bituman at

35lbs with 5cft of 1/2 standard size bajri per %sft of road

surface complete with rolling.

16-55 10 Rft m 4,233.78 16.27 49.60 1,389.04Providing and Laying PVC pipe (b) 8" dia in foot path of

bridge for utilities.

16-56 100 Cft m3 1,984.48 230.77 653.48 700.81Providing and filling sand behind abutment of bridges,

culverts.

16-57 1000 Cft m3 10,588.24 32.93 932.48 373.92Formation of shoulder with permeable material less than 7

% from 200 seive and P.I less than 4 as specified by NHA

16-58-a 100 Sft m2 897.56 4.50 41.85 96.58Cold Milling of asphalt concrete 0-70 mm

16-58-b 100 Sft m2 622.94 3.00 27.90 67.03Cold Milling of asphalt concrete 0-50 mm

16-58-c 100 Sft m2 351.10 1.80 16.74 37.78Cold Milling of asphalt concrete 0-30 mm

16-59 100 Sft m2 680.85 11.81 109.74 73.26Seal Coat / Pad Coat

16-60 100 Cft m3 15,311.28 602.12 1,705.00 5,407.13Providing and Laying Asphalt concrete in pot holes/ deep

patching upto 30 cm including ramming completel

16-61 100 Sft m2 170.50 18.35 170.50 18.35Grooving in existing BT road of size 4x4 cm @ 2 meter

c/c.

16-62 100 Sft m2 646.88 38.36 356.50 69.60Leveling dressing and compaction with power roller of

existing base coarse layer after asphalt scarification.

16-63-a 100 Rft m 13,074.94 37.63 1,147.00 428.97Providing and fixing kerb stone (12"x18"x6") in cement

sand mortar 1:3 in center media or round about as

specified.

Page 98 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 99: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-63-b 100 Rft m 12,469.94 37.63 1,147.00 409.12Providing and fixing kerb stone (12"x14"x6") in cement

sand mortar 1:3 in center media or round about as

specified.

16-63-c 100 Rft m 11,864.94 37.63 1,147.00 389.27Providing and fixing kerb stone (12"x12"x6") in cement

sand mortar 1:3 in center media or round about as

specified.

16-64 100 Cft m3 26.91 2.03 5.74 9.50Bailing out water by Mechanical mean.

16-65-a 100 Rft m 2,754.95 5.03 153.45 90.39Pavement marking in reflective thermoplast paint with

glass beads for line 15 cm width.

16-65-b 100 Rft m 3,639.46 5.03 153.45 119.40Pavement marking in reflective thermoplast paint with

glass beads for line 20 cm width.

16-66-a 100 Rft m 1,544.95 5.03 153.45 50.69Pavement marking in non-reflective thermoplast paint for

line 15 cm width.

16-66-b 100 Rft m 2,018.06 5.03 153.45 66.21Pavement marking in non-reflective thermoplast paint for

line 20 cm width.

16-67-a 100 Rft m 1,060.95 5.03 153.45 34.81Pavement marking in reflective chlorinated rubber paint

with glass beads for line 15 cm width.

16-67-b 100 Rft m 1,369.50 5.03 153.45 44.93Pavement marking in reflective chlorinated rubber paint

with glass beads for line 20 cm width.

16-68-a 100 Rft m 818.95 5.03 153.45 26.87Pavement marking in reflective chlorinated rubber paint for

line 15 cm width.

16-68-b 100 Rft m 1,045.22 5.03 153.45 34.29Pavement marking in reflective chlorinated rubber paint

for line 20 cm width.

16-69 100 Cft m3 3,479.56 199.79 565.75 1,228.80Providing & laying stone soling in water logged area

including granular filling & compaction complete.

16-70 100 Sft m2 139.50 15.01 139.50 15.01Tucking and chipping of road surface before hot surface

dressing over existing road.

16-71 100 Cft m3 26,926.86 100.21 283.77 9,509.14Leveling course on existing surface of road.

16-72-a Each each 11,578.70 83.70 83.70 11,578.70Jack Anchorage For 20 to 24 Wires 0.5" Strand

(Comprising Trumpet, Stressing Block & Wedges

Complete)

16-72-b Each each 9,279.70 83.70 83.70 9,279.70Jack Anchorage For 16 to 19 Wires 0.5" Strand

(Comprising Trumpet, Stressing Block & Wedges

Complete)

16-72-c Each each 5,528.70 83.70 83.70 5,528.70Jack Anchorage For 10 to 12 Wires 0.5" Strand

(Comprising Trumpet, Stressing Block & Wedges

Complete)

16-72-d Each each 7,464.70 83.70 83.70 7,464.70Jack Anchorage For 13 to 15 Wires 0.5" Strand

(Comprising Trumpet, Stressing Block & Wedges

Complete)

16-72-e Each each 4,318.70 83.70 83.70 4,318.70Jack Anchorage For 8 to 9 Wires 0.5" Strand (Comprising

Trumpet, Stressing Block & Wedges Complete)

Page 99 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 100: Rate nwfp 2008

Item Code Description

ROADS AND BRIDGESChapter #

:

16

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

16-72-f Each each 3,471.70 83.70 83.70 3,471.70Jack Anchorage For 5 to 7 Wires 0.5" Strand (Comprising

Trumpet, Stressing Block & Wedges Complete)

16-72-g Each each 2,261.70 83.70 83.70 2,261.70Jack Anchorage For upto 4 Wires 0.5" Strand (Comprising

Trumpet, Stressing Block & Wedges Complete)

16-73-a 1 Rft m 129.73 16.73 5.10 425.62Un-galvanized Sheath for 20 to 24 Wires 0.5" Strand Cable

16-73-b 1 Rft m 112.79 16.73 5.10 370.05Un-galvanized Sheath for 16 to 19 Wires 0.5" Strand Cable

16-73-c 1 Rft m 97.06 16.73 5.10 318.44Un-galvanized Sheath for 13 to 15 Wires 0.5" Strand Cable

16-73-d 1 Rft m 84.96 16.73 5.10 278.74Un-galvanized Sheath for 10 to 12 Wires 0.5" Strand Cable

16-73-e 1 Rft m 77.70 16.73 5.10 254.92Un-galvanized Sheath for 8 to 9 Wires 0.5" Strand Cable

16-73-f 1 Rft m 70.44 16.73 5.10 231.10Un-galvanized Sheath for 5 to 7 Wires 0.5" Strand Cable

16-73-g 1 Rft m 59.55 16.73 5.10 195.37Un-galvanized Sheath for upto 4 Wires 0.5" Strand Cable

16-73-h Each each 2,075.10 623.10 623.10 2,075.10Stressing and Grouting for Cables upto 24/0.5" (Single End

Stressing).

16-73-i Each each 1,867.40 415.40 415.40 1,867.40Stressing and Grouting for Cables ranging from 13/0.5" to

24/.05" (Single End Stressing).

16-73-j Each each 1,749.60 297.60 297.60 1,749.60Stressing and Grouting for Cable below 13/0.5" (Single

End Stressing).

16-74-a Tonne ton 163,350.00 0.00 0.00 165,971.28Supply of High Tensile Pre-stressed concrete steel wire

strand Grade 270K 0.5" dia. Packed in standard

reeless/weldless coils of two 2000 kgs approximately

binded and wraped in Hessian Cloth.

16-74-b Tonne ton 127,050.00 0.00 0.00 129,088.77Supply of P.C Steel wire Dia 7 mm and 8 mm. Packed in

reeless coils of 600 kgs to 800kgs properly binded.

16-74-c Tonne ton 114,950.00 0.00 0.00 116,794.60Supply of P.C Steel wire Dia 4 mm and 5 mm. Packed in

reeless coils of 600 kgs to 800kgs properly binded.

16-75-a 1 Rft m 173.29 16.73 5.10 568.54Galvanized Sheath for 20 to 24 Wires 0.5" Strand Cable

16-75-b 1 Rft m 150.30 16.73 5.10 493.11Galvanized Sheath for 16 to 19 Wires 0.5" Strand Cable

16-75-c 1 Rft m 129.73 16.73 5.10 425.62Galvanized Sheath for 13 to 15 Wires 0.5" Strand Cable

16-75-d 1 Rft m 112.79 16.73 5.10 370.05Galvanized Sheath for 10 to 12 Wires 0.5" Strand Cable

16-75-e 1 Rft m 103.11 16.73 5.10 338.29Galvanized Sheath for 8 to 9 Wires 0.5" Strand Cable

16-75-f 1 Rft m 93.43 16.73 5.10 306.53Galvanized Sheath for 5 to 7 Wires 0.5" Strand Cable

16-75-g 1 Rft m 78.91 16.73 5.10 258.89Galvanized Sheath for upto 4 Wires 0.5" Strand Cable

16-76-a 8 Rft m 12,438.19 0.00 0.00 5,100.96Precast Reinfored Concrete Kerb New Jersy Barrier for

Median (Double Face)

16-76-b 8 Rft m 8,659.55 0.00 0.00 3,551.32Precast Reinforced Concrete Kerb New Jersy Barrier for

Bridge (Single Face)

16-77 100 Sft m2 3,836.66 98.77 917.91 412.82Repair to pot holes including cleaning, brushing, removal

of loose material and filling of the same with clean stone of

size 0.75" to 1.5" with hot bitumen manual compaction

with rammer (water bound 3% biutmen)

Page 100 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 101: Rate nwfp 2008

Item Code Description

LINING OF CANALSChapter #

:

17

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

17-01-a 100 Sft m2 311.55 33.52 311.55 33.52Formation, dressing and preparing sub-grade in bed

17-01-b 100 Sft m2 434.00 46.70 434.00 46.70Formation, dressing and preparing sub-grade On slope

17-02 100 Sft m2 1,309.88 91.73 852.50 140.94Stabilized layer of cement, sand mortar 1:30 2" thick on

slope

17-03-a 100 Sft m2 816.88 65.94 612.87 87.901/2" thick plaster of cement, sand motar 1:10 in bed

17-03-b 100 Sft m2 986.76 84.22 782.75 106.171/2" thick plaster of cement, sand motar 1:10 On slope

17-04-a 100 Sft m2 1,657.22 84.22 782.75 178.321«" thick plaster of cement, sand mortar 1:6 in bed

17-04-b 100 Sft m2 1,874.22 107.57 999.75 201.671«" thick plaster of cement, sand mortar 1:6 On slope

17-05-a 100 Sft m2 955.42 65.94 612.87 102.803/8" thick plaster of cement, sand mortar 1:3 in bed

17-05-b 100 Sft m2 1,125.30 84.22 782.75 121.083/8" thick plaster of cement, sand mortar 1:3 On slope

17-06-a 100 Cft m3 12,612.88 1,086.55 3,076.75 4,454.20The rates covers

laying tiles including

mortar item 17.01 to

17.05 are payable

separately.

Lining with Brick tiles 12"x6"x2", in c/s mortar 1:6 over a

layer of 1/8" thick c/s mortar 1:6 (in bed)

17-06-b 100 Cft m3 13,039.13 1,237.07 3,503.00 4,604.73Lining with Brick tiles 12"x6"x2", in c/s mortar 1:6 over a

layer of 1/8" thick c/s mortar 1:6 (On slope)

17-07-a 100 Cft m3 13,685.42 1,086.55 3,076.75 4,832.96dittoLining with Brick tiles 12"x6"x2", in c/s mortar 1:3 over a

layer of 1/8" thick c/s mortar 1:3 (in bed)

17-07-b 100 Cft m3 14,111.67 1,237.07 3,503.00 4,983.49Lining with Brick tiles 12"x6"x2", in c/s mortar 1:3 over a

layer of 1/8" thick c/s mortar 1:3 (On slope)

17-08-a 100 Cft m3 10,634.53 1,086.55 3,076.75 3,755.55dittoLining with bricks 9"x4.5"x3" (First Class) in c/s mort. 1:6

ove a layer of 1/8" thick c/s mortar 1:6 (in bed)

17-08-b 100 Cft m3 11,060.78 1,237.07 3,503.00 3,906.08Lining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:6

over a layer of 1/8" thick c/s mortar 1:6 (On slope)

17-09-a 100 Cft m3 11,707.08 1,086.55 3,076.75 4,134.32dittoLining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:3

over a layer of 1/8" thick c/s mortar 1:3 (in bed)

17-09-b 100 Cft m3 12,133.33 1,237.07 3,503.00 4,284.85Lining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:3

over a layer of 1/8" thick c/s mortar 1:3 (On slope)

17-10-a-01 100 Cft m3 12,047.65 848.44 2,402.50 4,254.594" thick PCC lining, using washed screened & graded stone

aggregate : in bed : Ratio 1:2:4

17-10-a-02 100 Cft m3 10,124.72 848.44 2,402.50 3,575.514" thick PCC lining, using washed screened & graded stone

aggregate : in bed : Ratio 1:3:6

17-10-a-03 100 Cft m3 8,471.86 848.44 2,402.50 2,991.814" thick PCC lining, using washed screened & graded stone

aggregate : in bed : Ratio 1:4:8

17-10-b-01 100 Cft m3 12,473.90 998.96 2,828.75 4,405.124" thick PCC lining, using washed screened & graded stone

aggregate : On slope : Ratio 1:2:4

17-10-b-02 100 Cft m3 10,550.97 998.96 2,828.75 3,726.044" thick PCC lining, using washed screened & graded stone

aggregate : On slope : Ratio 1:3:6

17-10-b-03 100 Cft m3 8,898.11 998.96 2,828.75 3,142.344" thick PCC lining, using washed screened & graded stone

aggregate : On slope : Ratio 1:4:8

Page 101 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 102: Rate nwfp 2008

Item Code Description

LINING OF CANALSChapter #

:

17

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

17-11-a 1Rft m 453.32 385.97 117.64 1,487.28Providing and Laying PCC SEGMENTS in PRECAST

Lining (PARABOLA TYPE) TYPE A

17-11-b 1Rft m 219.94 257.32 78.43 721.57PROVIDinG AND LAYin PCC SEGMENTS in

PRECAST Lining (PARABOLA TYPE) TYPE B

17-11-c 1Rft m 161.17 209.85 63.96 528.76Providing and Laying PCC segments in Precast lining

(Parabola type) Type C

17-11-d 1Rft m 137.43 209.85 63.96 450.90Providing and Laying PCC segments in Precast lining

(Parabola type) Type d

17-11-e 1Rft m 114.86 192.90 58.80 376.84Providing and Laying PCC segments in Precast lining

(Parabola type) Type SPL D

17-11-f 1Rft m 104.09 192.90 58.80 341.51Providing and Laying PCC segments in Precast lining

(Parabola type) Type e

Page 102 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 103: Rate nwfp 2008

Item Code Description

SHEET PILINGChapter #

:

18

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

18-01 Each Cut 147.25 147.25 147.25 147.25Cutting Ransome & Larson piles.

18-02 Each Cut 159.03 159.03 159.03 159.03Cutting universal piles

18-03-a 1 RFT m 43.81 143.72 43.81 143.72a) The rates includes

laying and removing

of track and also

carriage way of piles

to machine, average

distance of 100 ft.

Driving steel piles to depth of: Upto 15'

18-03-b 1 RFT m 58.93 193.33 58.93 193.33b) The rates are for

the trackle ganges

only supplied by the

contractor. Mechincal

staff on machine will

be supplied by the

Govt;

Driving steel piles to depth of: More than 15' to 25'

18-03-c 1 RFT m 61.48 201.71 61.48 201.71c) T-piles and

adjustable junction

piles will be counted

as two piles.

Driving steel piles to depth of: More than 25' to 30'

18-04 Each Each 130.20 130.20 130.20 130.20Dolleying piles upto 5'

18-05 Each Each 17.67 17.67 17.67 17.67Drilling holes in piles by hand

18-06 Each Each 5,020.76 5,020.76 5,020.76 5,020.76Raising and lowering machine

18-07-a Job Job 2,883.00 2,883.00 2,883.00 2,883.00Turning Machine : 90

18-07-b Job Job 3,596.00 3,596.00 3,596.00 3,596.00Turning Machine : 135

18-07-c Job Job 4,619.00 4,619.00 4,619.00 4,619.00Turning Machine : 180

18-08 50 meter 50 m 4,501.20 4,501.20 4,501.20 4,501.20Travelling machine (light)

18-09 tonne tonne 103.23 103.23 103.23 103.23To be done by hand

carts or ramps,

including cost of

ropes.

Loading and unloading piles

18-10 50 meter 50 m 2,317.25 2,317.25 2,317.25 2,317.25Carriage of piling machine under different conditions

18-11 Each Each 13,726.80 13,726.80 13,726.80 13,726.80Erecting piling machines

18-12 Each Each 13,726.80 13,726.80 13,726.80 13,726.80Dismantling piling machine

Page 103 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 104: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-01 100 Cft m3 530.10 187.20 530.10 187.20Cutting pilchi, frash or sarkanda including carriage within

1.5 km.

19-02 100 Sft m2 1,004.40 108.07 1,004.40 108.07Weaving matresses

19-03-a Each Each 28.65 22.60 22.60 28.65The rate dones not

include supply of

sand or earth for

filling of bags, which

shall be paid extra.

Supply & fill used synthetic fibre/plastic bags 1.25cft

capacity with sand or earth, sewing & stacking : in dry

19-03-b Each Each 34.23 28.18 28.18 34.23Supply & fill used synthetic fibre/plastic bags 1.25cft

capacity with sand or earth, sewing & stacking : Under

water

19-03-c Each each 38.33 22.60 22.60 38.33Supply & fill used cotton bags 1.25 cft capacity with sand

or earth, sewing & stacking : in dry

19-03-d Each each 43.91 28.18 28.18 43.91Supply & fill used cotton bags 1.25 cft capacity with sand

or earth, sewing & stacking : Under Water

19-04-a Each Each 103.71 90.40 90.40 103.71dittoSupply & fill new synthetic fibre/plastic bags 4-5cft

capacity with sand or earth,sewing, stacking : in dry

19-04-b Each Each 126.03 112.72 112.72 126.03Supply & fill new synthetic fibre/plastic bags 4-5cft

capacity with sand or earth,sewing, stacking : Under water

19-04-c Each each 117.02 90.40 90.40 117.02Supply & fill used cotton bags 4-5 cft capacity with sand or

earth, sewing & stacking : in dry

19-04-d Each each 139.34 112.72 112.72 139.34Supply & fill used cotton bags 4-5 cft capacity with sand or

earth, sewing & stacking : Under Water

19-05-a 100 No. 100 No. 114.39 114.39 114.39 114.39Carriage of synthetic fibre/plastic bags 1.25 cft capacity

filled with sand / earth : 1st 50 m

19-05-b 100No/50

m

100No/50m 86.49 86.49 86.49 86.49Carriage of synthetic fibre/plastic bags 1.25 cft capacity

filled with sand / earth : 2nd & 3rd 50 m

19-05-c 100No/50

m

100No/50m 9.49 9.49 9.49 9.49Carriage of synthetic fibre/plastic bags 1.25 cft capacity

filled with sand / earth : 4th and subsequent 50 m

19-06-a 100 No. 100 Nos. 457.56 457.56 457.56 457.56Carriage of new synthetic fibre/plastic bags 4-5 cft capacity

filled with sand/earth : 1st 50 m

19-06-b 100No/50

m

100No/50m 345.96 345.96 345.96 345.96Carriage of new synthetic fibre/plastic bags 4-5 cft capacity

filled with sand/earth : 2nd & 3rd 50 m

19-06-c 100No/50

m

100No/50m 37.94 37.94 37.94 37.94Carriage of new synthetic fibre/plastic bags 4-5 cft capacity

filled with sand/earth : 4th & subsequent 50 m

19-07-a 100 Sft m2 306.90 33.02 306.90 33.02Rolling matresses to river edge & floating, after unrolling

with area : Upto 200 m2

19-07-b 100 Sft m2 488.25 52.54 488.25 52.54Rolling matresses to river edge & floating, after unrolling

with area : Over 200 to 250 m2

19-07-c 100 Sft m2 583.11 62.74 583.11 62.74Rolling matresses to river edge & floating, after unrolling

with area : Over 250 m2

19-08 100 No. 100 No. 492.64 404.55 404.55 492.64Sewing empty cement bags in sheets

Page 104 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 105: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-09 100 Cft m3 544.05 192.13 544.05 192.13Measured in the

shape of compact

round bundles and of

size specified for the

work before filling at

site.

Making compact round pilchi, frash or sarkanda round

bundles of specified size for the work

19-10 100 Cft m3 334.80 118.23 334.80 118.23Launching the bundles mentioned in Item 19-09 above &

placing in position

19-11-a 100 Cft m3 1,009.98 356.67 1,009.98 356.67Supply within 150m (500 feet) : Boulders 9" and above

19-11-b 100 Cft m3 675.18 238.44 675.18 238.44Supply within 150m (500 feet) : Over size shingle 3" to 9"

19-11-c 100 Cft m3 797.94 281.79 797.94 281.79Supply within 150m (500 feet): Mixed graded shingle

19-12 Each Each 102.60 69.75 69.75 102.60Supplying munj or patha trungers (6" mesh to hold 3 cft)

stones/boulders

19-13-a-01 100 Sft m2 2,041.44 86.86 807.24 219.66Provide & weave GI wire netting for wire crates 6"x9"

mesh : 15 SWG wire

19-13-a-02 100 Sft m2 4,222.88 155.97 1,449.56 454.38Provide & weave GI wire netting for wire crates 6"x9"

mesh : 10 SWG wire

19-13-a-03 100 Sft m2 7,368.94 228.82 2,126.60 792.90Provide & weave GI wire netting for wire crates 6"x9"

mesh : 8 SWG wire

19-13-b-01 100 Sft m2 2,728.48 116.75 1,085.00 293.58Provide & weave GI wire netting for wire crates 6"x6"

mesh : 15 SWG wire

19-13-b-02 100 Sft m2 5,801.35 226.02 2,100.56 624.22Provide & weave GI wire netting for wire crates 6"x6"

mesh : 10 SWG wire

19-13-b-03 100 Sft m2 9,817.39 303.54 2,821.00 1,056.35Provide & weave GI wire netting for wire crates 6"x6"

mesh : 8 SWG wire

19-13-c-01 100 Sft m2 3,427.83 147.57 1,371.44 368.84Provide & weave GI wire netting for wire crates 4"x6"

mesh : 15 SWG wire

19-13-c-02 100 Sft m2 7,104.57 277.39 2,577.96 764.45Provide & weave GI wire netting for wire crates 4"x6"

mesh : 10 SWG wire

19-13-c-03 100 Sft m2 11,942.89 372.65 3,463.32 1,285.05Provide & weave GI wire netting for wire crates 4"x6"

mesh : 8 SWG wire

19-14 100 Cft m3 1,368.00 98.53 279.00 483.11Providing and Laying shingle on top of bund, including

handling of materials within 100 m.

19-15-a 100 Cft m3 1,828.50 197.06 558.00 645.73Supply & dump at site, without boat, including handling

within 100m : Stone or boulder

19-15-b 100 Cft m3 1,647.00 197.06 558.00 581.63Supply & dump at site, without boat, including handling

within 100m : Shingle or spawls

19-15-c 100 Cft m3 2,838.50 147.79 418.50 1,002.41Supply & dump at site, without boat, including handling

within 100m : Brick bats

19-16-a 100 Cft m3 2,605.00 492.64 1,395.00 919.95Supplying and dumping by boat, including loading within

100m lead : Stone or boulder

19-16-b 100 Cft m3 2,484.00 492.64 1,395.00 877.22Supplying and dumping by boat, including loading within

100m lead : Shingle or spawls

Page 105 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 106: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-16-c 100 Cft m3 3,536.00 394.11 1,116.00 1,248.73Supplying and dumping by boat, including loading within

100m lead : Brick bats

19-17-a 100 Cft m3 3,117.50 246.32 697.50 1,100.94Provide & fill brick bats in crates, excluding cost of crates :

without hand packing.

19-17-b 100 Cft m3 3,257.00 295.58 837.00 1,150.20Provide & fill brick bats in crates, excluding cost of crates :

with hand packing.

19-18-a 100 Cft m3 1,812.64 212.82 602.64 640.13Supply & fill bricks in wire crates including sewing crates,

excl cost of crates : Stone or boulder

19-18-b 100 Cft m3 1,688.85 211.84 599.85 596.41Supply & fill bricks in wire crates including sewing crates,

excl cost of crates : Shingle or spawls

19-19 100 Cft m3 55.80 19.71 55.80 19.71Extra for anchoring boat for dumping by boats or tipping

crates

19-20 100 Cft m3 558.00 197.06 558.00 197.06Extra for tipping crates (in addition to achoring boats)

19-21 100 Sft m2 1,852.00 30.02 279.00 199.28Pilchi revetment, including carriage upto 1.5 km

19-22 100 Sft m2 36.30 0.00 0.00 3.91Surface protection with pilchi matresses including carriage

upto 1.5 km.

19-23 100 Sft m2 7,181.54 60.04 558.00 772.73Pilchi, sarkanda or frash pitching on slopes, incl supply

within 1.5 km, pegging & tying with wire

19-24-a 100 Sft m2 4,097.88 63.38 589.00 440.93P&E groynes, vertical wooden stakes 7"-12" dia Upto 1.5

m high, single row of stakes at 0.3m

19-24-b 100 Sft m2 5,031.38 111.74 1,038.50 541.38P&E groynes, vertical wooden stakes 7"-12" dia Upto 3 m

high, double row of stakes at 0.6m

19-25 100 Cft m3 3,046.00 306.53 868.00 1,075.69Providing and Laying stone pithcing/filling, dry hand

packed in pitching & aprons

19-26 100 Cft m3 3,077.00 317.48 899.00 1,086.63Supplying stone and stone filling in GI wire crate and its

sewing, excluding cost of crates

19-27 100 Cft m3 4,628.60 711.59 2,015.00 1,634.58Providing and Laying stone pitching with hammer dressed

stones on surface, laid in courses

19-28-a 100 Cft m3 5,186.60 908.65 2,573.00 1,831.63Providing and Laying stone pitching for top layer only : On

slope

19-28-b 100 Cft m3 4,628.60 711.59 2,015.00 1,634.58Providing and Laying stone pitching for top layer only : On

level

19-29-a 100 Cft m3 2,822.05 150.53 426.25 996.60Providing and Laying stone or spawl filling : On slope

19-29-b 100 Cft m3 2,752.30 125.90 356.50 971.97Providing and Laying stone or spawl filling : On level

19-30-a 100 Cft m3 7,310.71 1,111.18 3,146.50 2,581.76Providing and Laying grouted stone pitching, in 1:8 c/s

mortar Top layer on slope

19-30-b 100 Cft m3 6,737.21 908.65 2,573.00 2,379.23Providing and Laying grouted stone pitching, in 1:8 c/s

mortar Top layer on level

19-30-c 100 Cft m3 6,310.96 758.12 2,146.75 2,228.70Providing and Laying grouted stone pitching, in 1:8 c/s

mortar Stone pitching/filling on slope or on level

19-31-a 100 Sft m2 4,122.08 130.09 1,209.00 443.54Grouting stone pitching or apron etc, in : Cement, sand

mortar 1:3

Page 106 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 107: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-31-b 100 Sft m2 2,722.54 130.09 1,209.00 292.95Grouting stone pitching or apron etc, in : Cement, sand

mortar 1:8

19-32 100 Sft m2 1,007.05 45.86 426.25 108.36Sand grouting in stone apron, with high pressure hose

19-33 100 Cft m3 820.65 123.16 348.75 289.81Grouting stone filling or pitching with bajri

19-34 100 Cft m3 2,046.00 722.54 2,046.00 722.54Remove stone & repitching hand packed, on slopes or

level, making good damaged portion

19-35 100 Cft m3 837.00 295.58 837.00 295.58Collect & stack boulders from nullah beds or loose shale

etc within 100m lead

19-36 100 Cft m3 752.95 150.53 426.25 265.90Levelling and dressing stone filling under blocks and

grouting with shingle

19-37 100 Cft m3 1,184.90 251.79 713.00 418.44Grouting jharies between blocks with bajri

19-38-a 100 Cft m3 418.50 147.79 418.50 147.79Breaking stone into spawls and stacking

19-38-b 100 Cft m3 5,333.85 960.65 2,720.25 1,883.63Stone pitching with hammer dressed stone on surface laid

in courses including carriage of material with in 91.50 (300

feet) meters.

19-38-c 100 Cft m3 7,287.60 1,111.18 3,146.50 2,573.60Stone pitching hand packed with surface levelled off to the

correct section with hammer dressed stone and voids filled

in 1:8 cement mortar in floors of bridges and along banks

and in aprons etc including 91.50 meter lead.

19-38-d 100 Cft m3 1,131.50 399.59 1,131.50 399.59Removing stone and repitching, hand packed on slopes

after making good damage slope.

19-38-e 100 Cft m3 558.00 197.06 558.00 197.06Collecting and stacking boulders from nullah beds or loose

shale from any other site, within 91.50 (300 feet) meter

lead

19-38-f-01 100 Cft m3 5,186.60 908.65 2,573.00 1,831.63Stone pitching for top layer only on slop

19-38-f-02 100 Cft m3 4,628.60 711.59 2,015.00 1,634.58Stone pitching for top layer only on Bed

19-38-g-01 100 Cft m3 2,752.30 125.90 356.50 971.97Laying stone or spawl filling. a)on level

19-38-g-02 100 Cft m3 2,822.05 150.53 426.25 996.60Laying stone or spawl filling. a)on slop

19-39-a Each Each 14.26 14.26 14.26 14.26Fix floating spurs, with material from canal plantation

within 1 km : Upto 2' FS depth

19-39-b Each Each 20.24 20.24 20.24 20.24Fix floating spurs, with material from canal plantation

within 1 km : Over 2' to 3' FS depth

19-39-c Each Each 28.52 28.52 28.52 28.52Fix floating spurs, with material from canal plantation

within 1 km : Over 3' to 4' FS depth

19-39-d Each Each 57.04 57.04 57.04 57.04Fix floating spurs, with material from canal plantation

within 1 km : Exceeding 4' depth

19-40-a-01 100 No. 100 No. 1,171.07 929.07 929.07 1,171.07Royalty to be paid to

the forest Department

or cost to the private

owner, as the case

may be, if and when

required.

Stake & bush from canal plantation etc : Pegs 3.5' long,

3"-6" dia: Unsharpened within 1km

Page 107 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 108: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-40-a-02 100 No. 100 No. 441.75 441.75 441.75 441.75Stake & bush from canal plantation etc : Pegs 3.5' long,

3"-6" dia: Sharpening one end

19-40-a-03 100 No. 100 No. 348.75 348.75 348.75 348.75Stake & bush from canal plantation etc : Pegs 3.5' long,

3"-6" dia: Driving 1' below ground

19-40-a-04 100 Rft 100 Rft 157.65 139.50 139.50 157.65Stake & bush from canal plantation etc : Pegs 3.5' long,

3"-6" dia: Tying with munj, patha ban

19-40-a-05 100 Rft 100 Rft 1,339.50 976.50 976.50 1,339.50Stake & bush from canal plantation etc : Pegs 3.5' long,

3"-6" dia: Wattle+intertwine brushwood

19-40-b-01 100 No. 100 No. 1,431.57 1,068.57 1,068.57 1,431.57Stake & bush from canal plantation etc : Pegs 4' long, 3"-6"

dia: Unsharpened within 1km

19-40-b-02 100 No. 100 No. 441.75 441.75 441.75 441.75Stake & bush from canal plantation etc : Pegs 4' long, 3"-6"

dia: Sharpening one end

19-40-b-03 100 No. 100 No. 488.25 488.25 488.25 488.25Stake & bush from canal plantation etc : Pegs 4' long, 3"-6"

dia: Driving 1.25' below ground

19-40-b-04 100 Rft 100 Rft 157.65 139.50 139.50 157.65Stake & bush from canal plantation etc : Pegs 4' long, 3"-6"

dia: Tying with munj, patha ban

19-40-b-05 100 Rft 100 Rft 1,548.75 1,185.75 1,185.75 1,548.75dittoStake & bush from canal plantation etc : Pegs 4' long, 3"-6"

dia: Wattle+intertwine brushwood

19-40-c-01 100 No. 100 No. 1,528.50 1,286.50 1,286.50 1,528.50Stake & bush from canal plantation etc : Pegs 5' long, 3"-6"

dia: Unsharpened within 1km

19-40-c-02 100 No. 100 No. 471.20 471.20 471.20 471.20Stake & bush from canal plantation etc : Pegs 5' long, 3"-6"

dia: Sharpening one end

19-40-c-03 100 No. 100 No. 412.30 412.30 412.30 412.30Stake & bush from canal plantation etc : Pegs 5' long, 3"-6"

dia: Driving 1.5' below ground

19-40-c-04 100 Rft 100 Rft 157.65 139.50 139.50 157.65Stake & bush from canal plantation etc : Pegs 5' long, 3"-6"

dia: Tying with munj, patha ban

19-40-c-05 100 Rft 100 Rft 1,813.80 1,450.80 1,450.80 1,813.80Royalty to be paid to

the forest Department

or cost to the private

owner, as the case

may be, if and when

required.

Stake & bush from canal plantation etc : Pegs 5' long, 3"-6"

dia: Wattle+intertwine brushwood

19-40-d-01 100 No. 100 No. 1,815.25 1,573.25 1,573.25 1,815.25Stake & bush from canal plantation etc : Pegs 6' long, 3"-6"

dia: Unsharpened within 1km

19-40-d-02 100 No. 100 No. 547.77 547.77 547.77 547.77Stake & bush from canal plantation etc : Pegs 6' long, 3"-6"

dia: Sharpening one end

19-40-d-03 100 No. 100 No. 485.77 485.77 485.77 485.77Stake & bush from canal plantation etc : Pegs 6' long, 3"-6"

dia: Driving 1.75' below ground

19-40-d-04 100 Rft 100 Rft 157.65 139.50 139.50 157.65Stake & bush from canal plantation etc : Pegs 6' long, 3"-6"

dia: Tying with munj, patha ban

19-40-d-05 100 Rft 100 Rft 2,176.50 1,813.50 1,813.50 2,176.50dittoStake & bush from canal plantation etc : Pegs 6' long, 3"-6"

dia: Wattle+intertwine brushwood

Page 108 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 109: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-40-e-01 100 No. 100 No. 3,528.00 3,286.00 3,286.00 3,528.00Stake & bush from canal plantation etc : Pegs 8' long, 4"-8"

dia: Unsharpened within 1km

19-40-e-02 100 No. 100 No. 689.13 689.13 689.13 689.13Stake & bush from canal plantation etc : Pegs 8' long, 4"-8"

dia: Sharpening one end

19-40-e-03 100 No. 100 No. 537.23 537.23 537.23 537.23Stake & bush from canal plantation etc : Pegs 8' long, 4"-8"

dia: Driving 2' below ground

19-40-e-04 100 Rft 100 Rft 161.28 139.50 139.50 161.28Stake & bush from canal plantation etc : Pegs 8' long, 4"-8"

dia: Tying with munj, patha ban

19-40-e-05 100 Rft 100 Rft 2,455.50 2,092.50 2,092.50 2,455.50dittoStake & bush from canal plantation etc : Pegs 8' long, 4"-8"

dia: Wattle+intertwine brushwood

19-41-a-01 100 No. 100 No. 18,150.00 0.00 0.00 18,150.00dittoStake, market bamboo, bush from any source 8'-10' long,

2.5"-5" dia : Supply bamboo

19-41-a-02 100 No. 100 No. 589.00 589.00 589.00 589.00Stake, market bamboo, bush from any source 8'-10' long,

2.5"-5" dia : Sharpen one end

19-41-a-03 100 No. 100 No. 620.00 620.00 620.00 620.00Stake, market bamboo, bush from any source 8'-10' long,

2.5"-5" dia : Driving bamboo 2.5'

19-41-a-04 100 Rft 100 Rft 300.78 279.00 279.00 300.78Stake, market bamboo, bush from any source 8'-10' long,

2.5"-5" dia : Tying bamboo with wire

19-41-a-05 100 Rft 100 Rft 3,231.30 2,650.50 2,650.50 3,231.30Royalty to be paid to

the forest Department

or cost to the private

owner, as the case

may be, if and when

required.

Stake, market bamboo, bush from any source 8'-10' long,

2.5"-5" dia : Wattle & intertwine

19-41-b-01 100 No. 100 No. 21,780.00 0.00 0.00 21,780.00Stake, market bamboo, bush from any source 10'-12' long,

2.5"-5" dia : Supply bamboo

19-41-b-02 100 No. 100 No. 689.13 689.13 689.13 689.13Stake, market bamboo, bush from any source 10'-12' long,

2.5"-5" dia : Sharpen one end

19-41-b-03 100 No. 100 No. 651.00 651.00 651.00 651.00Stake, market bamboo, bush from any source 10'-12' long,

2.5"-5" dia : Driving bamboo 2.75'

19-41-b-04 100 Rft 100 Rft 1,582.43 139.50 139.50 1,582.43Stake, market bamboo, bush from any source 10'-12' long,

2.5"-5" dia : Tying bamboo with wire

19-41-b-05 100 Rft 100 Rft 4,018.20 3,292.20 3,292.20 4,018.20dittoStake, market bamboo, bush from any source 10'-12' long,

2.5"-5" dia : Wattle & intertwine

19-41-c-01 100 No. 100 No. 25,410.00 0.00 0.00 25,410.00Stake, market bamboo, bush from any source 12'-14' long,

2.5"-5" dia : Supply bamboo

19-41-c-02 100 No. 100 No. 777.48 777.48 777.48 777.48Stake, market bamboo, bush from any source 12'-14' long,

2.5"-5" dia : Sharpen one end

19-41-c-03 100 No. 100 No. 723.23 723.23 723.23 723.23Stake, market bamboo, bush from any source 12'-14' long,

2.5"-5" dia : Driving bamboo 3.5'

19-41-c-04 100 Rft 100 Rft 1,582.43 139.50 139.50 1,582.43Stake, market bamboo, bush from any source 12'-14' long,

2.5"-5" dia : Tying bamboo with wire

Page 109 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 110: Rate nwfp 2008

Item Code Description

PROTECTION AND DIVERSION WORKSChapter #

:

19

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

19-41-c-05 100 Rft 100 Rft 4,858.23 3,841.83 3,841.83 4,858.23dittoStake, market bamboo, bush from any source 12'-14' long,

2.5"-5" dia : Wattle & intertwine

19-41-d-01 100 No. 100 No. 29,040.00 0.00 0.00 29,040.00Stake, market bamboo, bush from any source 14'-16' long,

2.5"-5" dia : Supply bamboo

19-41-d-02 100 No. 100 No. 883.50 883.50 883.50 883.50Stake, market bamboo, bush from any source 14'-16' long,

2.5"-5" dia : Sharpen one end

19-41-d-03 100 No. 100 No. 806.00 806.00 806.00 806.00Stake, market bamboo, bush from any source 14'-16' long,

2.5"-5" dia : Driving bamboo 4'

19-41-d-04 100 Rft 100 Rft 1,582.43 139.50 139.50 1,582.43Stake, market bamboo, bush from any source 14'-16' long,

2.5"-5" dia : Tying bamboo with wire

19-41-d-05 100 Rft 100 Rft 5,067.60 3,906.00 3,906.00 5,067.60Royalty to be paid to

the forest Department

or cost to the private

owner, as the case

may be, if and when

required.

Stake, market bamboo, bush from any source 14'-16' long,

2.5"-5" dia : Wattle & intertwine

19-41-e-01 100 No. 100 No. 36,300.00 0.00 0.00 36,300.00Stake, market bamboo, bush from any source 16'-20' long,

2.5"-5" dia : Supply bamboo

19-41-e-02 100 No. 100 No. 1,036.64 1,036.64 1,036.64 1,036.64Stake, market bamboo, bush from any source 16'-20' long,

2.5"-5" dia : Sharpen one end

19-41-e-03 100 No. 100 No. 971.23 971.23 971.23 971.23Stake, market bamboo, bush from any source 16'-20' long,

2.5"-5" dia : Driving bamboo 4'

19-41-e-04 100 Rft 100 Rft 1,582.43 139.50 139.50 1,582.43Stake, market bamboo, bush from any source 16'-20' long,

2.5"-5" dia : Tying bamboo with wire

19-41-e-05 100 Rft 100 Rft 5,491.80 4,185.00 4,185.00 5,491.80dittoStake, market bamboo, bush from any source 16'-20' long,

2.5"-5" dia : Wattle & intertwine

19-42 100 Cft m3 533.40 98.54 279.04 188.37dittoCut & supply brushwood from canal plantation or from any

other source, within 1.5 km.

19-43 100 Cft m3 139.05 49.10 139.05 49.10Measured in

compacted and

packed shape before

filling.

Filling brush wood only, thoroughly packed

19-44 100 Rft 50 m 166.84 273.62 166.84 273.62Covering road 10' to 12' wide, with 3" sarkanda or jungle,

upto 50m lead

19-45 100 Sft m2 1,815.06 195.30 1,815.06 195.30Gachi pitching 1' thick

19-46 100 Sft m2 1,535.02 165.17 1,535.02 165.17Gachi pitching done with silt clearance and berm dressing

19-47 100 Cft m3 2,116.63 208.00 589.00 747.48Filter granular backfill behind retaining wall (stone/boulder

filling upto one meter to prevent choking of weep holes).

Page 110 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 111: Rate nwfp 2008

Item Code Description

OUTLETSChapter #

:

20

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

20-01-a Job Job 697.50 697.50 697.50 697.50Includes

consolidation of earth

after refilling

Earthwork for Outlets : Exc/Refill/Ram/Puddle Upto 50

cusecs channel discharge

20-01-b Job Job 920.70 920.70 920.70 920.70Earthwork for outlets : Exc/Refill/Ram/Puddle 51-100

cusecs channel discharge

20-01-c Job Job 1,395.00 1,395.00 1,395.00 1,395.00Earthwork for outlets : Exc/Refill/Ram/Puddle 101-200

cusecs channel discharge

20-01-d Job Job 1,883.25 1,883.25 1,883.25 1,883.25Earthwork for outlets : Exc/Refill/Ram/Puddle 201-350

cusecs channel discharge

20-01-e Job Job 2,790.00 2,790.00 2,790.00 2,790.00Earthwork for Outlets : Ex/Refill/Ram/Puddle Over 350

cusecs channel discharge

20-02-a Each Each 697.50 697.50 697.50 697.50The rates are for total

dismantlement and

remaoval of material.

The rates do not

include earthwork for

which rates are given

in item No 20-01

above.

Dismantling outlets: Old types such as KGO's orfices, etc

20-02-b Each Each 1,046.25 1,046.25 1,046.25 1,046.25Dismantling outlets: APM or OF, 'H' upto 2.0 ft.

20-02-c Each Each 1,395.00 1,395.00 1,395.00 1,395.00Dismantling outlets: APM or OF, 'H' from 2.1-3.0ft

20-02-d Each Each 1,743.75 1,743.75 1,743.75 1,743.75Dismantling outlets: APM or OF, 'H' above 3.0 ft

20-02-e Each Each 1,046.25 1,046.25 1,046.25 1,046.25Dismantling outlets: Tail cluster bifurcation

20-02-f Each Each 1,395.00 1,395.00 1,395.00 1,395.00Dismantling outlets: Tail cluster trifurcation

20-02-g Each Each 1,743.75 1,743.75 1,743.75 1,743.75Dismantling outlets: Tail cluster quardification

20-03 Each Each 493.35 286.44 286.44 493.35Making temporary APM brick block & fixing at site

20-04 Job Job 720.75 720.75 720.75 720.75Dismantling walls, taking out temporary APM brick block,

fixing iron block & rebuilding walls

20-05 Each Each 720.75 720.75 720.75 720.75Dismantling walls & fitting iron block of OF outlet

20-06-a Each Each 1,395.00 1,395.00 1,395.00 1,395.00Constructing, watching & removing bund for outlet built in

running water : Upto 3' depth

20-06-b Each Each 1,883.25 1,883.25 1,883.25 1,883.25Constructing, watching & removing bund for outlet built in

running water : Over 3' depth

20-07 Each Each 729.20 444.85 444.85 729.20Adjusting "B" of tail cluster by dismantling and rebuilding

throat walls

20-08 Each Each 1,316.42 860.25 860.25 1,316.42Adjusting "Y" of an APM outlet, including dismantling and

rebuilding

20-09-a Each Each 968.43 868.00 868.00 968.43Extra labour in fixing APM and OF outlet blocks Depth

exceeding 5.0'

20-09-b Each Each 751.43 651.00 651.00 751.43Extra labour in fixing APM and OF outlet blocks Depth

more than 4.0' to 5.0'

20-09-c Each Each 621.23 520.80 520.80 621.23Extra labour in fixing APM and OF outlet blocks Depth

more than 3.0' to 4.0'

Page 111 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 112: Rate nwfp 2008

Item Code Description

OUTLETSChapter #

:

20

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

20-09-d Each Each 512.65 434.00 434.00 512.65Extra labour in fixing APM and OF outlet blocks Depth

more than 2.0' to 3.0'

20-09-e Each Each 404.07 347.20 347.20 404.07Extra labour in fixing APM and OF outlet blocks Depth

upto 2.0'

20-10 Each Each 419.54 286.44 286.44 419.54Repairing damaged reducing collar of hume pipe outlets

20-11 1 Rft m 23.01 75.50 23.01 75.50Laying iron pipes for outlets.

20-12 Each Each 348.75 348.75 348.75 348.75At the discretion of

the

Engineer-in-Charge

depending upon the

distance and the

source of supply.

Water allowance for constructing outlets or culverts, when

canal water not flowing

20-13 Each Each 299.15 299.15 299.15 299.15Hoisting and placing RC slab or stone in position on

outlets or WC culverts

20-14-a 1 Rft m 67.14 192.71 58.74 220.27Fixing pipe outlet, including backfilling of earth &

puddling : Portion under bank

20-14-b 1 Rft m 35.71 89.61 27.31 117.17Fixing pipe outlet, including backfilling of earth &

puddling : Portion under road, beyond bank

20-15-a 1 Rft m 46.53 152.65 46.53 152.65Removing pipe outlet,refilling earth & puddling Portion

under bank

20-15-b 1 Rft m 17.44 57.21 17.44 57.21Removing pipe outlet,refilling earth & puddling Portion

under road, beyond

20-16-a 1 Rft m 76.46 223.29 68.06 250.85Changing pipe outlets by removing one pipe & replacing :

Portion under bank

20-16-b 1 Rft m 42.34 111.35 33.94 138.91Changing pipe outlets by removing one pipe & replacing :

Portion under road, beyond

Page 112 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 113: Rate nwfp 2008

Item Code Description

SINKING OF WELLSChapter #

:

21

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

21-01-a-01 100 Cft m3 206.99 73.10 206.99 73.10Excavate well in dry & dispose of soil within 50m in

ordinary soil or sand : Upto 1.5 m depth

21-01-a-02 100 Cft m3 216.47 76.45 216.47 76.45Excavate well in dry & dispose of soil within 50m in

ordinary soil or sand : 1.5 to 3 m depth

21-01-a-03 100 Cft m3 244.12 86.21 244.12 86.21Excavate well in dry & dispose of soil within 50m in

ordinary soil or sand : 3 to 4.5 m depth

21-01-a-04 100 Cft m3 278.88 98.49 278.88 98.49Excavate well in dry & dispose of soil within 50m in

ordinary soil or sand : 4.5 to 6 m depth

21-01-b-01 100 Cft m3 252.81 89.28 252.81 89.28Excavate well in dry & dispose of soil within 50m in hard

soil : Upto 1.5 m depth

21-01-b-02 100 Cft m3 263.87 93.19 263.87 93.19Excavate well in dry & dispose of soil within 50m in hard

soil : Above 1.5 to 3 m depth

21-01-b-03 100 Cft m3 288.36 101.83 288.36 101.83Excavate well in dry & dispose of soil within 50m in hard

soil : Above 3 to 4.5 m depth

21-01-b-04 100 Cft m3 324.71 114.67 324.71 114.67Excavate well in dry & dispose of soil within 50m in hard

soil : Above 4.5 to 6 m depth

21-01-c-01 100 Cft m3 544.34 192.23 544.34 192.23Excavate well in dry & dispose of soil within 50m in hard

strata like shingle : Upto 1.5 m depth

21-01-c-02 100 Cft m3 564.09 199.21 564.09 199.21Excavate well in dry & dispose of soil within 50m in hard

strata like shingle :1.5 to 3 m depth

21-01-c-03 100 Cft m3 587.79 207.58 587.79 207.58Excavate well in dry & dispose of soil within 50m in hard

strata like shingle : 3 to 4.5 m depth

21-01-c-04 100 Cft m3 631.24 222.92 631.24 222.92Excavate well in dry & dispose of soil within 50m in hard

strata like shingle : 4.5 to 6 m depth

21-02-a-01 100 Cft m3 1,116.33 394.23 1,116.33 394.23Dry sinking of well & disposal of soil within 50m in

ordinary soil : 3 to 4.5 m depth

21-02-a-02 100 Cft m3 1,395.21 492.71 1,395.21 492.71Dry sinking of well & disposal of soil within 50m in

ordinary soil : 4.5 to 6 m depth

21-02-a-03 100 Cft m3 1,674.09 591.20 1,674.09 591.20Dry sinking of well & disposal of soil within 50m in

ordinary soil : 6 to 7.5 m depth

21-02-a-04 100 Cft m3 1,952.98 689.69 1,952.98 689.69Dry sinking of well & disposal of soil within 50m in

ordinary soil : 7.5 to 9 m depth

21-02-a-05 100 Cft m3 2,231.86 788.17 2,231.86 788.17Dry sinking of well & disposal of soil within 50m in

ordinary soil : 9 to 10.5 m depth

21-02-a-06 100 Cft m3 2,510.74 886.66 2,510.74 886.66Dry sinking of well & disposal of soil within 50m in

ordinary soil : 10.5 to 12 m depth

21-02-a-07 100 Cft m3 2,790.42 985.43 2,790.42 985.43Dry sinking of well & disposal of soil within 50m in

ordinary soil : 12 to 13.5 m depth

21-02-a-08 100 Cft m3 3,069.30 1,083.91 3,069.30 1,083.91Dry sinking of well & disposal of soil within 50m in

ordinary soil : Exceeding 13.5 m depth

21-02-b-01 100 Cft m3 1,534.26 541.82 1,534.26 541.82Dry sinking of well & disposal of soil within 50m in hard

soil : 3 to 4.5 m depth

Page 113 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 114: Rate nwfp 2008

Item Code Description

SINKING OF WELLSChapter #

:

21

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

21-02-b-02 100 Cft m3 1,813.14 640.30 1,813.14 640.30Dry sinking of well & disposal of soil within 50m in hard

soil : 4.5 to 6 m depth

21-02-b-03 100 Cft m3 2,092.81 739.07 2,092.81 739.07Dry sinking of well & disposal of soil within 50m in hard

soil : 6 to 7.5 m depth

21-02-b-04 100 Cft m3 2,371.70 837.56 2,371.70 837.56Dry sinking of well & disposal of soil within 50m in hard

soil : 7.5 to 9 m depth

21-02-b-05 100 Cft m3 2,650.58 936.05 2,650.58 936.05Dry sinking of well & disposal of soil within 50m in hard

soil : 9 to 10.5 m depth

21-02-b-06 100 Cft m3 2,929.47 1,034.53 2,929.47 1,034.53Dry sinking of well & disposal of soil within 50m in hard

soil : 10.5 to 12 m depth

21-02-b-07 100 Cft m3 3,208.35 1,133.02 3,208.35 1,133.02Dry sinking of well & disposal of soil within 50m in hard

soil : 12 to 13.5 m depth

21-02-b-08 100 Cft m3 3,487.23 1,231.51 3,487.23 1,231.51Dry sinking of well & disposal of soil within 50m in hard

soil : Exceeding 13.5 m depth

21-02-c-01 100 Cft m3 2,092.02 738.79 2,092.02 738.79Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 3 to 4.5 m depth

21-02-c-02 100 Cft m3 2,371.70 837.56 2,371.70 837.56Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 4.5 to 6 m depth

21-02-c-03 100 Cft m3 2,650.58 936.05 2,650.58 936.05Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 6 to 7.5 m depth

21-02-c-04 100 Cft m3 2,929.47 1,034.53 2,929.47 1,034.53Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 7.5 to 9 m depth

21-02-c-05 100 Cft m3 3,208.35 1,133.02 3,208.35 1,133.02Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 9 to 10.5 m depth

21-02-c-06 100 Cft m3 3,487.23 1,231.51 3,487.23 1,231.51Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 10.5 to 12 m depth

21-02-c-07 100 Cft m3 3,766.91 1,330.27 3,766.91 1,330.27Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : 12 to 13.5 m depth

21-02-c-08 100 Cft m3 4,045.79 1,428.76 4,045.79 1,428.76Dry sinking of well & disposal of soil within 50m in hard

strata like shingle : Over 13.5 m depth

21-03-a-01 100 Cft m3 1,325.60 468.13 1,325.60 468.13The outer dimensions

of the curb shall from

basis of payment.

Wet sinking of well for depths below spring level Upto 1.5

m depth

21-03-a-02 100 Cft m3 2,665.68 941.38 2,665.68 941.38Wet sinking of well for depths below spring level Above

1.5 to 3 m depth

21-03-a-03 100 Cft m3 4,102.24 1,448.69 4,102.24 1,448.69Wet sinking of well for depths below spring level Above 3

to 4.5 m depth

21-03-a-04 100 Cft m3 5,553.27 1,961.12 5,553.27 1,961.12Wet sinking of well for depths below spring level Above

4.5 to 6 m depth

21-03-a-05 100 Cft m3 7,322.87 2,586.05 7,322.87 2,586.05Wet sinking of well for depths below spring level Above 6

to 7.5 m depth

Page 114 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 115: Rate nwfp 2008

Item Code Description

SINKING OF WELLSChapter #

:

21

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

21-03-a-06 100 Cft m3 9,354.33 3,303.45 9,354.33 3,303.45Wet sinking of well for depths below spring level Above

7.5 to 9 m depth

21-03-a-07 100 Cft m3 11,345.75 4,006.72 11,345.75 4,006.72Wet sinking of well for depths below spring level Above 9

to 10.5 m depth

21-03-a-08 100 Cft m3 14,029.52 4,954.48 14,029.52 4,954.48Wet sinking of well for depths below spring level Above

10.5 to 12 m depth

21-03-a-09 100 Cft m3 16,659.65 5,883.31 16,659.65 5,883.31Wet sinking of well for depths below spring level Above

12 to 13.5 m depth

21-03-a-10 100 Cft m3 20,044.70 7,078.73 20,044.70 7,078.73Wet sinking of well for depths below spring level

Exceeding 13.5 m depth

21-03-b-01 100 Cft m3 1,705.52 602.30 1,705.52 602.30Wet sinking of well for depths below spring level in

cohesive soil : Upto 1.5 m depth

21-03-b-02 100 Cft m3 3,333.00 1,177.04 3,333.00 1,177.04Wet sinking of well for depths below spring level in

cohesive soil : 1.5 to 3 m depth

21-03-b-03 100 Cft m3 5,030.79 1,776.61 5,030.79 1,776.61Wet sinking of well for depths below spring level in

cohesive soil : Above 3 to 4.5 m depth

21-03-b-04 100 Cft m3 6,665.21 2,353.80 6,665.21 2,353.80Wet sinking of well for depths below spring level in

cohesive soil : Above 4.5 to 6 m depth

21-03-b-05 100 Cft m3 9,192.81 3,246.41 9,192.81 3,246.41Wet sinking of well for depths below spring level in

cohesive soil : Above 6 to 7.5 m depth

21-03-b-06 100 Cft m3 11,591.90 4,093.64 11,591.90 4,093.64Wet sinking of well for depths below spring level in

cohesive soil : Above 7.5 to 9 m depth

21-03-b-07 100 Cft m3 14,218.25 5,021.13 14,218.25 5,021.13Wet sinking of well for depths below spring level in

cohesive soil : Above 9 to 10.5 m depth

21-03-b-08 100 Cft m3 17,775.71 6,277.44 17,775.71 6,277.44Wet sinking of well for depths below spring level in

cohesive soil : Above 10.5 to 12 m depth

21-03-b-09 100 Cft m3 20,825.26 7,354.38 20,825.26 7,354.38Wet sinking of well for depths below spring level in

cohesive soil : Above 12 to 13.5 m depth

21-03-b-10 100 Cft m3 24,913.98 8,798.30 24,913.98 8,798.30Wet sinking of well for depths below spring level in

cohesive soil : Exceeding 13.5 m depth

21-03-c-01 100 Cft m3 3,372.59 1,191.02 3,372.59 1,191.02Wet sinking of well for depths below spring level in

shingle/gravel etc : Upto 1.5 m depth

21-03-c-02 100 Cft m3 8,030.75 2,836.03 8,030.75 2,836.03Wet sinking of well for depths below spring level in

shingle/gravel etc : 1.5 to 3 m depth

21-03-c-03 100 Cft m3 10,950.47 3,867.13 10,950.47 3,867.13Wet sinking of well for depths below spring level in

shingle/gravel etc : 3 to 4.5 m depth

21-03-c-04 100 Cft m3 15,163.13 5,354.82 15,163.14 5,354.81Wet sinking of well for depths below spring level in

shingle/gravel etc : 4.5 to 6 m depth

21-03-c-05 100 Cft m3 22,788.77 8,047.79 22,788.77 8,047.79Wet sinking of well for depths below spring level in

shingle/gravel etc : 6 to 7.5 m depth

21-03-c-06 100 Cft m3 29,484.97 10,412.53 29,484.97 10,412.53Wet sinking of well for depths below spring level in

shingle/gravel etc : 7.5 to 9 m depth

Page 115 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 116: Rate nwfp 2008

Item Code Description

SINKING OF WELLSChapter #

:

21

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

21-03-c-07 100 Cft m3 36,979.11 13,059.06 36,979.11 13,059.06Wet sinking of well for depths below spring level in

shingle/gravel etc : 9 to 10.5 m depth

21-03-c-08 100 Cft m3 47,902.71 16,916.70 47,902.71 16,916.70Wet sinking of well for depths below spring level in

shingle/gravel etc : 10.5 to 12 m depth

21-03-c-09 100 Cft m3 60,229.09 21,269.72 60,229.09 21,269.72Wet sinking of well for depths below spring level in

shingle/gravel etc : 12 to 13.5 m depth

21-03-c-10 100 Cft m3 76,638.20 27,064.55 76,638.20 27,064.55Wet sinking of well for depths below spring level in

shingle/gravel etc : Exceeding 13.5 m depth

21-04 100 Cft m3 184,997.55 33,283.24 94,247.55 65,331.31Making & fixing in position, kikar wood well curb

21-05 Each Each 565.75 565.75 565.75 565.75Laying well curb in position only

21-06-a 100 Cft m3 21,023.35 2,720.53 7,703.67 7,424.33a) If concrete mixer is

supplied by

government, all

charges including

depreciation will be

recoverd from the

contractor.

Providing & laying RCC well curb in position, using

coarse sand : Ratio 1:1.5:3

21-06-b 100 Cft m3 22,414.54 2,720.53 7,703.67 7,915.63b) The rate does not

include cost of steel

reinforement and its

labour for

bending/binding,

which is payable

separately.

Providing & laying RCC well curb in position, using

coarse sand : Ratio 1:2:4

21-07 Ton tonne 106,772.00 14,339.79 14,570.00 105,085.00Providing and fixing structural steel for cutting edge

Page 116 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 117: Rate nwfp 2008

Item Code Description

SURFACE DRAINAGEChapter #

:

22

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

22-01-a-01 100 Rft m 1,915.17 18.57 566.10 62.83Tega formed of pacca bricks on end, laid in and over c/s

mortar : 3" thick : Ratio 1:3

22-01-a-02 100 Rft m 1,715.44 18.57 566.10 56.28Tega formed of pacca bricks on end, laid in and over c/s

mortar : 3" thick : Ratio 1:5

22-01-b-01 100 Rft m 2,216.99 20.50 624.82 72.74Tega formed of pacca bricks on end, laid in and over c/s

mortar : 4.5" thick : Ratio 1:3

22-01-b-02 100 Rft m 2,089.53 20.50 624.82 68.55Tega formed of pacca bricks on end, laid in and over c/s

mortar : 4.5" thick : Ratio 1:5

22-02-a 100 Sft m2 2,950.53 85.09 790.79 317.48Pacca flat brick 3" thick, laid in reimbursement, in c/s

mortar, on sides of drains etc : Ratio 1:3

22-02-b 100 Sft m2 2,737.02 85.09 790.79 294.50Pacca flat brick 3" thick, laid in reimbursement, in c/s

mortar, on sides of drains etc : Ratio 1:5

22-02-c 100 Sft m2 2,676.01 85.09 790.79 287.94Pacca flat brick 3" thick, laid in reimbursement, in c/s

mortar, on sides of drains etc : Ratio 1:6

22-03-a 100 Sft m2 4,116.22 94.98 882.73 442.91Pacca brick on edge, laid in reimbursement, in c/s mortar,

on sides of drains etc : Ratio 1:3

22-03-b 100 Sft m2 3,800.31 94.98 882.73 408.91Pacca brick on edge, laid in reimbursement, in c/s mortar,

on sides of drains etc : Ratio 1:5

22-03-c 100 Sft m2 3,707.29 94.98 882.73 398.90Pacca brick on edge, laid in reimbursement, in c/s mortar,

on sides of drains etc : Ratio 1:6

22-04-a 100 Sft m2 3,173.81 79.65 740.27 341.50Pacca flat brick, Herring bond pitching in c/s mortar laid to

line, grade, slope etc : Ratio 1:3

22-04-b 100 Sft m2 2,931.99 79.65 740.27 315.48Pacca flat brick, Herring bond pitching in c/s mortar laid to

line, grade, slope etc : Ratio 1:5

22-04-c 100 Sft m2 2,878.80 79.65 740.27 309.76Pacca flat brick, Herring bond pitching in c/s mortar laid to

line, grade, slope etc : Ratio 1:6

22-05-a 100 Rft m 4,454.98 23.75 723.97 146.16The rate does not

include cost of

excavation, which is

to be paid separately.

Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type I

22-05-b 100 Rft m 10,342.43 60.36 1,839.76 339.32Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type II

22-05-c 100 Rft m 13,098.26 76.74 2,338.98 429.73Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type III

22-05-d 100 Rft m 14,854.77 82.67 2,519.67 487.36Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type IV

22-05-e 100 Rft m 19,605.57 110.87 3,379.28 643.23Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type V

22-05-f 100 Rft m 21,995.97 125.32 3,819.70 721.65Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type VI

22-05-g 100 Rft m 22,777.19 127.23 3,877.91 747.28Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type VII

Page 117 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 118: Rate nwfp 2008

Item Code Description

SURFACE DRAINAGEChapter #

:

22

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

22-05-h 100 Rft m 33,928.57 191.64 5,841.10 1,113.14Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type VIII

22-05-i 100 Rft m 38,410.41 218.47 6,658.88 1,260.18Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type IX

22-05-j 100 Rft m 44,548.93 235.70 7,184.26 1,461.58Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type X

22-05-k 100 Rft m 47,258.26 257.64 7,852.83 1,550.47Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type XI

22-05-l 100 Rft m 48,374.84 263.36 8,027.16 1,587.10Construct Punjab standard drains, of cement concrete

1:1.5:3, complete : Type XII

22-06-a 100 Rft m 4,571.15 139.89 4,263.89 149.97Laying RC hume pipes in position including jointing 6" to

12" dia

22-06-b 100 Rft m 6,984.96 208.68 6,360.47 229.17Laying RC hume pipes in position including jointing 12" to

24" dia

22-06-c 100 Rft m 9,484.27 280.27 8,542.64 311.16Laying RC hume pipes in position including jointing 24" to

36" dia

Page 118 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 119: Rate nwfp 2008

Item Code Description

SEWERAGEChapter #

:

23

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

23-01-a 1 RFT m 87.12 152.71 46.55 285.82Providing and Laying RCC pipe, moulded with cement

concrete 1:1.5:3, including cost of reinforcement, testing

etc : 4" dia:

23-01-b 1 RFT m 98.32 171.32 52.22 322.57Providing and Laying RCC pipe, moulded with cement

concrete 1:1.5:3, including cost of reinforcement, testing

etc : 6" dia:

23-01-c 1 RFT m 140.46 194.57 59.31 460.83Providing and Laying RCC pipe, moulded with cement

concrete 1:1.5:3, including cost of reinforcement, testing

etc : 9" dia:

23-02-a 1 RFT m 93.65 131.78 40.17 307.25Providing and Laying non-reinforced concrete pipe,

moulded with cement concrete 1:1.5:3 complete : 4"

internal diameter

23-02-b 1 RFT m 125.99 171.32 52.22 413.36Providing and Laying non-reinforced concrete pipe,

moulded with cement concrete 1:1.5:3 complete : 6" i/d

23-02-c 1 RFT m 157.47 250.39 76.32 516.64Providing and Laying non-reinforced concrete pipe,

moulded with cement concrete : 9" i/d wall thickness 1".

23-03-a-01 1 RFT m 296.50 428.30 130.54 972.76Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 12" i/d, Wall B

23-03-a-02 1 RFT m 418.90 527.13 160.67 1,374.33Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 15" i/d, Wall B

23-03-a-03 1 RFT m 498.32 642.45 195.82 1,634.90Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 18" i/d, Wall B

23-03-a-04 1 RFT m 624.91 779.42 237.57 2,050.24Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 21" i/d, Wall B

23-03-a-05 1 RFT m 703.77 856.59 261.09 2,308.95Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 24" i/d, Wall B

23-03-a-06 1 RFT m 923.18 1,152.83 351.38 3,028.80Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 27" i/d, Wall B

23-03-a-07 1 RFT m 1,092.59 1,284.89 391.63 3,584.61Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 30" i/d, Wall B

23-03-a-08 1 RFT m 1,183.03 1,400.20 426.78 3,881.34Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 33" i/d, Wall B

23-03-a-09 1 RFT m 1,278.16 1,530.87 466.61 4,193.43Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 36" i/d, Wall B

23-03-a-10 1 RFT m 1,782.99 1,976.76 602.52 5,849.71Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 42" i/d, Wall B

23-03-a-11 1 RFT m 2,242.28 2,273.28 692.90 7,356.56Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 48" i/d, Wall B

23-03-a-12 1 RFT m 2,748.28 2,965.13 903.77 9,016.68Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 54" i/d, Wall B

23-03-a-13 1 RFT m 3,458.60 4,085.30 1,245.20 11,347.12Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 60" i/d, Wall B

Page 119 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 120: Rate nwfp 2008

Item Code Description

SEWERAGEChapter #

:

23

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

23-03-a-14 1 RFT m 4,402.74 5,609.46 1,709.76 14,444.68Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 66" i/d, Wall B

23-03-a-15 1 RFT m 5,275.92 7,626.99 2,324.71 17,309.45Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class II : 72" i/d, Wall B

23-03-b-01 1 RFT m 314.99 428.30 130.54 1,033.42Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 12" i/d, Wall B

23-03-b-02 1 RFT m 437.34 527.13 160.67 1,434.83Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 15" i/d, Wall B

23-03-b-03 1 RFT m 535.20 642.45 195.82 1,755.90Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 18" i/d, Wall B

23-03-b-04 1 RFT m 735.30 778.50 237.29 2,412.39Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 21" i/d, Wall B

23-03-b-05 1 RFT m 814.44 856.59 261.09 2,672.03Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 24" i/d, Wall B

23-03-b-06 1 RFT m 941.74 1,153.23 351.51 3,089.71Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 27" i/d, Wall B

23-03-b-07 1 RFT m 1,147.88 1,284.89 391.63 3,766.03Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 30" i/d, Wall B

23-03-b-08 1 RFT m 1,533.48 1,400.20 426.78 5,031.12Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 33" i/d, Wall B

23-03-b-09 1 RFT m 1,721.17 1,531.85 466.91 5,646.89Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 36" i/d, Wall B

23-03-b-10 1 RFT m 2,004.34 1,976.76 602.52 6,575.91Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 42" i/d, Wall B

23-03-b-11 1 RFT m 3,275.51 2,274.28 693.20 10,746.42Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 48" i/d, Wall B

23-03-b-12 1 RFT m 4,408.34 2,965.13 903.77 14,463.07Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 54" i/d, Wall B

23-03-b-13 1 RFT m 5,303.11 4,085.30 1,245.20 17,398.67Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 60" i/d, Wall B

23-03-b-14 1 RFT m 6,313.38 5,584.34 1,702.11 20,713.19Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 66" i/d, Wall B

23-03-b-15 1 RFT m 7,489.34 7,626.99 2,324.71 24,571.31Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class III : 72" i/d, Wall B

23-03-c-01 1 RFT m 327.17 428.30 130.54 1,073.39Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 12" i/d, Wall B

23-03-c-02 1 RFT m 475.34 527.13 160.67 1,559.53Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 15" i/d, Wall B

23-03-c-03 1 RFT m 712.27 642.45 195.82 2,336.85Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 18" i/d, Wall B

23-03-c-04 1 RFT m 975.08 778.50 237.29 3,199.09Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 21" i/d, Wall B

Page 120 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 121: Rate nwfp 2008

Item Code Description

SEWERAGEChapter #

:

23

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

23-03-c-05 1 RFT m 1,072.67 856.59 261.09 3,519.27Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 24" i/d, Wall B

23-03-c-06 1 RFT m 1,273.60 1,152.74 351.35 4,178.49Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 27" i/d, Wall B

23-03-c-07 1 RFT m 1,498.34 1,284.89 391.63 4,915.80Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 30" i/d, Wall B

23-03-c-08 1 RFT m 1,902.39 1,400.20 426.78 6,241.44Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 33" i/d, Wall B

23-03-c-09 1 RFT m 2,126.46 1,530.18 466.40 6,976.57Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 36" i/d, Wall B

23-03-c-10 1 RFT m 2,630.98 1,976.76 602.52 8,631.83Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 42" i/d, Wall B

23-03-c-11 1 RFT m 3,459.96 2,274.28 693.20 11,351.58Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 48" i/d, Wall B

23-03-c-12 1 RFT m 4,223.89 2,965.13 903.77 13,857.91Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 54" i/d, Wall B

23-03-c-13 1 RFT m 5,303.11 4,085.30 1,245.20 17,398.67Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 60" i/d, Wall B

23-03-c-14 1 RFT m 6,497.83 5,584.34 1,702.11 21,318.35Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 66" i/d, Wall B

23-03-c-15 1 RFT m 8,042.68 7,626.99 2,324.71 26,386.75Providing and Laying RCC pipe sewers complete As per

ASTM C-76-79, Class IV : 72" i/d, Wall B

23-04-a 1 RFT m 147.56 0.00 0.00 484.12a) This rate shall be

payable, in addition

to the item of

excavation below

SSWL for sewer and

manholes under

chapter 3 earthwork

Lowering of sub-soil water table by tubewells Upto 1 ft

below SSWL

23-04-b 1 RFT m 313.57 0.00 0.00 1,028.76b) The grant of these

rates shall be subject

to Superintending

Engineer's approval.

Lowering of sub-soil water table by tubewells 0 - 2 ft

below SSWL

23-04-c 1 RFT m 494.33 0.00 0.00 1,621.82c) The rate includes

cost of providing

pumps, POL and all

operation charges at

the site of work, etc

Lowering of sub-soil water table by tubewell 0 - 3 ft below

SSWL

23-04-d 1 RFT m 686.16 0.00 0.00 2,251.18Lowering of sub-soil water table by tubewells 0 - 4 ft

below SSWL

23-04-e 1 RFT m 900.12 0.00 0.00 2,953.16Lowering of sub-soil water table by tubewells 0 - 5 ft

below SSWL

23-04-f 1 RFT m 1,121.46 0.00 0.00 3,679.34Lowering of sub-soil water table by tubewells 0 - 6 ft

below SSWL

Page 121 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 122: Rate nwfp 2008

Item Code Description

SEWERAGEChapter #

:

23

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

23-04-g 1 RFT m 1,328.05 0.00 0.00 4,357.12Lowering of sub-soil water table by tubewells 0 - 7 ft

below SSWL

23-04-h 1 RFT m 1,519.88 0.00 0.00 4,986.48Lowering of sub-soil water table by tubewells 0 - 8 ft

below SSWL

23-04-i 1 RFT m 1,726.46 0.00 0.00 5,664.25Lowering of sub-soil water table by tubewells 0 - 9 ft

below SSWL

23-04-j 1 RFT m 2,036.34 0.00 0.00 6,680.91Lowering of sub-soil water table by tubewells 0 - 10 ft

below SSWL

23-04-k 1 RFT m 2,154.39 0.00 0.00 7,068.21Lowering of sub-soil water table by tubewells 0 - 11 ft

below SSWL

23-04-l 1 RFT m 2,360.98 0.00 0.00 7,745.98Lowering of sub-soil water table by tubewells 0 - 12 ft

below SSWL

23-05-a Each Each 4,111.04 805.66 805.66 4,111.04Pipe connection to be

paid separately.

Constructing gully grating chamber complete With CI

gully trap,weighing 81 lbs. frame hinged

23-05-b Each Each 3,037.50 805.66 805.66 3,037.50Constructing gully grating chamber complete Concrete

gully trap

23-06 Set Set 593.65 593.65 593.65 593.65Fixing manhole frame and cover in RCC slab, including

carriage to site

23-07 Set Set 4,451.69 1,362.18 1,362.18 4,451.69Providing and Fixing 3" thick RCC manhole cover, 22" dia

with tee shaped CI frame of 20" clear i/d complete

23-08-a Set Set 14,219.40 1,899.31 1,899.31 14,219.40RCC manhole cover 22" dia with: Tee shaped CI frame,

22" i/d complete

23-08-b Set Set 12,762.35 1,897.76 1,897.76 12,762.35RCC manhole cover 22" dia with: 3"x3"x1/4" angle iron

frame, 22" i/d complete

23-09-a 100 Kg 100 Kg 7,960.18 158.10 158.10 7,960.18Providing and Fixing CI ventilating shaft of 9" i/d, painted

with bitumenous paint complete : 18 ft. long

23-09-b 100 Kg 100 Kg 8,012.88 210.80 210.80 8,012.88Providing and Fixing CI ventilating shaft of 9" i/d, painted

with bitumenous paint complete : 24 ft. long

23-09-c 100 Kg 100 Kg 8,065.58 263.50 263.50 8,065.58Providing and Fixing CI ventilating shaft of 9" i/d, painted

with bitumenous paint complete : 30 ft. long

23-09-d 100 Kg 100 Kg 8,118.28 316.20 316.20 8,118.28Providing and Fixing CI ventilating shaft of 9" i/d, painted

with bitumenous paint complete : 36 ft. long

23-10 Each Each 10,493.30 1,426.00 1,426.00 10,493.30Septic Tank (int.Size: 7'x2'x5') complete

23-11 Each Each 10,190.56 1,426.00 1,426.00 10,190.56Soakage Pit (6'dia x 15' deep) complete

Page 122 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 123: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-01 Job Job 19,360.00 0.00 0.00 19,360.00Mobilization of plant, equipment and camping

arrangements etc & demobilization after completion

24-02-a-01 1 Rft m 96.55 158.20 48.22 316.75Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 3" i/d

24-02-a-02 1 Rft m 144.31 235.64 71.82 473.47Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 4" i/d

24-02-a-03 1 Rft m 213.37 355.19 108.26 700.05Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 5" i/d

24-02-a-04 1 Rft m 309.90 533.92 162.74 1,016.72Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 6" i/d

24-02-a-05 1 Rft m 442.77 800.90 244.11 1,452.67Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 8" i/d

24-02-a-06 1 Rft m 614.50 1,201.34 366.17 2,016.06Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 10" i/d

24-02-a-07 1 Rft m 755.70 1,501.68 457.71 2,479.35Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 12" i/d

24-02-a-08 1 Rft m 914.84 1,877.12 572.15 3,001.44Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 15" i/d

24-02-a-09 1 Rft m 1,092.15 2,346.42 715.19 3,583.17Tubewell boring in all soils except shingle/rock From

ground upto 100' below ground : 18" i/d

24-02-b-01 1 Rft m 363.13 605.13 184.44 1,191.38Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 5" i/d

24-02-b-02 1 Rft m 592.49 854.29 260.39 1,943.88Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 6" i/d

24-02-b-03 1 Rft m 575.61 1,041.17 317.35 1,888.48Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 8" i/d

24-02-b-04 1 Rft m 642.88 1,131.53 344.89 2,109.20Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 10" i/d

24-02-b-05 1 Rft m 827.53 1,590.69 484.84 2,715.00Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 12" i/d

24-02-b-06 1 Rft m 1,052.05 2,158.66 657.96 3,451.62Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 15" i/d

24-02-b-07 1 Rft m 1,255.95 2,698.32 822.45 4,120.58Tubewell boring in all soils except shingle/rock From 100'

to 200' below ground : 18" i/d

24-02-c-01 1 Rft m 490.27 817.06 249.04 1,608.51Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 5" i/d

24-02-c-02 1 Rft m 619.85 1,068.03 325.53 2,033.62Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 6" i/d

24-02-c-03 1 Rft m 634.57 1,022.77 311.74 2,081.91Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 8" i/d

24-02-c-04 1 Rft m 884.87 1,729.93 527.28 2,903.13Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 10" i/d

Page 123 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 124: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-02-c-05 1 Rft m 1,042.87 2,072.31 631.64 3,421.49Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 12" i/d

24-02-c-06 1 Rft m 1,157.26 2,374.52 723.75 3,796.78Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 15" i/d

24-02-c-07 1 Rft m 1,382.89 2,972.55 906.03 4,537.04Tubewell boring in all soils except shingle/rock From 200'

to 300' below ground : 18" i/d

24-02-d-01 1 Rft m 863.41 1,561.74 476.02 2,832.70Tubewell boring in all soils except shingle/rock From 300'

to 400' below ground : 8" i/d

24-02-d-02 1 Rft m 1,061.85 2,075.91 632.74 3,483.76Tubewell boring in all soils except shingle/rock From 300'

to 400' below ground : 10" i/d

24-02-d-03 1 Rft m 1,251.44 2,486.77 757.97 4,105.79Tubewell boring in all soils except shingle/rock From 300'

to 400' below ground : 12" i/d

24-02-d-04 1 Rft m 1,389.10 2,850.72 868.90 4,557.43Tubewell boring in all soils except shingle/rock From 300'

to 400' below ground : 15" i/d

24-02-d-05 1 Rft m 1,657.86 3,561.78 1,085.63 5,439.16Tubewell boring in all soils except shingle/rock From 300'

to 400' below ground : 18" i/d

24-03-a-01 1 Rft m 836.91 0.00 0.00 2,745.76Rotary drilling except in shingle, gravel & rock From

ground to 250' below ground : 5"-18" i/d

24-03-a-02 1 Rft m 1,018.35 0.00 0.00 3,341.04Rotary drilling except in shingle, gravel & rock From

ground to 250' below ground : 20"-26" i/d

24-03-b-01 1 Rft m 1,046.14 0.00 0.00 3,432.20Rotary drilling except in shingle, gravel & rock Exceeding

250' below ground : 5"-18" i/d

24-03-b-02 1 Rft m 1,272.94 0.00 0.00 4,176.30Rotary drilling except in shingle, gravel & rock Exceeding

250' below ground : 20"-26" i/d

24-04-a-01 1 Rft m 2,092.27 0.00 0.00 6,864.41Location and depth of

shingle, gravel or

rock is to be

determined from the

bore log.

Boring for tubewell in shingle, gravel & rock From ground

to 200' below ground : 12"-18" i/d

24-04-a-02 1 Rft m 2,545.87 0.00 0.00 8,352.59Boring for tubewell in shingle, gravel & rock From ground

to 200' below ground : 20"-26" i/d

24-04-b-01 1 Rft m 2,619.52 0.00 0.00 8,594.24Boring for tubewell in shingle, gravel & rock Over 200'

depth below ground : 12"-18" i/d

24-04-b-02 1 Rft m 3,187.43 0.00 0.00 10,457.44Boring for tubewell in shingle, gravel & rock Over 200'

depth below ground : 20"-26" i/d

24-05 Job Job 6,569.85 662.63 662.63 6,569.85Providing strong substantially built box of deodar

4'x2«'x9", with compartments & lock

24-06 Per set Per set 1,285.40 1,116.00 1,116.00 1,285.40Furnishing sample of water from bore hole

24-07-a 1 Rft m 1,531.84 658.92 200.84 5,025.72Cost/labour of

jointing both ends is

included in the rate.

Providing and installing brass strainer in tubewell bore

hole 6" i/d, 3/16" thick

24-07-b 1 Rft m 2,711.81 957.37 291.81 8,897.00Providing and installing brass strainer in tubewell bore

hole 8" i/d, 3/16" thick

Page 124 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 125: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-07-c 1 Rft m 2,963.26 988.38 301.26 9,721.98Providing and installing brass strainer in tubewell bore

hole 10" i/d 3/16" thick

24-07-d 1 Rft m 3,695.16 988.38 301.26 12,123.23Providing and installing brass strainer in tubewell bore

hole 10" i/d, 1/4" thick

24-07-e 1 Rft m 3,780.73 1,054.27 321.34 12,403.97Providing and installing brass strainer in tubewell bore

hole 12" i/d, 1/4" thick

24-08-a 1 Rft m 1,904.51 436.59 133.07 6,248.40In the case of increase

and decreas in the

length of bail plug, tie

rates will be increased

or decreased as per

rates given in section

No 12 to this

diameter.

Providing and installing MS bail plug in tubewell bore

hole 6" i/d, 2 ft. long

24-08-b 1 Rft m 2,479.60 449.62 137.04 8,135.18Providing and installing MS bail plug in tubewell bore

hole 8" i/d, 2 ft. long

24-08-c 1 Rft m 3,133.00 449.62 137.04 10,278.88Providing and installing MS bail plug in tubewell bore

hole 10" i/d, 2 ft. long

24-08-d 1 Rft m 3,576.47 479.38 146.12 11,733.81Providing and installing MS bail plug in tubewell bore

hole 12" i/d, 2 ft. long

24-09-a-01 1 Rft m 469.89 632.56 192.80 1,541.65Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'B' working pressure : 6" i/d

24-09-a-02 1 Rft m 664.51 790.70 241.01 2,180.14Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'B' working pressure : 8" i/d

24-09-a-03 1 Rft m 1,165.78 843.42 257.07 3,824.75Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'B' working pressure : 10" i/d

24-09-a-04 1 Rft m 1,563.34 948.84 289.21 5,129.06Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'B' working pressure : 12" i/d

24-09-b-01 1 Rft m 590.89 632.56 192.80 1,938.63Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'C' working pressure : 6" i/d

24-09-b-02 1 Rft m 854.48 790.70 241.01 2,803.40Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'C' working pressure : 8" i/d

24-09-b-03 1 Rft m 1,592.91 843.42 257.07 5,226.09Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'C' working pressure : 10" i/d

24-09-b-04 1 Rft m 2,170.76 948.84 289.21 7,121.91Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'C' working pressure : 12" i/d

24-09-c-01 1 Rft m 802.64 632.56 192.80 2,633.35Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'D' working pressure : 6" i/d

24-09-c-02 1 Rft m 1,177.55 790.70 241.01 3,863.34Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'D' working pressure : 8" i/d

24-09-c-03 1 Rft m 2,000.93 843.42 257.07 6,564.71Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'D' working pressure : 10" i/d

Page 125 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 126: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-09-c-04 1 Rft m 2,769.71 948.84 289.21 9,086.97Providing and installing PVC strainer, in tubewell

borehole comp. BSS Class 'D' working pressure : 12" i/d

24-10-a-01 Each Each 746.59 210.80 210.80 746.59Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'B' working pressure : 6" i/d : 2' long

24-10-a-02 Each Each 1,086.95 263.50 263.50 1,086.95Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'B' working pressure : 8" i/d : 2' long

24-10-a-03 Each Each 2,043.51 263.50 263.50 2,043.51Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'B' working pressure : 10" i/d : 2'

long

24-10-a-04 Each Each 2,816.54 316.20 316.20 2,816.54Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'B' working pressure : 12" i/d : 2'

long

24-10-b-01 Each Each 984.72 210.80 210.80 984.72Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'C' working pressure : 6" i/d : 2' long

24-10-b-02 Each Each 1,461.28 263.50 263.50 1,461.28Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'C' working pressure : 8" i/d : 2' long

24-10-b-03 Each Each 2,882.91 263.50 263.50 2,882.91Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'C' working pressure : 10" i/d : 2'

long

24-10-b-04 Each Each 4,009.33 316.20 316.20 4,009.33Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'C' working pressure : 12" i/d : 2'

long

24-10-c-01 Each Each 1,232.37 210.80 210.80 1,232.37Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'D' working pressure : 6" i/d : 2' long

24-10-c-02 Each Each 1,826.81 263.50 263.50 1,826.81Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'D' working pressure : 8" i/d : 2' long

24-10-c-03 Each Each 3,733.74 263.50 263.50 3,733.74Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'D' working pressure : 10" i/d : 2'

long

24-10-c-04 Each Each 5,188.78 316.20 316.20 5,188.77Providing and installing PVC pipe with wooden bail plug

in tubewell BSS Class 'D' working pressure : 12" i/d : 2'

long

24-11-a 1 Rft m 688.21 1,186.05 361.51 2,257.90Providing and installing MS blind pipe socket/welded

joint MS reducer in tubewell borehole : 6" i/d, 3/16" thick

24-11-b 1 Rft m 899.49 1,383.73 421.76 2,951.08Providing and installing MS blind pipe socket/welded

joint MS reducer in tubewell borehole : 8" i/d, 3/16" thick

24-11-c 1 Rft m 1,082.75 1,647.30 502.10 3,552.33Providing and installing MS blind pipe socket/welded

joint MS reducer in tubewell borehole : 10" i/d 3/16" thick

24-11-d 1 Rft m 1,249.82 1,897.69 578.41 4,100.45Providing and installing MS blind pipe socket/welded

joint MS reducer in tubewell borehole : 12" i/d, 1/4" thick

24-12-a-01 1 Rft m 609.66 1,106.98 337.41 2,000.19Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'B' working pressure : 6" i/d

Page 126 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 127: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-12-a-02 1 Rft m 820.09 1,317.84 401.68 2,690.60Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'B' working pressure : 8" i/d

24-12-a-03 1 Rft m 1,450.52 1,791.48 546.04 4,758.92Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'B' working pressure : 10" i/d

24-12-a-04 1 Rft m 1,812.76 1,779.08 542.26 5,947.39Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'B' working pressure : 12" i/d

24-12-b-01 1 Rft m 734.68 1,120.16 341.43 2,410.35Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'C' working pressure : 6" i/d

24-12-b-02 1 Rft m 1,010.31 1,317.84 401.68 3,314.66Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'C' working pressure : 8" i/d

24-12-b-03 1 Rft m 1,772.84 1,449.62 441.84 5,816.42Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'C' working pressure : 10" i/d

24-12-b-04 1 Rft m 2,418.85 1,779.08 542.26 7,935.87Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'C' working pressure : 12" i/d

24-12-c-01 1 Rft m 860.52 1,120.16 341.43 2,823.21Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'D' working pressure : 6" i/d

24-12-c-02 1 Rft m 1,196.04 1,317.84 401.68 3,924.02Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'D' working pressure : 8" i/d

24-12-c-03 1 Rft m 2,205.18 1,449.62 441.84 7,234.83Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'D' working pressure : 10" i/d

24-12-c-04 1 Rft m 3,018.17 1,779.08 542.26 9,902.12Providing and installing PVC blind pipe in tubewell with

strainer BSS Class 'D' working pressure : 12" i/d

24-13-a Hour Hour 423.50 0.00 0.00 423.50Compressor,

accessories along

with working staff to

be supplied by Govt;

Test & develop tubewell of size 6" i/d & above

continuously : Upto 1.5 cusecs discharge

24-13-b Hour Hour 496.10 0.00 0.00 496.10Test & develop tubewell of size 6" i/d & above

continuously : Over 1.5 cusecs discharge with DNT unit

24-14 1 Rft m 129.77 348.84 106.33 425.74The rate includes

wastage etc.

Shrouding with graded pack grave 3/8" to 1/8" around

tubewell in bore hole

24-15-a 1 Rft m 196.13 98.84 30.13 643.48a) Pipes to be

supplied by Govt;

Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches, complete : 3" i/d

24-15-b 1 Rft m 263.72 131.78 40.17 865.23b) Providing and

installing specials and

valves is not included

in the rate, which is

payable separately.

Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches, complete : 4" i/d

24-15-c 1 Rft m 503.67 197.68 60.25 1,652.47Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches, complete : 6" i/d

24-15-d 1 Rft m 1,350.63 329.46 100.42 4,431.20Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches. complete : 8" i/d

24-15-e 1 Rft m 1,716.83 428.30 130.54 5,632.63Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches, complete : 10" i/d

Page 127 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 128: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-15-f 1 Rft m 2,380.85 428.30 130.54 7,811.19Providing and Laying cut, joint, test & disinfect, CI

pipeline in trenches, complete : 12" i/d

24-16-a-01 1 Rft m 552.41 125.19 38.16 1,812.37Providing and Laying cut, joint, test & disinfect GI pipe

line Using heavy quality GI Pipe : 4" Dia

24-16-a-02 1 Rft m 937.53 177.91 54.23 3,075.87Providing and Laying cut, joint, test & disinfect GI pipe

line Using heavy quality GI Pipe : 6" Dia

24-16-a-03 1 Rft m 1,957.89 230.62 70.29 6,423.53Providing and Laying cut, joint, test & disinfect GI pipe

line Using heavy quality GI Pipe : 8" Dia

24-16-b-01 1 Rft m 478.96 125.19 38.16 1,571.40Providing and Laying cut, joint, test & disinfect GI pipe

line Using medium quality GI Pipe : 4" Dia

24-16-b-02 1 Rft m 699.76 177.91 54.23 2,295.81Providing and Laying cut, joint, test & disinfect GI pipe

line Using medium quality GI Pipe : 6" Dia

24-16-b-03 1 Rft m 814.20 230.62 70.29 2,671.26Providing and Laying cut, joint, test & disinfect GI pipe

line Using medium quality GI Pipe : 8" Dia

24-16-c-01 1 Rft m 48.40 32.95 10.04 158.79Cost of sockets, tees,

elbows, bends, valves,

crosses, unions and

plugs etc is included

in the rates.

Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 1/2" i/d

24-16-c-02 1 Rft m 66.83 39.54 12.05 219.25Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 3/4" i/d

24-16-c-03 1 Rft m 90.19 43.02 13.11 295.90Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 1" i/d

24-16-c-04 1 Rft m 114.92 52.71 16.07 377.05Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 1.25" i/d

24-16-c-05 1 Rft m 143.19 59.30 18.08 469.78Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 1.5" i/d

24-16-c-06 1 Rft m 177.52 66.02 20.12 582.41Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 2" i/d

24-16-c-07 1 Rft m 237.58 72.48 22.09 779.47Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 2.5" i/d

24-16-c-08 1 Rft m 282.77 98.84 30.13 927.74Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 3" i/d

24-16-c-09 1 Rft m 401.52 125.19 38.16 1,317.33Providing and Laying cut, joint, test & disinfect GI pipe

line Using light quality GI Pipe : 4" i/d

24-17-a-01 1 Rft m 79.23 52.71 16.07 259.94Providing and

installing specials and

valves is not included

in the rate, which is

payable separately.

Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 3" i/d

24-17-a-02 1 Rft m 110.57 59.30 18.08 362.76Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 4" i/d

Page 128 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 129: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-17-a-03 1 Rft m 165.73 85.66 26.11 543.74Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 6" i/d

24-17-a-04 1 Rft m 267.37 118.61 36.15 877.20Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 8" i/d

24-17-a-05 1 Rft m 427.75 141.63 43.17 1,403.40Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 10" i/d

24-17-a-06 1 Rft m 590.41 197.68 60.25 1,937.05Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 12" i/d

24-17-a-07 1 Rft m 789.24 230.62 70.29 2,589.37Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 14" i/d

24-17-a-08 1 Rft m 1,014.37 263.57 80.34 3,327.99Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 16" i/d

24-17-a-09 1 Rft m 1,249.94 303.10 92.39 4,100.87Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 18" i/d

24-17-a-10 1 Rft m 1,517.30 355.82 108.45 4,978.03Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 20" i/d

24-17-a-11 1 Rft m 2,120.39 421.71 128.54 6,956.66Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'B'working pressure : 24" i/d

24-17-b-01 1 Rft m 79.59 52.71 16.07 261.13Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 3" i/d

24-17-b-02 1 Rft m 115.24 59.30 18.08 378.08Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 4" i/d

24-17-b-03 1 Rft m 225.38 85.66 26.11 739.45Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 6" i/d

24-17-b-04 1 Rft m 330.19 118.61 36.15 1,083.31Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 8" i/d

24-17-b-05 1 Rft m 550.07 151.55 46.19 1,804.70Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 10" i/d

24-17-b-06 1 Rft m 774.94 215.12 65.57 2,542.46Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 12" i/d

24-17-b-07 1 Rft m 1,053.01 230.62 70.29 3,454.75Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 14" i/d

24-17-b-08 1 Rft m 1,465.65 263.57 80.34 4,808.57Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 16" i/d

24-17-b-09 1 Rft m 1,812.85 303.10 92.39 5,947.66Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 18" i/d

24-17-b-10 1 Rft m 2,201.70 355.82 108.45 7,223.44Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 20" i/d

24-17-b-11 1 Rft m 3,125.65 421.71 128.54 10,254.74Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'C'working pressure : 24" i/d

24-17-c-01 1 Rft m 79.59 52.71 16.07 261.13Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 3" i/d

Page 129 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 130: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-17-c-02 1 Rft m 145.11 64.54 19.67 476.09Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 4" i/d

24-17-c-03 1 Rft m 278.66 93.22 28.41 914.25Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 6" i/d

24-17-c-04 1 Rft m 468.53 129.07 39.34 1,537.16Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 8" i/d

24-17-c-05 1 Rft m 816.42 182.60 55.66 2,678.54Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 10" i/d

24-17-c-06 1 Rft m 1,162.51 215.12 65.57 3,813.99Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 12" i/d

24-17-c-07 1 Rft m 1,479.14 250.97 76.50 4,852.82Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 14" i/d

24-17-c-08 1 Rft m 2,127.87 286.82 87.42 6,981.20Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 16" i/d

24-17-c-09 1 Rft m 2,649.16 329.85 100.54 8,691.47Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 18" i/d

24-17-c-10 1 Rft m 3,356.03 387.21 118.02 11,010.60Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 20" i/d

24-17-c-11 1 Rft m 4,278.70 458.92 139.88 14,037.71Providing and Laying cut, joint, test & disinfect AC pipe

line BSS Class 'D'working pressure : 24" i/d

24-18-a-01 1 Rft m 110.29 57.36 17.48 361.85a) Providing and

installing specials and

valves is not included

in the rate, which is

payable separately.

Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 3" i/d

24-18-a-02 1 Rft m 159.67 64.54 19.67 523.84b) When sockets are

used for jointing of

pipes instead of by

overlap pipe. Its

providing installation

will be paid extra.

Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 4" i/d

24-18-a-03 1 Rft m 300.66 93.22 28.41 986.43Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 6" i/d

24-18-a-04 1 Rft m 457.76 129.07 39.34 1,501.83Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 8" i/d

24-18-a-05 1 Rft m 954.74 164.92 50.27 3,132.36Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 10" i/d

24-18-a-06 1 Rft m 1,336.07 215.12 65.57 4,383.43Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'B'working pressure : 12" i/d

24-18-b-01 1 Rft m 97.71 57.36 17.48 320.56Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 2.5" i/d

24-18-b-02 1 Rft m 129.17 57.36 17.48 423.78Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 3" i/d

Page 130 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 131: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-18-b-03 1 Rft m 158.82 64.54 19.67 521.06Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 4" i/d

24-18-b-04 1 Rft m 421.66 93.22 28.41 1,383.41Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 6" i/d

24-18-b-05 1 Rft m 647.97 129.07 39.34 2,125.89Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 8" i/d

24-18-b-06 1 Rft m 1,381.27 164.92 50.27 4,531.72Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 10" i/d

24-18-b-07 1 Rft m 1,942.16 215.12 65.57 6,371.91Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'C'working pressure : 12" i/d

24-18-c-01 1 Rft m 47.26 45.89 13.99 155.06Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 1.25" i/d

24-18-c-02 1 Rft m 60.44 53.40 16.28 198.29Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 1.5" i/d

24-18-c-03 1 Rft m 84.04 53.40 16.28 275.71Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 2" i/d

24-18-c-04 1 Rft m 119.73 57.36 17.48 392.81Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 2.5" i/d

24-18-c-05 1 Rft m 127.59 57.36 17.48 418.62Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 3" i/d

24-18-c-06 1 Rft m 253.93 64.54 19.67 833.09Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 4" i/d

24-18-c-07 1 Rft m 547.50 93.22 28.41 1,796.27Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 6" i/d

24-18-c-08 1 Rft m 833.71 129.07 39.34 2,735.26Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 8" i/d

24-18-c-09 1 Rft m 1,813.60 164.92 50.27 5,950.14Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 10" i/d

24-18-c-10 1 Rft m 2,541.47 215.12 65.57 8,338.16Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'D' working pressure : 12" i/d

24-18-d-01 1 Rft m 33.94 49.43 15.07 111.36Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'E' working pressure : 3/4" i/d

24-18-d-02 1 Rft m 35.00 27.10 8.26 114.83Providing and Laying cut, joint, test, disinfect PVC pipe

line BSS Class 'E' working pressure : 1" i/d

Page 131 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 132: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-19-a-01 kg kg 188.40 28.67 28.67 188.40a) Labour rates

include the cost of

jointing material and

labour b) The internal

dia of the pipe, from

which the branch is

taken out, will be

considered internal

dia for the purpose of

payment of specials.

Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CISS specials, with spigot & socket : 3"-6" i/d

24-19-a-02 kg kg 194.29 34.56 34.56 194.29Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CISS specials, with spigot & socket : 8"-12" i/d

24-19-b-01 kg kg 174.06 14.34 14.34 174.06Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CI flanged specials with flanged joint : 3"-6" i/d

24-19-b-02 kg kg 182.66 22.94 22.94 182.66Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CI flanged specials with flanged joint : 8"-12" i/

24-19-c-01 kg kg 166.30 6.58 6.58 166.30Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CI specials with tyton joints : 3"-6" i/d

24-19-c-02 kg kg 171.70 11.98 11.98 171.70Providing and Fixing CI specials of BSS class 'B', 'C' & 'D'

CI specials with tyton joints : 8"-12" i/d

24-20-a kg kg 196.74 37.02 37.02 196.74a) Labour rates

include the cost of

jointing material and

labour b) The internal

dia of the pipe, from

which the branch is

taken out, will be

considered internal

dia for the purpose of

payment of specials.

Providing and Fixing CI specials of BSS Class 'B', 'C' & 'D'

working pressure for AC pipe line : 3" to 6" i/d

24-20-b kg kg 217.07 57.35 57.35 217.07Providing and Fixing CI specials of BSS Class 'B', 'C' & 'D'

working pressure for AC pipe line : 8" to 18" i/d

24-21-a Each Each 2,682.23 867.22 867.22 2,682.23Labour rates include

the cost of jointing

material and labour

Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 3" i/d

24-21-b Each Each 2,649.40 229.40 229.40 2,649.40Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 4" i/d

24-21-c Each Each 4,783.40 911.40 911.40 4,783.40Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 6" i/d

24-21-d Each Each 8,776.40 911.40 911.40 8,776.40Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 8" i/d

24-21-e Each Each 12,642.00 1,147.00 1,147.00 12,642.00Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 10" i/d

24-21-f Each Each 17,450.50 1,720.50 1,720.50 17,450.50Providing and Fixing sluice valve, BSS quality/weight,

Class 'B' working pressure for CI & AC pipe line : 12" i/d

Page 132 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 133: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-22-a Each Each 2,922.63 926.13 926.13 2,922.63dittoProviding and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 3" i/d

24-22-b Each Each 3,588.13 926.13 926.13 3,588.13Providing and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 4" i/d

24-22-c Each Each 5,406.20 1,147.00 1,147.00 5,406.20Providing and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 6" i/d

24-22-d Each Each 10,085.25 1,433.75 1,433.75 10,085.25Providing and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 8" i/d

24-22-e Each Each 14,512.25 1,867.75 1,867.75 14,512.25Providing and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 10" i/d

24-22-f Each Each 19,597.00 2,294.00 2,294.00 19,597.00Providing and Fixing sluice valve of BSS quality weight

for GI & PVC pipe line including jointing material : 12" i/d

24-23 Each Each 5,985.75 1,720.50 1,720.50 5,985.75a) Labour rates

include cost of

jointing material and

labour b) Connecting

pipes and specials , if

used will be paid

extra.

Providing and Fixing fire hydrants BSS quality and weight

of 2.5" dia (including cost of jointing material)

24-24-a Each Each 3,034.60 1,147.00 1,147.00 3,034.60Providing and Fixing air valve 2«" i/d of BSS quality and

weight complete with jointing material : Single

24-24-b Each Each 4,793.90 1,720.50 1,720.50 4,793.90Providing and Fixing air valve 2«" i/d of BSS quality and

weight complete with jointing material : Double

24-25-a Each Each 1,307.93 702.92 702.92 1,307.93Providing and Fixing CI flanges 5/8" thick on pipes

including turning, facing & fitting etc complete : 3" to 6"

i/d

24-25-b Each Each 2,073.68 1,033.07 1,033.07 2,073.68Providing and Fixing CI flanges 5/8" thick on pipes

including turning, facing & fitting etc complete : 8" to 12"

i/d

24-26-a-01 Each Each 167.40 98.19 98.19 167.40Providing and installing PVC bends BSS Class 'B'working

pressure : 2" i/d

24-26-a-02 Each Each 245.96 107.53 107.53 245.96Providing and installing PVC bends BSS Class 'B'working

pressure : 3" i/d

24-26-a-03 Each Each 316.40 143.38 143.38 316.40Providing and installing PVC bends BSS Class 'B'working

pressure : 4" i/d

24-26-a-04 Each Each 986.53 207.89 207.89 986.53Providing and installing PVC bends BSS Class 'B'working

pressure : 6" i/d

24-26-a-05 Each Each 3,055.23 286.75 286.75 3,055.23Providing and installing PVC bends BSS Class 'B'working

pressure : 8" i/d

24-26-a-06 Each Each 4,655.13 329.38 329.38 4,655.13Providing and installing PVC bends BSS Class 'B'working

pressure : 10" i/d

24-26-a-07 Each Each 5,586.15 395.25 395.25 5,586.15Providing and installing PVC bends BSS Class 'B'working

pressure : 12" i/d

Page 133 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 134: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-26-b-01 Each Each 176.80 90.29 90.29 176.80Providing and installing PVC bends BSS Class 'C'working

pressure : 2" i/d

24-26-b-02 Each Each 271.84 98.81 98.81 271.84Providing and installing PVC bends BSS Class 'C'working

pressure : 3" i/d

24-26-b-03 Each Each 339.39 131.75 131.75 339.39Providing and installing PVC bends BSS Class 'C'working

pressure : 4" i/d

24-26-b-04 Each Each 1,318.39 191.04 191.04 1,318.40Providing and installing PVC bends BSS Class 'C'working

pressure : 6" i/d

24-26-b-05 Each Each 3,724.10 263.50 263.50 3,724.10Providing and installing PVC bends BSS Class 'C'working

pressure : 8" i/d

24-26-b-06 Each Each 5,520.27 329.38 329.38 5,520.27Providing and installing PVC bends BSS Class 'C'working

pressure : 10" i/d

24-26-b-07 Each Each 6,624.33 395.25 395.25 6,624.33Providing and installing PVC bends BSS Class 'C'working

pressure : 12" i/d

24-26-c-01 Each Each 194.11 90.29 90.29 194.11Providing and installing PVC bends BSS Class 'D'working

pressure : 2" i/d

24-26-c-02 Each Each 358.36 98.81 98.81 358.36Providing and installing PVC bends BSS Class 'D'working

pressure : 3" i/d

24-26-c-03 Each Each 489.43 143.38 143.38 489.43Providing and installing PVC bends BSS Class 'D'working

pressure : 4" i/d

24-26-c-04 Each Each 1,938.19 207.89 207.89 1,938.19Providing and installing PVC bends BSS Class 'D'working

pressure : 6" i/d

24-26-c-05 Each Each 5,304.62 286.75 286.75 5,304.62Providing and installing PVC bends BSS Class 'D'working

pressure : 8" i/d

24-26-c-06 Each Each 6,587.52 358.44 358.44 6,587.52Providing and installing PVC bends BSS Class 'D'working

pressure : 10" i/d

24-26-c-07 Each Each 7,351.33 430.13 430.13 7,351.33Providing and installing PVC bends BSS Class 'D'working

pressure : 12" i/d

24-27-a-01 Each Each 247.19 143.38 143.38 247.19Providing and installing PVC tees BSS Class 'B'working

pressure : 2" i/d

24-27-a-02 Each Each 772.33 172.05 172.05 772.33Providing and installing PVC tees BSS Class 'B'working

pressure : 3" i/d

24-27-a-03 Each Each 1,445.93 229.40 229.40 1,445.93Providing and installing PVC tees BSS Class 'B'working

pressure : 4" i/d

24-27-a-04 Each Each 2,824.36 315.42 315.42 2,824.36Providing and installing PVC tees BSS Class 'B'working

pressure : 6" i/d

24-27-a-05 Each Each 3,018.83 465.97 465.97 3,018.83Providing and installing PVC tees BSS Class 'B'working

pressure : 8" i/d

24-27-a-06 Each Each 3,133.11 537.66 537.66 3,133.11Providing and installing PVC tees BSS Class 'B'working

pressure : 10" i/d

24-27-a-07 Each Each 3,327.15 645.19 645.19 3,327.15Providing and installing PVC tees BSS Class 'B'working

pressure : 12" i/d

Page 134 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 135: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-27-b-01 Each Each 264.50 143.38 143.38 264.50Providing and installing PVC tees BSS Class 'C'working

pressure : 2" i/d

24-27-b-02 Each Each 431.60 172.05 172.05 431.60Providing and installing PVC tees BSS Class 'C'working

pressure : 3" i/d

24-27-b-03 Each Each 671.29 229.40 229.40 671.29Providing and installing PVC tees BSS Class 'C'working

pressure : 4" i/d

24-27-b-04 Each Each 1,197.88 315.42 315.42 1,197.88Providing and installing PVC tees BSS Class 'C'working

pressure : 6" i/d

24-27-b-05 Each Each 6,522.02 465.97 465.97 6,522.02Providing and installing PVC tees BSS Class 'C'working

pressure : 8" i/d

24-27-b-06 Each Each 7,801.97 534.71 534.71 7,801.97Providing and installing PVC tees BSS Class 'C'working

pressure : 10" i/d

24-27-b-07 Each Each 9,902.29 645.19 645.19 9,902.29Providing and installing PVC tees BSS Class 'C'working

pressure : 12" i/d

24-27-c-01 Each Each 406.91 143.38 143.38 406.91Providing and installing PVC tees BSS Class 'D'working

pressure : 2" i/d

24-27-c-02 Each Each 695.13 172.05 172.05 695.13Providing and installing PVC tees BSS Class 'D'working

pressure : 3" i/d

24-27-c-03 Each Each 852.31 229.40 229.40 852.31Providing and installing PVC tees BSS Class 'D'working

pressure : 4" i/d

24-27-c-04 Each Each 2,910.88 315.42 315.42 2,910.88Providing and installing PVC tees BSS Class 'D'working

pressure : 6" i/d

24-27-c-05 Each Each 4,618.69 465.97 465.97 4,618.69Providing and installing PVC tees BSS Class 'D'working

pressure : 8" i/d

24-27-c-06 Each Each 5,921.55 537.66 537.66 5,921.55Providing and installing PVC tees BSS Class 'D'working

pressure : 10" i/d

24-27-c-07 Each Each 6,874.27 645.19 645.19 6,874.27Providing and installing PVC tees BSS Class 'D'working

pressure : 12" i/d

24-28-a-01 Each Each 108.61 48.05 48.05 108.61Providing and installing PVC sockets BSS Class

'B'working pressure : 2" i/d

24-28-a-02 Each Each 179.95 50.18 50.18 179.95Providing and installing PVC sockets BSS Class

'B'working pressure : 3" i/d

24-28-a-03 Each Each 210.11 71.69 71.69 210.11Providing and installing PVC sockets BSS Class

'B'working pressure : 4" i/d

24-28-a-04 Each Each 823.83 564.28 564.28 823.83Providing and installing PVC sockets BSS Class

'B'working pressure : 6" i/d

24-28-a-05 Each Each 748.98 143.38 143.38 748.98Providing and installing PVC sockets BSS Class

'B'working pressure : 8" i/d

24-28-a-06 Each Each 1,909.37 179.07 179.07 1,909.37Providing and installing PVC sockets BSS Class

'B'working pressure : 10" i/d

24-28-a-07 Each Each 2,810.51 215.06 215.06 2,810.51Providing and installing PVC sockets BSS Class

'B'working pressure : 12" i/d

Page 135 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 136: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-28-b-01 Each Each 117.26 48.05 48.05 117.26Providing and installing PVC sockets BSS Class

'C'working pressure : 2" i/d

24-28-b-02 Each Each 428.91 282.10 282.10 428.91Providing and installing PVC sockets BSS Class

'C'working pressure : 3" i/d

24-28-b-03 Each Each 244.72 71.69 71.69 244.72Providing and installing PVC sockets BSS Class

'C'working pressure : 4" i/d

24-28-b-04 Each Each 982.82 100.36 100.36 982.82Providing and installing PVC sockets BSS Class

'C'working pressure : 6" i/d

24-28-b-05 Each Each 1,787.16 143.38 143.38 1,787.16Providing and installing PVC sockets BSS Class

'C'working pressure : 8" i/d

24-28-b-06 Each Each 2,255.58 179.22 179.22 2,255.58Providing and installing PVC sockets BSS Class

'C'working pressure : 10" i/d

24-28-b-07 Each Each 3,329.60 215.06 215.06 3,329.60Providing and installing PVC sockets BSS Class

'C'working pressure : 12" i/d

24-28-c-01 Each Each 169.17 48.05 48.05 169.17Providing and installing PVC sockets BSS Class

'D'working pressure : 2" i/d

24-28-c-02 Each Each 400.23 50.18 50.18 400.23Providing and installing PVC sockets BSS Class

'D'working pressure : 3" i/d

24-28-c-03 Each Each 670.64 71.69 71.69 670.64Providing and installing PVC sockets BSS Class

'D'working pressure : 4" i/d

24-28-c-04 Each Each 1,792.60 100.36 100.36 1,792.60Providing and installing PVC sockets BSS Class

'D'working pressure : 6" i/d

24-28-c-05 Each Each 2,652.31 143.38 143.38 2,652.31Providing and installing PVC sockets BSS Class

'D'working pressure : 8" i/d

24-28-c-06 Each Each 2,965.00 179.22 179.22 2,965.00Providing and installing PVC sockets BSS Class

'D'working pressure : 10" i/d

24-28-c-07 Each Each 3,589.15 215.06 215.06 3,589.15Providing and installing PVC sockets BSS Class

'D'working pressure : 12" i/d

24-29-a-01 Each Each 176.06 98.19 98.19 176.06Providing and installing PVC tappered core BSS Class

'B'working pressure : 2" i/d

24-29-a-02 Each Each 202.70 107.53 107.53 202.70Providing and installing PVC tappered core BSS Class

'B'working pressure : 3" i/d

24-29-a-03 Each Each 259.31 143.38 143.38 259.31Providing and installing PVC tappered core BSS Class

'B'working pressure : 4" i/d

24-29-a-04 Each Each 360.16 207.89 207.89 360.16Providing and installing PVC tappered core BSS Class

'B'working pressure : 6" i/d

24-29-a-05 Each Each 546.29 286.75 286.75 546.29Providing and installing PVC tappered core BSS Class

'B'working pressure : 8" i/d

24-29-a-06 Each Each 791.01 358.44 358.44 791.01Providing and installing PVC tappered core BSS Class

'B'working pressure : 10" i/d

24-29-a-07 Each Each 909.03 424.55 424.55 909.03Providing and installing PVC tappered core BSS Class

'B'working pressure : 12" i/d

Page 136 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 137: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-29-b-01 Each Each 184.71 98.19 98.19 184.71Providing and installing PVC tappered core BSS Class

'C'working pressure : 2" i/d

24-29-b-02 Each Each 211.35 107.53 107.53 211.35Providing and installing PVC tappered core BSS Class

'C'working pressure : 3" i/d

24-29-b-03 Each Each 267.96 143.38 143.38 267.96Providing and installing PVC tappered core BSS Class

'C'working pressure : 4" i/d

24-29-b-04 Each Each 369.11 208.19 208.19 369.11Providing and installing PVC tappered core BSS Class

'C'working pressure : 6" i/d

24-29-b-05 Each Each 554.95 286.75 286.75 554.95Providing and installing PVC tappered core BSS Class

'C'working pressure : 8" i/d

24-29-b-06 Each Each 818.70 358.44 358.44 818.70Providing and installing PVC tappered core BSS Class

'C'working pressure : 10" i/d

24-29-b-07 Each Each 976.01 430.96 430.96 976.01Providing and installing PVC tappered core BSS Class

'C'working pressure : 12" i/d

24-29-c-01 Each Each 167.40 98.19 98.19 167.40Providing and installing PVC tappered core BSS Class

'D'working pressure : 2" i/d

24-29-c-02 Each Each 197.51 107.53 107.53 197.51Providing and installing PVC tappered core BSS Class

'D'working pressure : 3" i/d

24-29-c-03 Each Each 286.99 143.38 143.38 286.99Providing and installing PVC tappered core BSS Class

'D'working pressure : 4" i/d

24-29-c-04 Each Each 424.18 207.89 207.89 424.18Providing and installing PVC tappered core BSS Class

'D'working pressure : 6" i/d

24-29-c-05 Each Each 650.11 286.75 286.75 650.11Providing and installing PVC tappered core BSS Class

'D'working pressure : 8" i/d

24-29-c-06 Each Each 1,033.25 358.44 358.44 1,033.26Providing and installing PVC tappered core BSS Class

'D'working pressure : 10" i/d

24-29-c-07 Each Each 1,314.31 430.13 430.13 1,314.31Providing and installing PVC tappered core BSS Class

'D'working pressure : 12" i/d

24-30-a-01 1 Rft m 24.40 43.10 13.14 80.06Providing and Laying HDPE pipe Din-/Din-/ISO-4427

incl testing & disinfect complete (20mm dia)

24-30-a-02 1 Rft m 27.78 43.10 13.14 91.14Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 including testing & disinfect

complete (25mm dia)

24-30-a-03 1 Rft m 37.58 43.10 13.14 123.29Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 incl testing & disinfect

complete (32mm dia)

24-30-a-04 1 Rft m 54.99 57.36 17.48 180.43Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 including testing & disinfect

complete (40mm dia)

24-30-a-05 1 Rft m 65.74 57.36 17.48 215.68Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 including testing & disinfect

complete (50mm dia)

Page 137 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 138: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-30-a-06 1 Rft m 156.19 57.36 17.48 512.44Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 incl testing & disinfect

complete (75mm dia)

24-30-a-07 1 Rft m 250.31 64.54 19.67 821.22Providing and Laying HDPE pipe

Din-8074/Din-8075/ISO-4427 including testing & disinfect

complete (110mm dia)

24-30-b-01 Each Each 46.51 34.41 34.41 46.51Providing and installing HDPE Socket 20mm dia

24-30-b-02 Each Each 47.72 34.41 34.41 47.72Providing and installing HDPE Socket 25mm dia

24-30-b-03 Each Each 50.14 34.41 34.41 50.14Providing and installing HDPE Socket 32mm dia

24-30-b-04 Each Each 81.93 48.05 48.05 81.93Providing and installing HDPE Socket 40mm dia

24-30-b-05 Each Each 285.46 255.21 255.21 285.46Providing and installing HDPE Socket 50mm dia

24-30-b-06 Each Each 146.98 50.18 50.18 146.98Providing and installing HDPE Socket 75mm dia

24-30-b-07 Each Each 192.69 71.69 71.69 192.69Providing and installing HDPE Socket 110mm dia

24-30-c-01 Each Each 135.27 114.70 114.70 135.27Providing and installing HDPE Tee 20mm dia

24-30-c-02 Each Each 144.95 114.70 114.70 144.95Providing and installing HDPE Tee 25mm dia

24-30-c-03 Each Each 158.26 114.70 114.70 158.26Providing and installing HDPE Tee 32mm dia

24-30-c-04 Each Each 215.98 143.38 143.38 215.98Providing and installing HDPE Tee 40mm dia

24-30-c-05 Each Each 297.05 143.38 143.38 297.05Providing and installing HDPE Tee 50mm dia

24-30-c-06 Each Each 2,494.04 172.05 172.05 2,494.04Providing and installing HDPE Tee 75mm dia

24-30-c-07 Each Each 5,250.90 229.40 229.40 5,250.90Providing and installing HDPE Tee 110mm dia

24-30-d-01 Each Each 95.81 77.65 77.65 95.81Providing and installing HDPE bend 20mm dia

24-30-d-02 Each Each 101.86 77.65 77.65 101.86Providing and installing HDPE bend 25mm dia

24-30-d-03 Each Each 113.96 77.65 77.65 113.96Providing and installing HDPE bend 32mm dia

24-30-d-04 Each Each 153.85 98.19 98.19 153.85Providing and installing HDPE bend 40mm dia

24-30-d-05 Each Each 170.79 98.19 98.19 170.79Providing and installing HDPE bend 50mm dia

24-30-d-06 Each Each 422.13 107.53 107.53 422.13Providing and installing HDPE bend 75mm dia

24-30-d-07 Each Each 415.63 143.38 143.38 415.63Providing and installing HDPE bend 110mm dia

24-30-e-01 Each Each 100.64 40.15 40.15 100.64Providing and installing HDPE adaptor 20mm

24-30-e-02 Each Each 136.95 40.15 40.15 136.95Providing and installing HDPE adaptor 25mm

24-30-e-03 Each Each 167.20 40.15 40.15 167.20Providing and installing HDPE adaptor 32mm

24-30-e-04 Each Each 314.25 48.05 48.05 314.25Providing and installing HDPE adaptor 40mm

24-30-e-05 Each Each 392.90 48.05 48.05 392.90Providing and installing HDPE adaptor 50mm

24-30-e-06 Each Each 957.68 50.18 50.18 957.68Providing and installing HDPE adaptor 75mm

24-30-e-07 Each Each 1,959.29 71.69 71.69 1,959.29Providing and installing HDPE adaptor 110mm

24-31-a 1 Rft m 3,101.09 2,065.13 629.45 10,174.19S/H/J G.I. Flanged Pipe 18" i/d 6.35mm thick

24-31-b 1 Rft m 3,732.12 787.60 240.06 12,244.49S/H/J G.I. Flanged Pipe 16" i/d 6.35mm thick

24-31-c 1 Rft m 2,934.38 1,032.56 314.73 9,627.22S/H/J G.I. Flanged Pipe 12" i/d 6.35mm thick

24-31-d 1 Rft m 2,264.82 860.47 262.27 7,430.52S/H/J G.I. Flanged Pipe 10" i/d 6.35mm thick

24-31-e 1 Rft m 1,884.46 688.38 209.82 6,182.60S/H/J G.I. Flanged Pipe 8" i/d 5mm thick

Page 138 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 139: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-31-f 1 Rft m 980.16 516.28 157.36 3,215.76S/H/J G.I. Flanged Pipe 6" i/d 5mm thick

24-31-g 1 Rft m 556.24 344.19 104.91 1,824.93S/H/J G.I. Flanged Pipe 4" i/d 5mm thick

24-32-a 1 Rft m 3,472.10 1,720.94 524.54 11,391.41S/H/J MS Flanged Pipe 18" i/d 6.35mm thick

24-32-b 1 Rft m 2,969.35 1,147.29 349.70 9,741.95S/H/J MS Flanged Pipe 16" i/d 6.35mm thick

24-32-c 1 Rft m 2,227.31 860.47 262.27 7,307.45S/H/J MS Flanged Pipe 12" i/d 6.35mm

24-32-d 1 Rft m 1,734.42 688.38 209.82 5,690.34S/H/J MS Flanged Pipe 10" i/d 6.35mm thick

24-32-e 1 Rft m 1,404.21 573.65 174.85 4,606.98S/H/J MS Flanged Pipe 8" i/d 5mm thick

24-32-f 1 Rft m 902.18 458.92 139.88 2,959.90S/H/J MS Flanged Pipe 6" i/d 5mm thick

24-32-g 1 Rft m 516.97 286.82 87.42 1,696.11 S/H/J MS Flanged Pipe 4" i/d 5mm thick

24-33 1 Sft m2 491.41 443.30 41.20 5,287.54Supplying and Fixing MS manhole cover of 0.25" thick

sheet & angle iron frame 2"x2"x0.25" with lock complete

24-34 1 Rft m 520.62 78.14 23.82 1,708.06Supplying and Fixing flat iron (2"x3/8") ladder for OHR,

holes @ 15" c/c, steps of MS bars 5/8" i/d & paint compl

24-35 1 Rft m 46.02 5.74 1.75 150.97Supplying and Fixing C.I. vent pipe for storage tanks

including jally etc

24-36-a Each Each 858.78 11.78 11.78 858.78Supplying and Fixing MS cap of 3/16" thick sheet : 10" i/d

24-36-b Each Each 798.28 11.78 11.78 798.28Supplying and Fixing MS Cap of 3/16" thick sheet : 8" i/d

24-36-c Each Each 737.78 11.78 11.78 737.78Supplying and Fixing MS Cap of 3/16" thick sheet : 6" i/d

24-38-a Each Each 76,558.00 16,058.00 16,058.00 76,558.00Supplying and Fixing Flanged Expansion Joints BSS

2035: 18" i/d

24-38-b Each Each 59,870.00 11,470.00 11,470.00 59,870.00Supplying and Fixing Flanged Expansion Joint BS-2035 :

16" i/d

24-38-c Each Each 29,259.20 5,059.20 5,059.20 29,259.20Supplying and Fixing Flanged Expansion Joint BS-2035 :

12" i/d

24-38-d Each Each 18,190.40 3,670.40 3,670.40 18,190.40Supplying and Fixing Flanged Expansion Joint BSS-2035

: 10" i/d

24-38-e Each Each 13,388.20 2,982.20 2,982.20 13,388.20Supplying and Fixing Flanged Expansion Joint BSS 2035

: 8" i/d

24-38-f Each Each 8,865.80 1,605.80 1,605.80 8,865.80Supplying and Fixing Flanged Expansion Joints BSS 2035

: 6" i/d

24-38-g Each Each 6,821.40 1,376.40 1,376.40 6,821.40Supplying and Fixing Flanged Expansion Joint BSS-2035

: 4" i/d

24-39-a Each Each 2,828.40 1,376.40 1,376.40 2,828.40Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 18" i/d

24-39-b Each Each 1,825.10 917.60 917.60 1,825.10Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 16" i/d

24-39-c Each Each 1,057.50 573.50 573.50 1,057.50Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 12" i/d

24-39-d Each Each 707.10 344.10 344.10 707.10Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 10" i/d

Page 139 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 140: Rate nwfp 2008

Item Code Description

TUBEWELL AND WATER SUPPLYChapter #

:

24

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

24-39-e Each Each 471.40 229.40 229.40 471.40Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 8" i/d

24-39-f Each Each 353.55 172.05 172.05 353.55Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 6" i/d

24-39-g Each Each 296.20 114.70 114.70 296.20Supplying and Fixing MS Suspension Clamp 3/8" thick

for housing pipe : 4" i/d

24-40 1 Rft m 191.45 22.95 6.99 628.10Supplying and Fixing PVC Water Stopper 8" wide 3/8"

thick

24-41 No no 30,342.50 697.50 697.50 30,342.50Conducting Elec: Resistivity survey of the area and

furnishing its reports.

24-42 Job job 12,937.00 837.00 837.00 12,937.00Logging of bore hole with electrical equipment and

furnishing reports.

24-43 1 Rft m 137.01 125.18 38.15 449.51Providing and lowering pezu meter 1.25" GI pipe including

all accessories.

24-44 1 Rft m 1,538.72 1,054.27 321.34 5,048.29P&L Reflux valves (C.I) of BSS quality/weight including

jointing material 3" i/d-6" i/d.

24-45-a No joint 996.35 125.15 125.15 996.35Laying cut, joint, test & disinfect of 8"i/d of GI pipe line

including cost of welding, excavation and filling

compaction etc complete.

24-45-b joint joint 803.96 125.15 125.15 803.96Laying cut, joint, test & disinfect of 6"i/d of GI pipe line

including cost of welding, excavation and filling

compaction etc complete.

24-45-c joint joint 611.57 125.15 125.15 611.57Laying cut, joint, test & disinfect of 4"i/d of GI pipe line

including cost of welding, excavation and filling

compaction etc complete.

24-45-d Joint joint 420.39 125.15 125.15 420.39Laying cut, joint, test & disinfect of 3"i/d of GI pipe line

including cost of welding, excavation and filling

compaction etc complete.

24-46 1 Rft m 5,504.88 1,116.29 340.24 18,060.62Testing of soil for bearing capacity & chemical contents

upto any depth.

Page 140 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 141: Rate nwfp 2008

Item Code Description

IRON WORKChapter #

:

25

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

25-01 1 RFT m 8.58 28.15 8.58 28.15Laying, linking and packing tramway line

25-02 1 RFT m 2.84 9.32 2.84 9.32Dismantling tramway track

25-03 1 RFT m 22.95 75.29 22.95 75.29Laying, linking of BG track, including packing,

straightening and levelling

25-04 Each Each 2,247.50 2,247.50 2,247.50 2,247.50Linking points and crossings, complete with fastenings

25-05 Each Each 286.75 286.75 286.75 286.75Bending or straightening BG rail with jim crow

25-06 Each Each 837.00 837.00 837.00 837.00Fixing street lamp posts

25-07 Each Each 32.40 32.40 32.40 32.40Binding ends of sleepers and timbers of all sizes & kinds,

including spreading & restacking

25-08 Each Each 3.46 3.46 3.46 3.46Opening stacks of sleepers & timber of all kinds and sizes,

including spreading for inspection

25-09 tonne tonne 116,572.00 27,032.00 27,032.00 116,572.00Small iron work, such as gusset plates, knees, bends,

stirrups, straps, rings etc excluding erection

25-10 tonne tonne 107,520.00 17,980.00 17,980.00 107,520.00Fabrication of heavy steel work with angle, tees, sheet iron

etc for making trusses, girders etc

25-11 tonne tonne 4,920.48 4,920.48 4,920.48 4,920.48Erection and fitting in position iron trusses, staging of

water tanks, etc

25-12 1 SFT m2 6.92 74.41 6.92 74.41Fixing corrugated iron sheet including rivetting, etc

25-13 tonne tonne 6,125.60 6,125.60 6,125.60 6,125.60Erecting corrugated iron sheet tanks, upto 20' height

25-14 tonne tonne 347.20 347.20 347.20 347.20Erecting rolled steel beams or old rails, in roof etc, erection

& fixing in position

25-15 tonne tonne 174.22 174.22 174.22 174.22Erecting rolled steel beams or rails, erection for posts etc

(other than in roofs)

25-16 kg kg 128.10 61.85 61.85 128.10Making bolts & nuts of iron rods

25-17-a Each cut Each cut 129.16 129.16 129.16 129.16Cutting rails,rolled steel joist & beams, with hacksaw :

Upto 6" size

25-17-b Each cut Each cut 193.75 193.75 193.75 193.75Cutting rails,rolled steel joist & beams, with hacksaw :

Above 6" size

25-18 Each cut Each cut 64.58 64.58 64.58 64.58Cutting rails or rolled steel beams of size below 6" with jim

25-19 Per Bend Per Bend 240.36 110.72 110.72 240.36Bending rolled steel beams or rails

25-20 Each hole Each hole 26.86 26.86 26.86 26.86Drilling holes,in plates upto 1/2" thick per inch dia. or part

thereof

25-21 Each hole Each hole 12.40 12.40 12.40 12.40Extra for drilling holes in plates over 1/2" thick per inch

dia, or part thereof

25-22 Each Each 3.88 3.88 3.88 3.88Rivetting 1/8" dia

25-23 Each Each 11.19 11.19 11.19 11.19Cutting out Rivets, all sizes.

25-24 1 RFT m 19.38 63.59 19.38 63.59Fitting and erection of gutters of sheet iron

25-25 Each Each 27.38 27.38 27.38 27.38Cutting and fixing iron bars, for barred windows

25-26 Each Each 13.43 13.43 13.43 13.43Cutting GI sheets of 2'-8" wide.

25-27 Each cut Each cut 304.71 299.66 299.66 304.71Notching web or foot of rail posts for housing rail beams

25-28 1 SFT m2 26.45 268.80 24.98 284.62Hoop iron netted trellis work fixed with nails

Page 141 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 142: Rate nwfp 2008

Item Code Description

IRON WORKChapter #

:

25

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

25-29 1 SFT m2 12.13 124.58 11.58 130.48Fixing zinc, iron or GI sheet on table tops

25-30 1 SFT m2 429.92 2,356.00 218.96 4,625.90Making and fixing steel grated doors, complete with

locking arrangements & angle iron frame

25-31 1 SFT m2 582.74 2,314.15 215.07 6,270.26Making and fixing steel grated door, with 1/16" thick

sheeting, including angle iron frame & lock

25-32 1 SFT m2 134.40 633.82 58.91 1,446.19Making and fixing grating in opening, including fixing at

site with flat iron 2"x3/8" and 3/4" sq. bars

25-33 1 SFT m2 224.57 426.68 39.65 2,416.38Providing and Fixing terrace railing of 2" i/d conduit pipe

16 SWG welded with 5/8"x5/8" sq bar 2.75' high complete

25-34 1 SFT m2 476.62 1,453.56 135.09 5,128.39Providing and Fixing collapsible gate made of 2"x2"x1/4"

tee iron at top & bottom, lock etc complete

25-35 1 SFT m2 138.22 181.86 16.90 1,487.19Providing and Fixing 24 SWG GI sheet rolling shutter of

steel frame of MS channel 2"x1.25"x1/8" complete

25-36 1 RFT m 164.63 61.80 18.84 540.11Providing and Fixing MS angle iron 1«"x1«"x1/4" edge

protector nozing of steps of stairs, complete

25-37 1 RFT m 343.45 220.77 67.29 1,126.80Providing and Fixing stair railing of 2.5" i/d GI pipe,

welded with 5/8"x5/8" MS bars 2'-9" high, fixed in each

step

25-38 1 SFT m2 124.39 505.20 46.95 1,338.48Providing and Fixing GI wire gauze 24 SWG, 12x12

meshes per sq.in., fixed to steel windows or doors etc

25-39-a-01 1 SFT m2 336.65 156.83 14.58 3,622.39Providing and Fixing steel windows with openable glazed

panels Without wire guaze : Glass pane 2mm thick

25-39-a-02 1 SFT m2 340.28 156.83 14.58 3,661.45Providing and Fixing steel windows with openable glazed

panels Without wire gauze : Glass pane 2.5mm thick

25-39-a-03 1 SFT m2 334.23 156.83 14.58 3,596.35Providing and Fixing steel windows with openable glazed

panels Without wire gauze : Glass pane 3mm thick

25-39-a-04 1 SFT m2 346.33 156.83 14.58 3,726.54Providing and Fixing steel windows with openable glazed

panels Without wire gauze : Glass pane 4mm thick

25-39-a-05 1 SFT m2 348.75 156.83 14.58 3,752.58Providing and Fixing steel windows with openable glazed

panels Without wire gauze : Glass pane 5mm thick

25-39-b-01 1 SFT m2 401.12 172.68 16.05 4,316.04Providing and Fixing steel windows with openable glazed

panels With 22 SWG wire gauze : Glass pane 2mm

25-39-b-02 1 SFT m2 404.75 172.68 16.05 4,355.09Providing and Fixing steel windows with openable glazed

panels With 22 SWG wire gauze : Glass pane 2.5mm

25-39-b-03 1 SFT m2 398.70 172.68 16.05 4,290.00Providing and Fixing steel windows with openable glazed

panels With 22 SWG wire gauze : Glass pane 3mm

25-39-b-04 1 SFT m2 410.80 172.68 16.05 4,420.19Providing and Fixing steel windows with openable glazed

panels With 22 SWG wire gauze : Glass pane 4mm

25-39-b-05 1 SFT m2 413.22 172.68 16.05 4,446.23Providing and Fixing steel windows with openable glazed

panels With 22 SWG wire gauze : Glass pane 5mm

25-40 1 SFT m2 531.38 2,836.31 263.60 5,717.64Supply and Fixing iron grating for fire place

Page 142 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 143: Rate nwfp 2008

Item Code Description

IRON WORKChapter #

:

25

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

25-41 1 RFT m 839.85 503.65 153.51 2,755.42Providing and Fixing angle iron railing, using

2.5"x2.5"x3/8" angle iron post 4.5'long, 5'to 6" apart,

complete

25-42 1 RFT m 100.26 97.21 29.63 328.92Providing and Fixing barbed wire fencing of

1.5"x1.5"x3/16" angle iron post 3.25' long, 5 to 6 ft. centre

to centre

25-43 1 RFT m 114.20 104.34 31.80 374.66Providing and Fixing barbed wire fencing on compound

wall of 1.5"x1.5"x3/16" angle iron post 3' long, 4' apart

25-46 1 SFT m2 531.89 620.20 57.64 5,723.09Supplying and Fixing 18SWG Steel Almirah, 12" max

depth including box shelves, back, shelves, lock, spray

paint complete

25-47-a 1 SFT m2 354.72 693.90 64.49 3,816.81Supplying and Fixing 18 SWG MS Sheet Door with angle

iron frame (1.5"x1.5"x1/8"), bolt, hinges, paint etc

complete

25-47-b 1 SFT m2 499.81 1,074.77 99.89 5,378.00Supplying and Fixing 18 SWG MS Sheet Gate with angle

iron frame (2"x2"x3/16") with side window, lock, painting

etc

Page 143 of 144NWFP CSR 2008 - Approved 25-Aug-2008

Page 144: Rate nwfp 2008

Item Code Description

MISCELLANEOUSChapter #

:

26

Rate (British System) Rate (Metric System)

Unit Unit Composite Composite

COMPOSITE SCHEDULE OF RATES 2008 NWFP

LabourLabour

RemarksSpec.

No

26-01 Each Each 327.75 43.40 43.40 327.75Supplying bamboo jhandies 10' to 12' with iron shoes and

flags 15" square

26-02 100 No. 100 No 654.03 182.13 182.13 654.03Supplying wooden pegs for levelling 1.5" square 6" long

26-03 100 No. 100 No 1,590.45 658.75 658.75 1,590.45Supplying wooden pegs for alignment, 2" to 3" square, 9"

long

26-04 Each Each 1,013.20 868.00 868.00 1,013.20Fixing enamelled iron gauges flush with masonry including

cost of hooks

26-05 Each Each 427.07 139.50 139.50 427.07Supply & fix boundry pillars in position, including digging

pits

26-06 Each Each 317.85 83.70 83.70 317.85Composite rate does

not include cost of

iron distance marks.

Fixing main line type distance mark in position including

making 1:3:6 cement concrete base block

26-07-a 1 RFT m 44.89 147.29 44.89 147.29Boring and fixing 1.5" dia pressure pipe in ordinary soil

26-07-b 1 RFT m 83.17 272.87 83.17 272.87Boring and fixing 1.5 dia pressure pipe in clay

26-07-c 1 RFT m 121.45 398.45 121.45 398.45Boring and fixing 1.5" dia pressure pipe in shingle

26-08 1 RFT m 32.80 107.60 32.80 107.60Repairs to hand pump, pulling out & refitting

26-09 Each Each 198.40 198.40 198.40 198.40Fixing hand pump (machine only)

26-10-a 100 SFT m2 1,080.56 116.27 1,080.56 116.27Capacity of cart, 20

cubic feet

Washing of Durries / Synthetic Matting

26-10-b Each Each 23.34 23.34 23.34 23.34Washing of Bed Sheets

26-10-c Each Each 11.66 11.66 11.66 11.66Washing of Table Cloth / Napkins / Dusters etc

26-11-a kg kg 287.55 69.75 69.75 287.55Recaning of chairs/stools : With plastic cane.

26-11-b kg kg 1,307.65 97.65 97.65 1,307.65Recaning of chairs/stools : With willow cane.

26-12 Each Each 109.44 69.75 69.75 109.44Sweeping chimneys

26-13 Each Each 70.31 70.31 70.31 70.31For capacity other

than 400 gallons, the

rate shall be work out

on proper rate basis.

Cleaning of water tanks upto 400 gallons capacity

26-14 Cart load Cart load 325.25 111.60 111.60 325.25Capacity of cart, 20

cubic feet

Supplying manure

26-15 100

Sft/spray

m2 122.26 0.83 7.75 13.16Spraying anti-termite liquid mixed with water in the ratio

of 1:40

26-16-a 1 RFT m 137.56 14.47 4.41 451.30Providing and Fixing barbed wire fencing with 4 horizontal

& 2 cross wires : Without PCC base

26-16-b 1 RFT m 139.50 14.47 4.41 457.67Providing and Fixing barbed wire fencing with 4 horizontal

& 2 cross wires : With PCC 1:4:8 base 12"x12"x21"

26-17 100 SFT m2 5,598.17 539.82 5,016.90 602.36Making notice board 1/2" thick of c/s mortar 1:3 with

2"x1/2" beading

26-18 Each Each 31.50 13.95 13.95 31.50Binding office books/registers.

Page 144 of 144NWFP CSR 2008 - Approved 25-Aug-2008