CHAPTER NO. 25 IRON WORK DESCRIPTION OF ITEM: 1 Laying, Linking & Packing Tram way line. Detail Unit of Rate 100 Rft. Rate Qty Per Unit Rate Analysis for 350 Rft LABOUR 1 Jamadar (Mate) 1.00 No. 85.00 2 Keyman (Skilled Cooly) 1.00 No. 160.00 3 Coolies (Unskilled) 7.00 Nos. 140.00 Total Sundries 10.00 Percent Total Contractor's Profit & Ove 20.00 Percent Total ITEM RATE Labour Rate Per 100 Lft. Rs. 462.00 Say Labour Rate Per R M Rs. 15.15 Say
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1
CHAPTER NO. 25
IRON WORK
DESCRIPTION OF ITEM:
1 Laying, Linking & Packing
Tram way line.
Detail Unit of Rate 100 Rft.
Rate
Qty Per Unit Amount
Rate Analysis for 350 Rft
LABOUR
1 Jamadar (Mate) 1.00 No. 85.00 85.00
2 Keyman (Skilled Cooly) 1.00 No. 160.00 160.00
3 Coolies (Unskilled) 7.00 Nos. 140.00 980.00
Total 1225.00
Sundries 10.00 Percent 122.50
Total 1347.50
Contractor's Profit & Overh 20.00 Percent 269.50
Total 1617.00
ITEM RATE
Labour Rate Per 100 Lft. Rs. 462.00 Say 462.00
Labour Rate Per R M Rs. 15.15 Say 15.15
Page 2
2. Dismantling Tramway track.
Detail Unit of Rate 100 Rft.
Rate
Qty Per Unit Amount
Rate Analysis for 1400 Rft.
LABOUR
1 Jamadar (Mate) 1.0 No. 85.00 85.00
2 Skilled Cooly 1.0 No. 160.00 160.00
3 Coolies (Unskilled) 10.0 Nos. 140.00 1400.00
Total 1645.00
Sundries 10.00 Percent 164.50
Total 1809.50
Contractor's Profit & Overh 20.00 Percent 361.90
Total 2171.40
ITEM RATE
Labour Rate Per 100 Lft. Rs. 155.10 Say 155.10
Labour Rate per RM Rs. 5.09 Say 5.10
Page 3
3. Laying, Linking of B.G Track including packing, straightening and levelling.
Detail Unit = 100 Rft
Rate
Qty Per Unit Amount
Rate Analysis per 120 Rft.
LABOUR
1 Jamadar (Mate) 1.0 No. 85.00 85.00
2 Keyman (Skilled Cooly) 1.0 No. 160.00 160.00
3 Coolies (Unskilled) 6.0 Nos. 140.00 840.00
Total 1085.00
Sundries 10.00 Percent 108.50
Total 1193.50
Contractor's Profit & Overh 20.00 Percent 238.70
Total 1432.20
ITEM RATE
Labour Rate Per 100 Lft. Rs. 1,193.50 Say 1193.50
Labour Rate per RM Rs. 39.15 Say 39.15
Page 4
4. Linking points and crossings complete with fastenings.
Detail Unit = Each
Rate
Qty Per Unit Amount
LABOUR
1 Jamadar (Mate) 0.5 No. 85.00 42.50
2 Keyman (Skilled Cooly) 0.5 No. 160.00 80.00
3 Coolies (Unskilled) 5.5 Nos. 140.00 770.00
Total 892.50
Sundries 10.00 Percent 89.25
Total 981.75
Contractor's Profit & Overh 20.00 Percent 196.35
Total Say 1178.10
ITEM RATE
Labour Rate Per Each Rs. 1,178.10 Say 1178.10
Page 5
5. Bending or straightening B.G. rail with Jim crow
Detail Unit Rate Per Each Point
Rate
Qty Per Unit Amount
LABOUR
1 Black Smith 0.20 No. 170.00 per day 34.00
2 Coolies (Unskilled) 0.50 No. 140.00 per day 70.00
Total 104.00
Sundries 10.00 Percent 10.40
Total 114.40
Contractor's Profit & Overh 20.00 Percent 22.88
Total Say 137.28
ITEM RATE
Labour Rate Per Each Point Rs. 137.28 Say 137.30
Page 6
6. Fixing street lamp post.
Detail Unit Rate Per Each
Rate
Qty Per Unit Amount
LABOUR
1 Coolies (Unskilled) 0.85 No. 140.00 per day 119.00
Total 119.00
Sundries 10.00 Percent 11.90
Total 130.90
Contractor's Profit & Overh 20.00 Percent 26.18
Total 157.08
ITEM RATE
Labour Rate Per/Each Rs. 157.08 Say 157.10
Page 7
7. Binding ends of sleepers and timbers of all sizes and kinds including spreading and
restacking.
Detail Unit Rate Per 100 Nos.
Rate
Qty Per Unit Amount
LABOUR
1 Fitter 1.5 No. 170.00 per day 255.00
2 Mate 0.5 No. 85.00 per day 42.50
3 Coolies (unskilled) 5.75 No. 140.00 per day 805.00
Total 1102.50
Sundries 10.00 Percent 110.25
Total 1212.75
Contractor's Profit & Overh 20.00 Percent 242.55
Total 1455.30
ITEM RATE
Labour Rate Per 100 Nos. Rs. 1,455.30 Say 1455.30
Page 8
8. Opening stacks of sleepers and Timbers of all kinds and sizes including spreading for
inspection and restacking within chain lead.
Detail Unit Rate Per 100 Nos.
Rate
Qty Per Unit Amount
Rate Analysis for 1500 Nos.
LABOUR
1 Mate 1.0 No. 85.00 per day 85.00
2 Coolies (unskilled) 14.0 Nos. 140.00 per day 1960.00
Total 2045.00
Sundries 10.00 Percent 204.50
Total 2249.50
Contractor's Profit & Overh 20.00 Percent 449.90
Total 2699.40
Say 2699.40
ITEM RATE
Labour Rate Per 100 Nos. Rs. 179.96 Say 179.95
Page 9
9. Small Iron work such as gusset plates, knees, bends, strips, straps, rings etc. including
cutting, drilling, revitting, bending assembling & fixing but excluding erection in position.
Detail Unit = 1 Cwt.
Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL
1 Iron = 1.0 Cwt. 55.90 Kg 24.00 per Kg 1341.60
wastage 10% = 0.1 Cwt.
1.10 Cwt. or 55.90
2 Char Coal 8.40 Kg 4.00 per Kg 33.60
3 Steel Revits 0.68 Kg 35.01 per Kg 23.81
Total 1399.01
Contractor's Profit & Overh 20.00 Percent 279.80
Total 1678.81
LABOUR
Black Smith 1.50 Nos. 170.00 per day 255.00
Coolies (Unskilled) 2.50 Nos. 140.00 per day 350.00
Total 605.00
Sundries 10.00 Percent 60.50
Total 665.50
Contractor's Profit & Overh 20.00 Percent 133.10
Total 798.60
Say 535.40
ITEM RATE
Labour Rate for 1 Cwt. Rs. 535.40 Say 535.40
Composite Rate for 1 Cwt. Rs. 2214.21 Say 2214.20
Labour Rate/100 Kgs. Rs. 1053.94 Say 1053.95
Composite Rate/100 Kgs. Rs. 4358.68 Say 4358.70
Page 10
10. Fabrication of heavy steel work, with angle, tees, flat iron, round iron and sheet iron for
making trusses, girders, tanks etc. including cutting, drilling, revitting handling,
assembling and fixing but excluding erection in position.
Detail Unit = 1 Cwt.
Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL
1 Iron = 1.00 Cwt
wastage 5% = 0.05 Cwt 53.36 Kg 88.00 Per Kg. 4695.68
1.05 Cwt. or (53.36 Kg.)
2 Char Coal 7.46 Kg 6.00 Per Kg. 44.76
3 Steel Revits 0.45 Kg 90.00 Per Kg. 40.50
Total 4780.94
Contractor's Profit & Overh 25.00 Percent 1195.24
Total 5976.18
LABOUR
1 Black Smith 0.5 No. 275.00 per day 137.50
2 Hammer man 0.9 No. 125.00 per day 112.50
Total 250.00
Sundries 10.00 Percent 25.00
Total 275.00
Contractor's Profit & Overh 25.00 Percent 68.75
Total 343.75
ITEM RATE
Labour Rate/Cwt Rs. 343.75 Say 343.75
Composite Rate/One Cwt. Rs. 6319.93 Say 6319.95
Labour Rate/100 Kg. Rs. 676.67 Say 676.65
Composite Rate/100 Kg Rs. 12440.80 Say 12440.80
Page 11
11. Erection and fitting in position of iron trusses, staging of water tanks.
Detail Unit = 100 Kg
Rate
Qty Per Unit Amount
Rate Analysis for 9.00 Cwt.
LABOUR
1 Fitter 2.0 No. 170.00 per day 340.00
2 Coolies (unskilled) 2.0 No. 140.00 per day 280.00
Total 620.00
Sundries 10.00 Percent 62.00
Total 682.00
Contractor's Profit & Overh 20.00 Percent 136.40
Total 818.40
Rate/Cwt 818.40 = Rs. 65.88
9
ITEM RATE
Labour Rate / Cwt. Rs. 90.93 Say 90.95
Labour Rate 100 Kg Rs. 179.00 Say 179.00
Page 12
12. Fixing corrugated iron sheet including revitting.
Detail Unit Rate Per 100 Sft.
Rate
Qty Per Unit Amount
Rate Analysis for 125 Sft.
LABOUR
1 Black smith 1.0 No. 170.00 Per day 170.00
2 Coolies (unskilled) 1.0 No. 140.00 Per day 140.00
Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20.00 Percent 68.20
Total 409.20
ITEM RATE
Labour Rate 100 Sft. Rs. 327.36 Say 327.35
Labour Rate/Sq.m Rs. 35.22 Say 35.20
Page 13
13. Erecting corrugated iron sheet tanks upto 20 ft. height.
Detail Unit = 100 Kg
Rate
Qty Per Unit Amount
Rate Analysis for 14.25 Cwt.
LABOUR
1 Black smith 2.0 Nos. 170.00 Per day 340.00
2 Coolies (unskilled) 9.5 Nos. 140.00 Per day 1330.00
Total 1670.00
Sundries 10.00 Percent 167.00
Total 1837.00
Contractor's Profit & Overh 20.00 Percent 367.40
Total 2204.40
Rate / Cwt. 2204.40 = Rs. 154.69
14.25
ITEM RATE
Labour Rate/ One Cwt Rs. 154.69 Say 154.70
Labour Rate / 100 Kg. Rs. 304.52 Say 304.50
Page 14
14. Erecting rolled steel beams on old rails in roofs etc., erection and fixing in position.
Detail Unit 100 Kg.
Rate
Qty Per Unit Amount
Rate Analysis for 30 Cwt.
LABOUR
1 Black smith 0.5 No. 170.00 Per day 85.00
2 Coolies (unskilled) 14.5 Nos. 140.00 Per day 2030.00
Total 2115.00
Sundries 10.00 Percent 211.50
Total 2326.50
Contractor's Profit & Overh 20.00 Percent 465.30
Total 2791.80
ITEM RATE
Labour Rate /Cwt. Rs. 93.06 Say 93.05
Labour Rate / 100 Kg. Rs. 183.19 Say 183.20
Page 15
15. Erecting rolled steel beams or rails, erection for posts etc. (other than in roofs).
Detail Unit 100 Kg.
Rate
Qty Per Unit Amount
Rate Analysis for 30 Cwt.
LABOUR
1 Black smith 0.5 No. 170.00 Per day 85.00
2 Coolies (unskilled) 6.75 Nos. 140.00 Per day 945.00
Total 1030.00
Sundries 10.00 Percent 103.00
Total 1133.00
Contractor's Profit & Overh 20.00 Percent 226.60
Total 1359.60
Rate/Cwt. 1359.61 = Rs. 45.32
30
ITEM RATE
Labour Rate /Cwt. Rs. 45.32 Say 45.30
Labour Rate / 100 Kg. Rs. 89.21 Say 89.20
Page 16
16. Making bolts and nuts of iron rods.
Detail Unit 100 Kg.
Rate
Qty Per Unit Amount
Rate Analysis for 1 Cwt.
MATERIAL
1 Mild Steel 1 .0 Cwt. 55.90 Kg 18.00 Per Kg. 1006.20
wastage 10% 0.1 Cwt
1.1 Cwt. or (55.90 Kg)
2 Steel chisel 0.68 Kg 24.00 Per Kg. 16.32
3 Coal 46.51 Kg 12.00 Per Kg. 558.12
Total 1580.64
Contractor's Profit & Overh 20.00 Percent 316.13
Total 1896.77
LABOUR
1 Black Smith 1.5 Nos. 170.00 Per day 255.00
2 Hammer man 0.75 No. 75.00 Per day 56.25
3 Cooly (Unskilled) 0.75 No. 140.00 Per day 105.00
Total 416.25
Sundries 10.00 Percent 41.63
Total 457.88
Contractor's Profit & Overh 20.00 Percent 91.58
Total 549.45
ITEM RATE
Labour Rate/ Cwt. Rs. 549.45 Say 549.45
Composite Rate/Cwt Rs. 2446.22 Say 2446.20
Labour Rate/100 Kg. Rs. 1081.59 Say 1081.60
Composite Rate/100 Kg. Rs. 4815.39 Say 4815.40
Page 17
17. Cutting rails, rolled steel joists and beams with hack saw:-
a) upto 6" size.
Detail Unit per cut
Rate
Qty Per Unit Amount
Rate Analysis for 1 Cut.
LABOUR
1 Fitter 0.15 No. 170.00 Per day 25.50
2 Coolies (unskilled) 0.15 No. 140.00 Per day 21.00
Total 46.50
Sundries 10.00 Percent 4.65
Total 51.15
Contractor's Profit & Overh 20.00 Percent 10.23
Total 61.38
ITEM RATE
Labour Rate per Cut Rs. 61.38 Say 61.40
Page 18
17. b) Above 6" size.
Detail Unit per Cut
Rate
Qty Per Unit Amount
Rate Analysis for 5 Cuts.
LABOUR
1 Fitter 1.20 Nos. 170.00 Per day 204.00
2 Coolies (unskilled) 1 No. 140.00 Per day 140.00
Total 344.00
Sundries 10.00 Percent 34.40
Total 378.40
Contractor's Profit & Overh 20.00 Percent 75.68
Total 454.08
ITEM RATE
Labour Rate per Cut. Rs. 90.82 Say 90.80
Page 19
18. Cutting rails or rolled steel beams of size below 6" with Jim.
Detail Unit per Cut
Rate
Qty Per Unit Amount
Rate Analysis for 14 Cuts
LABOUR
1 Fitter 1.00 No. 170.00 Per day 170.00
2 Coolies (unskilled) 1.00 No. 140.00 Per day 140.00
Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20.00 Percent 68.20
Total 409.20
ITEM RATE
Labour Rate per Cut. Rs. 29.23 Say 29.25
Page 20
19. Bending rolled steel beams on rails.
Detail Unit / Bend
Rate
Qty Per Unit Amount
Rate Analysis for 10 Bends
MATERIAL
1 Steam coal 139.95 Kg 12.00 Per Kg 1679.40
Total 1679.40
Contractor's Profit & Overh 20.00 Percent 335.88
Total 2015.28
LABOUR
1 Black Smith 0.75 No. 170.00 Per day 127.50
2 Hammer man 0.75 No. 75.00 Per day 56.25
Total 183.75
Sundries 10.00 Percent 18.38
Total 202.13
Contractor's Profit & Overh 20.00 Percent 40.43
Total 242.55
ITEM RATE
Labour Rate Per Bend Rs. 24.26 Say 24.25
Composite Rate/Bend Rs. 225.78 Say 225.80
Page 21
20. Drilling holes in plates upto 1/2" thick per inch dia or part thereof.
Detail Unit Rate per Hole
Rate
Qty Per Unit Amount
Rate Analysis for 40 holes
LABOUR
1 Fitter (Grade I) 0.50 No. 170.00 Per day 85.00
2 Coolies (unskilled) 2.00 No. 140.00 Per day 280.00
Total 365.00
Sundries 10.00 Percent 36.50
Total 401.50
Contractor's Profit & Overh 20.00 Percent 80.30
Total 481.80
ITEM RATE
Labour Rate per hole Rs. 12.05 Say 12.05
Page 22
21. Extra for drilling holes in plates over each 1/2" thick per inch dia or part thereof.
Detail Unit Rate Per Hole
Rate
Qty Per Unit Amount
Rate Analysis for 120 holes
LABOUR
1 Fitter (Grade I) 0.25 No. 170.00 Per day 42.50
2 Coolies (unskilled) 4.00 Nos. 140.00 Per day 560.00
Total 602.50
Sundries 10.00 Percent 60.25
Total 662.75
Contractor's Profit & Overh 20.00 Percent 132.55
Total 795.30
ITEM RATE
Labour Rate per hole Rs. 6.63 Say 6.65
Page 23
22. Riveting 1/8" dia
Detail Unit Rate Per 100 Nos.
Rate
Qty Per Unit Amount
Rate Analysis for 120 Nos.
LABOUR
1 Riveted 0.50 No. 85.00 Per day 42.50
2 Coolies (unskilled) 0.50 No. 140.00 Per day 70.00
Total 112.50
Sundries 10.00 Percent 11.25
Total 123.75
Contractor's Profit & Overh 20.00 Percent 24.75
Total 148.50
ITEM RATE
Labour Rate for 100 Nos. Rs. 123.75 Say 123.75
Page 24
23. Cutting out rivets, all sizes.
Detail Unit 100 Nos.
Rate
Qty Per Unit Amount
Rate Analysis for 160 Nos.
LABOUR
1 Fitter (Grade II) 2.00 Nos. 170.00 Per day 340.00
2 Hammer man 2.00 Nos. 75.00 Per day 150.00
Total 490.00
Sundries 10.00 Percent 49.00
Total 539.00
Contractor's Profit & Overh 20.00 Percent 107.80
Total 646.80
ITEM RATE
Labour Rate for 100 Nos. Rs. 404.25 Say 404.25
Page 25
24. Fitting and erection of gutters of sheet iron.
Detail Unit / Lft.
Rate
Qty Per Unit Amount
Rate Analysis for 115 Feet
LABOUR
1 Fitter (Grade II) 1.00 No. 170.00 Per day 170.00
2 Mason 1.00 No. 300.00 Per day 300.00
3 Coolies (Unskilled) 10.00 Nos. 140.00 Per day 1400.00
Total 1870.00
Sundries 10.00 Percent 187.00
Total 2057.00
Contractor's Profit & Overh 20.00 Percent 411.40
Total 2468.40
ITEM RATE
Labour Rate Per Lft. Rs. 21.46 Say 21.45
Labour Rate per RM Rs. 70.40 Say 70.40
Page 26
25. Cutting and fixing iron bars for barred windows
Detail Unit / Bar
Rate
Qty Per Unit Amount
Rate Analysis for 35 Bars
LABOUR
1 Fitter (Grade III) 0.50 No. 170.00 Per day 85.00
2 Carpenter 0.50 No. 300.00 Per day 150.00
3 Coolies (Unskilled) 1.00 No. 140.00 Per day 140.00
Total 375.00
Sundries 10.00 Percent 37.50
Total 412.50
Contractor's Profit & Overh 20.00 Percent 82.50
Total 495.00
ITEM RATE
Labour Rate Per Bar Rs. 14.14 Say 14.15
Page 27
26. Cutting GI sheets.
Detail Unit Rate Per Cut
Rate
Qty Per Unit Amount
Rate Analysis for 65 Cuts
LABOUR
1 Fitter (Grade II) 1.00 No. 170.00 Per day 170.00
2 Hammer man 1.00 No. 75.00 Per day 75.00
Total 245.00
Sundries 10.00 Percent 24.50
Total 269.50
Contractor's Profit & Overh 20.00 Percent 53.90
Total 323.40
ITEM RATE
Labour Rate per cut Rs. 4.98 Say 5.00
Page 28
27. Notching web or foot of rail posts for housing rail beams.
Detail Unit Rate Per Notch
Rate
Qty Per Unit Amount
Rate Analysis for 3 Notches
MATERIAL
1 Steam Coal 28.00 Kg 12.00 Per Kg 336.00
Total 336.00
Contractor's Profit & Overh 20.00 Percent 67.20
Total 403.20
LABOUR
1 Black Smith 1.0 Nos. 170.00 Per day 170.00
2 Hammer man 1.0 Nos. 75.00 Per day 75.00
Total 245.00
Sundries 10.00 Percent 24.50
Total 269.50
Contractor's Profit & Overh 20.00 Percent 53.90
Total 323.40
ITEM RATE
Labour Rate/Notch Rs. 107.80 Say 107.80
Composite Rate/Notch Rs. 242.20 Say 242.20
Page 29
28. Hoop Iron netted trellis work fixed with nails.
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount
Rate Analysis for 50 Sft.
LABOUR
1 Fitter (Grade - II) 1.00 No. 170.00 Per day 170.00
2 Coolies (Unskilled) 1.00 No. 140.00 Per day 140.00
Total 310.00
Sundries 10.00 Percent 31.00
Total 341.00
Contractor's Profit & Overh 20.00 Percent 68.20
Total 409.20
ITEM RATE
Labour Rate per Sft. Rs. 8.18 Say 8.20
Labour Rate per Sq.m Rs. 88.06 Say 88.05
Page 30
29. Fixing zinc Iron or GI Sheets on table tops.
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount
Rate Analysis for 85 Sft.
LABOUR
1 Carpenter 1.00 No. 300.00 Per day 300.00
2 Coolies (Unskilled) 1.00 No. 140.00 Per day 140.00
Total 440.00
Sundries 10.00 Percent 44.00
Total 484.00
Contractor's Profit & Overh 20.00 Percent 96.80
Total 580.80
ITEM RATE
Labour Rate per Sft. Rs. 6.83 Say 6.85
Labour Rate per Sq.m Rs. 73.52 Say 73.50
Page 31
30. Making and fixing steel grated doors, complete with locking arrangement, angle iron frame 2"x2"x3/8" and
3/4" square bars 4" center to center
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount
Rate Analysis for 7' x 4' = 28.00 Sft.
MATERIAL
a)
1 Angle Iron frame 2"x2"x3/8"
vertical 4x7 28 Rft
Top rail 2 x 4'-0" 8 Rft
Bottom & central rail 8 Rft.
44 Rft. @ 90.44 Kg.
2 Grating(¾"x¾") = 9x7'-0" = 63 Rft. @ 1.88 l 53.74 Kg.
3 Gusset Plate (¼" thick)
8x6"x3" 1.0 0 Sft.
4x8"x3" 0.67 Sft.
1.67 Sft@ 7.58 Kg.
Total 151.76
Wastage 7.59
Total 159.35 Kg. 24.00 Per Kg. 3824.40
b Hold fast with pivot and fixed 6.00 Nos. 8.00 Each 48.00
c Locking arrangement with sliding bolt 1½ long
and 1" dia 1.00 No. 55.00 Each 55.00
d Coal 15.00 Kg. 12.00 Per Kg. 180.00
e Rivets and bolts 2.27 Kg. 35.01 Per Kg. 79.47
f Steel 1.13 Kg. 18.00 Per Kg. 20.34
Total 4207.21
Contractor's Profit & Overh 20.00 Percent 841.44
Total 5048.66
LABOUR
1 Black Smith 2.0 Nos. 170.00 Per day 340.00
2 Hammer man 3.0 Nos. 75.00 Per day 225.00
3 Blowman 2.0 Nos. 75.00 Per day 150.00
Total 715.00
Sundries 10.00 Percent 71.50
Total 786.50
Contractor's Profit & Overh 20.00 Percent 157.30
Total 943.80
ITEM RATE
Labour Rate per Sft. Rs. 33.71 Say 33.70
Composite Rate per Sft. Rs. 214.02 Say 214.00
Labour Rate per Sq.m Rs. 362.69 Say 362.70
Composite Rate per Sq.m Rs. 2302.81 Say 2302.80
Page 32
31. Making and fixing steel grated door with 1/16" thick sheeting including angle iron frame
2"x2"x3/8" and 3/4" square bars 4" center to center with locking arrangement.
Detail Unit Rate Per Sft.
Rate
Qty Per Unit Amount
Rate Analysis for 7'x4' = 28 Sft.
MATERIAL
1 As per Item No. 30 (a) to (f) 4207.00
2 M.S. sheet 1/16" , 7x4= 28 Sft.
Wastage @ 5% 1.4 Sft
29.40 Sft 33.35 Kg. 29.00 Per Kg. 967.15
@ 2.50 lb/Sft.
Total 5174.15
Contractor's Profit & Overh 20.00 Percent 1034.83
Total 6208.98
LABOUR
1 Black Smith 2.25 Nos. 170.00 Per day 382.50
2 Hammer man 3.00 Nos. 75.00 Per day 225.00
3 Blowman 2.00 Nos. 75.00 Per day 150.00
Total 757.50
Sundries 10.00 Percent 75.75
Total 833.25
Contractor's Profit & Overh 20.00 Percent 166.65
Total 999.90
Say 952.90
ITEM RATE
Labour Rate/Sft. Rs. 34.03 Say 34.05
Composite Rate per Sft. Rs. 255.78 Say 255.80
Labour Rate Per Sq.m Rs. 366.19 Say 366.20
Composite Rate per Sq.m Rs. 2752.21 Say 2752.20
Page 33
32. Making and fixing grating in opening, including fixing at site with flat iron 2"x3/8" and 3/4"
2 Cutting flat iron 2 Nos. cuts 2 cuts 3.60 Per cut 7.20
3 Welding bar with M.S. flat 22 Nos. 22 Nos 6.00 per No. 132.00
4 Drilling holes in stone or masonry 22 Nos 10.00 per hole 220.00
5 Mason 0.75 No. 300.00 per day 225.00
6 Cooly (Unskilled) 1.0 No. 140.00 per day 140.00
Total 856.20
Sundries 10.00 Percent 85.62
Total 941.82
Contractor's Profit & Overh 20.00 Percent 188.36
Total 1130.18
ITEM RATE
Labour Rate/Rft. Rs. 113.02 Say 113.00
Composite Rate/Rft. Rs. 293.06 Say 293.05
Labour Rate per Rm Rs. 370.80 Say 370.80
Composite Rate per Rm Rs. 961.48 Say 961.50
Page 35
34. Providing/fixing stair railing consisting of M.S. Box section size 1-1/2"x3" of 16 SWGwelded with M.S. flat 1"x1/8" continuously and welded over M.S. square bars 5/8"x5/8"punched in M.S. flat 2 ¾' high @ 5½" c/c fixed in steps of stair I/C painting 3 coatscomplete.
Detail Unit Rate Per Rft.Rate
Qty Per Unit Amount
MATERIAL
1 Rate of stair railing with hard wood hand railing(Item No. 33) Rate/ft. ###Less: rate of shisham wood railing 27.50 (No. 31 (a) wood work 137.50 137.50 Per Rft. 137.50Providing fixing M.S. Box section of 16 SWG 1½"x3" for hand rail 1.00 Rft.Add 5% wastage 0.05
1.05 Rft. 22.50 Per Rft. 23.63Painting 3 coats (Item 5d i & ii Painting) 0.62 Sft. 1.39 Per Sft. 0.80including Contractor Profit 54.73+72.6 Say 1.3
LABOUR1 Black smith 0.50 No. 170.00 per day 85.002 Welder 0.50 No. 170.00 per day 85.003 Welding machine on hire basis 0.50 No./day 120.00 per day 60.004 Electric charges with electrode L.S 120.00 120.005 Painter 0.34 No. 170.00 per day 57.806 Glazier 0.50 No. 170.00 per day 85.00
50.40 Rft 49.39 Kg. 22.00 Per Kg. 1086.58@ 2.16 lb/Rft.
3 1½ ft. long M.S. U-Clamp 3/4" dia threaded at 5 Nos. 20.00 Each 100.00both ends including nuts complete.
4 Paint for 2 coats 0.056 Litre 450.00 Per Litre 25.20
Total 4396.82Contractor's Profit & Overh 20.00 Percent 879.36Total 5276.18
LABOUR
1 Welding 15 No . welds 15.00 Nos 7.47 Per weld 112.002 Fitter 0.375 No. 170.00 Per day 63.753 Coolies (Unskilled) 1.50 Nos. 140.00 per day 210.004 Painter 0.125 No. 170.00 per day 21.25