Page 1 CHAPTER NO. 12 WOOD WORK DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed in position including cost of nails a) Deodar Wood. Detail Unit Rate (British System) pe Qty Rate Per Unit (Rs.) Material Deodar Wood including wastage (II Class) 1.15 Cft 500.00 P. Cft Nail 0.020 Kg. 43.00 P. Cft Screws above 1" long 1.00 Dozen 3.25 P.Doz Total Contractor's Profit & Overhead 20 Percent Total Labour Carpentre 0.63 No 300.00 P. Day Cooly Skilled 0.25 No 160.00 P. Day Total Sundries 10 Percent Total Contractor's Profit & Overhead 20 Percent Total Item Rates Labour Rate Per Cft Rs. 302.28 Say Labour Rate Per Cum Rs. ### Say Composite Rate Per Cft Rs. 997.21 Say Composite Rate Per Cum Rs. ### Say
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1
CHAPTER NO. 12
WOOD WORK
DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed & fixedin position including cost of nails & screws etc.
a) Deodar Wood.
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Deodar Wood including wastage (II Class) 1.15 Cft 500.00 P. Cft 575.00 Nail 0.020 Kg. 43.00 P. Cft 0.86 Screws above 1" long 1.00 Dozen 3.25 P.Doz 3.25
Total 579.11 Contractor's Profit & Overheads 20 Percent 115.82 Total 694.93
Labour
Carpentre 0.63 No 300.00 P. Day 189.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00
Total 229.00 Sundries 10 Percent 22.90 Total 251.90
Contractor's Profit & Overheads 20 Percent 50.38 Total 302.28
Item Rates
Labour Rate Per Cft Rs. 302.28 Say 302.30 Labour Rate Per Cum Rs. ### Say 10,676.55
Composite Rate Per Cft Rs. 997.21 Say 997.20 Composite Rate Per Cum Rs. ### Say 35,221.55
Page 2
Item No. 1 Plain wood work sawn wrought planed & fixedin position including cost of nails & screws etc.
b) Shisham Wood
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Shisham wood including 15% wastage 1.15 Cft 300.00 P. Cft 345.00 Nail 0.023 Kg. 43.00 P. Cft 0.99 Screws above 1" long 1.00 Dozen 3.25 P.Doz 3.25
Total 349.24 Contractor's Profit & Overheads 20 Percent 69.85 Total 419.09
Labour for 1.50 Cft.
Carpenters 1.00 No 300.00 P. Day 300.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60 Labour for 1 Cft. 334.40
Item Rates
Labour Rate Per Cft Rs. 334.40 Say 334.40 Labour Rate Per Cum Rs. ### Say 11,811.00
Composite Rate Per Cft Rs. 753.49 Say 753.50 Composite Rate Per Cum Rs. ### Say 26,613.15
Page 3
DESCRIPTION OF ITEM NO. 2: Plain wood work for regulation karries orneedles etc. including sawing plainingwroughting wood providing & fixing steel partsof karries i.e. end strips and rods etc.
a) Deodar Wood.
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
i) Deodar Wood
5.5x5/12x5/12 = 0.97 0.97 CftWastage 15% 0.15 Cft
1.12 Cft 500.00 P. Cft 560.00 ii) 1.6' (480mm) long iron strip 1½"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs2 Nox1¼' (380mm) long iron bars
¾" Ø (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs5.80 Lbs
Wastage 5% 0.29 Lbs6.09Lb (2 .76)Kg 28.00 P. Kg 77.28
iii) Iron Screw 1" (25mm) long 1.00 Dozen 1.68 P. Doz 1.68
Total 638.96 Contractor's Profit & Overheads 20 Percent 127.79 Total 766.75
Page 4
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.32 No 300.00 P. Day 96.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00
Total 136.00 Sundries 10 Percent 13.60 Total 149.60
Contractor's Profit & Overheads 20 Percent 29.92 Total 179.52
Item Rates
Labour Rate Per Cft Rs. 179.52 Say 179.50 Labour Rate Per Cum Rs. 6,340.65 Say 6,340.65
Composite Rate Per Cft Rs. 946.27 Say 946.25 Composite Rate Per Cum Rs. ### Say 33,422.35
Page 5
Item No. 2 Plain wood work for regulation karries or needlesetc. including sawing plaining wroughting wood,providing & fixing steel parts of karries i.e. endstrips and rods etc.
b) Shisham Wood
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
i) Shisham Wood
5.5x5/12x5/12 = 0.97 0.97 CftWastage 15% 0.15 Cft
1.12 Cft 300.00 P. Cft 336.00 ii) Iron Strip
1.6' (480mm) long iron strip 1½"
(37mm) wide x1/8" (3mm) thick @
0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs2 Nox1¼' (380mm) long iron bars
¾" Ø (20mm) on both ends @ 1.502
Lbs/ft. (2.235 Kg/m). 3.80 Lbs5.80 Lbs
Wastage 5% 0.29 Lbs6.09Lb (2 .76)Kg 28.00 P. Kg 77.28
iii) Iron Screw 1" (25mm) long 1.00 Dozen 1.68 P. Doz 1.68
Total 414.96 Contractor's Profit & Overheads 20 Percent 82.99 Total 497.95
Page 6
Detail Unit Rate (British System) per Cft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.32 No 300.00 P. Day 96.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00
Total 136.00 Sundries 10 Percent 13.60 Total 149.60
Contractor's Profit & Overheads 20 Percent 29.92 Total 179.52
Item Rates
Labour Rate Per Cft Rs. 179.52 Say 179.50 Labour Rate Per Cum Rs. 6,340.65 Say 6,340.65
Composite Rate Per Cft Rs. 677.45 Say 677.45 Composite Rate Per Cum Rs. ### Say 23,927.60
Page 7
DESCRIPTION OF ITEM NO 3: First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhat holdfast tower bolts, chocks rubber stop, cleats/G.I.clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).
Wastage 12% 0.62 Cft5.75 Cft 1400.00 P. Cft 8,050.00
(1½ + 2½)
(1½ + 2½)
Page 8
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00
Total 8,243.92 Contractor's Profit & Overheads 20 Percent 1,648.78 Total for 27 Sft. 9,892.71
Rate Per Sft 9892.71 = 366.40 27
Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Cooly Unskilled 1.25 Nos 140.00 P. Day 175.00
Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50
Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00
Rate Per Sft 1419.00 = 52.56 27
Item Rates
Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50
Composite Rate Per Sft Rs. 418.95 Say 418.90 Composite Rate Per Sqm Rs. 4,507.87 Say 4,507.85
Page 9
Item No. 3 First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhathold fast tower bolts, chocks rubber stop, cleats/G.I. clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).
Wastage 12% 0.57 Cft5.33 Cft 1400.00 P. Cft 7,462.00
(1½ + 2½)
(1½ + 2½)
Page 10
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting 7,462.00
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00
Total 7,655.92 Contractor's Profit & Overheads 20 Percent 1,531.18 Total for 27 Sft. 9,187.11
Rate Per Sft 9187.11 = 340.26 27
Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Cooly Unskilled 1.25 Nos 140.00 P. Day 175.00
Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50
Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00
Rate Per Sft 1419.00 = 52.56 27
Item Rates
Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50
Composite Rate Per Sft Rs. 392.81 Say 392.80 Composite Rate Per Sqm Rs. 4,226.67 Say 4,226.65
Page 11
Item No. 3 First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhathold fast tower bolts, chocks rubber stop, cleats/G.I. clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).
Wastage 12% 0.53 Cft4.92 Cft 1400.00 P. Cft 6,888.00
(1½ + 2½)
(1½ + 2½)
Page 12
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
6,888.00 Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00
Total 7,081.92 Contractor's Profit & Overheads 20 Percent 1,416.38 Total for 27 Sft. 8,498.31
Rate Per Sft 8498.31 = 314.75 27
Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Unskilled Cooly 1.25 Nos 140.00 P. Day 175.00
Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50 Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00
Rate Per Sft 1419.00 = 52.56 27
Item Rates
Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50
Composite Rate Per Sft Rs. 367.31 Say 367.30 Composite Rate Per Sqm Rs. 3,952.23 Say 3,952.25
Page 13
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inchs (625mm) including brass fitting sash bars etc. complete :
a) Teak wood framing 1¾" (45mm) thick with wiregauze fixed in position:
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.90
Total 3,536.00 Contractor's Profit & Overheads 20 Percent 707.20 Total for 27 Sft 4,243.20
Rate Per Sft 4243.20 = 157.16 27
Labour
Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft 250.80 Rate Per Sft 250.80 = 9.29
27Item Rates
Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95
Composite Rate Per Sft Rs. 166.44 Say 166.45 Composite Rate Per Sqm Rs. 1,790.94 Say 1,790.95
Page 15
DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sash bars etc. complete :
a) Teak wood framing 1¾" (45mm) thick with wiregauze fixed in position:
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.00 Doz 3.25 P. Doz 6.50 Spring Hings 2.00 Nos 44.00 Each 88.00
Wire Gauze
2x1'-2"x2'-1" = 4.83 Sft4x1'-2"x1'-7" = 7.33 Sft
12.16 SftWastage 10% 1.22 Sft
13.38 Sft 6.00 Sft 80.28
Total 3,620.38 Contractor's Profit & Overheads 20 Percent 724.08 Total for 27 Sft. 3,986.80 Rate Per Sft 3986.80 = 147.66
27Labour
Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total 250.80 Rate Per Sft 250.80 = 9.29
27Item Rates
Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95
Composite Rate Per Sft Rs. 156.95 Say 156.95 Composite Rate Per Sqm Rs. 1,688.76 Say 1,688.75
Page 17
Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:
b) Teak wood framing 1½" (40mm) thick with wiregauze fixed in position.
Hinges 4" (100mm) 6 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2 Nos 17.00 Each 34.00 Handles 6" (150mm) 2 Nos 8.00 Each 16.00 Hook & Clamps 2 Nos 4.00 Each 8.00 Screws / Nail 2 Doz 3.25 P. Doz 6.50
Page 18
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 3,255.98 Contractor's Profit & Overheads 20 Percent 651.20 Total for 27 Sft. 3,907.18
Rate Per Sft 3907.18 = 144.71 27
Labour
Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00
Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80
Rate Per Sft 250.80 = 9.29 27
Item Rates
Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95
Composite Rate Per Sft Rs. 154.00 Say 154.00 Composite Rate Per Sqm Rs. 1,657.03 Say 1,657.05
Page 19
Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:
b) Teak wood framing 1½" (40mm) thick with wiregauze fixed in position.
Hinges 4" (100mm) 6 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2 Nos 17.00 Each 34.00 Handles 6" (150mm) 2 Nos 8.00 Each 16.00 Hook & Clamps 2 Nos 4.00 Each 8.00 Screws / Nail 2 Doz 3.25 Doz 6.50 Spring hings 2 Nos 44.00 Each 88.00
Page 20
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauze
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 3,343.98 Contractor's Profit & Overheads 20 Percent 668.80 Total for 27 Sft. 4,012.78
Rate Per Sft 4012.78 = 148.62 27
Labour
Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00
Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80
Rate Per Sft 250.80 = 9.29 27
Item Rates
Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95
Composite Rate Per Sft Rs. 157.91 Say 157.90 Composite Rate Per Sqm Rs. 1,699.11 Say 1,699.10
Page 21
Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:
c) G.I. Wire gauze 22 SWG 12x12 meshes per SqInch (25mm) fixed to chowkhat with ¾" (20mm)teak wood strips and screws.
Screws above 1" long 2.00 Doz 3.25 Doz 6.50 Nail 0.07 Kg. 43.00 P. Kg. 3.01
Total 410.71 Contractor's Profit & Overheads 20 Percent 82.14 Total for 12 Sft. 492.85
Rate Per Sft 492.85 = 41.07 12
Page 22
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.40 No 300.00 P. Day 120.00 Skilled Cooly 0.20 No 160.00 P. Day 32.00
Total 152.00 Sundries 10 Percent 15.20 Total 167.20 Contractor's Profit & Overheads 20 Percent 33.44 Total for 12 Sft. 200.64
Rate Per Sft 200.64 = 16.72 12
Item Rates
Labour Rate Per Sft Rs. 16.72 Say 16.70 Labour Rate Per Sqm Rs. 179.91 Say 179.90
Composite Rate Per Sft Rs. 57.79 Say 57.80 Composite Rate Per Sqm Rs. 621.83 Say 621.85
Page 23
Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:
d) G.I. Wire gauze 22 SWG 12x12 meshes per SqInch (25mm) fixed with ½" (12mm) teakwood strips and screws.
Screws 2.00 Doz 3.25 P. Doz 6.50 Nail 0.07 Doz 43.00 P. Doz 3.01 Wooden Plug 6.00 Nos 0.50 Each 3.00
Total 975.31 Contractor's Profit & Overheads 20 Percent 195.06 Total for 8 Sft 1,170.37
Rate Per Sft 1170.37 = 146.30 8
Page 24
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.125 No 160.00 P. Day 20.00
Total 95.00 Sundries 10 Percent 9.50 Total 104.50
Contractor's Profit & Overheads 20 Percent 20.90 Total for 8 Sft. 125.40
Rate Per Sft 125.40 = 15.68 8
Item Rates
Labour Rate Per Sft Rs. 15.68 Say 15.70 Labour Rate Per Sqm Rs. 168.66 Say 168.65
Composite Rate Per Sft Rs. 161.98 Say 162.00 Composite Rate Per Sqm Rs. 1,742.92 Say 1,742.90
Page 25
DESCRIPTION OF ITEM NO 5: Providing and fixing expanded metal ½" to ¾"(12mm to 20mm) mesh 16 gauze fixed tochowkhat with 1" (25mm) teak wood strips andscrews etc. complete.
8.40 Sft 6.67 Sft 56.03 Nail and Screw 2.00 Doz 3.25 P. Doz 6.50
Total 454.53 Contractor's Profit & Overheads 20 Percent 90.91 Total for 8 Sft. 545.43 Rate Per Sft 545.43 = 68.18
8
Labour
Carpenters 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 115.00 Sundries 10 Percent 11.50 Total 126.50 Contractor's Profit & Overheads 20 Percent 25.30 Total for 8 Sft. 151.80 Rate Per Sft 151.80 = 18.98
8Item Rates
Labour Rate Per Sft Rs. 18.98 Say 19.00 Labour Rate Per Sqm Rs. 204.17 Say 204.15
Composite Rate Per Sft Rs. 87.15 Say 87.15 Composite Rate Per Sqm Rs. 937.78 Say 937.80
Page 26
DESCRIPTION OF ITEM NO 6: Providing and fixing expanded metal ½" to ¾" (12mm to 20mm) mesh 16 gauze fixed to chowkhatwith 1" (25mm) cover moulding & screwsincluding teak wood frame 2"x2" (50x50mm).
12.60 Sft 6.67 Sft 84.04 Nail and Screw L.S. 8.00 Total 1,058.04 Contractor's Profit & Overheads 20 Percent 211.61 Total for 12 Sft. 1,269.65 Rate Per Sft 1269.65 = 105.80
12Labour
Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total for 12 Sft. 250.81 Rate Per Sft 250.81 = 20.90
12Item Rates
Labour Rate Per Sft Rs. 20.90 Say 20.90 Labour Rate Per Sqm Rs. 224.89 Say 224.90
Composite Rate Per Sft Rs. 126.71 Say 126.70 Composite Rate Per Sqm Rs. 1,363.35 Say 1,363.35
Page 27
DESCRIPTION OF ITEM NO 7: First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)
Wastage 15% 0.77 Cft5.90 Cft 550.00 P. Cft 3,245.00
2(14"+14"+22"+22")5/8"(1½"+2½")
4(14"+18.5"+18.5")5/8"(1½"+2½")
Page 28
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00
Total 3,438.92 Contractor's Profit & Overheads 20 Percent 687.78 Total for 27 Sft. 4,126.71 Rate Per Sft 4126.71 = 152.84
27Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00
Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.20 Rate Per Sft 1399.20 = 51.82
27Item Rates
Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60
Composite Rate Per Sft Rs. 204.66 Say 204.65 Composite Rate Per Sqm Rs. 2,202.18 Say 2,202.20
Page 29
Item No. 7 First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)
Wastage 15% 0.71 Cft5.47 Cft 550.00 P. Cft 3,008.50
2(14"+14"+22"+22")5/8" (1½"+2½")
4(14"+14"+18.5"+18.5")5/8"(1½"+2½")
Page 30
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00
Total for 27 Sft. 3,202.42 Contractor's Profit & Overheads 20 Percent 640.48 Total for 27 Sft. 3,842.91 Rate Per Sft 3842.91 = 142.32
27Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00 Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.21 Rate Per Sft 1399.21 = 51.82
27Item Rates
Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60
Composite Rate Per Sft Rs. 194.14 Say 194.15 Composite Rate Per Sqm Rs. 2,088.97 Say 2,088.95
Page 31
Item No. 7 First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)
Wastage 15% 0.68 Cft5.18 Cft 550.00 P. Cft 2,849.00
2(14"+14"+22"+22")5/8"(1½"+2½")
4(14"+14"+18.5"+18.5")5/8"(1½"+2½")
Page 32
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spibes 0.20 Kg. 30.00 P. Kg. 6.00
Total 3,033.72 Contractor's Profit & Overheads 20 Percent 606.74 Total for 27 Sft. 3,640.47 Rate Per Sft 3640.47 = 134.83
27Labour
Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00
Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.20 Rate Per Sft 1399.20 = 51.82
27Item Rates
Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60
Composite Rate Per Sft Rs. 186.65 Say 186.65 Composite Rate Per Sqm Rs. 2,008.40 Say 2,008.40
Page 33
DESCRIPTION OF ITEM NO 8: Deodar wood framed braced and battened doors &windows complete with iron fitting & fixed inposition including chowkhat.
a) 2¼"(55mm) thick with 1¼"(32mm) thick planks.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 3' x 7' = 21 Sft
Material
Deodar Wood
Top Rail 1x3¾x3"x4½" 0.35 CftVertical Rail 2x7¼"x3"x4½" 1.36 Cft
Hinges 10" (250mm) 3.00 Nos 10.00 Each 30.00 Tower Bolts 9" (225mm) 1.00 No 17.00 Each 17.00 Bolts 8" (200mm) with staple for pad
lock. 1.00 No 32.00 Each 32.00 Wrought Iron hold fast 6.00 Nos 4.00 Each 24.00 Hinges chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door stop 6" (150mm) 1.00 No 12.00 Each 12.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Screws above 1" long 2.00 Doz 3.25 Doz 6.50 Nails of sorts 0.06 Kg 43.00 P. Kg 2.58
Total 2,289.68 Contractor's Profit & Overheads 20 Percent 457.94 Total for 21 Sft. 2,747.62
Rate Per Sft 2747.62 = 130.84 21
Page 34
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 2.50 Nos 300.00 P. Day 750.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 910.00 Sundries 10 Percent 91.00 Total 1,001.00
Contractor's Profit & Overheads 20 Percent 200.20 Total for 21 Sft. 1,201.20 Rate Per Sft 1201.20 = 57.19
21Item Rates
Labour Rate Per Sft Rs. 57.19 Say 57.20 Labour Rate Per Sqm Rs. 615.36 Say 615.35
Composite Rate Per Sft Rs. 188.03 Say 188.05 Composite Rate Per Sqm Rs. 2,023.19 Say 2,023.20
Page 35
Item No. 8 Deodar wood framed braced and battened doors &windows complete with iron fitting & fixed inposition including chowkhat.
b) 1¾" (45mm) thick with 1" (25mm) battens andplanking.
Hinges 5" (125mm) 3.00 Nos 5.60 Each 16.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Wrought Iron hold fast 4.00 Nos 7.00 Each 28.00 Hinges chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door stops 6" (150mm) 1.00 No 12.00 Each 12.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50 Nails of sorts 0.06 Kg 43.00 P. Kg 2.58
Total 1,817.48 Contractor's Profit & Overheads 20 Percent 363.50 Total for 19.5 Sft. 2,180.98
Rate Per Sft 2180.98 = 111.84 19.5
Page 36
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 2.00 Nos 300.00 P. Day 600.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 760.00 Sundries 10 Percent 76.00 Total 836.00
Contractor's Profit & Overheads 20 Percent 167.20 Total for 19.5 1,003.20
Rate Per Sft 1003.20 = 51.45 19.5
Item Rates
Labour Rate Per Sft Rs. 51.45 Say 51.45 Labour Rate Per Sqm Rs. 553.56 Say 553.55
Composite Rate Per Sft Rs. 163.29 Say 163.30 Composite Rate Per Sqm Rs. 1,757.01 Say 1,757.00
Page 37
DESCRIPTION OF ITEM NO 9: 1" (25mm) thick battened doors and windows fittedin position complete with iron fittings withoutchowkhat.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Sft
Material
Deodar Wood 9.50 Cft 500.00 Cft 4,750.00 T. Hinges 6" (150mm) 4.00 Nos 14.00 Each 56.00 Tower bolt 6" (150mm) 2.00 Nos 9.58 Each 19.17 Stops 2.00 Nos 12.00 Each 24.00 Nails 0.063 Kg. 43.00 Kg. 2.71 Screws 2.00 Dozen 3.25 P. Doz 6.50
Total 4,858.38 Contractor's Profit & Overheads 20 Percent 971.68 Total for 100 Sft. 5,830.05 Rate Per Sft 5830.05 = 58.30
100Labour
Carpenters 16.00 Nos 300.00 P. Day 4,800.00 Skilled Cooly 3.00 Nos 160.00 P. Day 480.00
Total 5,280.00 Sundries 10 Percent 528.00 Total 5,808.00
Contractor's Profit & Overheads 20 Percent 1,161.60 Total for 100 Sft. 6,969.60
Rate Per Sft 6969.60 = 69.70 100.0
Item Rates
Labour Rate Per Sft Rs. 69.70 Say 69.70 Labour Rate Per Sqm Rs. 749.93 Say 749.95
Composite Rate Per Sft Rs. 128.00 Say 128.00 Composite Rate Per Sqm Rs. 1,377.24 Say 1,377.25
Page 38
DESCRIPTION OF ITEM NO 10: Deodar battened ledged & braced doors andwindows 2¼" (56mm) thick (1¼" (30mm) thickledge braces and 1" thick battens complete withiron fittings chowkhats and fixed in position.
Hinges Chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door Stop 6" (150mm) 1.00 No 3.00 Each 3.00 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Tower Hinges 8" (200mm) 2.00 Nos 13.00 Each 26.00 Wrought Iron hold fast 4.00 Nos 7.00 Each 28.00 Hasp and staple 1.00 No 12.00 Each 12.00 Handles 2.00 Nos 8.00 Each 16.00 Screws above 1' long 2.00 Doz 3.25 P. Doz 6.50 Nails of sorts 0.13 Kg 43.00 P. Kg 5.38
Total 2,035.47 Contractor's Profit & Overheads 20 Percent 407.09 Total for 19.5 Sft 2,237.69
Rate Per Sft 2237.69 = 114.75 19.5
Page 39
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 2.50 Nos 300.00 P. Day 750.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 910.00 Sundries 10 Percent 91.00 Total 1,001.00
Contractor's Profit & Overheads 20 Percent 200.20 Total for 19.5 Sft. 1,201.20
Rate Per Sft 1201.20 = 61.60 19.5
Item Rates
Labour Rate Per Sft Rs. 61.60 Say 61.60 Labour Rate Per Sqm Rs. 662.82 Say 662.80
Composite Rate Per Sft Rs. 176.35 Say 176.35 Composite Rate Per Sqm Rs. 1,897.56 Say 1,897.55
Page 40
DESCRIPTION OF ITEM NO 11: a) Deodar wood framed with braces and 22 SWGG.I. Sheet facing including hold fast, woodenbeading, hinges and locking arrangement, asDirected by the Engineer Incharge.
70.40 Sft 6.00 Sft 422.40 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 18" (450mm) long 1.00 No 80.00 Each 80.00 Nails 0.23 Kg 43.00 P. Kg 9.89
Total 4,378.04 Contractor's Profit & Overheads 20 Percent 875.61 Total for 64 Sft. 5,253.65 Rate Per Sft 5253.65 = 82.09
64
Labour
Carpenters 3.50 Nos 300.00 P. Day 1,050.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00
Total 1,290.00 Sundries 10 Percent 129.00 Total 1,419.00 Contractor's Profit & Overheads 20 Percent 283.80 Total for 64 Sft. 1,702.80 Rate Per Sft 1702.80 = 26.61
64.0Item Rates
Labour Rate Per Sft Rs. 26.61 Say 26.60 Labour Rate Per Sqm Rs. 286.28 Say 286.30
Composite Rate Per Sft Rs. 108.69 Say 108.70 Composite Rate Per Sqm Rs. 1,169.55 Say 1,169.55
Page 41
DESCRIPTION OF ITEM NO 11: a) Deodar wood framed with braces and 22 SWGG.I. Sheet facing including hold fast, woodenbeading, hinges and locking arrangement, asDirected by the Engineer Incharge.
140.80 Sft 6.00 Sft 844.80 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 1½" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.47 Kg 43.00 P. Kg 20.21
Total 4,810.76 Contractor's Profit & Overheads 20 Percent 962.15 Total for 64 Sft. 5,772.91 Rate Per Sft 5772.91 = 90.20
64Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00
Total 1,440.00 Sundries 10 Percent 144.00 Total 1,584.00
Contractor's Profit & Overheads 20 Percent 316.80 Total for 64 Sft. 1,900.80 Rate Per Sft 1900.80 = 29.70
64.0Item Rates
Labour Rate Per Sft Rs. 29.70 Say 29.70 Labour Rate Per Sqm Rs. 319.57 Say 319.55
Composite Rate Per Sft Rs. 119.90 Say 119.90 Composite Rate Per Sqm Rs. 1,290.14 Say 1,290.15
Page 42
Item No. 11 b) Partal wood frame with braces & 22 SWG G.I.Sheet facing including hold fast wooden beadinghinges and locking arrangement as directed byEngineering incharge.
70.40 Sft 6.00 Sft 422.40 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 1½" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.23 Kg 43.00 P. Kg 9.89
Total 2,978.04 Contractor's Profit & Overheads 20 Percent 595.61 Total for 64 Sft. 3,573.65 Rate Per Sft 3573.65 = 55.84
64
Labour
Carpenters 3.50 Nos 300.00 P. Day 1,050.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00
Total 1,290.00 Sundries 10 Percent 129.00 Total 1,419.00
Contractor's Profit & Overheads 20 Percent 283.80 Total 1,702.80 Rate Per Sft 1702.80 = 26.61
64.0Item Rates
Labour Rate Per Sft Rs. 26.61 Say 26.60 Labour Rate Per Sqm Rs. 286.28 Say 286.30
Composite Rate Per Sft Rs. 82.44 Say 82.45 Composite Rate Per Sqm Rs. 887.10 Say 887.10
Page 43
Item No. 11 b) Partal wood frame with braces & 22 SWG G.I.Sheet facing including hold fast wooden beadinghinges and locking arrangement as directed byEngineering incharge.
140.80 Sft 6.00 Sft 844.80 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 18" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.47 Kg 43.00 P. Kg 20.21
Total 3,410.76 Contractor's Profit & Overheads 20 Percent 682.15 Total for 64 Sft. 4,092.91 Rate Per Sft 4092.91 = 63.95
64Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00
Total 1,440.00 Sundries 10 Percent 144.00 Total 1,584.00
Contractor's Profit & Overheads 20 Percent 316.80 Total for 64 Sft. 1,900.80 Rate Per Sft 1900.80 = 29.70
64.0Item Rates
Labour Rate Per Sft Rs. 29.70 Say 29.70 Labour Rate Per Sqm Rs. 319.57 Say 319.55
Composite Rate Per Sft Rs. 93.65 Say 93.65 Composite Rate Per Sqm Rs. 1,007.69 Say 1,007.70
Page 44
DESCRIPTION OF ITEM NO 12: First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.
a) Deodar framing 1¾" (45mm) with wire gauge fixed in position.
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50
Page 45
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 1,495.98 Contractor's Profit & Overheads 20 Percent 299.20 Total for 27 Sft. 1,795.18 Rate Per Sft 1795.18 = 66.49
27Labour
Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00
Total 570.00 Sundries 10 Percent 57.00 Total 627.00
Contractor's Profit & Overheads 20 Percent 125.40 Total for 27 Sft. 752.40 Rate Per Sft 752.40 = 27.87
27.0Item Rates
Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85
Composite Rate Per Sft Rs. 94.35 Say 94.35 Composite Rate Per Sqm Rs. 1,015.26 Say 1,015.25
Page 46
Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.
a) Deodar wood framing 1¾" (45mm) thick withwire gauge fixed in position.
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50 Spring Hinges 2.00 Nos 44.00 Each 88.00
Page 47
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 1,583.98 Contractor's Profit & Overheads 20 Percent 316.80 Total for 27 Sft. 1,900.78 Rate Per Sft 1900.78 = 70.40
27Labour
Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00
Total 570.00 Sundries 10 Percent 57.00 Total 627.00
Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87
27.0Item Rates
Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85
Composite Rate Per Sft Rs. 98.27 Say 98.25 Composite Rate Per Sqm Rs. 1,057.34 Say 1,057.35
Page 48
Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.
b) Deodar Wood framing 1½" (40mm) thick withwire gauze fixed in position.
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (228mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50
Page 49
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 1,385.98 Contractor's Profit & Overheads 20 Percent 277.20 Total for 27 Sft. 1,663.18 Rate Per Sft 1663.18 = 61.60
27Labour
Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00
Total 570.00 Sundries 10 Percent 57.00 Total 627.00
Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87
27Item Rates
Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85
Composite Rate Per Sft Rs. 89.47 Say 89.45 Composite Rate Per Sqm Rs. 962.65 Say 962.65
Page 50
Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 144 mashes per squareinch (625mm) including iron fittings complete.
b) Deodar Wood framing 1½" (40mm) thick withwire gauze fixed in position.
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (228mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50 Spring 2.00 Nos 44.00 Each 88.00
Page 51
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Wire Gauge
2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft
12.16 SftWastage 15% 1.82 Sft
13.98 Sft 6.00 Sft 83.88
Total 1,468.48 Contractor's Profit & Overheads 20 Percent 293.70 Total for 27 Sft. 1,762.18 Rate Per Sft 1762.18 = 65.27
27Labour
Carpenters 1.50 No 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00
Total 570.00 Sundries 10 Percent 57.00 Total 627.00
Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87
27Item Rates
Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85
Composite Rate Per Sft Rs. 93.13 Say 93.15 Composite Rate Per Sqm Rs. 1,002.11 Say 1,002.10
Page 52
Item No. 12 c) G.I. wire gauze 22 SWG, 12x12 meshes per squareinch (256mm) fixed to chowkhat with ¾" (20mm)thick deodar wood screw and strip.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 3' = 12 Sft
Material
Wood Work
Wood 0.25 Cft 550.00 P. Cft 137.50 Wire gauze 12.00 Sft 6.00 Sft 72.00 Nails L.S. 8.00
Total 217.50 Contractor's Profit & Overheads 20 Percent 43.50 Total for 12 Sft. 261.00 Rate Per Sft 261.00 = 21.75
12Labour
Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00
Contractor's Profit & Overheads 20 Percent 41.80 Total 250.80 Rate Per Sft 250.80 = 20.90
12Item Rates
Labour Rate Per Sft Rs. 20.90 Say 20.90 Labour Rate Per Sqm Rs. 224.88 Say 224.90
Composite Rate Per Sft Rs. 42.65 Say 42.65 Composite Rate Per Sqm Rs. 458.91 Say 458.90
Page 53
Item No. 12 d) G.I. wire gauze 22 SWG, 12x12 meshes persquare inch (625mm) fixed to chowkhat with ½"(12mm) strip on separate frame of deodar wood2"x2" (50x50mm).
0.56 Cft 550.00 P. Cft 308.00 Wire Gauze 144 Mesh/Sqare in CW 4x2 8.00 Sft Wastage 10% 0.80 Sft
8.80 Cft 6.00 P. Sft 52.80
Fitting
Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50 Nails 0.08 Kg 43.00 P. Kg 3.58 Wooden Plugs 6.00 Nos 1.00 Each 6.00
Total 376.88 Contractor's Profit & Overheads 20 Percent 75.38 Total for 8 Sft. 452.26 Rate Per Sft 452.26 = 56.53
8
Page 54
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00
Contractor's Profit & Overheads 20 Percent 41.80 Total for 8 Sft. 250.80 Rate Per Sft 250.80 = 31.35
8Item Rates
Labour Rate Per Sft Rs. 31.35 Say 31.35 Labour Rate Per Sqm Rs. 337.33 Say 337.35
Composite Rate Per Sft Rs. 87.88 Say 87.90 Composite Rate Per Sqm Rs. 945.62 Say 945.60
Page 55
DESCRIPTION OF ITEM NO 13: Making and fixing trellis doors and windows ofdeodar wood complete.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 18 Sft
Material
Deodar Wood 2.30 Cft 500.00 P. Cft 1,150.00 Nail 0.126 Kg. 43.00 P. Kg. 5.42 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower Bolt 9" (225mm) 2.00 Nos 17.00 Each 34.00 Hasp & Staple 1.00 No 4.00 Each 4.00
Total 1,219.94 Contractor's Profit & Overheads 20 Percent 243.99 Total for 18 Sft. 1,463.93 Rate Per Sft 1463.93 = 81.33
18Labour
Carpenter 1.50 No 300.00 P. Day 450.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 610.00 Sundries 10 Percent 61.00 Total 671.00
Contractor's Profit & Overheads 20 Percent 134.20 Total for 18 Sft. 805.20 Rate Per Sft 805.20 = 44.73
18Item Rates
Labour Rate Per Sft Rs. 44.73 Say 44.75 Labour Rate Per Sqm Rs. 481.33 Say 481.35
Composite Rate Per Sft Rs. 126.06 Say 126.05 Composite Rate Per Sqm Rs. 1,356.44 Say 1,356.45
Page 56
DESCRIPTION OF ITEM NO 14: Providing & fixing mild steel chowkhat of doors,windows, C. Window etc. including hold fast,making and threading holes for hinges etc.complete
a) M.S. angle iron 1½"x1½"x¼" (40x40x6mm)welded M.S. flat 2"x¼" (50x6mm)
4 @ 0.42 Lbs/ft 1.68 Lbs77.28Lb (3 5.06)Kg 24.00 P. Kg 841.44
Total 841.44 Contractor's Profit & Overheads 20 Percent 168.29 Total for 27 Sft. 1,009.73 Rate Per Sft 1009.73 = 37.40
27
Horizontal 1x4 4 Rft
Wastage 5% 0.90 Rft
Horizontal 1x4 4 Rft
Wastage 5% 0.90 Rft
Page 57
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Making holes in frame for hinges 4x4 16.00 Nos 1.41 Each 22.59 Welding plate with angle iron 18.00 Nos 6.00 Each 108.00 Welding hold fast with frame 6.00 Nos 4.00 Each 24.00 Welding M.S.Steel bar with frame 2.00 Nos 4.00 Each 8.00
Total 162.59 Sundries 10 Percent 16.26 Total 178.85
Contractor's Profit & Overheads 20 Percent 35.77 Total 214.62 Rate Per Sft 214.62 = 7.95
27Item Rates
Labour Rate Per Sft Rs. 7.95 Say 7.95 Labour Rate Per Sqm Rs. 85.53 Say 85.55
Composite Rate Per Sft Rs. 45.35 Say 45.35 Composite Rate Per Sqm Rs. 487.92 Say 487.90
Page 58
Item No. 14 Providing & fixing mild steel chowkhat of doors,windows, C. Window etc. including hold fast,making and threading holes for hinges etc.complete
b) M.S. Tee iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. Flat ½"x¼" (12x6mm)
18.90ft @ 0.425 Lbs/ft 8.03 LbsM.S. Bar ½" dia 4' @ 0.67 Lbs/ft 2.68 Lbs
55.31Lb (2 5.10) Kg 24.00 P. Kg 602.40
Total 602.40 Contractor's Profit & Overheads 20 Percent 120.48 Total for 27 Sft. 722.88 Rate Per Sft 722.88 = 26.77
27
Horizontal 1x4 4 Rft
Wastage 5% 0.90 Rft
Page 59
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Making holes in frame for hinges 4x4 16.00 Nos 1.41 Each 22.59 Welding plate with angle iron 18.00 Nos 6.00 Each 108.00 Welding hold fast with frame 6.00 Nos 4.00 Each 24.00 Welding M.S.Steel bar with frame 2.00 Nos 4.00 Each 8.00
Total 162.59 Sundries 10 Percent 16.26 Total 178.85
Contractor's Profit & Overheads 20 Percent 35.77 Total 214.62 Rate Per Sft 214.62 = 7.95
27Item Rates
Labour Rate Per Sft Rs. 7.95 Say 7.95 Labour Rate Per Sqm Rs. 85.53 Say 85.55
Composite Rate Per Sft Rs. 34.72 Say 34.70 Composite Rate Per Sqm Rs. 373.61 Say 373.60
Page 60
Item No. 15 Providing and fixing M.S. Sheet hollow pressedframe of doors, windows, CW, etc. (Chowkhatonly) of 20 SWG welded with M.S. flat6"x1½"x1/8" (150x40x3mm) M.S. hold fast 9"x1"x1/8" (225x25x3mm) welded/ screwed 4"(100mm) long iron hinges including fittingchowkhat with cement sand mortar 1:8 andembedding hold fast in cement concrete 1:2:4,complete in all respects.
a) Single Rebate.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
M.S. Sheet 20 Swg 15"(375mm) wide
18' long x15/12 (5.486x0.380m) 22.50 Kg.Wastage 10% 2.25 Kg.
24.75 Kg.SAY 25.00 Kg. Or 29.00 Kg. 493.58
M.S. Flat 6"x¼"x1/8" (150x6x3mm) 17.02 Kg3.5 Rft @ 0.531 Lbs/Rft 1.86 LbsM.S. Flat hold fast 9"x1"x1/8" (225x25x3mm)
4.5 Rft @ 0.425 Lbs/Rft 1.91 Lbs3.77Lb (1 .71) Kg 22.00 P. Kg 37.62
Fitting
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Screws 3.00 Doz 3.25 P. Doz 9.75 Nails 0.28 Kg. 43.00 P. Kg. 12.04 Welding Charges 60.00 Cement sand mortar ratio 1:8 for
filling hollow space 18'x4'/12"x3/12
including wastage (0.057m³)
(5.486x0.100x0.075m) 2.00 Cft
Page 61
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Cement 0.20 Bag 230.00 Each 46.00 Sand 2.00 Cft 3.50 P. Cft 7.00 Cement Concrete 1:2:4 for fixing hold fast
Cement 0.08 Bag 230.00 Bag 18.40 Sand 0.20 Cft. 350.00 % Cft. 0.70 Bajri 0.40 Cft. 1850.00 % Cft. 7.40
Total 720.09 Contractor's Profit & Overheads 20 Percent 144.02 Total for 28 Sft. 864.11 Rate Per Sft 864.11 = 30.86
28Labour
Moulder/ Black Smith 0.50 No 300.00 P. Day 150.00 Cooly 0.50 No 140.00 P. Day 70.00 SKilled Cooly (for Mortor Filling in the
hallow space) 0.50 No 160.00 P. Day 80.00
Total 300.00 Sundries 10 Percent 30.00 Total 330.00
Contractor's Profit & Overheads 20 Percent 66.00 Total for 28 Sft. 396.00 Rate Per Sft 396.00 = 14.14
28Item Rates
Labour Rate Per Sft Rs. 14.14 Say 14.15 Labour Rate Per Sqm Rs. 152.18 Say 152.20
Composite Rate Per Sft Rs. 45.00 Say 45.00 Composite Rate Per Sqm Rs. 484.24 Say 484.25
Page 62
Item No. 15 Providing and fixing M.S. Sheet hollow pressedframe of doors, windows, C. window, etc. (Chowkhat only) of 20 SWG welded with M.S. flat6"x1¼"x1/8" (150x32x3mm) M.S. hold fast 9"x1"x1/8" (225x25x3mm) welded/ screwed 4"(100mm) long iron hinges including fittingchowkhat with cement sand mortar 1:8 andembedding hold fast in cement concrete 1:2:4,complete in all respects.
b) Double Rebate.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
M.S. Sheet 20SWG 17"(432mm) wide
19' longx18x18/17(5.486x0.432)= 25.50 Sft
28.05 Sft 19.10 Kg 29.00 P. Kg 553.90
M.S. Flat 7.5x1¼"x1/8(2.30x0.032x0.003)=7 No.
4.50 Rft @ 0.531 Lbs/Rft 2.39 LbsM.S. Flat hold fast 9"x1"x1/8"= 6 No
4.50 Rft @ 0.425 Lbs/Rft 1.91 Lbs4.30Lbs (1 .95) Kg 22.00 P. Kg 42.90
Fitting
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Screws 3.00 Doz 3.25 P. Doz 9.75 Nails 0.28 Kg. 43.00 P. Kg. 12.04 Welding Charges 80.00 Cement sand mortar ratio 1:8 for
filling hollow space
18"x11/24x4/12 = (5.486x0.275x0.1m) 2.75 Cft
Wastage 10% 2.55 Sft
Page 63
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Cement 0.28 Bag 230.00 Each 63.25 Sand 2.75 Cft 3.50 P. Cft 9.63 Cement Concrete 1:2:4 for (fixing
hold fast) Cement 0.08 Bag 230.00 Bag 18.40 Sand 0.20 Cft. 350.00 % Cft. 0.70 Bajri 0.40 Cft. 1850.00 % Cft. 7.40
Total 825.56 Contractor's Profit & Overheads 20 Percent 165.11 Total for 28 Sft. 990.68 Rate Per Sft 990.68 = 35.38
28
Moulder/ Black Smith 0.75 No 300.00 P. Day 225.00 Cooly 0.50 No 140.00 P. Day 70.00 SKilled Cooly (for Mortor Filling in the
hollow space) 0.50 No 160.00 P. Day 80.00
Total 375.00 Sundries 10 Percent 37.50 Total 412.50
Contractor's Profit & Overheads 20 Percent 82.50 Total for 28 Sft. 495.00 Rate Per Sft 495.00 = 17.68
28Item Rates
Labour Rate Per Sft Rs. 17.68 Say 17.70 Labour Rate Per Sqm Rs. 190.22 Say 190.20
Composite Rate Per Sft Rs. 53.06 Say 53.05 Composite Rate Per Sqm Rs. 570.92 Say 570.95
Page 64
DESCRIPTION OF ITEM NO 16: Extra for providing & fixing iron double springhinges, with brass fittings (it shall include brassfinger plate, 6" tower bolts)
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 21 Sft
Material
4" (100mm) double section spring
hinges iron. 3.00 Nos 50.00 Each 150.00 Brass finger plate 2.00 Nos 30.00 Each 60.00 6" (150mm) brass tower bolt 1.00 No 30.00 Each 30.00 Brass screws 1½" (40mm) 2.00 Doz 8.00 P. Doz 16.00 Brass Screw 1" (25mm) 2.50 Doz 3.25 P. Doz 8.13
264.13
Deduct Cost of Iron Fittings
5" (125mm) Butt Hinges 4.00 Nos 5.50 Each 22.00 9" (225mm) Tower Bolts 2.00 Nos 17.00 Each 34.00 6" (150mm) Handle 2.00 Nos 8.00 Each 16.00 Hinges Chocks 2.00 Nos 2.00 Each 4.00 Door Stops 2.00 Nos 12.00 Each 24.00 Screws 1½" 3.00 Doz 3.25 P. Doz 9.75 Screws 1" 3.00 Doz 1.68 P. Doz 5.04
114.79
Total 262.50-112.96 = 149.34 Contractor's Profit & Overheads 20 Percent 29.87 Total for 21 Sft. 179.20 Rate Per Sft 179.20 = 8.53
21
Page 65
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00
Total 23.00 Sundries 10 Percent 2.30 Total 25.30
Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36 Rate Per Sft 30.36 = 1.45
21
Item Rates
Labour Rate Per Sft Rs. 1.45 Say 1.45 Labour Rate Per Sqm Rs. 15.56 Say 15.55
Composite Rate Per Sft Rs. 9.98 Say 10.00 Composite Rate Per Sqm Rs. 107.38 Say 107.40
Page 66
DESCRIPTION OF ITEM NO 17: Providing and fixing brass spring hinges, to wiregauzed doors.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Brass spring hinges Complete with
screws 1 No 60.00 Each 60.00
Total 60.00 Contractor's Profit & Overheads 20 Percent 12.00 Total 72.00
Labour
Carpenter 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00
Total 23.00 Sundries 10 Percent 2.30 Total 25.30
Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36
Item Rates
Labour Rate for Each Rs. 30.36 Say 30.35
Composite Rate for Each Rs. 102.36 Say 102.35
Page 67
DESCRIPTION OF ITEM NO 18: Providing and fixing sliding bolt to doors.
i) Iron sliding bolt 10" (250mm) long.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 16 Each
Material
Sliding bolt 10"(250mm) long complete with
screws & nuts. 16 Nos 35.00 Each 560.00
Total 560.00 Contractor's Profit & Overheads 20 Percent 112.00 Total 672.00
Labour
Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60
Item Rates
Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16
Composite Rate for Each Rs. 1173.60 73.35 Say 73.35 16
Page 68
Item No. 18 Providing and fixing sliding bolt to doors.
ii) Iron sliding bolt 12" (300mm) long.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 16 Each
Material
Sliding bolt 12" (300mm) long complete
with screws with & nuts. 16 Nos 45.00 Each 720.00
Total 720.00 Contractor's Profit & Overheads 20 Percent 144.00 Total 864.00
Labour
Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60
Item Rates
Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16
Composite Rate for Each Rs. 1365.60 85.35 Say 85.35 16
Page 69
Item No. 18 Providing and fixing sliding bolt to doors.
iii) Brass sliding bolt 10" (250mm) long.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Anaylysis for = 16 Each
Material
Brass sliding bolt 10" (250mm) long
complete with screws & nuts. 16 Nos 75.00 Each 1,200.00
Total 1,200.00 Contractor's Profit & Overheads 20 Percent 240.00 Total 1,440.00
Labour
Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60
Item Rates
Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16
Composite Rate for Each Rs. 1941.60 121.35 Say 121.35 16
Page 70
Item No. 18 Providing and fixing sliding bolt to doors.
iv) Brass sliding bolt 12" (300mm) long.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 16 Each
Material
Brass sliding bolt 12" (300mm) long
complete with screws & nuts. 16 Nos 85.00 Each 1,360.00
Total 1,360.00 Contractor's Profit & Overheads 20 Percent 272.00 Total 1,632.00
Labour
Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60
Item Rates
Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16
Composite Rate for Each Rs. 2133.60 133.35 Say 133.35 16
Page 71
DESCRIPTION OF ITEM NO 19: Extra for brass fittings to doors and windows,except for hinges, which shall be of iron.
i) Deodar wood panelled or panelled and glazed orfully glazed.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
9" (225mm) Tower bolt 3.00 Nos 27.00 Each 81.00 6" (150mm) Handles 3.00 Nos 40.00 Each 120.00 2" (50mm) Butt hinges 2.00 Nos 5.00 Each 10.00 Screws 1" 3.50 Doz 3.25 P. Doz 11.38
222.38 Deduct Cost of Iron Fittings
9" (225mm) Tower Bolts 3.00 Nos 17.00 Each 51.00 6" (150mm) Handle 3.00 Nos 9.60 Each 28.80 2" (50mm) butt hinges 2.00 Nos 6.00 Each 12.00 Screws above 1" long 3.50 Doz 3.25 P. Doz 11.38
103.18
Total 222.38-101.04 = 119.20 Contractor's Profit & Overheads 20 Percent 23.84 Total for 28 Sft. 143.04 Rate Per Sft 143.04 = 5.11
28
Labour
Carpenter 0.04 No 300.00 P. Day 12.00 Skilled Cooly 0.04 No 160.00 P. Day 6.40
Total 18.40 Sundries 10 Percent 1.84 Total 20.24 Contractor's Profit & Overheads 20 Percent 4.05 Total 24.29 Rate Per Sft 24.29 = 0.87
28
Labour Rate Per Sft Rs. 0.87 Say 0.85 Labour Rate Per Sqm Rs. 9.33 Say 9.35 Composite Rate Per Sft Rs. 5.98 Say 6.00 Composite Rate Per Sqm Rs. 64.30 Say 64.30
Material (Brass Fittings)
Page 72
Item No. 19 Extra for brass fittings to doors and windows,except for hinges, which shall be of iron.
ii) Deodar wood wire gauzed shutters.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
9" (225mm) Tower balt 2.00 Nos 27.00 Each 54.00 6" (150mm) Handles 2.00 Nos 40.00 Each 80.00 2" (50mm) butt hinges 2.00 Nos 5.00 Each 10.00 Screws 1" 3.50 Doz 3.25 P. Doz 11.38
155.38 Deduct Cost of Iron Fittings
9" (225mm) Tower Bolts 2.00 Nos 17.00 Each 34.00 8" (200mm) Handle 2.00 Nos 9.60 Each 19.20
### 2" (50mm) Butt hinges 2.00 Nos 6.00 Each 12.00 Screws 1" 3.00 Doz 3.25 P. Doz 9.75
74.95
Total 153.75-73.12 = 80.42 Contractor's Profit & Overheads 20 Percent 16.08 Total for 28 Sft. 96.51 Rate Per Sft 96.51 = 3.45
28Labour
Carpenter 0.04 No 300.00 P. Day 12.00 Skilled Cooly 0.04 No 160.00 P. Day 6.40
Total 18.40 Sundries 10 Percent 1.84 Total 20.24 Contractor's Profit & Overheads 20 Percent 4.05 Total for 28 Sft. 24.29 Rate Per Sft 24.29 = 0.87
28Item Rates
Labour Rate Per Sft Rs. 0.87 Say 0.85 Labour Rate Per Sqm Rs. 9.33 Say 9.35
Composite Rate Per Sft Rs. 4.31 Say 4.30 Composite Rate Per Sqm Rs. 46.42 Say 46.40
Material (Brass Fittings)
Page 73
DESCRIPTION OF ITEM NO 20: Extra for providing and fixing, approved qualityrim lock adjustable over the style surface.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Rim lock complete with screws 1.00 No 140.00 Each 140.00 Deduct cost of handle 2.00 Nos 8.00 Each 16.00
Total 156.00 Contractor's Profit & Overheads 20 Percent 31.20 Total 187.20
Labour
Carpenter 0.17 No 300.00 P. Day 51.00 Skilled Cooly 0.13 No 160.00 P. Day 20.80
Total 71.80 Sundries 10 Percent 7.18 Total 78.98
Contractor's Profit & Overheads 20 Percent 15.80 Total 94.78
Item Rates
Labour Rate for Each Rs. 94.78 Say 94.80
Composite Rate for Each Rs. 281.98 Say 282.00
Page 74
DESCRIPTION OF ITEM NO 21: Providing and fixing approved quality morticelock.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Mortice lock compelte with screws 1.00 No 175.00 Each 175.00 Deduct cost of handles 2.00 Nos 8.00 Each 16.00
Total 159.00 Contractor's Profit & Overheads 20 Percent 31.80 Total 190.80
Labour
Carpenter 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.17 No 160.00 P. Day 26.67
Total 101.67 Sundries 10 Percent 10.17 Total 111.83
Contractor's Profit & Overheads 20 Percent 22.37 Total 134.20
Item Rates Labour Rate for Each Rs. 134.20 Say 134.20
Composite Rate for Each Rs. 325.00 Say 325.00
—
Page 75
DESCRIPTION OF ITEM NO 22: Providing and fixing expanded metal ½" to ¾"(12mm to 20mm) mesh 16 gauge.
a) Fixed to chowkhat with 1" (25mm) thick deodarwood strip and screws etc.
Hings 3" (75mm) 6.00 Nos 3.75 Each 22.50 Hasp & Staple (Brass) 1.00 No 12.00 Each 12.00 Brass Handle 6" (150mm) 2.00 Nos 70.00 Each 140.00 Wooden Plugs 10.00 Nos 1.00 Each 10.00 Nails / Screws L.S. 19.00 Bitumen 1.43 Kg. 14.00 P. Kg. 20.02
Total 2,814.02 Contractor's Profit & Overheads 20 Percent 562.80 Total for 15 Sft. 3,376.82 Rate Per Sft 3376.82 = 225.12
15
Page 78
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenter 2.50 No 300.00 P. Day 750.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 830.00 Sundries 10 Percent 83.00 Total 913.00
Contractor's Profit & Overheads 20 Percent 182.60 Total for 15 Sft. 1,095.60 Rate Per Sft 1095.60 = 73.04
15
Item Rates
Labour Rate Per Sft Rs. 73.04 Say 73.05 Labour Rate Per Sqm Rs. 785.91 Say 785.90
Composite Rate Per Sft Rs. 298.16 Say 298.15 Composite Rate Per Sqm Rs. 3,208.22 Say 3,208.20
Page 79
Item No. 23 b) Providing and fixing deodar wood almirah 9" to12" (225 to 300mm) depth, with shelves shutterand brass fittings, etc. without boxing & back complete.
Hings 3" (75mm) 6.00 Nos 3.75 Each 22.50 Hasp & Staple (Brass) 1.00 No 12.00 Each 12.00 Brass Handle 6" (150mm) 2.00 Nos 70.00 Each 140.00 Wooden Plugs 6.00 Nos 1.00 Each 6.00 Nails / Screws L.S. 12.00
Total 1,292.50 Contractor's Profit & Overheads 20 Percent 258.50 Total for 15 Sft. 1,551.00 Rate Per Sft 1551.00 = 103.40
15Labour
Carpenter 1.75 Nos 300.00 P. Day 525.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 605.00 Sundries 10 Percent 60.50 Total 665.50 Contractor's Profit & Overheads 20 Percent 133.10 Total for 15 Sft. 798.60 Rate Per Sft 798.60 = 53.24
15Item Rates
Labour Rate Per Sft Rs. 53.24 Say 53.25 Labour Rate Per Sqm Rs. 572.86 Say 572.85
Composite Rate Per Sft Rs. 156.64 Say 156.65 Composite Rate Per Sqm Rs. 1,685.45 Say 1,685.45
Page 80
Item No. 24 Providing and fixing class room almirahconsisting of 1" (25mm) thick solid flush shutterwith deodar wood lipping ¼" (6mm) thick alround(sterling made) fixed in deodar wood frame 3"x1"(75x25mm) I/C full hinges C.P. fittings withR.C.C. (1:1-½:3) shelves 1-½" (40mm) thick I/C 3coats of painting.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4.5' x 3.5' = 15.75 Sft
Material
Precast reinforced cement concrete
(1:1-½"3)
Shelves 2x3-¼x1-1/8x1/8 0.91 Cft 83.60 P. Cft 76.07 Steel ¼" (12mm) dia
Full hinges 1" (25mm) I/C screws 2x4 8.00 Nos 20.00 Each 160.00 C.P. dasti I/C screws 2.00 Nos 8.00 Each 16.00 Khunda chapks (Best quality) I/C screws 1.00 No 12.00 Each 12.00 Rawal plug 1-½" long 12.00 Nos 3.00 Each 36.00 Screws 1-½" long 1.00 Doz 3.25 P. Doz 3.25 Glue 0.20 Kg. 80.00 P.Kg. 16.00 Painting 3 coats 0.428 Gln. 450.00 P. Gln. 192.60
Total 1,786.04 Contractor's Profit & Overheads 20 Percent 357.21 Total for 15.75 Sft. 2,143.25 Rate Per Sft 2143.25 = 136.08
15.75 Labour
For bringing the leaves to proper size
fixing deodar wood lipping with glue
and nail making/ fixing deodar wood
frame & fixing at site with rawal plug &
screws.
Carpenter 1.00 No 300.00 P. Day 300.00 Helper 1.00 No 75.00 P. Day 75.00
Total 375.00 Sundries 10 Percent 37.50 Total 412.50
Contractor's Profit & Overheads 20 Percent 82.50 Total for 15.75 Sft. 495.00 Rate Per Sft 495.00 = 31.43
15.75
Item Rates
Labour Rate Per Sft Rs. 31.43 Say 31.45 Labour Rate Per Sqm Rs. 338.17 Say 338.15
Composite Rate Per Sft Rs. 167.51 Say 167.50 Composite Rate Per Sqm Rs. 1,802.39 Say 1,802.40
Page 82
DESCRIPTION OF ITEM NO 25: Providing and fixing wooden box type ward robe22" (550mm) deep including ¾" (20mm) thickboxing and shelves, hanger rods, hard board backdrawers, brass fitting locking arrangements,handles internal bolts shoe rods, etc. includingthree coats of enamel paints.
i) Partal wood boxing and deodar wood shelves andleaves etc.
4.38 Cft 350.00 P. Cft 1,533.00 Shutters Deodar Wood
1x1-2/3x6½x1/12 0.91 Cft1x2-1/3x6½x1/12 1.26 Cft
2.17 CftWastage 15% 0.33 Cft
2.50 Cft 500.00 P. Cft 1,250.00 Hard Board
4x6½ 26.00 SftWastage 10% 2.60 Sft
28.60 Sft 3.50 Sft 100.10 Sawing Charges
6.88x10 68.80 Sft 0.80 Sft 55.04
Page 83
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fittings
Hings 4" (100mm) 6.00 Nos 4.60 Each 27.60 Handle 2.00 Nos 8.00 Each 16.00 Tie rod welding fixing arragement 2.25 Nos 28.00 Each 63.00 Hanger hook including pull out rod 2.00 Nos 8.00 Each 16.00 Tower bolt 4" (100mm) 1.00 Nos 7.00 Each 7.00 Bitumen Painting 1.43 Kg. 14.00 Each 20.02
Total 3,087.76 Contractor's Profit & Overheads 20 Percent 617.55 Total for 26 Sft. 3,705.32 Rate Per Sft 3705.32 = 142.51
26Labour
Carpenters 4.00 No 300.00 P. Day 1,200.00 Skilled Cooly 2.00 No 160.00 P. Day 320.00
Total 1,520.00 Sundries 10 Percent 152.00 Total 1,672.00
Contractor's Profit & Overheads 20 Percent 334.40 Total 2,006.40 Rate Per Sft 2006.40 = 77.17
26
Item Rates
Labour Rate Per Sft Rs. 77.17 Say 77.15 Labour Rate Per Sqm Rs. 830.34 Say 830.35
Composite Rate Per Sft Rs. 219.68 Say 219.70 Composite Rate Per Sqm Rs. 2,363.77 Say 2,363.75
Page 84
Item No. 25 Providing and fixing wooden box type ward robe22" (550mm) deep including ¾" (20mm) thickboxing and shelves, hanger rods, hard board backdrawers, brass fitting locking arrangements,handles internal bolts shoe rods, etc. includingthree coats of enamel paints.
Bitumen Painting 2 Coat 1.43 Kg. 14.00 Each 20.02 Painting 3 Coats 0.27 Kg. 450.00 P. Gln. 121.50
Page 85
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fittings
Hings 4" (100mm) 6.00 Nos 4.50 Each 27.00 Handle 2.00 Nos 8.00 Each 16.00 Tie rod welding fixing arragement 8.00 Hanger hook including full out rod 2.00 Nos 8.00 Each 16.00 Screws 4.00 Doz 3.25 P. Doz 13.00 Tower bolt 4" (100mm) 1.00 Nos 7.00 Each 7.00 Nail 0.19 Kg 43.00 P. Kg 8.17 Locking arrangement 1.00 Nos 55.00 Each 55.00
Total 5,562.29 Contractor's Profit & Overheads 20 Percent 1,112.46 Total for 40 Sft. 6,674.75 Rate Per Sft 6674.75 = 166.87
40
Carpenters 6.00 Nos 300.00 P. Day 1,800.00 Skilled Cooly 2.00 Nos 160.00 P. Day 320.00 Painter 1.00 Nos 170.00 P. Day 170.00
Total 2,290.00 Sundries 10 Percent 229.00 Total 2,519.00
Contractor's Profit & Overheads 20 Percent 503.80 Total for 40 Sft. 3,022.80 Rate Per Sft 3022.80 = 75.57
40
Item Rates
Labour Rate Per Sft Rs. 75.57 Say 75.55 Labour Rate Per Sqm Rs. 813.13 Say 813.15
Composite Rate Per Sft Rs. 242.44 Say 242.45 Composite Rate Per Sqm Rs. 2,608.64 Say 2,608.65
Page 86
Item No. 26 Providing/ fixing ward robe 22" (550mm) deep consisting of RCC shelves 1-½" (40mm) thick I/c ½"
(12mm) thick vin board boxing and back (one sideply) vin board shutter ¾" (20mm) thick I/c Deodarwood lipping ¼"(6mm) on all edges fixes I/c deodarwood frame 3"x1" with hanger rod in centre portiondrawers at bottom and openable shutter on upperportion I/c full hinges C.P. fitting and painting 3coats.
C.P. Handle 9.00 Nos 8.00 Each 72.00 Catcher (Germany) 9.00 Nos 6.40 Each 57.60 China Lock (Glone) 3.00 Nos 24.00 Each 72.00 Rawal Plug 1½" (40mm) 30.00 Nos 0.30 Each 9.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 C.P. Hanger rod with 2 hooks 1.00 No 96.00 Each 96.00 C.P. Hooks 2.00 Nos 8.00 Each 16.00
Page 88
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Glue 2.00 Kg 80.00 P. Kg 160.00 Nail L.S. 32.00 Painting 4(7½ x 7) 2.86 Gln. 17.00 P. Gln. 48.62
Total 8,553.39 Contractor's Profit & Overheads 20 Percent 1,710.68 Total for 52.50 Sft. 10,264.07 Rate Per Sft 10264.07 = 195.51
52.50Labour
Labour for making ward robe complete 52.50 Sft 29.00 Sft 1,522.50
Total 1,522.50 Sundries 10 Percent 152.25 Total 1,674.75
Contractor's Profit & Overheads 20 Percent 334.95 Total 2,009.70 Rate Per Sft 2009.70 = 38.28
52.50
Item Rates
Labour Rate Per Sft Rs. 38.28 Say 38.30 Labour Rate Per Sqm Rs. 411.89 Say 411.90
Composite Rate Per Sft Rs. 233.79 Say 233.80 Composite Rate Per Sqm Rs. 2,515.54 Say 2,515.55
Page 89
DESCRIPTION OF ITEM NO 27: Providing and fixing chowkhat for doors, window,& C. Windows including hold fast etc.
a) Teak Wood.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Teak Wood
Top Rail 1x4¾x3"x4½" 0.45 CftVertical Rail 2x7x3"x4½" 1.33 Cft
1.78 CftWastage 12% 0.22 Cft
2.00 Cft 1400.00 P. Cft 2,800.00 Iron hold fast 6.00 Nos 12.00 Each 72.00
Total 2,872.00 Contractor's Profit & Overheads 20 Percent 574.40 Total for 27 Sft. 3,446.40 Rate Per Sft 3446.40 = 127.64
27Labour
Carpenter 0.70 No 300.00 P. Day 210.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00
Total 290.00 Sundries 10 Percent 29.00 Total 319.00
Contractor's Profit & Overheads 20 Percent 63.80 Total for 27 Sft. 382.80 Rate Per Sft 382.80 = 14.18
27
Item Rates
Labour Rate Per Sft Rs. 14.18 Say 14.20 Labour Rate Per Sqm Rs. 152.55 Say 152.55
Composite Rate Per Sft Rs. 141.82 Say 141.80 Composite Rate Per Sqm Rs. 1,526.01 Say 1,526.00
Page 90
Item No. 27 Providing and fixing chowkhat for doors windows& C. Windows including hold fast etc.
b) Deodar Wood.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
For Frame
Top Rail 1x4¾'x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 Cft
1.78 CftWastage 15% 0.27 Cft
2.05 Cft 550.00 P. Cft 1,127.50 Iron hold fast 6.00 Nos 12.00 Each 72.00
Total 1,199.50 Contractor's Profit & Overheads 20 Percent 239.90 Total for 27 Sft. 1,439.40 Rate Per Sft 1439.40 = 53.31
27Labour
Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00
Total 190.00 Sundries 10 Percent 19.00 Total 209.00
Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80 Rate Per Sft 250.80 = 9.29
27
Item Rates
Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95
Composite Rate Per Sft Rs. 62.60 Say 62.60 Composite Rate Per Sqm Rs. 673.58 Say 673.60
Page 91
Item No. 27 Providing and fixing chowkhat for doors, windows,& C. Windows including hold fast etc.
c) Shisham Wood.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 6.75' = 27 Sft
Material
Shishim Wood
Top Rail 1x4¾'x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 Cft
1.78 CftWastage 15% 0.27 Cft
2.05 Cft 300.00 P. Cft 614.10 Iron hold fast 6.00 Nos 12.00 Each 72.00
Total 686.10 Contractor's Profit & Overheads 20 Percent 137.22 Total for 27 Sft. 823.32 Rate Per Sft 823.32 = 30.49
27Labour
Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.40 No 160.00 P. Day 64.00
Total 214.00 Sundries 10 Percent 21.40 Total 235.40
Contractor's Profit & Overheads 20 Percent 47.08 Total for 27 Sft. 282.48 Rate Per Sft 282.48 = 10.46
27
Item Rates
Labour Rate Per Sft Rs. 10.46 Say 10.45 Labour Rate Per Sqm Rs. 112.57 Say 112.55
Composite Rate Per Sft Rs. 40.96 Say 40.95 Composite Rate Per Sqm Rs. 440.68 Say 440.70
Page 92
DESCRIPTION OF ITEM NO 28:Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.
a) 1" (25mm) Thick.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 9.50 Cft 500.00 P. Cft 4,750.00 Nail & Screws bolt and brackets L.S. 24.00
Total 4,774.00 Contractor's Profit & Overheads 20 Percent 954.80 Total for 100 Sft. 5,728.80 Rate Per Sft 5728.80 = 57.29
100Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 75.24 Say 75.25 Composite Rate Per Sqm Rs. 809.58 Say 809.60
Page 93
Item No. 28 Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.
b) ¾" (20mm) Thick.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 7.12 Cft 500.00 P. Cft 3,560.00 Asscessories for fixing L.S. 24.00
Total 3,584.00 Contractor's Profit & Overheads 20 Percent 716.80 Total for 100 Sft. 4,300.80 Rate Per Sft 4300.80 = 43.01
100Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 60.96 Say 60.95 Composite Rate Per Sqm Rs. 655.93 Say 655.95
Page 94
Item No. 28 Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.
c) ½" (12mm) Thick
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 4.75 Cft 500.00 P. Cft 2,375.00 Asscessories for fixing L.S. 24.00
Total 2,399.00 Contractor's Profit & Overheads 20 Percent 479.80 Total for 100 Sft. 2,878.80 Rate Per Sft 2878.80 = 28.79
100Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 46.74 Say 46.75 Composite Rate Per Sqm Rs. 502.92 Say 502.90
Page 95
DESCRIPTION OF ITEM NO 29:Making and fixing deodar wood shelves,including brackets.
i) 1" (25mm) Thick.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 9.50 Cft 500.00 P. Cft 4,750.00 Accessoires for fitting L.S. 24.00
Total 4,774.00 Contractor's Profit & Overheads 20 Percent 954.80 Total for 100 Sft. 5,728.80 Rate Per Sft 5728.80 = 57.29
100Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 75.24 Say 75.25 Composite Rate Per Sqm Rs. 809.58 Say 809.60
Page 96
Item No. 29 Making and fixing deodar wood shelves,including brackets.
ii) 1½" (40mm) Thick
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 14.25 Cft 500.00 P. Cft 7,125.00 Asscessories for fixing L.S. 24.00
Total 7,149.00 Contractor's Profit & Overheads 20 Percent 1,429.80 Total for 100 Sft. 8,578.80 Rate Per Sft 8578.80 = 85.79
100
Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 103.74 Say 103.75 Composite Rate Per Sqm Rs. 1,116.24 Say 1,116.25
Page 97
Item No. 29 Making and fixing deodar wood shelves,including brackets.
iii) 2" (50mm) Thick.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 100 Sft
Material
Deodar Wood 19.00 Cft 500.00 P. Cft 9,500.00 Asscessories for fixing L.S. 24.00
Total 9,524.00 Contractor's Profit & Overheads 20 Percent 1,904.80 Total for 100 Sft. 11,428.80 Rate Per Sft 11428.80 = 114.29
100Labour
Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00
Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95
100
Item Rates
Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15
Composite Rate Per Sft Rs. 132.24 Say 132.25 Composite Rate Per Sqm Rs. 1,422.90 Say 1,422.90
Page 98
DESCRIPTION OF ITEM NO 30: a) Making and fixing cleats for doors and windows including hinges and screws.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 10 Nos
Material
Hinges 2" (50mm) 10.00 Nos 2.50 Each 25.00 Screws 1" (25mm) 3.50 Doz 3.25 P. Doz 11.38 Deodar wood 0.21 Cft 500.00 P. Cft 105.00
Total 141.38 Contractor's Profit & Overheads 20 Percent 28.28 Total 169.65
Labour
Carpenters 0.40 No 300.00 P. Day 120.00 Skilled Cooly 0.20 No 160.00 P. Day 32.00
Total 152.00 Sundries 10 Percent 15.20 Total 167.20
Contractor's Profit & Overheads 20 Percent 33.44 Total 200.64
Item Rates
Labour Rate for Each Rs. 200.64 20.06 Say 20.05 10
Composite Rate for Each Rs. 370.29 37.03 Say 37.05 10
Page 99
Item No. 30 b) Making and fixing cleats with brass hooks for roofventilator.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Brass hooks 1 No 4.00 Each 4.00 Deodar Wood 0.01 Cft 500.00 P. Cft 5.00 Screws/ Nails 2.00 Nos 3.25 P. Doz 0.44
Total 9.44 Contractor's Profit & Overheads 20 Percent 1.89 Total 11.33
Labour for 1.25 Nos.
Carpenter 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00
Total 23.00 Sundries 10 Percent 2.30 Total 25.30
Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36
Item Rates
Labour Rate for Each Rs. 30.36 24.29 Say 24.30 1.25
Composite Rate for Each Rs. 35.62 Say 35.60
Page 100
Item No. 30 c) Providing and fixing door stops of 1½" (40mm)dia rubber block.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 30 Nos
Material
Door rubber stopper 30.00 Nos 2.80 Each 84.00 Gutty 30.00 Nos 0.25 Each 7.50 Screws 2.50 Doz 3.25 P. Doz 8.13
Total 99.62 Contractor's Profit & Overheads 20 Percent 19.92 Total 119.55
Labour
Carpenter 0.25 No 300.00 P. Day 75.00
Total 75.00 Sundries 10 Percent 7.50 Total 82.50
Contractor's Profit & Overheads 20 Percent 16.50 Total 99.00
Item Rates
Labour Rate for Each Rs. 99.00 3.30 Say 3.30 30
Composite Rate for Each Rs. 218.55 7.28 Say 7.30 30
Page 101
Item No. 30 d) Providing and fixing G.I. hook with clamps fordoors.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
G.I. Hook 1.00 No 2.00 Each 2.00 Gutty 1.00 No 0.25 Each 0.25
Total 2.25 Contractor's Profit & Overheads 20 Percent 0.45 Total 2.70
Labour (Labour for 30 No.)
Carpenter 0.08 No 300.00 P. Day 24.00
Total 24.00 Sundries 10 Percent 2.40 Total 26.40
Contractor's Profit & Overheads 20 Percent 5.28 Total 31.68
Item Rates
Labour Rate for Each Rs. 31.68 1.06 Say 1.05 30
Composite Rate for Each Rs. 3.76 Say 3.75
Page 102
DESCRIPTION OF ITEM:
Item No. 31 Hard wood railing of any shape and designincluding bends and corners fixed in positionincluding polishing complete as directed by Engineer Incharge.
a) Shisham Wood.
Detail Unit Rate (British System) per Rft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 12 Rft
Material
Shisham wood 0.90 Cft 300.00 P. Cft 270.00 Sand paper 3.00 Nos 6.00 Each 18.00 Polishing material 0.075 Kg. 160.00 P. Kg. 12.00
Total 300.00 Contractor's Profit & Overheads 20 Percent 60.00 Total 12 Rft. 360.00 Rate Per Rft 360.00 = 30.00
12Labour
Carpenters 1.50 No 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00 Polisher 0.50 No 170.00 P. Day 85.00
Total 655.00 Sundries 10 Percent 65.50 Total 720.50
Contractor's Profit & Overheads 20 Percent 144.10 Total for 12 Rft. 864.60 Rate Per Rft 864.60 = 72.05
12Item Rates
Labour Rate Per Rft Rs. 72.05 Say 72.05 Labour Rate Per Rm Rs. 236.32 Say 236.30
Composite Rate Per Rft Rs. 102.05 Say 102.05 Composite Rate Per Rm Rs. 334.72 Say 334.70
Page 103
Item No. 31 Hard wood railing of any shape and designincluding bends and corners fixed in positionincluding polishing complete as directed by Engineer Incharge.
b) Teak Wood.
Detail Unit Rate (British System) per Rft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 10 Rft
Material
Teak wood 0.90 Cft 1400.00 P. Cft 1,260.00 Sand paper 3.00 Nos 6.00 Each 18.00 Polishing material 0.075 Kg. 160.00 P. Kg. 12.00
Total 1,290.00 Contractor's Profit & Overheads 20 Percent 258.00 Total for 10 Rft. 1,548.00 Rate Per Rft 1548.00 = 154.80
10Labour
Carpenters 1.00 No. 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00 Polisher 0.20 No 170.00 P. Day 34.00
Total 414.00 Sundries 10 Percent 41.40 Total 455.40
Contractor's Profit & Overheads 20 Percent 91.08 Total for 10 Rft. 546.48 Rate Per Rft 546.48 = 54.65
10
Item Rates
Labour Rate Per Rft Rs. 54.65 Say 54.65 Labour Rate Per Rm Rs. 179.26 Say 179.25
Composite Rate Per Rft Rs. 209.45 Say 209.45 Composite Rate Per Rm Rs. 687.00 Say 687.00
Page 104
DESCRIPTION OF ITEM NO 32:Deodar wood dado or Picture Rail 3"x1½"(50x40mm) as per approved design includingmoulding and fixed in place, cost of screws nails,plugs and painting complete.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 10 Rft
Material
Deodar wood 0.60 Cft 500.00 P. Cft 300.00 Sand paper 1.00 Sht 6.00 P. Sht 6.00 Rawal Plugs 0.50 No 0.30 Each 0.15 Screws 0.50 Doz 3.25 P. Doz 1.63 Polishing material 0.038 Kg. 160.00 P. Kg. 6.00
Total 313.78 Contractor's Profit & Overheads 20 Percent 62.76 Total for 10 Rft. 376.53 Rate Per Rft 376.53 = 37.65
10Labour
Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00 Polisher 0.10 No 170.00 P. Day 17.00
Total 207.00 Sundries 10 Percent 20.70 Total 227.70
Contractor's Profit & Overheads 20 Percent 45.54 Total for 10 Rft. 273.24 Rate Per Rft 273.24 = 27.32
10
Item Rates
Labour Rate Per Rft Rs. 27.32 Say 27.30 Labour Rate Per Rm Rs. 89.62 Say 89.60
Composite Rate Per Rft Rs. 64.98 Say 65.00 Composite Rate Per Rm Rs. 213.12 Say 213.15
Page 105
DESCRIPTION OF ITEM NO 33: Sawing wood by hand.
a) Soft wood (Deodar Kail, Chir)
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Sawyer 1.50 Nos 170.00 P. Day 255.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00
Total 495.00 Sundries 10 Percent 49.50 Total 544.50
Contractor's Profit & Overheads 20 Percent 108.90 Total 653.40
Item Rates
Labour Rate Per 100 Sft Rs. 653.40 x 100 =154.28 Say 217.80 300
Labour Rate Per Sqm Rs. 23.44 Say 23.45
Page 106
Item No. 33: Sawing wood by hand.
b) Hard Wood (Shisham, Kikar, Sal or Teak)
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit Amount
Rate Analysis for = 450 Sft
Labour
Sawyer 3.00 Nos 170.00 P. Day 510.00 Skilled Cooly 3.00 Nos 160.00 P. Day 480.00
Total 990.00 Sundries 10 Percent 99.00 Total 1,089.00
Contractor's Profit & Overheads 20 Percent 217.80 Total 1,306.80
Item Rates
Labour Rate Per 100 Sft Rs. 1306.80 x 100=205.7 Say 290.40 450
Labour Rate Per Sqm Rs. 31.25 Say 31.25
Page 107
DESCRIPTION OF ITEM NO 34: Sawing wood by machine.
a) Soft Wood.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Sawyer 1.00 No 170.00 P. Day 170.00 Skilled Cooly 0.77 No 160.00 P. Day 123.20
Total 293.20 Sundries 10 Percent 29.32 Total 322.52
Contractor's Profit & Overheads 20 Percent 64.50 Total 387.02
Item Rates
Labour Rate Per 100 Sft Rs. 387.02 x 100=94.97 Say 129.01 300
Labour Rate Per Sqm Rs. 13.88 Say 13.90
Page 108
Item No. 34 Sawing wood by machine.
b) Hard Wood.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 300 Sft
Labour
Sawyer 1.50 Nos 170.00 P. Day 255.00 Skilled Cooly 1.16 Nos 160.00 P. Day 185.60
Total 440.60 Sundries 10 Percent 44.06 Total 484.66
Contractor's Profit & Overheads 20 Percent 96.93 Total 581.59
Item Rates
Labour Rate Per 100 Sft Rs. 581.59 x 100=142.62 Say 193.85 300 193.86
Labour Rate Per Sqm Rs. 20.86 Say 20.85
Page 109
DESCRIPTION OF ITEM NO 35: Making and fixing sun shade of deodar woodincluding fixing brackets.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 5 Sft
Material
Deodar Wood
Horizontal Planks
Top 4x5x1/3x1/24 0.28 CftVertical 2x1¾x1/6x5/68 0.06 CftSupports along sun shade 0.04 Cft2x3/2x1/8x5/48
0.56 Cft 500.00 P. Cft 280.00 Sawing & Nails L.S. 8.00
Total 288.00 Contractor's Profit & Overheads 20 Percent 57.60 Total for 5 Sft. 345.60 Rate Per Sft 345.60 = 69.12
5Labour
Carpenter 0.25 No 300.00 P. Day 75.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00
Total 91.00 Sundries 10 Percent 9.10 Total 100.10
Contractor's Profit & Overheads 20 Percent 20.02 Total for 5 Sft. 120.12 Rate Per Sft 120.12 = 24.02
5Item Rates
Labour Rate Per Sft Rs. 24.02 Say 24.00 Labour Rate Per Sqm Rs. 258.50 Say 258.50
Composite Rate Per Sft Rs. 93.14 Say 93.15 Composite Rate Per Sqm Rs. 1,002.23 Say 1,002.25
Page 110
DESCRIPTION OF ITEM NO 36: Making and fixing 1" (25mm) thick Kail or Chirwooden notice board with frame.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 18 Sft
Material
Kail or Chir Wood 1.64 Cft 350.00 P. Cft 574.00 Nails 0.093 Kg. 43.00 P. Kg. 4.00 Glue 0.075 Kg. 80.00 P. Kg. 6.00 Iron Hook 1.00 No. 2.00 Each 2.00
Total 586.00 Contractor's Profit & Overheads 20 Percent 117.20 Total for 18 Sft. 703.20 Rate Per Sft 703.20 = 39.07
18Labour
Carpenter 0.75 No 300.00 P. Day 225.00 Cooly Skilled 0.75 No 160.00 P. Day 120.00
Total 345.00 Sundries 10 Percent 34.50 Total 379.50
Contractor's Profit & Overheads 20 Percent 75.90 Total for 18 Sft. 455.40 Rate Per Sft 455.40 = 25.30
18
Item Rates
Labour Rate Per Sft Rs. 25.30 Say 25.30 Labour Rate Per Sqm Rs. 272.23 Say 272.25
Composite Rate Per Sft Rs. 64.37 Say 64.35 Composite Rate Per Sqm Rs. 692.59 Say 692.60
Page 111
DESCRIPTION OF ITEM NO 37: Making deodar Punkha Pole = 10'x6"x6"(3.047x0.150x0.150M).
Detail Unit Rate (British System) per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Deodar wood 2.50 Cft 500.00 P. Cft 1,250.00 Hooks 2.00 Doz 12.00 P. Doz 24.00
Total 1,274.00 Contractor's Profit & Overheads 20 Percent 254.80 Total 1,528.80
Labour
Carpenter 0.20 No 300.00 P. Day 60.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00
Total 76.00 Sundries 10 Percent 7.60 Total 83.60
Contractor's Profit & Overheads 20 Percent 16.72 Total 100.32
Item Rates
Labour Rate for Each Rs. 100.32 Say 100.30
Composite Rate for Each Rs. 1629.12 Say 1,629.10
Page 112
DESCRIPTION OF ITEM NO 38: Dismantling and refixing eaves boards.
Detail Unit Rate (British System) per Rft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 70 Rft
Labour
Carpenter 1.00 No 300.00 P. Day 300.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00
Total 380.00 Sundries 10 Percent 38.00 Total 418.00
Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60
Item Rates
Labour Rate Per Rft Rs. 501.60 7.17 Say 7.15 70
Labour Rate Per Rm Rs. 23.51 Say 23.50
Page 113
DESCRIPTION OF ITEM NO 39: Making wooden stair cases complete 2' to 3' (600 to915mm) wide frame 1½" (40mm) thick planks ofdeodar wood, including hand rails.
10.50 Cft 500.00 P. Cft 5,250.00 Nails 0.93 Kg 28.00 P. Kg 26.04 Bolts ½" to 3" (12 to 76mm) long 5.880 Kg. 45.00 P. Kg 264.60 Steel rods dia ¾ 3x3'-6" = 10.5 Rft 15.3Lb (7 .5Kg) 17.00 P. Kg 127.50 Washers 12.00 Nos 0.50 Each 6.00
Total 5,674.14 Contractor's Profit & Overheads 20 Percent 1,134.83 Total for 15 Rft. 6,808.97 Rate Per Rft 6808.97 = 453.93
15Labour
Carpenter 2.00 Nos 300.00 P. Day 600.00 Blacksmith 0.50 No 170.00 P. Day 85.00 Hammer-man 0.50 No 75.00 P. Day 37.50 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00
Total 1,042.50 Sundries 10 Percent 104.25 Total 1,146.75 Contractor's Profit & Overheads 20 Percent 229.35 Total for 15 Rft. 1,376.10 Rate Per Rft 1376.10 = 91.74
15Item Rates
Labour Rate Per Rft Rs. 91.74 Say 91.75 Labour Rate Per Rm Rs. 300.91 Say 300.90
Composite Rate Per Rft Rs. 545.67 Say 545.65 Composite Rate Per Rm Rs. 1,789.80 Say 1,789.80
Page 114
DESCRIPTION OF ITEM NO 40: Providing and fixing partition including frame work.a - (i) Sheets on one side of frame work.
Hard Board.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
1x8x16 128.00 SftWastage 5% 6.40 Sft
134.40 Sft 3.50 Sft 470.40 Deodar Wood & other Accessories
Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 Cft 2x8x3"x2½" 0.83 Cft 3x8x2"x2½" 0.83 Cft
3.89 CftWastage 15% 0.58 Cft
4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 P. Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50
Total 2,732.11 Contractor's Profit & Overheads 20 Percent 546.42 Total for 128 Sft. 3,278.53 Rate Per Sft 3278.53 x 100 = 2,561.35
128Labour
Carpenter 1.00 Nos 300.00 P. Day 300.00 Cooly Skilled 1.00 Nos 160.00 P. Day 160.00
Total 460.00 Sundries 10 Percent 46.00 Total 506.00 Contractor's Profit & Overheads 20 Percent 101.20 Total for 128 Sft. 607.20 Rate Per Sft 607.20 x 100 = 474.38
128Item Rates
Labour Rate Per 100 Sft Rs. 474.38 Say 474.40 Labour Rate Per Sqm Rs. 51.04 Say 51.05
Composite Rate Per 100 Sft Rs. 3,035.73 Say 3,035.75 Composite Rate Per Sqm Rs. 326.64 Say 326.65
Page 115
Item No. 40 Providing and fixing partition including frame work.a - (ii) Ply wood ¼" (6mm) thick.
One Side.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Ply Wood 1x8'x16 128.00 SftWastage 5% 6.40 Sft
134.40 Sft 10.00 Sft 1,344.00 Deodar Wood
Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 CftVertical post 3x8x2½"x2½" 0.83 CftVertical post 3x8x2½"x2½" 0.83 Cft
3.89 CftWastage 15% 0.58 Cft
4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50
Total 3,605.71 Contractor's Profit & Overheads 20 Percent 721.14 Total for 128 Sft. 4,326.85 Rate Per Sft 4326.85 x 100 = 3,380.35
128Labour
Carpenter 1.00 Nos 300.00 P. Day 300.00 Cooly Skilled 1.00 Nos 160.00 P. Day 160.00
Total 460.00 Sundries 10 Percent 46.00 Total 506.00 Contractor's Profit & Overheads 20 Percent 101.20 Total for 128 Sft. 607.20 Rate Per Sft 607.20 x 100 = 474.38
128Item Rates
Labour Rate Per 100 Sft Rs. 474.38 Say 474.40 Labour Rate Per Sqm Rs. 51.04 Say 51.05
Composite Rate Per 100 Sft Rs. 3,854.73 Say 3,854.75 Composite Rate Per Sqm Rs. 414.77 Say 414.75
Page 116
Item No. 40 Providing and fixing partition including frame work.a - (iii) Masonite sheet.
134.40 Sft 22.00 Sft 2,956.80 Deodar Wood & other Accessories
Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 Cft 2x8x3"x2½" 0.83 Cft3x8x2"x2½" 0.83 Cft
3.89 CftWastage 15% 0.58 Cft
4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 P. Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50
Total 5,218.51 Contractor's Profit & Overheads 20 Percent 1,043.70 Total for 128 Sft. 6,262.21 Rate Per Sft 6262.21 x 100 = 4,892.35
128Labour
Carpenter 1.00 Nos 170.00 P. Day 170.00 Cooly Skilled 1.00 Nos 85.00 P. Day 85.00
Total 255.00 Sundries 10 Percent 25.50 Total 280.50 Contractor's Profit & Overheads 20 Percent 56.10 Total for 128 Sft. 336.60 Rate Per Sft 336.60 x 100 = 262.97
128Item Rates
Labour Rate Per 100 Sft Rs. 262.97 Say 262.95 Labour Rate Per Sqm Rs. 28.30 Say 28.30
Composite Rate Per 100 Sft Rs. 5,155.32 Say 5,155.30 Composite Rate Per Sqm Rs. 554.71 Say 554.70
Page 117
Item No. 40 Providing and fixing partition including frame work.b (1) Sheets on both sides of frame work.
Hard Board.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Hard Board Sheet
2 x 16 x 8 256.00 SftWastage 5% 12.80 Sft
268.80 Sft 3.50 Sft 940.80 Deodar Wood & other Accessories
4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws of all sorts 2.00 Doz 3.25 P. Doz 6.50 Total 3,212.40 Contractor's Profit & Overheads 20 Percent 642.48 Total for 128 Sft. 3,854.88 Rate Per Sft 3854.88 x 100 = 3,011.63
128Labour
Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00
Total 552.00 Sundries 10 Percent 55.20 Total 607.20 Contractor's Profit & Overheads 20 Percent 121.44 Total for 128 Sft. 728.64 Rate Per Sft 728.64 x 100 = 569.25
128
Item Rates
Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25
Composite Rate Per 100 Sft Rs. 3,580.88 Say 3,580.90 Composite Rate Per Sqm Rs. 385.30 Say 385.30
Page 118
Item No. 40 Providing and fixing partition including frame work.b - (ii) Ply wood. ¼" (6mm) thick
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 128 Sft
Material
Ply Wood Sheet 2 x 16 x 8 (2 x 4.876 x 256.00 Sft2.438) = 23.78 M²
Wastage 5% 12.80 Sft268.80 Sft 10.50 Sft 2,822.40
Deodar Wood for frame work
Horizontal post 2x16x3"x2½" 1.67 CftCross 1x16x2"x2½" 0.56 CftVertical post 2x8x3"x2½" 0.83 CftVertical post 3x8x2"x2½" 0.83 Cft
3.89 CftWastage 15% 0.58 Cft
4.47 Cft 550.00 P. Cft 2,458.50 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws 3.00 Doz 3.25 P. Doz 9.75 Total 5,320.75 Contractor's Profit & Overheads 20 Percent 1,064.15 Total for 128 Sft. 6,384.90 Rate Per Sft 6384.90 x 100 = 4,988.20
128Labour
Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00
Total 552.00 Sundries 10 Percent 55.20 Total 607.20
Contractor's Profit & Overheads 20 Percent 121.44 Total for 128 Sft. 728.64 Rate Per Sft 728.64 x 100 = 569.25
128Item Rates
Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25
Composite Rate Per 100 Sft Rs. 5,557.45 Say 5,557.45 Composite Rate Per Sqm Rs. 597.98 Say 598.00
Page 119
Item No. 40 Providing and fixing partition including frame work.b - (iii) Masonite sheet.
4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws 2.00 Doz 3.25 P. Doz 6.50 Total 8,185.20 Contractor's Profit & Overheads 20 Percent 1,637.04 Total 9,822.24 Rate Per Sft 9822.24 x 100 = 7,673.63
128Labour
Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00
Total 552.00 Sundries 10 Percent 55.20 Total 607.20 Contractor's Profit & Overheads 20 Percent 121.44 Total 728.64 Rate Per Sft 728.64 x 100 = 569.25
128Item Rates
Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25
Composite Rate Per 100 Sft Rs. 8,242.88 Say 8,242.90 Composite Rate Per Sqm Rs. 886.93 Say 886.95
Page 120
DESCRIPTION OF ITEM NO 41: Providing and fixing ceiling including frame work.i) Hard Board.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Hard Board 16x12 192.00 Sft 3.50 Sft 672.00
Partal Wood
7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft
6.88 CftWastage 10% 0.69 Cft
7.57 Cft 350.00 P. Cft 2,649.50 Hard Wood Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 3,674.29 Contractor's Profit & Overheads 20 Percent 734.86 Total for 192 Sft. 4,409.15 Rate Per Sft 4409.15 x 100 = 2,296.43
192Labour
Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00
192Item Rates
Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60
Composite Rate Per 100 Sft Rs. 3,231.43 Say 3,231.45 Composite Rate Per Sqm Rs. 347.70 Say 347.70
Page 121
Item No. 41 Providing and fixing ceiling including frame work.ii) Chip Board Sheets.
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 192 Sft
Material
Chip Board 1x16x12 192.00 Sft 16.40 Sft 3,148.80
Partal Wood & other Accessories
Partal Wood.
7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft
6.88 CftWastage 10% 0.69 Cft
7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 6,151.09 Contractor's Profit & Overheads 20 Percent 1,230.22 Total for 192 Sft. 7,381.31 Rate Per Sft 7381.31 x 100 = 3,844.43
192Labour
Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00
192Item Rates
Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60 Composite Rate Per 100 Sft Rs. 4,779.43 Say 4,779.45 Composite Rate Per Sqm Rs. 514.27 Say 514.25
Page 122
Item No. 41 Providing and fixing ceiling including framework.
7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 5,018.29 Contractor's Profit & Overheads 20 Percent 1,003.66 Total for 192 Sft. 6,021.95 Rate Per Sft 6021.95 x 100 = 3,136.43
192Labour
Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00
192Item Rates
Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60
Composite Rate Per 100 Sft Rs. 4,071.43 Say 4,071.45 Composite Rate Per Sqm Rs. 438.09 Say 438.10
Page 123
Item No. 41 Providing and fixing ceiling including frame work.iv) Masonite Sheet.
7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gulli 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grating 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 7,610.29 Contractor's Profit & Overheads 20 Percent 1,522.06 Total for 192 Sft. 9,132.35 Rate Per Sft 9132.35 x 100 = 4,756.43
192Labour
Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly Unskilled 1.00 No 140.00 P. Day 140.00
Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00
192Item Rates
Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60
Composite Rate Per 100 Sft Rs. 5,691.43 Say 5,691.45 Composite Rate Per Sqm Rs. 612.40 Say 612.40
Page 124
Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.
a) Deodar wood frame panelling.i) ¾" (20mm) Thick.
Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.00 Each 32.00 Screws above 1" long 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25
Total 2,548.35 Contractor's Profit & Overheads 20 Percent 509.67 Total for 144 Sft. 3,058.02 Rate Per Sft 3058.02 x 100 = 2,123.63
144
Page 125
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenters 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00
Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00
Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00
144
Item Rates
Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45
Composite Rate Per 100 Sft Rs. 3,168.63 Say 3,168.65 Composite Rate Per Sqm Rs. 340.94 Say 340.95
Page 126
Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.
a) Deodar wood frame panellingii) 1" (25mm) Thick.
3.06 Cft 500.00 P. Cft 1,530.00 Sawing charge 3.06 Cft 8.00 24.48 Making holes in walls L.S. 37.33 Screws of all sorts 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair L.S. 20.00
Total 2,728.23 Contractor's Profit & Overheads 20 Percent 545.65 Total for 144 Sft. 3,273.88 Rate Per Sft 3273.88 x 100 = 2,273.52
144
Page 127
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00
Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00
Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00
144
Item Rates
Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45
Composite Rate Per 100 Sft Rs. 3,318.52 Say 3,318.50 Composite Rate Per Sqm Rs. 357.07 Say 357.05
Page 128
Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.
3.06 Cft 350.00 P. Cft 1,071.00 Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.50 Each 40.00 Screws of all sorts 6.00 Nos 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25
Total 2,097.35 Contractor's Profit & Overheads 20 Percent 419.47 Total for 144 Sft. 2,516.82 Rate Per Sft 2516.82 x 100 = 1,747.79
144
Page 129
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Doz 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00
Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00
Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00
144
Item Rates
Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45
Composite Rate Per 100 Sft Rs. 2,792.79 Say 2,792.80 Composite Rate Per Sqm Rs. 300.50 Say 300.50
Page 130
Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.
b) Pertal wood frame panellingii) 1" (25mm) Thick.
3.06 Cft 350.00 P. Cft 1,071.00 Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.00 Each 32.00 Screws of all sorts 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25
Total 2,305.57 Contractor's Profit & Overheads 20 Percent 461.11 Total for 144 Sft. 2,766.68 Rate Per Sft 2766.68 x 100 = 1,921.31
144
Page 131
Detail Unit Rate (British System) per 100 Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00
Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00
Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00
144
Item Rates
Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45
Composite Rate Per 100 Sft Rs. 2,966.31 Say 2,966.30 Composite Rate Per Sqm Rs. 319.17 Say 319.20
Page 132
DESCRIPTION OF ITEM NO 43: a) Fixing door including chowkhat.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Mason 0.25 No 300.00 P. Day 75.00 Cooly 0.25 No 140.00 P. Day 35.00
Total 110.00 Sundries 10 Percent 11.00 Total 121.00
Contractor's Profit & Overheads 20 Percent 24.20 Total 145.20
Item Rates
Labour Rate for Each Rs. 145.20 Say 145.20
Page 133
Item No. 43 b) Fixing windows including chowkhat.
Detail Unit Rate (British System)per Each
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Mason 0.125 No 300.00 P. Day 37.50 Cooly 0.125 No 140.00 P. Day 17.50
Total 55.00 Sundries 10 Percent 5.50 Total 60.50
Contractor's Profit & Overheads 20 Percent 12.10 Total 72.60
Item Rates
Labour Rate for Each Rs. 72.60 Say 72.60
Page 134
DESCRIPTION OF ITEM NO 44: a) Glazing with panes 160Z to 180Z (454Gm to 512Gm) including cost of putty.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Detail of glass panes
Glass Panes 14.00 SftWastage 10% 1.40 Sft
15.40 Sft 12.00 Sft 184.80 Cost of Putty and nails L.S. 12.00
Total 196.80 Contractor's Profit & Overheads 20 Percent 39.36 Total for 14 Sft. 236.16 Rate Per Sft 236.16 = 16.87
14Labour
Glazier for cutting and fixing glass
panes including supplying front & back. 0.25 No 170.00 P. Day 42.50 Cooly Skilled 0.25 No 160.00 P. Day 40.00
Total 82.50 Sundries 10 Percent 8.25 Total 90.75
Contractor's Profit & Overheads 20 Percent 18.15 Total for 14 Sft. 108.90 Rate Per Sft 108.90 = 7.78
14
Item Rates
Labour Rate Per Sft Rs. 7.78 Say 7.80 Labour Rate Per Sqm Rs. 83.70 Say 83.70
Composite Rate Per Sft Rs. 24.65 Say 24.65 Composite Rate Per Sqm Rs. 265.20 Say 265.20
Page 135
Item No. 44 b) Glazing with panes 16 Oz. to 18 Oz. (454Gm to 512Gm) using deodar wooden fillets and putty.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Glass Panes 14.00 Sft 12.00 Sft 168.00 D. Wood 0.09 Cft 550.00 P. Cft 49.50 Cost of nails and putty. L.S. 12.00
Total 229.50 Contractor's Profit & Overheads 20 Percent 45.90 Total for 14 Sft. 275.40 Rate Per Sft 275.40 = 19.67
14Labour
Glazier for cutting and fixing glass
panes including supplying front & back. 0.25 No 170.00 P. Day 42.50 Cooly Skilled 0.25 No 160.00 P. Day 40.00 Cartpenter for 0.13 No 300.00 P. Day 39.00
Total 121.50 Sundries 10 Percent 12.15 Total 133.65
Contractor's Profit & Overheads 20 Percent 26.73 Total for 14 Sft. 160.38 Rate Per Sft 160.38 = 11.46
14
Item Rates
Labour Rate Per Sft Rs. 11.46 Say 11.45 Labour Rate Per Sqm Rs. 123.26 Say 123.25
Composite Rate Per Sft Rs. 31.13 Say 31.15 Composite Rate Per Sqm Rs. 334.93 Say 334.95
Page 136
DESCRIPTION OF ITEM NO 45: Glazing with glass panes 24 Oz. to 26 Oz. (680Gm to737Gm) using putty and deodar wooden fillets.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 15 Sft
putty and deodar wooden fillet.
Considering 5 Nos panes of average
size i.e. 5x18"x24" 15 Sft
Material
Glass Panes 15.00 SftWastage 10% 1.50 Sft
16.50 Sft 14.00 Sft 231.00 D. Wood for fillets 0.06 Cft 550.00 P. Cft 33.00 Cost of putty and nails L.S. 12.00
Total 276.00 Contractor's Profit & Overheads 20 Percent 55.20 Total for 15 Sft. 331.20 Rate Per Sft 331.20 = 22.08
15Labour
Glazier 0.38 No 170.00 P. Day 64.60 Cooly Skilled 0.38 No 160.00 P. Day 60.80 Cartpenter 0.13 No 300.00 P. Day 39.00 Cooly 0.13 No 140.00 P. Day 18.20
Total 182.60 Sundries 10 Percent 18.26 Total 200.86
Contractor's Profit & Overheads 20 Percent 40.17 Total for 15 Sft. 241.03 Rate Per Sft 241.03 = 16.07
15Item Rates
Labour Rate Per Sft Rs. 16.07 Say 16.05 Labour Rate Per Sqm Rs. 172.90 Say 172.90
Composite Rate Per Sft Rs. 38.15 Say 38.15 Composite Rate Per Sqm Rs. 410.48 Say 410.50
Page 137
DESCRIPTION OF ITEM NO 46:
a) Cutting to required sizes and fixing glass paneswith putty.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 14 Sft
Material
Cost of nails & putty L.S. 12.00
Total 12.00 Contractor's Profit & Overheads 20 Percent 2.40 Total for 14 Sft. 14.40 Rate Per Sft 14.40 = 1.03
14Labour
Glazier 0.20 No 170.00 P. Day 34.00 Cooly Skilled 0.15 No 160.00 P. Day 24.00
Total 58.00 Sundries 10 Percent 5.80 Total 63.80
Contractor's Profit & Overheads 20 Percent 12.76 Total for 14 Sft. 76.56 Rate Per Sft 76.56 = 5.47
14
Item Rates
Labour Rate Per Sft Rs. 5.47 Say 5.45 Labour Rate Per Sqm Rs. 58.84 Say 58.85
Composite Rate Per Sft Rs. 6.50 Say 6.50 Composite Rate Per Sqm Rs. 69.91 Say 69.90
Page 138
Item No. 46 b) Cutting to required sizes and fixing glass paneswith wooden fillets and putty.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for = 16 Sft
Material
Deodar wood for fillets 0.10 Cft 500.00 P. Cft 50.00 Putty and nails L.S. 12.00
Total 62.00 Contractor's Profit & Overheads 20 Percent 12.40 Total for 16 Sft. 74.40 Rate Per Sft 74.40 = 4.65
16Labour
Glazier 0.20 No 170.00 P. Day 34.00 Cooly Skilled 0.20 No 160.00 P. Day 32.00 Carpenter 0.10 No 300.00 P. Day 30.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00
Total 112.00 Sundries 10 Percent 11.20 Total 123.20
Contractor's Profit & Overheads 20 Percent 24.64 Total for 16 Sft. 147.84 Rate Per Sft 147.84 = 9.24
16
Item Rates
Labour Rate Per Sft Rs. 9.24 Say 9.25 Labour Rate Per Sqm Rs. 99.42 Say 99.40
Composite Rate Per Sft Rs. 13.89 Say 13.90 Composite Rate Per Sqm Rs. 149.46 Say 149.45
Page 139
DESCRIPTION OF ITEM NO 47: Glazing with plate glass ¼" (6mm) thick includingthe cost of deodar wood fillets and putty.
8.80 Sft 32.00 Sft 281.60 Deodar wood for fillets 0.05 Cft 500.00 P. Cft 25.00 Cost of nails and putty L.S. 12.00
Total 318.60 Contractor's Profit & Overheads 20 Percent 63.72 Total for 8 Sft. 382.32 Rate Per Sft 382.32 = 47.79
8Labour
Glazier 0.17 No 170.00 P. Day 28.90 Cooly Skilled 0.17 No 160.00 P. Day 27.20 Carpenter 0.06 No 300.00 P. Day 18.00 Cooly Skilled 0.06 No 160.00 P. Day 9.60
Total 83.70 Sundries 10 Percent 8.37 Total 92.07
Contractor's Profit & Overheads 20 Percent 18.41 Total for 8 Sft. 110.48 Rate Per Sft 110.48 = 13.81
8
Item Rates
Labour Rate Per Sft Rs. 13.81 Say 13.80 Labour Rate Per Sqm Rs. 148.60 Say 148.60
Composite Rate Per Sft Rs. 61.60 Say 61.60 Composite Rate Per Sqm Rs. 662.82 Say 662.80
Page 140
Item No. 47 b) Glazing exceeding 8 Sft (0.744M²)and not exceeding 24 Sft (2.230M²)
17.60 Sft 32.00 Sft 563.20 Deodar wood for fillets 0.10 Cft 500.00 P. Cft 50.00 Cost of nails and putty L.S. 26.40
Total 639.60 Contractor's Profit & Overheads 20 Percent 127.92 Total for 16 Sft. 767.52 Rate Per Sft 767.52 = 47.97
16Labour
Glazier 0.33 No 170.00 P. Day 56.10 Cooly Skilled 0.33 No 160.00 P. Day 52.80 Carpenter 0.13 No 300.00 P. Day 39.00 Cooly Skilled 0.13 No 160.00 P. Day 20.80
Total 168.70 Sundries 10 Percent 16.87 Total 185.57
Contractor's Profit & Overheads 20 Percent 37.11 Total for 16 Sft. 222.68 Rate Per Sft 222.68 = 13.92
16
Item Rates
Labour Rate Per Sft Rs. 13.92 Say 13.90 Labour Rate Per Sqm Rs. 149.75 Say 149.75
Composite Rate Per Sft Rs. 61.89 Say 61.90 Composite Rate Per Sqm Rs. 665.91 Say 665.90
Page 141
DESCRIPTION OF ITEM NO 48: Providing and fixing 1½" (40mm) thick deodarwood panelled or panelled and glazed, doors andwindows, with mild steel chowkhat (frame), etc.complete in all respects (excluding sliding bolt orlock) with :
i) M.S. angle iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. flat 2"x¼" (50x6mm)
Vertical Style 4x6'-8½"x4"x1½" 1.12 CftHorizontal Top 2x1'-11½"x4"x1½" 0.16 CftMiddle Top 2x1'-11½"x4"x1½" 0.16 CftLocal Top 2x1'-11½"x6"x1½" 0.24 CftBottom Top 2x1'-11½"x8"x1½" 0.32 Cft
Panells
2x16½"x23"x5/8" 0.24 Cft4x16½"x19½"x5/8" 0.47 Cft
Beading
2(16½+16½+23+23) 5/80.01 Cft
2x8
4(16½+16½+19½+19½) 5/80.02 Cft
2x82.74 Cft
Wastage 30% 0.82 Cft3.56 Cft 500.00 P. Cft 1,780.00
Horizontal l 1 x 4 = 4.00 Rft.
Wastage 5% 0.90 Rft.
(1½+2½) = 0.01
(1½+1½)
Page 142
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower bolt 9: (225mm) 3.00 Nos 27.00 Each 81.00 Handle 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber 2.00 Nos 4.00 Each 8.00 Hook & clamp 2.00 Nos 4.00 Each 8.00
Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P.Kg. 4.00 Spikes 0.13 Kg. 30.00 P.Kg. 3.99 Sawing charge 35.60 Sft 0.80 Sft 28.48
Total 2,843.09 Contractor's Profit & Overheads 20 Percent 568.62 Total for 27 Sft. 3,411.71 Rate Per Sft 3411.71 = 126.36
27Labour
Carpenter 2.40 Nos 300.00 P. Day 720.00 Cooly Skilled 1.80 Nos 160.00 P. Day 288.00 Welder 1.00 No 170.00 P. Day 170.00 Blacksmith 0.57 No 170.00 P. Day 96.90
Total 1,274.90 Sundries 10 Percent 127.49 Total 1,402.39
Contractor's Profit & Overheads 20 Percent 280.48 Total for 27 Sft. 1,682.87 Rate Per Sft 1682.87 = 62.33
27Item Rates
Labour Rate Per Sft Rs. 62.33 Say 62.35 Labour Rate Per Sqm Rs. 670.65 Say 670.65
Composite Rate Per Sft Rs. 188.69 Say 188.70 Composite Rate Per Sqm Rs. 2,030.29 Say 2,030.30
Page 143
Item No. 48 Providing and fixing 1½" (40mm) thick deodarwood panelled or panelled and glazed, doors andwindows, with mild steel chowkhat (frame), etc.complete in all respects (excluding sliding bolt orlock) with :
ii) M.S. Tee Iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. flat ½"x¼" (12x6mm).
55.31Lbs ( 25.10)Kg 22.00 P. Kg 552.20 Deodar Wood
Vertical Style 4x6'-8½"x4"x1½" 1.12 CftHorizontal Top 2x1'-11½"x4"x1½" 0.16 CftMiddle Top 2x1'-11½"x4"x1½" 0.16 CftLocal Top 2x1'-11½"x6"x1½" 0.24 CftBottom Top 2x1'-11½"x8"x1½" 0.32 Cft
Panells
2x16½"x23"x5/8" 0.24 Cft4x16½"x19½"x5/8" 0.47 Cft
Beading
2(16½+16½+23+23) 5/80.01 Cft
2x8
4(16½+16½+19½+19½) 5/80.02 Cft
2x82.74 Cft
Wastage 30% 0.82 Cft3.56 Cft 500.00 P. Cft 1,780.00
Horizontal 1x4 4 Rft
Wastage 5% 0.90 Rft
(1½+2½)
(1½+1½)
Page 144
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Fitting
Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower bolt 9: (225mm) 3.00 Nos 17.00 Each 51.00 Handle 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber 2.00 Nos 4.00 Each 8.00 Hook & clamp 2.00 Nos 4.00 Each 8.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P.Kg. 4.00 Spikes 0.13 Kg. 30.00 P.Kg. 3.99 Sawing charge 35.60 Sft 0.80 Sft 28.48
Total 2,576.59 Contractor's Profit & Overheads 20 Percent 515.32 Total for 27 Sft. 3,091.91 Rate Per Sft 3091.91 = 114.52
27Labour
Carpenter 2.40 Nos 300.00 P. Day 720.00 Cooly Skilled 1.80 Nos 160.00 P. Day 288.00 Welder 1.00 No 170.00 P. Day 170.00 Blacksmith 0.57 No 170.00 P. Day 96.90
Total 1,274.90 Sundries 10 Percent 127.49 Total 1,402.39
Contractor's Profit & Overheads 20 Percent 280.48 Total for 27 Sft. 1,682.87 Rate Per Sft 1682.87 = 62.33
27
Item Rates
Labour Rate Per Sft Rs. 62.33 Say 62.35 Labour Rate Per Sqm Rs. 670.65 Say 670.65
Composite Rate Per Sft Rs. 176.84 Say 176.85 Composite Rate Per Sqm Rs. 1,902.84 Say 1,902.85
Page 145
DESCRIPTION OF ITEM NO 49: Providing and fixing 1½" (40mm) thick hollow flushdoors and windows, with commercial ply (3mm) onboth faces of deodar wood shutter frame 1¼"(32mm) thick and partal wood braces at about 3"(76mm) apart and deodar wood lipping 1½"x3/8",(40x10mm) fixed with M.S. chowkhat (frame),including chromium plated fittings, etc. complete inall respects (without sliding bolt or lock)
a) M.S. Angle Iron 1½"x1½"x¼" welded with M.S.flat 2"x¼"
Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber chocks 1.00 No 4.00 Each 4.00 Hook & clamp 1.00 No 4.00 Each 4.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.75 Kg. 80.00 P.Kg. 60.00 Spikes 0.20 Kg. 30.00 P.Kg. 6.00 Sawing charge 21.70 Sft 0.80 Sft 17.36
Commercial Ply (3mm)
2x3'-11½"x6'-8¾" 53.38 SftWastage 15% 8.01 Sft
61.39 Sft 10.50 Sft 644.60 Total 2,740.80 Contractor's Profit & Overheads 20 Percent 548.16 Total for 27 Sft. 3,288.96 Rate Per Sft 3288.96 = 121.81
27Labour
Welder for making frame 1 No 170.00 Each 170.00 Black Smith 1 Nos 170.00 Each 170.00
For Panelling pressing and erecting door
Carpentre 1 Nos 300.00 P. Day 300.00 Skilled Cooly 1 No 160.00 P. Day 160.00
Total 800.00 Sundries 10 Percent 80.00 Total 880.00 Contractor's Profit & Overheads 20 Percent 176.00 Total for 27 Sft. 1,056.00 Rate Per Sft 1056.00 = 39.11
27Item Rates
Labour Rate Per Sft Rs. 39.11 Say 39.10 Labour Rate Per Sqm Rs. 420.84 Say 420.85
Composite Rate Per Sft Rs. 160.92 Say 160.90 Composite Rate Per Sqm Rs. 1,731.55 Say 1,731.55
Page 147
DESCRIPTION OF ITEM NO 49: Providing and fixing 1½" (40mm) thick hollow flushdoors and windows, with commercial ply (3mm) onboth faces of deodar wood shutter frame 1¼"(32mm) thick and partal wood braces at about 3"(76mm) apart and deodar wood lipping 1½"x3/8",(40x10mm) fixed with M.S. chowkhat (frame),including chromium plated fittings, etc. complete inall respects (without sliding bolt or lock)
b) M.S. Tee Iron 1½"x1½"x¼" welded with M.S.flat ½"x¼"
Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber chocks 1.00 No 4.00 Each 4.00 Hook & clamp 1.00 No 4.00 Each 4.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.75 Kg. 80.00 P.Kg. 60.00 Spikes 0.20 Kg. 30.00 P.Kg. 6.00 Sawing charge 21.70 Sft 0.80 Sft 17.36
Commercial Ply (3mm)
2x3'-11½"x6'-8¾" 53.38 SftWastage 15% 8.01 Sft
61.39 Sft 10.50 Sft 644.60 Total 2,521.68 Contractor's Profit & Overheads 20 Percent 504.34 Total for 27 Sft. 3,026.02 Rate Per Sft 3026.02 = 112.07
27Labour
Welder for making frame 1 No 170.00 Each 170.00 Black Smith 1 Nos 170.00 Each 170.00
For Rendring & Erection Door
Carpentre 1 Nos. 300.00 P. Day 300.00 Skilled Cooly 1 No. 160.00 P. Day 160.00
Total 800.00 Sundries 10 Percent 80.00 Total 880.00 Contractor's Profit & Overheads 20 Percent 176.00 Total for 27 Sft. 1,056.00 Rate Per Sft 1056.00 = 39.11
27Item Rates
Labour Rate Per Sft Rs. 39.11 Say 39.10 Labour Rate Per Sqm Rs. 420.84 Say 420.85
Composite Rate Per Sft Rs. 151.19 Say 151.20 Composite Rate Per Sqm Rs. 1,626.76 Say 1,626.75
Page 149
DESCRIPTION OF ITEM NO 50: Providing and fixing 1½" (40mm) thick solid flushdoor shutter sterling or equivalent with commercialply (5mm thick) on both sides double pressed anddeodar wood lipping 1½"x3/8" (40x10mm) aroundshutter including chromium plated fittings, ironhinges with aluminium kick plate 22SWG on bothsides & finger plate complete in all respects.
Remarks : If C.I. finger plate and kick plate are notprovided/ fixed the composite rate will be reducedby Rs. 7.60 Per Sft (81.76M²).
Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt C.P. 2.00 Nos 30.00 Each 60.00 C.P. Handle best quality 2.00 Nos 10.50 Each 21.00 Door stopper 1.00 No 12.00 Each 12.00 C.P. finger plate with screws 1.00 No 80.00 Each 80.00 Kick plate 22 SWG on both sides 2.00 Nos 30.00 Each 60.00
Total 2,820.40 Contractor's Profit & Overheads 20 Percent 564.08 Total for 24.5 Sft. 3,384.48 Rate Per Sft 3384.48 = 138.14
24.5
Page 150
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
For planning & fixing of lipping with
door fitting complete.
Carpentre 1.00 No 300.00 P. Day 300.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00
Total 460.00 Sundries 10 Percent 46.00 Total 506.00
Contractor's Profit & Overheads 20 Percent 101.20 Total for 24.5 Sft. 607.20 Rate Per Sft 607.20 = 24.78
24.5
Item Rates
Labour Rate Per Sft Rs. 24.78 Say 24.80 Labour Rate Per Sqm Rs. 266.67 Say 266.65
Composite Rate Per Sft Rs. 162.93 Say 162.95 Composite Rate Per Sqm Rs. 1,753.08 Say 1,753.10
Page 151
DESCRIPTION OF ITEM NO 51: Providing and fixing panelled door of M.S. Sheetwith forged door leaves of M.S. Sheet 22 SWG fittedin hollow frame chowkhat 3"x4½" (76x114mm)made of M.S. sheet 18 SWG, filled with plain cementconcrete 1:3:6 etc. complete, with all fittings andhammer painting, including carriage to site andfixing in position.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4' x 7' = 28 Sft
Material
M.S. Sheet 18 SWG
for chowkhat
18¾'x15" 23.44 SftWastage 20% 4.69 Sft
28.13 Sft 40.00 Sft 1,125.20 M.S. Sheet 22 SWG
for shutter
26½x7 1/8 31.50 SftWastage 20% 6.30 Sft
37.80 Sft 32.00 Sft 1,209.60 M.S. Flat 1"x1/16" (25x2mm)
6'-9½"x0.21 1.43Lb (0. 65) Kg 22.00 P. Kg 14.30
Fitting
Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Screws L.S. 4.00 Welding electrode 4.00 Nos 2.01 Each 8.02 Electricity Charges L.S. 16.00
Cement concrete (1:3:6)
Cement 0.21 Bag 230.00 Each 48.30 Sand 0.76 Cft 3.50 P. Cft 2.66 Bagri 1.52 Cft 18.50 P. Cft 28.12
Total 2,605.80 Contractor's Profit & Overheads 20 Percent 521.16 Total for 28 Sft. 3,126.96 Rate Per Sft 3126.96 = 111.68
28
Page 152
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Welder 0.50 No 170.00 P. Day 85.00 Blacksmith 2.50 Nos 170.00 P. Day 425.00 Mason 0.25 No 300.00 P. Day 75.00 Coolies 0.75 No 140.00 P. Day 105.00
Total 690.00 Sundries 10 Percent 69.00 Total 759.00
Contractor's Profit & Overheads 20 Percent 151.80 Total for 28 Sft. 910.80 Rate Per Sft 910.80 = 32.53
28
Item Rates
Labour Rate Per Sft Rs. 32.53 Say 32.55 Labour Rate Per Sqm Rs. 350.01 Say 350.00
Composite Rate Per Sft Rs. 144.21 Say 144.20 Composite Rate Per Sqm Rs. 1,551.65 Say 1,551.65
Page 153
DESCRIPTION OF ITEM NO 52: Providing and laying 24 SWG aluminium kickplate 4" (100mm) high fixed with screws 4"(100mm) Centre to Centre on bottom rail of flushdoors only. of commercial ply.
Detail Unit Rate (British System) per Rft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 4 Rft
Material
Aluminium plate 4" (100mm) wide
and 24 SWG 0.18 Kg 96.00 P. Kg 17.28
Total 17.28 Contractor's Profit & Overheads 20 Percent 3.46 Total for 4 Rft. 20.74 Rate Per Rft 20.74 = 5.18
4Labour
Carpenter 0.12 No 300.00 P. Day 36.00
Total 36.00 Sundries 10 Percent 3.60 Total 39.60
Contractor's Profit & Overheads 20 Percent 7.92 Total for 4 Rft. 47.52 Rate Per Rft 47.52 = 11.88
4
Item Rates
Labour Rate Per Rft Rs. 11.88 Say 11.90 Labour Rate Per Rm Rs. 38.97 Say 38.95
Composite Rate Per Rft Rs. 17.06 Say 17.05 Composite Rate Per Rqm Rs. 55.97 Say 55.95
Page 154
DESCRIPTION OF ITEM NO 53: Providing and fixing curtain railing to doors andwindows, comprising of TOSO-elite Japan madesuperior type of railing or equivalent, fixed over 4"x¾" (100x20mm) deodar wood strip, includingpainting.
Detail Unit Rate (British System) per Rft
Qty RatePer Unit (Rs.) Amount (Rs.)
Material
Rate For 10 Rft
Railing 10.00 Rft 9.00 P. Rft 90.00 Cutting of Railing 5.29 Screws 1.00 Dozen 1.68 P, Doz 1.68 Guttis 6.00 Nos 0.25 Each 1.50 Deodar wood 0.21 Cft 550.00 P. Cft 115.50
Total 213.97 Contractor's Profit & Overheads 20 Percent 42.79 Total for 10 Rft. 256.77
Material Rate Per Rft. 256.77 = 25.68 10
Labour
Rate For 80 Rft
Carpenter 1.00 No 300.00 P. Day 300.00
Total 300.00 Sundries 10 Percent 30.00 Total 330.00
Contractor's Profit & Overheads 20 Percent 66.00 Total 396.00 Rate Per Sft 396.00 = 4.95
80
Item Rates
Labour Rate Per Rft Rs. 4.95 Say 4.95 Labour Rate Per Rm Rs. 16.24 Say 16.25
Composite Rate Per Rft Rs. 30.63 Say 30.65 Composite Rate Per Rm Rs. 100.46 Say 100.45
Page 155
DESCRIPTION OF ITEM NO 54: Providing and fixing M.S. flat ½"1/8" (12x3mm)grill including ¾"x1/8" (20x3mm) M.S. Flat Frameof windows of approved design including painting 3coat complete in all respect.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 2½ x 3½ = 8.75 Sft
Material
M.S. Flat Frame for Grill ¾"x1/8"
(20x3mm)
2½'+3½'+2½'+3½' 12 Sft
@ 0.32 Lbs/Rft 3.84 Lbs (1 .88)Kg 22.00 P. Kg 41.36 M.S. Flat ½"x1/8" (12x3mm)
72.45Lb (7.0 )Kg 22.00 P. Kg 154.00 @ 0.21 lbs/rft 15.21 lbs
Hold fast 6" (150mm) long 6.00 Nos 12.00 Each 72.00 Electrical Charges L.S. 5.00 Electrod 0.33 Pkt 360.00 Pkt 21.12 Paint 0.098Lb (0. 08) Gl 450.00 P. Gl 44.10
Total 337.58 Contractor's Profit & Overheads 20 Percent 67.52 Total for 100 Sft. 405.10 Rate Per Sft 405.10 = 46.30
8.75
Page 156
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Welder 0.17 Nos 170.00 P. Day 28.90 Blacksmith 0.17 No 170.00 P. Day 28.90 Masson 0.20 Nos 300.00 P. Day 60.00 Painter 0.09 No 170.00 P. Day 15.30
Total 133.10 Sundries 10 Percent 13.31 Total 146.41
Contractor's Profit & Overheads 20 Percent 29.28 Total for 100 Sft. 175.69 Rate Per Sft 175.69 = 20.08
8.75
Item Rates
Labour Rate Per Sft Rs. 20.08 Say 20.10 Labour Rate Per Sqm Rs. 216.05 Say 216.05
Composite Rate Per Sft Rs. 66.38 Say 66.40 Composite Rate Per Sqm Rs. 714.20 Say 714.20
Page 157
DESCRIPTION OF ITEM NO 55: Providing and fixing G.I. Wire gauge 22 SWG12x12 meshes per Sq Inch (625mm) fixed to steelwindow complete with flat iron putti ½"x1/8"(12x3mm) and machine made screws.
13.20 Sft 6.00 Sft 79.20 Flat Iron ½"x1/8" (12x3mm)
3+3+4+4+4 18.00 Rft
18.90 Rft @ 0.21 Lbs/Rft 4 Lbs (1. 82) Kg 22.00 P. Kg 40.04 Screws 6.70 Dozen 1.68 P. Doz 11.26
Total 130.50 Contractor's Profit & Overheads 20 Percent 26.10 Total for 100 Sft. 156.60 Rate Per Sft 156.60 = 13.05
12
Labour Rate for 55 Sft.
Blacksmith 1.00 No 170.00 P. Day 170.00 Skilled Cooly 0.40 No 160.00 P. Day 64.00
Total 234.00 Sundries 10 Percent 23.40 Total 257.40 Contractor's Profit & Overheads 20 Percent 51.48 Total for 100 Sft. 308.88 Rate Per Sft 308.88 = 5.62
55Item Rates
Labour Rate Per Sft Rs. 5.62 Say 5.60 Labour Rate Per Sqm Rs. 60.43 Say 60.45
Composite Rate Per Sft Rs. 18.67 Say 18.65 Composite Rate Per Sqm Rs. 200.84 Say 200.85
Wastage 5% 0.90 Rft
Page 158
DESCRIPTION OF ITEM NO 56: Providing and fixing wooden moulding stopper2½"x5/8" (63x16mm) on door frame fitted with plyof approved quality complete in all respect.
0.22 Cft 500.00 P. Cft 110.00 Glue 0.26 Kg. 80.00 P. Cft 20.80 Nails 0.116 Kg. 43.00 P. Cft 4.99
Total 135.79 Contractor's Profit & Overheads 20 Percent 27.16 Total for 16 Sft. 162.95 Rate Per Sft 162.95 = 10.18
16Labour
Labour for sawing, planning and fixing
16 Rft (4.876Rm) moulding in position
carpenter. 0.50 No 300.00 P. Day 150.00
Total 150.00 Sundries 10 Percent 15.00 Total 165.00
Contractor's Profit & Overheads 20 Percent 33.00 Total for 16 Sft. 198.00 Rate Per Sft 198.00 = 12.38
16
Item Rates
Labour Rate Per Sft Rs. 12.38 Say 12.40 Labour Rate Per Sqm Rs. 133.16 Say 133.15
Composite Rate Per Sft Rs. 22.56 Say 22.55 Composite Rate Per Sqm Rs. 242.74 Say 242.75
Page 160
DESCRIPTION OF ITEM NO 57: Providing and fixing deodar wood dolly framehaving 1½"x1½" (40x40mm) vertical andhorizontal double posts with 1½"x½" (40x40mm)full width of jamb braces at 12" (300mm)including filling of hollow space in between braceswith 1:3:6 P.C.C. fixing of ply of approvedquality there upon & hold fasts complete in allrespects.
0.90 Cft 48.53 P. Cft 43.68 Teak Wood Ply 17.25 x 0.75 12.94 SftWastage 10% 1.29 Sft
14.23 Sft 19.50 Sft 277.49 Glue 0.29 Kg. 80.00 P. Cft 23.20 Nails 0.116 Kg. 43.00 P. Cft 4.99 Hold fast 4.00 Nos 12.00 Each 48.00
Total 867.35 Contractor's Profit & Overheads 20 Percent 173.47 Total for 13 Sft. 1,040.82 Rate Per Sft 1040.82 = 80.06
13
Page 161
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Labour
Carpenter 0.50 No 300.00 P. Day 150.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00
Total 230.00 Sundries 10 Percent 23.00 Total 253.00
Contractor's Profit & Overheads 20 Percent 50.60 Total for 13 Sft. 303.60 Rate Per Sft 303.60 = 23.35
13
Item Rates
Labour Rate Per Sft Rs. 23.35 Say 23.35 Labour Rate Per Sqm Rs. 251.29 Say 251.30
Composite Rate Per Sft Rs. 103.42 Say 103.40 Composite Rate Per Sqm Rs. 1,112.77 Say 1,112.75
Page 162
Item No. 57 Providing and fixing deodar wood dolly frame having1½"x1½" (40x40mm) vertical and horizontal double postswith 1½"x½" (40x40mm) full width of jamb braces at 12"(300mm) including filling of hollow space in betweenbraces with 1:3:6 P.C.C. fixing of ply of approved qualitythere upon & hold fasts complete in all respects.
b) With Commercial Ply.
Detail Unit Rate (British System) per Sft
Qty RatePer Unit (Rs.) Amount (Rs.)
Rate Analysis for 13 Sft
Deodar wood 0.94 Cft 500.00 P. Cft 470.00 PCC (1:3:6) 0.90 Cft 48.84 P. Cft 43.96 Commercial ply 14.23 Sft 10.50 P. Sft 149.42 Glue 0.29 Kg. 80.00 P. Cft 23.20 Nails 0.116 Kg. 43.00 P. Cft 4.99 Hold fast L.S. 40.00 Total 731.56 20 Percent 146.31 Total 877.87 Contractor's Profit & Overheads 20 Percent Total for 13 Sft. 877.87 Rate Per Sft 877.87 = 67.53
13Labour
Carpenter 0.50 No 300.00 P. Day 150.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00
Total 230.00 Sundries 10 Percent 23.00 Total 253.00 Contractor's Profit & Overheads 20 Percent 50.60 Total for 13 Sft. 303.60 Rate Per Sft 303.60 = 23.35
13Item Rates
Labour Rate Per Sft Rs. 23.35 Say 23.35 Labour Rate Per Sqm Rs. 251.29 Say 251.30
Composite Rate Per Sft Rs. 90.88 Say 90.90 Composite Rate Per Sqm Rs. 977.89 Say 977.90
Page 163
DESCRIPTION OF ITEM NO 58: Providing and fixing ornamental woodenarchitrave 3"x½" (75x12mm) tapered to ¼"(6mm) all along the door frame complete in allrespects.
Total 123.00 Contractor's Profit & Overheads 20 Percent 24.60 Total for 24.50 Sft. 147.60 Rate Per Sft 147.60 = 6.02
24.50Labour
Carpenter 0.25 No 300.00 P. Day 75.00 Fixing in position L.S. 14.93
Total 89.93 Sundries 10 Percent 8.99 Total 98.93 Contractor's Profit & Overheads 20 Percent 19.79 Total for 24.50 118.71 Rate Per Sft 118.71 = 4.85
24.50Item Rates
Labour Rate Per Sft Rs. 4.85 Say 4.85 Labour Rate Per Sqm Rs. 52.14 Say 52.15
Composite Rate Per Sft Rs. 10.87 Say 10.85 Composite Rate Per Sqm Rs. 116.96 Say 116.95
Page 165
Item No. 58 Providing and fixing vin board cabinet in kitchen i/c termite proofing and polishing / painting with synthetic enamel as specific with handle and draws screw complete in all respects as per drawing