Top Banner
Page 1 CHAPTER NO. 12 WOOD WORK DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed in position including cost of nails a) Deodar Wood. Detail Unit Rate (British System) pe Qty Rate Per Unit (Rs.) Material Deodar Wood including wastage (II Class) 1.15 Cft 500.00 P. Cft Nail 0.020 Kg. 43.00 P. Cft Screws above 1" long 1.00 Dozen 3.25 P.Doz Total Contractor's Profit & Overhead 20 Percent Total Labour Carpentre 0.63 No 300.00 P. Day Cooly Skilled 0.25 No 160.00 P. Day Total Sundries 10 Percent Total Contractor's Profit & Overhead 20 Percent Total Item Rates Labour Rate Per Cft Rs. 302.28 Say Labour Rate Per Cum Rs. ### Say Composite Rate Per Cft Rs. 997.21 Say Composite Rate Per Cum Rs. ### Say
332

Rate analsis Chapter No. 12 (Wood Work)

Nov 19, 2014

Download

Documents

M HAFEEZ RAJA
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Rate analsis Chapter No. 12 (Wood Work)

Page 1

CHAPTER NO. 12

WOOD WORK

DESCRIPTION OF ITEM NO. 1: Plain wood work sawn wrought planed & fixedin position including cost of nails & screws etc.

a) Deodar Wood.

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Deodar Wood including wastage (II Class) 1.15 Cft 500.00 P. Cft 575.00 Nail 0.020 Kg. 43.00 P. Cft 0.86 Screws above 1" long 1.00 Dozen 3.25 P.Doz 3.25

Total 579.11 Contractor's Profit & Overheads 20 Percent 115.82 Total 694.93

Labour

Carpentre 0.63 No 300.00 P. Day 189.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00

Total 229.00 Sundries 10 Percent 22.90 Total 251.90

Contractor's Profit & Overheads 20 Percent 50.38 Total 302.28

Item Rates

Labour Rate Per Cft Rs. 302.28 Say 302.30 Labour Rate Per Cum Rs. ### Say 10,676.55

Composite Rate Per Cft Rs. 997.21 Say 997.20 Composite Rate Per Cum Rs. ### Say 35,221.55

Page 2: Rate analsis Chapter No. 12 (Wood Work)

Page 2

Item No. 1 Plain wood work sawn wrought planed & fixedin position including cost of nails & screws etc.

b) Shisham Wood

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Shisham wood including 15% wastage 1.15 Cft 300.00 P. Cft 345.00 Nail 0.023 Kg. 43.00 P. Cft 0.99 Screws above 1" long 1.00 Dozen 3.25 P.Doz 3.25

Total 349.24 Contractor's Profit & Overheads 20 Percent 69.85 Total 419.09

Labour for 1.50 Cft.

Carpenters 1.00 No 300.00 P. Day 300.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60 Labour for 1 Cft. 334.40

Item Rates

Labour Rate Per Cft Rs. 334.40 Say 334.40 Labour Rate Per Cum Rs. ### Say 11,811.00

Composite Rate Per Cft Rs. 753.49 Say 753.50 Composite Rate Per Cum Rs. ### Say 26,613.15

Page 3: Rate analsis Chapter No. 12 (Wood Work)

Page 3

DESCRIPTION OF ITEM NO. 2: Plain wood work for regulation karries orneedles etc. including sawing plainingwroughting wood providing & fixing steel partsof karries i.e. end strips and rods etc.

a) Deodar Wood.

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

i) Deodar Wood

5.5x5/12x5/12 = 0.97 0.97 CftWastage 15% 0.15 Cft

1.12 Cft 500.00 P. Cft 560.00 ii) 1.6' (480mm) long iron strip 1½"

(37mm) wide x1/8" (3mm) thick @

0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs2 Nox1¼' (380mm) long iron bars

¾" Ø (20mm) on both ends @ 1.502

Lbs/ft. (2.235 Kg/m). 3.80 Lbs5.80 Lbs

Wastage 5% 0.29 Lbs6.09Lb (2 .76)Kg 28.00 P. Kg 77.28

iii) Iron Screw 1" (25mm) long 1.00 Dozen 1.68 P. Doz 1.68

Total 638.96 Contractor's Profit & Overheads 20 Percent 127.79 Total 766.75

Page 4: Rate analsis Chapter No. 12 (Wood Work)

Page 4

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.32 No 300.00 P. Day 96.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00

Total 136.00 Sundries 10 Percent 13.60 Total 149.60

Contractor's Profit & Overheads 20 Percent 29.92 Total 179.52

Item Rates

Labour Rate Per Cft Rs. 179.52 Say 179.50 Labour Rate Per Cum Rs. 6,340.65 Say 6,340.65

Composite Rate Per Cft Rs. 946.27 Say 946.25 Composite Rate Per Cum Rs. ### Say 33,422.35

Page 5: Rate analsis Chapter No. 12 (Wood Work)

Page 5

Item No. 2 Plain wood work for regulation karries or needlesetc. including sawing plaining wroughting wood,providing & fixing steel parts of karries i.e. endstrips and rods etc.

b) Shisham Wood

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

i) Shisham Wood

5.5x5/12x5/12 = 0.97 0.97 CftWastage 15% 0.15 Cft

1.12 Cft 300.00 P. Cft 336.00 ii) Iron Strip

1.6' (480mm) long iron strip 1½"

(37mm) wide x1/8" (3mm) thick @

0.625 Lbs/ft. (0.930 Kg/Mtr). 2.00 Lbs2 Nox1¼' (380mm) long iron bars

¾" Ø (20mm) on both ends @ 1.502

Lbs/ft. (2.235 Kg/m). 3.80 Lbs5.80 Lbs

Wastage 5% 0.29 Lbs6.09Lb (2 .76)Kg 28.00 P. Kg 77.28

iii) Iron Screw 1" (25mm) long 1.00 Dozen 1.68 P. Doz 1.68

Total 414.96 Contractor's Profit & Overheads 20 Percent 82.99 Total 497.95

Page 6: Rate analsis Chapter No. 12 (Wood Work)

Page 6

Detail Unit Rate (British System) per Cft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.32 No 300.00 P. Day 96.00 Cooly Skilled 0.25 No 160.00 P. Day 40.00

Total 136.00 Sundries 10 Percent 13.60 Total 149.60

Contractor's Profit & Overheads 20 Percent 29.92 Total 179.52

Item Rates

Labour Rate Per Cft Rs. 179.52 Say 179.50 Labour Rate Per Cum Rs. 6,340.65 Say 6,340.65

Composite Rate Per Cft Rs. 677.45 Say 677.45 Composite Rate Per Cum Rs. ### Say 23,927.60

Page 7: Rate analsis Chapter No. 12 (Wood Work)

Page 7

DESCRIPTION OF ITEM NO 3: First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhat holdfast tower bolts, chocks rubber stop, cleats/G.I.clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).

i) 2" (50mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood

Frame

Top Rail 4¾'x3"x4½" 0.45 CftVertical 2x7'x3"x4½" 1.33 CftVertical Style 4x6'-6½"x4"x2" 1.46 CftHorizental Rail 2x1'-10"x4"x2" 0.20 CftMiddle Rail 2x1'-10"x6"x2" 0.20 CftLock Rail 2x1'-10"x6"x2" 0.31 CftBottom Rail 2x1'-10"x8"x2" 0.42 Cft

Panells

2x14"x22"x¾" 0.27 Cft4x14"x18.5"x¾" 0.45 Cft

Beading

2(14"+14"+22"+22")x5/8" 0.02 Cft

2x8

4(14"+14"+18½"+18½")5/8" 0.02 Cft

2x85.13 Cft

Wastage 12% 0.62 Cft5.75 Cft 1400.00 P. Cft 8,050.00

(1½ + 2½)

(1½ + 2½)

Page 8: Rate analsis Chapter No. 12 (Wood Work)

Page 8

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00

Total 8,243.92 Contractor's Profit & Overheads 20 Percent 1,648.78 Total for 27 Sft. 9,892.71

Rate Per Sft 9892.71 = 366.40 27

Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Cooly Unskilled 1.25 Nos 140.00 P. Day 175.00

Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50

Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00

Rate Per Sft 1419.00 = 52.56 27

Item Rates

Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50

Composite Rate Per Sft Rs. 418.95 Say 418.90 Composite Rate Per Sqm Rs. 4,507.87 Say 4,507.85

Page 9: Rate analsis Chapter No. 12 (Wood Work)

Page 9

Item No. 3 First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhathold fast tower bolts, chocks rubber stop, cleats/G.I. clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).

ii) 1¾" (45mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood

Frame

Top Rail 4¾'x3"x4½" 0.45 CftVertical 2x7'x3"x4½" 1.33 CftVertical Style 4x6'-6½"x4"x1¾" 1.25 Cft

Horizontal Rail

Top 2x1'-10"x4"x1¾" 0.18 CftMiddle 2x1'-10"x4"x1¾" 0.18 CftLock 2x1'-10"x6"x1¾" 0.27 CftBottom 2x1'-10"x8"x1¾" 0.36 Cft

Panels

2x14"x22"x¾" 0.27 Cft4x14"x18.5"x¾" 0.44 Cft

Beading

2(14"x14"x22"+22")x5/8" 0.01 Cft

2x8

4(14"+14"+18.5"+18.5")5/8" 0.02 Cft

2x84.76 Cft

Wastage 12% 0.57 Cft5.33 Cft 1400.00 P. Cft 7,462.00

(1½ + 2½)

(1½ + 2½)

Page 10: Rate analsis Chapter No. 12 (Wood Work)

Page 10

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting 7,462.00

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00

Total 7,655.92 Contractor's Profit & Overheads 20 Percent 1,531.18 Total for 27 Sft. 9,187.11

Rate Per Sft 9187.11 = 340.26 27

Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Cooly Unskilled 1.25 Nos 140.00 P. Day 175.00

Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50

Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00

Rate Per Sft 1419.00 = 52.56 27

Item Rates

Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50

Composite Rate Per Sft Rs. 392.81 Say 392.80 Composite Rate Per Sqm Rs. 4,226.67 Say 4,226.65

Page 11: Rate analsis Chapter No. 12 (Wood Work)

Page 11

Item No. 3 First class teak wood wrought joinery in door &windows etc. panelled, panelled and glazed or fullyglazed & fixed in position including chowkhathold fast tower bolts, chocks rubber stop, cleats/G.I. clamps, chords with hooks, nails screws etc.complete (Excluding sliding bolt and lock).

iii) 1½" (37mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood for Frame

Frame

Top Rail 1x4¾'x3"x4½" 0.45 CftVertical 2x7'x3"x4½" 1.33 CftVertical style 4x6'-6½"x4"x1½" 1.08 Cft

Leaves

Top Rail 2x1'-10"x4"x1½" 0.15 CftMiddle 2x1'-10"x4"x1½" 0.15 CftLock 2x1'-10"x6"x1½" 0.23 CftBottom 1x1'-10"x8"x1½" 0.30 Cft

Panels

2x14"x22"x5/8" 0.23 Cft4x14"x18.5"x5/8" 0.44 Cft

Beading

2(14"x14"x22"+22")x5/8" 0.01 Cft

2x8

4(14"+14"+18.5"+18.5")5/8" 0.02 Cft

2x84.39 Cft

Wastage 12% 0.53 Cft4.92 Cft 1400.00 P. Cft 6,888.00

(1½ + 2½)

(1½ + 2½)

Page 12: Rate analsis Chapter No. 12 (Wood Work)

Page 12

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

6,888.00 Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00

Total 7,081.92 Contractor's Profit & Overheads 20 Percent 1,416.38 Total for 27 Sft. 8,498.31

Rate Per Sft 8498.31 = 314.75 27

Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Unskilled Cooly 1.25 Nos 140.00 P. Day 175.00

Total 1,075.00 Sundries 10 Percent 107.50 Total 1,182.50 Contractor's Profit & Overheads 20 Percent 236.50 Total for 27 Sft. 1,419.00

Rate Per Sft 1419.00 = 52.56 27

Item Rates

Labour Rate Per Sft Rs. 52.56 Say 52.55 Labour Rate Per Sqm Rs. 565.50 Say 565.50

Composite Rate Per Sft Rs. 367.31 Say 367.30 Composite Rate Per Sqm Rs. 3,952.23 Say 3,952.25

Page 13: Rate analsis Chapter No. 12 (Wood Work)

Page 13

DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inchs (625mm) including brass fitting sash bars etc. complete :

a) Teak wood framing 1¾" (45mm) thick with wiregauze fixed in position:

i) Without spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood

Top Rail 1x4'x3"x½" 0.04 CftVertical 2x7'x3"x½" 0.15 CftFillet 2(15½"+15½"+25"+25")1½"x3/8" 0.02 CftFillet 2(15½"+15½"+19"+19")x½"x3/8" 0.03 Cft

Leaf

Vertical Style 4x6'-6½"x4"x1¾" 1.27 Cft

Horizontal

Top 2x1'-10½"x1½"x1¾" 0.06 CftMiddle 2x1'-10½"x3"x1¾" 0.07 CftLock 2x1'-10½"x6"x1¾" 0.27 CftBottom 2x1'-10½"x6"x1¾" 0.27 Cft

2.18 CftWastage 10% 0.22 Cft

2.40 Cft 1400.00 P. Cft 3,360.00

Page 14: Rate analsis Chapter No. 12 (Wood Work)

Page 14

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting 3,360.00

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50

Wire Gauze

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.90

Total 3,536.00 Contractor's Profit & Overheads 20 Percent 707.20 Total for 27 Sft 4,243.20

Rate Per Sft 4243.20 = 157.16 27

Labour

Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft 250.80 Rate Per Sft 250.80 = 9.29

27Item Rates

Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95

Composite Rate Per Sft Rs. 166.44 Say 166.45 Composite Rate Per Sqm Rs. 1,790.94 Say 1,790.95

Page 15: Rate analsis Chapter No. 12 (Wood Work)

Page 15

DESCRIPTION OF ITEM NO 4: First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sash bars etc. complete :

a) Teak wood framing 1¾" (45mm) thick with wiregauze fixed in position:

ii) With spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood

Top Rail 1x4'x3"x½" 0.04 CftVertical 2x7'x3"x½" 0.15 CftFillet 2(15½"+15½"+25"+25")1½"x3/8" 0.02 CftFillet 2(15½"+15½"+19"+19")1½"x3/8" 0.03 Cft

Leaf

Vertical Style = 4'x6'-6½"x4"x1¾" 1.27 Cft

Horizontal

Top 2x1'-10½"x1½"x1¾" 0.06 CftMiddle 2x1'-10½"x3"x1¾" 0.07 CftLock 2x1'-10½"x6"x1¾" 0.27 CftBottom 2x1'-10½"x6"x1¾" 0.27 Cft

2.18 CftWastage 10% 0.22 Cft

2.40 Cft 1400.00 P. Cft 3,360.00

Page 16: Rate analsis Chapter No. 12 (Wood Work)

Page 16

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.00 Doz 3.25 P. Doz 6.50 Spring Hings 2.00 Nos 44.00 Each 88.00

Wire Gauze

2x1'-2"x2'-1" = 4.83 Sft4x1'-2"x1'-7" = 7.33 Sft

12.16 SftWastage 10% 1.22 Sft

13.38 Sft 6.00 Sft 80.28

Total 3,620.38 Contractor's Profit & Overheads 20 Percent 724.08 Total for 27 Sft. 3,986.80 Rate Per Sft 3986.80 = 147.66

27Labour

Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total 250.80 Rate Per Sft 250.80 = 9.29

27Item Rates

Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95

Composite Rate Per Sft Rs. 156.95 Say 156.95 Composite Rate Per Sqm Rs. 1,688.76 Say 1,688.75

Page 17: Rate analsis Chapter No. 12 (Wood Work)

Page 17

Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:

b) Teak wood framing 1½" (40mm) thick with wiregauze fixed in position.

i) Without spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Ist Class Teak Wood

Vertical Style 4x6'-6½"x4"x1½" 1.09 Cft

Horizontal

Top Rail 2x1-10½"x3"x1½" 0.12 CftMiddle 2x1-10½"x1½"x1½" 0.06 CftLock 2x1'-10½"x6"x1½" 0.24 CftBottom 2x1'-10½"x6"x1½" 0.24 CftFillet 2(15½"+15½"+25"+25")½"x3/8" 0.02 CftFillet 2(15½"+15½"+19"+19")½"x3/8" 0.03 CftTop Rail 1x4'x3"x½" 0.05 CftVertical Rail 2x7'x3"x½" 0.15 Cft

2.00 CftWastage 10% 0.20 Cft

2.20 Cft 1400.00 P. Cft 3,080.00 Fitting

Hinges 4" (100mm) 6 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2 Nos 17.00 Each 34.00 Handles 6" (150mm) 2 Nos 8.00 Each 16.00 Hook & Clamps 2 Nos 4.00 Each 8.00 Screws / Nail 2 Doz 3.25 P. Doz 6.50

Page 18: Rate analsis Chapter No. 12 (Wood Work)

Page 18

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauze

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 3,255.98 Contractor's Profit & Overheads 20 Percent 651.20 Total for 27 Sft. 3,907.18

Rate Per Sft 3907.18 = 144.71 27

Labour

Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00

Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80

Rate Per Sft 250.80 = 9.29 27

Item Rates

Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95

Composite Rate Per Sft Rs. 154.00 Say 154.00 Composite Rate Per Sqm Rs. 1,657.03 Say 1,657.05

Page 19: Rate analsis Chapter No. 12 (Wood Work)

Page 19

Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:

b) Teak wood framing 1½" (40mm) thick with wiregauze fixed in position.

ii) With spring or spring hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Ist Class Teak Wood

Vertical Style 4x6-6½"x4"x1½" 1.09 Cft

Horizontal

Top Rail 2x1'-10½"x3"x1½" 0.12 CftMiddle 2x1'-10½"x1½"x1½" 0.06 CftLock 2x1'-10½"x6"x1½" 0.24 CftBottom 2x1'-10½"x6"x1½" 0.24 CftFillet 2(15½"+15½"+25"+25")½"x3/8" 0.02 CftFillet 2(15½"+15½"+19"+19")½"x3/8" 0.03 CftTop Rail 1x4'x3"x½" 0.05 CftVertical Rail 2x7'x3"x½" 0.15 Cft

2.00 CftWastage 10% 0.20 Cft

2.20 Cft 1400.00 P. Cft 3,080.00 Fitting

Hinges 4" (100mm) 6 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2 Nos 17.00 Each 34.00 Handles 6" (150mm) 2 Nos 8.00 Each 16.00 Hook & Clamps 2 Nos 4.00 Each 8.00 Screws / Nail 2 Doz 3.25 Doz 6.50 Spring hings 2 Nos 44.00 Each 88.00

Page 20: Rate analsis Chapter No. 12 (Wood Work)

Page 20

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauze

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 3,343.98 Contractor's Profit & Overheads 20 Percent 668.80 Total for 27 Sft. 4,012.78

Rate Per Sft 4012.78 = 148.62 27

Labour

Carpenters 0.50 Nos 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00

Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80

Rate Per Sft 250.80 = 9.29 27

Item Rates

Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95

Composite Rate Per Sft Rs. 157.91 Say 157.90 Composite Rate Per Sqm Rs. 1,699.11 Say 1,699.10

Page 21: Rate analsis Chapter No. 12 (Wood Work)

Page 21

Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:

c) G.I. Wire gauze 22 SWG 12x12 meshes per SqInch (25mm) fixed to chowkhat with ¾" (20mm)teak wood strips and screws.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 4' = 12 Sft

Material

Teak Wood

Horizontal Strips 2x3'x3"x¾" 0.09 CftVertital Strips 2x3.5'x3"x¾" 0.11 Cft

0.2 CftWastage 15% 0.03 Cft

0.23 Cft 1400.00 P. Cft 322.00 Wire gauze = 1x3x4 12 SftWastage 10% 1.2 Sft

13.20 Sft 6.00 Sft 79.20

Fitting

Screws above 1" long 2.00 Doz 3.25 Doz 6.50 Nail 0.07 Kg. 43.00 P. Kg. 3.01

Total 410.71 Contractor's Profit & Overheads 20 Percent 82.14 Total for 12 Sft. 492.85

Rate Per Sft 492.85 = 41.07 12

Page 22: Rate analsis Chapter No. 12 (Wood Work)

Page 22

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.40 No 300.00 P. Day 120.00 Skilled Cooly 0.20 No 160.00 P. Day 32.00

Total 152.00 Sundries 10 Percent 15.20 Total 167.20 Contractor's Profit & Overheads 20 Percent 33.44 Total for 12 Sft. 200.64

Rate Per Sft 200.64 = 16.72 12

Item Rates

Labour Rate Per Sft Rs. 16.72 Say 16.70 Labour Rate Per Sqm Rs. 179.91 Say 179.90

Composite Rate Per Sft Rs. 57.79 Say 57.80 Composite Rate Per Sqm Rs. 621.83 Say 621.85

Page 23: Rate analsis Chapter No. 12 (Wood Work)

Page 23

Item No. 4 First class teak wood wrought joinery in wiregauze doors & windows with frames 22 SWGgalvanized iron wire gauze 12x12 meshes tosquare inch (625mm) including brass fitting sashbars etc. complete:

d) G.I. Wire gauze 22 SWG 12x12 meshes per SqInch (25mm) fixed with ½" (12mm) teakwood strips and screws.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 2' = 8 Sft

Material

Teak Wood

Horizontal Rail 2x4'x2"x2" 0.22 CftVertital Rail 2x2'x2"x2" 0.11 CftStrip Rail 2x4'x2"x2" 0.05 CftStrips Rail 2x1 2/3'x2"x2" 0.03 CftMoulding 0.15 Cft

0.56 CftWastage 15% 0.09 Cft

0.65 Cft 1400.00 P. Cft 910.00

Wire gauze 12x12 meshes/Sq. in (25mm)

Area 4x2 = 8 Sft. 8.00 SftWastage 10% 0.80 Sft

8.80 Sft 6.00 Sft 52.80 Fitting

Screws 2.00 Doz 3.25 P. Doz 6.50 Nail 0.07 Doz 43.00 P. Doz 3.01 Wooden Plug 6.00 Nos 0.50 Each 3.00

Total 975.31 Contractor's Profit & Overheads 20 Percent 195.06 Total for 8 Sft 1,170.37

Rate Per Sft 1170.37 = 146.30 8

Page 24: Rate analsis Chapter No. 12 (Wood Work)

Page 24

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.125 No 160.00 P. Day 20.00

Total 95.00 Sundries 10 Percent 9.50 Total 104.50

Contractor's Profit & Overheads 20 Percent 20.90 Total for 8 Sft. 125.40

Rate Per Sft 125.40 = 15.68 8

Item Rates

Labour Rate Per Sft Rs. 15.68 Say 15.70 Labour Rate Per Sqm Rs. 168.66 Say 168.65

Composite Rate Per Sft Rs. 161.98 Say 162.00 Composite Rate Per Sqm Rs. 1,742.92 Say 1,742.90

Page 25: Rate analsis Chapter No. 12 (Wood Work)

Page 25

DESCRIPTION OF ITEM NO 5: Providing and fixing expanded metal ½" to ¾"(12mm to 20mm) mesh 16 gauze fixed tochowkhat with 1" (25mm) teak wood strips andscrews etc. complete.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 2' = 8 Sft

Material

Teak Wood

Cover moulding/ Strips.

2x2'x1/12'x3/12' 0.08 Cft2x3x10/12'x1/12'x3/12' 0.16 Cft

0.24 CftWastage 15% 0.04 Cft

0.28 Cft 1400.00 P. Cft 392.00 Expended Metal

4'x2' 8.00 SftWastage 5% 0.40 Sft

8.40 Sft 6.67 Sft 56.03 Nail and Screw 2.00 Doz 3.25 P. Doz 6.50

Total 454.53 Contractor's Profit & Overheads 20 Percent 90.91 Total for 8 Sft. 545.43 Rate Per Sft 545.43 = 68.18

8

Labour

Carpenters 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 115.00 Sundries 10 Percent 11.50 Total 126.50 Contractor's Profit & Overheads 20 Percent 25.30 Total for 8 Sft. 151.80 Rate Per Sft 151.80 = 18.98

8Item Rates

Labour Rate Per Sft Rs. 18.98 Say 19.00 Labour Rate Per Sqm Rs. 204.17 Say 204.15

Composite Rate Per Sft Rs. 87.15 Say 87.15 Composite Rate Per Sqm Rs. 937.78 Say 937.80

Page 26: Rate analsis Chapter No. 12 (Wood Work)

Page 26

DESCRIPTION OF ITEM NO 6: Providing and fixing expanded metal ½" to ¾" (12mm to 20mm) mesh 16 gauze fixed to chowkhatwith 1" (25mm) cover moulding & screwsincluding teak wood frame 2"x2" (50x50mm).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 3' = 12 Sft

Material

Teak Wood Frame

2Nox4'x2"x2" 0.23 Cft2Nox3'x2"x2" 0.17 CftMoulding 13 2/3x1/12x2/12 0.20 Cft

0.60 CftWastage 15% 0.09 Cft

0.69 Cft 1400.00 P. Cft 966.00 Expanded Metal

1'x4'x3' 12.00 SftWastage 5% 0.60 Sft

12.60 Sft 6.67 Sft 84.04 Nail and Screw L.S. 8.00 Total 1,058.04 Contractor's Profit & Overheads 20 Percent 211.61 Total for 12 Sft. 1,269.65 Rate Per Sft 1269.65 = 105.80

12Labour

Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total for 12 Sft. 250.81 Rate Per Sft 250.81 = 20.90

12Item Rates

Labour Rate Per Sft Rs. 20.90 Say 20.90 Labour Rate Per Sqm Rs. 224.89 Say 224.90

Composite Rate Per Sft Rs. 126.71 Say 126.70 Composite Rate Per Sqm Rs. 1,363.35 Say 1,363.35

Page 27: Rate analsis Chapter No. 12 (Wood Work)

Page 27

DESCRIPTION OF ITEM NO 7: First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)

a) 2" (50mm) thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Top Rail 4¾x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 CftVertical Style 4x6'x6½"x4"x2" 1.46 CftHorizotal Style 2x1'-10"x4"x2" 0.20 CftMiddle Style 2x1'-10"x4"x2" 0.20 CftMiddle Style 2x1'-10"x4"x2" 0.31 CftBottom Style 2x1'-10"x8"x2" 0.42 Cft

Panells

2'x14"x22"x¾" 0.27 Cft4'x14"x18.5"x¾" 0.45 Cft

Beading 0.02 Cft

2x80.02 Cft

2x85.13 Cft

Wastage 15% 0.77 Cft5.90 Cft 550.00 P. Cft 3,245.00

2(14"+14"+22"+22")5/8"(1½"+2½")

4(14"+18.5"+18.5")5/8"(1½"+2½")

Page 28: Rate analsis Chapter No. 12 (Wood Work)

Page 28

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00

Total 3,438.92 Contractor's Profit & Overheads 20 Percent 687.78 Total for 27 Sft. 4,126.71 Rate Per Sft 4126.71 = 152.84

27Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00

Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.20 Rate Per Sft 1399.20 = 51.82

27Item Rates

Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60

Composite Rate Per Sft Rs. 204.66 Say 204.65 Composite Rate Per Sqm Rs. 2,202.18 Say 2,202.20

Page 29: Rate analsis Chapter No. 12 (Wood Work)

Page 29

Item No. 7 First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)

b) 1¾" (45mm) thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Top Rail 4¾x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 CftVertical Style 4x6-6½"x4"x1¾" 1.25 Cft

Horizontal Rail

Top 2x1'-10"x4"x1¾" 0.18 CftMiddle 2x1'-10"x4"x1¾" 0.18 CftLock 2x1'-10"x6"x1¾" 0.27 CftBottom 2x1'-10"x8"x1¾" 0.36 Cft

Panells

2'x14"x22"x¾" 0.27 Cft4'x14"x18.5"x¾" 0.44 Cft

Beadings 0.01 Cft

2x80.02 Cft

2x84.76 Cft

Wastage 15% 0.71 Cft5.47 Cft 550.00 P. Cft 3,008.50

2(14"+14"+22"+22")5/8" (1½"+2½")

4(14"+14"+18.5"+18.5")5/8"(1½"+2½")

Page 30: Rate analsis Chapter No. 12 (Wood Work)

Page 30

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spikes 0.20 Kg. 30.00 P. Kg. 6.00

Total for 27 Sft. 3,202.42 Contractor's Profit & Overheads 20 Percent 640.48 Total for 27 Sft. 3,842.91 Rate Per Sft 3842.91 = 142.32

27Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00 Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.21 Rate Per Sft 1399.21 = 51.82

27Item Rates

Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60

Composite Rate Per Sft Rs. 194.14 Say 194.15 Composite Rate Per Sqm Rs. 2,088.97 Say 2,088.95

Page 31: Rate analsis Chapter No. 12 (Wood Work)

Page 31

Item No. 7 First class deodar wood wrought joinery in doors andwindows etc. panelled or panelled or glazed or fullyglazed fixed in position including chowkhat, holdfast, hinges, tower bolt rubber stop cleats/G I clamp,handles and chord with hooks etc. complete(excluding sliding bolts or lock)

c) 1½" (40mm) thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Top Rail 1x4¾x3"x4½" 0.45 CftVertical Rail 2x7x3"x4½" 1.33 CftVertical Style 4x6'-6½"x4"x1½" 1.20 Cft

Horizontal Rail

Top 2x1'-10"x4"x1¾" 0.15 CftMiddle 2x1'-10"x4"x1½" 0.15 CftLock 2x1'-10"x6"x1½" 0.23 CftBottom 2x1'-10"x8"x1½" 0.30 Cft

Panells

2'x14"x22"x¾"x5/8" 0.22 Cft4'x14"x18.5"x5/8" 0.44 Cft

Beadings 0.01 Cft

2x80.02 Cft

2x84.50 Cft

Wastage 15% 0.68 Cft5.18 Cft 550.00 P. Cft 2,849.00

2(14"+14"+22"+22")5/8"(1½"+2½")

4(14"+14"+18.5"+18.5")5/8"(1½"+2½")

Page 32: Rate analsis Chapter No. 12 (Wood Work)

Page 32

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Handles 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron Hold Fast 6.00 Nos 8.00 Each 48.00 Rubber Pad 2.00 Nos 4.00 Each 8.00 Hook & Clamps 2.00 Nos 4.00 Each 8.00 Screws / Nail 2.50 Doz 3.25 Doz 8.13 Glue 0.05 Kg. 80.00 P. Kg. 4.00 Spibes 0.20 Kg. 30.00 P. Kg. 6.00

Total 3,033.72 Contractor's Profit & Overheads 20 Percent 606.74 Total for 27 Sft. 3,640.47 Rate Per Sft 3640.47 = 134.83

27Labour

Carpenters 3.00 Nos 300.00 P. Day 900.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,060.00 Sundries 10 Percent 106.00 Total 1,166.00

Contractor's Profit & Overheads 20 Percent 233.20 Total for 27 Sft. 1,399.20 Rate Per Sft 1399.20 = 51.82

27Item Rates

Labour Rate Per Sft Rs. 51.82 Say 51.80 Labour Rate Per Sqm Rs. 557.61 Say 557.60

Composite Rate Per Sft Rs. 186.65 Say 186.65 Composite Rate Per Sqm Rs. 2,008.40 Say 2,008.40

Page 33: Rate analsis Chapter No. 12 (Wood Work)

Page 33

DESCRIPTION OF ITEM NO 8: Deodar wood framed braced and battened doors &windows complete with iron fitting & fixed inposition including chowkhat.

a) 2¼"(55mm) thick with 1¼"(32mm) thick planks.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 7' = 21 Sft

Material

Deodar Wood

Top Rail 1x3¾x3"x4½" 0.35 CftVertical Rail 2x7¼"x3"x4½" 1.36 Cft

Leaf

Plank 1x2 2/12x6 17/24x1/12 1.44 CftBattens 3x2x1/3'x3/8'x5/8' 0.27 CftBraces 2x3 47/48x3/8x5/8 0.31 Cft

3.73 CftWastage 15% 0.56 Cft

4.29 Cft 500.00 P. Cft 2,145.00 Fitting

Hinges 10" (250mm) 3.00 Nos 10.00 Each 30.00 Tower Bolts 9" (225mm) 1.00 No 17.00 Each 17.00 Bolts 8" (200mm) with staple for pad

lock. 1.00 No 32.00 Each 32.00 Wrought Iron hold fast 6.00 Nos 4.00 Each 24.00 Hinges chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door stop 6" (150mm) 1.00 No 12.00 Each 12.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Screws above 1" long 2.00 Doz 3.25 Doz 6.50 Nails of sorts 0.06 Kg 43.00 P. Kg 2.58

Total 2,289.68 Contractor's Profit & Overheads 20 Percent 457.94 Total for 21 Sft. 2,747.62

Rate Per Sft 2747.62 = 130.84 21

Page 34: Rate analsis Chapter No. 12 (Wood Work)

Page 34

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 2.50 Nos 300.00 P. Day 750.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 910.00 Sundries 10 Percent 91.00 Total 1,001.00

Contractor's Profit & Overheads 20 Percent 200.20 Total for 21 Sft. 1,201.20 Rate Per Sft 1201.20 = 57.19

21Item Rates

Labour Rate Per Sft Rs. 57.19 Say 57.20 Labour Rate Per Sqm Rs. 615.36 Say 615.35

Composite Rate Per Sft Rs. 188.03 Say 188.05 Composite Rate Per Sqm Rs. 2,023.19 Say 2,023.20

Page 35: Rate analsis Chapter No. 12 (Wood Work)

Page 35

Item No. 8 Deodar wood framed braced and battened doors &windows complete with iron fitting & fixed inposition including chowkhat.

b) 1¾" (45mm) thick with 1" (25mm) battens andplanking.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 6.5' = 19.5 Sft

Material

Deodar Wood

Top Rail 1x3¾'x¼'x3/8 0.35 CftVertical Rail 2x6¼'x¼x3/8 1.17 CftLeaf Plank 1x2 7/12x6 5/24x 1/16 1.00 CftLedges 2x3 13/20x1/3x1/12 0.20 CftBraces 2x3 13/20x1/3x1/12 0.20 Cft

2.92 CftWastage 15% 0.44 Cft

3.36 Cft 500.00 P. Cft 1,680.00 Fitting

Hinges 5" (125mm) 3.00 Nos 5.60 Each 16.80 Tower Bolts 9" (225mm) 3.00 Nos 17.00 Each 51.00 Wrought Iron hold fast 4.00 Nos 7.00 Each 28.00 Hinges chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door stops 6" (150mm) 1.00 No 12.00 Each 12.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50 Nails of sorts 0.06 Kg 43.00 P. Kg 2.58

Total 1,817.48 Contractor's Profit & Overheads 20 Percent 363.50 Total for 19.5 Sft. 2,180.98

Rate Per Sft 2180.98 = 111.84 19.5

Page 36: Rate analsis Chapter No. 12 (Wood Work)

Page 36

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 2.00 Nos 300.00 P. Day 600.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 760.00 Sundries 10 Percent 76.00 Total 836.00

Contractor's Profit & Overheads 20 Percent 167.20 Total for 19.5 1,003.20

Rate Per Sft 1003.20 = 51.45 19.5

Item Rates

Labour Rate Per Sft Rs. 51.45 Say 51.45 Labour Rate Per Sqm Rs. 553.56 Say 553.55

Composite Rate Per Sft Rs. 163.29 Say 163.30 Composite Rate Per Sqm Rs. 1,757.01 Say 1,757.00

Page 37: Rate analsis Chapter No. 12 (Wood Work)

Page 37

DESCRIPTION OF ITEM NO 9: 1" (25mm) thick battened doors and windows fittedin position complete with iron fittings withoutchowkhat.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 100 Sft

Material

Deodar Wood 9.50 Cft 500.00 Cft 4,750.00 T. Hinges 6" (150mm) 4.00 Nos 14.00 Each 56.00 Tower bolt 6" (150mm) 2.00 Nos 9.58 Each 19.17 Stops 2.00 Nos 12.00 Each 24.00 Nails 0.063 Kg. 43.00 Kg. 2.71 Screws 2.00 Dozen 3.25 P. Doz 6.50

Total 4,858.38 Contractor's Profit & Overheads 20 Percent 971.68 Total for 100 Sft. 5,830.05 Rate Per Sft 5830.05 = 58.30

100Labour

Carpenters 16.00 Nos 300.00 P. Day 4,800.00 Skilled Cooly 3.00 Nos 160.00 P. Day 480.00

Total 5,280.00 Sundries 10 Percent 528.00 Total 5,808.00

Contractor's Profit & Overheads 20 Percent 1,161.60 Total for 100 Sft. 6,969.60

Rate Per Sft 6969.60 = 69.70 100.0

Item Rates

Labour Rate Per Sft Rs. 69.70 Say 69.70 Labour Rate Per Sqm Rs. 749.93 Say 749.95

Composite Rate Per Sft Rs. 128.00 Say 128.00 Composite Rate Per Sqm Rs. 1,377.24 Say 1,377.25

Page 38: Rate analsis Chapter No. 12 (Wood Work)

Page 38

DESCRIPTION OF ITEM NO 10: Deodar battened ledged & braced doors andwindows 2¼" (56mm) thick (1¼" (30mm) thickledge braces and 1" thick battens complete withiron fittings chowkhats and fixed in position.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 6.5' = 19.5 Sft

Material

Deodar Wood

Chowkhat 2x6¾'x3"x4½" 1.30 Cft1x3"x3"x4½" 0.19 CftLeaf Batten 1x2'-7"x6"-3"x1/12 1.35 CftStyles 3x2'-5½"x4"-1¼" 0.26 CftBraces 2x3.0"x4"x1¼" 0.20 Cft

3.30 CftWastage 15% 0.50 Cft

3.80 Cft 500.00 P. Cft 1,900.00 Fitting

Hinges Chocks 4" (100mm) 1.00 No 4.60 Each 4.60 Door Stop 6" (150mm) 1.00 No 3.00 Each 3.00 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Tower Hinges 8" (200mm) 2.00 Nos 13.00 Each 26.00 Wrought Iron hold fast 4.00 Nos 7.00 Each 28.00 Hasp and staple 1.00 No 12.00 Each 12.00 Handles 2.00 Nos 8.00 Each 16.00 Screws above 1' long 2.00 Doz 3.25 P. Doz 6.50 Nails of sorts 0.13 Kg 43.00 P. Kg 5.38

Total 2,035.47 Contractor's Profit & Overheads 20 Percent 407.09 Total for 19.5 Sft 2,237.69

Rate Per Sft 2237.69 = 114.75 19.5

Page 39: Rate analsis Chapter No. 12 (Wood Work)

Page 39

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 2.50 Nos 300.00 P. Day 750.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 910.00 Sundries 10 Percent 91.00 Total 1,001.00

Contractor's Profit & Overheads 20 Percent 200.20 Total for 19.5 Sft. 1,201.20

Rate Per Sft 1201.20 = 61.60 19.5

Item Rates

Labour Rate Per Sft Rs. 61.60 Say 61.60 Labour Rate Per Sqm Rs. 662.82 Say 662.80

Composite Rate Per Sft Rs. 176.35 Say 176.35 Composite Rate Per Sqm Rs. 1,897.56 Say 1,897.55

Page 40: Rate analsis Chapter No. 12 (Wood Work)

Page 40

DESCRIPTION OF ITEM NO 11: a) Deodar wood framed with braces and 22 SWGG.I. Sheet facing including hold fast, woodenbeading, hinges and locking arrangement, asDirected by the Engineer Incharge.

i) G.I. Sheet facing one side

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 8' x 8' = 64 Sft

Material

Deodar Wood 7.00 Cft 550.00 Cft 3,850.00 22 gauge G.I. Plain sheet 64.00 SftWastage 10% 6.40 Sft

70.40 Sft 6.00 Sft 422.40 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 18" (450mm) long 1.00 No 80.00 Each 80.00 Nails 0.23 Kg 43.00 P. Kg 9.89

Total 4,378.04 Contractor's Profit & Overheads 20 Percent 875.61 Total for 64 Sft. 5,253.65 Rate Per Sft 5253.65 = 82.09

64

Labour

Carpenters 3.50 Nos 300.00 P. Day 1,050.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00

Total 1,290.00 Sundries 10 Percent 129.00 Total 1,419.00 Contractor's Profit & Overheads 20 Percent 283.80 Total for 64 Sft. 1,702.80 Rate Per Sft 1702.80 = 26.61

64.0Item Rates

Labour Rate Per Sft Rs. 26.61 Say 26.60 Labour Rate Per Sqm Rs. 286.28 Say 286.30

Composite Rate Per Sft Rs. 108.69 Say 108.70 Composite Rate Per Sqm Rs. 1,169.55 Say 1,169.55

Page 41: Rate analsis Chapter No. 12 (Wood Work)

Page 41

DESCRIPTION OF ITEM NO 11: a) Deodar wood framed with braces and 22 SWGG.I. Sheet facing including hold fast, woodenbeading, hinges and locking arrangement, asDirected by the Engineer Incharge.

ii) G.I. Sheet facing on both side.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 8' x 8' = 64 Sft

Material

Deodar Wood 7.00 Cft 550.00 P. Cft 3,850.00 22 gauge G.I. Plain sheet 128.00 SftWastage 10% 12.80 Sft

140.80 Sft 6.00 Sft 844.80 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 1½" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.47 Kg 43.00 P. Kg 20.21

Total 4,810.76 Contractor's Profit & Overheads 20 Percent 962.15 Total for 64 Sft. 5,772.91 Rate Per Sft 5772.91 = 90.20

64Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00

Total 1,440.00 Sundries 10 Percent 144.00 Total 1,584.00

Contractor's Profit & Overheads 20 Percent 316.80 Total for 64 Sft. 1,900.80 Rate Per Sft 1900.80 = 29.70

64.0Item Rates

Labour Rate Per Sft Rs. 29.70 Say 29.70 Labour Rate Per Sqm Rs. 319.57 Say 319.55

Composite Rate Per Sft Rs. 119.90 Say 119.90 Composite Rate Per Sqm Rs. 1,290.14 Say 1,290.15

Page 42: Rate analsis Chapter No. 12 (Wood Work)

Page 42

Item No. 11 b) Partal wood frame with braces & 22 SWG G.I.Sheet facing including hold fast wooden beadinghinges and locking arrangement as directed byEngineering incharge.

i) G.I. Sheet facing one side

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 8' x 8' = 64 Sft

Material

Partal Wood 7.00 Cft 350.00 P. Cft 2,450.00 22 gauge G.I. Plain sheet 64.00 SftWastage 10% 6.40 Sft

70.40 Sft 6.00 Sft 422.40 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 1½" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.23 Kg 43.00 P. Kg 9.89

Total 2,978.04 Contractor's Profit & Overheads 20 Percent 595.61 Total for 64 Sft. 3,573.65 Rate Per Sft 3573.65 = 55.84

64

Labour

Carpenters 3.50 Nos 300.00 P. Day 1,050.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00

Total 1,290.00 Sundries 10 Percent 129.00 Total 1,419.00

Contractor's Profit & Overheads 20 Percent 283.80 Total 1,702.80 Rate Per Sft 1702.80 = 26.61

64.0Item Rates

Labour Rate Per Sft Rs. 26.61 Say 26.60 Labour Rate Per Sqm Rs. 286.28 Say 286.30

Composite Rate Per Sft Rs. 82.44 Say 82.45 Composite Rate Per Sqm Rs. 887.10 Say 887.10

Page 43: Rate analsis Chapter No. 12 (Wood Work)

Page 43

Item No. 11 b) Partal wood frame with braces & 22 SWG G.I.Sheet facing including hold fast wooden beadinghinges and locking arrangement as directed byEngineering incharge.

ii) G.I. Sheet facing on both side

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Anaylsis for 8' x 8' = 64 Sft

Material

Partal Wood 7.00 Cft 350.00 P. Cft 2,450.00 22 gauge G.I. Plain sheet 128.00 SftWastage 10% 12.80 Sft

140.80 Sft 6.00 Sft 844.80 Hold fast with pivots & clamp 6.00 Nos 1.00 Each 6.00 Screws above 1" long 3.00 Doz 3.25 P. Doz 9.75 Sliding bolts 18" (450 mm) long 1.00 No 80.00 Each 80.00 Nails 0.47 Kg 43.00 P. Kg 20.21

Total 3,410.76 Contractor's Profit & Overheads 20 Percent 682.15 Total for 64 Sft. 4,092.91 Rate Per Sft 4092.91 = 63.95

64Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00

Total 1,440.00 Sundries 10 Percent 144.00 Total 1,584.00

Contractor's Profit & Overheads 20 Percent 316.80 Total for 64 Sft. 1,900.80 Rate Per Sft 1900.80 = 29.70

64.0Item Rates

Labour Rate Per Sft Rs. 29.70 Say 29.70 Labour Rate Per Sqm Rs. 319.57 Say 319.55

Composite Rate Per Sft Rs. 93.65 Say 93.65 Composite Rate Per Sqm Rs. 1,007.69 Say 1,007.70

Page 44: Rate analsis Chapter No. 12 (Wood Work)

Page 44

DESCRIPTION OF ITEM NO 12: First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.

a) Deodar framing 1¾" (45mm) with wire gauge fixed in position.

i) Without Springs or Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Deodar Wood Frame

Top Rail 1x4x3"x½" 0.04 CftVertical Rail 2x7x3"x½" 0.15 CftFillet 2(15½+15½+25+25)½x3/8 0.02 CftLeaves 2(15½+15½+19+19)½x3/8 0.03 Cft

Vertical Style

4x6'-6½"x4"x1¾ 1.27 Cft

Horizontal

Top 2x1'-10½"x3"x1¾" 0.07 CftMiddle 2x1'-10½"x1½"x1¾" 0.06 CftLock 2x1'-10½"x6"x1¾" 0.27 CftBottom 2x1'-10½"x6"x1¾" 0.27 Cft

2.18 CftWastage 10% 0.22 Cft

2.40 Cft 550.00 P. Cft 1,320.00 Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (225mm) 2.00 Nos 17.00 Each 34.00 Handles 6" 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50

Page 45: Rate analsis Chapter No. 12 (Wood Work)

Page 45

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauge

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 1,495.98 Contractor's Profit & Overheads 20 Percent 299.20 Total for 27 Sft. 1,795.18 Rate Per Sft 1795.18 = 66.49

27Labour

Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00

Total 570.00 Sundries 10 Percent 57.00 Total 627.00

Contractor's Profit & Overheads 20 Percent 125.40 Total for 27 Sft. 752.40 Rate Per Sft 752.40 = 27.87

27.0Item Rates

Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85

Composite Rate Per Sft Rs. 94.35 Say 94.35 Composite Rate Per Sqm Rs. 1,015.26 Say 1,015.25

Page 46: Rate analsis Chapter No. 12 (Wood Work)

Page 46

Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.

a) Deodar wood framing 1¾" (45mm) thick withwire gauge fixed in position.

ii) With Springs & Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Deodar Wood Frame

Top Rail 1x4'x3"x½" 0.04 CftVertical Rail 2x7'x3"x½" 0.15 CftFillet 2(15½"+15½"+25"+25")½"x3/8" 0.02 CftLeaves 2(15½"+15½"+19"+19")½"x3/8" 0.03 Cft

Vertical Style

4x6'-6½"x4"x1¾" 1.27 Cft

Horizontal

Top 2x1'-10½"x3"x1¾" 0.07 CftMiddle 2x1'-10½"x1½"x1¾" 0.06 CftLock 2x1'-10½"x6"x1¾" 0.27 CftBottom 2x1'-10½"x6"x1¾" 0.27 Cft

2.18 CftWastage 10% 0.22 Cft

2.40 Cft 550.00 P. Cft 1,320.00 Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50 Spring Hinges 2.00 Nos 44.00 Each 88.00

Page 47: Rate analsis Chapter No. 12 (Wood Work)

Page 47

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauge

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 1,583.98 Contractor's Profit & Overheads 20 Percent 316.80 Total for 27 Sft. 1,900.78 Rate Per Sft 1900.78 = 70.40

27Labour

Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00

Total 570.00 Sundries 10 Percent 57.00 Total 627.00

Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87

27.0Item Rates

Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85

Composite Rate Per Sft Rs. 98.27 Say 98.25 Composite Rate Per Sqm Rs. 1,057.34 Say 1,057.35

Page 48: Rate analsis Chapter No. 12 (Wood Work)

Page 48

Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 12x12 mashes per squareinch (625mm) including iron fittings complete.

b) Deodar Wood framing 1½" (40mm) thick withwire gauze fixed in position.

i) Without Springs as Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4'x6.75' = 27 Sft

Material

1st Class Deodar Wood

Vertical Style 4x6'-6½"x4"x1½" 1.09 Cft

Horizontal

Top 2x1'-10½"x3"x1½" 0.12 CftMiddle 2x1'-10½"x1½"x1½" 0.06 CftLock 2x1'-10½"x6"x1½" 0.24 CftBottom 2x1'-10½"x6"x1½" 0.24 CftFillets 2(15½"+15½"25+25) ½x 3/8 0.02 CftFrame 4(15½"+15½"19+19) ½x 3/8 0.03 CftTop Rail 1x4x3"x1½" 0.05 CftVertical Rail 2x7x3"x1½" 0.15 Cft

2.00 CftWastage 10% 0.20 Cft

2.20 Cft 550.00 P. Cft 1,210.00 Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (228mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50

Page 49: Rate analsis Chapter No. 12 (Wood Work)

Page 49

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauge

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 1,385.98 Contractor's Profit & Overheads 20 Percent 277.20 Total for 27 Sft. 1,663.18 Rate Per Sft 1663.18 = 61.60

27Labour

Carpenters 1.50 Nos 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00

Total 570.00 Sundries 10 Percent 57.00 Total 627.00

Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87

27Item Rates

Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85

Composite Rate Per Sft Rs. 89.47 Say 89.45 Composite Rate Per Sqm Rs. 962.65 Say 962.65

Page 50: Rate analsis Chapter No. 12 (Wood Work)

Page 50

Item No. 12 First class deodar wood wrought joinery work inwire gauze doors and windows with 22 SWGgalvanized wire gauze 144 mashes per squareinch (625mm) including iron fittings complete.

b) Deodar Wood framing 1½" (40mm) thick withwire gauze fixed in position.

ii) With Springs as Spring Hinges.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4'x6.75' = 27 Sft

Material

1st Class Deodar Wood

Vertical Style 4x6'-6½"x4"x1½" 1.09 Cft

Horizontal

Top 2x1'-10½"x3"x1½" 0.12 CftMiddle 2x1'-10½"x1½"x1½" 0.06 CftLock 2x1'-10½"x6"x1½" 0.24 CftBottom 2x1'-10½"x6"x1½" 0.24 CftFillets 2(15½"+15½"25+25) ½x 3/8 0.02 CftTop Rail 1x4'x3"x1½" 0.05 CftVertical Rail 2x7'x3"x1½" 0.15 Cft

1.97 CftWastage 10% 0.22 Cft

2.19 Cft 550.00 P. Cft 1,204.50 Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower Bolts 9" (228mm) 2.00 Nos 17.00 Each 34.00 Handles 6" (150mm) 2.00 Nos 8.00 Each 16.00 Hook & Clamp 2.00 Nos 4.00 Each 8.00 Screws / Nails 2.00 Doz 3.25 P. Doz 6.50 Spring 2.00 Nos 44.00 Each 88.00

Page 51: Rate analsis Chapter No. 12 (Wood Work)

Page 51

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Wire Gauge

2x1'-2"x2'-1" 4.83 Sft4x1'-2"x1'-7" 7.33 Sft

12.16 SftWastage 15% 1.82 Sft

13.98 Sft 6.00 Sft 83.88

Total 1,468.48 Contractor's Profit & Overheads 20 Percent 293.70 Total for 27 Sft. 1,762.18 Rate Per Sft 1762.18 = 65.27

27Labour

Carpenters 1.50 No 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00

Total 570.00 Sundries 10 Percent 57.00 Total 627.00

Contractor's Profit & Overheads 20 Percent 125.40 Total 752.40 Rate Per Sft 752.40 = 27.87

27Item Rates

Labour Rate Per Sft Rs. 27.87 Say 27.85 Labour Rate Per Sqm Rs. 299.85 Say 299.85

Composite Rate Per Sft Rs. 93.13 Say 93.15 Composite Rate Per Sqm Rs. 1,002.11 Say 1,002.10

Page 52: Rate analsis Chapter No. 12 (Wood Work)

Page 52

Item No. 12 c) G.I. wire gauze 22 SWG, 12x12 meshes per squareinch (256mm) fixed to chowkhat with ¾" (20mm)thick deodar wood screw and strip.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 3' = 12 Sft

Material

Wood Work

Wood 0.25 Cft 550.00 P. Cft 137.50 Wire gauze 12.00 Sft 6.00 Sft 72.00 Nails L.S. 8.00

Total 217.50 Contractor's Profit & Overheads 20 Percent 43.50 Total for 12 Sft. 261.00 Rate Per Sft 261.00 = 21.75

12Labour

Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00

Contractor's Profit & Overheads 20 Percent 41.80 Total 250.80 Rate Per Sft 250.80 = 20.90

12Item Rates

Labour Rate Per Sft Rs. 20.90 Say 20.90 Labour Rate Per Sqm Rs. 224.88 Say 224.90

Composite Rate Per Sft Rs. 42.65 Say 42.65 Composite Rate Per Sqm Rs. 458.91 Say 458.90

Page 53: Rate analsis Chapter No. 12 (Wood Work)

Page 53

Item No. 12 d) G.I. wire gauze 22 SWG, 12x12 meshes persquare inch (625mm) fixed to chowkhat with ½"(12mm) strip on separate frame of deodar wood2"x2" (50x50mm).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 2' x 4' = 8 Sft

Material

Deodar Wood

Horizontal Rail 2x4"x2"x2" 0.22 CftVertical Rail 2x2"x2"x2" 0.11 CftStrips 2x4"x2"x½" 0.05 CftStrips 2x1'-8"x2"x½" 0.03 CftMoulding L.S. 0.06 Cft

0.47 CftWastage 20% 0.09 Cft

0.56 Cft 550.00 P. Cft 308.00 Wire Gauze 144 Mesh/Sqare in CW 4x2 8.00 Sft Wastage 10% 0.80 Sft

8.80 Cft 6.00 P. Sft 52.80

Fitting

Screws above 1" long 2.00 Doz 3.25 P. Doz 6.50 Nails 0.08 Kg 43.00 P. Kg 3.58 Wooden Plugs 6.00 Nos 1.00 Each 6.00

Total 376.88 Contractor's Profit & Overheads 20 Percent 75.38 Total for 8 Sft. 452.26 Rate Per Sft 452.26 = 56.53

8

Page 54: Rate analsis Chapter No. 12 (Wood Work)

Page 54

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00

Contractor's Profit & Overheads 20 Percent 41.80 Total for 8 Sft. 250.80 Rate Per Sft 250.80 = 31.35

8Item Rates

Labour Rate Per Sft Rs. 31.35 Say 31.35 Labour Rate Per Sqm Rs. 337.33 Say 337.35

Composite Rate Per Sft Rs. 87.88 Say 87.90 Composite Rate Per Sqm Rs. 945.62 Say 945.60

Page 55: Rate analsis Chapter No. 12 (Wood Work)

Page 55

DESCRIPTION OF ITEM NO 13: Making and fixing trellis doors and windows ofdeodar wood complete.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 18 Sft

Material

Deodar Wood 2.30 Cft 500.00 P. Cft 1,150.00 Nail 0.126 Kg. 43.00 P. Kg. 5.42 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower Bolt 9" (225mm) 2.00 Nos 17.00 Each 34.00 Hasp & Staple 1.00 No 4.00 Each 4.00

Total 1,219.94 Contractor's Profit & Overheads 20 Percent 243.99 Total for 18 Sft. 1,463.93 Rate Per Sft 1463.93 = 81.33

18Labour

Carpenter 1.50 No 300.00 P. Day 450.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 610.00 Sundries 10 Percent 61.00 Total 671.00

Contractor's Profit & Overheads 20 Percent 134.20 Total for 18 Sft. 805.20 Rate Per Sft 805.20 = 44.73

18Item Rates

Labour Rate Per Sft Rs. 44.73 Say 44.75 Labour Rate Per Sqm Rs. 481.33 Say 481.35

Composite Rate Per Sft Rs. 126.06 Say 126.05 Composite Rate Per Sqm Rs. 1,356.44 Say 1,356.45

Page 56: Rate analsis Chapter No. 12 (Wood Work)

Page 56

DESCRIPTION OF ITEM NO 14: Providing & fixing mild steel chowkhat of doors,windows, C. Window etc. including hold fast,making and threading holes for hinges etc.complete

a) M.S. angle iron 1½"x1½"x¼" (40x40x6mm)welded M.S. flat 2"x¼" (50x6mm)

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Structural Steel

M.S. Angle Iron 1½"x1½"x¼" (40x40x6mm)

Vertical 2x7 14 Rft

18.00 Rft

18.90 Rft

18.90 Rft @ 2.32 Lbs/Rft 43.85 LbsM.S. Flat 2"x¼" (50x6mm)

Vertical 2x7 14 Rft

18.00 Rft

18.90 Rft

18.9 @ 1.68 Lbs/ft 31.75 LbsM.S. Flat Patti 1"x1/8" (25x3mm) at

bottom.

4 @ 0.42 Lbs/ft 1.68 Lbs77.28Lb (3 5.06)Kg 24.00 P. Kg 841.44

Total 841.44 Contractor's Profit & Overheads 20 Percent 168.29 Total for 27 Sft. 1,009.73 Rate Per Sft 1009.73 = 37.40

27

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Page 57: Rate analsis Chapter No. 12 (Wood Work)

Page 57

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Making holes in frame for hinges 4x4 16.00 Nos 1.41 Each 22.59 Welding plate with angle iron 18.00 Nos 6.00 Each 108.00 Welding hold fast with frame 6.00 Nos 4.00 Each 24.00 Welding M.S.Steel bar with frame 2.00 Nos 4.00 Each 8.00

Total 162.59 Sundries 10 Percent 16.26 Total 178.85

Contractor's Profit & Overheads 20 Percent 35.77 Total 214.62 Rate Per Sft 214.62 = 7.95

27Item Rates

Labour Rate Per Sft Rs. 7.95 Say 7.95 Labour Rate Per Sqm Rs. 85.53 Say 85.55

Composite Rate Per Sft Rs. 45.35 Say 45.35 Composite Rate Per Sqm Rs. 487.92 Say 487.90

Page 58: Rate analsis Chapter No. 12 (Wood Work)

Page 58

Item No. 14 Providing & fixing mild steel chowkhat of doors,windows, C. Window etc. including hold fast,making and threading holes for hinges etc.complete

b) M.S. Tee iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. Flat ½"x¼" (12x6mm)

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Structural Steel

Tee Iron 1½"x1½"x¼" (40x40x6mm)

Vertical 2x7 14 Rft

18.00 Rft

18.90 Rft

18.90ft @ 2.32 Lbs/ft 44.60 LbsM.S. Flat ½"x¼" (12x6mm)

18.90ft @ 0.425 Lbs/ft 8.03 LbsM.S. Bar ½" dia 4' @ 0.67 Lbs/ft 2.68 Lbs

55.31Lb (2 5.10) Kg 24.00 P. Kg 602.40

Total 602.40 Contractor's Profit & Overheads 20 Percent 120.48 Total for 27 Sft. 722.88 Rate Per Sft 722.88 = 26.77

27

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Page 59: Rate analsis Chapter No. 12 (Wood Work)

Page 59

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Making holes in frame for hinges 4x4 16.00 Nos 1.41 Each 22.59 Welding plate with angle iron 18.00 Nos 6.00 Each 108.00 Welding hold fast with frame 6.00 Nos 4.00 Each 24.00 Welding M.S.Steel bar with frame 2.00 Nos 4.00 Each 8.00

Total 162.59 Sundries 10 Percent 16.26 Total 178.85

Contractor's Profit & Overheads 20 Percent 35.77 Total 214.62 Rate Per Sft 214.62 = 7.95

27Item Rates

Labour Rate Per Sft Rs. 7.95 Say 7.95 Labour Rate Per Sqm Rs. 85.53 Say 85.55

Composite Rate Per Sft Rs. 34.72 Say 34.70 Composite Rate Per Sqm Rs. 373.61 Say 373.60

Page 60: Rate analsis Chapter No. 12 (Wood Work)

Page 60

Item No. 15 Providing and fixing M.S. Sheet hollow pressedframe of doors, windows, CW, etc. (Chowkhatonly) of 20 SWG welded with M.S. flat6"x1½"x1/8" (150x40x3mm) M.S. hold fast 9"x1"x1/8" (225x25x3mm) welded/ screwed 4"(100mm) long iron hinges including fittingchowkhat with cement sand mortar 1:8 andembedding hold fast in cement concrete 1:2:4,complete in all respects.

a) Single Rebate.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 7' = 28 Sft

Material

M.S. Sheet 20 Swg 15"(375mm) wide

18' long x15/12 (5.486x0.380m) 22.50 Kg.Wastage 10% 2.25 Kg.

24.75 Kg.SAY 25.00 Kg. Or 29.00 Kg. 493.58

M.S. Flat 6"x¼"x1/8" (150x6x3mm) 17.02 Kg3.5 Rft @ 0.531 Lbs/Rft 1.86 LbsM.S. Flat hold fast 9"x1"x1/8" (225x25x3mm)

4.5 Rft @ 0.425 Lbs/Rft 1.91 Lbs3.77Lb (1 .71) Kg 22.00 P. Kg 37.62

Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Screws 3.00 Doz 3.25 P. Doz 9.75 Nails 0.28 Kg. 43.00 P. Kg. 12.04 Welding Charges 60.00 Cement sand mortar ratio 1:8 for

filling hollow space 18'x4'/12"x3/12

including wastage (0.057m³)

(5.486x0.100x0.075m) 2.00 Cft

Page 61: Rate analsis Chapter No. 12 (Wood Work)

Page 61

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Cement 0.20 Bag 230.00 Each 46.00 Sand 2.00 Cft 3.50 P. Cft 7.00 Cement Concrete 1:2:4 for fixing hold fast

Cement 0.08 Bag 230.00 Bag 18.40 Sand 0.20 Cft. 350.00 % Cft. 0.70 Bajri 0.40 Cft. 1850.00 % Cft. 7.40

Total 720.09 Contractor's Profit & Overheads 20 Percent 144.02 Total for 28 Sft. 864.11 Rate Per Sft 864.11 = 30.86

28Labour

Moulder/ Black Smith 0.50 No 300.00 P. Day 150.00 Cooly 0.50 No 140.00 P. Day 70.00 SKilled Cooly (for Mortor Filling in the

hallow space) 0.50 No 160.00 P. Day 80.00

Total 300.00 Sundries 10 Percent 30.00 Total 330.00

Contractor's Profit & Overheads 20 Percent 66.00 Total for 28 Sft. 396.00 Rate Per Sft 396.00 = 14.14

28Item Rates

Labour Rate Per Sft Rs. 14.14 Say 14.15 Labour Rate Per Sqm Rs. 152.18 Say 152.20

Composite Rate Per Sft Rs. 45.00 Say 45.00 Composite Rate Per Sqm Rs. 484.24 Say 484.25

Page 62: Rate analsis Chapter No. 12 (Wood Work)

Page 62

Item No. 15 Providing and fixing M.S. Sheet hollow pressedframe of doors, windows, C. window, etc. (Chowkhat only) of 20 SWG welded with M.S. flat6"x1¼"x1/8" (150x32x3mm) M.S. hold fast 9"x1"x1/8" (225x25x3mm) welded/ screwed 4"(100mm) long iron hinges including fittingchowkhat with cement sand mortar 1:8 andembedding hold fast in cement concrete 1:2:4,complete in all respects.

b) Double Rebate.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 7' = 28 Sft

Material

M.S. Sheet 20SWG 17"(432mm) wide

19' longx18x18/17(5.486x0.432)= 25.50 Sft

28.05 Sft 19.10 Kg 29.00 P. Kg 553.90

M.S. Flat 7.5x1¼"x1/8(2.30x0.032x0.003)=7 No.

4.50 Rft @ 0.531 Lbs/Rft 2.39 LbsM.S. Flat hold fast 9"x1"x1/8"= 6 No

4.50 Rft @ 0.425 Lbs/Rft 1.91 Lbs4.30Lbs (1 .95) Kg 22.00 P. Kg 42.90

Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Screws 3.00 Doz 3.25 P. Doz 9.75 Nails 0.28 Kg. 43.00 P. Kg. 12.04 Welding Charges 80.00 Cement sand mortar ratio 1:8 for

filling hollow space

18"x11/24x4/12 = (5.486x0.275x0.1m) 2.75 Cft

Wastage 10% 2.55 Sft

Page 63: Rate analsis Chapter No. 12 (Wood Work)

Page 63

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Cement 0.28 Bag 230.00 Each 63.25 Sand 2.75 Cft 3.50 P. Cft 9.63 Cement Concrete 1:2:4 for (fixing

hold fast) Cement 0.08 Bag 230.00 Bag 18.40 Sand 0.20 Cft. 350.00 % Cft. 0.70 Bajri 0.40 Cft. 1850.00 % Cft. 7.40

Total 825.56 Contractor's Profit & Overheads 20 Percent 165.11 Total for 28 Sft. 990.68 Rate Per Sft 990.68 = 35.38

28

Moulder/ Black Smith 0.75 No 300.00 P. Day 225.00 Cooly 0.50 No 140.00 P. Day 70.00 SKilled Cooly (for Mortor Filling in the

hollow space) 0.50 No 160.00 P. Day 80.00

Total 375.00 Sundries 10 Percent 37.50 Total 412.50

Contractor's Profit & Overheads 20 Percent 82.50 Total for 28 Sft. 495.00 Rate Per Sft 495.00 = 17.68

28Item Rates

Labour Rate Per Sft Rs. 17.68 Say 17.70 Labour Rate Per Sqm Rs. 190.22 Say 190.20

Composite Rate Per Sft Rs. 53.06 Say 53.05 Composite Rate Per Sqm Rs. 570.92 Say 570.95

Page 64: Rate analsis Chapter No. 12 (Wood Work)

Page 64

DESCRIPTION OF ITEM NO 16: Extra for providing & fixing iron double springhinges, with brass fittings (it shall include brassfinger plate, 6" tower bolts)

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 21 Sft

Material

4" (100mm) double section spring

hinges iron. 3.00 Nos 50.00 Each 150.00 Brass finger plate 2.00 Nos 30.00 Each 60.00 6" (150mm) brass tower bolt 1.00 No 30.00 Each 30.00 Brass screws 1½" (40mm) 2.00 Doz 8.00 P. Doz 16.00 Brass Screw 1" (25mm) 2.50 Doz 3.25 P. Doz 8.13

264.13

Deduct Cost of Iron Fittings

5" (125mm) Butt Hinges 4.00 Nos 5.50 Each 22.00 9" (225mm) Tower Bolts 2.00 Nos 17.00 Each 34.00 6" (150mm) Handle 2.00 Nos 8.00 Each 16.00 Hinges Chocks 2.00 Nos 2.00 Each 4.00 Door Stops 2.00 Nos 12.00 Each 24.00 Screws 1½" 3.00 Doz 3.25 P. Doz 9.75 Screws 1" 3.00 Doz 1.68 P. Doz 5.04

114.79

Total 262.50-112.96 = 149.34 Contractor's Profit & Overheads 20 Percent 29.87 Total for 21 Sft. 179.20 Rate Per Sft 179.20 = 8.53

21

Page 65: Rate analsis Chapter No. 12 (Wood Work)

Page 65

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00

Total 23.00 Sundries 10 Percent 2.30 Total 25.30

Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36 Rate Per Sft 30.36 = 1.45

21

Item Rates

Labour Rate Per Sft Rs. 1.45 Say 1.45 Labour Rate Per Sqm Rs. 15.56 Say 15.55

Composite Rate Per Sft Rs. 9.98 Say 10.00 Composite Rate Per Sqm Rs. 107.38 Say 107.40

Page 66: Rate analsis Chapter No. 12 (Wood Work)

Page 66

DESCRIPTION OF ITEM NO 17: Providing and fixing brass spring hinges, to wiregauzed doors.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Brass spring hinges Complete with

screws 1 No 60.00 Each 60.00

Total 60.00 Contractor's Profit & Overheads 20 Percent 12.00 Total 72.00

Labour

Carpenter 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00

Total 23.00 Sundries 10 Percent 2.30 Total 25.30

Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36

Item Rates

Labour Rate for Each Rs. 30.36 Say 30.35

Composite Rate for Each Rs. 102.36 Say 102.35

Page 67: Rate analsis Chapter No. 12 (Wood Work)

Page 67

DESCRIPTION OF ITEM NO 18: Providing and fixing sliding bolt to doors.

i) Iron sliding bolt 10" (250mm) long.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 16 Each

Material

Sliding bolt 10"(250mm) long complete with

screws & nuts. 16 Nos 35.00 Each 560.00

Total 560.00 Contractor's Profit & Overheads 20 Percent 112.00 Total 672.00

Labour

Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60

Item Rates

Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16

Composite Rate for Each Rs. 1173.60 73.35 Say 73.35 16

Page 68: Rate analsis Chapter No. 12 (Wood Work)

Page 68

Item No. 18 Providing and fixing sliding bolt to doors.

ii) Iron sliding bolt 12" (300mm) long.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 16 Each

Material

Sliding bolt 12" (300mm) long complete

with screws with & nuts. 16 Nos 45.00 Each 720.00

Total 720.00 Contractor's Profit & Overheads 20 Percent 144.00 Total 864.00

Labour

Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60

Item Rates

Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16

Composite Rate for Each Rs. 1365.60 85.35 Say 85.35 16

Page 69: Rate analsis Chapter No. 12 (Wood Work)

Page 69

Item No. 18 Providing and fixing sliding bolt to doors.

iii) Brass sliding bolt 10" (250mm) long.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Anaylysis for = 16 Each

Material

Brass sliding bolt 10" (250mm) long

complete with screws & nuts. 16 Nos 75.00 Each 1,200.00

Total 1,200.00 Contractor's Profit & Overheads 20 Percent 240.00 Total 1,440.00

Labour

Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60

Item Rates

Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16

Composite Rate for Each Rs. 1941.60 121.35 Say 121.35 16

Page 70: Rate analsis Chapter No. 12 (Wood Work)

Page 70

Item No. 18 Providing and fixing sliding bolt to doors.

iv) Brass sliding bolt 12" (300mm) long.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 16 Each

Material

Brass sliding bolt 12" (300mm) long

complete with screws & nuts. 16 Nos 85.00 Each 1,360.00

Total 1,360.00 Contractor's Profit & Overheads 20 Percent 272.00 Total 1,632.00

Labour

Carpenter 1.00 No 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60

Item Rates

Labour Rate for Each Rs. 501.60 31.35 Say 31.35 16

Composite Rate for Each Rs. 2133.60 133.35 Say 133.35 16

Page 71: Rate analsis Chapter No. 12 (Wood Work)

Page 71

DESCRIPTION OF ITEM NO 19: Extra for brass fittings to doors and windows,except for hinges, which shall be of iron.

i) Deodar wood panelled or panelled and glazed orfully glazed.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 7' = 28 Sft

9" (225mm) Tower bolt 3.00 Nos 27.00 Each 81.00 6" (150mm) Handles 3.00 Nos 40.00 Each 120.00 2" (50mm) Butt hinges 2.00 Nos 5.00 Each 10.00 Screws 1" 3.50 Doz 3.25 P. Doz 11.38

222.38 Deduct Cost of Iron Fittings

9" (225mm) Tower Bolts 3.00 Nos 17.00 Each 51.00 6" (150mm) Handle 3.00 Nos 9.60 Each 28.80 2" (50mm) butt hinges 2.00 Nos 6.00 Each 12.00 Screws above 1" long 3.50 Doz 3.25 P. Doz 11.38

103.18

Total 222.38-101.04 = 119.20 Contractor's Profit & Overheads 20 Percent 23.84 Total for 28 Sft. 143.04 Rate Per Sft 143.04 = 5.11

28

Labour

Carpenter 0.04 No 300.00 P. Day 12.00 Skilled Cooly 0.04 No 160.00 P. Day 6.40

Total 18.40 Sundries 10 Percent 1.84 Total 20.24 Contractor's Profit & Overheads 20 Percent 4.05 Total 24.29 Rate Per Sft 24.29 = 0.87

28

Labour Rate Per Sft Rs. 0.87 Say 0.85 Labour Rate Per Sqm Rs. 9.33 Say 9.35 Composite Rate Per Sft Rs. 5.98 Say 6.00 Composite Rate Per Sqm Rs. 64.30 Say 64.30

Material (Brass Fittings)

Page 72: Rate analsis Chapter No. 12 (Wood Work)

Page 72

Item No. 19 Extra for brass fittings to doors and windows,except for hinges, which shall be of iron.

ii) Deodar wood wire gauzed shutters.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 7' = 28 Sft

9" (225mm) Tower balt 2.00 Nos 27.00 Each 54.00 6" (150mm) Handles 2.00 Nos 40.00 Each 80.00 2" (50mm) butt hinges 2.00 Nos 5.00 Each 10.00 Screws 1" 3.50 Doz 3.25 P. Doz 11.38

155.38 Deduct Cost of Iron Fittings

9" (225mm) Tower Bolts 2.00 Nos 17.00 Each 34.00 8" (200mm) Handle 2.00 Nos 9.60 Each 19.20

### 2" (50mm) Butt hinges 2.00 Nos 6.00 Each 12.00 Screws 1" 3.00 Doz 3.25 P. Doz 9.75

74.95

Total 153.75-73.12 = 80.42 Contractor's Profit & Overheads 20 Percent 16.08 Total for 28 Sft. 96.51 Rate Per Sft 96.51 = 3.45

28Labour

Carpenter 0.04 No 300.00 P. Day 12.00 Skilled Cooly 0.04 No 160.00 P. Day 6.40

Total 18.40 Sundries 10 Percent 1.84 Total 20.24 Contractor's Profit & Overheads 20 Percent 4.05 Total for 28 Sft. 24.29 Rate Per Sft 24.29 = 0.87

28Item Rates

Labour Rate Per Sft Rs. 0.87 Say 0.85 Labour Rate Per Sqm Rs. 9.33 Say 9.35

Composite Rate Per Sft Rs. 4.31 Say 4.30 Composite Rate Per Sqm Rs. 46.42 Say 46.40

Material (Brass Fittings)

Page 73: Rate analsis Chapter No. 12 (Wood Work)

Page 73

DESCRIPTION OF ITEM NO 20: Extra for providing and fixing, approved qualityrim lock adjustable over the style surface.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Rim lock complete with screws 1.00 No 140.00 Each 140.00 Deduct cost of handle 2.00 Nos 8.00 Each 16.00

Total 156.00 Contractor's Profit & Overheads 20 Percent 31.20 Total 187.20

Labour

Carpenter 0.17 No 300.00 P. Day 51.00 Skilled Cooly 0.13 No 160.00 P. Day 20.80

Total 71.80 Sundries 10 Percent 7.18 Total 78.98

Contractor's Profit & Overheads 20 Percent 15.80 Total 94.78

Item Rates

Labour Rate for Each Rs. 94.78 Say 94.80

Composite Rate for Each Rs. 281.98 Say 282.00

Page 74: Rate analsis Chapter No. 12 (Wood Work)

Page 74

DESCRIPTION OF ITEM NO 21: Providing and fixing approved quality morticelock.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Mortice lock compelte with screws 1.00 No 175.00 Each 175.00 Deduct cost of handles 2.00 Nos 8.00 Each 16.00

Total 159.00 Contractor's Profit & Overheads 20 Percent 31.80 Total 190.80

Labour

Carpenter 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.17 No 160.00 P. Day 26.67

Total 101.67 Sundries 10 Percent 10.17 Total 111.83

Contractor's Profit & Overheads 20 Percent 22.37 Total 134.20

Item Rates Labour Rate for Each Rs. 134.20 Say 134.20

Composite Rate for Each Rs. 325.00 Say 325.00

Page 75: Rate analsis Chapter No. 12 (Wood Work)

Page 75

DESCRIPTION OF ITEM NO 22: Providing and fixing expanded metal ½" to ¾"(12mm to 20mm) mesh 16 gauge.

a) Fixed to chowkhat with 1" (25mm) thick deodarwood strip and screws etc.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 2' = 8 Sft

Material

Deodar Wood

Strips vertical 2x2x½"x3/12" 0.08 CftHorizontal 2x3-10/12x½"x3/12" 0.16 Cft

0.24 CftWastage 20% 0.05 Cft

0.29 CftSAY 0.30 Cft 550.00 P. Cft 165.00

Expanded metal 1x4x2 8.00 SftWastage 10% 0.80 Sft

8.80 Sft 6.67 Sft 58.70 Nails / Screws 2.00 Doz 3.25 P. Doz 6.50

Total 230.20 Contractor's Profit & Overheads 20 Percent 46.04 Total for 8 Sft. 276.24 Rate Per Sft 276.24 = 34.53

8Labour

Carpenter 0.25 No 300.00 P. Day 75.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 115.00 Sundries 10 Percent 11.50 Total 126.50 Contractor's Profit & Overheads 20 Percent 25.30 Total for 8 Sft. 151.80 Rate Per Sft 151.80 = 18.98

8Item Rates

Labour Rate Per Sft Rs. 18.98 Say 19.00 Labour Rate Per Sqm Rs. 204.17 Say 204.15

Composite Rate Per Sft Rs. 53.50 Say 53.50 Composite Rate Per Sqm Rs. 575.71 Say 575.70

Page 76: Rate analsis Chapter No. 12 (Wood Work)

Page 76

Item No. 22 Providing and fixing expanded metal ½" to ¾"(12mm to 20mm) mesh 16 gauge.

b) Fixed with 1" (25mm) cover moulding & screwsincluding deodar wood frame 2"x2" (50x50mm).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 3' = 12 Sft

Material

Deodar Wood Frame

2 No 4'x2/12"x212" 0.23 Cft2 No 3'x2/12"x212" 0.17 CftMoulding 1x13 2/3'x1/12x2/12 0.20 Cft

0.60 CftWastage 20% 0.12 Cft

0.72 Cft 550.00 P. Cft 396.00 Expended metal 1x4x3 12.00 SftWastage 10% 1.20 Sft

13.20 Sft 6.67 Sft 88.04 Nails / Screws 2.00 Doz 3.25 P. Doz 6.50

Total 490.54 Contractor's Profit & Overheads 20 Percent 98.11 Total for 12 Sft. 588.65 Rate Per Sft 588.65 = 49.05

12Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00 Contractor's Profit & Overheads 20 Percent 41.80 Total for 12 Sft. 250.80 Rate Per Sft 250.80 = 20.90

12Item Rates

Labour Rate Per Sft Rs. 20.90 Say 20.90 Labour Rate Per Sqm Rs. 224.88 Say 224.90

Composite Rate Per Sft Rs. 69.95 Say 69.95 Composite Rate Per Sqm Rs. 752.71 Say 752.70

Page 77: Rate analsis Chapter No. 12 (Wood Work)

Page 77

DESCRIPTION OF ITEM NO 23: a) Providing and fixing deodar wood almirah 9" to 12" (225 to 300mm) depth, including boxing

with back shelves, shutter and brass fittings etc.complete.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 5' = 15 Sft

Material

Deodar Wood

Sides 2x1'x5'x1/12" 0.84 CftBack 1x3'x5'x¾" 0.94 CftTop & Bottom 2x3'x1'x1/12" 0.50 CftPlank 3x3'x1'x1/12" 0.75 CftShutters 2x1.5'x5'x1/12" 1.25 Cft

4.28 CftWastage 10% 0.43 Cft

4.71 Cft 550.00 P. Cft 2,590.50

Fittings Brass

Hings 3" (75mm) 6.00 Nos 3.75 Each 22.50 Hasp & Staple (Brass) 1.00 No 12.00 Each 12.00 Brass Handle 6" (150mm) 2.00 Nos 70.00 Each 140.00 Wooden Plugs 10.00 Nos 1.00 Each 10.00 Nails / Screws L.S. 19.00 Bitumen 1.43 Kg. 14.00 P. Kg. 20.02

Total 2,814.02 Contractor's Profit & Overheads 20 Percent 562.80 Total for 15 Sft. 3,376.82 Rate Per Sft 3376.82 = 225.12

15

Page 78: Rate analsis Chapter No. 12 (Wood Work)

Page 78

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenter 2.50 No 300.00 P. Day 750.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 830.00 Sundries 10 Percent 83.00 Total 913.00

Contractor's Profit & Overheads 20 Percent 182.60 Total for 15 Sft. 1,095.60 Rate Per Sft 1095.60 = 73.04

15

Item Rates

Labour Rate Per Sft Rs. 73.04 Say 73.05 Labour Rate Per Sqm Rs. 785.91 Say 785.90

Composite Rate Per Sft Rs. 298.16 Say 298.15 Composite Rate Per Sqm Rs. 3,208.22 Say 3,208.20

Page 79: Rate analsis Chapter No. 12 (Wood Work)

Page 79

Item No. 23 b) Providing and fixing deodar wood almirah 9" to12" (225 to 300mm) depth, with shelves shutterand brass fittings, etc. without boxing & back complete.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3' x 5' = 15 Sft

Material

Deodar Wood

Plank 3x10x3'x1'x1/12" 0.75 CftShutters 2x1.5'x5'x1/12" 1.25 Cft

2.00 CftWastage 10% 0.20 Cft

2.20 Cft 500.00 P. Cft 1,100.00 Fittings Brass

Hings 3" (75mm) 6.00 Nos 3.75 Each 22.50 Hasp & Staple (Brass) 1.00 No 12.00 Each 12.00 Brass Handle 6" (150mm) 2.00 Nos 70.00 Each 140.00 Wooden Plugs 6.00 Nos 1.00 Each 6.00 Nails / Screws L.S. 12.00

Total 1,292.50 Contractor's Profit & Overheads 20 Percent 258.50 Total for 15 Sft. 1,551.00 Rate Per Sft 1551.00 = 103.40

15Labour

Carpenter 1.75 Nos 300.00 P. Day 525.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 605.00 Sundries 10 Percent 60.50 Total 665.50 Contractor's Profit & Overheads 20 Percent 133.10 Total for 15 Sft. 798.60 Rate Per Sft 798.60 = 53.24

15Item Rates

Labour Rate Per Sft Rs. 53.24 Say 53.25 Labour Rate Per Sqm Rs. 572.86 Say 572.85

Composite Rate Per Sft Rs. 156.64 Say 156.65 Composite Rate Per Sqm Rs. 1,685.45 Say 1,685.45

Page 80: Rate analsis Chapter No. 12 (Wood Work)

Page 80

Item No. 24 Providing and fixing class room almirahconsisting of 1" (25mm) thick solid flush shutterwith deodar wood lipping ¼" (6mm) thick alround(sterling made) fixed in deodar wood frame 3"x1"(75x25mm) I/C full hinges C.P. fittings withR.C.C. (1:1-½:3) shelves 1-½" (40mm) thick I/C 3coats of painting.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4.5' x 3.5' = 15.75 Sft

Material

Precast reinforced cement concrete

(1:1-½"3)

Shelves 2x3-¼x1-1/8x1/8 0.91 Cft 83.60 P. Cft 76.07 Steel ¼" (12mm) dia

4x3.25 (4x0.975=3.900Rm) 13.00 Rft

18.63 Rft

19.56 Rft 1.48 Kg 24.00 Kg 35.52 @ 0.167 Lbs/Rft

Deodar wood frame I/C sawing

2x4'½x¼'x1/12' 0.19 Cft2x3'x½x¼'x1/12' 0.15 Cft

0.34 CftWastage 35% 0.12 Cft

0.46 Cft 550.00 P. Cft 253.00 1" (25mm) thick solid flush shutter

(Sterling made)

1x3'x4' (1x0.900x1.200 = 1.080) 12.00 SftWastage 5% 0.60 Sft

12.60 Sft 72.00 Sft 907.20 Deodar wood lipping 6mm thick

(Sterling made)

2x4' (2x1.200 = 2.400) 8.00 Rft2x2x-½' (2x2x0.450 = 1.800) 6.00 Rft

14.00 Rft 5.60 Rft 78.40

5x1 1'/6(5x0.375=1.875Rm) 5.63 Rft

Wastage 5% 0.93 Rft

Page 81: Rate analsis Chapter No. 12 (Wood Work)

Page 81

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Full hinges 1" (25mm) I/C screws 2x4 8.00 Nos 20.00 Each 160.00 C.P. dasti I/C screws 2.00 Nos 8.00 Each 16.00 Khunda chapks (Best quality) I/C screws 1.00 No 12.00 Each 12.00 Rawal plug 1-½" long 12.00 Nos 3.00 Each 36.00 Screws 1-½" long 1.00 Doz 3.25 P. Doz 3.25 Glue 0.20 Kg. 80.00 P.Kg. 16.00 Painting 3 coats 0.428 Gln. 450.00 P. Gln. 192.60

Total 1,786.04 Contractor's Profit & Overheads 20 Percent 357.21 Total for 15.75 Sft. 2,143.25 Rate Per Sft 2143.25 = 136.08

15.75 Labour

For bringing the leaves to proper size

fixing deodar wood lipping with glue

and nail making/ fixing deodar wood

frame & fixing at site with rawal plug &

screws.

Carpenter 1.00 No 300.00 P. Day 300.00 Helper 1.00 No 75.00 P. Day 75.00

Total 375.00 Sundries 10 Percent 37.50 Total 412.50

Contractor's Profit & Overheads 20 Percent 82.50 Total for 15.75 Sft. 495.00 Rate Per Sft 495.00 = 31.43

15.75

Item Rates

Labour Rate Per Sft Rs. 31.43 Say 31.45 Labour Rate Per Sqm Rs. 338.17 Say 338.15

Composite Rate Per Sft Rs. 167.51 Say 167.50 Composite Rate Per Sqm Rs. 1,802.39 Say 1,802.40

Page 82: Rate analsis Chapter No. 12 (Wood Work)

Page 82

DESCRIPTION OF ITEM NO 25: Providing and fixing wooden box type ward robe22" (550mm) deep including ¾" (20mm) thickboxing and shelves, hanger rods, hard board backdrawers, brass fitting locking arrangements,handles internal bolts shoe rods, etc. includingthree coats of enamel paints.

i) Partal wood boxing and deodar wood shelves andleaves etc.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.5' = 26 Sft

Material

Partal Wood

Boxing

Side 2x6-1/3x22/12x3/48 1.45 CftTop & Bottom 2x4 22/12x3/48 0.92 CftFoot Rack 1x3-7/8x22/12x3/48 0.44 CftVertical Style 1x5x22/12x3/48 0.57 CftStrips 6x22/12x1/8x3/48 0.09 CftBack 2x1½x22/12x3/48 0.34 Cft

3.81 CftWastage 15% 0.57 Cft

4.38 Cft 350.00 P. Cft 1,533.00 Shutters Deodar Wood

1x1-2/3x6½x1/12 0.91 Cft1x2-1/3x6½x1/12 1.26 Cft

2.17 CftWastage 15% 0.33 Cft

2.50 Cft 500.00 P. Cft 1,250.00 Hard Board

4x6½ 26.00 SftWastage 10% 2.60 Sft

28.60 Sft 3.50 Sft 100.10 Sawing Charges

6.88x10 68.80 Sft 0.80 Sft 55.04

Page 83: Rate analsis Chapter No. 12 (Wood Work)

Page 83

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fittings

Hings 4" (100mm) 6.00 Nos 4.60 Each 27.60 Handle 2.00 Nos 8.00 Each 16.00 Tie rod welding fixing arragement 2.25 Nos 28.00 Each 63.00 Hanger hook including pull out rod 2.00 Nos 8.00 Each 16.00 Tower bolt 4" (100mm) 1.00 Nos 7.00 Each 7.00 Bitumen Painting 1.43 Kg. 14.00 Each 20.02

Total 3,087.76 Contractor's Profit & Overheads 20 Percent 617.55 Total for 26 Sft. 3,705.32 Rate Per Sft 3705.32 = 142.51

26Labour

Carpenters 4.00 No 300.00 P. Day 1,200.00 Skilled Cooly 2.00 No 160.00 P. Day 320.00

Total 1,520.00 Sundries 10 Percent 152.00 Total 1,672.00

Contractor's Profit & Overheads 20 Percent 334.40 Total 2,006.40 Rate Per Sft 2006.40 = 77.17

26

Item Rates

Labour Rate Per Sft Rs. 77.17 Say 77.15 Labour Rate Per Sqm Rs. 830.34 Say 830.35

Composite Rate Per Sft Rs. 219.68 Say 219.70 Composite Rate Per Sqm Rs. 2,363.77 Say 2,363.75

Page 84: Rate analsis Chapter No. 12 (Wood Work)

Page 84

Item No. 25 Providing and fixing wooden box type ward robe22" (550mm) deep including ¾" (20mm) thickboxing and shelves, hanger rods, hard board backdrawers, brass fitting locking arrangements,handles internal bolts shoe rods, etc. includingthree coats of enamel paints.

ii) Deodar wood boxing and shelves & leaves etc.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 8' x 5' = 40 Sft

Material

Deodar Wood

Boxing

Vetical Side 2x8x22/12x3/48 1.83 CftControl Side 1x7-7/8x22/12x3/48 0.90 CftHorizontal T&B 2x4 11/12x22/12x3/48 1.13 CftShelves 5x2x22/12x3/48 1.15 CftVertical 1x1½x22/12x3/48 0.17 CftShoes 2x½x1/5x1/12 0.02 CftSutter 2x2 3/5x8x1/12 3.47 CftStrips 2x8x1/12x1/24 0.06 CftStrips 2x5x1/12x1/24 0.03 Cft

8.76 CftWastage 15% 1.31 Cft

10.07 Cft 500.00 P. Cft 5,035.00 Hard Wood Board

Back 5x8 40.00 SftWastage 10% 4.00 Sft

44.00 Sft 3.50 Sft 154.00 Sawing Charges :

10.20x10 102.00 Sft 0.80 Sft 81.60

Bitumen Painting 2 Coat 1.43 Kg. 14.00 Each 20.02 Painting 3 Coats 0.27 Kg. 450.00 P. Gln. 121.50

Page 85: Rate analsis Chapter No. 12 (Wood Work)

Page 85

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fittings

Hings 4" (100mm) 6.00 Nos 4.50 Each 27.00 Handle 2.00 Nos 8.00 Each 16.00 Tie rod welding fixing arragement 8.00 Hanger hook including full out rod 2.00 Nos 8.00 Each 16.00 Screws 4.00 Doz 3.25 P. Doz 13.00 Tower bolt 4" (100mm) 1.00 Nos 7.00 Each 7.00 Nail 0.19 Kg 43.00 P. Kg 8.17 Locking arrangement 1.00 Nos 55.00 Each 55.00

Total 5,562.29 Contractor's Profit & Overheads 20 Percent 1,112.46 Total for 40 Sft. 6,674.75 Rate Per Sft 6674.75 = 166.87

40

Carpenters 6.00 Nos 300.00 P. Day 1,800.00 Skilled Cooly 2.00 Nos 160.00 P. Day 320.00 Painter 1.00 Nos 170.00 P. Day 170.00

Total 2,290.00 Sundries 10 Percent 229.00 Total 2,519.00

Contractor's Profit & Overheads 20 Percent 503.80 Total for 40 Sft. 3,022.80 Rate Per Sft 3022.80 = 75.57

40

Item Rates

Labour Rate Per Sft Rs. 75.57 Say 75.55 Labour Rate Per Sqm Rs. 813.13 Say 813.15

Composite Rate Per Sft Rs. 242.44 Say 242.45 Composite Rate Per Sqm Rs. 2,608.64 Say 2,608.65

Page 86: Rate analsis Chapter No. 12 (Wood Work)

Page 86

Item No. 26 Providing/ fixing ward robe 22" (550mm) deep consisting of RCC shelves 1-½" (40mm) thick I/c ½"

(12mm) thick vin board boxing and back (one sideply) vin board shutter ¾" (20mm) thick I/c Deodarwood lipping ¼"(6mm) on all edges fixes I/c deodarwood frame 3"x1" with hanger rod in centre portiondrawers at bottom and openable shutter on upperportion I/c full hinges C.P. fitting and painting 3coats.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 7.5' x 7' = 52.50 Sft

Material

RCC shelves (Precast RCC 1x1-½x3 top

and bottom

2x7-¼x2x1/8 3.62 Cft4x2-½x2x1/8 2.50 Cft

6.12 Cft 79.92 P. Cft 489.10 Steel Reinforcement

6.12x1.50 9.18 Kg 17.00 P. Kg 156.06

½" thick vin board (one side ply) for

boxing.

Top/ Bottom 6x2x2-¼x1-7/8 50.63 SftSide 6x2x1-1/8x1-7/8 25.31 SftBack 6x2-¼x1-1/8 15.18 SftTop/ Bottom 3x2x2-¼x1-7/8 25.31 SftVertical 6x2x1-¼x1-7/8 28.12 SftSide 2x4x1-7/8 15.00 SftBack 3x2x2-¼x1-¼ 16.87 SftBack 1x2-¼x4 9.00 Sft

185.42 SftWastage 10% 18.54 Sft

203.96 Sft 21.10 Sft 4,303.56 Vin board ¾" thick on both side ply

6x2-¼x1-¼ 16.87 Sft3x4x2-¼ 27.00 Sft

43.87 SftWastage 10% 4.38 Sft

48.25 Sft 24.00 Sft 1,158.00

Page 87: Rate analsis Chapter No. 12 (Wood Work)

Page 87

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Deodar Wood

Frame 4x7x3/12x1/12 0.58 CftFrame 4x7-½x3/12x1/12 0.62 CftLipping 3x6x2-¼x1/16x1/24 0.11 CftLipping 6x2x1-1/8x1/16x1/24 0.04 CftLipping 2x3x4x1/16x1/24 0.06 Cft

For drawers side supporting

3x2x1-7/8x1/12x1/24 0.04 CftDrawers 3x2-¼x1-1/8x1/24 0.32 CftSide 2x3x1-7/8x1-1/8x1/24 0.53 Cft

2.30 CftWastage 35% 0.81 Cft

3.11 Cft 550.00 P. Cft 1,710.50 Hard Board for drawers

3x2-¼x1-7/8(3x0.686x0.573=1.179 12.65 SftWastage 10% 1.26 Sft

13.91 Sft 3.50 Sft 48.69 Full hinges ¾" (20mm) wide (Imported)

3x4 (3x1.219 = 3.657) 12.00 Rft3x1-1/8 (3x0.343 = 1.029) 3.37 Rft

15.37 RftWastage 5% (Add Wastage 5%) 0.76 Rft

16.13 Rft 7.20 Rft 116.14

C.P. Handle 9.00 Nos 8.00 Each 72.00 Catcher (Germany) 9.00 Nos 6.40 Each 57.60 China Lock (Glone) 3.00 Nos 24.00 Each 72.00 Rawal Plug 1½" (40mm) 30.00 Nos 0.30 Each 9.00 Screws above 1" long 2.50 Doz 3.25 P. Doz 8.13 C.P. Hanger rod with 2 hooks 1.00 No 96.00 Each 96.00 C.P. Hooks 2.00 Nos 8.00 Each 16.00

Page 88: Rate analsis Chapter No. 12 (Wood Work)

Page 88

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Glue 2.00 Kg 80.00 P. Kg 160.00 Nail L.S. 32.00 Painting 4(7½ x 7) 2.86 Gln. 17.00 P. Gln. 48.62

Total 8,553.39 Contractor's Profit & Overheads 20 Percent 1,710.68 Total for 52.50 Sft. 10,264.07 Rate Per Sft 10264.07 = 195.51

52.50Labour

Labour for making ward robe complete 52.50 Sft 29.00 Sft 1,522.50

Total 1,522.50 Sundries 10 Percent 152.25 Total 1,674.75

Contractor's Profit & Overheads 20 Percent 334.95 Total 2,009.70 Rate Per Sft 2009.70 = 38.28

52.50

Item Rates

Labour Rate Per Sft Rs. 38.28 Say 38.30 Labour Rate Per Sqm Rs. 411.89 Say 411.90

Composite Rate Per Sft Rs. 233.79 Say 233.80 Composite Rate Per Sqm Rs. 2,515.54 Say 2,515.55

Page 89: Rate analsis Chapter No. 12 (Wood Work)

Page 89

DESCRIPTION OF ITEM NO 27: Providing and fixing chowkhat for doors, window,& C. Windows including hold fast etc.

a) Teak Wood.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Teak Wood

Top Rail 1x4¾x3"x4½" 0.45 CftVertical Rail 2x7x3"x4½" 1.33 Cft

1.78 CftWastage 12% 0.22 Cft

2.00 Cft 1400.00 P. Cft 2,800.00 Iron hold fast 6.00 Nos 12.00 Each 72.00

Total 2,872.00 Contractor's Profit & Overheads 20 Percent 574.40 Total for 27 Sft. 3,446.40 Rate Per Sft 3446.40 = 127.64

27Labour

Carpenter 0.70 No 300.00 P. Day 210.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00

Total 290.00 Sundries 10 Percent 29.00 Total 319.00

Contractor's Profit & Overheads 20 Percent 63.80 Total for 27 Sft. 382.80 Rate Per Sft 382.80 = 14.18

27

Item Rates

Labour Rate Per Sft Rs. 14.18 Say 14.20 Labour Rate Per Sqm Rs. 152.55 Say 152.55

Composite Rate Per Sft Rs. 141.82 Say 141.80 Composite Rate Per Sqm Rs. 1,526.01 Say 1,526.00

Page 90: Rate analsis Chapter No. 12 (Wood Work)

Page 90

Item No. 27 Providing and fixing chowkhat for doors windows& C. Windows including hold fast etc.

b) Deodar Wood.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

For Frame

Top Rail 1x4¾'x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 Cft

1.78 CftWastage 15% 0.27 Cft

2.05 Cft 550.00 P. Cft 1,127.50 Iron hold fast 6.00 Nos 12.00 Each 72.00

Total 1,199.50 Contractor's Profit & Overheads 20 Percent 239.90 Total for 27 Sft. 1,439.40 Rate Per Sft 1439.40 = 53.31

27Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00

Total 190.00 Sundries 10 Percent 19.00 Total 209.00

Contractor's Profit & Overheads 20 Percent 41.80 Total for 27 Sft. 250.80 Rate Per Sft 250.80 = 9.29

27

Item Rates

Labour Rate Per Sft Rs. 9.29 Say 9.30 Labour Rate Per Sqm Rs. 99.95 Say 99.95

Composite Rate Per Sft Rs. 62.60 Say 62.60 Composite Rate Per Sqm Rs. 673.58 Say 673.60

Page 91: Rate analsis Chapter No. 12 (Wood Work)

Page 91

Item No. 27 Providing and fixing chowkhat for doors, windows,& C. Windows including hold fast etc.

c) Shisham Wood.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Shishim Wood

Top Rail 1x4¾'x3"x4½" 0.45 CftVertical Rail 2x7'x3"x4½" 1.33 Cft

1.78 CftWastage 15% 0.27 Cft

2.05 Cft 300.00 P. Cft 614.10 Iron hold fast 6.00 Nos 12.00 Each 72.00

Total 686.10 Contractor's Profit & Overheads 20 Percent 137.22 Total for 27 Sft. 823.32 Rate Per Sft 823.32 = 30.49

27Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.40 No 160.00 P. Day 64.00

Total 214.00 Sundries 10 Percent 21.40 Total 235.40

Contractor's Profit & Overheads 20 Percent 47.08 Total for 27 Sft. 282.48 Rate Per Sft 282.48 = 10.46

27

Item Rates

Labour Rate Per Sft Rs. 10.46 Say 10.45 Labour Rate Per Sqm Rs. 112.57 Say 112.55

Composite Rate Per Sft Rs. 40.96 Say 40.95 Composite Rate Per Sqm Rs. 440.68 Say 440.70

Page 92: Rate analsis Chapter No. 12 (Wood Work)

Page 92

DESCRIPTION OF ITEM NO 28:Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.

a) 1" (25mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 9.50 Cft 500.00 P. Cft 4,750.00 Nail & Screws bolt and brackets L.S. 24.00

Total 4,774.00 Contractor's Profit & Overheads 20 Percent 954.80 Total for 100 Sft. 5,728.80 Rate Per Sft 5728.80 = 57.29

100Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 75.24 Say 75.25 Composite Rate Per Sqm Rs. 809.58 Say 809.60

Page 93: Rate analsis Chapter No. 12 (Wood Work)

Page 93

Item No. 28 Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.

b) ¾" (20mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 7.12 Cft 500.00 P. Cft 3,560.00 Asscessories for fixing L.S. 24.00

Total 3,584.00 Contractor's Profit & Overheads 20 Percent 716.80 Total for 100 Sft. 4,300.80 Rate Per Sft 4300.80 = 43.01

100Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 60.96 Say 60.95 Composite Rate Per Sqm Rs. 655.93 Say 655.95

Page 94: Rate analsis Chapter No. 12 (Wood Work)

Page 94

Item No. 28 Making & fixing deodar wood planking in eaveboards etc. planed on both side related & fixedincluding nails & screws, bolt & brackets.

c) ½" (12mm) Thick

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 4.75 Cft 500.00 P. Cft 2,375.00 Asscessories for fixing L.S. 24.00

Total 2,399.00 Contractor's Profit & Overheads 20 Percent 479.80 Total for 100 Sft. 2,878.80 Rate Per Sft 2878.80 = 28.79

100Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 46.74 Say 46.75 Composite Rate Per Sqm Rs. 502.92 Say 502.90

Page 95: Rate analsis Chapter No. 12 (Wood Work)

Page 95

DESCRIPTION OF ITEM NO 29:Making and fixing deodar wood shelves,including brackets.

i) 1" (25mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 9.50 Cft 500.00 P. Cft 4,750.00 Accessoires for fitting L.S. 24.00

Total 4,774.00 Contractor's Profit & Overheads 20 Percent 954.80 Total for 100 Sft. 5,728.80 Rate Per Sft 5728.80 = 57.29

100Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 75.24 Say 75.25 Composite Rate Per Sqm Rs. 809.58 Say 809.60

Page 96: Rate analsis Chapter No. 12 (Wood Work)

Page 96

Item No. 29 Making and fixing deodar wood shelves,including brackets.

ii) 1½" (40mm) Thick

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 14.25 Cft 500.00 P. Cft 7,125.00 Asscessories for fixing L.S. 24.00

Total 7,149.00 Contractor's Profit & Overheads 20 Percent 1,429.80 Total for 100 Sft. 8,578.80 Rate Per Sft 8578.80 = 85.79

100

Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 103.74 Say 103.75 Composite Rate Per Sqm Rs. 1,116.24 Say 1,116.25

Page 97: Rate analsis Chapter No. 12 (Wood Work)

Page 97

Item No. 29 Making and fixing deodar wood shelves,including brackets.

iii) 2" (50mm) Thick.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 100 Sft

Material

Deodar Wood 19.00 Cft 500.00 P. Cft 9,500.00 Asscessories for fixing L.S. 24.00

Total 9,524.00 Contractor's Profit & Overheads 20 Percent 1,904.80 Total for 100 Sft. 11,428.80 Rate Per Sft 11428.80 = 114.29

100Labour

Carpenters 4.00 Nos 300.00 P. Day 1,200.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00

Contractor's Profit & Overheads 20 Percent 299.20 Total for 100 Sft. 1,795.20 Rate Per Sft 1795.20 = 17.95

100

Item Rates

Labour Rate Per Sft Rs. 17.95 Say 17.95 Labour Rate Per Sqm Rs. 193.16 Say 193.15

Composite Rate Per Sft Rs. 132.24 Say 132.25 Composite Rate Per Sqm Rs. 1,422.90 Say 1,422.90

Page 98: Rate analsis Chapter No. 12 (Wood Work)

Page 98

DESCRIPTION OF ITEM NO 30: a) Making and fixing cleats for doors and windows including hinges and screws.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 10 Nos

Material

Hinges 2" (50mm) 10.00 Nos 2.50 Each 25.00 Screws 1" (25mm) 3.50 Doz 3.25 P. Doz 11.38 Deodar wood 0.21 Cft 500.00 P. Cft 105.00

Total 141.38 Contractor's Profit & Overheads 20 Percent 28.28 Total 169.65

Labour

Carpenters 0.40 No 300.00 P. Day 120.00 Skilled Cooly 0.20 No 160.00 P. Day 32.00

Total 152.00 Sundries 10 Percent 15.20 Total 167.20

Contractor's Profit & Overheads 20 Percent 33.44 Total 200.64

Item Rates

Labour Rate for Each Rs. 200.64 20.06 Say 20.05 10

Composite Rate for Each Rs. 370.29 37.03 Say 37.05 10

Page 99: Rate analsis Chapter No. 12 (Wood Work)

Page 99

Item No. 30 b) Making and fixing cleats with brass hooks for roofventilator.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Brass hooks 1 No 4.00 Each 4.00 Deodar Wood 0.01 Cft 500.00 P. Cft 5.00 Screws/ Nails 2.00 Nos 3.25 P. Doz 0.44

Total 9.44 Contractor's Profit & Overheads 20 Percent 1.89 Total 11.33

Labour for 1.25 Nos.

Carpenter 0.05 No 300.00 P. Day 15.00 Skilled Cooly 0.05 No 160.00 P. Day 8.00

Total 23.00 Sundries 10 Percent 2.30 Total 25.30

Contractor's Profit & Overheads 20 Percent 5.06 Total 30.36

Item Rates

Labour Rate for Each Rs. 30.36 24.29 Say 24.30 1.25

Composite Rate for Each Rs. 35.62 Say 35.60

Page 100: Rate analsis Chapter No. 12 (Wood Work)

Page 100

Item No. 30 c) Providing and fixing door stops of 1½" (40mm)dia rubber block.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 30 Nos

Material

Door rubber stopper 30.00 Nos 2.80 Each 84.00 Gutty 30.00 Nos 0.25 Each 7.50 Screws 2.50 Doz 3.25 P. Doz 8.13

Total 99.62 Contractor's Profit & Overheads 20 Percent 19.92 Total 119.55

Labour

Carpenter 0.25 No 300.00 P. Day 75.00

Total 75.00 Sundries 10 Percent 7.50 Total 82.50

Contractor's Profit & Overheads 20 Percent 16.50 Total 99.00

Item Rates

Labour Rate for Each Rs. 99.00 3.30 Say 3.30 30

Composite Rate for Each Rs. 218.55 7.28 Say 7.30 30

Page 101: Rate analsis Chapter No. 12 (Wood Work)

Page 101

Item No. 30 d) Providing and fixing G.I. hook with clamps fordoors.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

G.I. Hook 1.00 No 2.00 Each 2.00 Gutty 1.00 No 0.25 Each 0.25

Total 2.25 Contractor's Profit & Overheads 20 Percent 0.45 Total 2.70

Labour (Labour for 30 No.)

Carpenter 0.08 No 300.00 P. Day 24.00

Total 24.00 Sundries 10 Percent 2.40 Total 26.40

Contractor's Profit & Overheads 20 Percent 5.28 Total 31.68

Item Rates

Labour Rate for Each Rs. 31.68 1.06 Say 1.05 30

Composite Rate for Each Rs. 3.76 Say 3.75

Page 102: Rate analsis Chapter No. 12 (Wood Work)

Page 102

DESCRIPTION OF ITEM:

Item No. 31 Hard wood railing of any shape and designincluding bends and corners fixed in positionincluding polishing complete as directed by Engineer Incharge.

a) Shisham Wood.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 12 Rft

Material

Shisham wood 0.90 Cft 300.00 P. Cft 270.00 Sand paper 3.00 Nos 6.00 Each 18.00 Polishing material 0.075 Kg. 160.00 P. Kg. 12.00

Total 300.00 Contractor's Profit & Overheads 20 Percent 60.00 Total 12 Rft. 360.00 Rate Per Rft 360.00 = 30.00

12Labour

Carpenters 1.50 No 300.00 P. Day 450.00 Skilled Cooly 0.75 No 160.00 P. Day 120.00 Polisher 0.50 No 170.00 P. Day 85.00

Total 655.00 Sundries 10 Percent 65.50 Total 720.50

Contractor's Profit & Overheads 20 Percent 144.10 Total for 12 Rft. 864.60 Rate Per Rft 864.60 = 72.05

12Item Rates

Labour Rate Per Rft Rs. 72.05 Say 72.05 Labour Rate Per Rm Rs. 236.32 Say 236.30

Composite Rate Per Rft Rs. 102.05 Say 102.05 Composite Rate Per Rm Rs. 334.72 Say 334.70

Page 103: Rate analsis Chapter No. 12 (Wood Work)

Page 103

Item No. 31 Hard wood railing of any shape and designincluding bends and corners fixed in positionincluding polishing complete as directed by Engineer Incharge.

b) Teak Wood.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 10 Rft

Material

Teak wood 0.90 Cft 1400.00 P. Cft 1,260.00 Sand paper 3.00 Nos 6.00 Each 18.00 Polishing material 0.075 Kg. 160.00 P. Kg. 12.00

Total 1,290.00 Contractor's Profit & Overheads 20 Percent 258.00 Total for 10 Rft. 1,548.00 Rate Per Rft 1548.00 = 154.80

10Labour

Carpenters 1.00 No. 300.00 P. Day 300.00 Skilled Cooly 0.50 No 160.00 P. Day 80.00 Polisher 0.20 No 170.00 P. Day 34.00

Total 414.00 Sundries 10 Percent 41.40 Total 455.40

Contractor's Profit & Overheads 20 Percent 91.08 Total for 10 Rft. 546.48 Rate Per Rft 546.48 = 54.65

10

Item Rates

Labour Rate Per Rft Rs. 54.65 Say 54.65 Labour Rate Per Rm Rs. 179.26 Say 179.25

Composite Rate Per Rft Rs. 209.45 Say 209.45 Composite Rate Per Rm Rs. 687.00 Say 687.00

Page 104: Rate analsis Chapter No. 12 (Wood Work)

Page 104

DESCRIPTION OF ITEM NO 32:Deodar wood dado or Picture Rail 3"x1½"(50x40mm) as per approved design includingmoulding and fixed in place, cost of screws nails,plugs and painting complete.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 10 Rft

Material

Deodar wood 0.60 Cft 500.00 P. Cft 300.00 Sand paper 1.00 Sht 6.00 P. Sht 6.00 Rawal Plugs 0.50 No 0.30 Each 0.15 Screws 0.50 Doz 3.25 P. Doz 1.63 Polishing material 0.038 Kg. 160.00 P. Kg. 6.00

Total 313.78 Contractor's Profit & Overheads 20 Percent 62.76 Total for 10 Rft. 376.53 Rate Per Rft 376.53 = 37.65

10Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Skilled Cooly 0.25 No 160.00 P. Day 40.00 Polisher 0.10 No 170.00 P. Day 17.00

Total 207.00 Sundries 10 Percent 20.70 Total 227.70

Contractor's Profit & Overheads 20 Percent 45.54 Total for 10 Rft. 273.24 Rate Per Rft 273.24 = 27.32

10

Item Rates

Labour Rate Per Rft Rs. 27.32 Say 27.30 Labour Rate Per Rm Rs. 89.62 Say 89.60

Composite Rate Per Rft Rs. 64.98 Say 65.00 Composite Rate Per Rm Rs. 213.12 Say 213.15

Page 105: Rate analsis Chapter No. 12 (Wood Work)

Page 105

DESCRIPTION OF ITEM NO 33: Sawing wood by hand.

a) Soft wood (Deodar Kail, Chir)

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 300 Sft

Labour

Sawyer 1.50 Nos 170.00 P. Day 255.00 Skilled Cooly 1.50 Nos 160.00 P. Day 240.00

Total 495.00 Sundries 10 Percent 49.50 Total 544.50

Contractor's Profit & Overheads 20 Percent 108.90 Total 653.40

Item Rates

Labour Rate Per 100 Sft Rs. 653.40 x 100 =154.28 Say 217.80 300

Labour Rate Per Sqm Rs. 23.44 Say 23.45

Page 106: Rate analsis Chapter No. 12 (Wood Work)

Page 106

Item No. 33: Sawing wood by hand.

b) Hard Wood (Shisham, Kikar, Sal or Teak)

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit Amount

Rate Analysis for = 450 Sft

Labour

Sawyer 3.00 Nos 170.00 P. Day 510.00 Skilled Cooly 3.00 Nos 160.00 P. Day 480.00

Total 990.00 Sundries 10 Percent 99.00 Total 1,089.00

Contractor's Profit & Overheads 20 Percent 217.80 Total 1,306.80

Item Rates

Labour Rate Per 100 Sft Rs. 1306.80 x 100=205.7 Say 290.40 450

Labour Rate Per Sqm Rs. 31.25 Say 31.25

Page 107: Rate analsis Chapter No. 12 (Wood Work)

Page 107

DESCRIPTION OF ITEM NO 34: Sawing wood by machine.

a) Soft Wood.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 300 Sft

Labour

Sawyer 1.00 No 170.00 P. Day 170.00 Skilled Cooly 0.77 No 160.00 P. Day 123.20

Total 293.20 Sundries 10 Percent 29.32 Total 322.52

Contractor's Profit & Overheads 20 Percent 64.50 Total 387.02

Item Rates

Labour Rate Per 100 Sft Rs. 387.02 x 100=94.97 Say 129.01 300

Labour Rate Per Sqm Rs. 13.88 Say 13.90

Page 108: Rate analsis Chapter No. 12 (Wood Work)

Page 108

Item No. 34 Sawing wood by machine.

b) Hard Wood.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 300 Sft

Labour

Sawyer 1.50 Nos 170.00 P. Day 255.00 Skilled Cooly 1.16 Nos 160.00 P. Day 185.60

Total 440.60 Sundries 10 Percent 44.06 Total 484.66

Contractor's Profit & Overheads 20 Percent 96.93 Total 581.59

Item Rates

Labour Rate Per 100 Sft Rs. 581.59 x 100=142.62 Say 193.85 300 193.86

Labour Rate Per Sqm Rs. 20.86 Say 20.85

Page 109: Rate analsis Chapter No. 12 (Wood Work)

Page 109

DESCRIPTION OF ITEM NO 35: Making and fixing sun shade of deodar woodincluding fixing brackets.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 5 Sft

Material

Deodar Wood

Horizontal Planks

Top 4x5x1/3x1/24 0.28 CftVertical 2x1¾x1/6x5/68 0.06 CftSupports along sun shade 0.04 Cft2x3/2x1/8x5/48

Suporting brackets 2x1x1/8x5/48 0.03 CftFront ears hard strips 1x5x1/4x1/12 0.10 Cft

0.51 CftWastage 10% 0.05 Cft

0.56 Cft 500.00 P. Cft 280.00 Sawing & Nails L.S. 8.00

Total 288.00 Contractor's Profit & Overheads 20 Percent 57.60 Total for 5 Sft. 345.60 Rate Per Sft 345.60 = 69.12

5Labour

Carpenter 0.25 No 300.00 P. Day 75.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00

Total 91.00 Sundries 10 Percent 9.10 Total 100.10

Contractor's Profit & Overheads 20 Percent 20.02 Total for 5 Sft. 120.12 Rate Per Sft 120.12 = 24.02

5Item Rates

Labour Rate Per Sft Rs. 24.02 Say 24.00 Labour Rate Per Sqm Rs. 258.50 Say 258.50

Composite Rate Per Sft Rs. 93.14 Say 93.15 Composite Rate Per Sqm Rs. 1,002.23 Say 1,002.25

Page 110: Rate analsis Chapter No. 12 (Wood Work)

Page 110

DESCRIPTION OF ITEM NO 36: Making and fixing 1" (25mm) thick Kail or Chirwooden notice board with frame.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 18 Sft

Material

Kail or Chir Wood 1.64 Cft 350.00 P. Cft 574.00 Nails 0.093 Kg. 43.00 P. Kg. 4.00 Glue 0.075 Kg. 80.00 P. Kg. 6.00 Iron Hook 1.00 No. 2.00 Each 2.00

Total 586.00 Contractor's Profit & Overheads 20 Percent 117.20 Total for 18 Sft. 703.20 Rate Per Sft 703.20 = 39.07

18Labour

Carpenter 0.75 No 300.00 P. Day 225.00 Cooly Skilled 0.75 No 160.00 P. Day 120.00

Total 345.00 Sundries 10 Percent 34.50 Total 379.50

Contractor's Profit & Overheads 20 Percent 75.90 Total for 18 Sft. 455.40 Rate Per Sft 455.40 = 25.30

18

Item Rates

Labour Rate Per Sft Rs. 25.30 Say 25.30 Labour Rate Per Sqm Rs. 272.23 Say 272.25

Composite Rate Per Sft Rs. 64.37 Say 64.35 Composite Rate Per Sqm Rs. 692.59 Say 692.60

Page 111: Rate analsis Chapter No. 12 (Wood Work)

Page 111

DESCRIPTION OF ITEM NO 37: Making deodar Punkha Pole = 10'x6"x6"(3.047x0.150x0.150M).

Detail Unit Rate (British System) per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Deodar wood 2.50 Cft 500.00 P. Cft 1,250.00 Hooks 2.00 Doz 12.00 P. Doz 24.00

Total 1,274.00 Contractor's Profit & Overheads 20 Percent 254.80 Total 1,528.80

Labour

Carpenter 0.20 No 300.00 P. Day 60.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00

Total 76.00 Sundries 10 Percent 7.60 Total 83.60

Contractor's Profit & Overheads 20 Percent 16.72 Total 100.32

Item Rates

Labour Rate for Each Rs. 100.32 Say 100.30

Composite Rate for Each Rs. 1629.12 Say 1,629.10

Page 112: Rate analsis Chapter No. 12 (Wood Work)

Page 112

DESCRIPTION OF ITEM NO 38: Dismantling and refixing eaves boards.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 70 Rft

Labour

Carpenter 1.00 No 300.00 P. Day 300.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00

Total 380.00 Sundries 10 Percent 38.00 Total 418.00

Contractor's Profit & Overheads 20 Percent 83.60 Total 501.60

Item Rates

Labour Rate Per Rft Rs. 501.60 7.17 Say 7.15 70

Labour Rate Per Rm Rs. 23.51 Say 23.50

Page 113: Rate analsis Chapter No. 12 (Wood Work)

Page 113

DESCRIPTION OF ITEM NO 39: Making wooden stair cases complete 2' to 3' (600 to915mm) wide frame 1½" (40mm) thick planks ofdeodar wood, including hand rails.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 15 Rft

Material

Deodar Wood

Detail of Deodar Wood

2x5/6x15x1/8 3.12 CftStops 14x2½x1/8x5/6 3.65 Cftand Rail 2x15x¼x¼ 1.88 Cftand Rail 2x4x3x¼x¼ 1.50 Cft

10.15 CftWastage L. S. 0.35 Cft

10.50 Cft 500.00 P. Cft 5,250.00 Nails 0.93 Kg 28.00 P. Kg 26.04 Bolts ½" to 3" (12 to 76mm) long 5.880 Kg. 45.00 P. Kg 264.60 Steel rods dia ¾ 3x3'-6" = 10.5 Rft 15.3Lb (7 .5Kg) 17.00 P. Kg 127.50 Washers 12.00 Nos 0.50 Each 6.00

Total 5,674.14 Contractor's Profit & Overheads 20 Percent 1,134.83 Total for 15 Rft. 6,808.97 Rate Per Rft 6808.97 = 453.93

15Labour

Carpenter 2.00 Nos 300.00 P. Day 600.00 Blacksmith 0.50 No 170.00 P. Day 85.00 Hammer-man 0.50 No 75.00 P. Day 37.50 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00

Total 1,042.50 Sundries 10 Percent 104.25 Total 1,146.75 Contractor's Profit & Overheads 20 Percent 229.35 Total for 15 Rft. 1,376.10 Rate Per Rft 1376.10 = 91.74

15Item Rates

Labour Rate Per Rft Rs. 91.74 Say 91.75 Labour Rate Per Rm Rs. 300.91 Say 300.90

Composite Rate Per Rft Rs. 545.67 Say 545.65 Composite Rate Per Rm Rs. 1,789.80 Say 1,789.80

Page 114: Rate analsis Chapter No. 12 (Wood Work)

Page 114

DESCRIPTION OF ITEM NO 40: Providing and fixing partition including frame work.a - (i) Sheets on one side of frame work.

Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Hard Board Sheet

1x8x16 128.00 SftWastage 5% 6.40 Sft

134.40 Sft 3.50 Sft 470.40 Deodar Wood & other Accessories

Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 Cft 2x8x3"x2½" 0.83 Cft 3x8x2"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 P. Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50

Total 2,732.11 Contractor's Profit & Overheads 20 Percent 546.42 Total for 128 Sft. 3,278.53 Rate Per Sft 3278.53 x 100 = 2,561.35

128Labour

Carpenter 1.00 Nos 300.00 P. Day 300.00 Cooly Skilled 1.00 Nos 160.00 P. Day 160.00

Total 460.00 Sundries 10 Percent 46.00 Total 506.00 Contractor's Profit & Overheads 20 Percent 101.20 Total for 128 Sft. 607.20 Rate Per Sft 607.20 x 100 = 474.38

128Item Rates

Labour Rate Per 100 Sft Rs. 474.38 Say 474.40 Labour Rate Per Sqm Rs. 51.04 Say 51.05

Composite Rate Per 100 Sft Rs. 3,035.73 Say 3,035.75 Composite Rate Per Sqm Rs. 326.64 Say 326.65

Page 115: Rate analsis Chapter No. 12 (Wood Work)

Page 115

Item No. 40 Providing and fixing partition including frame work.a - (ii) Ply wood ¼" (6mm) thick.

One Side.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Ply Wood 1x8'x16 128.00 SftWastage 5% 6.40 Sft

134.40 Sft 10.00 Sft 1,344.00 Deodar Wood

Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 CftVertical post 3x8x2½"x2½" 0.83 CftVertical post 3x8x2½"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50

Total 3,605.71 Contractor's Profit & Overheads 20 Percent 721.14 Total for 128 Sft. 4,326.85 Rate Per Sft 4326.85 x 100 = 3,380.35

128Labour

Carpenter 1.00 Nos 300.00 P. Day 300.00 Cooly Skilled 1.00 Nos 160.00 P. Day 160.00

Total 460.00 Sundries 10 Percent 46.00 Total 506.00 Contractor's Profit & Overheads 20 Percent 101.20 Total for 128 Sft. 607.20 Rate Per Sft 607.20 x 100 = 474.38

128Item Rates

Labour Rate Per 100 Sft Rs. 474.38 Say 474.40 Labour Rate Per Sqm Rs. 51.04 Say 51.05

Composite Rate Per 100 Sft Rs. 3,854.73 Say 3,854.75 Composite Rate Per Sqm Rs. 414.77 Say 414.75

Page 116: Rate analsis Chapter No. 12 (Wood Work)

Page 116

Item No. 40 Providing and fixing partition including frame work.a - (iii) Masonite sheet.

One Side.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Masonite sheet 1x8x16 128.00 SftWastage 5% 6.40 Sft

134.40 Sft 22.00 Sft 2,956.80 Deodar Wood & other Accessories

Frame work 2x16x3"x2½" 1.67 CftHorizontal post 1x16x2"x2½" 0.56 Cft 2x8x3"x2½" 0.83 Cft3x8x2"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.47 Kg 43.00 P. Kg 20.21 Screws 2.00 Doz 3.25 P. Doz 6.50

Total 5,218.51 Contractor's Profit & Overheads 20 Percent 1,043.70 Total for 128 Sft. 6,262.21 Rate Per Sft 6262.21 x 100 = 4,892.35

128Labour

Carpenter 1.00 Nos 170.00 P. Day 170.00 Cooly Skilled 1.00 Nos 85.00 P. Day 85.00

Total 255.00 Sundries 10 Percent 25.50 Total 280.50 Contractor's Profit & Overheads 20 Percent 56.10 Total for 128 Sft. 336.60 Rate Per Sft 336.60 x 100 = 262.97

128Item Rates

Labour Rate Per 100 Sft Rs. 262.97 Say 262.95 Labour Rate Per Sqm Rs. 28.30 Say 28.30

Composite Rate Per 100 Sft Rs. 5,155.32 Say 5,155.30 Composite Rate Per Sqm Rs. 554.71 Say 554.70

Page 117: Rate analsis Chapter No. 12 (Wood Work)

Page 117

Item No. 40 Providing and fixing partition including frame work.b (1) Sheets on both sides of frame work.

Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Hard Board Sheet

2 x 16 x 8 256.00 SftWastage 5% 12.80 Sft

268.80 Sft 3.50 Sft 940.80 Deodar Wood & other Accessories

Horizontal Post.

2x16x3"x2½" 1.67 Cft 1x16x2"x2½" 0.56 CftVertical post 2x8x3"x2½" 0.83 Cft 3x8x2"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws of all sorts 2.00 Doz 3.25 P. Doz 6.50 Total 3,212.40 Contractor's Profit & Overheads 20 Percent 642.48 Total for 128 Sft. 3,854.88 Rate Per Sft 3854.88 x 100 = 3,011.63

128Labour

Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00

Total 552.00 Sundries 10 Percent 55.20 Total 607.20 Contractor's Profit & Overheads 20 Percent 121.44 Total for 128 Sft. 728.64 Rate Per Sft 728.64 x 100 = 569.25

128

Item Rates

Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25

Composite Rate Per 100 Sft Rs. 3,580.88 Say 3,580.90 Composite Rate Per Sqm Rs. 385.30 Say 385.30

Page 118: Rate analsis Chapter No. 12 (Wood Work)

Page 118

Item No. 40 Providing and fixing partition including frame work.b - (ii) Ply wood. ¼" (6mm) thick

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Ply Wood Sheet 2 x 16 x 8 (2 x 4.876 x 256.00 Sft2.438) = 23.78 M²

Wastage 5% 12.80 Sft268.80 Sft 10.50 Sft 2,822.40

Deodar Wood for frame work

Horizontal post 2x16x3"x2½" 1.67 CftCross 1x16x2"x2½" 0.56 CftVertical post 2x8x3"x2½" 0.83 CftVertical post 3x8x2"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 550.00 P. Cft 2,458.50 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws 3.00 Doz 3.25 P. Doz 9.75 Total 5,320.75 Contractor's Profit & Overheads 20 Percent 1,064.15 Total for 128 Sft. 6,384.90 Rate Per Sft 6384.90 x 100 = 4,988.20

128Labour

Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00

Total 552.00 Sundries 10 Percent 55.20 Total 607.20

Contractor's Profit & Overheads 20 Percent 121.44 Total for 128 Sft. 728.64 Rate Per Sft 728.64 x 100 = 569.25

128Item Rates

Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25

Composite Rate Per 100 Sft Rs. 5,557.45 Say 5,557.45 Composite Rate Per Sqm Rs. 597.98 Say 598.00

Page 119: Rate analsis Chapter No. 12 (Wood Work)

Page 119

Item No. 40 Providing and fixing partition including frame work.b - (iii) Masonite sheet.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 128 Sft

Material

Masonite sheet 2x16'x8' 256.00 SftWastage 5% 12.80 Sft

268.80 Sft 22.00 Sft 5,913.60 Deodar Wood & other Accessories

Horizontal Post.

2x16x3"x2½" 1.67 Cft 1x16x2"x2½" 0.56 CftVertical post 2x8x3"x2½" 0.83 Cft 3x8x2"x2½" 0.83 Cft

3.89 CftWastage 15% 0.58 Cft

4.47 Cft 500.00 P. Cft 2,235.00 Nails of all sorts 0.70 Kg 43.00 P. Kg 30.10 Screws 2.00 Doz 3.25 P. Doz 6.50 Total 8,185.20 Contractor's Profit & Overheads 20 Percent 1,637.04 Total 9,822.24 Rate Per Sft 9822.24 x 100 = 7,673.63

128Labour

Carpenter 1.20 Nos 300.00 P. Day 360.00 Cooly Skilled 1.20 Nos 160.00 P. Day 192.00

Total 552.00 Sundries 10 Percent 55.20 Total 607.20 Contractor's Profit & Overheads 20 Percent 121.44 Total 728.64 Rate Per Sft 728.64 x 100 = 569.25

128Item Rates

Labour Rate Per 100 Sft Rs. 569.25 Say 569.25 Labour Rate Per Sqm Rs. 61.25 Say 61.25

Composite Rate Per 100 Sft Rs. 8,242.88 Say 8,242.90 Composite Rate Per Sqm Rs. 886.93 Say 886.95

Page 120: Rate analsis Chapter No. 12 (Wood Work)

Page 120

DESCRIPTION OF ITEM NO 41: Providing and fixing ceiling including frame work.i) Hard Board.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 192 Sft

Material

Hard Board 16x12 192.00 Sft 3.50 Sft 672.00

Partal Wood

7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft

6.88 CftWastage 10% 0.69 Cft

7.57 Cft 350.00 P. Cft 2,649.50 Hard Wood Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 3,674.29 Contractor's Profit & Overheads 20 Percent 734.86 Total for 192 Sft. 4,409.15 Rate Per Sft 4409.15 x 100 = 2,296.43

192Labour

Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00

192Item Rates

Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60

Composite Rate Per 100 Sft Rs. 3,231.43 Say 3,231.45 Composite Rate Per Sqm Rs. 347.70 Say 347.70

Page 121: Rate analsis Chapter No. 12 (Wood Work)

Page 121

Item No. 41 Providing and fixing ceiling including frame work.ii) Chip Board Sheets.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 192 Sft

Material

Chip Board 1x16x12 192.00 Sft 16.40 Sft 3,148.80

Partal Wood & other Accessories

Partal Wood.

7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft

6.88 CftWastage 10% 0.69 Cft

7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 6,151.09 Contractor's Profit & Overheads 20 Percent 1,230.22 Total for 192 Sft. 7,381.31 Rate Per Sft 7381.31 x 100 = 3,844.43

192Labour

Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00

192Item Rates

Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60 Composite Rate Per 100 Sft Rs. 4,779.43 Say 4,779.45 Composite Rate Per Sqm Rs. 514.27 Say 514.25

Page 122: Rate analsis Chapter No. 12 (Wood Work)

Page 122

Item No. 41 Providing and fixing ceiling including framework.

iii) Ply Wood ¼" (6mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 192 Sft

Material

Ply Wood ¼" (6mm) 12x16 192.00 Sft 10.50 Sft 2,016.00

Partal Wood & other Accessories

Partal Wood :

7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft

6.88 CftWastage 10% 0.69 Cft

7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gutti 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grouting 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 5,018.29 Contractor's Profit & Overheads 20 Percent 1,003.66 Total for 192 Sft. 6,021.95 Rate Per Sft 6021.95 x 100 = 3,136.43

192Labour

Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 1.00 No 140.00 P. Day 140.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00

192Item Rates

Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60

Composite Rate Per 100 Sft Rs. 4,071.43 Say 4,071.45 Composite Rate Per Sqm Rs. 438.09 Say 438.10

Page 123: Rate analsis Chapter No. 12 (Wood Work)

Page 123

Item No. 41 Providing and fixing ceiling including frame work.iv) Masonite Sheet.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 192 Sft

Material

Masonite Sheet 1x16x12 192.00 Sft 24.00 Sft 4,608.00

Partal Wood & other Accessories

Partal Wood.

7x16x3"x1½" 3.50 Cft 9x16x3"x1½" 3.38 Cft

6.88 CftWastage 10% 0.69 Cft

7.57 Cft 350.00 P. Cft 2,649.50 Wooden Hand Gulli 32.00 Nos 2.00 Each 64.00 Screws 3.00 Doz 3.25 P. Doz 9.75 Nail 0.70 Kg 43.00 P. Kg 30.10 Cement for grating 0.178 Bag 230.00 P. Bag 40.94 M.S clamp 4.00 Nos 40.00 Each 160.00 M.S hook 4.00 Nos 12.00 Each 48.00 Total 7,610.29 Contractor's Profit & Overheads 20 Percent 1,522.06 Total for 192 Sft. 9,132.35 Rate Per Sft 9132.35 x 100 = 4,756.43

192Labour

Carpenter 3.00 Nos 300.00 P. Day 900.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly Unskilled 1.00 No 140.00 P. Day 140.00

Total 1,360.00 Sundries 10 Percent 136.00 Total 1,496.00 Contractor's Profit & Overheads 20 Percent 299.20 Total for 192 Sft. 1,795.20 Rate Per Sft 1795.20 x 100 = 935.00

192Item Rates

Labour Rate Per 100 Sft Rs. 935.00 Say 935.00 Labour Rate Per Sqm Rs. 100.61 Say 100.60

Composite Rate Per 100 Sft Rs. 5,691.43 Say 5,691.45 Composite Rate Per Sqm Rs. 612.40 Say 612.40

Page 124: Rate analsis Chapter No. 12 (Wood Work)

Page 124

Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.

a) Deodar wood frame panelling.i) ¾" (20mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore ¾" thick 144.00 SftWastage 5% 7.20 Sft

151.20 Sft 4.25 Sft 642.60 Deodar Wood

Frame Main 3x12¼x3"x2" 1.53 CftCross 3x12¼x1½"x2" 0.77 CftWooden Strips 12x1½"x½" 0.25 Cft

2.55 CftWastage 20% 0.51 Cft

3.06 Cft 500.00 P. Cft 1,530.00

Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.00 Each 32.00 Screws above 1" long 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25

Total 2,548.35 Contractor's Profit & Overheads 20 Percent 509.67 Total for 144 Sft. 3,058.02 Rate Per Sft 3058.02 x 100 = 2,123.63

144

Page 125: Rate analsis Chapter No. 12 (Wood Work)

Page 125

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenters 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00

Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00

Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00

144

Item Rates

Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45

Composite Rate Per 100 Sft Rs. 3,168.63 Say 3,168.65 Composite Rate Per Sqm Rs. 340.94 Say 340.95

Page 126: Rate analsis Chapter No. 12 (Wood Work)

Page 126

Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.

a) Deodar wood frame panellingii) 1" (25mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore 1" thick 144.00 SftWastage 5% 7.20 Sft

151.20 Sft 5.68 Sft 858.82 Deodar Wood

Frame Main 3x12¼x2"x3" 1.53 CftCross 3x12¼x1½"x2" 0.77 CftWooden Strips 4x12x1½"x½" 0.25 Cft

2.55 CftWastage 20% 0.51 Cft

3.06 Cft 500.00 P. Cft 1,530.00 Sawing charge 3.06 Cft 8.00 24.48 Making holes in walls L.S. 37.33 Screws of all sorts 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair L.S. 20.00

Total 2,728.23 Contractor's Profit & Overheads 20 Percent 545.65 Total for 144 Sft. 3,273.88 Rate Per Sft 3273.88 x 100 = 2,273.52

144

Page 127: Rate analsis Chapter No. 12 (Wood Work)

Page 127

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00

Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00

Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00

144

Item Rates

Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45

Composite Rate Per 100 Sft Rs. 3,318.52 Say 3,318.50 Composite Rate Per Sqm Rs. 357.07 Say 357.05

Page 128: Rate analsis Chapter No. 12 (Wood Work)

Page 128

Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.

b) Pertal wood frame panellingi) ¾" (20mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore ¾" thick 144.00 SftWastage 5% 7.20 Sft

151.20 Sft 4.25 Sft 642.60 Pertal Wood

Frame Main Style 3x12¼x2"x3" 1.53 CftCross Style 3x12¼x1½"x2" 0.77 CftCross Style 4x12x1½"x½" 0.25 Cft

2.55 CftWastage 20% 0.51 Cft

3.06 Cft 350.00 P. Cft 1,071.00 Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.50 Each 40.00 Screws of all sorts 6.00 Nos 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25

Total 2,097.35 Contractor's Profit & Overheads 20 Percent 419.47 Total for 144 Sft. 2,516.82 Rate Per Sft 2516.82 x 100 = 1,747.79

144

Page 129: Rate analsis Chapter No. 12 (Wood Work)

Page 129

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Doz 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00

Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00

Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00

144

Item Rates

Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45

Composite Rate Per 100 Sft Rs. 2,792.79 Say 2,792.80 Composite Rate Per Sqm Rs. 300.50 Say 300.50

Page 130: Rate analsis Chapter No. 12 (Wood Work)

Page 130

Item No. 42 Providing and fixing thermopore false ceilingincluding wooden frame panelling, cost of M.S.clamps, making holes in walls and repairingdamaged surface, complete in all respects.

b) Pertal wood frame panellingii) 1" (25mm) Thick.

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit Amount

Rate Analysis for 12' x 12' = 144 Sft

Material

Thermopore 1" thick 144.00 SftWastage 5% 7.20 Sft

151.20 Sft 5.68 Sft 858.82 Pertal Wood

Frame Main Style 3x12¼x2"x3" 1.53 CftCross Style 3x12¼x1½"x2" 0.77 CftCross Style 4x12x1½"x½" 0.25 Cft

2.55 CftWastage 20% 0.51 Cft

3.06 Cft 350.00 P. Cft 1,071.00 Sawing charge 3.06 Cft 8.00 P. Cft 24.48 Making holes in walls L.S. 37.33 Wooden gutties 3 interval 16.00 Nos 2.00 Each 32.00 Screws of all sorts 6.00 Doz 3.25 P. Doz 19.50 Nail 0.70 Kg 43.00 P. Kg 30.10 M.S. hooks 4.00 Nos 12.00 Each 48.00 M.S. clamps 4.00 Nos 40.00 Each 160.00 Cement sand for repair 0.083 Bag 230.00 P. Bag 19.09 Sand 1.500 Cft. 350.00 % Cft. 5.25

Total 2,305.57 Contractor's Profit & Overheads 20 Percent 461.11 Total for 144 Sft. 2,766.68 Rate Per Sft 2766.68 x 100 = 1,921.31

144

Page 131: Rate analsis Chapter No. 12 (Wood Work)

Page 131

Detail Unit Rate (British System) per 100 Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenter 2.25 Nos 300.00 P. Day 675.00 Cooly Skilled 2.00 Nos 160.00 P. Day 320.00 Cooly 0.50 No 140.00 P. Day 70.00 Mason 0.25 No 300.00 P. Day 75.00

Total 1,140.00 Sundries 10 Percent 114.00 Total 1,254.00

Contractor's Profit & Overheads 20 Percent 250.80 Total for 144 Sft. 1,504.80 Rate Per Sft 1504.80 x 100 = 1,045.00

144

Item Rates

Labour Rate Per 100 Sft Rs. 1,045.00 Say 1,045.00 Labour Rate Per Sqm Rs. 112.44 Say 112.45

Composite Rate Per 100 Sft Rs. 2,966.31 Say 2,966.30 Composite Rate Per Sqm Rs. 319.17 Say 319.20

Page 132: Rate analsis Chapter No. 12 (Wood Work)

Page 132

DESCRIPTION OF ITEM NO 43: a) Fixing door including chowkhat.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Mason 0.25 No 300.00 P. Day 75.00 Cooly 0.25 No 140.00 P. Day 35.00

Total 110.00 Sundries 10 Percent 11.00 Total 121.00

Contractor's Profit & Overheads 20 Percent 24.20 Total 145.20

Item Rates

Labour Rate for Each Rs. 145.20 Say 145.20

Page 133: Rate analsis Chapter No. 12 (Wood Work)

Page 133

Item No. 43 b) Fixing windows including chowkhat.

Detail Unit Rate (British System)per Each

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Mason 0.125 No 300.00 P. Day 37.50 Cooly 0.125 No 140.00 P. Day 17.50

Total 55.00 Sundries 10 Percent 5.50 Total 60.50

Contractor's Profit & Overheads 20 Percent 12.10 Total 72.60

Item Rates

Labour Rate for Each Rs. 72.60 Say 72.60

Page 134: Rate analsis Chapter No. 12 (Wood Work)

Page 134

DESCRIPTION OF ITEM NO 44: a) Glazing with panes 160Z to 180Z (454Gm to 512Gm) including cost of putty.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 14 Sft

Material

Detail of glass panes

Glass Panes 14.00 SftWastage 10% 1.40 Sft

15.40 Sft 12.00 Sft 184.80 Cost of Putty and nails L.S. 12.00

Total 196.80 Contractor's Profit & Overheads 20 Percent 39.36 Total for 14 Sft. 236.16 Rate Per Sft 236.16 = 16.87

14Labour

Glazier for cutting and fixing glass

panes including supplying front & back. 0.25 No 170.00 P. Day 42.50 Cooly Skilled 0.25 No 160.00 P. Day 40.00

Total 82.50 Sundries 10 Percent 8.25 Total 90.75

Contractor's Profit & Overheads 20 Percent 18.15 Total for 14 Sft. 108.90 Rate Per Sft 108.90 = 7.78

14

Item Rates

Labour Rate Per Sft Rs. 7.78 Say 7.80 Labour Rate Per Sqm Rs. 83.70 Say 83.70

Composite Rate Per Sft Rs. 24.65 Say 24.65 Composite Rate Per Sqm Rs. 265.20 Say 265.20

Page 135: Rate analsis Chapter No. 12 (Wood Work)

Page 135

Item No. 44 b) Glazing with panes 16 Oz. to 18 Oz. (454Gm to 512Gm) using deodar wooden fillets and putty.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 14 Sft

Material

Glass Panes 14.00 Sft 12.00 Sft 168.00 D. Wood 0.09 Cft 550.00 P. Cft 49.50 Cost of nails and putty. L.S. 12.00

Total 229.50 Contractor's Profit & Overheads 20 Percent 45.90 Total for 14 Sft. 275.40 Rate Per Sft 275.40 = 19.67

14Labour

Glazier for cutting and fixing glass

panes including supplying front & back. 0.25 No 170.00 P. Day 42.50 Cooly Skilled 0.25 No 160.00 P. Day 40.00 Cartpenter for 0.13 No 300.00 P. Day 39.00

Total 121.50 Sundries 10 Percent 12.15 Total 133.65

Contractor's Profit & Overheads 20 Percent 26.73 Total for 14 Sft. 160.38 Rate Per Sft 160.38 = 11.46

14

Item Rates

Labour Rate Per Sft Rs. 11.46 Say 11.45 Labour Rate Per Sqm Rs. 123.26 Say 123.25

Composite Rate Per Sft Rs. 31.13 Say 31.15 Composite Rate Per Sqm Rs. 334.93 Say 334.95

Page 136: Rate analsis Chapter No. 12 (Wood Work)

Page 136

DESCRIPTION OF ITEM NO 45: Glazing with glass panes 24 Oz. to 26 Oz. (680Gm to737Gm) using putty and deodar wooden fillets.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 15 Sft

putty and deodar wooden fillet.

Considering 5 Nos panes of average

size i.e. 5x18"x24" 15 Sft

Material

Glass Panes 15.00 SftWastage 10% 1.50 Sft

16.50 Sft 14.00 Sft 231.00 D. Wood for fillets 0.06 Cft 550.00 P. Cft 33.00 Cost of putty and nails L.S. 12.00

Total 276.00 Contractor's Profit & Overheads 20 Percent 55.20 Total for 15 Sft. 331.20 Rate Per Sft 331.20 = 22.08

15Labour

Glazier 0.38 No 170.00 P. Day 64.60 Cooly Skilled 0.38 No 160.00 P. Day 60.80 Cartpenter 0.13 No 300.00 P. Day 39.00 Cooly 0.13 No 140.00 P. Day 18.20

Total 182.60 Sundries 10 Percent 18.26 Total 200.86

Contractor's Profit & Overheads 20 Percent 40.17 Total for 15 Sft. 241.03 Rate Per Sft 241.03 = 16.07

15Item Rates

Labour Rate Per Sft Rs. 16.07 Say 16.05 Labour Rate Per Sqm Rs. 172.90 Say 172.90

Composite Rate Per Sft Rs. 38.15 Say 38.15 Composite Rate Per Sqm Rs. 410.48 Say 410.50

Page 137: Rate analsis Chapter No. 12 (Wood Work)

Page 137

DESCRIPTION OF ITEM NO 46:

a) Cutting to required sizes and fixing glass paneswith putty.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 14 Sft

Material

Cost of nails & putty L.S. 12.00

Total 12.00 Contractor's Profit & Overheads 20 Percent 2.40 Total for 14 Sft. 14.40 Rate Per Sft 14.40 = 1.03

14Labour

Glazier 0.20 No 170.00 P. Day 34.00 Cooly Skilled 0.15 No 160.00 P. Day 24.00

Total 58.00 Sundries 10 Percent 5.80 Total 63.80

Contractor's Profit & Overheads 20 Percent 12.76 Total for 14 Sft. 76.56 Rate Per Sft 76.56 = 5.47

14

Item Rates

Labour Rate Per Sft Rs. 5.47 Say 5.45 Labour Rate Per Sqm Rs. 58.84 Say 58.85

Composite Rate Per Sft Rs. 6.50 Say 6.50 Composite Rate Per Sqm Rs. 69.91 Say 69.90

Page 138: Rate analsis Chapter No. 12 (Wood Work)

Page 138

Item No. 46 b) Cutting to required sizes and fixing glass paneswith wooden fillets and putty.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 16 Sft

Material

Deodar wood for fillets 0.10 Cft 500.00 P. Cft 50.00 Putty and nails L.S. 12.00

Total 62.00 Contractor's Profit & Overheads 20 Percent 12.40 Total for 16 Sft. 74.40 Rate Per Sft 74.40 = 4.65

16Labour

Glazier 0.20 No 170.00 P. Day 34.00 Cooly Skilled 0.20 No 160.00 P. Day 32.00 Carpenter 0.10 No 300.00 P. Day 30.00 Cooly Skilled 0.10 No 160.00 P. Day 16.00

Total 112.00 Sundries 10 Percent 11.20 Total 123.20

Contractor's Profit & Overheads 20 Percent 24.64 Total for 16 Sft. 147.84 Rate Per Sft 147.84 = 9.24

16

Item Rates

Labour Rate Per Sft Rs. 9.24 Say 9.25 Labour Rate Per Sqm Rs. 99.42 Say 99.40

Composite Rate Per Sft Rs. 13.89 Say 13.90 Composite Rate Per Sqm Rs. 149.46 Say 149.45

Page 139: Rate analsis Chapter No. 12 (Wood Work)

Page 139

DESCRIPTION OF ITEM NO 47: Glazing with plate glass ¼" (6mm) thick includingthe cost of deodar wood fillets and putty.

a) Glazing upto 8 Sft (0.744M²).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 8 Sft

Material

Plate glass ¼" (6mm) thick 8.00 SftWastage 10% 0.80 Sft

8.80 Sft 32.00 Sft 281.60 Deodar wood for fillets 0.05 Cft 500.00 P. Cft 25.00 Cost of nails and putty L.S. 12.00

Total 318.60 Contractor's Profit & Overheads 20 Percent 63.72 Total for 8 Sft. 382.32 Rate Per Sft 382.32 = 47.79

8Labour

Glazier 0.17 No 170.00 P. Day 28.90 Cooly Skilled 0.17 No 160.00 P. Day 27.20 Carpenter 0.06 No 300.00 P. Day 18.00 Cooly Skilled 0.06 No 160.00 P. Day 9.60

Total 83.70 Sundries 10 Percent 8.37 Total 92.07

Contractor's Profit & Overheads 20 Percent 18.41 Total for 8 Sft. 110.48 Rate Per Sft 110.48 = 13.81

8

Item Rates

Labour Rate Per Sft Rs. 13.81 Say 13.80 Labour Rate Per Sqm Rs. 148.60 Say 148.60

Composite Rate Per Sft Rs. 61.60 Say 61.60 Composite Rate Per Sqm Rs. 662.82 Say 662.80

Page 140: Rate analsis Chapter No. 12 (Wood Work)

Page 140

Item No. 47 b) Glazing exceeding 8 Sft (0.744M²)and not exceeding 24 Sft (2.230M²)

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for = 16 Sft

Material

Plate glass ¼" (6mm) thick 16.00 SftWastage 10% 1.60 Sft

17.60 Sft 32.00 Sft 563.20 Deodar wood for fillets 0.10 Cft 500.00 P. Cft 50.00 Cost of nails and putty L.S. 26.40

Total 639.60 Contractor's Profit & Overheads 20 Percent 127.92 Total for 16 Sft. 767.52 Rate Per Sft 767.52 = 47.97

16Labour

Glazier 0.33 No 170.00 P. Day 56.10 Cooly Skilled 0.33 No 160.00 P. Day 52.80 Carpenter 0.13 No 300.00 P. Day 39.00 Cooly Skilled 0.13 No 160.00 P. Day 20.80

Total 168.70 Sundries 10 Percent 16.87 Total 185.57

Contractor's Profit & Overheads 20 Percent 37.11 Total for 16 Sft. 222.68 Rate Per Sft 222.68 = 13.92

16

Item Rates

Labour Rate Per Sft Rs. 13.92 Say 13.90 Labour Rate Per Sqm Rs. 149.75 Say 149.75

Composite Rate Per Sft Rs. 61.89 Say 61.90 Composite Rate Per Sqm Rs. 665.91 Say 665.90

Page 141: Rate analsis Chapter No. 12 (Wood Work)

Page 141

DESCRIPTION OF ITEM NO 48: Providing and fixing 1½" (40mm) thick deodarwood panelled or panelled and glazed, doors andwindows, with mild steel chowkhat (frame), etc.complete in all respects (excluding sliding bolt orlock) with :

i) M.S. angle iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. flat 2"x¼" (50x6mm)

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Angle Iron 1½"x1½"x¼"

Vertical 2 x 7 = 14.00 Rft.

18.00 Rft.

18.90 Rft.

18.90 Rft. @ 2.34 lbs/Rft. 44.23 lbsMS Bar ½"dia 4' @ 0.67 lbs/Rft. 2.68 lbsMS Flat 2"x¼ = 18.90 Rft. @ 1.70 lbs/Rft. 32.13 lbs

79.04 lbs35.85 Kgs 22.00 per Kg 788.70

Wood

Vertical Style 4x6'-8½"x4"x1½" 1.12 CftHorizontal Top 2x1'-11½"x4"x1½" 0.16 CftMiddle Top 2x1'-11½"x4"x1½" 0.16 CftLocal Top 2x1'-11½"x6"x1½" 0.24 CftBottom Top 2x1'-11½"x8"x1½" 0.32 Cft

Panells

2x16½"x23"x5/8" 0.24 Cft4x16½"x19½"x5/8" 0.47 Cft

Beading

2(16½+16½+23+23) 5/80.01 Cft

2x8

4(16½+16½+19½+19½) 5/80.02 Cft

2x82.74 Cft

Wastage 30% 0.82 Cft3.56 Cft 500.00 P. Cft 1,780.00

Horizontal l 1 x 4 = 4.00 Rft.

Wastage 5% 0.90 Rft.

(1½+2½) = 0.01

(1½+1½)

Page 142: Rate analsis Chapter No. 12 (Wood Work)

Page 142

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower bolt 9: (225mm) 3.00 Nos 27.00 Each 81.00 Handle 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber 2.00 Nos 4.00 Each 8.00 Hook & clamp 2.00 Nos 4.00 Each 8.00

Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P.Kg. 4.00 Spikes 0.13 Kg. 30.00 P.Kg. 3.99 Sawing charge 35.60 Sft 0.80 Sft 28.48

Total 2,843.09 Contractor's Profit & Overheads 20 Percent 568.62 Total for 27 Sft. 3,411.71 Rate Per Sft 3411.71 = 126.36

27Labour

Carpenter 2.40 Nos 300.00 P. Day 720.00 Cooly Skilled 1.80 Nos 160.00 P. Day 288.00 Welder 1.00 No 170.00 P. Day 170.00 Blacksmith 0.57 No 170.00 P. Day 96.90

Total 1,274.90 Sundries 10 Percent 127.49 Total 1,402.39

Contractor's Profit & Overheads 20 Percent 280.48 Total for 27 Sft. 1,682.87 Rate Per Sft 1682.87 = 62.33

27Item Rates

Labour Rate Per Sft Rs. 62.33 Say 62.35 Labour Rate Per Sqm Rs. 670.65 Say 670.65

Composite Rate Per Sft Rs. 188.69 Say 188.70 Composite Rate Per Sqm Rs. 2,030.29 Say 2,030.30

Page 143: Rate analsis Chapter No. 12 (Wood Work)

Page 143

Item No. 48 Providing and fixing 1½" (40mm) thick deodarwood panelled or panelled and glazed, doors andwindows, with mild steel chowkhat (frame), etc.complete in all respects (excluding sliding bolt orlock) with :

ii) M.S. Tee Iron 1½"x1½"x¼" (40x40x6mm)welded with M.S. flat ½"x¼" (12x6mm).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

T-Iron 1½"x1½"x¼"

Vetical 2x7 14 Rft

18.00 Rft

18.90 Rft

18.90 Rft 2.36 Lbs/Rft 44.60 LbsM.S. bar ½" Ø = 4' @ 0.67 Lbs 2.68 LbsM.S. flat ½"x¼"=18.90 Rft @ 0.425 Lbs 8.03 Lbs

55.31Lbs ( 25.10)Kg 22.00 P. Kg 552.20 Deodar Wood

Vertical Style 4x6'-8½"x4"x1½" 1.12 CftHorizontal Top 2x1'-11½"x4"x1½" 0.16 CftMiddle Top 2x1'-11½"x4"x1½" 0.16 CftLocal Top 2x1'-11½"x6"x1½" 0.24 CftBottom Top 2x1'-11½"x8"x1½" 0.32 Cft

Panells

2x16½"x23"x5/8" 0.24 Cft4x16½"x19½"x5/8" 0.47 Cft

Beading

2(16½+16½+23+23) 5/80.01 Cft

2x8

4(16½+16½+19½+19½) 5/80.02 Cft

2x82.74 Cft

Wastage 30% 0.82 Cft3.56 Cft 500.00 P. Cft 1,780.00

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

(1½+2½)

(1½+1½)

Page 144: Rate analsis Chapter No. 12 (Wood Work)

Page 144

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 8.00 Nos 4.60 Each 36.80 Tower bolt 9: (225mm) 3.00 Nos 17.00 Each 51.00 Handle 6" (150mm) 3.00 Nos 8.00 Each 24.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber 2.00 Nos 4.00 Each 8.00 Hook & clamp 2.00 Nos 4.00 Each 8.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.05 Kg. 80.00 P.Kg. 4.00 Spikes 0.13 Kg. 30.00 P.Kg. 3.99 Sawing charge 35.60 Sft 0.80 Sft 28.48

Total 2,576.59 Contractor's Profit & Overheads 20 Percent 515.32 Total for 27 Sft. 3,091.91 Rate Per Sft 3091.91 = 114.52

27Labour

Carpenter 2.40 Nos 300.00 P. Day 720.00 Cooly Skilled 1.80 Nos 160.00 P. Day 288.00 Welder 1.00 No 170.00 P. Day 170.00 Blacksmith 0.57 No 170.00 P. Day 96.90

Total 1,274.90 Sundries 10 Percent 127.49 Total 1,402.39

Contractor's Profit & Overheads 20 Percent 280.48 Total for 27 Sft. 1,682.87 Rate Per Sft 1682.87 = 62.33

27

Item Rates

Labour Rate Per Sft Rs. 62.33 Say 62.35 Labour Rate Per Sqm Rs. 670.65 Say 670.65

Composite Rate Per Sft Rs. 176.84 Say 176.85 Composite Rate Per Sqm Rs. 1,902.84 Say 1,902.85

Page 145: Rate analsis Chapter No. 12 (Wood Work)

Page 145

DESCRIPTION OF ITEM NO 49: Providing and fixing 1½" (40mm) thick hollow flushdoors and windows, with commercial ply (3mm) onboth faces of deodar wood shutter frame 1¼"(32mm) thick and partal wood braces at about 3"(76mm) apart and deodar wood lipping 1½"x3/8",(40x10mm) fixed with M.S. chowkhat (frame),including chromium plated fittings, etc. complete inall respects (without sliding bolt or lock)

a) M.S. Angle Iron 1½"x1½"x¼" welded with M.S.flat 2"x¼"

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Angle Iron 1½"x1½"x¼"

Vetical 2x7 14 Rft

18.00 Rft

18.90 Rft 43.85 LbsM.S. flat 2"x¼" (50x6mm)

Vetical 2x7 14 Rft

18.00 Rft

18.90 Rft

18.90 Rft @ 1.68 Lbs/Rft 31.75 LbsM.S. flat patti 1"x1/8" (25x3mm) at bottom 1.68 Lbs

77.28Lbs (35.06 Kg.) 22.00 P. Kg 771.32 Deodar Wood

Vertical Style 2x6'-8½"x4"x1¼" 0.47 CftVertical Style 3x6'-8½"x2"x1¼" 0.35 CftHorizontal Style 1x3'-11¼"x4"x1¼" 0.14 CftMiddle Style 1x3'-11¼"x4"x1¼" 0.14 CftLock Style 1x3'-11¼"x6"x1¼" 0.21 CftBottom Style 1x3'-11¼"x8"x1¼" 0.27 CftSide Strip 2x6'-8¾"x1½"x1/8" 0.02 CftSide Strip 2x3'-8½"x1½"x1/8" 0.01 Cft

1.61 CftWastage 35% 0.56 Cft

2.17 Cft 500.00 P. Cft 1,085.00

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Page 146: Rate analsis Chapter No. 12 (Wood Work)

Page 146

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber chocks 1.00 No 4.00 Each 4.00 Hook & clamp 1.00 No 4.00 Each 4.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.75 Kg. 80.00 P.Kg. 60.00 Spikes 0.20 Kg. 30.00 P.Kg. 6.00 Sawing charge 21.70 Sft 0.80 Sft 17.36

Commercial Ply (3mm)

2x3'-11½"x6'-8¾" 53.38 SftWastage 15% 8.01 Sft

61.39 Sft 10.50 Sft 644.60 Total 2,740.80 Contractor's Profit & Overheads 20 Percent 548.16 Total for 27 Sft. 3,288.96 Rate Per Sft 3288.96 = 121.81

27Labour

Welder for making frame 1 No 170.00 Each 170.00 Black Smith 1 Nos 170.00 Each 170.00

For Panelling pressing and erecting door

Carpentre 1 Nos 300.00 P. Day 300.00 Skilled Cooly 1 No 160.00 P. Day 160.00

Total 800.00 Sundries 10 Percent 80.00 Total 880.00 Contractor's Profit & Overheads 20 Percent 176.00 Total for 27 Sft. 1,056.00 Rate Per Sft 1056.00 = 39.11

27Item Rates

Labour Rate Per Sft Rs. 39.11 Say 39.10 Labour Rate Per Sqm Rs. 420.84 Say 420.85

Composite Rate Per Sft Rs. 160.92 Say 160.90 Composite Rate Per Sqm Rs. 1,731.55 Say 1,731.55

Page 147: Rate analsis Chapter No. 12 (Wood Work)

Page 147

DESCRIPTION OF ITEM NO 49: Providing and fixing 1½" (40mm) thick hollow flushdoors and windows, with commercial ply (3mm) onboth faces of deodar wood shutter frame 1¼"(32mm) thick and partal wood braces at about 3"(76mm) apart and deodar wood lipping 1½"x3/8",(40x10mm) fixed with M.S. chowkhat (frame),including chromium plated fittings, etc. complete inall respects (without sliding bolt or lock)

b) M.S. Tee Iron 1½"x1½"x¼" welded with M.S.flat ½"x¼"

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 6.75' = 27 Sft

Material

Tee Iron 1½"x1½"x¼"

Vetical 2x7 14 Rft

18.00 Rft

18.90 Rft @ 2.36Lbs/Rft 44.60 LbsM.S. flat ½"x¼" (40x6mm)

Vetical 2x7 14 Rft

18.00 Rft

18.90 Rft @ 0.423Lbs/Rft 8.03 LbsM.S. bar ½" dia = 4 Rft @ 0.67 Lbs 2.68 Lbs

55.31Lbs ( 25.10 Kg) 22.00 P. Kg 552.20 Deodar Wood

Vertical Style 2x6'-8½"x4"x1¼" 0.47 CftVertical Style 3x6'-8½"x2"x1¼" 0.35 CftHorizontal Style 1x3'-11¼"x4"x1¼" 0.14 CftMiddle Style 1x3'-11¼"x4"x1¼" 0.14 CftLock Style 1x3'-11¼"x6"x1¼" 0.21 CftBottom Style 1x3'-11¼"x8"x1¼" 0.27 CftSide Strip 2x6'-8¾"x1½"x1/8" 0.02 CftSide Strip 2x3'-8½"x1½"x1/8" 0.01 Cft

1.61 CftWastage 35% 0.56 Cft

2.17 Cft 500.00 P. Cft 1,085.00

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Horizontal 1x4 4 Rft

Wastage 5% 0.90 Rft

Page 148: Rate analsis Chapter No. 12 (Wood Work)

Page 148

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Fitting

Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Rubber chocks 1.00 No 4.00 Each 4.00 Hook & clamp 1.00 No 4.00 Each 4.00 Screws 2.50 Doz 3.25 P. Doz 8.13 Glue 0.75 Kg. 80.00 P.Kg. 60.00 Spikes 0.20 Kg. 30.00 P.Kg. 6.00 Sawing charge 21.70 Sft 0.80 Sft 17.36

Commercial Ply (3mm)

2x3'-11½"x6'-8¾" 53.38 SftWastage 15% 8.01 Sft

61.39 Sft 10.50 Sft 644.60 Total 2,521.68 Contractor's Profit & Overheads 20 Percent 504.34 Total for 27 Sft. 3,026.02 Rate Per Sft 3026.02 = 112.07

27Labour

Welder for making frame 1 No 170.00 Each 170.00 Black Smith 1 Nos 170.00 Each 170.00

For Rendring & Erection Door

Carpentre 1 Nos. 300.00 P. Day 300.00 Skilled Cooly 1 No. 160.00 P. Day 160.00

Total 800.00 Sundries 10 Percent 80.00 Total 880.00 Contractor's Profit & Overheads 20 Percent 176.00 Total for 27 Sft. 1,056.00 Rate Per Sft 1056.00 = 39.11

27Item Rates

Labour Rate Per Sft Rs. 39.11 Say 39.10 Labour Rate Per Sqm Rs. 420.84 Say 420.85

Composite Rate Per Sft Rs. 151.19 Say 151.20 Composite Rate Per Sqm Rs. 1,626.76 Say 1,626.75

Page 149: Rate analsis Chapter No. 12 (Wood Work)

Page 149

DESCRIPTION OF ITEM NO 50: Providing and fixing 1½" (40mm) thick solid flushdoor shutter sterling or equivalent with commercialply (5mm thick) on both sides double pressed anddeodar wood lipping 1½"x3/8" (40x10mm) aroundshutter including chromium plated fittings, ironhinges with aluminium kick plate 22SWG on bothsides & finger plate complete in all respects.

Remarks : If C.I. finger plate and kick plate are notprovided/ fixed the composite rate will be reducedby Rs. 7.60 Per Sft (81.76M²).

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3.5' x 7' = 24.5 Sft

Material

Solid flush

Door leaf 1½" (40mm) thick sterling

or equivalent with commerical ply

(5mm) thick both sides.

3½"x7'-0' = 24.50 Sft 24.50 Sft 92.00 Sft 2,254.00

Deodar Wood Lipping 3/8"

(3.5+3.5+7.0+7.0) 21.00 Rft 15.00 per/ft. 315.00

Hinges 4" (100mm) 4.00 Nos 4.60 Each 18.40 Tower bolt C.P. 2.00 Nos 30.00 Each 60.00 C.P. Handle best quality 2.00 Nos 10.50 Each 21.00 Door stopper 1.00 No 12.00 Each 12.00 C.P. finger plate with screws 1.00 No 80.00 Each 80.00 Kick plate 22 SWG on both sides 2.00 Nos 30.00 Each 60.00

Total 2,820.40 Contractor's Profit & Overheads 20 Percent 564.08 Total for 24.5 Sft. 3,384.48 Rate Per Sft 3384.48 = 138.14

24.5

Page 150: Rate analsis Chapter No. 12 (Wood Work)

Page 150

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

For planning & fixing of lipping with

door fitting complete.

Carpentre 1.00 No 300.00 P. Day 300.00 Skilled Cooly 1.00 No 160.00 P. Day 160.00

Total 460.00 Sundries 10 Percent 46.00 Total 506.00

Contractor's Profit & Overheads 20 Percent 101.20 Total for 24.5 Sft. 607.20 Rate Per Sft 607.20 = 24.78

24.5

Item Rates

Labour Rate Per Sft Rs. 24.78 Say 24.80 Labour Rate Per Sqm Rs. 266.67 Say 266.65

Composite Rate Per Sft Rs. 162.93 Say 162.95 Composite Rate Per Sqm Rs. 1,753.08 Say 1,753.10

Page 151: Rate analsis Chapter No. 12 (Wood Work)

Page 151

DESCRIPTION OF ITEM NO 51: Providing and fixing panelled door of M.S. Sheetwith forged door leaves of M.S. Sheet 22 SWG fittedin hollow frame chowkhat 3"x4½" (76x114mm)made of M.S. sheet 18 SWG, filled with plain cementconcrete 1:3:6 etc. complete, with all fittings andhammer painting, including carriage to site andfixing in position.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4' x 7' = 28 Sft

Material

M.S. Sheet 18 SWG

for chowkhat

18¾'x15" 23.44 SftWastage 20% 4.69 Sft

28.13 Sft 40.00 Sft 1,125.20 M.S. Sheet 22 SWG

for shutter

26½x7 1/8 31.50 SftWastage 20% 6.30 Sft

37.80 Sft 32.00 Sft 1,209.60 M.S. Flat 1"x1/16" (25x2mm)

6'-9½"x0.21 1.43Lb (0. 65) Kg 22.00 P. Kg 14.30

Fitting

Hinges 4" (100mm) 6.00 Nos 4.60 Each 27.60 Tower bolt 9: (225mm) 2.00 Nos 17.00 Each 34.00 Handle 6" (150mm) 2.00 Nos 8.00 Each 16.00 Iron hold fast 6.00 Nos 12.00 Each 72.00 Screws L.S. 4.00 Welding electrode 4.00 Nos 2.01 Each 8.02 Electricity Charges L.S. 16.00

Cement concrete (1:3:6)

Cement 0.21 Bag 230.00 Each 48.30 Sand 0.76 Cft 3.50 P. Cft 2.66 Bagri 1.52 Cft 18.50 P. Cft 28.12

Total 2,605.80 Contractor's Profit & Overheads 20 Percent 521.16 Total for 28 Sft. 3,126.96 Rate Per Sft 3126.96 = 111.68

28

Page 152: Rate analsis Chapter No. 12 (Wood Work)

Page 152

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Welder 0.50 No 170.00 P. Day 85.00 Blacksmith 2.50 Nos 170.00 P. Day 425.00 Mason 0.25 No 300.00 P. Day 75.00 Coolies 0.75 No 140.00 P. Day 105.00

Total 690.00 Sundries 10 Percent 69.00 Total 759.00

Contractor's Profit & Overheads 20 Percent 151.80 Total for 28 Sft. 910.80 Rate Per Sft 910.80 = 32.53

28

Item Rates

Labour Rate Per Sft Rs. 32.53 Say 32.55 Labour Rate Per Sqm Rs. 350.01 Say 350.00

Composite Rate Per Sft Rs. 144.21 Say 144.20 Composite Rate Per Sqm Rs. 1,551.65 Say 1,551.65

Page 153: Rate analsis Chapter No. 12 (Wood Work)

Page 153

DESCRIPTION OF ITEM NO 52: Providing and laying 24 SWG aluminium kickplate 4" (100mm) high fixed with screws 4"(100mm) Centre to Centre on bottom rail of flushdoors only. of commercial ply.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4 Rft

Material

Aluminium plate 4" (100mm) wide

and 24 SWG 0.18 Kg 96.00 P. Kg 17.28

Total 17.28 Contractor's Profit & Overheads 20 Percent 3.46 Total for 4 Rft. 20.74 Rate Per Rft 20.74 = 5.18

4Labour

Carpenter 0.12 No 300.00 P. Day 36.00

Total 36.00 Sundries 10 Percent 3.60 Total 39.60

Contractor's Profit & Overheads 20 Percent 7.92 Total for 4 Rft. 47.52 Rate Per Rft 47.52 = 11.88

4

Item Rates

Labour Rate Per Rft Rs. 11.88 Say 11.90 Labour Rate Per Rm Rs. 38.97 Say 38.95

Composite Rate Per Rft Rs. 17.06 Say 17.05 Composite Rate Per Rqm Rs. 55.97 Say 55.95

Page 154: Rate analsis Chapter No. 12 (Wood Work)

Page 154

DESCRIPTION OF ITEM NO 53: Providing and fixing curtain railing to doors andwindows, comprising of TOSO-elite Japan madesuperior type of railing or equivalent, fixed over 4"x¾" (100x20mm) deodar wood strip, includingpainting.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Rate For 10 Rft

Railing 10.00 Rft 9.00 P. Rft 90.00 Cutting of Railing 5.29 Screws 1.00 Dozen 1.68 P, Doz 1.68 Guttis 6.00 Nos 0.25 Each 1.50 Deodar wood 0.21 Cft 550.00 P. Cft 115.50

Total 213.97 Contractor's Profit & Overheads 20 Percent 42.79 Total for 10 Rft. 256.77

Material Rate Per Rft. 256.77 = 25.68 10

Labour

Rate For 80 Rft

Carpenter 1.00 No 300.00 P. Day 300.00

Total 300.00 Sundries 10 Percent 30.00 Total 330.00

Contractor's Profit & Overheads 20 Percent 66.00 Total 396.00 Rate Per Sft 396.00 = 4.95

80

Item Rates

Labour Rate Per Rft Rs. 4.95 Say 4.95 Labour Rate Per Rm Rs. 16.24 Say 16.25

Composite Rate Per Rft Rs. 30.63 Say 30.65 Composite Rate Per Rm Rs. 100.46 Say 100.45

Page 155: Rate analsis Chapter No. 12 (Wood Work)

Page 155

DESCRIPTION OF ITEM NO 54: Providing and fixing M.S. flat ½"1/8" (12x3mm)grill including ¾"x1/8" (20x3mm) M.S. Flat Frameof windows of approved design including painting 3coat complete in all respect.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 2½ x 3½ = 8.75 Sft

Material

M.S. Flat Frame for Grill ¾"x1/8"

(20x3mm)

2½'+3½'+2½'+3½' 12 Sft

@ 0.32 Lbs/Rft 3.84 Lbs (1 .88)Kg 22.00 P. Kg 41.36 M.S. Flat ½"x1/8" (12x3mm)

Straight 3½x2x3 21.00 Rft.Flower 6x4x1¼ 30.00 Rft.Side 6x4x¼ 6.00 Rft.Front 6x1x2 12.00 Rft.Total 69.00 Rft.Wastage 5% 3.45 Rft.

72.45Lb (7.0 )Kg 22.00 P. Kg 154.00 @ 0.21 lbs/rft 15.21 lbs

Hold fast 6" (150mm) long 6.00 Nos 12.00 Each 72.00 Electrical Charges L.S. 5.00 Electrod 0.33 Pkt 360.00 Pkt 21.12 Paint 0.098Lb (0. 08) Gl 450.00 P. Gl 44.10

Total 337.58 Contractor's Profit & Overheads 20 Percent 67.52 Total for 100 Sft. 405.10 Rate Per Sft 405.10 = 46.30

8.75

Page 156: Rate analsis Chapter No. 12 (Wood Work)

Page 156

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Welder 0.17 Nos 170.00 P. Day 28.90 Blacksmith 0.17 No 170.00 P. Day 28.90 Masson 0.20 Nos 300.00 P. Day 60.00 Painter 0.09 No 170.00 P. Day 15.30

Total 133.10 Sundries 10 Percent 13.31 Total 146.41

Contractor's Profit & Overheads 20 Percent 29.28 Total for 100 Sft. 175.69 Rate Per Sft 175.69 = 20.08

8.75

Item Rates

Labour Rate Per Sft Rs. 20.08 Say 20.10 Labour Rate Per Sqm Rs. 216.05 Say 216.05

Composite Rate Per Sft Rs. 66.38 Say 66.40 Composite Rate Per Sqm Rs. 714.20 Say 714.20

Page 157: Rate analsis Chapter No. 12 (Wood Work)

Page 157

DESCRIPTION OF ITEM NO 55: Providing and fixing G.I. Wire gauge 22 SWG12x12 meshes per Sq Inch (625mm) fixed to steelwindow complete with flat iron putti ½"x1/8"(12x3mm) and machine made screws.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 4 x 3 = 12 Sft

Material

Wire Gauge 144 (12x12) Mesh 12.00 SftWastage 10% 1.20 Sft

13.20 Sft 6.00 Sft 79.20 Flat Iron ½"x1/8" (12x3mm)

3+3+4+4+4 18.00 Rft

18.90 Rft @ 0.21 Lbs/Rft 4 Lbs (1. 82) Kg 22.00 P. Kg 40.04 Screws 6.70 Dozen 1.68 P. Doz 11.26

Total 130.50 Contractor's Profit & Overheads 20 Percent 26.10 Total for 100 Sft. 156.60 Rate Per Sft 156.60 = 13.05

12

Labour Rate for 55 Sft.

Blacksmith 1.00 No 170.00 P. Day 170.00 Skilled Cooly 0.40 No 160.00 P. Day 64.00

Total 234.00 Sundries 10 Percent 23.40 Total 257.40 Contractor's Profit & Overheads 20 Percent 51.48 Total for 100 Sft. 308.88 Rate Per Sft 308.88 = 5.62

55Item Rates

Labour Rate Per Sft Rs. 5.62 Say 5.60 Labour Rate Per Sqm Rs. 60.43 Say 60.45

Composite Rate Per Sft Rs. 18.67 Say 18.65 Composite Rate Per Sqm Rs. 200.84 Say 200.85

Wastage 5% 0.90 Rft

Page 158: Rate analsis Chapter No. 12 (Wood Work)

Page 158

DESCRIPTION OF ITEM NO 56: Providing and fixing wooden moulding stopper2½"x5/8" (63x16mm) on door frame fitted with plyof approved quality complete in all respect.

a) Teak Wood Moulding.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 16 Sft

Material Teak Wood

2x(6'-10½')+2'-3" 16.00 Rft16x2½"x5/8" 0.17 CftWastage 25% 0.04 Cft

0.22 Cft 1400.00 P. Cft 308.00 Glue 0.19 Kg. 80.00 P. Cft 15.20 Nails 0.116 Kg. 43.00 P. Cft 4.99

Total 328.19 Contractor's Profit & Overheads 20 Percent 65.64 Total for 16 Sft. 393.83 Rate Per Sft 393.83 = 24.61

16Labour

Labour for sawing, planning and fixing

16 Rft (4.876Rm) moulding in position

carpenter. 0.50 No 300.00 P. Day 150.00

Total 150.00 Sundries 10 Percent 15.00 Total 165.00

Contractor's Profit & Overheads 20 Percent 33.00 Total for 16 Sft. 198.00 Rate Per Sft 198.00 = 12.38

16

Item Rates

Labour Rate Per Sft Rs. 12.38 Say 12.40 Labour Rate Per Sqm Rs. 133.16 Say 133.15

Composite Rate Per Sft Rs. 36.99 Say 37.00 Composite Rate Per Sqm Rs. 398.00 Say 398.00

Page 159: Rate analsis Chapter No. 12 (Wood Work)

Page 159

Item No. 56 Providing and fixing wooden moulding stopper2½"x5/8" (63x16mm) on door frame fitted with plyof approved quality complete in all respect.

b) Deodar Wood Moulding.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 16 Sft

Material

Deodar wood 2x(6'-10½')+2'-3" 16.00 Rft16x2½"x5/8" 0.17 CftWastage 25% 0.04 Cft

0.22 Cft 500.00 P. Cft 110.00 Glue 0.26 Kg. 80.00 P. Cft 20.80 Nails 0.116 Kg. 43.00 P. Cft 4.99

Total 135.79 Contractor's Profit & Overheads 20 Percent 27.16 Total for 16 Sft. 162.95 Rate Per Sft 162.95 = 10.18

16Labour

Labour for sawing, planning and fixing

16 Rft (4.876Rm) moulding in position

carpenter. 0.50 No 300.00 P. Day 150.00

Total 150.00 Sundries 10 Percent 15.00 Total 165.00

Contractor's Profit & Overheads 20 Percent 33.00 Total for 16 Sft. 198.00 Rate Per Sft 198.00 = 12.38

16

Item Rates

Labour Rate Per Sft Rs. 12.38 Say 12.40 Labour Rate Per Sqm Rs. 133.16 Say 133.15

Composite Rate Per Sft Rs. 22.56 Say 22.55 Composite Rate Per Sqm Rs. 242.74 Say 242.75

Page 160: Rate analsis Chapter No. 12 (Wood Work)

Page 160

DESCRIPTION OF ITEM NO 57: Providing and fixing deodar wood dolly framehaving 1½"x1½" (40x40mm) vertical andhorizontal double posts with 1½"x½" (40x40mm)full width of jamb braces at 12" (300mm)including filling of hollow space in between braceswith 1:3:6 P.C.C. fixing of ply of approvedquality there upon & hold fasts complete in allrespects.

a) Teak Wood Ply

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 13 Sft

Material (Daodar Wood)

Vertical 2x2x7x1½"x1½" 0.44 CftHorizontal 2x3.5x0.125x0.125 0.11 CftBraces 12"x17.25x0.125 0.20 Cft

0.75 CftWastage 25% 0.19 Cft

0.94 Cft 500.00 P. Cft 470.00 PCC (1:3:6) 6"x10½"x1½" 0.82 CftWastage 10% 0.08 Cft

0.90 Cft 48.53 P. Cft 43.68 Teak Wood Ply 17.25 x 0.75 12.94 SftWastage 10% 1.29 Sft

14.23 Sft 19.50 Sft 277.49 Glue 0.29 Kg. 80.00 P. Cft 23.20 Nails 0.116 Kg. 43.00 P. Cft 4.99 Hold fast 4.00 Nos 12.00 Each 48.00

Total 867.35 Contractor's Profit & Overheads 20 Percent 173.47 Total for 13 Sft. 1,040.82 Rate Per Sft 1040.82 = 80.06

13

Page 161: Rate analsis Chapter No. 12 (Wood Work)

Page 161

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00

Total 230.00 Sundries 10 Percent 23.00 Total 253.00

Contractor's Profit & Overheads 20 Percent 50.60 Total for 13 Sft. 303.60 Rate Per Sft 303.60 = 23.35

13

Item Rates

Labour Rate Per Sft Rs. 23.35 Say 23.35 Labour Rate Per Sqm Rs. 251.29 Say 251.30

Composite Rate Per Sft Rs. 103.42 Say 103.40 Composite Rate Per Sqm Rs. 1,112.77 Say 1,112.75

Page 162: Rate analsis Chapter No. 12 (Wood Work)

Page 162

Item No. 57 Providing and fixing deodar wood dolly frame having1½"x1½" (40x40mm) vertical and horizontal double postswith 1½"x½" (40x40mm) full width of jamb braces at 12"(300mm) including filling of hollow space in betweenbraces with 1:3:6 P.C.C. fixing of ply of approved qualitythere upon & hold fasts complete in all respects.

b) With Commercial Ply.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 13 Sft

Deodar wood 0.94 Cft 500.00 P. Cft 470.00 PCC (1:3:6) 0.90 Cft 48.84 P. Cft 43.96 Commercial ply 14.23 Sft 10.50 P. Sft 149.42 Glue 0.29 Kg. 80.00 P. Cft 23.20 Nails 0.116 Kg. 43.00 P. Cft 4.99 Hold fast L.S. 40.00 Total 731.56 20 Percent 146.31 Total 877.87 Contractor's Profit & Overheads 20 Percent Total for 13 Sft. 877.87 Rate Per Sft 877.87 = 67.53

13Labour

Carpenter 0.50 No 300.00 P. Day 150.00 Cooly Skilled 0.50 No 160.00 P. Day 80.00

Total 230.00 Sundries 10 Percent 23.00 Total 253.00 Contractor's Profit & Overheads 20 Percent 50.60 Total for 13 Sft. 303.60 Rate Per Sft 303.60 = 23.35

13Item Rates

Labour Rate Per Sft Rs. 23.35 Say 23.35 Labour Rate Per Sqm Rs. 251.29 Say 251.30

Composite Rate Per Sft Rs. 90.88 Say 90.90 Composite Rate Per Sqm Rs. 977.89 Say 977.90

Page 163: Rate analsis Chapter No. 12 (Wood Work)

Page 163

DESCRIPTION OF ITEM NO 58: Providing and fixing ornamental woodenarchitrave 3"x½" (75x12mm) tapered to ¼"(6mm) all along the door frame complete in allrespects.

a) Teak Wood Architrave.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3.5 x 7 = 24.50 Sft

Material

Length of Architrave

2(7'-0")+3'-6" 17.50 Rft

quantity (3/12'x½'x1/12')x17.5' 0.18 CftWastage 25% 0.05 Cft

0.23 Cft 1400.00 P. Cft 322.00 Teak Wood

Nails 0.093 Kg. 43.00 P. Kg. 4.00

Total 326.00 Contractor's Profit & Overheads 20 Percent 65.20 Total for 24.50 Sft. 391.20 Rate Per Sft 391.20 = 15.97

24.50Labour

Carpenter 0.25 No 300.00 P. Day 75.00 Fixing in position L.S. 14.93

Total 89.93 Sundries 10 Percent 8.99 Total 98.93

Contractor's Profit & Overheads 20 Percent 19.79 Total for 24.50 Sft. 118.71 Rate Per Sft 118.71 = 4.85

24.50

Item Rates

Labour Rate Per Sft Rs. 4.85 Say 4.85 Labour Rate Per Sqm Rs. 52.14 Say 52.15

Composite Rate Per Sft Rs. 20.81 Say 20.80 Composite Rate Per Sqm Rs. 223.94 Say 223.95

Page 164: Rate analsis Chapter No. 12 (Wood Work)

Page 164

Item No. 58 Providing and fixing ornamental woodenarchitrave 3"x½" (75x12mm) tapered to ¼"(6mm) all along the door frame complete in allrespects.

b) Deodar Wood Architrave.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Rate Analysis for 3.5 x 7 = 24.50 Sft

Material

Length of Architrave

2(7')+3'-6" 17.50 Rft

quantity (3/12'x½'x1/12')x17.5' 0.18 CftWastage 25% 0.05 Cft

0.23 Cft 500.00 P. Cft 115.00 Deodar wood

Nails 0.186 Kg. 43.00 P. Kg. 8.00

Total 123.00 Contractor's Profit & Overheads 20 Percent 24.60 Total for 24.50 Sft. 147.60 Rate Per Sft 147.60 = 6.02

24.50Labour

Carpenter 0.25 No 300.00 P. Day 75.00 Fixing in position L.S. 14.93

Total 89.93 Sundries 10 Percent 8.99 Total 98.93 Contractor's Profit & Overheads 20 Percent 19.79 Total for 24.50 118.71 Rate Per Sft 118.71 = 4.85

24.50Item Rates

Labour Rate Per Sft Rs. 4.85 Say 4.85 Labour Rate Per Sqm Rs. 52.14 Say 52.15

Composite Rate Per Sft Rs. 10.87 Say 10.85 Composite Rate Per Sqm Rs. 116.96 Say 116.95

Page 165: Rate analsis Chapter No. 12 (Wood Work)

Page 165

Item No. 58 Providing and fixing vin board cabinet in kitchen i/c termite proofing and polishing / painting with synthetic enamel as specific with handle and draws screw complete in all respects as per drawing

Take Qty 8 x 2 = 16 Sft.

Detail Unit Rate (British System) per Sft

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

a) Vin Board 3/4 2x8x1½ = 24.00 Sft.Vin Board 5x2x1½ = 15.00 Sft.Total 39.00 Sft. Wastage 20% 7.80Total 46.80 Sft. 24.00 P. Sft. 1,123.20

b) Front Shutter Vin Board

4 x 2 x 2 = 16 16.00 Sft. 24.00 P. Sft. 384.00

c) Frame Deodar Wood 3"x1"

2 x 8 = 16 16.00 Ft.2 x 5 = 10 10.00 Ft.Total 26.00 Ft.Wastage 20% 5.20 Total 31.2 Ft.

31.2 1 3" 0.65 Ft. 500.00 P. Cft. 325.00 12 x 12

d) Termite 0.08 Litre 600.00 P. Litre 49.80

e) Gola 8x2x2 = 32.00 Ft.Wastage 20% 6.40Total 38.40 Ft. 12.00 P. Ft. 460.80

f) Painting / polishing including material + labour

Enamal Paint 0.011 Gallon 450.00 P. Gallon Painter 0.041 No. 170.00 P. Day

11.92 16.00 Ft. 11.92 190.72

g) Handle 4.00 Nos. 35.00 Each 140.00

x x

8'-0

2'-0

Page 166: Rate analsis Chapter No. 12 (Wood Work)

Page 166

h) Screws 3.75 Dozen 3.25 P. Doz 12.19

i) Hinges 2.00 Nos. 20.00 Each 40.00

Total 2,725.71 Contractor's Profit & Overheads 20 Percent 545.14 Total 3,270.85

Labour

Carpenter 1.50 Nos. 300.00 P. Day 450.00 Helper 1.25 Nos. 140.00 P. Day 175.00

Total 625.00 Sundries 10 Percent 62.50 Total 687.50 Contractor's Profit & Overheads 20 Percent 137.50 Total 825.00 Rate Per Sft 825.00 = 51.56

16Item Rates

Labour Rate Per Sft Rs. 51.56 Say 51.55 Labour Rate Per Sqm Rs. 554.81 Say 554.80

Composite Rate Per Sft Rs. 255.99 Say 256.00 Composite Rate Per Sqm Rs. 2,754.46 Say 2,754.45

Page 167: Rate analsis Chapter No. 12 (Wood Work)

Page 167

Amount (Rs.)

Page 168: Rate analsis Chapter No. 12 (Wood Work)

Page 168

Amount (Rs.)

Page 169: Rate analsis Chapter No. 12 (Wood Work)

Page 169

Amount (Rs.)

Page 170: Rate analsis Chapter No. 12 (Wood Work)

Page 170

Amount (Rs.)

Page 171: Rate analsis Chapter No. 12 (Wood Work)

Page 171

Amount (Rs.)

Page 172: Rate analsis Chapter No. 12 (Wood Work)

Page 172

Amount (Rs.)

Page 173: Rate analsis Chapter No. 12 (Wood Work)

Page 173

Amount (Rs.)

Page 174: Rate analsis Chapter No. 12 (Wood Work)

Page 174

Amount (Rs.)

Page 175: Rate analsis Chapter No. 12 (Wood Work)

Page 175

Amount (Rs.)

Page 176: Rate analsis Chapter No. 12 (Wood Work)

Page 176

Amount (Rs.)

Page 177: Rate analsis Chapter No. 12 (Wood Work)

Page 177

Amount (Rs.)

Page 178: Rate analsis Chapter No. 12 (Wood Work)

Page 178

Amount (Rs.)

Page 179: Rate analsis Chapter No. 12 (Wood Work)

Page 179

Amount (Rs.)

Page 180: Rate analsis Chapter No. 12 (Wood Work)

Page 180

Amount (Rs.)

Page 181: Rate analsis Chapter No. 12 (Wood Work)

Page 181

Amount (Rs.)

Page 182: Rate analsis Chapter No. 12 (Wood Work)

Page 182

Amount (Rs.)

Page 183: Rate analsis Chapter No. 12 (Wood Work)

Page 183

Amount (Rs.)

Page 184: Rate analsis Chapter No. 12 (Wood Work)

Page 184

Amount (Rs.)

Page 185: Rate analsis Chapter No. 12 (Wood Work)

Page 185

Amount (Rs.)

Page 186: Rate analsis Chapter No. 12 (Wood Work)

Page 186

Amount (Rs.)

Page 187: Rate analsis Chapter No. 12 (Wood Work)

Page 187

Amount (Rs.)

Page 188: Rate analsis Chapter No. 12 (Wood Work)

Page 188

Amount (Rs.)

Page 189: Rate analsis Chapter No. 12 (Wood Work)

Page 189

Amount (Rs.)

Page 190: Rate analsis Chapter No. 12 (Wood Work)

Page 190

Amount (Rs.)

Page 191: Rate analsis Chapter No. 12 (Wood Work)

Page 191

Amount (Rs.)

Page 192: Rate analsis Chapter No. 12 (Wood Work)

Page 192

Amount (Rs.)

Page 193: Rate analsis Chapter No. 12 (Wood Work)

Page 193

Amount (Rs.)

Page 194: Rate analsis Chapter No. 12 (Wood Work)

Page 194

Amount (Rs.)

Page 195: Rate analsis Chapter No. 12 (Wood Work)

Page 195

Amount (Rs.)

Page 196: Rate analsis Chapter No. 12 (Wood Work)

Page 196

Amount (Rs.)

Page 197: Rate analsis Chapter No. 12 (Wood Work)

Page 197

Amount (Rs.)

Page 198: Rate analsis Chapter No. 12 (Wood Work)

Page 198

Amount (Rs.)

Page 199: Rate analsis Chapter No. 12 (Wood Work)

Page 199

Amount (Rs.)

Page 200: Rate analsis Chapter No. 12 (Wood Work)

Page 200

Amount (Rs.)

Page 201: Rate analsis Chapter No. 12 (Wood Work)

Page 201

Amount (Rs.)

Page 202: Rate analsis Chapter No. 12 (Wood Work)

Page 202

Amount (Rs.)

Page 203: Rate analsis Chapter No. 12 (Wood Work)

Page 203

Amount (Rs.)

Page 204: Rate analsis Chapter No. 12 (Wood Work)

Page 204

Amount (Rs.)

Page 205: Rate analsis Chapter No. 12 (Wood Work)

Page 205

Amount (Rs.)

Page 206: Rate analsis Chapter No. 12 (Wood Work)

Page 206

Amount (Rs.)

Page 207: Rate analsis Chapter No. 12 (Wood Work)

Page 207

Amount (Rs.)

Page 208: Rate analsis Chapter No. 12 (Wood Work)

Page 208

Amount (Rs.)

Page 209: Rate analsis Chapter No. 12 (Wood Work)

Page 209

Amount (Rs.)

Page 210: Rate analsis Chapter No. 12 (Wood Work)

Page 210

Amount (Rs.)

Page 211: Rate analsis Chapter No. 12 (Wood Work)

Page 211

Amount (Rs.)

Page 212: Rate analsis Chapter No. 12 (Wood Work)

Page 212

Amount (Rs.)

Page 213: Rate analsis Chapter No. 12 (Wood Work)

Page 213

Amount (Rs.)

Page 214: Rate analsis Chapter No. 12 (Wood Work)

Page 214

Amount (Rs.)

Page 215: Rate analsis Chapter No. 12 (Wood Work)

Page 215

Amount (Rs.)

Page 216: Rate analsis Chapter No. 12 (Wood Work)

Page 216

Amount (Rs.)

Page 217: Rate analsis Chapter No. 12 (Wood Work)

Page 217

Amount (Rs.)

Page 218: Rate analsis Chapter No. 12 (Wood Work)

Page 218

Amount (Rs.)

Page 219: Rate analsis Chapter No. 12 (Wood Work)

Page 219

Amount (Rs.)

Page 220: Rate analsis Chapter No. 12 (Wood Work)

Page 220

Amount (Rs.)

Page 221: Rate analsis Chapter No. 12 (Wood Work)

Page 221

Amount (Rs.)

Page 222: Rate analsis Chapter No. 12 (Wood Work)

Page 222

Amount (Rs.)

Page 223: Rate analsis Chapter No. 12 (Wood Work)

Page 223

Amount (Rs.)

Page 224: Rate analsis Chapter No. 12 (Wood Work)

Page 224

Amount (Rs.)

Page 225: Rate analsis Chapter No. 12 (Wood Work)

Page 225

Amount (Rs.)

Page 226: Rate analsis Chapter No. 12 (Wood Work)

Page 226

Amount (Rs.)

Page 227: Rate analsis Chapter No. 12 (Wood Work)

Page 227

Amount (Rs.)

Page 228: Rate analsis Chapter No. 12 (Wood Work)

Page 228

Amount (Rs.)

Page 229: Rate analsis Chapter No. 12 (Wood Work)

Page 229

Amount (Rs.)

Page 230: Rate analsis Chapter No. 12 (Wood Work)

Page 230

Amount (Rs.)

Page 231: Rate analsis Chapter No. 12 (Wood Work)

Page 231

Amount (Rs.)

Page 232: Rate analsis Chapter No. 12 (Wood Work)

Page 232

Amount (Rs.)

Page 233: Rate analsis Chapter No. 12 (Wood Work)

Page 233

Amount (Rs.)

Page 234: Rate analsis Chapter No. 12 (Wood Work)

Page 234

Amount (Rs.)

Page 235: Rate analsis Chapter No. 12 (Wood Work)

Page 235

Amount (Rs.)

Page 236: Rate analsis Chapter No. 12 (Wood Work)

Page 236

Amount (Rs.)

Page 237: Rate analsis Chapter No. 12 (Wood Work)

Page 237

Amount (Rs.)

Page 238: Rate analsis Chapter No. 12 (Wood Work)

Page 238

Amount (Rs.)

Page 239: Rate analsis Chapter No. 12 (Wood Work)

Page 239

Amount (Rs.)

Page 240: Rate analsis Chapter No. 12 (Wood Work)

Page 240

Amount (Rs.)

Page 241: Rate analsis Chapter No. 12 (Wood Work)

Page 241

Amount (Rs.)

Page 242: Rate analsis Chapter No. 12 (Wood Work)

Page 242

Amount (Rs.)

Page 243: Rate analsis Chapter No. 12 (Wood Work)

Page 243

Amount (Rs.)

Page 244: Rate analsis Chapter No. 12 (Wood Work)

Page 244

Amount (Rs.)

Page 245: Rate analsis Chapter No. 12 (Wood Work)

Page 245

Amount (Rs.)

Page 246: Rate analsis Chapter No. 12 (Wood Work)

Page 246

Amount (Rs.)

Page 247: Rate analsis Chapter No. 12 (Wood Work)

Page 247

Amount (Rs.)

Page 248: Rate analsis Chapter No. 12 (Wood Work)

Page 248

Amount (Rs.)

Page 249: Rate analsis Chapter No. 12 (Wood Work)

Page 249

Amount (Rs.)

Page 250: Rate analsis Chapter No. 12 (Wood Work)

Page 250

Amount (Rs.)

Page 251: Rate analsis Chapter No. 12 (Wood Work)

Page 251

Amount (Rs.)

Page 252: Rate analsis Chapter No. 12 (Wood Work)

Page 252

Amount (Rs.)

Page 253: Rate analsis Chapter No. 12 (Wood Work)

Page 253

Amount (Rs.)

Page 254: Rate analsis Chapter No. 12 (Wood Work)

Page 254

Amount (Rs.)

Page 255: Rate analsis Chapter No. 12 (Wood Work)

Page 255

Amount (Rs.)

Page 256: Rate analsis Chapter No. 12 (Wood Work)

Page 256

Amount (Rs.)

Page 257: Rate analsis Chapter No. 12 (Wood Work)

Page 257

Amount (Rs.)

Page 258: Rate analsis Chapter No. 12 (Wood Work)

Page 258

Amount (Rs.)

Page 259: Rate analsis Chapter No. 12 (Wood Work)

Page 259

Amount (Rs.)

Page 260: Rate analsis Chapter No. 12 (Wood Work)

Page 260

Amount (Rs.)

Page 261: Rate analsis Chapter No. 12 (Wood Work)

Page 261

Amount (Rs.)

Page 262: Rate analsis Chapter No. 12 (Wood Work)

Page 262

Amount (Rs.)

Page 263: Rate analsis Chapter No. 12 (Wood Work)

Page 263

Amount (Rs.)

Page 264: Rate analsis Chapter No. 12 (Wood Work)

Page 264

Amount (Rs.)

Page 265: Rate analsis Chapter No. 12 (Wood Work)

Page 265

Amount (Rs.)

Page 266: Rate analsis Chapter No. 12 (Wood Work)

Page 266

Amount (Rs.)

Page 267: Rate analsis Chapter No. 12 (Wood Work)

Page 267

Amount (Rs.)

Page 268: Rate analsis Chapter No. 12 (Wood Work)

Page 268

Amount (Rs.)

Page 269: Rate analsis Chapter No. 12 (Wood Work)

Page 269

Amount (Rs.)

Page 270: Rate analsis Chapter No. 12 (Wood Work)

Page 270

Amount (Rs.)

Page 271: Rate analsis Chapter No. 12 (Wood Work)

Page 271

Amount (Rs.)

Page 272: Rate analsis Chapter No. 12 (Wood Work)

Page 272

Amount (Rs.)

Page 273: Rate analsis Chapter No. 12 (Wood Work)

Page 273

Amount (Rs.)

Page 274: Rate analsis Chapter No. 12 (Wood Work)

Page 274

Amount (Rs.)

Page 275: Rate analsis Chapter No. 12 (Wood Work)

Page 275

Amount (Rs.)

Page 276: Rate analsis Chapter No. 12 (Wood Work)

Page 276

Amount (Rs.)

Page 277: Rate analsis Chapter No. 12 (Wood Work)

Page 277

Amount (Rs.)

Page 278: Rate analsis Chapter No. 12 (Wood Work)

Page 278

Amount (Rs.)

Page 279: Rate analsis Chapter No. 12 (Wood Work)

Page 279

Amount (Rs.)

Page 280: Rate analsis Chapter No. 12 (Wood Work)

Page 280

Amount (Rs.)

Page 281: Rate analsis Chapter No. 12 (Wood Work)

Page 281

Amount (Rs.)

Page 282: Rate analsis Chapter No. 12 (Wood Work)

Page 282

Amount (Rs.)

Page 283: Rate analsis Chapter No. 12 (Wood Work)

Page 283

Amount (Rs.)

Page 284: Rate analsis Chapter No. 12 (Wood Work)

Page 284

Amount (Rs.)

Page 285: Rate analsis Chapter No. 12 (Wood Work)

Page 285

Amount (Rs.)

Page 286: Rate analsis Chapter No. 12 (Wood Work)

Page 286

Amount (Rs.)

Page 287: Rate analsis Chapter No. 12 (Wood Work)

Page 287

Amount (Rs.)

Page 288: Rate analsis Chapter No. 12 (Wood Work)

Page 288

Amount (Rs.)

Page 289: Rate analsis Chapter No. 12 (Wood Work)

Page 289

Amount (Rs.)

Page 290: Rate analsis Chapter No. 12 (Wood Work)

Page 290

Amount (Rs.)

Page 291: Rate analsis Chapter No. 12 (Wood Work)

Page 291

Amount (Rs.)

Page 292: Rate analsis Chapter No. 12 (Wood Work)

Page 292

Amount (Rs.)

Page 293: Rate analsis Chapter No. 12 (Wood Work)

Page 293

Amount (Rs.)

Page 294: Rate analsis Chapter No. 12 (Wood Work)

Page 294

Amount (Rs.)

Page 295: Rate analsis Chapter No. 12 (Wood Work)

Page 295

Amount (Rs.)

Page 296: Rate analsis Chapter No. 12 (Wood Work)

Page 296

Amount (Rs.)

Page 297: Rate analsis Chapter No. 12 (Wood Work)

Page 297

Amount (Rs.)

Page 298: Rate analsis Chapter No. 12 (Wood Work)

Page 298

Amount (Rs.)

Page 299: Rate analsis Chapter No. 12 (Wood Work)

Page 299

Amount (Rs.)

Page 300: Rate analsis Chapter No. 12 (Wood Work)

Page 300

Amount (Rs.)

Page 301: Rate analsis Chapter No. 12 (Wood Work)

Page 301

Amount (Rs.)

Page 302: Rate analsis Chapter No. 12 (Wood Work)

Page 302

Amount (Rs.)

Page 303: Rate analsis Chapter No. 12 (Wood Work)

Page 303

Amount (Rs.)

Page 304: Rate analsis Chapter No. 12 (Wood Work)

Page 304

Amount (Rs.)

Page 305: Rate analsis Chapter No. 12 (Wood Work)

Page 305

Amount (Rs.)

Page 306: Rate analsis Chapter No. 12 (Wood Work)

Page 306

Amount (Rs.)

Page 307: Rate analsis Chapter No. 12 (Wood Work)

Page 307

Amount (Rs.)

Page 308: Rate analsis Chapter No. 12 (Wood Work)

Page 308

Amount (Rs.)

Page 309: Rate analsis Chapter No. 12 (Wood Work)

Page 309

Amount (Rs.)

Page 310: Rate analsis Chapter No. 12 (Wood Work)

Page 310

Amount (Rs.)

Page 311: Rate analsis Chapter No. 12 (Wood Work)

Page 311

Amount (Rs.)

Page 312: Rate analsis Chapter No. 12 (Wood Work)

Page 312

Amount (Rs.)

Page 313: Rate analsis Chapter No. 12 (Wood Work)

Page 313

Amount (Rs.)

Page 314: Rate analsis Chapter No. 12 (Wood Work)

Page 314

Amount (Rs.)

Page 315: Rate analsis Chapter No. 12 (Wood Work)

Page 315

Amount (Rs.)

Page 316: Rate analsis Chapter No. 12 (Wood Work)

Page 316

Amount (Rs.)

Page 317: Rate analsis Chapter No. 12 (Wood Work)

Page 317

Amount (Rs.)

Page 318: Rate analsis Chapter No. 12 (Wood Work)

Page 318

Amount (Rs.)

Page 319: Rate analsis Chapter No. 12 (Wood Work)

Page 319

Amount (Rs.)

Page 320: Rate analsis Chapter No. 12 (Wood Work)

Page 320

Amount (Rs.)

Page 321: Rate analsis Chapter No. 12 (Wood Work)

Page 321

Amount (Rs.)

Page 322: Rate analsis Chapter No. 12 (Wood Work)

Page 322

Amount (Rs.)

Page 323: Rate analsis Chapter No. 12 (Wood Work)

Page 323

Amount (Rs.)

Page 324: Rate analsis Chapter No. 12 (Wood Work)

Page 324

Amount (Rs.)

Page 325: Rate analsis Chapter No. 12 (Wood Work)

Page 325

Amount (Rs.)

Page 326: Rate analsis Chapter No. 12 (Wood Work)

Page 326

Amount (Rs.)

Page 327: Rate analsis Chapter No. 12 (Wood Work)

Page 327

Amount (Rs.)

Page 328: Rate analsis Chapter No. 12 (Wood Work)

Page 328

Amount (Rs.)

Page 329: Rate analsis Chapter No. 12 (Wood Work)

Page 329

Amount (Rs.)