PAUD PROJECT PROGRESS - MAY 2017
PAUD PROJECT PROGRESS - MAY 2017
A1 BUILDING
A1 PROGRESS STATUS
• External plaster work completed
• Toilet Dado work in progress
• OHWT work in progress
• Flooring work started at ground floor
• Waterproofing work Completed
• Door shutter fixing work in progress
A1 EXTERNAL PLASTER
A2 BUILDING
A2 PROGRESS STATUS
• Block work completed at all Floors
• External plaster work in Progress– 20% Done
• Internal plaster completed till 5th Floor
• Water proofing completed till 4th Floor
• Electrical conduting work in progress
A3 BUILDING
A3 PROGRESS STATUS
• Staircase & Passage area painting work in progress
• External plumbing completed
• Lift installation completed
• Sanitary fixing work in progress – 30% Done
B1 BUILDING
B1 PROGRESS STATUS
• External Plaster – 100% Completed
• Concealed electrical conduiting done at all Floors
• Internal gypsum plaster done at all Floors
B2 BUILDING
B2 EXTERNAL PLASTER WIP
B2 PROGRESS STATUS
• Concealed electrical conduting work in progress, Completed till 6th
Floor
• Internal gypsum plaster activity in progress Completed till 5th Floor
• External plaster started
B3 BUILDING
B3 TOILET DADO STARTEDB3 ROOF FABRICATION
B3 PROGRESS STATUS
• Aluminum window work in progress – 70% Done
• Toilet Dado work in progress
• Staircase railing fabrication completed at all Floors
• Internal ceiling painting work started
• Roof fabrication work in progress
A3 APPROACH ROAD WORKSTP AREA PCC DONE
DEVELOPMENT ACTIVITIES
• STP area PCC done
• D4 side retaining wall casting done
• Road work started for Phase A & B
• External storm line work in progress
C1 BUILDING
C1 4TH SLAB SHUTTERING
C1 PROGRESS STATUS
• RCC Done till 3rd Slab
• 4th Slab RCC work in Progress
C2 BUILDING
C2 FOOTING CASTING
C2 PROGRESS STATUS
• 30 % Footing work completed
• 80% PCC work for footing completed
C3 BUILDING
C3 PROGRESS STATUS
• All Slab RCC work done till Terrace Slab
• Block work in progress at 3rd Floor
D3 BUILDING EXCAVATION
D4 BUILDING EXCAVATION
D4 ROAD EXCAVATION
D4 SIDE PLUM WALL
DEVELOPMENT ACTIVITIES
• D4 side retaining wall casting done
• Excavation at road near D4
THANK YOU