PAUD PROJECT PROGRESS - MAY 2017
31

Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

Mar 11, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

PAUD PROJECT PROGRESS - MAY 2017

Page 2: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 BUILDING

Page 3: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 PROGRESS STATUS

• External plaster work completed

• Toilet Dado work in progress

• OHWT work in progress

• Flooring work started at ground floor

• Waterproofing work Completed

• Door shutter fixing work in progress

Page 4: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 EXTERNAL PLASTER

Page 5: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A2 BUILDING

Page 6: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A2 PROGRESS STATUS

• Block work completed at all Floors

• External plaster work in Progress– 20% Done

• Internal plaster completed till 5th Floor

• Water proofing completed till 4th Floor

• Electrical conduting work in progress

Page 7: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 BUILDING

Page 8: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 PROGRESS STATUS

• Staircase & Passage area painting work in progress

• External plumbing completed

• Lift installation completed

• Sanitary fixing work in progress – 30% Done

Page 9: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B1 BUILDING

Page 10: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B1 PROGRESS STATUS

• External Plaster – 100% Completed

• Concealed electrical conduiting done at all Floors

• Internal gypsum plaster done at all Floors

Page 11: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 BUILDING

Page 12: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 EXTERNAL PLASTER WIP

Page 13: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 PROGRESS STATUS

• Concealed electrical conduting work in progress, Completed till 6th

Floor

• Internal gypsum plaster activity in progress Completed till 5th Floor

• External plaster started

Page 14: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 BUILDING

Page 15: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 TOILET DADO STARTEDB3 ROOF FABRICATION

Page 16: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 PROGRESS STATUS

• Aluminum window work in progress – 70% Done

• Toilet Dado work in progress

• Staircase railing fabrication completed at all Floors

• Internal ceiling painting work started

• Roof fabrication work in progress

Page 17: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 APPROACH ROAD WORKSTP AREA PCC DONE

Page 18: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

DEVELOPMENT ACTIVITIES

• STP area PCC done

• D4 side retaining wall casting done

• Road work started for Phase A & B

• External storm line work in progress

Page 19: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 BUILDING

Page 20: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 4TH SLAB SHUTTERING

Page 21: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 PROGRESS STATUS

• RCC Done till 3rd Slab

• 4th Slab RCC work in Progress

Page 22: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 BUILDING

Page 23: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 FOOTING CASTING

Page 24: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 PROGRESS STATUS

• 30 % Footing work completed

• 80% PCC work for footing completed

Page 25: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C3 BUILDING

Page 26: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C3 PROGRESS STATUS

• All Slab RCC work done till Terrace Slab

• Block work in progress at 3rd Floor

Page 27: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D3 BUILDING EXCAVATION

D4 BUILDING EXCAVATION

Page 28: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D4 ROAD EXCAVATION

Page 29: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D4 SIDE PLUM WALL

Page 30: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

DEVELOPMENT ACTIVITIES

• D4 side retaining wall casting done

• Excavation at road near D4

Page 31: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

THANK YOU