1 RAL Integration Issues RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL
16

RAL Integration Issues

Jan 01, 2016

Download

Documents

Meghan Malone

RAL Integration Issues. Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL. MICE Collaboration Meeting, Osaka, August 1-3, 2004. Scope. Layout Beam height Support structure Beam line shielding layout. MICE layout. Height of MICE beam. Dia 650. Aperture in ISIS wall. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: RAL Integration Issues

1

RAL Integration IssuesRAL Integration Issues

MICE Collaboration Meeting, Osaka, August 1-3, 2004

Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones

RAL

Page 2: RAL Integration Issues

2

• Layout

• Beam height

• Support structure

• Beam line shielding layout

Scope

Page 3: RAL Integration Issues

3

MICE layout

Page 4: RAL Integration Issues

4

Concrete floor

Support structure

Dia 650Aperture in ISIS wall

1684.2

160*

1524*

Height of MICE beam

Page 5: RAL Integration Issues

5

MICE support structure : Concept

• Requirements/specification: - to move MICE modules out the beam (to the side direction) for various MICE stages

( Qs: Do we need to move ALL modules?; Is the side direction preferable?)

• Accuracy/tolerances: - along the beam +/- 1 mm - across the beam +/- 1 mm

(Q: What position accuracy is required for module-to-module connection ?)

• Adjustment: - adjustment possibility is required.• Locking mechanism: - required.• Loads: - max load is 3 (?) tonnes.• Force transfer function: - gravity force to the floor; - module-to-module axial force to the floor ?

Page 6: RAL Integration Issues

6

MICE support structure : Options

• Commercial rail system: - usually high accuracy (+/- 0.1 mm )

( Q: Do we need it?)

- proven design; - delivery times – days ( if off-the-shelf product);

BUT high cost.

• Simple slides arrangement: - accuracy; - cost; - prototype.

Page 7: RAL Integration Issues

7

HEPCO SL2 stainless steel based slide system

Item Price/each, £ No./MICE Total No. Total price, with VAT, module k£ k£

Stock SL2 carriage (type AU SS L 76) 460 4 28 12.880 15.134 in assembled and adjusted condition

Spacer slide (rail) SS NL 76 Length of 4.5 m in 3-m and 1.5-m sections 2475 2 14 34.650 40.714

Grand total, k£ 55.848

Delivery time: 3-5 days

Hepco Slide Systems Ltd, Devon England EX16 6TG

MICE support structure: Commercial system

Page 8: RAL Integration Issues

8

MICE support structure: Commercial system (2)

Page 9: RAL Integration Issues

9

Concrete floor

Simple slides arrangement

MICE support structure: Alternative solution

Rails

Low-friction material blocks

Sliding carriages

Platform

Page 10: RAL Integration Issues

10

MICE support structure vs. MICE stages

Problem: some of MICE modules will be located in various positions along the beam for different stages of the experiment.

Possible solution: sliding rails (rails on rails).

Concrete floor

Platform

Steel plate

HEPCO rail system

Beam

Bottom rails 20

40

80

20

160*

MICEmodule

Page 11: RAL Integration Issues

11

Beam line and shielding layout

Beam line shielding:

• shields MICE against full beam loss in the ISIS beam pipe (-> 2m of steel is required);

• is removable for access to PSI solenoid;• ideally allows to work on the beam line components in the MICE hall even when the ISIS beam is on -> concept of temporary shielding.

Page 12: RAL Integration Issues

12

Beam line and shielding layout

Page 13: RAL Integration Issues

13

Steel shielding

Concrete shielding17-tonne magnetPSI solenoid

Crane zone limits

ISIS wall

Beam line shielding

Existing steelshielding

Page 14: RAL Integration Issues

14

PSI solenoid support structure and shielding

Concrete ISIS wall

Steelshielding

Page 15: RAL Integration Issues

15

Temporary shielding arrangement

These two magnets are in Off-beam position

PSI solenoid is in Test position

Temporary steel shielding

Page 16: RAL Integration Issues

16

Next steps

• MICE general layout: - start implementing MICE sub-systems (RF power system, hydrogen system etc.) and magnetic shielding (requires more modelling).

• Support structure: - agree on requirement/specs; - agree on concept; - get cost estimations for various options.

• Beam line and shielding layout: - finish detailed design; - get OK from ISIS Radiation Safety Officer