R E K A P I T U L A S I A N G G Kegiatan : Pekerjaan : Pembuatan Pos Jaga Lokasi : Tahun Anggaran : APBN-P 2012 No Uraian Pekerjaan 1 2 A PEKERJAAN PERSIAPAN B PEKERJAAN TANAH DAN PASIR C PEKERJAAN PONDASI D PEKERJAAN BETON E PEKERJAAN LANTAI DAN PASANGAN F PEKERJAAN PINTU, JENDELA & VENTILASI G PEKERJAAN PLAFOND H PEKERJAAN PENGECATAN I PEKERJAAN PENGGANTUNG J PEKERJAAN INSTALASI LISTRIK K PEKERJAAN SANITASI L PEKERJAAN AKHIR DAN LAIN-LAIN HARGA FISIK PPN 10% JUMLAH HARGA DIBULATKAN TERBILANG : LIMA PULUH TUJUH JUTA ENAM RATUS Mengetahui/Menyetujui Pejabat Pembuat Komitmen ICHSAN FIRMANSYAH M. AMIN, SE
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
R E K A P I T U L A S I A N G G A R A N
Kegiatan :
Pekerjaan : Pembuatan Pos Jaga
Lokasi :
Tahun Anggaran : APBN-P 2012
No Uraian PekerjaanJumlah Harga
(Rp.)1 2 3
A PEKERJAAN PERSIAPAN 1,500,000
B PEKERJAAN TANAH DAN PASIR 2,063,280
C PEKERJAAN PONDASI 4,141,955
D PEKERJAAN BETON 10,141,900
E PEKERJAAN LANTAI DAN PASANGAN 15,399,160
F PEKERJAAN PINTU, JENDELA & VENTILASI 4,409,261
G PEKERJAAN PLAFOND 1,418,725
H PEKERJAAN PENGECATAN 3,695,349
I PEKERJAAN PENGGANTUNG 1,432,605
J PEKERJAAN INSTALASI LISTRIK 1,310,000
K PEKERJAAN SANITASI 5,315,613
L PEKERJAAN AKHIR DAN LAIN-LAIN 1,500,000
HARGA FISIK 52,327,848
PPN 10% 5,232,785
JUMLAH HARGA 57,560,632
DIBULATKAN 57,500,000
TERBILANG : LIMA PULUH TUJUH JUTA ENAM RATUS RIBU RUPIAH
Palu, September 2012
Mengetahui/Menyetujui Dibuat Oleh,Pejabat Pembuat Komitmen Konsultan Perencana
PT. ADITAMA KARYA
ICHSAN FIRMANSYAH M. AMIN, SE ABDUL RAHMAN, ST., IAI
NIP. 19830303 200901 1 026 Direktur
RENCANA ANGGARAN BIAYA (RAB)
Kegiatan : Pekerjaan : Pembuatan Pos Jaga Lokasi : Tahun Anggaran : APBN-P 2012
No Uraian Pekerjaan Satuan VolumeHarga SatuanJumlah Harga
(Rp.) (Rp.)1 2 3 4.00 5 6A PEKERJAAN PERSIAPAN 1 Pek Pembersihaan Lokasi Ls 1.00 500,000 500,000 2 Pek. Papan Nama Proyek Ls 1.00 500,000 500,000 3 Pengukuran dan Pemasangan Bowplank Ls 1.00 500,000 500,000
Jumlah A 1,500,000 B PEKERJAAN TANAH DAN PASIR 1 Pek. Galian Tanah 7.38 52,650 388,557
2 Pek. Urugan Kembali Bekas Galian 1.85 17,550 32,380
3 Pek. Urugan Tanah Bawah Lantai (dipadatk 5.77 5,850 33,754
4 Pek. Urugan Pasir Bawah Pondasi 5.42 107,200 581,024
5 Pek. Urugan sirtu Bawah lantai (dipadatkan 10.99 93,500 1,027,565 Jumlah B 2,063,280
C PEKERJAAN PONDASI 1 Pek. Pas. Pondasi Batu Kali 7.09 507,395 3,597,431
2 Pek. Pas. Batu Kosong 2.45 222,255 544,525 Jumlah C 4,141,955
D PEKERJAAN BETON 1 Pek. Beton Bertulang 1.57 2,789,357 4,379,290
Jumlah K 1,310,000 K PEKERJAAN SANITASI 1 Kran Air Bh 1.00 40,363 40,363 2 Floor Drain Bh 1.00 25,250 25,250 3 Klosed Duduk Bh 1.00 1,150,000 1,150,000 4 Sumur Dangkal Pipa Gip 1 1/2" Kedalaman LS 1.00 1,500,000 1,500,000 5 Mesin Pompa 125 Watt LS 1.00 600,000 600,000 6 Pipa dan Aksesoris LS 1.00 500,000 500,000 7 Pek. Saptick Tank Buis Beton Bulat 2 susun LS 1.00 1,500,000 1,500,000
Jumlah K 5,315,613 L PEKERJAAN AKHIR DAN LAIN-LAIN 1 Pekerjaan Pembersihan Lokasi Ls 1.00 500,000 500,000 2 Dokumentasi LS 1.00 500,000 500,000 3 As Build Drawing Ls 1.00 500,000 500,000
Jumlah K 1,500,000
Palu, September 2012
Mengetahui/Menyetujui Dibuat Oleh, Pejabat Pembuat Komitmen Konsultan Perencana
PT. ADITAMA KARYA
ICHSAN FIRMANSYAH M. AMIN, SE ABDUL RAHMAN, ST., IAI NIP. 19830303 200901 1 026 Direktur
M2
5 of 12
ANALISA HARGA SATUAN PEKERJAAN Kegiatan : Pekerjaan : Pembuatan Pos Jaga Lokasi : Tahun Anggaran : APBN-P 2012
PEKERJAAN PERSIAPAN1 M' Pagar Sementara dari Seng Gelombang, Tinggi 2 meter
Bahan :1.250 Btg Dolken kayu diameter 8-10/400 c @ - 2.500 Kg Semen portland @ - 1.200 Lbr Seng gelombang 3 inci – 5 inci @ -
0.005 Pasir beton @ -
0.009 Koral beton @ -
0.072 Kayu 5/7 @ - 0.060 Kg Paku biasa 2 inci – 5 inci @ - 0.450 Ltr Meni besi @ -
Tenaga :0.200 OH Tukang kayu @ - 0.400 OH Pekerja @ - 0.020 OH Kepala tukang @ -
0.020 OH Mandor @ - Jumlah -
1 M' Pengukuran dan Pemasangan BowplankBahan :
0.012 M³ Kayu 5/7 @ 1,200,000.00 14,400.00 0.020 Kg Paku biasa 2 inci – 5 inci @ 24,000.00 480.00 0.007 M³ Kayu papan 3/20 @ 1,200,000.00 8,400.00
Tenaga :0.200 OH Tukang kayu @ 70,000.00 14,000.00 0.400 OH Pekerja @ 55,000.00 22,000.00 0.020 OH Kepala tukang @ 75,000.00 1,500.00
0.020 OH Mandor @ 70,000.00 1,400.00 Jumlah 62,180.00
1 M2 Pembuatan Kantor SementaraBahan :
1.250 Btg Dolken kayu diameter 8-10/400 @ 10,000.00 12,500.00 0.180 M³ Kayu @ 1,750,000.00 315,000.00 0.850 Kg Kayu biasa @ 1,200,000.00 1,020,000.00 1.100 Kg Besi strip @ 16,400.00 18,040.00
Bahan :1.250 batang Dolken kayu diameter 8-10/400 c @ 10,000.00 12,500.00 0.186 M³ Kayu @ 1,750,000.00 325,500.00 0.300 Kg Kayu biasa @ 1,200,000.00 360,000.00
18.000 Kg Semen Portland @ 1,500.00 27,000.00 0.030 M³ Pasir beton @ 80,000.00 2,400.00 0.050 M³ Koral beton @ 197,000.00 9,850.00 1.500 Lbr Seng gelombang bwg 32 @ 56,000.00 84,000.00 1.500 Lbr Plywood 4 mm @ -
Tenaga :2.000 OH Tukang kayu @ 70,000.00 140,000.00 1.000 OH Pekerja @ 55,000.00 55,000.00 0.200 OH Kepala tukang @ 75,000.00 15,000.00 0.050 OH Mandor @ 70,000.00 3,500.00
Jumlah 1,034,750.00 PEKERJAAN TANAHMenggali 1 M³ Tanah Biasa Sedalam 2 Meter
Tenaga :1.500 OH Pekerja @ 55,000.00 82,500.00 0.750 OH Tukang batu @ 70,000.00 52,500.00 0.075 OH Kepala tukang @ 75,000.00 5,625.00 0.075 OH Mandor @ 70,000.00 5,250.00
Jumlah 507,395.00
Bahan :1.200 M³ Batu belah 15 cm/20 cm @ 95,000.00 114,000.00 0.432 M³ Pasir Urug @ 75,000.00 32,400.00
Tenaga :0.780 OH Pekerja @ 55,000.00 42,900.00 0.390 OH Tukang batu @ 70,000.00 27,300.00 0.039 OH Kepala tukang @ 75,000.00 2,925.00 0.039 OH Mandor @ 70,000.00 2,730.00
Jumlah 222,255.00 PEKERJAAN BETON
Bahan :0.045 M³ Kayu kelas III @ 1,200,000.00 54,000.00 0.300 Kg Paku 5 cm-12cm @ 24,000.00 7,200.00 0.100 Ltr Minyak bekisting @ - -
Tenaga :0.520 OH Pekerja @ 55,000.00 28,600.00 0.260 OH Tukang kayu @ 70,000.00 18,200.00 0.026 OH Kepala tukang @ 75,000.00 1,950.00 0.026 OH Mandor @ 70,000.00 1,820.00
Jumlah 111,770.00
Bahan :0.040 M³ Kayu kelas III @ 1,200,000.00 48,000.00 0.400 Kg Paku 5 cm-12cm @ 24,000.00 9,600.00 0.200 Ltr Minyak bekisting @ - - 0.015 M³ Kayu kelas II balok @ 1,200,000.00 18,000.00 0.350 Lbr Plywood 9 mm @ 90,000.00 31,500.00 2.000 Btg Dolken kayu galam, @ 15,000.00 30,000.00
Jumlah 201,060.00 Membuat 1 M2 Bekisting Balok Beton
Bahan :0.040 M³ Kayu kelas III @ 1,200,000.00 48,000.00 0.400 Kg Paku 5 cm-12cm @ 24,000.00 9,600.00 0.200 Ltr Minyak bekisting @ 10,000.00 2,000.00 0.018 M³ Kayu kelas II balok @ 1,200,000.00 21,600.00 0.350 Lbr Plywood 9 mm @ 90,000.00 31,500.00 2.000 Btg Dolken kayu galam, @ 10,000.00 20,000.00
Memasang 1 M3 Pondasi Batu Belah, Campuran 1 PC : 5 PP
Memasang 1 M3 Batu kosong (anstamping)
Membuat 1 M2 Bekisting Untuk Sloof Beton
Membuat 1 M2 Bekisting Kolom Beton
9 of 12
Bahan :0.040 M³ Kayu kelas III @ 1,200,000.00 48,000.00 0.400 Kg Paku 5 cm-12cm @ 24,000.00 9,600.00 0.200 Ltr Minyak bekisting @ - - 0.015 M³ Kayu kelas II balok @ 1,200,000.00 18,000.00 0.350 Lbr Plywood 9 mm @ 90,000.00 31,500.00 6.000 Btg Dolken kayu galam, @ 10,000.00 60,000.00
Jumlah 129,255.00 Untuk 1 Kg Pembesian Polos/ulir @ 12,925.50
Memasang 1M2 Bekisting untuk TanggaBahan :
0.030 M³ Kayu kelas III @ 1,200,000.00 36,000.00 0.400 Kg Paku 5 cm – 12 cm @ 24,000.00 9,600.00 0.150 Ltr Minyak bekisting @ 10,000.00 1,500.00 0.015 M³ Balok kayu kelas II @ 1,750,000.00 26,250.00 0.350 Lbr Plywood tebal 9 mm @ - 2.000 Btg Dolken kayu galam, @ 10,000.00 20,000.00
Tenaga :0.300 OH Pekerja @ 55,000.00 16,500.00 0.150 OH Tukang Batu @ 70,000.00 10,500.00 0.015 OH Kepala tukang @ 75,000.00 1,125.00 0.015 OH Mandor @ 70,000.00 1,050.00
Jumlah 39,906.00
Bahan :3.250 Kg Portland Cement @ 1,500.00 4,875.00
Tenaga :0.200 OH Pekerja @ 55,000.00 11,000.00 0.100 OH Tukang Batu @ 70,000.00 7,000.00 0.010 OH Kepala tukang @ 75,000.00 750.00 0.010 OH Mandor @ 70,000.00 700.00
Jumlah 24,325.00 PEKERJAAN KAYUMembuat dan Memasang 1M³ Kusen Pintu dan Kusen Jendela, Kayu Kelas II atau III
Bahan :1.200 M³ Balok kayu @ 1,750,000.00 2,100,000.00 1.250 Kg Paku 10 cm @ 24,000.00 30,000.00 1.000 Kg Lem kayu @ 25,000.00 25,000.00
Tenaga :6.000 OH Pekerja @ 55,000.00 330,000.00
18.000 OH Tukang Kayu @ 70,000.00 1,260,000.00 1.800 OH Kepala tukang @ 75,000.00 135,000.00 0.300 OH Mandor @ 70,000.00 21,000.00
Jumlah 3,901,000.00
Membuat 1M2 Plesteran 1 PC : 5 PP, tebal 15 mm
Membuat 1M2 Plesteran 1 PC : 2 KP : 8 PP 5 PP, tebal 15 mm
Membuat 1M2 Acian
12 of 12
Bahan :0.024 M³ Papan kayu @ 1,750,000.00 42,000.00 0.300 Kg Lem kayu @ 25,000.00 7,500.00
Tenaga :0.800 OH Pekerja @ 55,000.00 44,000.00 2.400 OH Tukang Kayu @ 70,000.00 168,000.00 0.240 OH Kepala tukang @ 75,000.00 18,000.00 0.040 OH Mandor @ 70,000.00 2,800.00
Jumlah 282,300.00
Bahan :0.064 M³ Papan kayu @ 1,750,000.00 112,000.00 0.500 Kg Lem kayu @ 25,000.00 12,500.00
Tenaga :1.000 OH Pekerja @ 55,000.00 55,000.00 3.000 OH Tukang Kayu @ 70,000.00 210,000.00 0.300 OH Kepala tukang @ 75,000.00 22,500.00 0.050 OH Mandor @ 70,000.00 3,500.00
Jumlah 415,500.00
Bahan :0.040 M³ Papan kayu @ 1,750,000.00 70,000.00 0.500 Kg Lem kayu @ 25,000.00 12,500.00
Tenaga :1.000 OH Pekerja @ 55,000.00 55,000.00 3.000 OH Tukang Kayu @ 70,000.00 210,000.00 0.300 OH Kepala tukang @ 75,000.00 22,500.00 0.050 OH Mandor @ 70,000.00 3,500.00
Jumlah 373,500.00
Bahan :1.100 M³ Balok kayu @ 1,750,000.00 1,925,000.00
15.000 Kg Besi strip tebal 5 mm @ 16,400.00 246,000.00 5.600 Kg Paku 12 cm @ 24,000.00 134,400.00
Tenaga :4.000 OH Pekerja @ 55,000.00 220,000.00
12.000 OH Tukang Kayu @ 70,000.00 840,000.00 1.200 OH Kepala tukang @ 75,000.00 90,000.00 0.200 OH Mandor @ 70,000.00 14,000.00
Jumlah 3,469,400.00
Bahan :1.100 M³ Balok kayu @ 1,750,000.00 1,925,000.00
15.000 Kg Besi strip tebal 5 mm @ 16,400.00 246,000.00 3.000 Kg Paku 12 cm @ 24,000.00 72,000.00
Tenaga :4.000 OH Pekerja @ 55,000.00 220,000.00
12.000 OH Tukang Kayu @ 70,000.00 840,000.00 1.200 OH Kepala tukang @ 75,000.00 90,000.00 0.200 OH Mandor @ 70,000.00 14,000.00
Jumlah 3,407,000.00
Bahan :0.014 M³ Kaso-kaso (5 x 7) cm @ 1,750,000.00 24,500.00 0.004 M³ Reng (2 x 3) cm @ 1,750,000.00 6,300.00 0.250 Kg Paku 5 cm dan 10 cm @ 24,000.00 6,000.00
Tenaga :0.100 OH Pekerja @ 55,000.00 5,500.00 0.100 OH Tukang Kayu @ 70,000.00 7,000.00 0.010 OH Kepala tukang @ 75,000.00 750.00 0.005 OH Mandor @ 70,000.00 350.00
Jumlah 50,400.00
Membuat dan Memasang 1M2 Pintu dan Jendela Kaca, Kayu Kelas I atau II
Membuat dan Memasang 1 M2 Pintu dan Jendela Jalusi Kayu Kelas I atau II
Membuat dan Memasang 1 M2 Daun Pintu Panel, Kayu Kelas I atau II
Memasang 1 M2 Konstruksi Kuda-kuda Konvensional, kayu kelas I, II dan III bentang 6 meter
Memasang 1 M3 Konstruksi Gording, kayu kelas II
Memasang 1 M2 Rangka Atap Genteng Keramik kayu kelas II
Mengetahui/Menyetujui Dibuat Oleh,Pejabat Pembuat Komitmen Konsultan Perencana
PT. ADITAMA KARYA0000
ICHSAN FIRMANSYAH M. AMIN, SE ABDUL RAHMAN, ST., IAINIP. 19830303 200901 1 026 Direktur
DAFTAR HARGA SATUAN, BAHAN DAN UPAH
Kegiatan :
Pekerjaan : Pembuatan Pos Jaga
Lokasi :
Tahun Anggaran : APBN-P 2012 -
No. U r a i a n Satuan Harga Satuan
A. U P A H 1 Pekerja hari Rp 55,000 2 Tukang Batu, Kayu, Besi, Cat hari Rp 70,000 3 Kepala Tukang hari Rp 75,000 4 Mandor hari Rp 70,000 5 Tukang Bongkar Cetakan Beton/Siram hari Rp 50,000
B. B A H A N 1 Sirtu m3 Rp 65,000 2 Pasir Urug m3 Rp 75,000 3 Pasir Pasangan/Pasir Cor m3 Rp 80,000 4 Kerikil Sungai hasil saringan m3 Rp 90,000 5 Batu Pecah 1/2 m3 Rp 205,000 6 Batu Pecah 2/3 m3 Rp 197,000 7 Semen zak Rp 75,000
Kg Rp 1,500 8 Batu Kali/Batu Gunung/Batu Belah m3 Rp 95,000 9 Batu Bata bh Rp 680
10 Besi Beton Polos kg Rp 11,200 11 Kawat Beton kg Rp 14,000 12 Kayu Kelas III m3 Rp 1,200,000 13 Kayu Kelas II m3 Rp 1,750,000 14 Dolken Kayu Btg Rp 10,000 15 Minyak Bekisting Ltr Rp 10,000 16 Paku Triplek kg Rp 20,000 17 Paku kg Rp 24,000 18 Paku Seng kg Rp 25,000 19 Paku Skrup Kg Rp 25,000 20 Sekrup Gipsum Kg Rp 75,000 21 Cat Tembok kg Rp 22,000 22 Cat Besi kg Rp 37,500 23 Cat Kayu kg Rp 37,500 24 Minyak Cat / Thinner ltr Rp 16,000 25 Meni Kayu kg Rp 12,500 26 Plamir Tembok kg Rp 8,500 27 Plamir Kayu kg Rp 12,500 28 Seng Gelombang BJLS 0.2 lbr Rp 56,000 29 Seng Talang m' Rp 17,500 30 Besi Strip kg Rp 16,400 31 Atap Genteng Zinczalume 0,25 mm Lbr Rp 55,000 32 Bubungan Genteng Zinczalume 0,25 mm m' Rp 20,000 33 Metal Hollow Btg Rp 35,000 34 Rangka Kuda-kuda Baja Ringan Btg Rp 65,000 35 Reng baja Ringan Btg Rp 50,000 36 Engsel Pintu psg Rp 30,000 37 Handel/Kunci Pintu bh Rp 160,000 38 Engsel Jendela Psg Rp 22,500
39 Gerendel Jendela Bh Rp 15,000
No. U r a i a n Satuan Harga Satuan (Rp.)
40 Gerendel Pintu (Pintu Depan) Bh Rp 13,750 41 Haak Angin Psg Rp 14,000 42 Gypsum Board 9mm Lbr Rp 75,000
Polywood 9mm Lbr Rp 90,000 43 Teakwood Lbr Rp 78,000 44 Tripleks 3 mm Lbr Rp 50,000 45 Tripleks Lapis Alumunium Lbr Rp 125,000 46 Slot/Gembok lengkap bh Rp 40,000 47 Lem Kayu kg Rp 25,000 48 Keramik 30 x 30 dos Rp 47,500
Bh Rp 4,275 49 Keramik 20 x 20 dos Rp 48,000
Bh Rp 4,320 50 Keramik 20 x 25 dos Rp 48,000 51 Semen Warna (Putih) zak Rp 55,000
Kg Rp 11,000 52 Kloset Jongkok Bh Rp 157,000 5354 Bak Fibre Psg Rp 225,000 55 Kran Air Psg Rp 32,500 56 Floor Drain Bh Rp 17,500 57 Seal Tape Bh Rp 4,500 58 Kaca Polos 5 mm m2 Rp 120,000 59 Lampu Philips XL Bh Rp 32,000 60 Wastafel Set Rp 250,000 61 Bak Cuci Piring Stainless steel Bh Rp 300,000 62 Pipa Galvanis 1'' M' Rp 20,000 63 PVC type AW 3" M' Rp 18,500 64 Instalasi Titik Lampu Titik Rp 100,000 65 Lampu Down Light Bh Rp 55,000 66 Lampu SL Bh Rp 20,000 67 Saklar Ganda Bh Rp 30,000 68 Saklar Seri Bh Rp 50,000 69 Saklar Tunggal Bh Rp 25,000 70 Panel Listrik Bh Rp 150,000 71 Stop Kontak Bh Rp 55,000
Palu, September 2012
Mengetahui/Menyetujui Dibuat Oleh, Pejabat Pembuat Komitmen Konsultan Perencana
PT. ADITAMA KARYA
ICHSAN FIRMANSYAH M. AMIN, SE ABDUL RAHMAN, ST., IAI NIP. 19830303 200901 1 026 Direktur