REKAPITULASI RENCANA ANGGARAN BIAYA (RAB) PERENCANAAN KANTOR BADAN NARKOTIKA NASIONAL (BNN) PADA KAWASAN MOI DI MAKASSAR PEKERJAAN : PERENCANAAN KANTOR BNN ANGGARAN : TAHUN 2011 NO J E N I S P E K E R J A A N TOTAL HARGA (Rp.) A LANTAI I (DASAR) I PEK. PERSIAPAN Rp. 73,639,822.50 I PEK. PONDASI KONSTRUKSI SARANG LABA - LABA (KSLL) Rp. 2,031,803,097.50 II PEK. STRUKTUR BETON Rp. 377,441,899.78 IV PEKERJAAN DINDING Rp. 224,960,911.89 V PEKERJAAN PINTU DAN JENDELA Rp. 563,673,128.53 VI PEK. PLAFOND Rp. 74,011,152.43 VII PEKERJAAN LANTAI Rp. 322,230,292.47 VIII PEK. PENGECATAN Rp. 67,349,299.18 IX PEK. INSTALASI LISTRIK Rp. 162,985,500.00 X PEK. SANITASI DAN INSTALASI Rp. 103,303,658.54 B LANTAI II (DUA) I PEK. STRUKTUR BETON Rp. 1,208,477,521.53 II PEKERJAAN DINDING Rp. 235,693,072.46 III PEKERJAAN PINTU DAN JENDELA Rp. 628,066,868.62 IV PEK. PLAFOND Rp. 113,692,742.73 V PEKERJAAN LANTAI Rp. 301,403,830.67 VI PEK. PENGECATAN Rp. 82,749,104.09 VII PEK. KONSTRUKSI ATAP Rp. 523,439,934.21 VIII PEK. INSTALASI LISTRIK Rp. 107,771,500.00 IX PEK. SANITASI DAN INSTALASI Rp. 27,511,627.50 X PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR Rp. 81,222,583.05 REAL COST TOTAL Rp. 7,311,427,547.68 PPN 10% Rp. 731,142,754.77 TOTAL COST Rp. 8,042,570,302.44 DIBULATKAN Rp. 8,042,570,000.00 2011 Diketahui/Disetujui : Konsultan Perencana, PEJABAT PELAKSANA TEKNIS KEGIATAN CV. BAJIRUPA CONSULTANT Ir. H. JUMRAS, M.Si BADARUDDIN, ST Nip. 19620707 199203 1 012 Direktur Mengetahui/Menyetujui : KEPALA BIDANG PENATAAN BANGUNAN DAN LINGKUNGAN DINAS TATARUANG DAN PERMUKIMAN PROVINSI SULAWESI SELATAN Ir. H. DANIYAL DARABA, M.Si Nip. 19560407 198303 1 012 TERBILANG : Tujuh milyar enam ratus tujuh puluh tiga juta dua ratus lima puluh sembilan ribu rupiah,-
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)PERENCANAAN KANTOR BADAN NARKOTIKA NASIONAL (BNN)
PADA KAWASAN MOI DI MAKASSAR
PEKERJAAN : PERENCANAAN KANTOR BNNANGGARAN : TAHUN 2011
NO J E N I S P E K E R J A A N TOTAL HARGA (Rp.)
A LANTAI I (DASAR)
I PEK. PERSIAPAN Rp. 73,639,822.50 I PEK. PONDASI KONSTRUKSI SARANG LABA - LABA (KSLL) Rp. 2,031,803,097.50 II PEK. STRUKTUR BETON Rp. 377,441,899.78 IV PEKERJAAN DINDING Rp. 224,960,911.89 V PEKERJAAN PINTU DAN JENDELA Rp. 563,673,128.53
VI PEK. PLAFOND Rp. 74,011,152.43 VII PEKERJAAN LANTAI Rp. 322,230,292.47 VIII PEK. PENGECATAN Rp. 67,349,299.18 IX PEK. INSTALASI LISTRIK Rp. 162,985,500.00 X PEK. SANITASI DAN INSTALASI Rp. 103,303,658.54
B LANTAI II (DUA) I PEK. STRUKTUR BETON Rp. 1,208,477,521.53 II PEKERJAAN DINDING Rp. 235,693,072.46 III PEKERJAAN PINTU DAN JENDELA Rp. 628,066,868.62 IV PEK. PLAFOND Rp. 113,692,742.73 V PEKERJAAN LANTAI Rp. 301,403,830.67 VI PEK. PENGECATAN Rp. 82,749,104.09 VII PEK. KONSTRUKSI ATAP Rp. 523,439,934.21 VIII PEK. INSTALASI LISTRIK Rp. 107,771,500.00 IX PEK. SANITASI DAN INSTALASI Rp. 27,511,627.50 X PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR Rp. 81,222,583.05
REAL COST TOTAL Rp. 7,311,427,547.68 PPN 10% Rp. 731,142,754.77 TOTAL COST Rp. 8,042,570,302.44 DIBULATKAN Rp. 8,042,570,000.00
X PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR
1. Pek. Saluran Air Keliling Gedung 113.58 m' 242,615.74 27,555,083.05
2. Pek. Tower air Uk. 2,00 x 2,00 m , Tinggi 8,00 m 1.00 Unit 16,000,000.00 16,000,000.00
3. Pek. Reling Tangga dan Balkon 42.55 m' 850,000.00 36,167,500.00
4. Pek. Penyelesaian Akhir/Pembersihan 1.00 Ls 1,500,000.00 1,500,000.00
Jumlah 81,222,583.05
Realcost Lt. I Dan II Rp 7,311,427,547.68
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN PONDOK PESANTREN TAHFIZHUL QURAN AL - IMAM ASHIM
KOTA MAKASSAR
PEKERJAAN : PEMB. PONDOK PESANTREN TAHFIZHUL QURAN AL-IMAN ASHIMLOKASI : KEL. BANGKALA, KEC. MANGGALA, KOTA MAKASSARANGGARAN : TAHUN 2014
NO J E N I S P E K E R J A A N TOTAL HARGA (Rp.)
A PEKERJAAN PERSIAPAN
I PEK. PERSIAPAN Rp. 47,782,625.00 B PEKERJAAN LANTAI I (SATU)I PEK. TANAH DAN PONDASI Rp. 119,078,224.63 II PEK. STRUKTUR BETON Rp. 271,153,114.55 III PEKERJAAN DINDING Rp. 126,973,751.62 IV PEKERJAAN PINTU DAN JENDELA Rp. 96,188,677.82 V PEK. PLAFOND Rp. 75,497,827.28 VI PEKERJAAN LANTAI Rp. 230,623,335.16 VII PEK. PENGECATAN Rp. 49,407,447.46 VIII PEK. INSTALASI LISTRIK Rp. 96,377,000.00 IX PEK. SANITASI DAN INSTALASI Rp. 40,835,020.33 C PEKERJAAN LANTAI II (DUA) I PEK. STRUKTUR BETON Rp. 919,665,118.96 II PEKERJAAN DINDING Rp. 161,045,459.04 III PEKERJAAN PINTU DAN JENDELA Rp. 116,624,110.15 IV PEK. PLAFOND Rp. 90,486,896.59 V PEKERJAAN LANTAI Rp. 137,197,669.98 VI PEK. PENGECATAN Rp. 58,681,588.55 VII PEK. INSTALASI LISTRIK Rp. 48,473,600.00 VIII PEK. SANITASI DAN INSTALASI Rp. 12,775,445.83
D PEKERJAAN LANTAI III (TIGA) I PEK. STRUKTUR BETON Rp. 890,263,135.11 II PEKERJAAN DINDING Rp. 150,686,202.22 III PEKERJAAN PINTU DAN JENDELA Rp. 107,469,297.65 IV PEK. PLAFOND Rp. 90,486,896.59 V PEKERJAAN LANTAI Rp. 137,197,669.98 VI PEK. PENGECATAN Rp. 54,539,051.40 VII PEK. INSTALASI LISTRIK Rp. 46,473,600.00 VIII PEK. SANITASI DAN INSTALASI Rp. 19,861,073.33
E PEKERJAAN LANTAI IV (EMPAT) I PEK. STRUKTUR BETON Rp. 890,263,135.11 II PEKERJAAN DINDING Rp. 150,686,202.22 III PEKERJAAN PINTU DAN JENDELA Rp. 107,469,297.65 IV PEK. PLAFOND Rp. 90,486,896.59 V PEKERJAAN LANTAI Rp. 137,197,669.98 VI PEK. PENGECATAN Rp. 54,539,051.40 VII PEK. INSTALASI LISTRIK Rp. 46,473,600.00 VIII PEK. SANITASI DAN INSTALASI Rp. 19,861,073.33
F PEKERJAAN ATAP (PLAT ATAP) I PEK. STRUKTUR BETON Rp. 766,962,484.65 II PEKERJAAN DINDING Rp. 58,934,324.87 III PEKERJAAN PINTU DAN JENDELA Rp. 4,182,347.95 IV PEKERJAAN LANTAI Rp. 1,433,986.65 V PEK. PENGECATAN Rp. 86,211,322.62 VI PEK. INSTALASI LISTRIK Rp. 873,500.00 VII PEK. SANITASI DAN INSTALASI Rp. 6,372,461.67 G PEKERJAAN LAIN-LAIN DAN PENYELESAIAN AKHIR I PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR Rp. 1,573,072,000.00
REAL COST TOTAL Rp. 8,190,863,193.90
DIBULATKAN Rp. 8,190,863,000.00
TERBILANG : Delapan milyar seratus sembilan puluh juta delapan ratus enam puluh tiga ribu rupiah,-
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN PONDOK PESANTREN TAHFIZHUL QURAN AL - IMAM ASHIM
KOTA MAKASSAR
PEKERJAAN : PEMB. PONDOK PESANTREN TAHFIZHUL QURAN AL-IMAN ASHIM
LOKASI : KEL. BANGKALA, KEC. MANGGALA, KOTA MAKASSAR
ANGGARAN : TAHUN 2014
NO URAIAN PEKERJAAN VOL. SAT HRG. SAT. (Rp.) JML. HARGA
A. PEKERJAAN PERSIAPAN
I PEK. PERSIAPAN
1. Pek. Pengukuran dan Pas. Bowplank 115.00 M' 108,575.00 12,486,125.00
2. Pek. Penyediaan P3K, Listrik Dan Air Kerja 1.00 Ls 5,000,000.00 5,000,000.00
3. Pek. Kantor Sementara Dengan Lantai Plesteran/Direksi Keet 12.00 M2 2,266,375.00 27,196,500.00
4. Pek. Papan Nama Proyek 1.00 Ls 600,000.00 600,000.00
5. Pek. Pembersihan Lahan 1.00 Ls 2,500,000.00 2,500,000.00
Jumlah 47,782,625.00
B. LANTAI I (DASAR)
I PEK. TANAH DAN PONDASI
1. Pek. Galian Tanah Pondasi Poer 76.80 m3 75,375.00 5,788,800.00
2. Pek. Galian Tanah Pondasi Garis 97.06 m3 60,625.00 5,884,020.00
3. Pek. Urugan Tanah Kembali (Pondasi Poer) 25.60 m3 25,125.00 643,200.00
4. Pek. Urugan Tanah Kembali (Pondasi Garis) 32.35 m3 20,208.33 653,780.00
I PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR
1. Pek. Penyelesaian Akhir/Pembersihan 1.00 Ls 1,000,000.00 1,000,000.00
2. Pek. Rangka Baja Berat + Atap Spandek (Atas Plat Atap) 1.00 Ls 1,572,072,000.00 1,572,072,000.00
Jumlah 1,573,072,000.00
Realcost Rp 6,693,886,267.63
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN GEDUNG KANTOR PERKEBUNAN INDUK
DINAS PERKEBUNAN PROVINSI SULAWESI BARAT
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR PERKEBUNANANGGARAN : TAHUN 2011
NO J E N I S P E K E R J A A N TOTAL HARGA (Rp.)
A LANTAI I (DASAR)
I PEK. PERSIAPAN Rp. 52,712,422.50 I PEK. TANAH DAN PONDASI Rp. 234,894,253.73 II PEK. STRUKTUR BETON Rp. 473,282,228.28 IV PEKERJAAN DINDING Rp. - V PEKERJAAN PINTU DAN JENDELA Rp. -
VI PEK. PLAFOND Rp. - VII PEKERJAAN LANTAI Rp. 119,050,287.62 VIII PEK. PENGECATAN Rp. - IX PEK. INSTALASI LISTRIK Rp. 27,216,000.00 X PEK. SANITASI DAN INSTALASI Rp. -
B LANTAI II (DUA) I PEK. STRUKTUR BETON Rp. 1,087,359,528.62 II PEKERJAAN DINDING Rp. - III PEKERJAAN PINTU DAN JENDELA Rp. - IV PEK. PLAFOND Rp. - V PEKERJAAN LANTAI Rp. - VI PEK. PENGECATAN Rp. - VII PEK. KONSTRUKSI ATAP Rp. 523,439,934.21 VIII PEK. INSTALASI LISTRIK Rp. - IX PEK. SANITASI DAN INSTALASI Rp. - X PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR Rp. -
REAL COST TOTAL Rp. 2,517,954,654.97 PPN 10% Rp. 251,795,465.50 TOTAL COST Rp. 2,769,750,120.46 DIBULATKAN Rp. 2,769,750,000.00
Mamuju, 2011
Mengetahui/Menyetujui : Diketahui/Disetujui
KEPALA DINAS PERKEBUNAN PEJABAT PELAKSANA TEKNIS KEGIATAN
Tiga milyar empat ratus tujuh puluh juta delapan ratus enam puluh enam ribu rupiah,-
Mamuju, 2011.
Mengetahui/Menyetujui : Diketahui/DisetujuiKEPALA DINAS PERKEBUNAN PEJABAT PELAKSANA TEKNIS KEGIATANPROVINSI SULAWESI BARAT
Drs. H. MUHTAR BELO, MM KIMOTO BADO Nip. 19551012 198203 1 006 Nip. 19641231 199402 1 026
Mengetahui/Menyetujui :KEPALA DINAS PU PROVINSI SULAWESI BARAT
Ir. H. IDHAM HASIB, M.SiNip. 19570116 198503 1 001
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN GEDUNG KANTOR DINAS KESEHATAN
KABUPATEN ENREKANG
PEKERJAAN : PEMBANGUNAN GUESS HOUSE DINAS KESEHATAN ENREKANGANGGARAN : TAHUN 2010
NO J E N I S P E K E R J A A N TOTAL HARGA (Rp.)
I PEK. PERSIAPAN Rp. 59,398,950.00 II PEK. TANAH DAN PONDASI Rp. 78,838,598.78 III PEK. STRUKTUR BETON Rp. 187,292,499.26 IV PEKERJAAN DINDING Rp. 212,434,061.14 V PEKERJAAN PINTU DAN JENDELA Rp. 64,220,080.56
VI PEK. PLAFOND Rp. 52,569,463.03 VII PEKERJAAN LANTAI Rp. 141,185,209.89 VIII PEK. PENGECATAN Rp. 59,456,600.15 IX PEK. KONSTRUKSI ATAP Rp. 164,536,675.45 X PEK. INSTALASI LISTRIK Rp. 83,384,000.00 XI PEK. SANITASI DAN INSTALASI Rp. 61,554,741.67 XII PEK. SARANA INFRASTRUKTUR DAN PENYELESAIAN AKHIR Rp. 500,000.00
REAL COST TOTAL Rp. 1,165,370,879.92 PPN 10% Rp. 116,537,087.99 TOTAL COST Rp. 1,281,907,967.91 DIBULATKAN Rp. 1,281,907,000.00
Enrekang, 2010
Mengetahui : Konsultan Perencana, KEPALA DINAS KESEHATAN CV. BAJIRUPA CONSULTANT
KAB. ENREKANG
Dr. H. MUHAMMAD YAMIN BADARUDDIN, ST Nip. 196206021990011002 Direktur
Mengetahui/Menyetujui :BUPATI ENREKANG
H. LA TINRO LA TUNRUNG
TERBILANG : Satu milyar empat puluh empat juta lima ratus ribu rupiah,-
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG KANTOR DINAS KESEHATAN
KABUPATEN ENREKANG
PEKERJAAN : PEMBANGUNAN GUESS HOUSE DINAS KESEHATAN ENREKANG
ANGGARAN : TAHUN 2010
NO URAIAN PEKERJAAN VOL. SAT HRG. SAT. (Rp.) JML. HARGA
I PEK. PERSIAPAN
1. Pek. Pengukuran dan Pas. Bowplank 86.00 M' 108,575.00 9,337,450.00
2. Pek. Penyediaan P3K, Listrik Dan Air Kerja 1.00 Ls 1,000,000.00 1,000,000.00
3. Pek. Kantor Sementara Dengan Lantai Plesteran/Direksi Keet 12.00 M2 2,266,375.00 27,196,500.00
4. Pek. Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
5. Pek. Pembongkaran Gedung Existing = 3 Unit Gedung 1.00 Ls 5,000,000.00 5,000,000.00
6. Izin Mendirikan Bangunan (IMB) 1.00 Ls 4,455,000.00 4,455,000.00
7. Pek. Anti Rayap (Sistem Semprot) 297.00 M2 30,000.00 8,910,000.00
8. Administrasi, Dokumentasi Dan Quality Control 1.00 Ls 3,000,000.00 3,000,000.00
Jumlah 59,398,950.00
II PEK. TANAH DAN PONDASI
1. Pek. Galian Tanah Pondasi 110.40 m3 60,625.00 6,693,000.00
2. Pek. Urugan Kembali 36.80 m3 20,208.33 743,666.67
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB) PEMBANGUNAN GEDUNG KANTOR BARU DAN PERKEBUNAN INDUK
PROVINSI SULAWESI BARAT TAHUN ANGGARAN 2011
NO. JENIS PEKERJAAN TOTAL HARGA (Rp.)
I PEK. PEMBANGUNAN PERKEBUNAN BARU Rp. 6,022,644,000.00
II PEK. PEMBANGUNAN GEDUNG KANTOR BARU Rp. 3,303,842,100.00
III PEK. PERENCANAAN Rp. 312,800,000.00
IV PEK. PENGAWASAN Rp. 216,839,000.00
V PENGELOLA PROYEK Rp. 100,000,000.00
Total Cost + PPN 10% Rp. 9,956,125,100.00 Dibulatkan Rp. 9,956,125,000.00
Mamuju, 2011
Mengetahui/Menyetujui : Diketahui/DisetujuiKEPALA DINAS PERKEBUNAN PEJABAT PELAKSANA TEKNIS KEGIATANPROVINSI SULAWESI BARAT
Drs. H. MUHTAR BELO, MM KIMOTO BADO Nip. 19551012 198203 1 006 Nip. 19641231 199402 1 026
Mengetahui/Menyetujui :
KEPALA DINAS PU PROVINSI SULAWESI BARAT
Ir. H. IDHAM HASIB, M.SiNip. 19570116 198503 1 010
Terbilang : Sepuluh milyar rupiah,-
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
A.6 PEKERJAAN PERSIAPAN
A.6.2 Memasang 1 M' pagar sementara dari seng gelombang tinggi 2 meter 1.250 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 37,500.00 2.500 Kg Semen Portland @ Rp 1,150.00 Rp 2,875.00 0.005 M3 Pasir beton @ Rp 148,000.00 Rp 740.00 0.009 M3 split/chipping 2-3 cm @ Rp 267,000.00 Rp 2,403.00 0.072 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 327,600.00 0.060 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 1,050.00 0.400 Ltr Residu @ Rp 6,400.00 Rp 2,560.00 0.200 Oh Tukang kayu @ Rp 100,000.00 Rp 20,000.00 0.400 Oh Pekerja @ Rp 75,000.00 Rp 30,000.00 0.020 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 2,600.00 0.020 Oh Mandor @ Rp 175,000.00 Rp 3,500.00
Rp 430,828.00
A.6.4 Mengukur dan memasang 1 M' bouwplank 0.012 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 54,600.00 0.020 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 350.00 0.007 M3 Kayu klas II (papan) @ Rp 4,850,000.00 Rp 33,950.00 0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00 0.100 Oh Pekerja @ Rp 75,000.00 Rp 7,500.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 108,575.00
A.6.5 Membuat1 M2 kantor sementara, dengan lantai plesteran 1.250 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 37,500.00 0.180 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 819,000.00 0.850 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 14,875.00 1.100 Kg Besi strip @ Rp 12,500.00 Rp 13,750.00 35.000 Kg Semen Portland @ Rp 1,150.00 Rp 40,250.00 0.150 M3 Pasir pasang @ Rp 134,000.00 Rp 20,100.00 0.100 M3 Pasir beton @ Rp 148,000.00 Rp 14,800.00 0.150 M3 split/chipping 2-3 cm @ Rp 267,000.00 Rp 40,050.00 30.000 Bh Batu merah @ Rp 550.00 Rp 16,500.00 0.250 Lbr Seng plat BJLS 0.30 @ Rp 50,000.00 Rp 12,500.00 2.000 set Kaca nako lengkap teralis @ Rp 350,000.00 Rp 700,000.00 0.080 M2 Kaca bening 5 mm @ Rp 105,000.00 Rp 8,400.00 0.150 Bh Kunci tanam biasa @ Rp 173,000.00 Rp 25,950.00 0.060 Lbr Multipleks 1.22 x 2.44 x 6 mm @ Rp 82,500.00 Rp 4,950.00 2.000 Oh Tukang kayu @ Rp 100,000.00 Rp 200,000.00 1.000 Oh Tukang batu @ Rp 100,000.00 Rp 100,000.00 2.000 Oh Pekerja @ Rp 75,000.00 Rp 150,000.00 0.300 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 39,000.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00
Rp 2,266,375.00
B.6 PEKERJAAN TANAH
B.6.1 Menggali 1 M3 tanah biasa sedalam 1 m 0.750 Oh Pekerja @ Rp 75,000.00 Rp 56,250.00 0.025 Oh Mandor @ Rp 175,000.00 Rp 4,375.00
Rp 60,625.00
B.6.2 Menggali 1 M3 tanah biasa sedalam 2 m 0.900 Oh Pekerja @ Rp 75,000.00 Rp 67,500.00 0.045 Oh Mandor @ Rp 175,000.00 Rp 7,875.00
Rp 75,375.00
B.6.9a. Untuk Galian Tanah Biasa Sedalam 1 m
0.250 Oh Pekerja @ Rp 75,000.00 Rp 18,750.00 0.008 Oh Mandor @ Rp 175,000.00 Rp 1,458.33
Rp 20,208.33
Mengurug kembali 1 M3 galian (Dihitung 1/3 Kali Indeks Pekerjaan Galian)
b. Untuk Galian Tanah Biasa Sedalam 2 m 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.015 Oh Mandor @ Rp 175,000.00 Rp 2,625.00
Rp 25,125.00
B.6.10 Memadatkan 1 M3 tanah (per 20 cm) 0.500 Oh Pekerja @ Rp 75,000.00 Rp 37,500.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00
Rp 46,250.00
B.6.11 Mengurug 1 M3 pasir urug 1.200 M3 Pasir urug @ Rp 128,000.00 Rp 153,600.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.010 Oh Mandor @ Rp 175,000.00 Rp 1,750.00
Rp 177,850.00
Mengurug 1 M3 Tanah Timbunan 1.200 M3 Tanah timbunan @ Rp 152,000.00 Rp 182,400.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.010 Oh Mandor @ Rp 175,000.00 Rp 1,750.00
Rp 206,650.00
B.6.15 Mengurug 1 M3 sirtu padat untuk peninggian lantai bangunan 1.200 M3 Sirtu @ Rp 177,000.00 Rp 212,400.00 0.250 Oh Pekerja @ Rp 75,000.00 Rp 18,750.00 0.025 Oh Mandor @ Rp 175,000.00 Rp 4,375.00
Rp 235,525.00
An. K 158 M3 GALIAN TANAH BIASA (PAKAI ALAT/PEMBUANGAN SETEMPAT)(Asumsi : Menggunakan Alat, 80% Galian Dibuang Dilokasi, 20% Galian Dibuang Dan Diangkut Keluar Dengan DumpTruck)(Asumsi : Jarak 1 Tripp PP < 2 Km, 2.5 rit PP/Jam/Truck) 1.000 Oh Mandor @ Rp 175,000.00 Rp 175,000.00 1.000 Oh Operator terampil @ Rp 107,250.00 Rp 107,250.00 1.000 Oh Pembantu operator @ Rp 60,500.00 Rp 60,500.00 1.000 Oh Sopir Terampil @ Rp 71,500.00 Rp 71,500.00 1.000 Oh Pembantu Sopir @ Rp 50,000.00 Rp 50,000.00 2.000 Oh Pekerja @ Rp 75,000.00 Rp 150,000.00 5.000 Jam Excavator @ Rp 639,036.99 Rp 3,195,184.97 5.000 Jam Dump Truck, Kap. 5 Ton @ Rp 414,820.16 Rp 2,074,100.80 0.240 Set Alat -alat bantu 1 set (3 alat) @ Rp 100,000.00 Rp 24,000.00
Rp 5,907,535.77 Untuk 1 M3 Rp 37,389.47
An. K 12 Are PENGUPASAN TANAH DAN PEMBERSIHAN SEMAK PADA DAMIJA (MENGGUNAKAN BURUH)(Asumsi : Menggunakan Tenaga Manusia, Tak ada pohon besar, Pembersihan 100 m/hari, Hasil kerja 25 m2/orang - hari)(Uraian : Mengupas dan membuang semak - semak dengan tenaga manusia pada Damija) 1.000 Oh Mandor @ Rp 175,000.00 Rp 175,000.00 48.000 Oh Pekerja @ Rp 75,000.00 Rp 3,600,000.00 1.920 Set Alat -alat bantu 1 set (3 alat) @ Rp 100,000.00 Rp 192,000.00
Rp 3,967,000.00 Untuk 1 Are Rp 330,583.33 Untuk 1 M2 Rp 3,305.83
An. K 2400 M2 PENGUPASAN TANAH DAN PEMBERSIHAN SEMAK PADA DAMIJA (MENGGUNAKAN ALAT)(Asumsi : Menggunakan Alat Berat, Tak ada pohon besar, Pembersihan 200 m/hari)(Uraian : Alat Berat Mengupas dan membuang semak - semak dari daerah milik jalan) 1.000 Oh Mandor @ Rp 175,000.00 Rp 175,000.00 1.000 Oh Operator terampil @ Rp 107,250.00 Rp 107,250.00 1.000 Oh Pembantu operator @ Rp 60,500.00 Rp 60,500.00 2.000 Oh Pekerja @ Rp 75,000.00 Rp 150,000.00 5.000 Jam Buldozer 110 HP @ Rp 706,966.29 Rp 3,534,831.45 1.000 Set Alat -alat bantu 1 set (3 alat) @ Rp 100,000.00 Rp 100,000.00
Rp 4,127,581.45 Untuk 1 M2 Rp 1,719.83
An. El 1 M3 GALIAN UNTUK DRAINASE, SALURAN DAN SALURAN AIR (MENGGUNAKAN ALAT)(Asumsi : Menggunakan Alat Berat, Pada Daerah Sepanjang Jalan, Jam kerja Efektif per hari = 7 Jam)(Uraian : Penggalian Oleh Excavator, Hasil Galian Dibuang Menggunakan Dump truck Sejauh 2 KM) 0.0075 Jam Mandor @ Rp 25,000.00 Rp 187.50
(Asumsi : Harga Satuan upah perhari dibagi 7 jam) 0.030 Jam Pekerja @ Rp 10,714.29 Rp 319.29
(Asumsi : Harga Satuan upah perhari dibagi 7 jam) 0.0075 Jam Excavator @ Rp 639,036.99 Rp 4,792.78 0.1302 Jam Dump Truck, Kap. 5 Ton @ Rp 414,820.16 Rp 54,009.58 - Set Alat -alat bantu 1 set (3 alat) @ Rp 100,000.00 Rp -
Rp 59,309.15
C.6 PEKERJAAN PONDASI
C.6.2 Memasang 1 M3 pondasi batu belah, campuran 1PC : 4PP 1.200 M3 Batu gunung @ Rp 167,000.00 Rp 200,400.00 163.000 Kg Semen Portland @ Rp 1,150.00 Rp 187,450.00 0.520 M3 Pasir pasang @ Rp 134,000.00 Rp 69,680.00 1.500 Oh Tukang batu @ Rp 100,000.00 Rp 150,000.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 0.060 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 7,800.00 0.075 Oh Mandor @ Rp 175,000.00 Rp 13,125.00
Rp 673,455.00
C.6.9 Memasang 1 M3 batu kosong (aanstamping) 1.200 M3 Batu gunung @ Rp 167,000.00 Rp 200,400.00 0.432 M3 Pasir urug @ Rp 128,000.00 Rp 55,296.00 0.780 Oh Pekerja @ Rp 75,000.00 Rp 58,500.00 0.390 Oh Tukang batu @ Rp 100,000.00 Rp 39,000.00 0.039 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 5,070.00 0.039 Oh Mandor @ Rp 175,000.00 Rp 6,825.00
Rp 365,091.00
D.6 PEKERJAAN DINDING
D.6.3 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 4PP 140.000 Bh Batu merah @ Rp 550.00 Rp 77,000.00 26.550 Kg Semen Portland @ Rp 1,150.00 Rp 30,532.50 0.093 M3 Pasir pasang @ Rp 134,000.00 Rp 12,462.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 0.200 Oh Tukang batu @ Rp 100,000.00 Rp 20,000.00 0.020 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 2,600.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 192,844.50
D.6.4 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 5PP 140.000 Bh Batu merah @ Rp 550.00 Rp 77,000.00 22.200 Kg Semen Portland @ Rp 1,150.00 Rp 25,530.00 0.102 M3 Pasir pasang @ Rp 134,000.00 Rp 13,668.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 0.200 Oh Tukang batu @ Rp 100,000.00 Rp 20,000.00 0.020 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 2,600.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 189,048.00
D.6.8 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 3PP 70.000 Bh Batu merah @ Rp 550.00 Rp 38,500.00 14.370 Kg Semen Portland @ Rp 1,150.00 Rp 16,525.50 0.040 M3 Pasir pasang @ Rp 134,000.00 Rp 5,360.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,300.00 0.015 Oh Mandor @ Rp 175,000.00 Rp 2,625.00
Rp 96,810.50
D.6.9 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 4PP 70.000 Bh Batu merah @ Rp 550.00 Rp 38,500.00
11.500 Kg Semen Portland @ Rp 1,150.00 Rp 13,225.00 0.043 M3 Pasir pasang @ Rp 134,000.00 Rp 5,762.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,300.00 0.015 Oh Mandor @ Rp 175,000.00 Rp 2,625.00
Rp 93,912.00
D.6.10 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 5PP 70.000 Bh Batu merah @ Rp 550.00 Rp 38,500.00 9.680 Kg Semen Portland @ Rp 1,150.00 Rp 11,132.00 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,300.00 0.015 Oh Mandor @ Rp 175,000.00 Rp 2,625.00
Rp 92,087.00 E.6 PEKERJAAN PLESTERAN
E.6.3 Memasang 1 M2 plesteran 1PC : 3PP, tebal 15 mm 7.776 Kg Semen Portland @ Rp 1,150.00 Rp 8,942.40 0.023 M3 Pasir pasang @ Rp 134,000.00 Rp 3,082.00 0.200 Oh Pekerja @ Rp 75,000.00 Rp 15,000.00 0.150 Oh Tukang batu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,950.00 0.010 Oh Mandor @ Rp 175,000.00 Rp 1,750.00
Rp 45,724.40
E.6.5 Memasang 1 M2 plesteran 1PC : 5PP, tebal 15 mm 5.184 Kg Semen Portland @ Rp 1,150.00 Rp 5,961.60 0.026 M3 Pasir pasang @ Rp 134,000.00 Rp 3,484.00 0.200 Oh Pekerja @ Rp 75,000.00 Rp 15,000.00 0.150 Oh Tukang batu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,950.00 0.010 Oh Mandor @ Rp 175,000.00 Rp 1,750.00
Rp 43,145.60
E.6.20 Memasang 1 M2 plesteran skoning 1PC : 2PP, tebal 10 mm 0.500 Kg Semen Portland @ Rp 1,150.00 Rp 575.00 0.013 M3 Pasir pasang @ Rp 134,000.00 Rp 1,742.00 0.057 Oh Pekerja @ Rp 75,000.00 Rp 4,275.00 0.380 Oh Tukang batu @ Rp 100,000.00 Rp 38,000.00 0.038 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 4,940.00 0.003 Oh Mandor @ Rp 175,000.00 Rp 525.00
Rp 50,057.00
E.6.27 Memasang 1 M2 acian 3.250 Kg Semen Portland @ Rp 1,150.00 Rp 3,737.50 0.150 Oh Pekerja @ Rp 75,000.00 Rp 11,250.00 0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,300.00 0.008 Oh Mandor @ Rp 175,000.00 Rp 1,400.00
Rp 27,687.50 F.6 PEKERJAAN KAYU
F.6.1 1 M3 Membuat dan memasang kusen pintu dan jendela, kayu kls. I 1.100 M3 Kayu klas I (balok) untuk kosen pintu/jen @ Rp 9,550,000.00 Rp 10,505,000.00 1.250 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 21,875.00 1.000 Kg Lem kayu @ Rp 12,500.00 Rp 12,500.00 6.000 Oh Pekerja @ Rp 75,000.00 Rp 450,000.00 20.000 Oh Tukang kayu @ Rp 100,000.00 Rp 2,000,000.00 2.000 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 260,000.00 0.300 Oh Mandor @ Rp 175,000.00 Rp 52,500.00
Rp 13,301,875.00
F.6.5 1 M2 Membuat dan memasang daun pintu panel, kayu kls. I atau II 0.040 M3 Kayu klas I (papan) listplank dan pintu/je @ Rp 10,050,000.00 Rp 402,000.00 0.500 Kg Lem kayu @ Rp 12,500.00 Rp 6,250.00
1.000 Oh Pekerja @ Rp 75,000.00 Rp 75,000.00 2.500 Oh Tukang kayu @ Rp 100,000.00 Rp 250,000.00 0.250 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 32,500.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00
Rp 774,500.00
F.6.6 1 M2 Membuat dan memasang pintu dan jendela kaca, kayu kls. I atau II 0.024 M3 Kayu klas I (papan) listplank dan pintu/je @ Rp 10,050,000.00 Rp 241,200.00 0.300 Kg Lem kayu @ Rp 12,500.00 Rp 3,750.00 0.800 Oh Pekerja @ Rp 75,000.00 Rp 60,000.00 2.000 Oh Tukang kayu @ Rp 100,000.00 Rp 200,000.00 0.200 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 26,000.00 0.040 Oh Mandor @ Rp 175,000.00 Rp 7,000.00
Rp 537,950.00
F.6.8 1 M2 Membuat daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kls. II 0.025 M3 Kayu klas II (papan) @ Rp 4,850,000.00 Rp 121,250.00 0.030 Kg Paku Biasa 1/2" - 1" @ Rp 17,500.00 Rp 525.00 0.500 Kg Lem kayu @ Rp 12,500.00 Rp 6,250.00 1.000 Lbr Plywood Uk.90x220 cm Tebal 4 mm @ Rp 92,000.00 Rp 92,000.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 2.000 Oh Tukang kayu @ Rp 100,000.00 Rp 200,000.00 0.200 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 26,000.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 496,275.00
F.6.8 - SPL 1 M2 Membuat daun pintu Teakwood rangkap Lapis HPL, rangka tertutup kayu kls. II 0.025 M3 Kayu klas II (papan) @ Rp 4,850,000.00 Rp 121,250.00 0.030 Kg Paku Biasa 1/2" - 1" @ Rp 17,500.00 Rp 525.00 0.500 Kg Lem kayu @ Rp 12,500.00 Rp 6,250.00 1.000 Lbr Teakwood Uk. 90 x 220 x 4 mm @ Rp 92,000.00 Rp 92,000.00 0.700 Lbr HPL Uk. 120 x 240 @ Rp 176,000.00 Rp 123,200.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 2.500 Oh Tukang kayu @ Rp 100,000.00 Rp 250,000.00 0.250 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 32,500.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 675,975.00
G.6 PEKERJAAN BETON
G.6.1 247.000 Kg Semen Portland @ Rp 1,150.00 Rp 284,050.00 869.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 91,865.71 999.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 197,580.00 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 796,660.71
G.6.4 Membuat 1 M3 lantai kerja beton mutu f'c=7,4 Mpa (K 100), slump (3-6) cm, w/c=0,87 230.000 Kg Semen Portland @ Rp 1,150.00 Rp 264,500.00 893.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 94,402.86 1,027.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 203,117.78 200.000 Ltr Air @ Rp 250.00 Rp 50,000.00 1.200 Oh Pekerja @ Rp 75,000.00 Rp 90,000.00 0.200 Oh Tukang batu @ Rp 100,000.00 Rp 20,000.00 0.020 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 2,600.00 0.060 Oh Mandor @ Rp 175,000.00 Rp 10,500.00
Rp 735,120.63
G.6.5 326.000 Kg Semen Portland @ Rp 1,150.00 Rp 374,900.00
Membuat 1 M3 beton mutu f'c=7,4 Mpa (K100), slump (12 ± 2) cm, w/c=0,87
Membuat 1 M3 beton mutu f'c=14,5 Mpa (K 175), slump (12 ± 2) cm, w/c=0,66
760.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 80,342.86 1,029.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 203,513.33 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 881,921.19
G.6.7 371.000 Kg Semen Portland @ Rp 1,150.00 Rp 426,650.00 698.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 73,788.57 1,047.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 207,073.33 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 930,676.90
G.6.8 384.000 Kg Semen Portland @ Rp 1,150.00 Rp 441,600.00 692.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 73,154.29 1,039.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 205,491.11 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 943,410.40
G.6.9 406.000 Kg Semen Portland @ Rp 1,150.00 Rp 466,900.00 684.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 72,308.57 1,026.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 202,920.00 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 965,293.57
G.6.10 413.000 Kg Semen Portland @ Rp 1,150.00 Rp 474,950.00 681.000 Kg Pasir beton (Kg) @ Rp 105.71 Rp 71,991.43 1,021.000 Kg split/chipping 2-3 cm(Kg) @ Rp 197.78 Rp 201,931.11 215.000 Ltr Air @ Rp 250.00 Rp 53,750.00 1.650 Oh Pekerja @ Rp 75,000.00 Rp 123,750.00 0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00 0.028 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,640.00 0.083 Oh Mandor @ Rp 175,000.00 Rp 14,525.00
Rp 972,037.54
G.6.17 Pembesian 1 Kg dengan besi polos atau besi ulir 10.500 Kg Besi beton polos @ Rp 11,000.00 Rp 115,500.00 0.150 Kg Kawat beton @ Rp 21,000.00 Rp 3,150.00 0.070 Oh Pekerja @ Rp 75,000.00 Rp 5,250.00 0.070 Oh Tukang besi @ Rp 100,000.00 Rp 7,000.00 0.007 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 910.00 0.004 Oh Mandor @ Rp 175,000.00 Rp 700.00
Untuk Pembesian 10 Kg Rp 132,510.00 Untuk Pembesian 1 Kg Rp 13,251.00
G.6.20 Memasang 1 M2 bekisting untuk pondasi 0.040 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 131,000.00 0.300 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 5,250.00
Membuat 1 M3 beton mutu f'c=19,3 Mpa (K 225), slump (12 ± 2) cm, w/c=0,58
Membuat 1 M3 beton mutu f'c=21,7 Mpa (K 250), slump (12 ± 2) cm, w/c=0,56
Membuat 1 M3 beton mutu f'c=24,0 Mpa (K 275), slump (12 ± 2) cm, w/c=0,53
Membuat 1 M3 beton mutu f'c=26,4 Mpa (K 300), slump (12 ± 2) cm, w/c=0,52
0.100 Ltr Minyak bekisting @ Rp 3,500.00 Rp 350.00 0.520 Oh Pekerja @ Rp 75,000.00 Rp 39,000.00 0.260 Oh Tukang kayu @ Rp 100,000.00 Rp 26,000.00 0.026 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 3,380.00 0.026 Oh Mandor @ Rp 175,000.00 Rp 4,550.00
Rp 209,530.00
Memasang 1 M2 bekisting untuk pondasi 2 x Pemakaian 0.020 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 65,500.00
(Papan 2 kali Pakai) 0.300 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 5,250.00 0.100 Ltr Minyak bekisting @ Rp 3,500.00 Rp 350.00 0.520 Oh Pekerja @ Rp 75,000.00 Rp 39,000.00 0.260 Oh Tukang kayu @ Rp 100,000.00 Rp 26,000.00 0.026 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 3,380.00 0.026 Oh Mandor @ Rp 175,000.00 Rp 4,550.00
Rp 144,030.00
G.6.21 Memasang 1 M2 bekisting untuk sloof 0.045 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 147,375.00 0.300 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 5,250.00 0.100 Ltr Minyak bekisting @ Rp 3,500.00 Rp 350.00 0.520 Oh Pekerja @ Rp 75,000.00 Rp 39,000.00 0.260 Oh Tukang batu @ Rp 100,000.00 Rp 26,000.00 0.026 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,380.00 0.026 Oh Mandor @ Rp 175,000.00 Rp 4,550.00
Rp 225,905.00
Memasang 1 M2 bekisting untuk sloof 2 Kali Pemakaian 0.023 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 73,687.50
(Papan 2 kali Pakai) 0.300 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 5,250.00 0.100 Ltr Minyak bekisting @ Rp 3,500.00 Rp 350.00 0.520 Oh Pekerja @ Rp 75,000.00 Rp 39,000.00 0.260 Oh Tukang batu @ Rp 100,000.00 Rp 26,000.00 0.026 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,380.00 0.026 Oh Mandor @ Rp 175,000.00 Rp 4,550.00
Rp 152,217.50
G.6.22 Memasang 1 M2 bekisting untuk kolom 0.040 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 131,000.00 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.015 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 68,250.00 0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 45,500.00 2.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 60,000.00 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 405,015.00 Memasang 1 M2 bekisting untuk kolom Untuk 2x Pemakaian 0.020 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 65,500.00
(papan 2 x pakai) 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.008 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 34,125.00
(Balok 2x pakai) 0.175 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 22,750.00
(Multipleks 2x pakai) 1.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 30,000.00
(dolken 2x pakai) 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 252,640.00
G.6.23 Memasang 1 M2 bekisting untuk balok 0.040 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 131,000.00 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.018 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 81,900.00 0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 45,500.00 2.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 60,000.00 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 418,665.00 Memasang 1 M2 bekisting untuk balok Untuk 2x pemakaian 0.020 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 65,500.00
(papan 2 x pakai) 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.009 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 40,950.00
(Balok 2x pakai) 0.175 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 22,750.00
(Multipleks 2x pakai) 1.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 30,000.00
(dolken 2x pakai) 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 259,465.00
G.6.24 Memasang 1 M2 bekisting untuk lantai 0.040 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 131,000.00 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.015 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 68,250.00 0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 45,500.00 6.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 180,000.00 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 525,015.00
Memasang 1 M2 bekisting untuk lantai Untuk 2x Pemakaian 0.020 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 65,500.00
(papan 2 x pakai) 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.008 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 34,125.00
(Balok 2x pakai) 0.175 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 22,750.00
(Multipleks 2x pakai) 3.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 90,000.00
(dolken 2x pakai) 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 312,640.00
G.6.25 Memasang 1 M2 bekisting untuk dinding 0.030 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 98,250.00
0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.020 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 91,000.00 0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 45,500.00 3.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 90,000.00 4.000 Bh Spacer/formite/penjaga jarak bekisting @ Rp 17,500.00 Rp 70,000.00 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 495,015.00
Memasang 1 M2 bekisting untuk dinding Untuk 2x Pemakaian 0.015 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 49,125.00
(papan 2 x pakai) 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.200 Ltr Minyak bekisting @ Rp 3,500.00 Rp 700.00 0.010 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 45,500.00
(Balok 2x pakai) 0.175 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 22,750.00
(Multipleks 2x pakai) 1.500 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 45,000.00
(dolken 2x pakai) 2.000 Bh Spacer/formite/penjaga jarak bekisting @ Rp 17,500.00 Rp 35,000.00
(spacer 2x pemakaian) 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 297,640.00
G.6.26 Memasang 1 M2 bekisting untuk tangga 0.030 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 98,250.00 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.150 Ltr Minyak bekisting @ Rp 3,500.00 Rp 525.00 0.015 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 68,250.00 0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 45,500.00 2.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 60,000.00 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 372,090.00
Memasang 1 M2 bekisting untuk tangga Untuk 2x Pemakaian 0.015 M3 Kayu klas III (papan) @ Rp 3,275,000.00 Rp 49,125.00
(papan 2 x pakai) 0.400 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 7,000.00 0.150 Ltr Minyak bekisting @ Rp 3,500.00 Rp 525.00 0.008 M3 Kayu klas II (balok) @ Rp 4,550,000.00 Rp 34,125.00
(Balok 2x pakai) 0.175 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 130,000.00 Rp 22,750.00
(Multipleks 2x pakai) 1.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 30,000.00
(dolken 2x pakai) 0.660 Oh Pekerja @ Rp 75,000.00 Rp 49,500.00 0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00 0.033 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 4,290.00 0.033 Oh Mandor @ Rp 175,000.00 Rp 5,775.00
Rp 236,090.00
H.6 PEKERJAAN PENUTUP ATAP
H.6.2 - SPL Memasang 1 M2 Atap Genteng Keramik 16.000 Bh Genteng keramik Natural @ Rp 16,000.00 Rp 256,000.00 0.150 Oh Pekerja @ Rp 75,000.00 Rp 11,250.00 0.075 Oh Tukang kayu @ Rp 100,000.00 Rp 7,500.00 0.008 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,040.00 0.008 Oh Mandor @ Rp 175,000.00 Rp 1,400.00
Rp 277,190.00
H.6.5 - SPL Memasang 1 M' Bubung Genteng Keramik 5.000 Bh Nok genteng keramik Natural @ Rp 20,500.00 Rp 102,500.00 8.000 Kg Semen Portland @ Rp 1,150.00 Rp 9,200.00 0.032 M3 Pasir pasang @ Rp 134,000.00 Rp 4,288.00 0.400 Oh Pekerja @ Rp 75,000.00 Rp 30,000.00 0.200 Oh Tukang kayu @ Rp 100,000.00 Rp 20,000.00 0.020 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 2,600.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 350.00
Rp 168,938.00
H.6.32 Memasang 1 M2 Atap Genteng Metal 1.020 Lbr Genteng metal @ Rp 87,000.00 Rp 88,740.00 0.200 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 3,500.00 0.200 Oh Pekerja @ Rp 75,000.00 Rp 15,000.00 0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.001 Oh Mandor @ Rp 175,000.00 Rp 175.00
Rp 118,715.00
H.6.36 Memasang 1 M' Nok Genteng Metal 1.100 Lbr Nok genteng Metal @ Rp 40,500.00 Rp 44,550.00 0.050 Kg Paku Biasa 1/2" - 1" @ Rp 17,500.00 Rp 875.00 0.250 Oh Pekerja @ Rp 75,000.00 Rp 18,750.00 0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,950.00 0.013 Oh Mandor @ Rp 175,000.00 Rp 2,275.00
Rp 83,400.00
H.6.38 - SPL Memasang 1 M2 Atap Seng Spandek 1.000 M2 Long Spandek Type G550 AZ-100 T=0,4 @ Rp 68,000.00 Rp 68,000.00 8.000 Bh Paku Sekrup + Mor + Pelapis @ Rp 2,500.00 Rp 20,000.00 0.120 Oh Pekerja @ Rp 75,000.00 Rp 9,000.00 0.060 Oh Tukang kayu @ Rp 100,000.00 Rp 6,000.00 0.006 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 780.00 0.006 Oh Mandor @ Rp 175,000.00 Rp 1,050.00
Rp 104,830.00
H.6.39 - SPL Memasang 1 M' Atap Nok Seng Spandek 0.900 M Nok Long Spandek Type G550 AZ-100 T @ Rp 41,500.00 Rp 37,350.00 10.000 Bh Paku Sekrup + Mor + Pelapis @ Rp 2,500.00 Rp 25,000.00 0.150 Oh Pekerja @ Rp 75,000.00 Rp 11,250.00 0.070 Oh Tukang kayu @ Rp 100,000.00 Rp 7,000.00 0.008 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,040.00 0.006 Oh Mandor @ Rp 175,000.00 Rp 1,050.00
Rp 82,690.00
SPL Memasang Lisplank Ukuran 2x (2x20) cm, woodplank 1.050 Lbr Woodplank 2/20 x 4 M @ Rp 60,000.00 Rp 63,000.00 0.060 Kg Paku Biasa 1/2" - 1" @ Rp 17,500.00 Rp 1,050.00 7.000 M Besi Hollow 4 x 4 @ Rp 22,500.00 Rp 157,500.00 0.100 Oh Pekerja @ Rp 75,000.00 Rp 7,500.00 0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00 1.000 Ls Alat Bantu @ Rp 5,000.00 Rp 5,000.00
Rp 254,100.00
H.6.42 Memasang 1 M2 Alluminium Foil/sisalation 1.050 M2 Aluminium foil/sisalation single type @ Rp 12,500.00 Rp 13,125.00 0.150 Oh Pekerja @ Rp 75,000.00 Rp 11,250.00 0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00 0.005 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 650.00 0.008 Oh Mandor @ Rp 175,000.00 Rp 1,400.00
Rp 31,425.00
I.6 PEKERJAAN LANGIT - LANGIT/PLAFOND
I.6.6 Memasang 1 M2 langit-langit lambriziring kayu, tebal 9 mm 0.015 M3 Kayu klas II (papan) @ Rp 4,850,000.00 Rp 72,750.00 0.010 Kg Paku biasa 1/2" - 1" @ Rp 17,500.00 Rp 175.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 0.800 Oh Tukang kayu @ Rp 100,000.00 Rp 80,000.00 0.080 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 10,400.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 213,575.00
I.6.7 Memasang 1 M2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 0.364 Lbr Gypsumboard 9 mm @ Rp 55,000.00 Rp 20,020.00 0.110 Kg Paku sekrup 3,5" @ Rp 21,500.00 Rp 2,365.00 0.100 Oh Pekerja @ Rp 75,000.00 Rp 7,500.00 0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00 0.005 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 650.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 36,410.00
SPL Memasang 1 M2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm + rangka Hollow 4.000 M Besi Hollow Galvanis 2/4 @ Rp 7,000.00 Rp 28,000.00 1.500 Bh Ramsel nails @ Rp 2,500.00 Rp 3,750.00 0.365 M2 Gypsumboard 9 mm @ Rp 55,000.00 Rp 20,052.08 0.030 Kg UB 888/400 Compoud @ Rp 4,500.00 Rp 135.00 0.016 Roll Isolasi Gypsun @ Rp 25,000.00 Rp 400.00 11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp 11,500.00 0.010 Lbr Kertas Amplas @ Rp 5,000.00 Rp 50.00 0.070 Oh Pekerja @ Rp 75,000.00 Rp 5,250.00 0.700 Oh Tukang besi @ Rp 100,000.00 Rp 70,000.00 0.007 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 910.00 0.012 Oh Mandor @ Rp 175,000.00 Rp 2,100.00
Rp 142,147.08
SPL Memasang 1 M2 langit-langit Calsyboard board ukuran (120x240) mm, tebal 6 mm + rangka Hollow 4.000 M Besi Hollow Galvanis 2/4 @ Rp 7,000.00 Rp 28,000.00 1.500 Bh Ramsel nails @ Rp 2,500.00 Rp 3,750.00 0.365 M2 Calsyboard 6 mm @ Rp 70,000.00 Rp 25,520.83 0.030 Kg UB 888/400 Compoud @ Rp 4,500.00 Rp 135.00 0.016 Roll Isolasi Gypsun @ Rp 25,000.00 Rp 400.00 11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp 11,500.00 0.010 Lbr Kertas Amplas @ Rp 5,000.00 Rp 50.00 0.070 Oh Pekerja @ Rp 75,000.00 Rp 5,250.00 0.700 Oh Tukang besi @ Rp 100,000.00 Rp 70,000.00 0.007 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 910.00 0.012 Oh Mandor @ Rp 175,000.00 Rp 2,100.00
Rp 147,615.83
SPL Memasang 1 M2 langit-langit Lambrasering Aluminium + rangka Hollow 3.500 M Besi Hollow Galvanis 2/4 @ Rp 7,000.00 Rp 24,500.00 1.050 M2 Lambrasering Aluminium L = 12 Cm @ Rp 455,000.00 Rp 477,750.00 11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp 11,500.00 0.070 Oh Pekerja @ Rp 75,000.00 Rp 5,250.00 0.700 Oh Tukang besi @ Rp 100,000.00 Rp 70,000.00 0.007 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 910.00 0.012 Oh Mandor @ Rp 175,000.00 Rp 2,100.00
Rp 592,010.00
SPL Memasang 1 M' list langit-langit Aluminium 1.050 M' List Alluminium Strip @ Rp 7,000.00 Rp 7,350.00 4.000 Bh Srews/sekrup @ Rp 1,000.00 Rp 4,000.00 0.050 Oh Pekerja @ Rp 75,000.00 Rp 3,750.00 0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00 0.005 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 650.00 0.003 Oh Mandor @ Rp 175,000.00 Rp 525.00
Rp 21,275.00
J.6 PEKERJAAN PIPA DAN SANITER
J.6.1 Memasang 1 Bh kloset duduk/monoblok 1.000 Bh Closet duduk dudblok + Kran Shower @ Rp 2,000,000.00 Rp 2,000,000.00 6 % Perlengkapan Rp 120,000.00 3.300 Oh Pekerja @ Rp 75,000.00 Rp 247,500.00 1.100 Oh Tukang batu @ Rp 100,000.00 Rp 110,000.00 0.001 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 130.00 0.160 Oh Mandor @ Rp 175,000.00 Rp 28,000.00
Rp 2,505,630.00
J.6.4 Memasang 1 Bh urinoir 1.000 Bh Urinoir @ Rp 1,900,000.00 Rp 1,900,000.00
3 % Perlengkapan Rp 57,000.00 6.000 Kg Semen Portland @ Rp 1,150.00 Rp 6,900.00 0.010 M3 Pasir pasang @ Rp 134,000.00 Rp 1,340.00 1.000 Oh Pekerja @ Rp 75,000.00 Rp 75,000.00 1.000 Oh Tukang batu @ Rp 100,000.00 Rp 100,000.00 0.300 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 39,000.00 0.110 Oh Mandor @ Rp 175,000.00 Rp 19,250.00
Rp 2,198,490.00
J.6.5 Memasang 1 Bh wastafel 1.000 Bh Wastafel keramik @ Rp 405,000.00 Rp 405,000.00 12 % Perlengkapan Rp 48,600.00 6.000 Kg Semen Portland @ Rp 1,150.00 Rp 6,900.00 0.010 M3 Pasir pasang @ Rp 134,000.00 Rp 1,340.00 1.200 Oh Pekerja @ Rp 75,000.00 Rp 90,000.00 1.450 Oh Tukang batu @ Rp 100,000.00 Rp 145,000.00 0.150 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 19,500.00 0.100 Oh Mandor @ Rp 175,000.00 Rp 17,500.00
Rp 733,840.00
J.6.9 Memasang 1 Bh badkip porselen 1.000 Bh Bath tub + Acs @ Rp 8,500,000.00 Rp 8,500,000.00 2 % Perlengkapan Rp 170,000.00 0.008 Oh Pekerja @ Rp 75,000.00 Rp 562.50 0.075 Oh Tukang pipa @ Rp 100,000.00 Rp 7,500.00 0.008 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 975.00 0.004 Oh Mandor @ Rp 175,000.00 Rp 665.00
Rp 8,679,702.50
J.6.25 Memasang 1 M' pipa PVC tipe AW diameter 1/2" 1.200 M' Pipa PVC AW 1/2'' @ Rp 5,625.00 Rp 6,750.00 35 % Perlengkapan Rp 1,968.75 0.036 Oh Pekerja @ Rp 75,000.00 Rp 2,700.00 0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00 0.006 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 780.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 315.00
Rp 18,513.75
Memasang 1 M' pipa PVC tipe AW diameter 1/2" Untuk Instalasi Air Panas 1.200 M' Pipa PVC Air Panas 1/2'' @ Rp 41,250.00 Rp 49,500.00 35 % Perlengkapan Rp 14,437.50
0.036 Oh Pekerja @ Rp 75,000.00 Rp 2,700.00 0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00 0.006 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 780.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 315.00
Rp 73,732.50
J.6.26 Memasang 1 M' pipa PVC tipe AW diameter 3/4" 1.200 M' Pipa PVC AW 3/4'' @ Rp 4,583.33 Rp 5,500.00 35 % Perlengkapan Rp 1,604.17 0.036 Oh Pekerja @ Rp 75,000.00 Rp 2,700.00 0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00 0.006 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 780.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 315.00
Rp 16,899.17
J.6.27 Memasang 1 M' pipa PVC tipe AW diameter 1" 1.200 M' Pipa PVC AW 1'' @ Rp 6,000.00 Rp 7,200.00 35 % Perlengkapan Rp 2,100.00 0.036 Oh Pekerja @ Rp 75,000.00 Rp 2,700.00 0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00 0.006 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 780.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 315.00
Rp 19,095.00
J.6.29 Memasang 1 M' pipa PVC tipe D diameter 2" 1.200 M' Pipa PVC 2'' (D) @ Rp 38,125.00 Rp 45,750.00 35 % Perlengkapan Rp 13,343.75 0.054 Oh Pekerja @ Rp 75,000.00 Rp 4,050.00 0.090 Oh Tukang pipa @ Rp 100,000.00 Rp 9,000.00 0.009 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,170.00 0.003 Oh Mandor @ Rp 175,000.00 Rp 472.50
Rp 73,786.25
J.6.31 Memasang 1 M' pipa PVC tipe D diameter 3" 1.200 M' Pipa PVC 3'' (D) @ Rp 78,750.00 Rp 94,500.00 35 % Perlengkapan Rp 27,562.50 0.081 Oh Pekerja @ Rp 75,000.00 Rp 6,075.00 0.135 Oh Tukang pipa @ Rp 100,000.00 Rp 13,500.00 0.014 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,755.00 0.004 Oh Mandor @ Rp 175,000.00 Rp 717.50
Rp 144,110.00
J.6.32 Memasang 1 M' pipa PVC tipe D diameter 3" 1.200 M' Pipa PVC 4'' (D) @ Rp 118,250.00 Rp 141,900.00 35 % Perlengkapan Rp 41,387.50 0.081 Oh Pekerja @ Rp 75,000.00 Rp 6,075.00 0.135 Oh Tukang pipa @ Rp 100,000.00 Rp 13,500.00 0.014 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,755.00 0.004 Oh Mandor @ Rp 175,000.00 Rp 717.50
Rp 205,335.00
J.6.33 Memasang 1 Bh bak cuci piring stainles steel 1.000 Bh Washbasin stainless stel @ Rp 300,000.00 Rp 300,000.00 1.000 Bh Waterdrain + accesoriss @ Rp 50,000.00 Rp 50,000.00 0.030 Oh Pekerja @ Rp 75,000.00 Rp 2,250.00 0.300 Oh Tukang batu @ Rp 100,000.00 Rp 30,000.00 0.030 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 3,900.00 0.002 Oh Mandor @ Rp 175,000.00 Rp 262.50
Rp 386,412.50
J.6.35 Memasang 1 Bh kran diameter 3/4" atau 1/2" 1.000 Bh Kran air biasa 1/2" - 3/4" @ Rp 50,500.00 Rp 50,500.00 0.025 Bh Seal tape @ Rp 3,500.00 Rp 87.50 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 63,512.50
Memasang 1 Bh kran air ganda diameter 3/4" atau 1/2" 1.000 Bh Kran air ganda 1/2" - 3/4" @ Rp 250,000.00 Rp 250,000.00 0.025 Bh Seal tape @ Rp 3,500.00 Rp 87.50 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 263,012.50
Memasang 1 Bh kran Shower 1.000 Bh Kran Shower @ Rp 125,000.00 Rp 125,000.00 0.025 Bh Seal tape @ Rp 3,500.00 Rp 87.50 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 138,012.50
Memasang 1 Bh Shower Tray 1.000 Bh Shower Tray + Acc @ Rp 265,000.00 Rp 265,000.00 0.025 Bh Seal tape @ Rp 3,500.00 Rp 87.50 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 278,012.50
Memasang 1 Bh Stop kran 1.000 Bh Stop Kran @ Rp 76,000.00 Rp 76,000.00 0.025 Bh Seal tape @ Rp 3,500.00 Rp 87.50 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang pipa @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 89,012.50
J.6.36 Memasang 1 Bh floor drain Dan Roof DrainA 1.000 Bh Floor drain Stainlees @ Rp 50,000.00 Rp 50,000.00 B 1.000 Bh Roof drain Stainlees @ Rp 125,000.00 Rp 125,000.00
0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Juml. A Rp 62,925.00 Juml. B Rp 137,925.00
L.6 PEKERJAAN KUNCI DAN KACA
L.6.2 Memasang 1 Bh kunci tanam biasa 1.000 Bh Kunci tanam biasa (2 x Slag) @ Rp 307,000.00 Rp 307,000.00 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 359,925.00
L.6.4 Memasang 1 Bh kunci silinder 1.000 Bh Kunci tanam silinder @ Rp 215,000.00 Rp 215,000.00 0.005 Oh Pekerja @ Rp 75,000.00 Rp 375.00 0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00 0.005 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 650.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 266,462.50
L.6.5 Memasang 1 Bh engsel pintu
1.000 Bh Engsel pintu Kw.1 @ Rp 35,500.00 Rp 35,500.00 0.015 Oh Pekerja @ Rp 75,000.00 Rp 1,125.00 0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,950.00 0.0008 Oh Mandor @ Rp 175,000.00 Rp 131.25
Rp 53,706.25
SPL Memasang 1 Psg Flooring Engsel pintu 1.000 Psg Flooring engsel @ Rp 1,800,000.00 Rp 1,800,000.00 0.015 Oh Pekerja @ Rp 75,000.00 Rp 1,125.00 0.300 Oh Tukang kayu @ Rp 100,000.00 Rp 30,000.00 0.030 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 3,900.00 0.0008 Oh Mandor @ Rp 175,000.00 Rp 131.25
Rp 1,835,156.25
L.6.6 Memasang 1 Bh engsel jendela 1.000 Bh Engsel jendela Kw.1 @ Rp 26,000.00 Rp 26,000.00 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.0005 Oh Mandor @ Rp 175,000.00 Rp 87.50
Rp 38,137.50
L.6.9 Memasang 1 Bh kait angin 1.000 Bh Kait angin @ Rp 15,500.00 Rp 15,500.00 0.015 Oh Pekerja @ Rp 75,000.00 Rp 1,125.00 0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,950.00 0.00075 Oh Mandor @ Rp 175,000.00 Rp 131.25
Rp 33,706.25
SPL Memasang 1 Bh grendel jendela 1.000 Bh Grendel jendela Kw.1 @ Rp 15,500.00 Rp 15,500.00 0.010 Oh Pekerja @ Rp 75,000.00 Rp 750.00 0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,300.00 0.00050 Oh Mandor @ Rp 175,000.00 Rp 87.50
Rp 27,637.50
L.6.10 Memasang 1 Bh door closer 1.000 Bh Door closer/espanyolet @ Rp 250,000.00 Rp 250,000.00 0.050 Oh Pekerja @ Rp 75,000.00 Rp 3,750.00 0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00 0.050 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 6,500.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 310,687.50
L.6.11 Memasang 1 Bh kunci selotA 1.000 Bh Kunci selot @ Rp 255,000.00 Rp 255,000.00 B 1.000 Bh Kunci selot biasa @ Rp 125,000.00 Rp 125,000.00
0.020 Oh Pekerja @ Rp 75,000.00 Rp 1,500.00 0.200 Oh Tukang kayu @ Rp 100,000.00 Rp 20,000.00 0.020 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 2,600.00 0.0010 Oh Mandor @ Rp 175,000.00 Rp 175.00
Juml. A Rp 279,275.00 Juml. B Rp 149,275.00
L.6.12 Memasang 1 Bh pegangan pintu/door holder 1.000 Bh Door Holder @ Rp 350,000.00 Rp 350,000.00 0.050 Oh Pekerja @ Rp 75,000.00 Rp 3,750.00 0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00 0.050 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 6,500.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 410,687.50
L.6.17 Memasang 1 M2 kaca, tebal 5 mm 1.100 M2 Kaca Ryben 5mm @ Rp 150,000.00 Rp 165,000.00 0.015 Oh Pekerja @ Rp 75,000.00 Rp 1,125.00
0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,950.00 0.00075 Oh Mandor @ Rp 175,000.00 Rp 131.25
Rp 183,206.25
Memasang 1 M2 kaca, tebal 5 mm 1.100 M2 Kaca Panasap 5mm @ Rp 485,000.00 Rp 533,500.00 0.015 Oh Pekerja @ Rp 75,000.00 Rp 1,125.00 0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00 0.015 Oh Kepala Tukang Kayu @ Rp 130,000.00 Rp 1,950.00 0.00075 Oh Mandor @ Rp 175,000.00 Rp 131.25
Rp 551,706.25
M.6 PEKERJAAN PENUTUP LANTAI DAN DINDING
M.6.13 Memasang 1 M2 lantai Keramik Anti Noda T = 1 cm, ukuran (60x60) cm 3.100 Bh Tegel keramik Anti noda, T = 1 Cm, 60 x @ Rp 71,480.14 Rp 221,588.45 9.600 Kg Semen Portland @ Rp 1,150.00 Rp 11,040.00 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 1.500 Kg Semen warna @ Rp 4,500.00 Rp 6,750.00 0.250 Oh Pekerja @ Rp 75,000.00 Rp 18,750.00 0.120 Oh Tukang batu @ Rp 100,000.00 Rp 12,000.00 0.012 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,560.00 0.013 Oh Mandor @ Rp 175,000.00 Rp 2,275.00
Rp 279,993.45
Memasang 1 M2 lantai Keramik Anti Noda T = 1 cm, ukuran (20x60) cm 9.160 Bh Tegel keramik Anti noda, T = 1 Cm, 20 x @ Rp 23,769.51 Rp 217,728.69 9.800 Kg Semen Portland @ Rp 1,150.00 Rp 11,270.00 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 1.300 Kg Semen warna @ Rp 4,500.00 Rp 5,850.00 0.250 Oh Pekerja @ Rp 75,000.00 Rp 18,750.00 0.120 Oh Tukang batu @ Rp 100,000.00 Rp 12,000.00 0.012 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,560.00 0.013 Oh Mandor @ Rp 175,000.00 Rp 2,275.00
Rp 275,463.69
M.6.14 Memasang 1 M2 lantai Keramik ukuran (40x40) cm 6.630 Bh Tegel keramik 40 x 40 cm (putih) @ Rp 9,666.67 Rp 64,090.00 9.800 Kg Semen Portland @ Rp 1,150.00 Rp 11,270.00 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 1.300 Kg Semen warna @ Rp 4,500.00 Rp 5,850.00 0.620 Oh Pekerja @ Rp 75,000.00 Rp 46,500.00 0.350 Oh Tukang batu @ Rp 100,000.00 Rp 35,000.00 0.035 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 4,550.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 178,540.00
Memasang 1 M2 lantai keramik ukuran (20x20) cm 26.500 Bh Tegel keramik 20 x 20 cm (kasar) @ Rp 2,112.00 Rp 55,968.00 10.400 Kg Semen Portland @ Rp 1,150.00 Rp 11,960.00 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 1.620 Kg Semen warna @ Rp 4,500.00 Rp 7,290.00 0.620 Oh Pekerja @ Rp 75,000.00 Rp 46,500.00 0.350 Oh Tukang batu @ Rp 100,000.00 Rp 35,000.00 0.035 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 4,550.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 172,548.00
SPL Memasang 1 M2 dinding keramik ukuran (20x40) cm 13.000 Bh Tegel keramik 20 x 40 cm ( warna ) @ Rp 6,640.00 Rp 86,320.00
9.300 Kg Semen Portland @ Rp 1,150.00 Rp 10,695.00 0.018 M3 Pasir pasang @ Rp 134,000.00 Rp 2,412.00 1.940 Kg Semen warna @ Rp 4,500.00 Rp 8,730.00 0.600 Oh Pekerja @ Rp 75,000.00 Rp 45,000.00 0.450 Oh Tukang batu @ Rp 100,000.00 Rp 45,000.00 0.045 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 5,850.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 209,257.00
SPL Memasang 1 M plint Keramik ukuran (10 x 60) cm 1.700 Bh Plint Keramik 10 x 60 Cm @ Rp 14,500.00 Rp 24,650.00 1.140 Kg Semen Portland @ Rp 1,150.00 Rp 1,311.00 0.003 M3 Pasir pasang @ Rp 134,000.00 Rp 402.00 0.100 Kg Semen warna @ Rp 4,500.00 Rp 450.00 0.090 Oh Pekerja @ Rp 75,000.00 Rp 6,750.00 0.090 Oh Tukang batu @ Rp 100,000.00 Rp 9,000.00 0.009 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,170.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 44,608.00
M.6.26 Memasang 1 M plint Keramik ukuran (10x40) cm 2.650 Bh Plint Keramik 10 x 40 cm @ Rp 2,900.00 Rp 7,685.00 1.140 Kg Semen Portland @ Rp 1,150.00 Rp 1,311.00 0.003 M3 Pasir pasang @ Rp 134,000.00 Rp 402.00 0.100 Kg Semen warna @ Rp 4,500.00 Rp 450.00 0.090 Oh Pekerja @ Rp 75,000.00 Rp 6,750.00 0.090 Oh Tukang batu @ Rp 100,000.00 Rp 9,000.00 0.009 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,170.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 27,643.00
M.6.43 - SPL Memasang 1 M2 lantai Granit 1.060 Bh Granit Lantai Type Starwhite, t = 2 cm @ Rp 350,000.00 Rp 371,000.00 8.190 Kg Semen Portland @ Rp 1,150.00 Rp 9,418.50 0.045 M3 Pasir pasang @ Rp 134,000.00 Rp 6,030.00 0.650 Kg Semen warna @ Rp 4,500.00 Rp 2,925.00 0.620 Oh Pekerja @ Rp 75,000.00 Rp 46,500.00 0.350 Oh Tukang batu @ Rp 100,000.00 Rp 35,000.00 0.035 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 4,550.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 480,673.50
M.6.55 - SPL Memasang 1 M2 dinding Granit 1.020 M2 Granit Dinding Type Starwhite, t = 2 cm @ Rp 350,000.00 Rp 357,000.00 2.000 Bh Paku Pancing @ Rp 27,000.00 Rp 54,000.00 12.440 Kg Semen Portland @ Rp 1,150.00 Rp 14,306.00 0.025 M3 Pasir pasang @ Rp 134,000.00 Rp 3,350.00 0.650 Kg Semen warna @ Rp 4,500.00 Rp 2,925.00 0.720 Oh Pekerja @ Rp 75,000.00 Rp 54,000.00 0.650 Oh Tukang batu @ Rp 100,000.00 Rp 65,000.00 0.065 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 8,450.00 0.035 Oh Mandor @ Rp 175,000.00 Rp 6,125.00
Rp 565,156.00
M.6.58 - SPL Memasang 1 M2 dinding batu Alam Undersheet 1.100 M2 Batu Alam Undersheet @ Rp 196,000.00 Rp 215,600.00 11.750 Kg Semen Portland @ Rp 1,150.00 Rp 13,512.50 0.035 M3 Pasir pasang @ Rp 134,000.00 Rp 4,690.00 0.620 Oh Pekerja @ Rp 75,000.00 Rp 46,500.00 0.350 Oh Tukang batu @ Rp 100,000.00 Rp 35,000.00 0.035 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 4,550.00 0.030 Oh Mandor @ Rp 175,000.00 Rp 5,250.00
Rp 325,102.50
M.6.28 - SPL Memasang 1 M plint Granit 1.700 Bh Plint Granit Type Starwhite, t = 2 cm @ Rp 35,000.00 Rp 59,500.00 1.140 Kg Semen Portland @ Rp 1,150.00 Rp 1,311.00 0.003 M3 Pasir pasang @ Rp 134,000.00 Rp 402.00 0.100 Kg Semen warna @ Rp 4,500.00 Rp 450.00 0.090 Oh Pekerja @ Rp 75,000.00 Rp 6,750.00 0.090 Oh Tukang batu @ Rp 100,000.00 Rp 9,000.00 0.009 Oh Kepala Tukang Batu @ Rp 130,000.00 Rp 1,170.00 0.005 Oh Mandor @ Rp 175,000.00 Rp 875.00
Rp 79,458.00
N.6 PEKERJAAN PENGECATAN
N.6.8 Mengecat 1 M2 bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup 0.200 Kg Cat meni @ Rp 16,375.00 Rp 3,275.00 0.150 Kg Dempul @ Rp 31,000.00 Rp 4,650.00 0.170 Kg Cat dasar @ Rp 19,000.00 Rp 3,230.00 0.260 Kg Cat kayu @ Rp 61,000.00 Rp 15,860.00 0.070 Oh Pekerja @ Rp 75,000.00 Rp 5,250.00 0.009 Oh Tukang cat @ Rp 100,000.00 Rp 900.00 0.006 Oh Kepala Tukang Cat @ Rp 130,000.00 Rp 780.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 34,382.50
N.6.10 - SPL Melabur 1 M2 bidang Batu Alam dengan Coating 0.360 Ltr Coating @ Rp 35,000.00 Rp 12,600.00 0.040 Oh Pekerja @ Rp 75,000.00 Rp 3,000.00 0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00 0.063 Oh Kepala Tukang Cat @ Rp 130,000.00 Rp 8,190.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 30,527.50
N.6.14 Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup) 0.100 Kg Plamur tembok @ Rp 15,000.00 Rp 1,500.00 0.100 Kg Cat dasar @ Rp 19,000.00 Rp 1,900.00 0.260 Kg Cat tembok Kw. 1 @ Rp 65,000.00 Rp 16,900.00 0.020 Oh Pekerja @ Rp 75,000.00 Rp 1,500.00 0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00 0.0063 Oh Kepala Tukang Cat @ Rp 130,000.00 Rp 819.00 0.0025 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 29,356.50
PEKERJAAN LISTRIK
SPL - 01 Mengerjakan 1 Titik Instalasi Penerangan 16.000 M' Kabel NYM (2x2,5) mm @ Rp 10,500.00 Rp 168,000.00 32.000 Bh Klem Kabel No. 10 @ Rp 500.00 Rp 16,000.00 1.000 Bh Pipa Instalasi Listrik @ Rp 11,500.00 Rp 11,500.00 1.000 Bh Inbow Dos @ Rp 5,000.00 Rp 5,000.00 4.000 Bh Las Dop @ Rp 500.00 Rp 2,000.00 4.000 Bh Isolasi @ Rp 25,000.00 Rp 100,000.00 1.000 Bh T - Dos 5/8" @ Rp 500.00 Rp 500.00 0.100 Ls Alat bantu @ Rp 5,000.00 Rp 500.00 0.500 Oh Tukang listrik @ Rp 100,000.00 Rp 50,000.00 0.500 Oh Kepala Tukang listrik @ Rp 130,000.00 Rp 65,000.00
Rp 418,500.00
SPL - 02 Mengerjakan 1 Titik Instalasi Stop Kontak 12.000 M' Kabel NYM (2x2,5) mm @ Rp 10,500.00 Rp 126,000.00 20.000 Bh Klem Kabel No. 10 @ Rp 500.00 Rp 10,000.00 2.000 Bh Pipa Instalasi Listrik @ Rp 11,500.00 Rp 23,000.00 1.000 Bh Inbow Dos @ Rp 5,000.00 Rp 5,000.00 6.000 Bh Las Dop @ Rp 500.00 Rp 3,000.00
2.000 Bh Isolasi @ Rp 25,000.00 Rp 50,000.00 1.000 Bh T - Dos 5/8" @ Rp 500.00 Rp 500.00 0.100 Ls Alat bantu @ Rp 5,000.00 Rp 500.00 0.500 Oh Tukang listrik @ Rp 100,000.00 Rp 50,000.00 0.500 Oh Kepala Tukang listrik @ Rp 130,000.00 Rp 65,000.00
Rp 333,000.00
PEKERJAAN SALURAN
SPL Mengerjakan 1 M' Saluran Keliling Bangunan 0.420 M3 Galian Tanah @ Rp 60,625.00 Rp 25,462.50 1.400 M2 Pas. Trassram 1/2 Bt. 1pc:4pp @ Rp 93,912.00 Rp 131,476.80 0.035 M3 Pasir Alas @ Rp 177,850.00 Rp 6,224.75 0.021 M3 Rabat Beton Alas Saluran t=7 cm @ Rp 735,120.63 Rp 15,437.53 1.400 M2 Plester Trasram @ Rp 45,724.40 Rp 64,014.16
Rp 242,615.74
PEKERJAAN KOSEN ALUMINIUM
SPL 1 Unit Pasang Pintu Kaca Tempered, Tebal 12 Mm, Uk. 85 x 240 cm 2.173 M2 Pintu Kaca Tempered 12 mm @ Rp 1,250,000.00 Rp 2,716,875.00 1.000 Oh Pekerja @ Rp 75,000.00 Rp 75,000.00 2.500 Oh Tukang Besi @ Rp 100,000.00 Rp 250,000.00 0.250 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 32,500.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00 1.000 Set Frame List, Baut / Sekrup DLL Rp 1,358,437.50 1.000 Ls Alat bantu + Fabrikasi dll Rp 135,843.75
Rp 4,577,406.25
1 Unit Pasang Pintu Kaca Tempered, Tebal 12 Mm, Uk. 80 x 240 cm 2.016 M2 Pintu Kaca Tempered 12 mm @ Rp 1,250,000.00 Rp 2,520,000.00 1.000 Oh Pekerja @ Rp 75,000.00 Rp 75,000.00 2.500 Oh Tukang Besi @ Rp 100,000.00 Rp 250,000.00 0.250 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 32,500.00 0.050 Oh Mandor @ Rp 175,000.00 Rp 8,750.00 1.000 Set Frame List, Baut / Sekrup DLL Rp 1,260,000.00 1.000 Ls Alat bantu + Fabrikasi dll Rp 126,000.00
Rp 4,272,250.00
K.6.11-SNI Mengerjakan 1 M' Kusen Aluminium 1.100 M' Kusen Aluminium Warna 4" x 1 3/4" @ Rp 150,000.00 Rp 165,000.00 2.000 Bh Sektrup Fixer @ Rp 1,850.00 Rp 3,700.00 0.060 Tube Sielent GE / Dow Coming Non Asam @ Rp 90,000.00 Rp 5,400.00 0.043 Oh Pekerja @ Rp 75,000.00 Rp 3,225.00 0.043 Oh Tukang besi @ Rp 100,000.00 Rp 4,300.00 0.0043 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 559.00 0.0021 Oh Mandor @ Rp 175,000.00 Rp 367.50
Rp 182,551.50
SPL.1 Mengerjakan 1 M' Bingkai Pintu/Jendela Aluminium A 1.100 M' Bingkai Pintu Aluminium Warna 4" x 1 1/2 @ Rp 130,000.00 Rp 143,000.00 B 1.100 M' Bingkai Pintu / Rangka Partisi Aluminium @ Rp 120,000.00 Rp 132,000.00 C 1.100 M' Bingkai Jendela Aluminium Warna (2"x1") @ Rp 100,000.00 Rp 110,000.00
0.060 Tube Sielent GE / Dow Coming Non Asam @ Rp 90,000.00 Rp 5,400.00 0.043 Oh Pekerja @ Rp 75,000.00 Rp 3,225.00 0.043 Oh Tukang besi @ Rp 100,000.00 Rp 4,300.00 0.0043 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 559.00 0.0021 Oh Mandor @ Rp 175,000.00 Rp 367.50 1.000 Ls Alat Bantu + Accessories dll Rp 12,833.33
A Rp 169,684.83 B Rp 158,684.83 C Rp 136,684.83
SPL Mengerjakan 1 M2 Pek. Cladding Aluminium Composite Panel + Rangka 1.150 M2 Alumunium Composite Panel (PVDF) @ Rp 280,000.00 Rp 322,000.00 4.000 M' Besi Hollow Galvanis 4/4 @ Rp 12,500.00 Rp 50,000.00 1.000 M' Baja siku 50.50.5 @ Rp 37,666.67 Rp 37,666.67 1.000 Bh Stiffener @ Rp 15,000.00 Rp 15,000.00
1.000 Tube Sielent GE / Dow Coming Non Asam @ Rp 90,000.00 Rp 90,000.00 1.000 Bh Bracket steel Galfanized @ Rp 35,000.00 Rp 35,000.00 0.300 Oh Pekerja @ Rp 75,000.00 Rp 22,500.00 0.100 Oh Tukang besi @ Rp 100,000.00 Rp 10,000.00 0.010 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 1,300.00 0.015 Oh Mandor @ Rp 175,000.00 Rp 2,625.00 1.000 Ls Alat bantu @ Rp 5,000.00 Rp 5,000.00
Rp 591,091.67
SPL Mengerjakan 1 M' Pek. Aluminium Strip 1.000 m' Alumunium Open Back 2,5 x 10 cm @ Rp 115,000.00 Rp 115,000.00 0.250 Tube Sielent GE / Dow Coming Non Asam @ Rp 90,000.00 Rp 22,500.00 1.000 Ls Alat bantu @ Rp 5,000.00 Rp 5,000.00 0.500 Oh Pekerja @ Rp 75,000.00 Rp 37,500.00 0.050 Oh Tukang besi @ Rp 100,000.00 Rp 5,000.00 0.050 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 6,500.00 0.003 Oh Mandor @ Rp 175,000.00 Rp 437.50
Rp 191,937.50
SPL Memasang 1 M' Pipa BS Dia. 1/2" Medium A2.430 1.100 M' Pipa BS 1/2" Medium A @ Rp 23,741.67 Rp 26,115.83
0.194 Kg Cat meni @ Rp 16,375.00 Rp 3,183.30 0.146 Oh Tukang besi @ Rp 100,000.00 Rp 14,580.00 0.146 Oh Pekerja @ Rp 75,000.00 Rp 10,935.00 0.015 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 1,895.40 0.001 Oh Mandor @ Rp 175,000.00 Rp 127.57 1.000 Ls Alat Bantu + Accessories + Fabrikasi dll Rp 5,683.71
Rp 62,520.82
SPL Memasang 1 M' Pipa BS Dia. 1 1/2" Medium A2.430 1.100 M' Pipa BS 1 1/2" Medium A @ Rp 69,996.67 Rp 76,996.33
0.194 Kg Cat meni @ Rp 16,375.00 Rp 3,183.30 0.146 Oh Tukang besi @ Rp 100,000.00 Rp 14,580.00 0.146 Oh Pekerja @ Rp 75,000.00 Rp 10,935.00 0.015 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 1,895.40 0.001 Oh Mandor @ Rp 175,000.00 Rp 127.57 1.000 Ls Alat Bantu + Accessories + Fabrikasi dll Rp 10,771.76
Rp 118,489.37
SPL Memasang 1 M' Pipa BS Dia. 2" Medium A3.580 1.100 M' Pipa BS 2" Medium A @ Rp 94,875.00 Rp 104,362.50
0.286 Kg Cat meni @ Rp 16,375.00 Rp 4,689.80 0.215 Oh Tukang besi @ Rp 100,000.00 Rp 21,480.00 0.215 Oh Pekerja @ Rp 75,000.00 Rp 16,110.00 0.021 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 2,792.40 0.001 Oh Mandor @ Rp 175,000.00 Rp 187.95 1.000 Ls Alat Bantu + Accessories + Fabrikasi dll Rp 14,962.27
Rp 164,584.92
SPL Memasang 1 M' Pipa BS Dia. 4" Medium A8.470 1.100 M' Pipa BS 4" Medium A @ Rp 252,000.00 Rp 277,200.00
0.678 Kg Cat meni @ Rp 16,375.00 Rp 11,095.70 0.508 Oh Tukang besi @ Rp 100,000.00 Rp 50,820.00 0.508 Oh Pekerja @ Rp 75,000.00 Rp 38,115.00 0.051 Oh Kepala Tukang Besi @ Rp 130,000.00 Rp 6,606.60 0.003 Oh Mandor @ Rp 175,000.00 Rp 444.67 1.000 Ls Alat Bantu + Accessories + Fabrikasi dll Rp 38,428.20
Rp 422,710.17
SPL 2 M1 PEK. PAGAR KAWAT DURI TINGGI 2.4 METER 0.032 M3 Kayu klas I (balok) untuk kuda-kuda @ Rp 8,550,000.00 Rp 273,600.00 0.480 Roll Kawat Duri 10 Kg @ Rp 240,000.00 Rp 115,200.00 0.200 Kg Paku biasa 2" - 5" @ Rp 17,500.00 Rp 3,500.00 1.000 Ls Upah Kerja Rp 77,760.00
Rp 470,060.00 U/ 1 M1 Pek. Pagar Kawat Duri = Rp 235,030.00
DAFTAR HARGA BAHAN DAN UPAH
Tahun Anggaran 2013
I. HARGA BAHAN
BAHAN BATU, PASIR, CIPPING DAN BATU MERAH SAT HARGABatu gunung Rp. 167,000.00Batu Kali Rp. 152,000.00Batu belah 7/10 Rp. 237,000.00Batu pecah 5/7 Rp. 256,000.00Pasir pasang Rp. 134,000.00Pasir beton Rp. 148,000.00Pasir beton (Kg) Kg Rp. 105.71Pasir urug Rp. 128,000.00split/chipping 2-3 cm Rp. 267,000.00split/chipping 2-3 cm(Kg) Kg Rp. 197.78Tanah Timbunan Rp. 152,000.00Krikil Rp. 277,000.00Krikil (Kg) Kg Rp. 205.19Sirtu Rp. 177,000.00Batu merah Bh Rp. 550.00Air Ltr Rp. 250.00
BAHAN SEMENSemen PC 50kg (zak) Zak Rp. 57,000.00Semen Portland Kg Rp. 1,150.00Semen PC 40 kg (zak) Zak Rp. 46,000.00Semen Nat Kg Rp. 10,000.00Semen Putih Zak Rp. 57,000.00Semen warna Kg Rp. 4,500.00
BAHAN BESIBesi beton polos Kg Rp. 11,000.00Kawat beton Kg Rp. 21,000.00Paku Biasa 1/2" - 1" Kg Rp. 17,500.00Paku biasa 2" - 5" Kg Rp. 17,500.00Paku asbes Kg Rp. 21,500.00Paku beton Dos Rp. 27,500.00Paku pancing Kg Rp. 27,000.00Baja siku 40.40.4 M Rp. 25,166.67Baja siku 50.50.5 M Rp. 37,666.67Besi Hollow 3 x 3 M Rp. 18,500.00Besi Hollow 4 x 4 M Rp. 22,500.00Besi Hollow Galvanis 2/4 M Rp. 7,000.00Besi Hollow Galvanis 4/4 M Rp. 12,500.00Besi strip Kg Rp. 12,500.00Paku sekrup 3,5" Kg Rp. 21,500.00Paku sekrup 4"-6" Kg Rp. 31,000.00Paku Sekrup + Mor + Pelapis Bh Rp. 2,500.00Alumunium Composite Panel (PVDF) Rp. 280,000.00Pintu Aluminium Bh Rp. 960,000.00Pintu PVC Bh Rp. 258,000.00List Alluminium strip M Rp. 7,000.00Srews/sekrup Bh Rp. 1,000.00Kawat Duri 10 Kg Roll Rp. 240,000.00Kawat Duri 8 Kg Roll Rp. 188,000.00
BAHAN PLAPONMulripleks 1.22 x 2.44 x 4 mm Lbr Rp. 51,000.00Multipleks 1.22 x 2.44 x 6 mm Lbr Rp. 82,500.00Multipleks 1.22 x 2.44 x 9 mm Lbr Rp. 130,000.00Gypsumboard 9 mm Lbr Rp. 55,000.00Calsyboard 6 mm Lbr Rp. 70,000.00Teakwood Uk. 90 x 220 x 4 mm Lbr Rp. 92,000.00
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M2
Plywood Uk.90x220 cm Tebal 4 mm Lbr Rp. 92,000.00Lambrasering Aluminium L = 20 Cm Rp. 580,000.00Lambrasering Aluminium L = 12 Cm Rp. 455,000.00Ramsel nails Bh Rp. 2,500.00UB 888/400 Compoud Kg Rp. 4,500.00Isolasi Gypsun Roll Rp. 25,000.00
BAHAN KERAMIKTegel keramik 40 x 40 cm (putih) Bh Rp. 9,666.67Tegel keramik 30 x 30 cm (putih) Bh Rp. 4,860.00Tegel keramik 20 x 20 cm (kasar) Bh Rp. 2,112.00Tegel keramik 20 x 20 cm (putih) Bh Rp. 1,920.00Tegel keramik 20 x 25 cm ( warna ) Bh Rp. 2,640.00Tegel keramik 20 x 40 cm ( warna ) Bh Rp. 6,640.00Tegel keramik 10 x 10 cm ( putih ) Bh Rp. 500.00Tegel keramik Anti noda, T = 1 Cm, 60 x 60 Cm Bh Rp. 71,480.14Tegel keramik Anti noda, T = 1 Cm, 20 x 60 Cm Bh Rp. 23,769.51Tegel keramik 40 x 40 cm Dos Rp. 58,000.00Tegel keramik 30 x 30 cm impresso Dos Rp. 54,000.00Tegel keramik 20 x 20 cm kia Dos Rp. 52,800.00Tegel keramik 20 x 25 cm kia Dos Rp. 52,800.00Granit Lantai Type Starwhite, t = 2 cm Rp. 350,000.00Granit Dinding Type Starwhite, t = 2 cm Rp. 350,000.00Plint Granit Type Starwhite, t = 2 cm M Rp. 35,000.00Plint Keramik 10 x 60 cm M Rp. 14,500.00Plint Keramik 10 x 40 cm M Rp. 2,900.00Batu Alam Undersheet Rp. 196,000.00
BAHAN ATAPGenteng keramik Natural Bh Rp. 16,000.00Karet Pelapis Genteng Rp. 17,100.00Nok genteng keramik Natural Bh Rp. 20,500.00Genteng metal Lbr Rp. 87,000.00Nok genteng Metal Lbr Rp. 40,500.00Long Spandek Type G550 AZ-100 T=0,4 mm, Lbr = 80 Cm Rp. 68,000.00Nok Long Spandek Type G550 AZ-100 T=0.4 mm M' Rp. 41,500.00Rangka Atap Baja Ringan Rp. 180,000.00Aluminium foil/sisalation single type Rp. 12,500.00Ancor / Seng Pelapis Genteng Rol Rp. 2,500,000.00
BAHAN SENG/ALUMINIUMSeng plat BJLS 0.30 Lbr Rp. 50,000.00Seng plat BJLS 0.28 Lbr Rp. 60,500.00Seng gelombang BWG 34 " BJLS 0.18 mm Kaki Rp. 7,000.00Seng gelombang BWG 33 " BJLS 0.22 mm Kaki Rp. 7,500.00Seng gelombang BWG 32 " BJLS 0.30 mm Kaki Rp. 9,000.00Seng gelombang BWG 28 " BJLS 0.35 mm Kaki Rp. 11,750.00Kusen Aluminium Warna 4" x 1 3/4" M' Rp. 150,000.00Bingkai Pintu Aluminium Warna 4" x 1 1/2" M' Rp. 130,000.00Bingkai Pintu / Rangka Partisi Aluminium Warna 3" x 1 1/2" M' Rp. 120,000.00Bingkai Jendela Aluminium Warna (2"x1") M' Rp. 100,000.00Alumunium Open Back 2,5 x 10 cm M' Rp. 115,000.00
BAHAN KAYUKayu klas I (balok) untuk kuda-kuda Rp. 8,550,000.00Kayu klas II (balok) Rp. 4,550,000.00Kayu klas II (papan) Rp. 4,850,000.00Kayu klas III (balok) Rp. 2,800,000.00Kayu klas III (papan) Rp. 3,275,000.00Kayu klas I (papan) listplank dan pintu/jendela Rp. 10,050,000.00
Btg Rp. 30,000.00Kayu klas I (balok) untuk kosen pintu/jendela Rp. 9,550,000.00HPL Uk. 120 x 240 Lbr Rp. 176,000.00Woodplank 2/20 x 4 M Lbr Rp. 60,000.00
BAHAN KACAKaca bening 3 mm Rp. 98,000.00Kaca bening 5 mm Rp. 105,000.00Kaca buram 5 mm Rp. 110,000.00Kaca Ryben 5mm Rp. 150,000.00Kaca Panasap 5mm Rp. 485,000.00Kaca nako lengkap teralis set Rp. 350,000.00Pintu Kaca Tempered 12 mm Rp. 1,250,000.00
BAHAN CATCat tembok Kw. 1 Kg Rp. 65,000.00Cat tembok Kw. 2 Kg Rp. 31,000.00Cat Seng Kg Rp. 78,000.00Cat kayu Kg Rp. 61,000.00Cat Besi Kg Rp. 61,000.00Minyak bekisting Ltr Rp. 3,500.00Cat meni Kg Rp. 16,375.00Plamur tembok Kg Rp. 15,000.00Lem kayu Kg Rp. 12,500.00Residu Ltr Rp. 6,400.00Kertas amplas Lbr Rp. 5,000.00Dempul Kg Rp. 31,000.00Minyak cat Kg Rp. 31,000.00Cat dasar Kg Rp. 19,000.00Cat Waterproofing Ltr Rp. 115,000.00Coating Ltr Rp. 35,000.00
BAHAN PIPAPipa PVC AW 1/2'' M' Rp. 5,625.00Pipa PVC AW 1'' M' Rp. 6,000.00Pipa PVC AW 1 1/2'' M' Rp. 13,333.33Pipa PVC AW 3/4'' M' Rp. 4,583.33Pipa PVC 8'' (D) M' Rp. 202,500.00Pipa PVC 6'' (D) M' Rp. 252,750.00Pipa PVC 4'' (D) M' Rp. 118,250.00Pipa PVC 3'' (D) M' Rp. 78,750.00Pipa PVC 2,5'' M' Rp. 55,000.00Pipa PVC 2'' (D) M' Rp. 38,125.00Pipa PVC Air Panas 1/2'' M' Rp. 41,250.00Pipa BS 1/2" Medium A M' Rp. 23,741.67Pipa BS 1 1/2" Medium A M' Rp. 69,996.67Pipa BS 2" Medium A M' Rp. 94,875.00Pipa BS 4" Medium A M' Rp. 252,000.00Lem pipa Klg Rp. 65,000.00
BAHAN LISTRIKLampu Pijar 40 Watt Bh Rp. 6,000.00Lampu Pijar 15 Watt Bh Rp. 4,800.00Lampu Downlight Kecil Bh Rp. 75,000.00Lampu Downlight Sedang Bh Rp. 95,000.00Lampu Downlight Besar Bh Rp. 125,000.00Lampu RM 2 x 36 Watt Set Rp. 390,000.00Lampu RM 2 x 18 Watt Set Rp. 282,000.00Lampu SL-E 15 Watt Bh Rp. 36,000.00Lampu SL-E 18 Watt Set Rp. 39,600.00Lampu SL-E 23 Watt Bh Rp. 44,400.00Lampu Hias Set Rp. 3,850,000.00Exaust Fan Set Rp. 937,500.00Stop Kontak Kw. 1 Bh Rp. 65,000.00Stop Kontak AC Kw. 1 Bh Rp. 75,000.00Saklar Tunggal Kw. 1 Bh Rp. 65,000.00Saklar Ganda Kw. 1 Bh Rp. 68,500.00Klem Kabel No. 10 Bh Rp. 500.00Pipa Instalasi Listrik Bh Rp. 11,500.00Inbow Dos Bh Rp. 5,000.00Las Dop Bh Rp. 500.00Isolasi Bh Rp. 25,000.00T - Dos 5/8" Bh Rp. 500.00Fitting Bh Rp. 15,600.00Kabel NYM (2x2,5) mm M' Rp. 10,500.00Kabel NYM (3x2,5) mm M' Rp. 14,500.00MCB 6A Ex. Supran Bh Rp. 61,200.00MCB 32A Ex. Supran Bh Rp. 85,000.00Fuse Box Bh Rp. 123,000.00Alat bantu Ls Rp. 5,000.00
BAHAN LAIN - LAINSpacer/formite/penjaga jarak bekisting Bh Rp. 17,500.00Sielent GE / Dow Coming Non Asam Tube Rp. 90,000.00Sektrup Fixer Bh Rp. 1,850.00Stiffener Bh Rp. 15,000.00Bracket steel Galfanized Bh Rp. 35,000.00
II. HARGA UPAH KERJA
Tukang kayu Oh Rp. 100,000.00Tukang las Oh Rp. 100,000.00Tukang Pipa Oh Rp. 100,000.00Tukang gali Oh Rp. 100,000.00Tukang batu Oh Rp. 100,000.00
RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN RUMAH JABATAN WAKIL KETUA DPRD
KABUPATEN ENREKANG
PEKERJAAN : PEMB. RUJAB WAKIL KETUA DPRD SEBANYAK = 2 UNITANGGARAN : 2010
NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA
I PEK. PERSIAPAN1 Pengukuran + Bouplank 1.00 Ls 1,500,000.00 1,500,000.00 2 Penyediaan P3K 1.00 Ls 500,000.00 500,000.00 3 Pek. Direksi Keet 12.00 M2 2,266,375.00 27,196,500.00 4 Pek. Izin Mendirikan Bangunan (IMB) - Ls 2,500,000.00 2,500,000.00 5 Pek. Jalan Masuk (Plat Duiker) 0.78 M3 3,436,760.00 2,680,672.80
34,377,172.80
II PEK.TANAH DAN PONDASI1 Pek. Galian Tanah Pondasi 90.72 M3 60,625.00 5,499,778.75 2 Urugan Tanah 50.84 M3 206,650.00 10,505,259.40 3 Pasir Urug Bawah Pondasi 2.76 M3 177,850.00 490,154.60 4 Pas. Batu Kosong 5.93 M3 365,091.00 2,165,719.81 5 Pas. Pondasi Batu Gunung 17.23 M3 673,455.00 11,604,976.56
10 Washbasin 1.00 Bh 386,412.50 386,412.50 11 Pipa PVC Dia 65 mm (Air Kotor) 50.00 M1 144,110.00 7,205,500.00 12 Pipa PVC Dia 50 mm (Air Kotor) 12.00 M1 73,786.25 885,435.00
NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA
13 Pipa PVC Dia 20 mm (Air Bersih) 32.00 M1 16,899.17 540,773.33 14 Pipa PVC Dia 15 mm (Air Bersih) 12.00 M1 18,513.75 222,165.00 15 Septictank 1.00 Unit 5,000,000.00 5,000,000.00 16 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00 17 Pemasukan Daya Air PAM - Ls 2,500,000.00 0.00 18 Pompa Boster Ex Sango 1.00 Unit 800,000.00 800,000.00 19 Grounding 1.00 Ls 15,000,000.00 15,000,000.00
48,214,865.83 XVIII PEKERJAAN SANITASI (LANTAI II)
1 Kloset Duduk Ex. TOTO/KIA (dud Blok) + Pasang 3.00 Bh 2,505,630.00 7,516,890.00 2 Ember Penampungan Air Sementara 3.00 Bh 150,000.00 450,000.00 3 Kran Air (Ex. Parnekel) 5.00 Bh 63,512.50 317,562.50 4 Stop Kran 2.00 Bh 89,012.50 178,025.00 5 Floor Drine 4.00 Bh 62,925.00 251,700.00 6 Tempat Sabun Ex. Toto (11x11 cm) 3.00 Bh 60,000.00 180,000.00 7 Pipa PVC Dia 65 mm (Air Kotor) 18.00 M1 144,110.00 2,593,980.00 8 Pipa PVC Dia 50 mm (Air Kotor) 4.00 M1 73,786.25 295,145.00 9 Pipa Gip Dia 20 mm (Air Bersih) 22.00 M1 16,899.17 371,781.67
10 Pipa Gip Dia 15 mm (Air Bersih) 8.00 M1 18,513.75 148,110.00 11 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00 12 Bak Penampungan Air (Kap. 1M3) 1.00 Bh 4,000,000.00 4,000,000.00
17,803,194.17 XIX PEKERJAAN LAIN-LAIN1 Pek. Tangga kePenampungan Air 3.00 M1 550,000.00 1,650,000.00 2 Pek. Pagar Dan Kolom 6.50 M1 1,250,000.00 8,125,000.00 3 Pek. Pintu Pagar 3.50 M2 1,750,000.00 6,125,000.00 6 Pek. Pembersihan setelah Pembangunan 1.00 Ls 500,000.00 500,000.00 7 Pek. Penangkal Petir Lengkap 2.00 Unit 2,500,000.00 5,000,000.00 8 Realing Void dan Tangga 17.44 M1 750,000.00 13,080,000.00