REKAPITULASI BILL OF QUANTITY PEKERJAAN : PEMBANGUNAN SALURAN AIR LIMBAH IPAL TERPADU SENTRA BATIK LOKASI : KELURAHAN SIMBANG KULON, KEC. BUARAN, KABUPATEN PEKALONGAN TH. ANGGARAN : 2008 NO URAIAN JU 1 2 I PEKERJAAN PERSIAPAN Rp. II PENGADAAN DAN PEMASANGAN PIPA Rp. III PEMBUATAN MANHOLE Rp. IV PEMBUATAN BAK PENAMPUNG DAN RUMAH POMPA Rp. V MECHANICAL ELECTRICAL Rp. VI PENGETESAN PIPA Rp. VII PEMASANGAN SAMBUNGAN RUMAH Rp. SUB TOTAL = Rp. PPN 10 % = Rp. TOTAL = Rp. DIBULATKAN = Rp. TERBILANG : ………………………………………………………………………………………………………………………
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REKAPITULASI BILL OF QUANTITYPEKERJAAN : PEMBANGUNAN SALURAN AIR LIMBAH IPAL TERPADU SENTRA BATIK
LOKASI : KELURAHAN SIMBANG KULON, KEC. BUARAN, KABUPATEN PEKALONGAN
PEKERJAAN : PEMBANGUNAN SALURAN AIR LIMBAH IPAL TERPADU SENTRA BATIKLOKASI : KELURAHAN SIMBANG KULON, KEC. BUARAN, KABUPATEN PEKALONGANTH. ANGGARAN : 2008
NO. URAIAN PEKERJAAN SATUAN VOLUME
I PEKERJAAN PERSIAPAN1 Pengukuran Ulang m 5,102 - 2 Uitzet Ls 1 - 3 Pembersihan lapangan Ls 1 - 4 Papan nama proyek Ls 1 - 5 Direksi keet / gudang Ls 1 -
Jumlah I -
II PENGADAAN DAN PEMASANGAN PIPA
1 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 100 mm m - -
2 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 150 mm m 1,840 - 3 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 200 mm m 3,262 - 4 Pengadaan dan Pemasangan Asesories Ls 1 - 5 Pekerjaan Galian Tanah Keras 4,052.00 - 6 Pekerjaan Galian Tanah Biasa 278.61 - 7 Pekerjaan Urugan Tanah dipadatkan 2,968.63 - 8 Urugan Pasir 88.01 -
9 Urugan Tanah Pilihan 527.99 -
10 Pekerjaan Beton Bertulang 1:2:3 131.08 -
11 Pembuangan Sisa Tanah Galian 747.08 -
12 Pekerjaan Pondasi Telford 10 cm 3,128.40 -
13 Pekerjaan Lapis Penetrasi 5 cm 3,128.40 -
14 Pekerjaan Lapis HRS 2 cm 350.00 - Jumlah II -
III PEMBUATAN MANHOLE
1 Pembuatan Manhole Dia 40 cm Unit 89 -
2 Pembuatan Manhole Dia 60 cm Unit 7 -
Jumlah III -
IV PEMBUATAN BAK PENAMPUNG DAN RUMAH POMPA1 Pekerjaan Galian Tanah 65.73 - 2 Pekerjaan Urugan Tanah 13.15 -
3 Pasangan Batu Kosong 4.05 -
4 Lantai Kerja Beton 1:3:5 1.35 -
5 Lantai Beton Bertulang K 225 3.60 - 6 Dinding Beton Bertulang K 225 6.35 -
7 Plat Atas Beton Bertulang K 225 1.35 - 8 Pengadaan dan Pemasangan Asesories Ls 1.00 - 9 Pengadaan dan Pemasangan Saringan (Bar Screen) Unit 1.00 -
10 Pembuatan Tangga Monyet m 2 - Jumlah IV -
V MECHANICAL ELECTRICAL1 Pengadaan dan Pemasangan Pompa Air Limbah Kap. 10 Lt/dt unit 2 - 2 Pengadaan dan Pemasangan Panel (2 unit) unit 1 - 3 Pembuatan Rumah Panel & meter KWH PLN unit 1 - 4 Pengadaan dan Pemasangan Kabel Udara m 700 -
5 Voltage Regulator 20 KVA 3 Phase (lengkap dng kabel) unit 1 -
J u m l a h VI -
VI PENGETESAN PIPA1 Pengetesan Pipa Ls 5,102 -
J u m l a h VII -
VII PEMASANGAN SAMBUNGAN RUMAH
1 Pemasangan sambungan rumah/Pipa service/Tersier m 175 - J u m l a h VIII -
JUMLAH I+II+III+IV+V+VI+VII Rp -
HARGA SATUAN (Rp)
JUMLAH HARGA (Rp)
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m3
m3
m3
m2
m3
m3
m3
ANALISA HARGA KOTA PEKALONGANLAMPIRAN KEPUTUSAN WALIKOTA PEKALONGAN
TAHUN 2008REF URAIAN KOEF SAT HARGA SAT
1 2 3 4 5.00SNI 03-2835-2002 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 1M'
SNI 03-3435-2002 1 M3 BALOK BETON BERTULANG (150 KG BESI + BEGISTING ) CAMPURAN 1:2:3Kayu Hutan 0.3200 m3 1,093,950.00Paku 3.2000 kg 14,590.00Besi beton polos 150.0000 kg 12,760.00Kawat beton 2.2500 kg 14,590.00Semen PC ( 40 kg ) 8.0750 zak 37,000.00Split pecah mesin 2/3 0.7800 m3 121,550.00pasir Beton 0.5200 m3 182,330.00Kayu Hutan 8 cm/4 m 0.1200 m3 1,093,950.00Plywood 2.8000 kg 103,320.00
Kayu Hutan 8 cm/4 m 0.5120 m3 1,093,950.00Pekerja 5.8000 org 30,000.00Tukang Batu 0.3500 org 38,675.00Tukang Kayu 2.8000 org 38,675.00Tukang Besi 1.0500 org 38,675.00Kepala Tukang 0.4200 org 41,438.00Mandor 0.1850 org 44,200.00
Jumlah
SNI 03-3435-2002 1 M3 DINDING BETON BERTULANG (150 KG BESI + BEGISTING ) CAMPURAN 1:2:3Kayu Hutan 0.2400 m3 1,093,950.00Paku 3.2000 kg 14,590.00Besi beton polos 150.0000 kg 12,760.00Kawat beton 2.2500 kg 14,590.00Semen PC (40 kg) 8.0750 zak 37,000.00Split pecah mesin 2/3 0.7800 m3 121,550.00Pasir Beton 0.5200 m3 182,330.00Kayu Hutan 0.1600 m3 1,093,950.00Plywood 2.8000 kg 103,320.00Kayu Hutan 8 cm/4 m 0.7680 m3 1,093,950.00Pekerja 5.6000 org 30,000.00Tukang Batu 0.3500 org 38,675.00Tukang Kayu 2.6400 org 38,675.00Tukang Besi 1.0500 org 38,675.00Kepala Tukang 0.4000 org 41,438.00Mandor 0.1930 org 44,200.00
Jumlah
SNI 03-3435-2002 1 M3 PONDASI BETON BERTULANG (150 KG BESI + BEGISTING ) CAMPURAN 1:2:3Kayu Hutan 0.2000 m3 1,093,950.00Paku 1.5000 kg 14,590.00Besi beton polos 150.0000 kg 12,760.00Kawat beton 2.2500 kg 14,590.00Semen PC (40 kg) 8.0750 zak 37,000.00Split pecah mesin 2/3 0.7800 m3 121,550.00Pasir Beton 0.5200 m3 182,330.00Pekerja 3.9000 org 30,000.00Tukang Batu 0.3500 org 38,675.00Tukang Kayu 1.0400 org 38,675.00Tukang Besi 1.0500 org 38,675.00Kepala Tukang 0.2450 org 41,438.00Mandor 0.1650 org 44,200.00
Jumlah
SNI 03-3435-2002 1 M3 PONDASI BETON BERTULANG (110 KG BESI + BEGISTING ) CAMPURAN 1:2:3Kayu Hutan 0.2000 m3 1,093,950.00Paku 1.5000 kg 14,590.00Besi beton polos 110.0000 kg 12,760.00Kawat beton 2.2500 kg 14,590.00Semen PC (40 kg) 8.0750 zak 37,000.00Split pecah mesin 2/3 0.7800 m3 121,550.00Pasir Beton 0.5200 m3 182,330.00
SNI 03-3435-2002 1 M2 PASANG BEKISTING UNTUK PONDASIKayu Hutan 0.0400 m3 1,093,950.00Paku 0.3000 kg 14,590.00Pekerja 0.3000 oh 30,000.00Tukang Batu 0.2600 oh 38,675.00Kepala Tukang 0.0260 oh 41,438.00Mandor 0.0050 oh 44,200.00
Jumlah
SNI 03-3435-2002 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI ATASKayu Hutan 0.0400 m3 1,093,950.00Paku 0.4000 kg 14,590.00Balok kayu Hutan 0.0150 m3 1,093,950.00Playwood 0.3500 lbr 103,320.00Kayu Hutan 8-10/4 0.1920 m3 1,093,950.00Pekerja 0.3000 oh 30,000.00Tukang Batu 0.3300 oh 38,675.00Kepala Tukang 0.0330 oh 41,438.00Mandor 0.0060 oh 44,200.00
Jumlah
SNI 03-3435-2002 1 M2 PASANG BEKISTING UNTUK DINDINGKayu Hutan 0.0300 m3 1,093,950.00Paku 0.4000 kg 14,590.00Balok kayu Hutan 0.0200 m3 1,093,950.00Playwood 0.3500 lbr 103,320.00Kayu Hutan 8-10/4 0.0960 m3 1,093,950.00Pekerja 0.3200 oh 30,000.00Tukang Batu 0.3300 oh 38,675.00Kepala Tukang 0.3300 oh 41,438.00Mandor 0.0060 oh 44,200.00
Jumlah
SNI 03-3435-2002 1 KG PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIRBesi Beton ( polos / ulir ) 1.0500 kg 12,760.00Kawat beton 0.0150 kg 14,590.00Pekerja 0.0070 oh 30,000.00Tukang Batu 0.0070 oh 38,675.00Kepala Tukang 0.0007 oh 41,438.00Mandor 0.0003 oh 44,200.00
6. KAPUR Pasang m3 109,400.00Semen merah m3 100,000.00
7. PORTLAND CEMEN 40 kg m3 37,000.0050 kg m3 46,250.00Tiga Roda 40 kg m3 33,500.00Tiga Roda 50 kg m3 41,000.00Semen Putih 40 kg m3 55,000.00Semen Putih 50 kg m3 67,000.00Semen Warna m3 7,000.00
8 Kayu Hutan m3 1,093,950.00
9 Plywood Lb 103,320.00
10 Kayu Bakar m3 97,240.00
11 Cat Besi Kg 32,820.00
VI. BAHAN BESI1. BESI BETON Besi Beton Polos kg 12,760.00
Besi Beton prests kg 16,000.00
Besi Beton ulir kg 13,070.00
2 Paku kg 14,590.00
3 Kawat Beton kg 14,590.00
4 Aspal kg 9,360.00
VII. B A H A N P I P A1. Pipa PVC SDR 41
Pipa PVC DN 110 ( 4" ) m 46,950.00 Panjang 6 mPipa PVC DN 160 ( 6" ) m 90,920.00 Panjang 6 mPipa PVC DN 200 ( 8" ) m 139,160.00 Panjang 6 mPipa PVC DN 250 ( 10" ) m 221,210.00 Panjang 6 mPipa PVC DN 315 ( 12" ) m 344,380.00 Panjang 6 m
2. Pipa Medium B Galvanis - SIIPipa Medium B Galvanis DN 110 ( 4" ) m 60,500.00 Panjang 6 mPipa Medium B Galvanis DN 160 ( 6" ) m 80,666.67 Panjang 6 mPipa Medium B Galvanis DN 200 ( 8" ) m 133,833.33 Panjang 6 mPipa Medium B Galvanis DN 250 ( 10" ) m 147,583.33 Panjang 6 mPipa Medium B Galvanis DN 300 ( 12" ) m 165,000.00 Panjang 6 m
VIII PERALATAN1 Mesin Gilas Set 64,822.53
DAFTAR HARGA SATUAN BAHAN BANGUNAN
SUMBER DATA : PASARAN BEBASD A E R A H : KOTA PEKALONGAN
HARGANO. JENIS BAHAN SATUAN MINIMUM KETERANGAN
(Rp)1. Pekerja Hr 30,000.002. Mandor Hr 44,200.003. Tukang Listrik Hr 38,675.004. Tukang Kayu Hr 38,675.005. Kepala tukang kayu Hr 41,438.006. Tukang batu Hr 38,675.007. Kepala tukang batu Hr 41,438.008. Tukang besi Hr 38,675.009. Kepala tukang besi Hr 41,438.00
10. Tukang cat Hr 38,675.0011. Kepala tukang cat Hr 41,438.0012. Tukang plitur Hr 38,675.0013. Tukang jalan Hr 38,675.0014. Tukang gali Hr 38,675.0015. Tukang masak aspal Hr 38,675.0016. Tukang leideng Hr 38,675.0017. Masinis Hr 40,000.0018. Pembantu masinis Hr 30,000.0019. Penjaga api Hr 35,000.0020. Penjaga malam Hr 30,000.0021. Sopir Hr 38,675.00
22. Pembantu sopir Hr 33,150.00
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN SALURAN AIR LIMBAH IPAL TERPADU SENTRA BATIKLOKASI : KELURAHAN SIMBANG KULON, KEC. BUARAN, KABUPATEN PEKALONGANTH. ANGGARAN : 2008
NO. URAIAN PEKERJAAN SATUAN VOLUME
I PEKERJAAN PERSIAPAN1 Pengukuran Ulang m 5,102 2,000.00 10,204,400.00 2 Uitzet Ls 1 2,175,000.00 2,175,000.00 3 Pembersihan lapangan Ls 1 2,500,000.00 2,500,000.00 4 Papan nama proyek Ls 1 150,000.00 150,000.00 5 Direksi keet / gudang Ls 1 1,500,000.00 1,500,000.00
Jumlah I 16,529,400.00
II PENGADAAN DAN PEMASANGAN PIPA
1 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 100 mm m - 55,166.25 -
2 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 150 mm m 1,840.20 106,831.00 196,590,406.20
3 Pengadaan dan Pemasangan Pipa PVC Setara SDR 41 DN 200 mm m 3,262.00 163,513.00 533,379,406.00 4 Pengadaan dan Pemasangan Asesories Ls 1.00 36,498,490.61 36,498,490.61 5 Pekerjaan Galian Tanah Keras 4,052.00 26,934.38 109,138,087.50 6 Pekerjaan Galian Tanah Biasa 278.61 22,667.97 6,315,523.12 7 Pekerjaan Urugan Tanah dipadatkan 2,968.63 21,547.50 63,966,543.91
8 Urugan Pasir 88.01 82,378.00 7,249,893.37
9 Urugan Tanah Pilihan 527.99 54,694.00 28,878,014.14
11 Pembuangan Sisa Tanah Galian 747.08 25,000.00 18,677,000.00 5.6
12 Pekerjaan Pondasi Telford 10 cm 3,128.40 28,459.47 89,032,603.21 8
13 Pekerjaan Lapis Penetrasi 5 cm 3,128.40 61,566.55 192,604,803.40
14 Pekerjaan Lapis HRS 2 cm 350.00 68,195.00 23,868,250.00 Jumlah II 1,550,522,733.59
III PEMBUATAN MANHOLE
1 Pembuatan Manhole Dia 40 cm Unit 89.00 1,275,000.00 113,475,000.00
2 Pembuatan Manhole Dia 60 cm Unit 7.00 2,050,000.00 14,350,000.00 Jumlah III 127,825,000.00
IV PEMBUATAN BAK PENAMPUNG DAN RUMAH POMPA1 Pekerjaan Galian Tanah 65.73 22,667.97 1,489,965.67
2 Pekerjaan Urugan Tanah 13.15 11,333.99 148,996.57
3 Pasangan Batu Kosong 4.05 159,600.13 647,098.74 4 Lantai Kerja Beton 1:3:5 1.35 103,094.16 139,331.75
5 Lantai Beton Bertulang K 225 3.60 3,255,921.48 11,731,085.09
6 Dinding Beton Bertulang K 225 6.35 4,103,562.99 26,037,107.17
7 Plat Atas Beton Bertulang K 225 1.35 4,591,472.31 6,203,079.09 8 Pengadaan dan Pemasangan Asesories Ls 1.00 500,000.00 500,000.00 9 Pengadaan dan Pemasangan Saringan (Bar Screen) Unit 1.00 400,000.00 400,000.00
10 Pembuatan Tangga Monyet m 2.00 750,000.00 1,500,000.00 Jumlah IV 48,796,664.08
V MECHANICAL ELECTRICAL1 Pengadaan dan Pemasangan Pompa Air Limbah Kap. 10 Lt/dt unit 2.00 46,181,250.00 92,362,500.00 2 Pengadaan dan Pemasangan Panel (2 unit) unit 1.00 28,170,000.00 28,170,000.00 3 Pembuatan Rumah Panel & meter KWH PLN unit 1.00 7,500,000.00 7,500,000.00 4 Pengadaan dan Pemasangan Kabel Udara m 700.00 54,000.00 37,800,000.00 5 Voltage Regulator 20 KVA 3 Phase (lengkap dng kabel) unit 1.00 38,707,875.00 38,707,875.00
J u m l a h V 204,540,375.00
VI PENGETESAN PIPA1 Pengetesan Pipa Ls 5,102.20 2,500.00 12,755,500.00
J u m l a h VI 12,755,500.00
VII PEMASANGAN SAMBUNGAN RUMAH1 Pemasangan sambungan rumah/Pipa service/Tersier m 175.00 96,800.00 16,940,000.00
J u m l a h VII 16,940,000.00
JUMLAH I+II+III+IV+V+VI+VII Rp 1,977,909,672.66
HARGA SATUAN (Rp)
JUMLAH HARGA (Rp)
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m3
m3
m3
m2
m3
m3
m3
REKAPITULASI RENCANA ANGGARAN BIAYAPEKERJAAN : PEMBANGUNAN SALURAN AIR LIMBAH IPAL TERPADU SENTRA BATIK
LOKASI : KELURAHAN SIMBANG KULON, KEC. BUARAN, KABUPATEN PEKALONGAN
TH. ANGGARAN : 2008
NO URAIAN JUMLAH HARGA (RP)
1 2 3
I PEKERJAAN PERSIAPAN Rp. 16,529,400.00
II PENGADAAN DAN PEMASANGAN PIPA Rp. 1,550,522,733.59
III PEMBUATAN MANHOLE Rp. 127,825,000.00
IV PEMBUATAN BAK PENAMPUNG DAN RUMAH POMPA Rp. 48,796,664.08
V MECHANICAL ELECTRICAL Rp. 204,540,375.00
VI PENGETESAN PIPA Rp. 12,755,500.00
VII PEMASANGAN SAMBUNGAN RUMAH Rp. 16,940,000.00
SUB TOTAL = Rp. 1,977,909,672.66
PPN 10 % = Rp. 197,790,967.27
TOTAL = Rp. 2,175,700,639.93
DIBULATKAN = Rp. 1,900,000,000.00
TERBILANG : Satu Milyar Sembilan Ratus Ribu Rupiah