RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN KANTOR CATATAN SIPIL
LOKASI : KOMPLEK PERKANTORAN BUKIT CINTO KENANG
TAHUN ANGGARAN : 2013
No Uraian Pekerjaan Analisa Volume Sat Harga Satuan Jumlah Harga
( Rp ) ( Rp ) 1 2 3 4 5 6 7
I. PEK. PERSIAPAN1 Pek. Papan Nama Proyek Ls 1.00 Bh 350,000.00 350,000.00 2 Pek. Pembuatan Barak Kerja Ls 1.00 Unit 3,850,000.00 3,850,000.00 3 Pek. Dokumentasi dan Pelaporan Ls 1.00 Ls 1,000,000.00 1,000,000.00 4 Pek. Penyediaan Air Kerja Ls 1.00 Ls 605,000.00 605,000.00 5 Pek. Pemasangan Bouwplank 4 78.00 M1 47,635.00 3,715,530.00
I. Total 9,520,530.00
II. PEK. TANAH / PONDASI1 ###Pek. Galian Tanah Pondasi 1 67.69 M3 43,125.00 2,919,131.25 2 ###Pek. Urugan Kembali bekas Galian 2 22.56 M3 14,373.56 324,267.57 3 ###Pek. Urugan Pasir Bawah Pondasi 3 3.57 M3 125,250.00 447,142.50 4 Pek. Cerucuk 56 252.00 Btg 39,700.00 10,004,400.00 5 Pek. Timbunan Tanah Pilihan EI-322 52.04 M3 87,416.00 4,549,128.64 6 ###Pek. Beton Lantai Kerja ad. 1: 3 : 5 7 3.57 M3 647,121.00 2,310,221.97 7 ###Pek. Pond. Tapak Beton Bertulang 1 : 2 : 3 uk. 80x80 5 4.70 M3 3,959,700.00 18,610,590.00 8 Pek. Pas. Pond. Bt Bata Tebal 1 Bt Dan 1 1/2 Bt Ad. 1 : 3 19 105.66 M2 181,480.00 19,175,176.80 9 Pek. Pas. Pond. Bt Bata Selasar Tebal 1 Batu Ad. 1 : 3 19 34.24 M2 181,480.00 6,213,875.20
PEKERJAAN : PEMBANGUNAN LANJUTAN KANTOR CATATAN SIPIL
LOKASI : KOMPLEK PERKANTORAN BUKIT CINTO KENANG
TAHUN ANGGARAN : 2013
No Uraian Pekerjaan Analisa Volume Sat Harga Satuan Jumlah Harga
( Rp ) ( Rp ) 1 2 3 4 5 6 7
IV. PEKERJAAN PINTU DAN JENDELA1 ###Pek. Kusen Pintu dan Jendela Kayu Kls I 30 1.43 M3 7,488,750.00 10,708,912.50 2 Pek. Daun Pintu Panel Kayu Kls I 31 9.80 M2 493,750.00 4,838,750.00 3 Pek. Jendela Kaca Mati Kls I Ls 2.73 M2 250,000.00 682,500.00 4 Pek. Daun Jendela Kaca Kayu Kls I 32 33.21 M2 599,000.00 19,892,790.00 5 Pek. Ventilasi kayu Uk. 20 x 35 Ls 21.00 M2 50,000.00 1,050,000.00
IV. Total 37,172,952.50
V. PEKERJAAN KUDA-KUDA DAN ATAP1 Pek. Kuda-kuda dan Rangka Atap Baja Ringan (Pabrikasi) 54 353.70 M2 157,150.00 55,583,955.00 2 Pek. Atap Genteng Metal 34 353.70 M2 88,740.00 31,387,338.00 3 ###Pek. Bubungan Atap Genteng Metal 35 29.00 M1 51,602.50 1,496,472.50 4 Pek. Jurai Luar 35 32.20 M1 51,602.50 1,661,600.50 5 ###Pek. List Plank GRC Ls 94.05 M1 30,000.00 2,821,500.00
IX. PEKERJAAN INSTALASI LISTRIK1 ###Pas. Instalasi Lampu Ls 28.00 Ttk 100,000.00 2,800,000.00 2 ###Pas. Instalasi Kabel Stop Kontak Ls 17.00 Ttk 100,000.00 1,700,000.00 3 Pas. Lampu TL 2 x 20 watt Kompilt Ls 10.00 Bh 170,000.00 1,700,000.00 4 Pas. Lampu Down Light Ls 6.00 Bh 120,000.00 720,000.00 5 Pas. Lampu Jantung Spiral Ls 8.00 Bh 42,500.00 340,000.00
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN KANTOR CATATAN SIPIL
LOKASI : KOMPLEK PERKANTORAN BUKIT CINTO KENANG
TAHUN ANGGARAN : 2013
No Uraian Pekerjaan Analisa Volume Sat Harga Satuan Jumlah Harga
( Rp ) ( Rp ) 1 2 3 4 5 6 76 Pas. Lampu Warna Di Aula Ls 4.00 Bh 85,000.00 340,000.00 7 Pas. Saklar Ganda Ls 13.00 Bh 21,000.00 273,000.00 8 Pas. Saklar Tunggal Ls 4.00 Bh 19,000.00 76,000.00 9 Pas. Box Sekring Ls 1.00 Bh 100,000.00 100,000.00
10 ###Pas. Stop Kontak Pada Dinding Ls 16.00 Bh 21,000.00 336,000.00 11 Pas. Stop Kontak Pada Lantai (Stanlies) Ls 1.00 Bh 475,000.00 475,000.00 12 Pas. Lampu Hias Pada Kolom Teras Ls 4.00 Bh 500,000.00 2,000,000.00
X. Total 10,860,000.00
X. PEKERJAAN SALURAN1 ###Pas. Batu Bata saluran air 1:4 45 86.00 M1 68,486.53 5,889,841.36 2 ###Pek. Plesteran Saluran 17 34.40 M2 38,148.00 1,312,291.20
XII. PEKERJAAN LAIN-LAIN1 Pek. Profil Kolom Teras Ls 1.00 Ls 900,000.00 900,000.00 2 Pas. Kayu Profil Ukiran Jambi Ls 4.60 M2 750,000.00 3,450,000.00 3 Pek. Pembersihan Akhir Lokasi Ls 1.00 Ls 1,000,000.00 1,000,000.00
XIV. Total 5,350,000.00
SUB TOTAL ( A ) 552,006,197.11 PPn 10% ( B ) 55,200,619.71 JUMLAH TOTAL ( A + B ) 607,206,816.82 DIBULATKAN 607,200,000.00
Jambi, 9 April 2013CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
1 1 M3 PEK.GALIAN TANAH BIASA SEDALAM 1 METER
Upah 0.7500 OH Pekerja Rp 55,000.00 Rp 41,250.00
0.0250 OH Mandor Rp 75,000.00 Rp 1,875.00
Rp 43,125.00
Total >>> 43,125.00
2 1 M3 URUGAN TANAH KEMBALI
Upah 0.3333 Rp 43,125.00 Rp 14,373.56
Rp 14,373.56
Total >>> Rp 14,373.56
3 1 M3 MENGURUG PASIR DIBAWAH LANTAI DAN PONDASI
Bahan 1.2000 M3 Pasir Urug Rp 90,000.00 Rp 108,000.00
Rp 108,000.00
Upah 0.3000 OH Pekerja Rp 55,000.00 Rp 16,500.00
0.0100 OH Mandor Rp 75,000.00 Rp 750.00
Rp 17,250.00
Total >>> Rp 125,250.00
4 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK
Bahan 0.0120 M3 Kayu 5/7 ( Kayu Kelas II) Rp 1,800,000.00 Rp 21,600.00
0.0070 M3 Kayu papan 3/20 (Kayu Kls II) Rp 1,800,000.00 Rp 12,600.00
0.0200 Kg Paku Biasa 2" - 5" Rp 15,500.00 Rp 310.00
Rp 34,510.00
Upah 0.0100 OH Kepala Tukang Rp 75,000.00 Rp 750.00
PERKIRAAN HARGA JUMLAHNO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
( Rp. ) ( Rp. )
A TENAGA
1 Pekerja (L01) Jam 0.0714 55,000.00 3,927.00 2 Mandor (L03) Jam 0.0178 75,000.00 1,335.00
JUMLAH HARGA TENAGA 5,262.00
B BAHAN
1 Material Tanah Pilihan (M09) M3 1.2000 44,600.00 53,520.00
JUMLAH HARGA BAHAN 53,520.00
C PERALATAN1 Whell Loader (E15) Jam 0.0178 266,496.57 4,743.64 2 Dump truck (E08) Jam 0.0718 173,305.83 12,443.36 3 Motor Grader (E13) Jam 0.0117 - - 4 Vibrator Roller (E19) Jam 0.0214 - - 5 Water Tanker (E23) Jam 0.0070 - - 6 Alat Bantu Ls 1.0000 3,500.00 3,500.00
JUMLAH HARGA PERALATAN 20,687.00
D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 79,469.00 E OVERHEAD & PROFIT 10.0% % x D 7,946.90 F HARGA SATUAN PEKERJAAN ( D + E ) DIBULATKAN 87,416.00
Note : 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/ atau ukuran berat untuk bahan - bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang dibayar dari
kontrak) dan biaya - biaya lainnya.
Jambi, 9 April 2013CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA
TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJA TOTAL
ALAT ALAT ALAT JAM SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS PERBAIKAN & PERAWATAN UPAH TOTAL BIAYA
UMUR KERJA HARGA ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK OPERATOR PEMBANTU BIAYA SEWA ALAT
ALAT 1 TAHUN ALAT MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
MODAL / SOPIR / JAM JAM KERJA
(HP) - (Tahun) (Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) Lt/HP/Jam Ltr/HP/Jam (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.No. JENIS PERALATAN KODE f1 x HP x 1 Orang 1 Orang
ALAT i(1+i)^A (B - C) x D 0.002 x B 0.125 0.01 Harga BBM 0.125 (g1 x B') Per Per
(10% X B) ----------- ----------- ----------- (e1 + e2) s / d s / d + s / d ----------- Jam Kerja Jam Kerja F+G+H+I E + J
KETERANGAN : 1. Tingkat Suku Bunga = 20.00 % per-tahun2. Upah Operator / Sopir / Mekanik = 10,714 Rupiah per-orang/jam 750003. Upah Pembantu Operator/Sopir/Mekanik = 6,429 Rupiah per-orang/jam 450004. Harga Bahan Bakar Bensin = 10,000 Rupiah per-liter5. Harga Bahan Bakar Solar = 10,000 Rupiah per-liter6. Minyak Pelumas = 35,000 Rupiah per-liter7. Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan8. Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
A1 Asbes Gelombang Uk. 6 x 11 Rp 35,000.00 / Lbr2 Asbes Gelombang Uk. 7 x 11 Rp 40,000.00 / Lbr3 Aspal Rp 10,500.00 / Kg4 Aluminium Foil Rp 33,500.00 / M25 Aluminium Alkal 28 Rp 39,000.00 / M26 Aluminium Alkal 30 Rp 37,500.00 / M27 Amplas Niken Rp 6,000.00 / Lbr8 Arang Rp 3,000.00 / Kg9 Aibon Rp 40,000.00 / Kg
10 Alat Bantu Rp 3,500.00 / Set11 Agregat Sirtu Rp 375,000.00 / M312 Agregat Kasar Rp 375,000.00 / M313 Agregat Halus Rp 385,000.00 / M3
B1 Batu Bata 5 x 10 x 20 Rp 500.00 / Bh2 Batu Bata 10 x 10 x 20 Rp 600.00 / Bh3 Batu Alam Alur Rel Kecil Rp 160,000.00 / M24 Batu Alam Alur Rp 175,000.00 / M25 Bataco Rp 3,500.00 / Bh6 Bak Air Fiber Glass Kap. = 0,5 m3 Rp 350,000.00 / Bh7 Bak Air Fiber Glass Kap. = 1,0 m3 Rp 450,000.00 / Bh8 Bak Air Fiber Glass Kap. = 2,0 m3 Rp 650,000.00 / Bh9 Bak Cuci Piring Stenless Rp 250,000.00 / Bh
10 Besi Beton Rp 14,800.00 / Kg11 Besi Ulir Rp 14,500.00 / Kg12 Besi Strip Rp 75,000.00 / Btg13 Besi Siku Rp 13,500.00 / Kg14 Besi Hollow Rp 58,000.00 / Btg15 Besi/Baja Konstruksi Rp 47,500.00 / Kg16 Batu Puru Murni Rp 270,000.00 / M317 Batu Kali Rp 410,000.00 / M3
C
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
1 Cat Tembok Rp 28,000.00 / Kg2 Cat Dasar Tembok Rp 30,000.00 / Kg3 Cat Minyak Rp 40,000.00 / Kg4 Cat Menie Kayu Rp 30,000.00 / Kg5 Cat Menie Besi Rp 30,000.00 / Kg6 Cat Marca (Non Termoplas) Rp 90,000.00 / Kg7 Cat Marca (Termo Plastik) Rp 97,500.00 / Kg8 Closet Jongkok Rp 185,000.00 / Bh9 Closet Duduk Rp 1,350,000.00 / Bh
10 Cincin Keramik Rp 6,500.00 / Lbr11 Conblok Rp 3,750.00 / Bh
D1 Dempul Kayu Rp 20,000.00 / Kg2 Dempul/Plamier Rp 6,000.00 / Kg3 Daya Listrik 1300 Watt Lengkap Rp 3,500,000.00 / Unit
E1 GRC Rp 60,000.00 / Lbr2 Engsel Pintu Rp 52,000.00 / Set3 Engsel Jendela Rp 30,000.00 / Set4 Engsel Kupu-kupu 4" Rp 6,000.00 / Set5 Engel Cabut h 140 x 60 mm Rp 8,000.00 / Set6 Ember Cor Rp 6,000.00 / Bh
F1 Filler (Abu Batu) Rp 750.00 / Kg
G1 Genteng Tanah Rp 2,500.00 / Bh2 Genteng Beton Rp 3,500.00 / Bh3 Genteng Keramik Rp 20,000.00 / Bh4 Genteng Metal Rp 32,000.00 / Lbr5 Gorong-Gorong Beton Dia. 20 cm P = 100 cm Rp 45,000.00 / Bh6 Gorong-Gorong Beton Dia. 30 cm P = 100 cm Rp 70,000.00 / Bh7 Gorong-Gorong Beton Dia. 40 cm P = 100 cm Rp 90,000.00 / Bh8 Gorong-Gorong Beton Dia. 60 cm P = 100 cm Rp 180,000.00 / Bh9 Gorong-Gorong Beton Dia. 80 cm P = 100 cm Rp 225,000.00 / Bh
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
10 Gorong-Gorong Beton Dia. 100 cm P = 100 cm Rp 300,000.00 / Bh11 Grendel Jendela Rp 7,000.00 / Bh12 Grendel Pintu Rp 16,000.00 / Bh13 Greace (Minyak Gemuk) Rp 30,000.00 / Kg14 Gypsum Rp 60,000.00 / M215 Glass Bead Rp 67,000.00 / Kg16 Gergaji Rp 60,000.00 / Bh
H1 Hak Angin Rp 8,500.00 / Bh
I1 Instalasi Titik Lampu/Stop Kontak Rp 100,000.00 / Ttk2 Instalasi Air Bersih Rp 75,000.00 / Ttk
K1 Kapur Tembok Rp 12,500.00 / Kg2 Kawat Beton Rp 20,000.00 / Kg3 Kayu Kelas I (Lokal) Standard Bulian Rp 5,000,000.00 / M34 Kayu Kelas II (Lokal) Rp 4,000,000.00 / M35 Kayu Kelas II ( Kasau 5 / 7 ) Rp 4,000,000.00 / M36 Kayu Kelas II ( Reng 2 / 4 ) Rp 4,000,000.00 / M37 Kayu Dolken Rp 5,500.00 / Btg8 Kayu Cerucuk Rp 25,000.00 / Btg9 Kayu Bulian Belahan P = 2 M' Rp 67,000.00 / Btg
10 Kayu Bulian Belahan P = 1,5 M' Rp 55,000.00 / Btg11 Kayu Bakar Rp 130,000.00 / M312 Kayu Bekisting Rp 1,800,000.00 / M313 Kayu Profil Rp 24,000.00 / Btg14 Kaca Bening 3 mm Rp 150,000.00 / M215 Kaca Bening 5 mm Rp 225,000.00 / M216 Kaca Ryben 3 mm Rp 200,000.00 / M217 Kaca Ryben 5 mm Rp 260,000.00 / M218 Kaca Es 3 mm Rp 230,000.00 / M219 Kaca Es 5 mm Rp 185,000.00 / M220 Kaca Patri 5 mm Rp 240,000.00 / M2
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
21 Kaca Naco Bening 7 Daun Lengkap Rp 120,000.00 / Set22 Kaca Naco Bening 8 Daun Lengkap Rp 130,000.00 / Set23 Kaca Naco Ryben 7 Daun Lengkap Rp 135,000.00 / Set24 Kaca Naco Ryben 8 Daun Lengkap Rp 140,000.00 / Set25 Katrol Timbah + Tali Ban Rp 50,000.00 / Set26 Kawat Duri Rp 120,000.00 / Rol27 Kawat Harmonika Rp 90,000.00 / Rol28 Kawat Ayam Rp 15,000.00 / M'29 Kerikil Rp 300,000.00 / M330 Keramik KIA 20 x 20 cm Rp 50,000.00 / Dus31 Keramik KIA 25 x 25 cm Rp 55,000.00 / Dus32 Keramik KIA 30 x 30 cm Rp 60,000.00 / Dus33 Keramik KIA 25 x 40 cm Rp 65,000.00 Dus34 Keramik KIA 40 x 40 cm Rp 70,000.00 / Dus35 Keramik Mulia 10 x 20 cm Rp 35,000.00 / Dus36 Keramik Mulia 20 x 20 cm Rp 35,000.00 / Dus37 Keramik Mulia 20 x 25 cm Rp 40,000.00 / Dus38 Keramik Mulia 30 x 30 cm Rp 45,000.00 / Dus39 Keramik Roman 10 x 20 cm Rp 40,000.00 / Dus40 Keramik Roman 20 x 20 cm Rp 45,000.00 / Dus41 Keramik Roman 30 x 30 cm Rp 50,000.00 / Dus42 Keramik Super Italy 10 x 20 cm Rp 67,500.00 / Dus43 Keramik Terakota 5 x 10 Rp 200,000.00 / Dus44 Kitchen Seng Logam Rp 725,000.00 / Bh45 Kisi-kisi Kayu Bulian Rp 25,875.00 / Bh46 Kisi-kisi Beton Cetak T = 80 cm Rp 17,250.00 / Bh47 Kunci Tanam 2 Slang Rp 150,000.00 / Set48 Kunci Tanam Merk SES Double Slang Rp 150,000.00 / Set49 Kunci Tanam Merk Jangkar 2 Slang No. 746 Rp 150,000.00 / Set50 Kunci Kamar Mandi Otomatis Rp 65,000.00 / Set51 Kunci Koltom Ukir Rp 172,500.00 / Set52 Kunci Koltom Biasa Rp 143,750.00 / Set53 Kran Air Rp 16,000.00 / Bh
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
L1 Lampu Down Light Besar Rp 120,000.00 / Bh2 Lampu Down Ligh Kecil Rp 80,000.00 / Bh3 Lampu Jantung Spiral Rp 42,500.00 / Bh4 Lampu TL 10 Watt Komplit Rp 60,000.00 / Bh5 Lampu TL 20 Watt Komplit Rp 85,000.00 / Bh6 Lampu TL 40 Watt Komplit Rp 100,000.00 / Bh7 Laterik Rp 200,000.00 / M38 List Profil Rp 4,000.00 / M'9 List Plank Ukiran Papan Tembesu Rp 130,000.00 / M'
10 List Profil Gypsum Rp 10,000.00 / M'11 Lempengan Rumput Rp 17,500.00 / M'
M1 Minyak Cat Rp 7,000.00 / Ltr2 Minyak Tanah (Industri) Rp 10,000.00 / Ltr3 Mur Baut Rp 4,000.00 / Set4 Minyak Pelumas (Oli) Rp 35,000.00 / Ltr5 Minyak Bensin (Industri) Rp 10,000.00 / Ltr6 Minyak Solar (Industri) Rp 10,000.00 / Ltr
N1 Nok Genteng Beton Rp 7,000.00 / Bh2 Nok Genteng Tanah Rp 7,000.00 / Bh3 Nok Genteng Metal Rp 25,000.00 / Bh4 Nok Genteng Keramik Rp 35,000.00 / Bh
P1 Pasir Kasar Rp 90,000.00 / M32 Pasir Halus Rp 90,000.00 / M33 Papan Klas I (Lokal) Rp 5,000,000.00 / M34 Papan Klas II (Lokal) Rp 4,000,000.00 / M35 Papan Bekisting Rp 1,800,000.00 / M36 Papan Merk Proyek Rp 350,000.00 / Bh7 Plywood 9mm Rp 120,000.00 / Lbr8 Paku Biasa Rp 15,500.00 / Kg
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
9 Paku Halus Rp 22,500.00 / Kg10 Paku Asbes Rp 20,000.00 / Kg11 Paku Bulian Rp 16,000.00 / Kg12 Paku Seng RRC Rp 20,000.00 / Kg13 Paku Beton Rp 13,500.00 / Ktk14 Paku Skrup Rp 30,000.00 / Kg15 Paku Anti Karat Rp 25,000.00 / Kg16 Paku Jembatan Rp 25,000.00 / Kg17 Pagar Besi Normal/Biasa Rp 300,000.00 / M'18 Pagar Besi Ulir Rp 475,000.00 / M'19 Pagar Petak (60 x 15) Rp 215,000.00 / M'20 Pagar Catur (60 x 15) Rp 250,000.00 / M'21 PatokTanah Rp 20,000.00 / Bh22 Perlak Oskar Rp 30,000.00 / M223 Pintu Besi Kombinasi Plat Rp 450,000.00 / M224 Pintu Pagar Besi Kombinasi Plat Lengkap Rel Rp 460,000.00 / M225 Pipa PVC Ø 1/2" Rp 16,000.00 / Btg26 Pipa PVC Ø 3/4" Rp 18,000.00 / Btg27 Pipa PVC Ø 1" Merk Wavin Rp 27,500.00 / Btg28 Pipa PVC Ø 2" Merk Wavin Rp 65,000.00 / Btg29 Pipa PVC Ø 3" Merk Wavin Rp 115,000.00 / Btg30 Pipa PVC Ø 4" Merk Wavin Rp 190,000.00 / Btg31 Pipa Galvanis Ø 1/2" Rp 85,000.00 / Btg32 Pipa Galvanis Ø 3/4" Rp 95,000.00 / Btg33 Pipa Galvanis Ø 1" Rp 105,000.00 / Btg34 Pipa Galvanis Ø 1. 1/2" Rp 145,000.00 / Btg35 Pipa Galvanis Ø 2" Rp 170,000.00 / Btg36 Pipa Galvanis Ø 3" Rp 250,000.00 / Btg37 Plat Rambu (High I Grade) Rp 1,750,000.00 / Unit37 Pipa Pembuang Hawa Dia.1 1/2" Rp 65,000.00 / Set38 Pompa Tangan Dragon Rp 400,000.00 / Set39 Pompa Air Otomatis Head 9 M' Lkp Pipa Hisap Rp 750,000.00 / Set40 Porselin Rp 85,000.00 / M241 Polyplek Rp 80,000.00 / Bh42 Plitur Mekanik Rp 30,000.00 / Ltr
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
R1 Residu Rp 6,500.00 / Ltr2 Rollling Door Plat Besi Rp 475,000.00 / M23 Rollling Door Plat Aluminium Rp 550,000.00 / M24 Rooster Beton 20 x 20 cm Rp 8,500.00 / Bh5 Rooster Beton 30 x 30 cm Rp 13,000.00 / Bh6 Rumput Rp 15,000.00 / M2
S1 Saklar Tunggal Persegi Broco Rp 19,000.00 / Bh2 Saklar Ganda Broco Rp 21,000.00 / Bh3 Saringan Air Plastik Rp 6,500.00 / Bh4 Saringan Air Besi Rp 25,000.00 / Bh5 Semen PC (@ 50 Kg) Rp 60,000.00 / Zak6 Semen Padang Type II (@ 40 Kg) Rp 53,600.00 / Zak7 Semen Putih Rp 2,000.00 / Kg8 Seng Gelombang 6 x 9 Rp 33,500.00 / Lbr9 Seng Gelombang 6 x 11 Rp 38,000.00 / Lbr
10 Seng Gelombang 7 x 11 Rp 45,000.00 / Lbr11 Seng Datar BJLS 20 Rp 50,000.00 / M112 Seng Datar BJLS 30 Rp 55,000.00 / M113 Seng Plastik 6 x 11 Rp 65,000.00 / Lbr14 Seng Plastik 7 x 11 Rp 75,000.00 / Lbr15 Selusuran Tangga Kayu Bulian Rp 70,000.00 / M'16 Sirap Rp 2,000.00 / Kpg17 Sirlak Rp 55,000.00 / Kg18 Sliding Door Besi Rp 875,000.00 / M219 Spritus Rp 9,000.00 / Ltr20 Stop Kontak Stanlies Rp 450,000.00 / Bh21 Stop Kontak Persegi Broco Rp 21,000.00 / Bh
T1 Talang PVC Besar @ 4 m Rp 50,000.00 / Btg2 Tanah Laterik Rp 185,000.00 / M33 Tanah Pilihan Rp 44,600.00 / M34 Tanah Timbun Biasa ( Urung ) Rp 45,000.00 / M35 Tarikan Pintu 5" Rp 30,000.00 / Bh6 Tarikan Jendela 3" Rp 7,500.00 / Bh
DAFTAR HARGA SATUAN BAHAN
HARGA SATUAN BAHAN
NO URAIAN HARGA ( Rp )
7 Teakwood (90 x 214 cm) Rp 65,000.00 / Lbr8 Teakwood (120 x 210 cm) Rp 75,000.00 / Lbr9 Tedmond 250 Ltr Rp 375,000.00 / Bh
10 Tedmond 500 Ltr Rp 700,000.00 / Bh11 Tedmond 1000 Ltr Rp 1,250,000.00 / Bh12 Tedeng Layar Ukir Rp 650,000.00 / M213 Ter/Blangkin Rp 55,000.00 / Ltr14 Teralis Jendela Rp 275,000.00 / M215 Thinner Rp 20,000.00 / Ltr16 Tiang Bendera Lengkap Tali Rp 750,000.00 / Unit17 Triplek 3 mm (120 x 240 cm) Rp 45,000.00 / Lbr18 Triplek 4 mm (120 x 240 cm) Rp 60,000.00 / Lbr19 Multiplek 6 mm (120 x 240 cm) Rp 80,000.00 / Lbr20 GRC (120 x 240 cm) Rp 65,000.00 / Lbr21 Ubin Mozaik 30 x 30 cm Rp 6,500.00 / Bh22 Ubin PC Badak 30 x 30 cm Rp 5,000.00 / Bh23 Ubin Plint PC Abu-abu 15 x 20 cm Rp 3,600.00 / Bh24 Ubin Plint PC Abu-abu 15 x 30 cm Rp 4,500.00 / Bh25 Ubin Plint Traso 15 x 30 cm Rp 4,700.00 / Bh26 Ubin PC Abu-abu 20 x 20 cm Rp 5,000.00 / Bh27 Ubin PC Abu-abu 30 x 30 cm Rp 5,500.00 / Bh28 Ubin Tahu 20 x 20 cm Warna Rp 5,800.00 / Bh29 Ubin Traso 30 x 30 cm Rp 6,000.00 / Bh30 Urinoir lengkap Rp 900,000.00 / Bh31 Ukiran Sebelah Rp 600,000.00 / M232 Ukiran Tembus Dua Muka Rp 800,000.00 / M2
W1 Water Meter/Izin PDAM Rp 750,000.00 / SR2 Wastafel Lengkap Cermin Rp 1,500,000.00 / Bh3 WastafelGantung Keramik Rp 1,000,000.00 / Bh4 Wastafel Biasa Rp 500,000.00 / Bh5 Wall Paper Rp 85,000.00 / M2
Jambi, 9 April 2013CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
DAFTAR HARGA SATUAN UPAH KERJA
HARGA SATUAN UPAH
NO TENAGA KERJA SATUAN HARGA SATUAN KET
1 Mandor OH Rp 75,000.00
2 Kepala Tukang OH Rp 75,000.00
3 Tukang Besi OH Rp 65,000.00
4 Tukang Kayu OH Rp 65,000.00
5 Tukang Batu OH Rp 65,000.00
6 Tukang Cat OH Rp 65,000.00
7 Tukang Bongkar OH Rp 65,000.00
8 Tukang Listrik OH Rp 65,000.00
9 Tukang Pipa OH Rp 65,000.00
10 Pekerja OH Rp 55,000.00
Jambi, 9 April 2013
CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
DAFTAR UPAH KERJA
NO TENAGA KERJA SATUAN HARGA SATUAN KET1 Mandor OH Rp 65,000.00 4 Kepala Tukang OH Rp 60,000.00 2 Tukang Besi OH Rp 60,000.00 3 Tukang Kayu OH Rp 60,000.00 4 Tukang Batu OH Rp 60,000.00 5 Tukang Cat OH Rp 60,000.00 6 Tukang Bongkar OH Rp 60,000.00 7 Tukang Listrik OH Rp 60,000.00 8 Tukang Pipa OH Rp 60,000.00 9 Pekerja OH Rp 50,000.00
Jambi, 9 April 2013
CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
Catatan :
* Operator terampil mengoperasikan jenis peralatan pekerjaan berat.
Misal : Bulldozer, Motor Grader, Whell Loader, Asphalt Finisher, Tandem Roller dll.
** Operator kurang Terampil mengoperasikan jenis peralatan untuk melayani pekerjaan yang agak ringan
Misal : Tamper Vibrator Plate dan Concrete Mixer.
Catatan :
* Operator terampil mengoperasikan jenis peralatan pekerjaan berat.
Misal : Bulldozer, Motor Grader, Whell Loader, Asphalt Finisher, Tandem Roller dll.
** Operator kurang Terampil mengoperasikan jenis peralatan untuk melayani pekerjaan yang agak ringan
Misal : Tamper Vibrator Plate dan Concrete Mixer.
Sengeti, Desember 2007
Mengetahui : Dibuat OlehKEPALA DINAS PEKERJAAN UMUM KEPALA BIDANG PUP
KABUPATEN MUARO JAMBI
H. RUDI ANSUR,ST.ME M.BUHARI,SSTNIP. 430 005 845 NIP.430 006 610
CALCULATION SHEET
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN KANTOR CAPIL
LOKASI : KECAMATAN TAMAN RAJO KABUPATEN MUARO JAMBI
Jambi, 9 April 2013Nomor : 325 / MK - IV / 2013Lampiran : 1 (satu) berkas
Kepada Yth ,Kelompok kerja Unit layananPengadaan Kabupaten Muaro Jambi Pada Dinas Pekerjaan UmumDi
Sengeti
Perihal : Penawaran Atas Paket Pekerjaan jasa Pekerjaan PEMBANGUNAN LANJUTAN KANTOR CATATAN SIPIL
Setelah Mempelajari dengan seksama Dokumen Pelelangan beserta adendumnya yang merupakan Bagian Dari Pengumuman Pelelangan nomor: 20/CIPKAR/POKJA.PU-DPU/2013 tanggal 1 April 2013,dan setelah kami mempelajari dengan seksama Dokumen Pengadaan dan Berita Acara Pemberian Penjelasan,dengan ini kami mengajukan penawaran untuk :
Pekerjaan PEMBANGUNAN LANJUTAN KANTOR CATATAN SIPIL
Sesuai dengan syarat-syarat umum kontrak,spesifikasi teknis dan gambar,serta daftar Kuantitas dan harga dengan :
1. Nilai Penawaran Sebesar : Rp. 607,200,000.00 ( Enam Ratus Tujuh Juta Dua ratus Ribu Rupiah ) Termasuk Pajak Pertambahan Nilai ( PPN ); dan
Sesuai dengan persyaratan Dokumen Pengadaan, bersama Surat Penawaran inikami lampirkan:1. Hasil pemindaian (scan) Jaminan Penawaran asli;2. File/scan daftar kuantitas dan harga;3. Scan surat perjanjian kemitraan/kerja sama operasi (apabila ada);4. File/scan dokumen penawaran teknis yang terdiri dari:
a. Metode Pelaksanaan;b. Jadwal Waktu Pelaksanaan;c. Daftar Personil Intid. Daftar Peralatan Minimal; dan
5. Data kualifikasi (disikan pada SPSE);
Penawar,CV. MAKBUL
KOMAR RAHMAN,SHDIREKTUR
2. Jangka waktu pelaksanaan selama 180 (Seratus Delapan Puluh) hari kalender.
Penawaran ini berlaku selama 45 (Empat Puluh Lima) hari kalender sejak tanggal pembukaan penawaran.
6. [Dokumen lain yang dipersyaratkan seperti Formulir Pra RK3K, Daftar Barang yang diimpor, Analisa Teknis Satuan Pekerjaan, Analisa Harga Satuan Pekerjaan].
Dengan disampaikannya Surat Penawaran ini, maka kami menyatakan sanggup dan akan tunduk pada semua ketentuan yang tercantum dalam Dokumen Pengadaan.