DAFTAR REKAPITULASI BIAYA KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTOR PEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAK LOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010 No. MACAM PEKERJAAN I PEKERJAAN PERSIAPAN II PEKERJAAN TANAH DAN PASIR III PEKERJAAN PASANGAN IV PEKERJAAN BETON BERTULANG V PEKERJAAN PLESTERAN VI PEKERJAAN KAYU VII PEKERJAAN KONSTRUKSI ATAP, PENUTUP ATAP DAN PYAN VIII PEKERJAAN KERAMIK IX PEKERJAAN BESI DAN KACA X PEKERJAAN PENGGANTUNG DAN PENGUNCI XI PEKERJAAN SANITASI DAN SANITAIR XII PEKERJAAN LISTRIK XIII PEKERJAAN CAT-CATAN XIV PEKERJAAN LAIN-LAIN JUMLAH PPN 10 % JUMLAH TOTAL DIBULATKAN TERBILANG : SERATUS TIGA PULUH DUA JUTA TUJUH RATUS RIBU RUPIAH Yogyakarta, Ju CV. Agun Dire
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
DAFTAR REKAPITULASI BIAYA
KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTORPEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAKLOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010
No. MACAM PEKERJAAN JUMLAH TOTAL
( Rp. )
I PEKERJAAN PERSIAPAN 3,716,375.00 II PEKERJAAN TANAH DAN PASIR 1,019,374.22 III PEKERJAAN PASANGAN 19,096,316.74 IV PEKERJAAN BETON BERTULANG 15,985,698.34 V PEKERJAAN PLESTERAN 9,571,825.47 VI PEKERJAAN KAYU 32,780,929.11 VII PEKERJAAN KONSTRUKSI ATAP, PENUTUP ATAP DAN PYAN 15,085,280.90 VIII PEKERJAAN KERAMIK 8,632,717.18 IX PEKERJAAN BESI DAN KACA 1,059,328.00 X PEKERJAAN PENGGANTUNG DAN PENGUNCI 3,695,129.00 XI PEKERJAAN SANITASI DAN SANITAIR 6,550,996.40 XII PEKERJAAN LISTRIK 4,545,000.00 XIII PEKERJAAN CAT-CATAN 5,613,024.67 XIV PEKERJAAN LAIN-LAIN 250,000.00
JUMLAH 127,601,995.03
PPN 10 % 12,760,199.50
JUMLAH TOTAL 140,362,194.53
DIBULATKAN 140,362,000.00
TERBILANG : SERATUS TIGA PULUH DUA JUTA TUJUH RATUS RIBU RUPIAH
Yogyakarta, Juni 2010
CV. TRI GUNA
Agung Subroto, SE., MSi.Direktur
DAFTAR PERINCIAN BIAYA
KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTORPEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAKLOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010
No. MACAM PEKERJAAN VOLUME SAT. HARGA SAT. JML. HARGA TOTAL ( Rp. ) ( Rp. ) ( Rp. )
I PEKERJAAN PERSIAPAN1 Uitzet dan bouwplank 10.00 M' 34,855.00 348,550.00 2 Ijin Mendirikan Bangunan 1.00 Ls 500,000.00 500,000.00 3 Bongkar rangka atap lama 121.00 M2 8,825.00 1,067,825.00 4 Bongkar pasangan bata lama 1.00 Ls 1,800,000.00 1,800,000.00
3,716,375.00 II PEKERJAAN TANAH DAN PASIR1 Galian tanah pondasi 23.18 M3 13,520.00 313,447.68 2 Urugan tanah kembali 7.73 M3 6,482.00 50,092.90 3 Urugan tanah peninggian peil 6.94 M3 66,549.00 462,081.32 4 Urugan pasir bawah pondasi 2.79 M3 69,380.00 193,752.32
1,019,374.22 III PEKERJAAN PASANGAN 1 Pasangan pondasi batu kali menerus 1:3:10 28.23 M3 260,204.00 7,345,298.72
2 Pasangan bata merah trasram 1:2 35.32 M2 55,997.00 1,977,814.04 3 Pasangan bata merah (dinding & gunung-gunung) 1:3:10 223.49 M2 41,845.00 9,352,043.66 4 Roster beton uk . 25 x 15 28.00 bh 2,500.00 70,000.00 5 Pasangan batu tempel (batu candi) 2.56 M2 137,172.00 351,160.32
15,985,698.34 V PEKERJAAN PLESTERAN1 Plesteran bata merah (trasram) 1:2 70.64 M2 22,086.00 1,560,155.04 2 Plesteran bata merah (dinding & gunung-gunung) 1:3:10 410.98 M2 16,030.00 6,588,089.55 3 Sponengan sudut 1: 2 272.56 M' 5,223.00 1,423,580.88
9,571,825.47 VI PEKERJAAN KAYU1 Daun pintu panil kayu, ram kayu Bengkirai 3,5/12 9.80 M2 413,775.00 4,054,581.22 2 Daun pintu panil multiplek lps. Alm. foil, ram kayu Bk 3,5/12 1.44 M2 403,895.00 581,608.80 3 Daun Jendela, boven ram kayu Bengkirai 3,5/12 12.69 M2 418,020.00 5,304,673.80 4 Kusen pintu, jendela, 6/12 kayu Bengkirai baru 0.60 M3 8,732,400.00 5,249,290.15 5 Kusen pintu, jendela, 6/12 kayu Bengkirai lama 0.18 M3 932,400.00 170,718.71 6 Papan lisplank kayu Bengkirai baru 2/20 cm 43.46 M' 62,340.00 2,709,296.40 7 Papan lisplank Kayu lama 2/20 23.94 M' 11,940.00 285,843.60 8 Gording, murplat kayu Bengkirei 8/12 (baru) 0.12 M3 7,766,600.00 921,553.69 9 Gording, murplat kayu Bengkirei 8/12 lama 0.84 M3 616,600.00 514,984.32
5,613,024.67 XIV PEKERJAAN LAIN-LAIN1 Pembersihan Lokasi 1.00 Ls 250,000.00 250,000.00
250,000.00
DAFTAR HARGA SATUAN BAHAN
KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTORPEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAKLOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010
No. MACAM BAHAN SATUAN HARGA SATUAN
JENIS BATUAN, PC DAN TEGEL DLL1 Batu kali 1 M3 Rp. 65,000.00 2 Batu Bata Merah 1 Bh Rp. 250.00 3 Kerikil 1 M3 Rp. 85,000.00 4 Batu pecah (Split 2/3) 1 M3 Rp. 90,000.00 5 Pasir Pasang 1 M3 Rp. 72,000.00 6 Pasir Urug 1 M3 Rp. 50,000.00 7 Tanah Urug 1 M3 Rp. 45,000.00 8 Kapur Pasang 1 M3 Rp. 140,000.00 9 Portland Cemen (PC 40 Kg) 1 Zak Rp. 40,000.00 10 Portland Cemen (PC 50 Kg) 1 Zak Rp. 50,000.00 11 Portland Cemen Warna 1 Kg Rp. 2,000.00 12 Tegel Keramik 30/30 Sekualitas ' MULIA' 1 M2 Rp. 30,000.00 13 Tegel Keramik 20/20 ' MULIA' 1 M2 Rp. 31,000.00 14 Tegel Keramik 20/25 ' MULIA' 1 M2 Rp. 31,500.00 15 Batu tempel hitam (batu candi) 1 M2 Rp. 85,000.00 16 Buis beton diameter 80 cm x 0.5 m 1 Bh Rp. 38,000.00 17 Eternit t = 3 sekualitas "kerang super" 1 M2 Rp. 10,500.00 18 Roster beton uk 15 x 25 bh Rp. 2,500.00
JENIS BESI ATAU LOGAM DAN KACA1 Besi Beton Polos 1 Kg Rp. 8,000.00 2 Besi Beton Ulir 1 Kg Rp. 8,000.00 3 Besi strip 1 Kg Rp. 8,700.00 4 Bendrat (kawat beton) 1 Kg Rp. 12,000.00 5 Baut, mur 1 Kg Rp. 14,000.00 6 Paku Eternit 1 Kg Rp. 13,000.00 7 Paku reng 1 Kg Rp. 12,000.00 8 Paku 2" - 5" 1 Kg Rp. 12,000.00 9 Paku Skrup 1 Kg Rp. 13,500.00 10 Flin coat 1 Kg Rp. 16,500.00 11 Paku Asbes 1 Kg Rp. 13,500.00 12 Kaca Es 5 mm 1 M2 Rp. 65,000.00 13 Kaca Raiben 5 mm 1 M2 Rp. 70,000.00 14 Kaca Bening 5 mm 1 M2 Rp. 60,000.00 15 Seng BJLS 30 Lembaran, lebar = 60 cm 1 M' Rp. 21,000.00 16 Kitchen zink 1 unit Rp. 150,000.00
JENIS KAYU 1 Kayu Bengkirai Balok (6/12, 8/12, 8/14) 1 M3 Rp. 6,500,000.00 2 Kayu Bengkirai Papan (2/12, 2/15, 2/20, 2/25) 1 M3 Rp. 7,000,000.00 3 Kayu Kruing Balok (6/12, 8/12, 8/14) 1 M3 Rp. 4,250,000.00 4 Kayu Kruing usuk (4/6, 5/7) 1 M3 Rp. 4,250,000.00 5 Kayu Kruing usuk (4/6, 5/7) 1 M' Rp. 15,000.00 6 Kayu Bengkirai (pabrikan) Plepet 1 M' Rp. 2,500.00 7 Kayu Kruing Papan 1 M3 Rp. 4,700,000.00 8 Reng Bengkirai 1 M' Rp. 2,700.00 9 Kayu Papan Begisting (Sengon) 1 M3 Rp. 950,000.00 10 Kayu Steger (dolken / kaso) kayu glugu 1 Btg Rp. 18,000.00 11 Kayu Steger (dolken / kaso) kayu glugu 1 M3 Rp. 1,725,000.00 12 Multiplek 9 mm 1 Lbr Rp. 90,000.00 13 Multliplek 4 mm lapis aluminium foil 1 Lbr Rp. 65,000.00
JENIS PENUTUP ATAP 1 Genteng plentong Sekualitas Exs Godean 1 Bh Rp. 600.00 2 Genteng bubungan Sekualitas Exs Godean 1 Bh Rp. 2,000.00 3 Asbes gelombang kecil 200x1050x3 mm 1 Lbr Rp. 32,000.00 4 Bubungan asbes gelombang kecil 1 Lbr Rp. 25,000.00
No. MACAM BAHAN SATUAN HARGA SATUAN
JENIS CAT1 Cat Kayu Produk "EMCO LUX" 1 Kg Rp. 36,000.00 2 Cat Tembok Produk "CATYLAC" 1 Kg Rp. 11,000.00 3 Cat Tembok Produk "MAXILITE" 1 Kg Rp. 10,500.00 4 Minyak Bekisting 1 Kg Rp. 6,000.00 5 Meni besi 1 Ltr Rp. 13,500.00 6 Meni Kayu 1 Kg Rp. 13,000.00 7 Plamur 1 Kg Rp. 13,000.00
KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTORPEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAKLOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010
No. KETERANGAN WAKTU HARGA SATUAN
1 Tenaga / pekerja 1 Hari Rp. 30,000.00 2 Mandor 1 Hari Rp. 38,000.00 3 Tukang Batu 1 Hari Rp. 36,000.00 4 Tukang Kayu 1 Hari Rp. 37,000.00 5 Tukang Besi 1 Hari Rp. 36,000.00 6 Tukang Cat 1 Hari Rp. 35,500.00 7 Kepala Tukang 1 Hari Rp. 37,500.00 8 Penjaga Malam 1 Hari Rp. 27,500.00
DAFTAR HARGA SATUAN UPAH
Luas Pintu Luas Pintu Luas PintuP1 P2 P3
3.66 1.94 1.72
Luas Jendela Luas Jendela Luas BV Luas BVJ1 J2 1 2
yogyakarta …,…2010 yogyakarta …,…2010 yogyakarta …,…2010petugas lapangan Cc Cc
jefri yayan mulyana indra wahyudi
DAFTAR ANALISA BIAYA PEKERJAAN
KEGIATAN : REHABILITASI BERAT/SEDANG GEDUNG KANTORPEKERJAAN : REHABILITASI BERAT/SEDANG PUSKESMAS NGEMPLAKLOKASI : KABUPATEN SLEMAN Th. ANGGARAN : 2010
1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK1 Kayu 5/7 0.0120 M3 1,725,000.00 20,700.002 Paku biasa 2" - 5" 0.0200 Kg 12,000.00 240.003 Kayu papan 3 /20 0.0070 M3 950,000.00 6,650.00
Tukang Kayu 0.1000 Oh 37,000.00 3,700.00 Pekerja 0.1000 Oh 30,000.00 3,000.00 Kepala tukang 0.0100 Oh 37,500.00 375.00 Mandor 0.0050 Oh 38,000.00 190.00 Jumlah 34,855.00 Dibulatkan 34,855.00
M2 MEMBONGKAR ATAP, USUK / RENG DIPAKAI LAGI1 Tukang kayu 0.0600 Oh 37,000.00 2,220.002 Kepala tukang 0.0060 Oh 37,500.00 225.003 Pekerja 0.2000 Oh 30,000.00 6,000.004 Mandor 0.0100 Oh 38,000.00 380.00
Jumlah 8,825.00 Dibulatkan 8,825.00
1 M3 GALIAN TANAH BIASA SEDALAM 1 M1 Pekerja 0.4000 Oh 30,000.00 12,000.002 Mandor 0.0400 Oh 38,000.00 1,520.00
1M3 PASANGAN PONDASI BATU KALI ( 1Pc:3Kp:10Ps )1 PC ( 40 Kg ) 61.0000 Kg 1,000.00 61,000.002 Kapur pasang 0.1470 M3 140,000.00 20,580.003 Pasir pasang 0.4920 M3 72,000.00 35,424.004 Batu belah 15/20 1.1000 M3 65,000.00 71,500.00
Tukang Batu 0.6000 Oh 36,000.00 21,600.00 Kepala Tukang 0.0600 Oh 37,500.00 2,250.00 Pekerja 1.5000 Oh 30,000.00 45,000.00 Mandor 0.0750 Oh 38,000.00 2,850.00 Jumlah 260,204.00 Dibulatkan 260,204.00
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA ( 1Pc:2Ps)1 PC ( 40 Kg ) 18.9500 Kg 1,000.00 18,950.002 Pasir pasang 0.0380 M3 72,000.00 2,736.003 Bata merah 5x11x22 cm 70.0000 Bh 250.00 17,500.00
Tukang Batu 0.1000 Oh 36,000.00 3,600.00 Kepala Tukang 0.0100 Oh 37,500.00 375.00 Pekerja 0.3200 Oh 30,000.00 9,600.00 Mandor 0.0150 Oh 38,000.00 570.00 Jumlah 53,331.00 Jasa Pemborong 5 % 2,666.55 Total 55,997.55 Dibulatkan 55,997.00
1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA ( 1pC:3kP:10 Ps)1 PC ( 40 Kg ) 4.5000 Kg 1,000.00 4,500.002 Pasir pasang 0.0500 M3 72,000.00 3,600.003 Kapur pasang 0.0150 M3 140,000.00 2,100.004 Bata merah 5x11x22 cm 70.0000 Bh 250.00 17,500.00
Tukang Batu 0.1000 Oh 36,000.00 3,600.00 Kepala Tukang 0.0100 Oh 37,500.00 375.00 Pekerja 0.3200 Oh 30,000.00 9,600.00 Mandor 0.0150 Oh 38,000.00 570.00 Jumlah 41,845.00 Dibulatkan 41,845.00
1 M2 PLESTERAN (1Pc:2Ps), TEBAL 15 MM1 PC ( 40 Kg ) 8.5200 Kg 1,000.00 8,520.002 Pasir pasang 0.0170 M3 72,000.00 1,224.00
Tukang Batu 0.1500 Oh 36,000.00 5,400.00 Kepala Tukang 0.0150 Oh 37,500.00 562.50 Pekerja 0.2000 Oh 30,000.00 6,000.00 Mandor 0.0100 Oh 38,000.00 380.00 Jumlah 22,086.50 Dibulatkan 22,086.00
1 M2 PLESTERAN (1Pc:3Ps), TEBAL 15 MM1 PC ( 40 Kg ) 6.4800 Kg 1,000.00 6,480.002 Pasir pasang 0.0190 M3 72,000.00 1,368.00
Tukang Batu 0.1500 Oh 36,000.00 5,400.00 Kepala Tukang 0.0150 Oh 37,500.00 562.50 Pekerja 0.2000 Oh 30,000.00 6,000.00 Mandor 0.0100 Oh 38,000.00 380.00 Jumlah 20,190.50 Dibulatkan 20,190.00
1 M2 PLESTERAN (1Pc:3Kp:10Ps), TEBAL 15 MM1 PC ( 40 Kg ) 1.8400 Kg 1,000.00 1,840.002 Pasir pasang 0.0140 M3 72,000.00 1,008.003 Kapur Pasang 0.0060 M3 140,000.00 840.00
Tukang Batu 0.1500 Oh 36,000.00 5,400.00 Kepala Tukang 0.0150 Oh 37,500.00 562.50
1M2 PASANG RANGKA LANGIT-LANGIT (1 X 1) M, KAYU BORNEO1 Kayu borneo (Kruing) 0.0120 M3 4,250,000.00 51,000.002 Paku biasa 2"- 5" 0.1000 Kg 12,000.00 1,200.00
Tukang Kayu 0.2500 Oh 37,000.00 9,250.00 Kepala Tukang 0.0250 Oh 37,500.00 937.50 Pekerja 0.1500 Oh 30,000.00 4,500.00 Mandor 0.0750 Oh 38,000.00 2,850.00 Jumlah 69,737.50 Dibulatkan 69,737.00
1M2 PASANG RANGKA LANGIT-LANGIT (1 X 1) M, KAYU BORNEO LAMA1 Paku biasa 2"- 5" 0.1000 Kg 12,000.00 1,200.002 Plepet Kamper 1/3 cm ( Pabrikan ) 3.0000 M' 2,500.00
Tukang Kayu 0.2500 Oh 37,000.00 9,250.00 Kepala Tukang 0.0250 Oh 37,500.00 937.50 Pekerja 0.1500 Oh 30,000.00 4,500.00 Mandor 0.0750 Oh 38,000.00 2,850.00 Jumlah 18,737.50 Jasa Pemborong 5 % 936.88 Total 19,674.38 Dibulatkan 19,674.00
1M' PASANG LISPLANK UKURAN (2 X 20) CM, KAYU BORNEO1 Kayu borneo (Bengkirai) 0.0072 M3 7,000,000.00 50,400.002 Paku biasa 2"- 5" 0.0500 Kg 12,000.00 600.00
Tukang Kayu 0.2000 Oh 37,000.00 7,400.00 Kepala Tukang 0.0200 Oh 37,500.00 750.00 Pekerja 0.1000 Oh 30,000.00 3,000.00 Mandor 0.0050 Oh 38,000.00 190.00 Jumlah 62,340.00 Dibulatkan 62,340.00
1M' PASANG LISPLANK UKURAN (2 X 20) CM, KAYU BORNEO LAMA1 Paku biasa 2"- 5" 0.0500 Kg 12,000.00 600.00
Tukang Kayu 0.2000 Oh 37,000.00 7,400.00 Kepala Tukang 0.0200 Oh 37,500.00 750.00 Pekerja 0.1000 Oh 30,000.00 3,000.00 Mandor 0.0050 Oh 38,000.00 190.00 Jumlah 11,940.00 Dibulatkan 11,940.00
1M2 PENGECATAN BIDANG KAYU BARU(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
1 Cat dasar 0.1700 Kg 36,000.00 6,120.002 Cat penutup 2X 0.2600 Kg 36,000.00 9,360.003 Cat meni 0.2000 Kg 13,000.00 2,600.004 Plamir kayu 0.1500 Kg 13,000.00 1,950.00
1 M' PASANG LISPLANG UKURAN (2X20) CM, KAYU BORNEO1 Kayu Bengkirai, papan 0.0072 M3 7,000,000.00 50,400.002 Paku biasa 2" - 5" 0.0500 Kg 12,000.00 600.00
1M' PASANG TALANG MIRING, SENG BJLS 28, PAPAN KAYU KRUING Seng plat 0.5000 Lbr 21,000.00 10,500.00 Paku Biasa 1/2" - 1" 0.0150 Kg 12,000.00 180.00 Kayu Kruing papan 0.0190 M3 4,700,000.00 89,300.00 Flin coat 0.3000 Kg 16,500.00 4,950.00
Tukang Kayu 0.4000 Oh 37,000.00 14,800.00 Kepala Tukang 0.0250 Oh 37,500.00 937.50 Pekerja 0.0400 Oh 30,000.00 1,200.00 Mandor 0.0013 Oh 38,000.00 49.40 Jumlah 121,916.90 Dibulatkan 121,916.00
MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1/2 " Pipa PVC 1.2000 M' 3,250.00 3,900.00 Perlengkapan 0.3500 Harga Pipa 3,250.00 1,137.50
Kepala Tukang 0.0060 Oh 37,500.00 225.00 Mandor 0.0018 Oh 38,000.00 68.40 Jumlah 8,570.90 Dibulatkan 8,570.00
MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3 " Pipa PVC 1.2000 M' 15,500.00 18,600.00 Perlengkapan 0.3500 Harga Pipa 15,500.00 5,425.00
Pekerja 0.0810 Oh 30,000.00 2,430.00 Tukang Batu 0.1350 Oh 36,000.00 4,860.00 Kepala Tukang 0.0135 Oh 37,500.00 506.25 Mandor 0.0041 Oh 38,000.00 155.80 Jumlah 31,977.05 Dibulatkan 31,977.00
MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 4 " Pipa PVC 1.2000 M' 21,500.00 25,800.00 Perlengkapan 0.3500 Harga Pipa 21,500.00 7,525.00
Pekerja 0.0810 Oh 30,000.00 2,430.00 Tukang Batu 0.1350 Oh 36,000.00 4,860.00 Kepala Tukang 0.0135 Oh 37,500.00 506.25 Mandor 0.0041 Oh 38,000.00 155.80 Jumlah 41,277.05 Dibulatkan 41,277.00
MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN1 Kloset Jongkok Porselen 1.000 Buah 85,000.00 85,000.00 2 Semen Portland 6.000 Kg 1,000.00 6,000.00 3 Pasir pasang 0.010 M3 72,000.00 720.00
Tukang Batu 1.500 Oh 36,000.00 54,000.00 Kepala Tukang 1.500 Oh 37,500.00 56,250.00 Pekerja 1.000 Oh 30,000.00 30,000.00 Mandor 0.160 Oh 38,000.00 6,080.00 Jumlah 238,050.00 Dibulatkan 238,050.00
MEMASANG 1 BUAH KRAN AIR BIASA1 Kran air 1.000 Buah 15,000.00 15,000.00 2 Seal tape 0.025 Bh 1,500.00 37.50
Tukang Batu 0.100 Oh 36,000.00 3,600.00 Kepala Tukang 0.010 Oh 37,500.00 375.00 Pekerja 0.010 Oh 30,000.00 300.00 Mandor 0.005 Oh 38,000.00 190.00 Jumlah 19,502.50 Dibulatkan 19,502.00
PEKERJAAN PASANG 1 BUAH FLOORDRAIN1 Floordrain 1.0000 Bh 15,000.00 15,000.00
Tukang Batu 0.100 Oh 36,000.00 3,600.00 Kepala Tukang 0.010 Oh 37,500.00 375.00 Pekerja 0.010 Oh 30,000.00 300.00 Mandor 0.005 Oh 38,000.00 190.00 Jumlah 19,465.00 Dibulatkan 19,465.00
PEKERJAAN PASANG 1 BUAH WASTAFEL1 Wastafel 1.0000 Bh 700,000.00 700,000.00
Tukang Batu 1.450 Oh 36,000.00 52,200.00 Kepala Tukang 0.150 Oh 37,500.00 5,625.00 Pekerja 1.200 Oh 30,000.00 36,000.00 Mandor 0.100 Oh 38,000.00 3,800.00 Jumlah 797,625.00 Dibulatkan 797,625.00
MEMASANG 1 BUAH BAK KONTROL TERTUTUP UKURAN 40 X 40 X 40 CM1 Batu bata 56.0000 M2 250.00 14,000.00 2 Semen Portland 44.0000 Kg 1,000.00 44,000.00 3 Pasir pasang 0.0700 M3 72,000.00 5,040.00 4 Batu kerikil 0.0700 M3 85,000.00 5,950.00 5 Besi beton 1.6000 Kg 8,000.00 12,800.00
Tukang Batu 1.0150 Oh 36,000.00 36,540.00 Kepala Tukang 0.0015 Oh 37,500.00 56.25 Pekerja 1.2000 Oh 30,000.00 36,000.00 Mandor 0.0160 Oh 38,000.00 608.00 Jumlah 154,994.25 Dibulatkan 154,994.00
PEKERJAAN 1 M³ MEMBUAT BETON, Mutu Beton f'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, w/c = 0,581 Semen Portland 371.0000 Kg 1,000.00 371,000.00 2 Pasir pasang 0.4986 M3 72,000.00 35,899.20 3 Batu pecah (Split 2/3 cm) 0.7756 M3 90,000.00 69,804.00 4 Air 215.0000 lt 100.00 21,500.00
Tukang Batu 0.2750 Oh 36,000.00 9,900.00 Kepala Tukang 0.0280 Oh 37,500.00 1,050.00 Pekerja 1.6500 Oh 30,000.00 49,500.00 Mandor 0.0830 Oh 38,000.00 3,154.00 Jumlah 561,807.20 Dibulatkan 561,807.00
1Kg PEMBESIAN DENGAN BESI POLOS ATAU ULIR1 Besi beton (Polos / Ulir) 1.0500 Kg 8,000.00 8,400.00 2 Kawat beton (Bendrat) 0.0150 Kg 12,000.00 180.00
1M3 MEMBUAT BETON K 2501 PC ( 50 Kg ) 384.0000 Kg 1,000.00 384,000.00 2 Pasir pasang 0.4490 M3 72,000.00 32,328.00 3 Batu pecah (Split 2/3 cm) 0.7696 Kg 90,000.00 69,264.00
Tukang Batu 0.2750 Oh 36,000.00 9,900.00 Kepala Tukang 0.0280 Oh 37,500.00 1,050.00 Pekerja 1.6500 Oh 30,000.00 49,500.00 Mandor 0.0830 Oh 38,000.00 3,154.00 Jumlah 549,196.00 Jasa Pemborong 10 % 54,919.60 Total 604,115.60 Dibulatkan 604,115.00
1M2 PASANG BEKISTING (Untuk Pondasi)1 Kayu Kelas III 0.0400 M3 4,250,000.00 170,000.00 2 Paku 5 cm - 10 cm 0.3000 Kg 12,000.00 3,600.00 3 Minyak bekisting 0.1000 Lt 6,000.00 600.00
Tukang Kayu 0.2600 Oh 37,000.00 9,620.00 Kepala Tukang Kayu 0.0260 Oh 37,500.00 975.00 Pekerja 0.5200 Oh 30,000.00 15,600.00 Mandor 0.0260 Oh 38,000.00 988.00 Jumlah 201,383.00 Jasa Pemborong 10 % 20,138.30 Total 221,521.30 Dibulatkan 221,521.00
1M2 PASANG BEKISTING (Untuk Sloof)1 Kayu Kelas III 0.0450 M3 4,250,000.00 191,250.00 2 Paku 5 cm - 10 cm 0.3000 Kg 12,000.00 3,600.00 3 Minyak bekisting 0.1000 Lt 6,000.00 600.00
Tukang Kayu 0.2600 Oh 37,000.00 9,620.00 Kepala Tukang Kayu 0.0260 Oh 37,500.00 975.00 Pekerja 0.5200 Oh 30,000.00 15,600.00 Mandor 0.0260 Oh 38,000.00 988.00 Jumlah 222,633.00 Jasa Pemborong 10 % 22,263.30 Total 244,896.30 Dibulatkan 244,896.00
1M2 PASANG BEKISTING (Untuk Kolom)1 Kayu Kelas III 0.0400 M3 4,250,000.00 170,000.00 2 Paku 5 cm - 10 cm 0.4000 Kg 12,000.00 4,800.00 3 Minyak bekisting 0.2000 Lt 6,000.00 1,200.00 4 Balok Kayu Kelas II 0.0150 M3 4,700,000.00 70,500.00 5 Plywood 9 mm 0.3500 Lbr 90,000.00 31,500.00 6 Scafolding 1.0000 Unit 25,000.00 25,000.00
Tukang Kayu 0.3300 Oh 37,000.00 12,210.00 Kepala Tukang Kayu 0.0330 Oh 37,500.00 1,237.50 Pekerja 0.6600 Oh 30,000.00 19,800.00 Mandor 0.0330 Oh 38,000.00 1,254.00 Jumlah 337,501.50 Jasa Pemborong 10 % 33,750.15
Total 371,251.65 Dibulatkan 371,251.00
1M2 PASANG BEKISTING (Untuk Balok)1 Kayu Kelas III 0.0400 M3 4,250,000.00 170,000.00 2 Paku 5 cm - 10 cm 0.4000 Kg 12,000.00 4,800.00 3 Minyak bekisting 0.2000 Lt 6,000.00 1,200.00 4 Balok Kayu Kelas II 0.0180 M3 4,700,000.00 84,600.00 5 Plywood 9 mm 0.3500 Lbr 90,000.00 31,500.00 6 Scafolding 1.0000 Unit 25,000.00 25,000.00
Tukang Kayu 0.3300 Oh 37,000.00 12,210.00 Kepala Tukang Kayu 0.0330 Oh 37,500.00 1,237.50 Pekerja 0.6600 Oh 30,000.00 19,800.00 Mandor 0.0330 Oh 38,000.00 1,254.00 Jumlah 351,601.50 Jasa Pemborong 10 % 35,160.15 Total 386,761.65 Dibulatkan 386,761.00
1M2 PASANG BEKISTING (Untuk Lantai)1 Kayu Kelas III 0.0400 M3 4,250,000.00 170,000.00 2 Paku 5 cm - 10 cm 0.4000 Kg 12,000.00 4,800.00 3 Minyak bekisting 0.2000 Lt 6,000.00 1,200.00 4 Balok Kayu Kelas II 0.0150 M3 4,700,000.00 70,500.00 5 Plywood 9 mm 0.3500 Lbr 90,000.00 31,500.00 6 Scafolding 1.0000 Unit 25,000.00 25,000.00
Tukang Kayu 0.3300 Oh 37,000.00 12,210.00 Kepala Tukang Kayu 0.0330 Oh 37,500.00 1,237.50 Pekerja 0.6600 Oh 30,000.00 19,800.00 Mandor 0.0330 Oh 38,000.00 1,254.00 Jumlah 337,501.50 Jasa Pemborong 10 % 33,750.15 Total 371,251.65 Dibulatkan 371,251.00