Top Banner
Table of Contents Table of Contents 1 About the Quick Start Guide 65 Getting Started 67 From the taskbar Start button 67 From your PC desktop 67 Creating a New Project 68 Selecting the Project Properties 69 Entering Your Field Level Data 72 Creating a Production Profile 74 Setting the Design Flowrates 76 Setting the Number of Wells 77 Setting the Wellhead Conditions 78 Selecting a Concept - Offshore 79 Selecting a Concept - Onshore 80 Using the Field Development Schematic 82 Adjusting a Component 83 Inputs 83 Sub-components 84 Cost sheet 85 Calculating the Operating Costs 86 Scheduling the Capital Costs 87 Generating the Investment and Production Profile 88 Saving Your Project 89 Opening a Saved Project 89 About QUE$TOR 90 Capabilities 90 Cost Databases 90 Estimate Basis 92 Recommended System Specifications 93 1 QUE$TOR Help
1081

QUE$TOR manual

Sep 26, 2015

Download

Documents

Mhenna

This guide is designed to help you understand the operation of the QUE$TOR program,
outlining the basic steps involved in developing a QUE$TOR project to produce a
scheduled estimate for capital and operating costs.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Table of Contents

    Table of Contents 1

    About the Quick Start Guide 65

    Getting Started 67

    From the taskbar Start button 67

    From your PC desktop 67

    Creating a New Project 68

    Selecting the Project Properties 69

    Entering Your Field Level Data 72

    Creating a Production Profile 74

    Setting the Design Flowrates 76

    Setting the Number of Wells 77

    Setting the Wellhead Conditions 78

    Selecting a Concept - Offshore 79

    Selecting a Concept - Onshore 80

    Using the Field Development Schematic 82

    Adjusting a Component 83

    Inputs 83

    Sub-components 84

    Cost sheet 85

    Calculating the Operating Costs 86

    Scheduling the Capital Costs 87

    Generating the Investment and Production Profile 88

    Saving Your Project 89

    Opening a Saved Project 89

    About QUE$TOR 90

    Capabilities 90

    Cost Databases 90

    Estimate Basis 92

    Recommended System Specifications 93

    1

    QUE$TORHelp

  • Minimum system specifications: 93

    Before installing QUE$TOR 93

    Installation requirements 93

    Exporting to Microsoft Excel from QUE$TOR 94

    Contacting Customer Support 95

    Copyright 97

    QUE$TOR Structure 98

    Once on the FDS 99

    About Project Properties 100

    Units of Measure 101

    Main Product 101

    Location 101

    Creating Procurement Strategies 103

    About Field Level Data 105

    Field Characteristics 106

    Fluid / Profile Characteristics 108

    Liquid data 108

    Gas data @ STP 108

    Well data 109

    Miscellaneous 110

    Miscellaneous Items 110

    Temperature 110

    BOEEquivalents 111

    About Production Profiles 112

    Production Profile Edit 113

    Production Profile 114

    Design Flowrates 116

    Peak daily average production rates 116

    Design rates 116

    Water injection 117

    2

    QUE$TORHelp

  • Gas injection 117

    Number of Wells 118

    About the Concept Selector 119

    Concept Selection for New Projects 120

    Concept Selection for Existing Projects 121

    Field Development Schematic 123

    Topsides docking to substructures 124

    Pipelines, Power cables & linking components 124

    About Component Level Data 127

    Cost Summary Tree 127

    Component Toolbar 128

    Component Duplication 130

    Well and Flow Distribution 133

    Offshore Cost Centres 136

    Equipment Costs 136

    Materials Costs 137

    Fabrication Costs 137

    Installation Costs 138

    Hook-up and Commissioning (HUC) Costs 138

    Design and Project Management Costs 138

    Insurance and Certification costs 139

    Contingency 139

    About Offshore Components 140

    Cost Summary Tree 140

    Input Panel 141

    Cost Estimate Sheets 141

    About Topsides 142

    User Interface 143

    Inputs 143

    Facilities 144

    3

    QUE$TORHelp

  • Cost Estimate 145

    Primary Inputs 146

    Functions 146

    Capacities 147

    Configuration 149

    Substructure 149

    Include electrical buildings 150

    Deck 150

    Installation and HUC 151

    Product Export 152

    Gas Disposal / Export 153

    Design Conditions 154

    Reservoir Pressure 154

    Dry tree wellhead temperature 154

    Arrival temperature 154

    Acid Gas / High T / High P 155

    Maximum monthly average air temperature 155

    Facilities 156

    Manifolding 158

    Multiphase metering 158

    Operating pressures 159

    Design pressures 159

    Oil Processing 161

    Oil Export 166

    Pipeline Sizing 166

    Details 167

    Driver 167

    Derating Factor 167

    Capacity 168

    Driver Model 168

    4

    QUE$TORHelp

  • Pump Weight 168

    Pump Driver Weight 168

    Metering Capacity 168

    Metering Weight 168

    Gas Processing 169

    Cooling 170

    Acid Gas Removal 170

    Membrane Unit 170

    Conventional Acid Gas Removal 172

    Dehydration 173

    Dewpoint Control 175

    Stabiliser 176

    Metering 176

    Gas Compression 177

    Compressor Classification and Selection 177

    Flash gas 177

    Export gas 178

    Gas lift 178

    Gas injection 178

    Compressor Sizing 178

    Compressor type 178

    Number of stages 179

    Power 179

    Derated power 179

    Number of compressors 179

    Design duty/compressor 179

    Driver type 179

    Driver model 180

    Driver rating 180

    Pipeline Sizing 180

    5

    QUE$TORHelp

  • Coolers 181

    Weights 181

    Water Injection 182

    Details 183

    Driver 183

    Configuration 184

    Weight 184

    Custom Equipment 185

    General 187

    Bulk materials, utilities and operating weight 187

    Utilities 187

    Power 187

    Civils 187

    Cost sheet 187

    Example 188

    Cost sheet 189

    Custom equipment library 190

    190

    Control and Communications 191

    Monitoring and Control 191

    Telemetry System 192

    On-Platform Communications 192

    Off-Platform Communications 192

    Drilling Facilities 193

    Rig details 193

    Number of rigs 194

    Maximum measured depth 194

    Power 194

    Weights 194

    Quarters 196

    6

    QUE$TORHelp

  • Existing facilities 196

    Number of beds 197

    Cabin size 197

    Helideck 197

    Platforms with No Quarters 197

    Manning 198

    Process Utilities 199

    Process Support Utilities 200

    General Utilities 200

    Ancillaries 201

    Chemical Injection 202

    Flare 207

    Gas Design Capacity 207

    Flare Type 207

    Flare Tower Type 208

    Power 209

    Power Requirement 209

    Emergency Power 210

    Generation and distribution 211

    Distribution only 211

    Derating 211

    Capacity 211

    Driver 211

    Weights 212

    Electrical Buildings 213

    Equipment List 214

    Equipment Costs 216

    Freight 216

    Bulk Materials Costs 217

    Steel 217

    7

    QUE$TORHelp

  • Piping 217

    Electrical bulks 218

    Instrument bulks 218

    Others 218

    Freight 219

    Fabrication Costs 220

    Loadout and Seafasten 220

    Installation Costs 221

    Tugs Transport Spread 221

    Barge Transport Spread 221

    Installation Spread 221

    Hook-up and Commissioning Costs 223

    Atshore HUC 223

    Inshore HUC 223

    Offshore HUC 223

    HUC Accommodation (flotel) 224

    General Costs 225

    Design 225

    Project Management 225

    Certification 226

    Insurance 226

    Contingency 226

    Hints on Developing Topsides Projects 227

    Sour Gas Service 227

    Gas lift projects 228

    About Jackets 229

    Calibration of jacket weights 229

    Inputs 231

    Jacket Type 231

    Water Depth 231

    8

    QUE$TORHelp

  • Topsides Operating Weight 232

    Installation Method 232

    Jacket attachments 233

    Soil conditions 233

    Environmental conditions 233

    Regional jacket steel factor 234

    Materials Costs 235

    Jacket Steel 235

    Piles 235

    Conductors 235

    Anodes 235

    Installation aids 235

    Freight 236

    Fabrication Costs 237

    Loadout and Seafasten 237

    Installation Costs 238

    Tugs Transport Spread 238

    Barge Transport Spread 238

    Installation Spread 238

    General Costs 239

    Design 239

    Project Management 239

    Certification 240

    Insurance 240

    Contingency 240

    Lightweight Structures 241

    Guyed Caisson 241

    Braced Monotower 242

    Lightweight Jacket 242

    About Gravity Based Structures 243

    9

    QUE$TORHelp

  • Inputs 244

    GBS Type 244

    Water Depth 244

    Topsides Operating Weight 244

    Storage Capacity 244

    Inshore Deck Mating 244

    Conductors 245

    Materials Costs 246

    Concrete 246

    Steel 246

    Solid Ballast 246

    Mechanical Outfitting 247

    Conductors 247

    Freight 247

    Fabrication Costs 248

    GBS 248

    Mechanical Outfitting 248

    Installation Costs 249

    Deck Mating 249

    Deck / Shaft HUC 249

    Tow Out 249

    Installation 249

    General Costs 250

    Design 250

    Project Management 250

    Certification 251

    Insurance 251

    Contingency 251

    About Offshore Pipelines 252

    Pipeline Links 253

    10

    QUE$TORHelp

  • Length 253

    Water depth 254

    Flow type 254

    To / From 254

    Pipeline Sizing 256

    General 256

    Material 257

    Liquid / Oil / Methanol Flowrate 258

    Water Flowrate 258

    Gas Flowrate 258

    Pressure In 258

    Pressure Out 258

    Fluid Temperature 258

    Buckle Arrestors 258

    Nominal Diameter 259

    Corrosion Allowance 259

    Wall Thickness 259

    Pipeline Installation 260

    Lay Vessel 260

    Pipeline Crossings 261

    Buried Length 261

    Coating 261

    Weight Coat 261

    Cathodic Protection 262

    Insulation Material 262

    Insulation U-value 262

    Export End 263

    Termination details 263

    Pipeline end terminations (PLETs) 264

    Receiving End 265

    11

    QUE$TORHelp

  • Termination details 265

    Pipeline end terminations (PLETs) 266

    About Pipeline Terminations 267

    Riser - Steel Fixed 268

    Riser Linepipe 268

    Coating 268

    Insulation 268

    Anodes 268

    Clamps 269

    Spools, Flanges & Fittings 269

    Subsea Emergency Shutdown Valve Systems 269

    Riser - Steel Retrofit 270

    Riser Linepipe 270

    Coating 270

    Insulation 270

    Anodes 270

    Clamps 270

    Spools, Flanges & Fittings 271

    Subsea Emergency Shutdown Valve Systems 271

    Riser - Steel Catenary 272

    Riser Linepipe 272

    Coating 272

    Insulation 272

    Anodes 272

    Strakes 273

    Buoyancy 273

    Flex Joint 273

    Spools, Flanges & Fittings 273

    Subsea Emergency Shutdown Valve Systems 273

    Riser - Flexible Lazy S 274

    12

    QUE$TORHelp

  • Riser Linepipe 274

    Riser Arch Buoy System 274

    Spools, Flanges & Fittings 274

    Subsea Emergency Shutdown Valve Systems 274

    Riser - J-Tube 275

    Riser Linepipe 275

    Coating 275

    Insulation 275

    Anodes 275

    Clamps 276

    Spools, Flanges & Fittings 276

    Subsea Emergency Shutdown Valve Systems 276

    Riser - Top Tension 277

    Riser Linepipe 277

    Coating 277

    Insulation 277

    Anodes 277

    Tensioning Equipment 278

    Buoyancy Cans 278

    Lower Assembly 278

    Foundation 278

    Spools, Flanges & Fittings 278

    Subsea Emergency Shutdown Valve Systems 278

    Riser - Single Leg Hybrid 279

    Flexible Linepipe 279

    Rigid Linepipe 279

    Coating 279

    Insulation 280

    Anodes 280

    Upper Assembly 280

    13

    QUE$TORHelp

  • Buoyancy Cans 280

    Lower Assembly 280

    Foundation 280

    Spools, Flanges & Fittings 280

    Subsea Emergency Shutdown Valve Systems 280

    Pipeline Tie-In 282

    Pipeline Tie-In 282

    Spools, Flanges & Fittings 282

    Subsea Emergency Shutdown Valve Systems 282

    Shore Approach 284

    Shore Approach Materials 284

    Subsea Emergency Shutdown Valve Systems 284

    Pipeline End Terminations (PLETs) 285

    Structure 285

    Valve 285

    Protection Structure 285

    Mudmat 285

    Jumper 286

    Jumper Connectors 286

    Installation Durations 287

    Pipelay Spreads 287

    Diving Support Vessel 287

    Trench Vessel 288

    Survey Vessel 288

    Dredge Vessel 288

    Rock Install Vessel 288

    Materials Costs 289

    Linepipe 289

    Coating 289

    Weight Coating 289

    14

    QUE$TORHelp

  • Insulation 290

    Onshore Welding and Reeling 290

    Terminations 290

    PLETs 290

    Freight 290

    Installation Costs 291

    Pipelay Spreads 291

    Diving Support Vessel 291

    Testing & Commissioning Equipment 291

    Trench Vessel 291

    Survey Vessel 292

    Dredge Vessel 292

    Rock Install Vessel 292

    Shore Approach 292

    General Costs 293

    Design 293

    Project Management 293

    Certification 294

    Insurance 294

    Contingency 294

    About Offshore Power Cables 295

    Power Cable Links 296

    Water depth 296

    To / From 297

    Cable Sizing 298

    General 298

    Power 298

    Voltage 298

    Conductor Size 298

    Burial 298

    15

    QUE$TORHelp

  • Rock Installation 299

    Termination details 300

    Export End 300

    Receiving End 300

    Installation Durations 301

    Cable laying 301

    Survey Vessel 301

    Rock Install Vessel 301

    Materials Costs 302

    Cable 302

    Gravel 302

    Export End Riser 302

    Export End Connection System 302

    Receiving End Riser 302

    Receiving End Connection System 303

    Landfall System 303

    Freight 303

    Installation Costs 304

    Cable Lay Spread 304

    Rock Install Vessel 304

    Survey Vessel 304

    Testing & Commissioning Equipment 304

    Shore Approach 304

    General Costs 305

    Design 305

    Project Management 305

    Certification 306

    Insurance 306

    Contingency 306

    About Semi-submersibles 307

    16

    QUE$TORHelp

  • Primary Inputs 308

    Semi-submersible Type 308

    Semi-submersible Generation 309

    Topsides Operating Weight 309

    Water Depth 309

    Number of Risers 309

    Conversion Upgrades 309

    Length of Sea Trials 310

    Additional Load 310

    Buoyancy Aid 310

    Drilling Facilities 310

    Marine transport 311

    Mooring System 312

    Mooring Type 312

    Anchor Type 313

    Soil Condition 313

    Environmental Conditions 314

    Mooring Chain Size 314

    Number of Mooring Lines 315

    Chain Length 315

    Rope Length 315

    Wire Length 315

    Equipment Costs 316

    Vessel Purchase 316

    Anchors 316

    Materials Costs 317

    General Upgrade 317

    Marine Upgrade 317

    Drilling Upgrade 317

    Mooring Upgrade 317

    17

    QUE$TORHelp

  • Mooring Chain 317

    Mooring Wire 318

    Mooring Rope 318

    Mooring Terminations 318

    Buoyancy Aid 318

    Freight 319

    Fabrication Costs 320

    Strip Out 320

    General Upgrade 320

    Marine Upgrade 320

    Drilling Upgrade 320

    Mooring Upgrade 320

    Buoyancy Aid 320

    Installation Costs 321

    Transport from fabrication yard 321

    Mob / Demob and Tow out 321

    Installation 321

    Hook-up and Commissioning Costs 322

    Sea Trials and Marine Commissioning 322

    General Costs 323

    Design 323

    Project Management 323

    Certification 324

    Insurance 324

    Contingency 324

    About Spar Buoys 325

    Primary Inputs 326

    Spar Type 326

    Riser Wall Type 327

    Number of Platform Wells 327

    18

    QUE$TORHelp

  • Water Depth 327

    Distance to Installation Site 327

    Topsides Operating Weight 327

    Marine transport 327

    Mooring System 329

    Mooring Type 329

    Anchor Type 330

    Soil Condition 330

    Environmental Conditions 331

    Mooring Chain Size 331

    Number of Lines 332

    Chain Length 332

    Rope Length 332

    Wire Length 332

    Materials Costs 333

    Hull Structure 333

    Hull Outfitting and Marine Systems 334

    Mooring Chains 334

    Mooring Wire / Rope 334

    Mooring Terminations 334

    Anchors 334

    Riser Pipe (conductors) 334

    Riser Connectors and Buoyancy Cans 334

    Riser Components 335

    Fabrication Costs 336

    Hull Structure 336

    Hull Outfitting and Marine Systems 336

    Riser Pipe (conductors) 336

    Hull Joining 336

    Installation Costs 337

    19

    QUE$TORHelp

  • Transport from Fabrication Yard 337

    Transport to Installation Site 337

    Hull Installation Duration 337

    Anchor and Mooring Installation 337

    General Costs 339

    Design 339

    Project Management 339

    Certification 340

    Insurance 340

    Contingency 340

    About Tankers 341

    Primary Inputs 342

    Tanker Type 342

    Tanker Size 343

    Water Depth 343

    Production Rate 343

    Water Injection Rate 343

    Gas Export/Injection 343

    Days of Storage 343

    Number of Risers 343

    General Upgrade 343

    MarineUpgrade 344

    Tanker Strengthening 344

    Length of Sea Trials 344

    Mooring Option 344

    Added Production Facilities Weight 345

    Elevated Deck 345

    Gas Lift 345

    Marine transport 345

    Mooring System 346

    20

    QUE$TORHelp

  • Mooring Type 346

    Anchor Type 347

    Soil Condition 347

    Environmental Conditions 348

    Mooring Chain Size 348

    Number of Lines 349

    Chain Length 349

    Rope Length 349

    Wire Length 349

    Equipment Costs 350

    Vessel Purchase 350

    Swivels/Disconnect 350

    Anchors 351

    Materials Costs 352

    Tanker Strengthening 352

    Marine / Offloading 352

    General Upgrade 352

    Mooring Chain 352

    Mooring Wire / Rope 353

    Mooring Terminations 353

    Frame / Mooring Arm 353

    Turret / Riser 353

    Chain table / Buoy 353

    Riser Porch 353

    Elevated Deck 354

    Freight 354

    Fabrication Costs 355

    Tanker Strengthening 355

    Marine / Offloading 355

    General Upgrade 355

    21

    QUE$TORHelp

  • Turret 355

    Riser Porch 355

    Elevated Deck 355

    Installation Costs 357

    Transport from fabrication yard 357

    Mob / Demob and Tow out 357

    Installation 357

    Hook-up and Commissioning Costs 358

    Sea Trials and Marine Commissioning 358

    General Costs 359

    Design 359

    Project Management 359

    Certification 360

    Insurance 360

    Contingency 360

    About Cylindrical Hulls 361

    Primary Inputs 362

    Production Rate 362

    Days of Storage 362

    Required Storage 362

    Topsides Operating Weight 363

    Hull Weight 363

    Water Depth 363

    Distance to Installation Site 363

    Marine Transport 363

    Mooring System 364

    Mooring Type 364

    Anchor Type 365

    Soil Condition 365

    Environmental Conditions 366

    22

    QUE$TORHelp

  • Mooring Chain Size 366

    Number of Lines 367

    Chain Length 367

    Rope Length 367

    Wire Length 367

    Materials Costs 368

    Hull Structure 368

    Hull Outfitting and Marine Systems 368

    Mooring Chains 368

    Mooring Wire / Rope 368

    Mooring Terminations 368

    Anchors 369

    Freight 369

    Fabrication Costs 370

    Hull Structure 370

    Hull Outfitting and Marine Systems 370

    Installation Costs 371

    Transport from Fabrication Yard 371

    Transport to Installation Site 371

    Anchor and Mooring Installation 371

    General Costs 372

    Design 372

    Project Management 372

    Certification 373

    Insurance 373

    Contingency 373

    About Tension Leg Platforms 374

    Inputs 375

    TLP Type 375

    Topsides Operating Weight 375

    23

    QUE$TORHelp

  • Water Depth 376

    Number of Wells 376

    Number of Pre-installed Risers 376

    Soil Conditions 376

    Environmental Conditions 376

    Marine transport 377

    Materials Costs 378

    Hull 378

    Foundations 378

    Tendons 378

    Tendon Connectors 379

    Production Risers 379

    Tensioning Equipment 379

    Buoyancy 379

    Freight 379

    Fabrication Costs 380

    Installation Costs 381

    Transport from fabrication yard 381

    Foundation Install 381

    Transportation to installation site 381

    Tendon Install 381

    TLP Connect / Tension 381

    General Costs 382

    Design 382

    Project Management 382

    Certification 383

    Insurance 383

    Contingency 383

    About Offshore Loading 384

    Primary Inputs 385

    24

    QUE$TORHelp

  • 385

    Loading Type 385

    Water Depth 386

    Export Rate 386

    FlexiblePipeline 386

    Number of Lines & Diameter 386

    Riser Length at Buoy 386

    Water Depth at Topsides 386

    Riser Length at Topsides 387

    Storage Tanker 387

    Storage Time 387

    Storage Capacity 387

    Tanker Size 387

    Marine transport 387

    Mooring System 389

    Mooring Type 389

    Anchor Type 390

    Soil Condition 390

    Environmental Conditions 391

    Mooring Chain Size 391

    Number of Mooring Lines 392

    Chain Length 392

    Rope Length 392

    Wire Length 392

    Equipment Costs 393

    Loading Buoy 393

    Anchors 393

    Storage Tanker 393

    Materials Costs 394

    Mooring Chain 394

    25

    QUE$TORHelp

  • Mooring Wire / Rope 394

    Mooring Terminations 394

    Flexible Riser at Buoy 394

    Riser System at Buoy 395

    Pipeline (flexible) 395

    Riser at Platform 395

    Riser System at Platform 395

    Installation Costs 396

    Transport from fabrication yard 396

    Tow out and installation 396

    Sea trials and marine commissioning 396

    General Costs 397

    Design 397

    Project Management 397

    Certification 398

    Insurance 398

    Contingency 398

    About Offshore Drilling 399

    Inputs 400

    Rig 401

    Category 401

    Profile 402

    Well Details 402

    Drilling Details 403

    Water Depth 403

    Reservoir Depth 403

    Reservoir Pressure 403

    Pressure Rating 403

    Longest Stepout 403

    Trip Speed 404

    26

    QUE$TORHelp

  • Rate of Build 404

    Acid Gas 404

    Use ESPs 404

    Drilling Profiles 405

    Well Profile 406

    Horizontal Section 406

    Measured Depth and Deviation 408

    Drilling/Completion Rig 409

    Completion Type 409

    Drilling Durations 410

    Add Well / Remove Well 410

    Drilling Curves 411

    Rig class 411

    Profile 411

    Stage 411

    Equipment Costs 413

    Xmas trees 413

    Wellheads 413

    Completions 413

    Electronic submersible pumps (ESP) 414

    Exploration wellheads / Appraisal wellheads 414

    Materials Costs 415

    Drilling/Completion 415

    Conductors 415

    Drilling Template 416

    Installation Costs 417

    From Floating or Jackup 417

    From Platform 418

    Specialist Services 418

    Transport 418

    27

    QUE$TORHelp

  • Site Preparation 418

    General Costs 420

    Design 420

    Project Management 420

    Certification 421

    Insurance 421

    About Subsea 422

    Inputs 423

    Primary 425

    Wells and Flowrates 425

    Services 425

    Layout 427

    Item defaults 427

    Flowline defaults 427

    Features 429

    Design conditions 429

    HIPPS 430

    Features 430

    Tie-in Point 432

    Flowlines 433

    Lay Vessel 433

    Flowline Type 434

    Buried Lines 434

    Material by Fluid Type 434

    Thermal Insulation Material 435

    Thermal Insulation U-value 435

    PLET selection 436

    Umbilicals 437

    Control System 437

    Control Tube Material 437

    28

    QUE$TORHelp

  • Inhibitor Chemicals 437

    Power Cables 437

    Installation 439

    Subsea Configuration 441

    Item and Link Names 442

    Item and Link Duplication 442

    Subsea Items 446

    General 446

    Well details 447

    Services 447

    Multiphase metering 447

    Umbilical Terminations 448

    Subsea Flowlines 449

    General 449

    Well / Tie-back ends 449

    Total flowrates 449

    Flowline sizing 450

    Coating and insulation 451

    Well end termination / Tie-back end termination 452

    Umbilicals 452

    Subsea Tie-back 453

    Tie-back type 453

    Water Depth 453

    Termination type 453

    Sub-type 453

    Riser Systems 454

    Riser Length 454

    Equipment Costs 455

    Intervention Tools 455

    Platform Controls Main 455

    29

    QUE$TORHelp

  • Platform Controls Additional 455

    Freight 455

    Detailed Item Cost Breakdown 455

    Main Structure 456

    Xmas trees 456

    Manifolding (Piping & Valves) 457

    Multiphase metering 457

    457

    Flowline Connectors/Pull-In 457

    457

    Cluster Satellites 457

    458

    Control and Testing 458

    HIPPS 458

    Materials Costs 459

    Riser Systems 459

    Links 459

    Umbilicals 460

    Risers 461

    Installation Costs 462

    General Costs 463

    Design 463

    Project Management 463

    Certification 464

    Insurance 464

    Contingency 464

    About Barges 465

    Developments with Barges 465

    Primary Inputs 466

    Storage Required 466

    30

    QUE$TORHelp

  • Production Rate 466

    Topside Operating Weight 466

    Barge Size 466

    Water Depth 467

    Marine transport 467

    Mooring System 468

    Mooring Type 468

    Anchor Type 469

    Soil Condition 470

    Environmental Conditions 470

    Mooring Chain Size 470

    Number of Lines 471

    Chain Length 471

    Rope Length 471

    Wire Length 471

    Equipment Costs 472

    Barge Cost 472

    Anchors 472

    Materials Costs 473

    Mooring Chain 473

    Mooring Wire/Rope 473

    Mooring Terminations 473

    Freight 473

    Installation Costs 474

    Transport from fabrication yard 474

    Tow Out and Installation 474

    Sea Trials and Marine Commissioning 474

    General Costs 475

    Design 475

    Project Management 475

    31

    QUE$TORHelp

  • Certification 476

    Insurance 476

    Contingency 476

    About Bridge Links 477

    Inputs 478

    Functions 478

    Details 478

    Process 479

    Flow Type 479

    Flowrates 480

    Pressure 480

    Diameter 480

    Materials Costs 481

    Primary Steel 481

    Secondary Steel 481

    Piping 481

    Electrical Bulks 481

    Instrument Bulks 482

    Others 482

    Freight 482

    Fabrication Costs 483

    Loadout and Seafasten 483

    Installation Costs 484

    Tugs Transport Spread 484

    Barge Transport Spread 484

    Installation Spread 484

    General Costs 485

    Design 485

    Project Management 485

    Certification 486

    32

    QUE$TORHelp

  • Insurance 486

    Contingency 486

    About User Defined 487

    Cost Estimate 488

    Operating Expenditure - OPEX 489

    Working with OPEX 490

    Locking/Unlocking 491

    Applying a Change to a Range of Cells 492

    Operating Personnel 494

    Inspection and Maintenance 495

    Platforms 495

    Pipelines 496

    Power Cables 496

    Subsea 497

    Logistics and Consumables 498

    Helicopters 498

    Supply Boats 498

    Rescue and Recovery Boat 498

    Fuel Gas 498

    Diesel 499

    Chemicals 499

    Well Costs 500

    Insurance 501

    Field / Project Costs 502

    Tariffs 503

    CO2 Emission Taxes 504

    Leases 505

    Capital Expenditure Scheduling 506

    CAPEX Scheduling Window 507

    Distributions 508

    33

    QUE$TORHelp

  • Intra-component Relationships 509

    Inter-component Relationships 510

    Locking 510

    First Oil 510

    Timescale 511

    Adding and Removing Components 511

    CAPEX Breakdown Graphs 512

    About Decommissioning 513

    Decommissioning Scenarios 514

    Decommissioning duration 514

    Delay after end of field life 514

    Component Decommissioning 515

    Cost estimate 515

    Scrap 515

    Inputs 516

    Distance to Disposal Site 516

    Temporary Piping Weight 516

    Padeyes Weight 516

    Crane Size 516

    Maximum Lift Weight 517

    Number of Lifts 517

    Weights 518

    Hazardous Volumes 519

    Flushing / Inerting 520

    Flushing Days 520

    Inerting Days 520

    Dismantle / Removal 521

    Cost Sheet 522

    Materials 522

    Fabrication 523

    34

    QUE$TORHelp

  • Decommissioning / removal 523

    Design and Project management 524

    Insurance 524

    Certification 524

    Contingency 525

    Scrap 525

    Inputs 526

    Removal 526

    Disposal 526

    Lifts 527

    Details 528

    Jacket 528

    Attachments 528

    Cost Sheet 529

    Materials 529

    Fabrication 530

    Decommissioning / removal 530

    Design and Project Management 531

    Insurance 531

    Certification 531

    Contingency 531

    Scrap 532

    Pipeline Decommissioning 533

    Removal 533

    Disposal 533

    Cleaning 534

    Details 535

    Pipeline Decommissioning Cost Sheet 536

    Decommissioning / Removal 536

    Design and Project Management 537

    35

    QUE$TORHelp

  • Insurance 538

    Certification 538

    Contingency 538

    Scrap 538

    About the Investment and Production Profile 539

    Exporting the Investment Profile into AS$ET 541

    QUE$TOR Structure 542

    Once on the FDS 543

    About Project Properties 544

    Units of Measure 545

    Main Product 545

    Location 545

    Creating Procurement Strategies 547

    To create a new procurement strategy 547

    About Field Level Data 549

    Field Characteristics 550

    Fluid / Profile Characteristics 552

    Liquid Data 552

    Gas Data @ STP 552

    Well Data 553

    Miscellaneous 554

    Miscellaneous Items 554

    Layout 554

    Artificial Lift 555

    Temperature 555

    BOEEquivalents 555

    About Production Profiles 556

    Production Profile Edit 557

    Production Profile 558

    Design Flowrates 560

    36

    QUE$TORHelp

  • Peak daily average production rates 560

    Design rates 560

    Water injection 561

    Gas injection 561

    Gas lift 561

    Number of Wells 562

    Wellhead Conditions 563

    About the Concept Selector 564

    Concept Selection for New Projects 565

    Concept Selection for Existing Projects 567

    Field Development Schematic 569

    Pipelines & Linking Components 570

    About Component Level Data 572

    Cost Summary Tree 572

    Component Toolbar 574

    Component Duplication 576

    Well and Flow Distribution 579

    Onshore Cost Centres 581

    Equipment Costs 581

    Materials Costs 581

    Prefabrication Costs 583

    Construction Costs 583

    Design and Project Management Costs 584

    Insurance and Certification Costs 585

    Contingency 585

    About Onshore Components 586

    Cost Summary Tree 586

    Input Panel 586

    Cost Estimate Sheets 587

    About Production Facilities 588

    37

    QUE$TORHelp

  • User Interface 589

    Inputs 589

    Facilities 590

    Cost Estimate 591

    Primary Inputs 592

    Terrain 592

    Elevation 592

    Functions 592

    Capacities 593

    Fluid Capacities 594

    Inlet High Pressure Fluids 594

    Arrival Temperature 594

    Arrival Pressure 594

    Well Stream Fluids 594

    Separated Fluids 595

    Inlet Medium Pressure Fluids 595

    Total Capacities 595

    Design Conditions 596

    Reservoir Pressure 596

    Acid gas / High T / High P 596

    Max. Ambient Air Temperature 596

    Prefabrication 597

    Winterisation 598

    598

    Manifolding 599

    Number of Flowlines 599

    Multiphase metering 599

    Operating Pressure 600

    Design Pressure 600

    Weight 600

    38

    QUE$TORHelp

  • Oil Processing 602

    Oil Processing Configurations 602

    Stream Properties 603

    Equipment Sizing 604

    Gas Processing 607

    Cooling 608

    Acid Gas Removal 608

    Membrane Unit 608

    Conventional Acid Gas Removal 609

    Sulphur 611

    Dehydration 612

    Dewpoint Control 613

    Gas Metering 614

    Deethaniser 614

    Stabiliser 614

    Produced Water 616

    Product Storage 617

    Atmospheric Storage Inputs 617

    Pressurised Storage Inputs 618

    Product Export 620

    Export Rate 620

    Size Export Pipeline 621

    Details 621

    Driver 622

    Derating Factor 622

    Capacity 622

    Driver Model 622

    Pump Weight 623

    Pump Driver Weight 623

    Metering Capacity 623

    39

    QUE$TORHelp

  • Metering Weight 623

    Gas Compression 624

    Compressor Classification and Selection 624

    Flash gas 624

    Export gas 625

    Gas lift 625

    Gas injection 625

    Compressor Sizing 625

    Compressor type 625

    Number of stages 626

    Power 626

    Derated power 626

    Number of compressors 626

    Design duty/compressor 626

    Driver type 626

    Driver model 627

    Driver rating 627

    Pipeline Sizing 627

    Coolers 628

    Weights 628

    Water Injection 629

    Details 629

    Driver 630

    Configuration 631

    Weight 631

    Custom Equipment 632

    General 634

    Bulk materials, utilities and operating weight 634

    Utilities 634

    Power 634

    40

    QUE$TORHelp

  • Civils 634

    Cost sheet 635

    Example 635

    Cost sheet 636

    Custom equipment library 637

    637

    Control and Communications 638

    Control System 638

    Communications 638

    Process Utilities 640

    Process Support Utilities 640

    General Utilities 641

    Power 643

    Power Requirement 643

    Emergency Power 644

    Generation and Distribution / Distribution only Radio Buttons 644

    Derating Factor 644

    Capacity 645

    Driver 645

    Weights 646

    Civils 647

    Foundation Area 647

    Plot Area 648

    Equipment List 649

    Equipment Costs 651

    Freight 651

    Material Costs 652

    Steelwork 652

    Piping 652

    Electrical 652

    41

    QUE$TORHelp

  • Instruments 653

    Others 653

    Civils Materials 653

    Freight 653

    Prefabrication Costs 654

    Loadout and Transport 654

    Construction Costs 655

    Site Preparation 655

    Civil Construction 655

    General Costs 656

    Design & Project Management 656

    Insurance 657

    Certification 657

    Contingency 657

    About Terminal Facilities 658

    User Interface 659

    Inputs 659

    Facilities 660

    Cost estimate 660

    Primary Inputs 661

    Location 661

    Inlet Flows 661

    Export Method 662

    Marine Transport 662

    Prefabrication 663

    Winterisation 664

    Product Storage 665

    Atmospheric Storage Inputs 665

    Pressurised Storage Inputs 666

    Product Export 668

    42

    QUE$TORHelp

  • Export Rate 668

    Size Export Pipeline 668

    Details 669

    Driver 669

    Derating Factor 669

    Capacity 669

    Driver Model 670

    Pump Weight 670

    Pump Driver Weight 670

    Metering Capacity 670

    Metering Weight 670

    Control and Communications 671

    Control System 671

    Communications 671

    Process Utilities 673

    Process Support Utilities 673

    General Utilities 674

    Power 675

    Generation and Distribution / Distribution only Radio Buttons 675

    Power Requirement 676

    Emergency Power 676

    Derating Factor 676

    Duty 676

    Driver 677

    Weights 677

    Civils 679

    Foundation Area 679

    Plot Area 680

    Equipment Costs 681

    Product Loading 681

    43

    QUE$TORHelp

  • Safety 682

    Freight 682

    Material Costs 683

    Steelwork 683

    Piping 683

    Electrical 683

    Instruments 684

    Others 684

    Offloading Buoy (marine) 684

    Offloading Pipeline 684

    Jetty Materials 684

    Civils Materials 684

    Freight 684

    Prefabrication Costs 685

    Loadout and Transport 685

    Construction Costs 686

    Site Preparation 686

    Civil Construction 686

    Buoy Installation 686

    Pipeline Installation 686

    Jetty Construction 687

    General Costs 688

    Design & Project Management 688

    Insurance 689

    Certification 689

    Contingency 689

    About Onshore Pipelines 690

    Pipeline Links 691

    Length 691

    Flow Type 691

    44

    QUE$TORHelp

  • To / From 692

    Pipeline Sizing 694

    For oil, gas, liquid & two phase lines 695

    For gas injection, gas lift and water injection lines 695

    Material 695

    Oil / Gasoline/Condensate / NGL / LPG 696

    Water Flowrate 696

    Gas Flowrate 696

    Fluid Temperature 696

    Pipeline Sections 697

    Nominal Diameter 697

    Fixed Diameter 697

    Corrosion Allowance 697

    Wall Thickness 697

    Slug Catchers 699

    Winterisation 700

    Pipeline winterisation 700

    Booster station winterisation 700

    Pipeline Sections 701

    Pipeline Sections 702

    Booster / Reducer Stations 703

    Booster / Reducer Stations 705

    Product Export / Gas Compression 705

    Control and Communications 707

    Utilities 708

    Power 709

    Generation and Distribution / Distribution only Radio Buttons 710

    Power Requirements 710

    Emergency Power 710

    Derating Factor 711

    45

    QUE$TORHelp

  • Duty 711

    Driver 711

    Weights 712

    Civils 712

    Terrain and Crossings 714

    Terrain Type 714

    Construction Type 714

    Length 714

    Number of Crossings 714

    Construction Duration 715

    Pipeline Schematic 716

    Construction Duration 717

    Equipment Costs 718

    Booster Stations 718

    Reducer Stations 719

    Slug Catchers 719

    Freight 719

    Materials Costs 720

    Linepipe 720

    Fittings 720

    Coatings 720

    Crossings 720

    Civils Materials 721

    Booster Stations 721

    Slug Catchers 722

    Freight 723

    Construction Costs 724

    Booster Stations 724

    Slug Catchers 725

    General Costs 726

    46

    QUE$TORHelp

  • Design & Project Management 726

    Insurance 727

    Certification 727

    Contingency 727

    About Wellpad Groups 728

    User Interface 729

    Inputs 729

    Primary Inputs 731

    Location 731

    Wells 731

    Prefabrication 733

    Winterisation 734

    Wellpad Editor 735

    Wellpad Editor Primary Inputs 737

    Linkages 737

    Equipment 737

    Multiphase meters 737

    Power Requirements 738

    Well Count 738

    Wellpad Editor Flowline Bundle 739

    Bundle 739

    Flowlines 740

    Construction 740

    Number of Crossings 741

    Wellpad Editor - Details 742

    Manifolding and Equipment 742

    Utilities 742

    Power 742

    Flowlines 743

    Flowline 743

    47

    QUE$TORHelp

  • Installation 744

    Control System 745

    Civils 746

    Equipment Costs 747

    Manifolding 747

    Multiphase Metering 747

    Freight 747

    Materials Costs 749

    Steelwork 749

    Piping 749

    Electrical 749

    Instruments 750

    Others 750

    Flowlines 750

    Umbilical 750

    Power Cable 750

    Crossings 750

    Civils Materials 750

    Freight 751

    Prefabrication Costs 752

    Loadout and Transport 752

    Construction Costs 753

    Site Preparation 753

    Civil Construction 753

    Flowline Testing 753

    Flowline Right of Way 753

    General Costs 755

    Design & Project Management 755

    Insurance 756

    Certification 756

    48

    QUE$TORHelp

  • Contingency 756

    About Onshore Drilling 757

    User Interface 758

    Inputs 758

    Details 760

    Rig Class 760

    Well Type 761

    Pumped Wells 761

    Profile 762

    Well Details 762

    Drilling Details 763

    Winterisation 765

    Winterisation Cost 765

    Drilling Profiles 766

    Well Type 767

    TVD 768

    Kick Off 768

    Horizontal Shift 768

    Profile Type 768

    Horizontal Section 768

    Measured Depth 770

    Maximum Deviation 771

    Drilling Rig 771

    Completion Rig 771

    Completion Type 771

    Drilling Durations 772

    772

    Drilling Curves 773

    Rig class 773

    Profile 773

    49

    QUE$TORHelp

  • Stage 774

    Equipment Costs 776

    Xmas trees 776

    Wellheads 776

    Completions 776

    Exploration wellheads / Appraisal wellheads 777

    Pumps 777

    Freight 777

    Material Costs 778

    Cement 778

    Mud 778

    Brine 778

    Bits 779

    Freight 779

    Construction Costs 780

    Rig Hire 780

    Drill Crew 780

    Consumables 780

    Drill Camps 781

    Transportation 781

    In-field Rig Down / Relocation / Rig up 781

    Mob / Demob 781

    Drilling Services 781

    Other Costs 782

    General Costs 783

    Design & Project Management 783

    Insurance 784

    Certification 784

    Contingency 784

    About Infrastructure 785

    50

    QUE$TORHelp

  • User Interface 786

    Inputs 786

    Facilities 787

    Cost Estimate 787

    Primary Inputs 788

    Location 788

    Distances to Major Populations 788

    Road 790

    Road Links 790

    Road Type 791

    Terrain 791

    Rail 792

    Terrain 793

    Construction Camp 794

    Operations Camp 795

    Administration Offices 796

    Permanent Housing 797

    Medical / Hospital Facilities 798

    Schools, Places of Worship, Community Buildings 799

    Power Transmission 800

    Airstrip 801

    Material and Construction Costs 802

    Road Construction 802

    Rail Construction 803

    Construction Camp 803

    Operations Camp 803

    Administration Buildings 803

    Permanent Housing 803

    Medical Facilities 803

    Schools, Places of Worship 803

    51

    QUE$TORHelp

  • Power Transmission 804

    Airstrips 804

    Community Projects/Others 804

    General Costs 805

    Design & Project Management 805

    Insurance 806

    Certification 806

    Contingency 806

    About User Defined Components 807

    Cost Estimate 808

    Operating Expenditure - OPEX 810

    Working with OPEX 811

    Locking/Unlocking 812

    Applying a Change to a Range of Cells 813

    Operating Personnel 814

    Inspection and Maintenance 815

    Logistics and Consumables 816

    Fuel Gas 816

    Diesel 816

    Chemicals 817

    Transportation 817

    Messing 817

    Vehicles 818

    Well Costs 819

    Insurance 820

    Field / Project Costs 821

    Support 821

    Land Costs 821

    Tariffs 823

    CO2 Emission Taxes 824

    52

    QUE$TORHelp

  • Lease costs 825

    Capital Expenditure Scheduling 826

    CAPEX Scheduling Window 827

    Distributions 828

    Intra-component Relationships 829

    Inter-component Relationships 830

    Locking 830

    First Oil 831

    Timescale 831

    Adding and Removing Components 831

    CAPEX Breakdown Graphs 832

    About Decommissioning 833

    Decommissioning Scenarios 834

    Decommissioning duration 834

    Delay after end of field life 834

    Component Decommissioning 835

    Cost estimate 835

    Scrap 835

    About the Investment and Production Profile 836

    Exporting the Investment Profile into AS$ET 838

    LNG Regasification Structure 839

    About Regasification Terminal Facilities 840

    User Interface 841

    Inputs 841

    Facilities 842

    Cost estimate 842

    Primary Inputs 844

    Terrain 844

    Elevation 844

    Functions 844

    53

    QUE$TORHelp

  • Capacities 845

    Inlet Composition 846

    Molecular weight 846

    Composition 846

    Gas Properties 847

    Design Specifications 848

    Sales gas specification 848

    Maximum ambient air temperature 848

    Prefabrication 849

    Winterisation 850

    Marine Infrastructure 851

    Ship / Berth Details 851

    Jetty details 852

    Marine Slip Details 852

    LNG Metering 853

    LNG Flowlines / Berth 853

    Breakwater 854

    Dredging 854

    LNG Storage 855

    Containment Type 855

    Number of Tanks / Capacity per Tank 856

    Diameter / Height 856

    LNG Processing 857

    Nitrogen injection 858

    Demethaniser 859

    Deethaniser 860

    Stabiliser 860

    Stream properties 860

    861

    LNG Pumping 862

    54

    QUE$TORHelp

  • In-tank Pumps / Tank 862

    LNG Processing Feed Pumps 863

    Send out Pumps 863

    Liquid Storage 865

    Atmospheric Storage Inputs 865

    Pressurised Storage Inputs 866

    Liquid Export 868

    Export Rate 869

    Size Export Pipeline 869

    Details 869

    Driver 870

    Derating Factor 870

    Capacity 870

    Driver Model 871

    Pump Weight 871

    Pump Driver Weight 871

    Metering Capacity 871

    Metering Weight 871

    Vapour Handling 872

    Derating Factor 872

    Boil off Gas Compression (BOG) 873

    Recondenser 874

    Vapour Return Blowers 874

    Vapourisation 876

    Process 876

    Open Rack 877

    Submerged Combustion 878

    Intermediate Fluid 878

    Gas Metering 879

    Control and Communications 880

    55

    QUE$TORHelp

  • Control System 880

    Communications 880

    Process Utilities 882

    Process Support Utilities 882

    General Utilities 883

    Power 885

    Power Requirement 885

    Generation and Distribution / Distribution only Radio Buttons 886

    Derating Factor 886

    Duty 886

    Driver 887

    Emergency Power 887

    Weights 888

    Civils 889

    Foundation Area 889

    Totals 890

    Equipment Costs 891

    Odourisation 891

    Safety 891

    Freight 892

    Material Costs 893

    Steelwork 893

    Berth 893

    Jetty 893

    Marine Slip 893

    Breakwater 894

    LNG Flowlines 894

    Piping (cryogenic) 894

    Piping 894

    Electrical 894

    56

    QUE$TORHelp

  • Instruments 894

    Others 894

    Civils Materials 895

    Freight 895

    Prefabrication Costs 896

    Loadout and Transport 896

    Construction Costs 897

    Site Preparation 897

    Civil Construction 897

    Tank Excavation 897

    General Costs 898

    Design & Project Management 898

    Insurance 899

    Certification 899

    Contingency 899

    Operating Expenditure - OPEX 900

    Working with OPEX 901

    Locking/Unlocking 902

    Applying a Change to a Range of Cells 903

    Operating Personnel 905

    Inspection and Maintenance 906

    Logistics and Consumables 907

    Nitrogen 907

    Fuel Gas 907

    Diesel 907

    Transportation 908

    Messing 908

    Vehicles 908

    Insurance 910

    Field / Project OPEX 911

    57

    QUE$TORHelp

  • Support 911

    Land Costs 911

    Tariffs 913

    CO2 Emission Taxes 914

    Leases 915

    Capital Expenditure Scheduling 916

    CAPEX Scheduling Window 917

    Distributions 918

    Locking 919

    First Oil 919

    Timescale 920

    Adding and Removing Components 920

    CAPEX Breakdown Graphs 921

    Investment and Production Profile 922

    Exporting the Investment Profile into AS$ET 924

    About Decommissioning 925

    Decommissioning Scenarios 926

    Decommissioning duration 926

    Delay after end of field life 926

    Component Decommissioning 928

    Cost estimate 928

    Scrap 928

    Data Input 929

    Text boxes 929

    Option buttons 929

    Dropdown lists 929

    Check boxes 930

    Locked Values 931

    To Unlock a Locked Value 931

    Units 932

    58

    QUE$TORHelp

  • Unit Nomenclature 932

    Form Conventions 933

    Tabs 933

    Form Buttons 933

    Component buttons 933

    Warning Messages 935

    About Program Menus 936

    File Menu 937

    Project Menu 938

    Options Menu 939

    Reports Menu 940

    Tools Menu 942

    Help Menu 943

    About Data Flow and Locking 944

    Data Flow between Components 945

    Exceptions to the hierarchy order 947

    Multiple topsides 947

    Data Flow Within Components 948

    Locking 949

    About Project Costs 950

    Project Cost Options 951

    To add a project cost 951

    To remove a project cost 952

    To set the default project costs 953

    Managing Project Costs 954

    Item name 954

    Cost 954

    Schedule distribution 954

    Schedule duration 955

    Creating a new project cost 955

    59

    QUE$TORHelp

  • Deleting a project cost 956

    About Contingency 957

    Base Cost Estimate 957

    Expected Value (or most likely cost) 957

    Contingency 957

    Accuracy Levels 958

    Operators Reserve 958

    Contingency Options 960

    About Component Ghosting 962

    Ghosting of Components 963

    Ghost CAPEX 963

    Ghost OPEX 964

    Ghosting Options 965

    About Decommissioning 966

    About Reports 967

    Component Reports 969

    Project Reports 970

    Locked Values 972

    Project Notes 974

    About Database Editor 976

    Procurement Strategies 977

    View/Edit Procurement Strategy 977

    Technical Databases 979

    View/Edit Technical Database 979

    Database Editor Interface 981

    Item Type (procurement strategies) 981

    Item Type (technical databases) 981

    Component Type 982

    Table Description 982

    About Project Editor 985

    60

    QUE$TORHelp

  • User Interface 986

    To Change a Procurement Strategy or Technical Database 986

    Procurement Strategies 988

    Technical Databases 989

    About Project Viewer 991

    User Interface 993

    Exporting from the Project Viewer 995

    About Unit Editor 996

    Custom Unit Sets 997

    About Network Licences 1000

    Feature 1000

    Days until expiry 1000

    Borrowed until 1000

    Network Licence Management 1001

    To borrow a feature from the network licence server 1001

    To return a feature to the network licence server 1001

    Restrictions 1002

    ANSI Pressure Ratings 1003

    Flow Definitions 1004

    Basis of Inspection and Maintenance 1005

    Comparison of Profile Timescales 1006

    Offshore Components 1007

    Offshore Concepts 1010

    Decommissioning Toolbar 1011

    Fabrication Details 1012

    Installation Vessel Maximum Lift Weights 1014

    CAPEX Scheduling Toolbar 1015

    Offshore Technical Databases 1016

    Offshore Toolbar 1017

    Barge Sizes With Storage 1018

    61

    QUE$TORHelp

  • Barge Sizes Without Storage 1019

    Offshore Casing / Tubing Programme 1020

    Offshore Drilling Profiles 1021

    Concept Selector - Export Options 1022

    CO2 Removal Only 1023

    H2S Removal Only 1024

    Simultaneous H2S and CO2 Removal 1025

    Solvent Data 1026

    Typical Gas Compositions 1027

    Default Dehydration Process 1028

    GBS Storage Capacity 1029

    Jacket Installation Factors 1030

    Maximum Topsides Weight 1031

    Monotower GBS Concrete Volume 1032

    Semi-submersible Characteristics 1033

    Maximum Load and Buoyancy Aid Weights 1034

    Subsea Flexible Flowline Limits 1035

    Flying Leads Calculation 1036

    Subsea Pressure Ratings 1037

    Subsea Toolbar 1038

    Standard Chain and Rope Sizes 1039

    Wind Speed Lookup 1040

    Single Point Mooring Systems 1041

    Tanker Storage Capacity 1042

    Offshore Gas Processing Product Specification 1043

    Oil Processing Defaults for Gas Projects 1044

    Oil Processing Defaults for Oil Projects 1045

    Oil Processing Toolbar 1046

    Tripod GBS Concrete Volume 1047

    Basis of Inspection and Maintenance 1048

    62

    QUE$TORHelp

  • Onshore Components 1049

    Onshore Concepts 1050

    Construction Details 1051

    Prefabrication Details 1053

    Onshore Technical Databases 1055

    Onshore Toolbar 1056

    Onshore Drilling - Profiles 1057

    Onshore Drilling - Rig Class 1058

    Default Dehydration Process 1059

    Onshore Casing / Tubing Programme 1060

    Solvent Data 1061

    CO2 Removal Only 1062

    H2S Removal Only 1063

    Simultaneous H2S and CO2 Removal 1064

    Typical Gas Compositions 1065

    Gas Processing Defaults 1066

    Column Operating Conditions - Single Column 1067

    Column Operating Conditions - Both Columns 1068

    Oil Processing Defaults for Gas Projects 1069

    Oil Processing Defaults for Oil Projects 1070

    GRP Pipe Sizes 1071

    Basis of Inspection and Maintenance 1072

    Double Containment LNG Storage Tanks 1073

    Full Containment LNG Storage Tanks 1074

    Single Containment LNG Storage Tanks 1075

    LNG Tanker Properties 1076

    LNG Regasification Onshore Toolbar 1077

    Comparison of Profile Timescales 1078

    Database Editor Toolbar 1079

    Project Viewer Toolbar 1080

    63

    QUE$TORHelp

  • Unit Sets 1081

    64

    QUE$TORHelp

  • About the Quick Start GuideThis guide is designed to help you understand the operation of the QUE$TOR program,outlining the basic steps involved in developing a QUE$TOR project to produce ascheduled estimate for capital and operating costs.

    QUE$TOR is structured around a field development schematic (FDS) which allows youto create a visualisation of the development. The FDS is driven by a number of highlevel inputs which allow the development conditions to be specified. The basicprogram calculation sequence followed in QUE$TOR to generate a full life-cycle fieldor prospect development cost estimate is shown below.

    To define the new project, QUE$TOR presents you with a series of forms that allowhigh level parameters of the development to be specified.The Field level data form ispopulated with default values for the basin selected in the Project properties form.Subsequent forms have values and selections based on earlier entries. Once you

    65

    QUE$TORHelp

  • have reviewed and adjusted as necessary the default inputs in each form, click on OKto apply the inputs and move on to the next form.Click on Cancel to ignore changesmade and go back to the previous form and make any necessary revisions.

    66

    QUE$TORHelp

  • Getting StartedQUE$TOR must be installed on a local PC. This must be done by a local administrator.See the release notes for installation instructions.

    QUE$TOR will run on these following operating systems:

    Windows XP Windows Vista Windows 7 Windows 8.

    A licence must be available; either a standalone dongle which plugs directly into yourcomputer or a network licence which is accessible across your company's local areanetwork. QUE$TOR Offshore, QUE$TOR Onshore and QUE$TOR LNG Regasificationrequire separate licences. Contact your IT department for further details.

    Depending on your installation options, you can launch QUE$TOR either from thetaskbar Start button or from your PC desktop.

    From the taskbar Start button

    Click Start and follow All Programs\IHS\QUE$TOR 2014 Q3

    From your PC desktop

    Double-click the QUE$TOR 2014 Q3 application shortcut icon .

    67

    QUE$TORHelp

  • Creating a New ProjectOn opening QUE$TOR the task selection form will appear.

    On this form you can choose to create a new project or open an existing project. Fornew projects you can either create a new offshore project or a new onshore project.For existing projects there are shortcuts to the last five projects saved.

    The location of your wells should determine whether you pick offshore or onshore asthe start point. If you are running a combined offshore and onshore project then thesecond location can be selected later in the project estimate.

    Once you have selected your project location i.e. offshore or onshore, click OK tomove onto the Project properties form. QUE$TOR will check that you have a validlicence to run the selected project type at this point.

    68

    QUE$TORHelp

  • Selecting the Project PropertiesThe project properties allow you to setup the basic information about your projectincluding the procurement strategy, regional technical database and units setpreference.

    Work through the following steps to set up your project:

    l Give your project a name.

    l Select the units you want to work in.Pick from one of the standard unit setsprovided or create your own using the Unit editor tool. For the majority of users

    69

    QUE$TORHelp

  • one of the default unit sets should meet your needs as you can change each unit asneeded throughout the program.

    l Select the main product. For Oil projects you will have to define your recoverableoil reserves and a gas oil ratio, while for gas projects you will input yourrecoverable gas reserves and a liquid gas ratio.

    l Select the geographical region, country, and basin to enable QUE$TOR to seedyour project with typical basin specific data generated from the IHS IRIS21 E&Pdatabase. This selection will also drive the default location of a new procurementstrategy and will set your regional technical database.

    l Create your procurement strategy. This can be done by clicking the Newbutton.This will display the Define procurement strategy form shown below. Procurementstrategies allow you to choose different regional cost databases for each costcentre. By default all costs are reported in US Dollars but this can be edited bychanging the currency name, symbol and exchange rate at the top of the form.

    70

    QUE$TORHelp

  • l Select the technical database to use for your project. This will normally be theregion which you have selected for your project.Use Browse to select analternative if required.

    Once you have completed the above steps, click OK to move onto the Field level dataform.

    71

    QUE$TORHelp

  • Entering Your Field Level DataThe Field level data form contains three tabs which list the values for the fieldcharacteristics, fluid characteristics and some miscellaneous data respectively.

    The information entered varies slightly depending on whether you have selected anoffshore or onshore project. Default values are populated from a database relevantto the basin you selected in the Project properties form.

    On this form, modify the data to the specifics of the field that you want to produce anestimate for. The purpose of the default data is to provide a reasonable value wherenone is known and therefore you should use your values over these defaults. Anyinput value can be changed by simply over-typing it.

    In this form, and any other form, the individual input units can be changed on the flyby clicking on the unit to the right of the value and selecting the unit you wish to usefrom the options available, this is shown for the recoverable reserves input below.

    72

    QUE$TORHelp

  • Once you have entered / confirmed the data on all three tabs click OK to move ontothe Production profile edit form.

    73

    QUE$TORHelp

  • Creating a Production ProfileThe production profile is created through two forms; the first form gives sevenentries through which you can influence the basic parameters of your productionprofile.

    Enter any of the values you know at this point and then click OK to move onto theProduction profile form which gives you a visual representation of these values.

    The production profile is displayed in a graphical and tabular format across four tabs;oil (or condensate), gas, water and gross liquids. Numbers in blue can be edited;numbers in black such as those in the gross liquids tab are derived numbers andtherefore cant be edited. This colour convention is common throughout QUE$TOR.

    74

    QUE$TORHelp

  • You can change the production for each year by entering the values in the table at thebottom of the form. This can either be typed in year by year or you can paste in aprofile from an external spreadsheet through a right mouse click. You can overwriteeither the daily or annual flowrates but not the cumulative row of the table. You canalso copy the data in the production profile and paste it into an external spreadsheet.

    Note: When pasting in a production profile from a spreadsheet ensure that thefield life specified in the production profile edit form is the same as that of the profileyou are pasting in.

    Once you are happy with the production profile, click OK to move onto the Designflowrates form.

    75

    QUE$TORHelp

  • Setting the Design FlowratesThe Design flowrates form gives the flowrates that will be used to design the facilitieswithin your project.

    The production values are based on the peak production with a design factor for oilprojects giving an allowance for day to day variation, and a swing factor in gasprojects giving an allowance for seasonal demand variation.

    The injection values should be adjusted based on your pressure maintenance and gasdisposal assumptions.

    Once you are happy with the design flowrates, click OK to move onto the Number ofwells form.

    76

    QUE$TORHelp

  • Setting the Number of WellsThe Number of wells form, shown below, sets the total number of wells requiredacross the field.

    The default number of production wells is based on the recoverable reserves, wellproductivity, plateau production and peak well flow. The default number of waterinjection wells assumes an average of two injectors for every five oil productionwells.Gas injectors are based on an average flowrate of 30 MMscf/day per well.

    Modify the well count to match your design assumptions and click OK to move ontothe Wellhead conditions form for onshore projects or the Concept selector form foroffshore projects.

    77

    QUE$TORHelp

  • Setting the Wellhead ConditionsThe Wellhead conditions form is only available for onshore projects and provides thewellhead conditions of the primary streams.

    Water injection, gas injection and gas lift pressure are only relevant if these servicesare selected. Adjust the conditions as necessary and then click OK to move onto theConcept selector form.

    78

    QUE$TORHelp

  • Selecting a Concept - OffshoreThe Concept selector form allows you to choose the basic concept of your fielddevelopment.

    QUE$TOR selects a field development concept based on the field level data andproduction profile.You can change this to another of the 14 default concepts using thelist box. If you want to configure your concept from scratch, select 'Blank concept'.

    Based on your concept, QUE$TOR will select typical oil and gas export options. Adjustthese to match your desired product export routes.

    When you click OK QUE$TOR runs the complete cost estimate using program defaultsthroughout and displays the field development schematic along with the costsummary tree.

    79

    QUE$TORHelp

  • Selecting a Concept - OnshoreThe Concept selector form allows you to choose the basic concept of your fielddevelopment.

    QUE$TOR selects a field development concept based on the field level data andproduction profile.You can change this to another of the 6 default concepts using thelist box. If you want to configure your concept from scratch, select 'Blank concept'.

    Based on your concept, QUE$TOR will select typical oil and gas export options. Adjustthese to match your desired product export routes.

    80

    QUE$TORHelp

  • When you click OK QUE$TOR runs the complete cost estimate using program defaultsthroughout and displays the field development schematic along with the costsummary tree.

    81

    QUE$TORHelp

  • Using the Field Development SchematicOn selecting your concept and clicking OK QUE$TOR will move through to the mainfield development schematic.

    The field development schematic shows the components within your chosen concepton the right hand side of the screen, with the associated high level CAPEX summaryon the left hand side of the screen.

    The schematic can be changed by adding and removing components. You can selectcomponents to add from the component toolbar at the top of the screen and click onthe schematic to place the component. To delete a component hit delete when thecomponent is selected or right click on the component and select Delete. You will beasked to confirm any deletions to prevent any components being inadvertentlydeleted.

    Components often require links so that the correct data can flow between them.

    Components are linked using the link icon in the toolbar . Once you have linkedtwo components you may need to add a pipeline by double clicking on the link.

    Note: Connections from drilling components, subsea, and wellpad groups do notrequire pipelines to be specified.

    Each component will be estimated using default assumptions based on the data youhave entered so far. To view a component in detail you can double click on it or rightclick on it and select Edit / view cost estimate.

    82

    QUE$TORHelp

  • Adjusting a ComponentYou can view the details of each component by either double clicking on thecomponent or by right clicking and selecting Edit / view cost estimate.

    Each component has two main parts to it: the inputs, where you can adjust the designparameters, and the cost sheet, where you can see the detailed breakdown of thecost.

    You can make changes within each of these areas and when you click Apply or OKthese changes will be applied to the component and the CAPEX estimate adjustedaccordingly. Clicking on OK will also exit the component. Clicking Cancel also exitsthe component; however you will lose all changes made since you entered thecomponent.

    Inputs

    The left hand side of the screen contains the main input data for that component. Theinput form for the topsides component is shown below.

    83

    QUE$TORHelp

  • The input form shows the main design parameters for a given component, such as thedesign flowrates. You can make changes to these values to match your designassumptions. When you click Apply these changes will be applied to the componentand the CAPEX estimate adjusted accordingly.

    Sub-components

    There are arrow buttons within many components that can be clicked on to openup one of the sub-components; the details of that system are then shown. Thetopsides Manifolding sub-component form is shown below.

    84

    QUE$TORHelp

  • You can make changes within each sub-component and when you click OK thesechanges will be applied to the component and the CAPEX estimate adjustedaccordingly.

    Cost sheet

    The right hand side of the screen has the cost sheet. This shows a detailed breakdownof the CAPEX estimate for the component. Each line item is made up of a quantity anda unit rate.

    The quantity is calculated from the design parameters and technical algorithms forthat item and the unit rate is taken from the selected procurement strategy. You canoverwrite any of the blue values within the cost sheet, as shown for the quantityentry above. Numbers in black are derived by multiplying the quantity by the unitrate so cant be overwritten.

    85

    QUE$TORHelp

  • Calculating the Operating CostsThe operating cost calculations should be run once you have finished the design ofyour development as the costs are based on the technical definition of thedevelopment.

    The OPEX algorithms are run by selecting OPEX from the Project menu. This willopen a separate window where a summary of the operating costs for each year ofproduction is displayed.

    The costs are broken down into various categories, which can be seen on the left sideof the screen. The detailed breakdown of these cost categories can be seen byclicking on these items, they are formatted as blue hypertext. This will open upfurther definition sheets for you to review or adjust the default values.

    Once you are happy with the operating costs, click OK to go back to fielddevelopment schematic so that you can generate the project schedule.

    86

    QUE$TORHelp

  • Scheduling the Capital CostsThe CAPEX scheduling calculations should be run once you have finished the design ofyour development as the schedule and costs are based on the details of thedevelopment.

    The CAPEX scheduling module can be accessed by selecting Scheduling from theProject menu. The schedule will be shown as a Gantt chart along with the underlyingdata for each component.

    For each component, a detailed schedule can be viewed by expanding the component

    using the icon. You can adjust the start date and activity duration either bydragging the bars within the Gantt chart or by adjusting the corresponding values inthe table. Adjusting these values will change when the calculated CAPEX values are tobe spent.

    Once you are happy with the project schedule, click OK to go back to fielddevelopment schematic so that you can generate the Investment and productionprofile.

    87

    QUE$TORHelp

  • Generating the Investment and Production ProfileThe investment and production profile is run by selecting Investment andproduction profiles from the Project menu.

    The investment and production profile gives a report of all of the values that could berequired to run an economic analysis, with the production, CAPEX and OPEX given foreach year of the project. The values in this report are in real terms, i.e. they arecosts specific to a particular point in time (depending on the version) and have notbeen inflated or discounted over the life of the project.

    This report can be printed or exported to Excel using the toolbar buttons.

    88

    QUE$TORHelp

  • Saving Your ProjectProjects are not automatically saved in QUE$TOR. We recommend you save yourproject when you reach the field development schematic and at regular intervalsafter this.

    To save a project select Save or Save As from the File menu or click on the Save

    project button . This will enable you to save the project in the usual Windowsfashion. The default location for saved projects is MyDocuments\IHS\QUE$TOR\Projects.

    Saved project files have a .qpr file extension and include the selected procurementstrategy, technical database and unit set. Once saved, projects are completelystandalone and have no further interaction with QUE$TORs databases. This meansthat saved projects can easily be sent to others who may not have the samedatabases.

    Saved projects can be moved, copied and renamed using Microsoft Windows Explorerin the same way as any Windows file. Projects can be opened either directly fromWindows Explorer or from within QUE$TOR. To open a saved project in QUE$TOReither select Open existing project from the form that appears when QUE$TORstarts or select Open from the File menu.

    Note: When you create a new project you won't be able to save the project untilyou reach the field development schematic.

    Opening a Saved Project

    To open a saved project select, using the option buttons, Browse for project and

    click OK to proceed or click on the Open project button .This will enable you toopen a project in the usual windows fashion.The Open existing project box hasshortcuts to the last five projects opened in QUE$TOR.Saved projects have a .qprfile extension.

    89

    QUE$TORHelp

  • About QUE$TORQUE$TOR has been designed to produce high level estimates of the capital andoperating costs of green field oil and gas developments. It will assist with projectmodelling, evaluation and subsequent decision making in the oil and gas industry.

    QUE$TOR provides a reliable, consistent methodology for producing cost estimatesand creates efficiency when optimising field developments. It has benefits in manyapplications, including:

    l Prospect evaluations

    l Screening studies

    l Feasibility studies

    l Conceptual studies

    l Optimisation studies

    QUE$TOR uses a systematic approach to generate a field development basis, capitaland operating costs, and project schedules from basic field data. QUE$TOR uses abottom up methodology; the calculations are based around detailed sizing algorithmsand engineering rules of thumb with regional variations where appropriate.

    This approach allows engineers, estimators and economists to produce weight andcost estimates quickly, consistently and accurately and to develop investmentprofiles.

    Capabilities

    QUE$TOR has the capability to handle most oil and gas developments worldwide, ithas clearly defined methodologies for offshore and onshore upstream developmentsas well as onshore LNG regasification projects. Any combination of these threeproject types can be modelled provided you have the requisite licences.

    In generating capital cost estimates for a field development, the estimate is brokendown into a number of discrete components.Combining these components allows afield development plan to be identified and estimated.It is then possible to generateoperating costs for the facilities specified and phase the expenditures as necessary.

    The use of separate cost and technical databases for all major worldwide oil and gasproducing regions means that any development, present or future, can be modelled.

    Cost Databases

    There are 17 offshore and 11 onshore regional cost databases behind the program.These cost databases are updated on a six-monthly basis with a new version of theprogram sent out for each update. Each new version can be installed alongside allexisting versions of the program allowing you to track costs of a project over time.

    Each of the databases is editable meaning that if there is a region where you have agood understanding of the costs you can overwrite some of the costs within theQUE$TOR databases to give you greater confidence in the estimate.

    90

    QUE$TORHelp

  • 91

    QUE$TORHelp

  • Estimate BasisThe following points should be considered when generating or reporting a costestimate using QUE$TOR.

    l QUE$TOR provides an estimate based on the costs within the markets today. Wemake no allowance for inflation or deflation of costs over the project life.

    l All of the costs within QUE$TOR are in real terms, i.e. they are costs specific to aparticular point in time (depending on the version). We do not apply anydiscounting or inflation to the estimate to costs incurred over the project life.

    l Pre-sanction costs, such as FEED studies and environmental impact assessments,are not included within the estimate by default. These costs can be optionallyadded as a percentage of the project CAPEX costs or as monetary value.

    l Post sanction costs that fall outside of the typical EPC contract scope, such as theowner's project management cost, are not included by default. These costs can beoptionally added as a percentage of the project CAPEX costs or as monetary value.

    l Contingencies within QUE$TOR are calibrated to target the P50 development cost.

    l QUE$TOR is designed for use early in the project cycle. Therefore the estimatelevel that can be attained by using the program is typically within the range of +/-25% to 40%.

    l The estimate produced is dependent on user entered values. Therefore, anyestimate should take into account the confidence of these values.

    92

    QUE$TORHelp

  • Recommended System SpecificationsQUE$TOR is supported for the following operating systems:

    l Windows XP service pack 2 or later

    l Windows Vista

    l Windows 7

    l Windows 8.

    The 32-bit (x86) and 64-bit (x64) versions of these operating systems are supported.

    To run QUE$TOR in a terminal server environment requires the use of networklicences.

    Minimum system specifications:

    l 1 GHz Pentium 4 processor

    l 512 MB RAM

    l 250 MB disk space

    l Minimum 1024x768 resolution

    l CD ROM drive

    Before installing QUE$TOR

    l QUE$TOR requires that you install Windows Installer 3.1, Windows ImagingComponent and .NET framework 4 or later.

    l QUE$TOR requires that the Sentinel SuperPro driver be installed on PCs that havea local security key (dongle) for their QUE$TOR licence.

    l These are included on the CD.

    Note: Administrator privileges are required to install these components.

    Installation requirements

    l QUE$TOR must be installed on a local PC. This must be done by a localadministrator. See the release notes for installation instructions.

    l A licence must be available to run QUE$TOR; either a standalone dongle whichplugs directly into your computer or a network licence which is accessible acrossyour company network. Contact your IT department for further details.

    93

    QUE$TORHelp

  • Exporting to Microsoft Excel from QUE$TOR

    It is not necessary for Microsoft Excel to be installed on the PC that QUE$TOR isrunning on to perform an export to an Excel format file. However, to view theexported file requires Microsoft Excel 2003 SP3 or later. The exported files may openin earlier versions, however some of the formatting may be lost.

    94

    QUE$TORHelp

  • Contacting Customer SupportAs part of the continuing licensing agreement for QUE$TOR, IHS offers a full technicalsupport service via its regional offices. Both computing and engineering supportrelating to the operation and understanding of the program are available.

    The QUE$TOR support group has a dedicated support email address: [email protected]

    Note: There is an 's', not a '$' in questor in the email address.

    The IHS software support team key contacts are as follows:

    North & CentralAmerica

    Jonathan Stephens - Product Manager,[email protected] Verma - Senior Field Development Engineer,[email protected] Wahab - Cost Analyst, [email protected]

    5333 WestheimerHoustonTexas 77056USA

    Tel: (+1) 713 840 8282Fax: (+1)713 995 8593

    South America Thais Hamilko - Product Specialist, E&I Prod Line-LATAM,[email protected]

    Rua So Bento, 29 - 7o andarCentroRio de JaneiroRJ, CEP 20090-010Brazil

    Tel: (+55) 21 3299 0440

    Europe, Africa &Middle East

    Rita Antonelli - Cost Manager, [email protected] Butcher - Field Development Engineer,[email protected] Helliwell - Engineering Advisor,[email protected] Williams - Engineering Manager,[email protected]

    133 HoundsditchLondonEC3A 7BX

    95

    QUE$TORHelp

  • UK

    Tel: (+44) 20 3159 3300Fax: (+44) 20 3159 3299

    S.E. Asia & Australia Sanjay Sinha - APAC Field Development SME,[email protected]

    First Floor, Tower AVatika Business ParkSohan Road, Sec 49Gurgaon 122018 - HaryanaIndia

    Tel: (+91) 124 454 2699

    China Yaxing Wang - Sr. Customer Solution Advisor,[email protected]

    Room 3001China World Office 1No.1, JianGuoMenWai AvenueBeijing100004China

    Tel: (+86) 10 5633 4567Fax: (+86) 10 5633 4500

    96

    QUE$TORHelp

  • CopyrightCopyright 2014, IHS Inc. and its affiliated and subsidiary companies, ALL RIGHTSRESERVED.

    Windows and Excel are registered trademarks of Microsoft Corporation.

    All other trademarks and service marks, including without limitation QUE$TOR,AS$ET and IHS ENERGY, belong to IHS Inc. and its affiliated and subsidiarycompanies, all rights reserved.

    This product, including software, data and documentation, is licensed to theauthorised user for its internal business purposes only and no part thereof may bedisclosed, disseminated, sold, licensed, copied, reproduced, translated, transmittedor transferred to any third party. All rights reserved.

    IHS Inc.15 Inverness Way EastEnglewood, Colorado 80112(303) 736-3000

    Rev May 2014

    97

    QUE$TORHelp

  • QUE$TOR StructureQUE$TOR is structured around a field development schematic (FDS) which allows youto create a visualisation of the development. The FDS is driven by a number of highlevel inputs which allow the development conditions to be specified.The basicprogram calculation sequence followed in QUE$TOR to generate a full life-cycle fieldor prospect development cost estimate is shown below.

    To define the new project, QUE$TOR presents you with a series of forms that allowhigh level parameters of the development to be specified. Once you have reviewedand adjusted as necessary the default inputs in each form, click on OK to apply theinputs and move on to the next form.Click on Cancel to go back to the previous formand adjust any changes made.

    98

    QUE$TORHelp

  • On starting each new project you will be led through the first four stages shownabove. Each of these stages will be populated with default values based upon yourchoices in the previous stage.

    When the concept selector is completed, QUE$TOR will generate a complete costestimate immediately made up of a series of components, e.g. topsides, jacket,drilling and pipelines.

    These components are all live linked to each other so that a change to one componentwill change all dependent components, e.g. jacket cost is dependent on topsidesoperating weight.You can enter and update these components and fix inputs so thatthey are no longer updated by the program.This is called locking. Although you canedit components in any order you should try to follow a logical path to avoid lockingvariables based on incorrect data.For example you should not lock the jacket weightuntil the topsides is fully defined. QUE$TORs order of calculation is explained infurther detail in Data flow and locking.

    OPEX and Scheduling take data from all components to generate field operating costs(OPEX) and schedule the calculated capital and operating costs along with theproduction profile to give an overall project investment profile.

    Once on the FDS

    Cost estimates in QUE$TOR are made up of a number of individual components suchas topsides and jackets.Each of these components will influence or be dependent onthe design of associated components, e.g. jacket design is dependent on itsassociated topsides.Components are linked or docked to those components fromwhich they require data.There are also high level parameters defined withinQUE$TOR, such as reserves, which influence all components.

    In generating a cost estimate QUE$TOR calculates one component at a time and thenpasses all requisite data on to the next component.The order of this is defined by thecalculation hierarchy.The concept selector generates a basic development plan froma selection of built-in defaults. The components selected by the concept are then runin the hierarchy order to provide a development capable of handling the wells andproduction defined in the production profile and field level data.

    If you wish to fix parameters within a component, preventing them from beingrecalculated by the program, you can lock them.

    99

    QUE$TORHelp

  • About Project PropertiesThe project properties is the starting point for defining a new project. It enables youto specify the location of the project, the procurement strategy and technicaldatabase to be used in the project and the preferred units.

    Note: It is not possible to make changes in this screen once a project iscreated. However, the Project editor does allow the procurement strategy and thetechnical database to be changed once the project is saved.

    l Name: enter a name for the project here.This will be the default file name whenyou save the project.

    100

    QUE$TORHelp

  • Units of Measure

    The units of measure define the units that will appear, both in the project and thereports. QUE$TOR has three built-in unit sets, metric, imperial and oilfield which areselected from the dropdown list.

    Custom unit sets can be defined using the Unit editor.To select a user defined unitset, select the use custom unit set option button and use the Browse button to locateit. The default location for custom unit sets is: My Documents \IHS \QUE$TOR\Unit Sets.

    Once in a project the units can be easily changed, for every input QUE$TOR providesa choice of relevant units. However the units in the reports are fixed by the choice ofunit set.

    Main Product

    The main product can be either oil or gas, the volume of the secondary product, e.g.associated gas when oil is selected, is defined by a ratio on the Field level data form.

    This should typically be Oil if the gas oil ratio (GOR) is 400 bbl/MMscf (70 m3/million Sm3)].

    Note: Once selected this cannot be changed in the project.

    Selection will also affect the default field level data (but this can adjusted if required)which in turn will influence the field life and plateau production rate.

    The default product type is set to the choice made in the last project you created, orto oil when QUE$TOR is shipped.

    Location

    QUE$TOR contains a database of typical field characteristics, extracted from the IHSIRIS21 E&P database. These are broken down on a basin by basin basis and providethe default properties for the field.Whilst you can overwrite all these characteristics,they can be useful if some data is unavailable.

    Procurement strategy

    This allows you to select the regional databases to be used for each of the costcentres for the new project. For example equipment could be sourced from NorthAmerica and design performed in Europe. The currency of the cost estimate can alsobe defined.

    The box displays existing procurement strategies which can be chosen by selection.

    To look for existing procurement strategies in a different folder, click on Browse.

    Click on New to create a procurement strategy. When you create a new procurementstrategy QUE$TOR bases the default regional database on the location selected.SeeCreating procurement strategies for more information.

    Click on View to examine a procurement strategy.

    Click on Delete to delete the selected procurement strategy.

    101

    QUE$TORHelp

  • Note: QUE$TOR does not ship with any built-in procurement strategies.

    Technical database

    The technical database contains regional specific technical data such asenvironmental data.QUE$TOR includes template databases for every offshore regionworldwide.The default database is based on the location chosen.To change to adifferent database, click on Browse.

    You will be prompted to choose whether you want to use a template databasesupplied with QUE$TOR or use a custom database. See Technical Databases forfurther information.

    Once you have adjusted all inputs as necessary, click OK. This applies your changesand closes the form to move on. Cancel will clear all entries in the form and takeyou back a step.

    102

    QUE$TORHelp

  • Creating Procurement StrategiesProcurement strategies allow you to choose different regional cost databases foreach cost centre. They can also be used to choose the currency for the cost estimate.The cost data in each regional database is stored in either US dollars or the localcurrency (for the UK, Norway and the Netherlands). When cost databases are broughtinto the procurement strategy QUE$TOR converts them all into US dollars. You canedit the exchange rate used for this conversion. You can then choose a currency forthe cost estimate and enter the exchange rate from US dollars to this currency.

    To create a new procurement strategy

    1. Click Create new procurement strategy in the project properties form. Thisopens the form shown below.

    2. Select a region and country.3. By default the cost database will be assigned a title which is the same as the

    country selected; this can be overwritten.4. Click OK.5. The procurement strategy definition form is displayed.

    103

    QUE$TORHelp

  • 6. QUE$TOR has built in defaults for every country which it uses to choose wherecost centres are sourced from. To adjust the default region use the dropdownlists.

    7. Check the exchange rate for each database. Some cost databases are in localcurrencies. In creating a procurement strategy QUE$TOR converts all costs to USdollars.A default exchange rate is entered if the cost database is in local currencybut this should obviously be treated with care and edited to reflect expectedexchange rates. The rate should be in the form of local currency to 1 US dollar,e.g. UK0.624 = US$1.