Its happening nowQueens Quay Revitalization
Central Waterfront Update Meeting: June 6, 2012
7/31/2019 Queens Quay Revitalization Plan
2/59
Beginning the transformation of Queens Quay from
austere and uninviting
BEFORE
7/31/2019 Queens Quay Revitalization Plan
3/59
into a truly great and vibrant waterfront street
AFTER
7/31/2019 Queens Quay Revitalization Plan
4/59
BEFORE
From a place to move through
7/31/2019 Queens Quay Revitalization Plan
5/59
AFTER
into a great place to be
7/31/2019 Queens Quay Revitalization Plan
6/59
June 2006: Central Waterfront Design Competition
7/31/2019 Queens Quay Revitalization Plan
7/59Summer 2006: Quay to the City Pilot Project
7/31/2019 Queens Quay Revitalization Plan
8/59
April 2010: Full Approval for Environmental Assessment
7/31/2019 Queens Quay Revitalization Plan
9/59
Fall 2010 Summer 2011: Detailed Design for Queens Quay
7/31/2019 Queens Quay Revitalization Plan
10/59
November 2011 June 2012: Planning for Construction
7/31/2019 Queens Quay Revitalization Plan
11/59
Its happening nowQueens Quay Vision
http://sp/sites/cwf/03/Marcom/Queens%20Quay/New%20renderings%20MAY%202012/04.jpg7/31/2019 Queens Quay Revitalization Plan
12/59
Design and Construction Team
Design Team
Lead Designer: West 8 + DTAH
Civil/Municipal Engineer: ARUP
Structural Engineering: Halsall
Bus/Traffic Management: BA Group
Utility Coordination/Design: DPM Energy
Electrical: TSL Consulting & Design Group
Environmental and Geotechnical: LVM Franz/Golder Associates
Cost Estimating: AW Hooker Associates Ltd.
Urban Forestry: James Urban and AssociatesIrrigation: Smart Watering Systems
Construction Team
Construction Manager: Eastern Construction Company Ltd.
Toronto Hydro Constr. Contractor: Powerline Plus Ltd.Bell Canada Constr. Contractor: Aecon
7/31/2019 Queens Quay Revitalization Plan
13/59
Design Elements for Queens Quay
4. Roadway
1. Southside Promenade
2. Martin Goodman Trail
5. Northside sidewalk
3. TTC Streetcar Corridor
7/31/2019 Queens Quay Revitalization Plan
14/59
Design Elements for Queens Quay
1. Southside Promenade
7/31/2019 Queens Quay Revitalization Plan
15/59
New Pedestrian Promenade: Generous granite mosaic
7/31/2019 Queens Quay Revitalization Plan
16/59
Design Elements for Queens Quay
2. Martin Goodman Trail
7/31/2019 Queens Quay Revitalization Plan
17/59
New Martin Goodman Trail: Connecting east and west and framedby double row of trees
7/31/2019 Queens Quay Revitalization Plan
18/59
7/31/2019 Queens Quay Revitalization Plan
19/59
TTC: New streetcar right-of-way with expanded platforms
and amenities
7/31/2019 Queens Quay Revitalization Plan
20/59
Design Elements for Queens Quay
4. Roadway
7/31/2019 Queens Quay Revitalization Plan
21/59
Roadway: New Two-lane, twoway road with expanded turning lanes
and laybys and improved signalization
7/31/2019 Queens Quay Revitalization Plan
22/59
INSERT Northside sidewalk elements Page
Design Elements for Queens Quay
5. Northside sidewalk
7/31/2019 Queens Quay Revitalization Plan
23/59
North Side Beautification: Granite curbs/sidewalk pavers and tree-
planting
7/31/2019 Queens Quay Revitalization Plan
24/59
Completely upgraded utilities and municipal services
Storm sewer installation Watermain installation
7/31/2019 Queens Quay Revitalization Plan
25/59
Improvement to Public and Private Space - Northside
BEFORE
7/31/2019 Queens Quay Revitalization Plan
26/59
Improvement to Public and Private Space - Northside
AFTER
7/31/2019 Queens Quay Revitalization Plan
27/59
NOW
Improvement to Public and Private Space - Southside
7/31/2019 Queens Quay Revitalization Plan
28/59
AFTER
Improvement to Public and Private Space - Southside
7/31/2019 Queens Quay Revitalization Plan
29/59
Interim Martin Goodman Trail Connection
Existing: Looking East at Pier 27
7/31/2019 Queens Quay Revitalization Plan
30/59
Martin Goodman Trail Connection
Looking East at Pier 27
7/31/2019 Queens Quay Revitalization Plan
31/59
Interim Martin Goodman Trail Connection
Existing: Looking East at Redpath
7/31/2019 Queens Quay Revitalization Plan
32/59
Interim Martin Goodman Trail Connection
Looking East at Redpath
7/31/2019 Queens Quay Revitalization Plan
33/59
Its happening nowHow construction will unfold
7/31/2019 Queens Quay Revitalization Plan
34/59
Queens Quay Central Waterfront
Yo Yo Ma Lane Bay Street
Interim MGT Connection
Bay Street Jarvis Street
EBF Queens Quay
Jarvis Street - Parliament
7/31/2019 Queens Quay Revitalization Plan
35/59
Coordinated Construction
Transit infrastructure and most of the utilities and municipal services beneath
Queens Quay require major upgrades and/or expansion now
The TTC tracks have reached the end of their service life
Toronto Hydro is replacing aging electrical infrastructure
Bell will building new infrastructure and run new fibre optic cable
The aging sanitary line will be rebuilt and relocated
Storm sewer and water main upgrades
These projects would have happened in the near future with or without the
revitalization of Queens Quay
We are coordinating these upgrades with our work to avoid the need for more
disruptive construction in the near future
Construction is about more than rebuilding the surface of the roadway
7/31/2019 Queens Quay Revitalization Plan
36/59
Coordinated Construction
Streamlined Schedule Overlapping approach allows different construction
programs to run simultaneously.
Moratorium After Construction Complete Avoids the need for more construction
on Queens Quay in the near future.
Cost Effective Streamlined schedule means crews are not required to stop work
and remobilize.
Benefits of working in a coordinated manner
7/31/2019 Queens Quay Revitalization Plan
37/59
7/31/2019 Queens Quay Revitalization Plan
38/59
7/31/2019 Queens Quay Revitalization Plan
39/59
7/31/2019 Queens Quay Revitalization Plan
40/59
7/31/2019 Queens Quay Revitalization Plan
41/59
7/31/2019 Queens Quay Revitalization Plan
42/59
7/31/2019 Queens Quay Revitalization Plan
43/59
7/31/2019 Queens Quay Revitalization Plan
44/59
7/31/2019 Queens Quay Revitalization Plan
45/59
7/31/2019 Queens Quay Revitalization Plan
46/59
7/31/2019 Queens Quay Revitalization Plan
47/59
What to Expect
Accessing Queens Quay During Construction
Queens Quay will be safe andfunctional
Access will be maintained to all
businesses and residences at all
times
The waterfront is Open For
Business during construction
Cars, transit and pedestrian traffic
will always be able to access
Queens Quay
7/31/2019 Queens Quay Revitalization Plan
48/59
What to Expect
Types of Construction Impacts
Temporary fences around all
construction areas to maintainpedestrian and vehicular safety
Construction noise as permitted by the
City of Toronto between 7am and 7pm
while work is occurring
Possible dust and debris during workhours
Possible brief interruptions to
telephone, power or water when
connections are being switched over
(notice to be provided)
Short-term occasional night work when
TTC installs track
7/31/2019 Queens Quay Revitalization Plan
49/59
What to Expect
PEDESTRIANS: Temporary
gangplanks to ensure continuous
pedestrian access to all buildings
and stores during sidewalk
reconstruction
MOTORISTS: Temporary one-way
traffic operations alternating
between the north and south side
of the TTC tracks to avoidconstruction areas
Changes in How the Street Operates During Construction
7/31/2019 Queens Quay Revitalization Plan
50/59
What to Expect
TRANSIT: Temporary TTC bus service
running westbound on Queens Quayand eastbound on Lake Shore while
the streetcar line is rebuilt in the first
stage of work.
CYCLISTS: Building the Martin
Goodman Trail is a key goal for thisproject as there are currently no
bicycle lanes along Queens Quay in
the Central Waterfront. Cyclists
should use caution when traveling
along Queens Quay during
construction or consider usinganother alternative route.
Changes in How the Street Operates During Construction cont
7/31/2019 Queens Quay Revitalization Plan
51/59
7/31/2019 Queens Quay Revitalization Plan
52/59
7/31/2019 Queens Quay Revitalization Plan
53/59
7/31/2019 Queens Quay Revitalization Plan
54/59
Its happening nowLearn more
d/ k
7/31/2019 Queens Quay Revitalization Plan
55/59
QUEENS QUAYOPEN HOUSE
Drop-in and review proposedconstruction plans and timelines.
Look for your home or business andtalkto us about what to expect.
When:Saturday, June 9, 2012
Where: Waterpark Place Lobby20 Bay St.
Time: 10am - 2pm
Stay Connected/Ask Questions
Construction Information
d/ k i
7/31/2019 Queens Quay Revitalization Plan
56/59
Construction Information
Waterfront Torontos website
www.waterfrontoronto.ca will be the
main hub for information: Weekly construction notices
subscribe online
Construction schedule
Detailed construction
information
Live webcams Contact information
Stay Connected/Ask Questions
S C d/A k Q i
http://www.waterfrontoronto.ca/http://www.waterfrontoronto.ca/7/31/2019 Queens Quay Revitalization Plan
57/59
Construction Information
Construction Liaison Committee
Forum for residents and businesses to
discuss construction issues. Group meets regularly to discuss
construction schedule, issues and
impacts
Residents: every condo is represented
on the CLC
Businesses: The Waterfront BIA andother businesses are represented
Contact your rep if you have an issue
to raise (www.waterfrontoronto.ca)
Stay Connected/Ask Questions
St C t d/A k Q ti
7/31/2019 Queens Quay Revitalization Plan
58/59
Construction Information
Questions/Issues:
Email: [email protected]
Call: Waterfront Toronto Queens Quay info line is 416.214.9990
For urgent construction issues call:
Eastern construction: Robert Pasut, Community Liaison Officer
(416) 505-3073
Stay Connected/Ask Questions
7/31/2019 Queens Quay Revitalization Plan
59/59
Questions