1 Quarterly Review January 24, 2002 QUARTERLY REVIEW January 24, 2002
1
Quarterly ReviewJanuary 24, 2002
QUARTERLY REVIEW
January 24, 2002
2
Quarterly ReviewJanuary 24, 2002
Agenda
• 0830 QR - Project Overview• 0930 break• 0945 QR - Technical Progress• 1045 Break• 1100 QR - Management• 1200 Lunch• 1300 Tour of design area workstations• 1330 Hardware tour
- Instrument Shop- EE Lab- Blue Room
• 1400 Software - Hardware Demo
3
Quarterly ReviewJanuary 24, 2002
GNIRS Quarterly Review
Table of Contents
• Introduction Pg 4
• Project Summary Pg 6
• Configuration & Integration Pg 23
• Project Management Pg 43
• Appendices Pg 64
4
Quarterly ReviewJanuary 24, 2002
Introduction
• This is the 7th GNIRS Quarterly Review• GNIRS is in the final design and fabrication phase
– All bench assemblies are complete
– Bulkhead and Dewar Shell assemblies are complete
– Mechanism fabrication is complete
– Mechanism testing is underway
– OIWFS integration is complete except for the detector
• We are on track for delivery in October of 2002
5
Quarterly ReviewJanuary 24, 2002
Outline
• Project summary– Last QR Response– Progress Overview– Cost and Schedule Status
• Problems and Concerns • Configuration Update• Technical Progress• Project management• Plans for next review
6
Quarterly ReviewJanuary 24, 2002
Project Summary
• Response to last QR report• Progress overview• Summary schedule• Work left• Budget and expenditures to date
7
Quarterly ReviewJanuary 24, 2002
Response to October QR - Issues to be Reviewed
• Completion of items– OIWFS integration
– Lens delivery/testing
– Mechanism fabrication
– Mechanism/optical testing
– Fixed Assy 3D/2D design
– TE fabrication
– Bulkhead fabrication
– Dewar component fabrication
– Optics procurement
• ATP (Plan)
• Design delays– Radiation Shields
• Rework items
• OIWFS issues
• IFU late delivery
• Change orders
• Documentation approach
8
Quarterly ReviewJanuary 24, 2002
Task Status
ITEM STATUS COMMENT
OIWFS component integration Complete – Detector installation on hold
Waiting for Gemini decision on prism. February cut-off date.
Lens delivery/testing Complete
Mechanism fabrication Complete Some rework in process
Mechanism/optical testing Not Complete – delayed because of fabrication delays
Should complete in March
Fixed Assembly 3D/2D design Not Complete – Radiation shields still in process
Completion expected in January
TE fabrication Complete
Bulkhead fabrication Complete Fit checks complete except for radiation shields
Dewar component fabrication Complete
Optics procurement Not Complete – Simulator optics not yet purchased
Simulator is in design stage. Not a pacing item. Rescheduled to a later date.
9
Quarterly ReviewJanuary 24, 2002
Response to October QR
• Planned Completions by this Quarterly Review – 3D and 2D design of all fixed assemblies– Fabrication of all mechanisms– Fabrication of the Bulkhead Assembly– Mechanical fabrication except for:
• Rework items• Shipping container• Items associated with flexure testing
– Mechanism and optical subassembly testing– Receive all optics– Electronics fabrication and checkout except for:
• Some cables• Rework items
– Initial software coding– Component controller software testing– OIWFS component integration– Change orders for Chile Delivery and for Differential Pressure Switch– Manual outlines
10
Quarterly ReviewJanuary 24, 2002
Response to October QR
• ATP– A draft of the ATP and commissioning plan was submitted to
Gemini for review; returned with minor comments last week
• Change Orders are in process– For Chile delivery
– For the Differential Pressure Switch
• Manual outlines – Maintenance Manual in process
– Software and Operation manuals are not started
11
Quarterly ReviewJanuary 24, 2002
Response to October QR
• Software coding– Component controller software
• Coding is complete• Checkout complete as far as can be done without actual hardware to
exercise• All checks with the electronics are complete
– EPICS software is 95% complete
• IFU late delivery– Proceeding with mass modules – We will try to integrate the IFU when it becomes available
12
Quarterly ReviewJanuary 24, 2002
Summary Project Plan
N D J F M A M J J A S O N D J F M A M J J A S OCY-2000 CY-2001
Risk Reduction Prototypes
PFR
Structural Analysis
Fixed Assemblies Design/Fab
Bench Design/Fab/Assy
OIWFS/Post-Slit/Pre-Slit
WFS Integration/Alignment
Mechanism Design/Fab/Assy/Test
9 Mechanisms
Software Development/Code/Test
SW Plan/Low-Level/High-Level Code
Electronics Design/Fab/Test
Optics Procurement
MFR
OIWFS Hardware
Rotary Mechanism Flexure Tests
Systems Engineering
Mirrors/Lenses/Filters/Gratings/Prisms
J F M A M J J A S O N DCY-2002
Integration/Alignment
IFU Modules
Manuals
ATP
Ship
Training
Rotary Mechanism Flexure Tests
Flexure Testing
OIWFS Prism
13
Quarterly ReviewJanuary 24, 2002
Revised Bench Integration Plan12/1 12/15 1/1 1/15 2/1 2/15 3/1 3/15 4/1 4/15 5/1 5/15 6/1
Bulkhead Clean & Mt Hdwr
- cryocoolers
Fab
OIWFS
Prism
PS Int
Wire Bench Heaters, Etc.
Warm Test
Active Shield Design/Fab
Passive Shield Design
Install PS &
Wire
Install Cold Shields & Finish Wiring
Cold Tests FlexureTest
SciArray
EngArray
Pre-Slit
Bench
IFU
Plug/Play
IFU
not Plug/Play
Collimator Clean Adj
Acq Mirror Clean/Test Cold Bench Wire Test Test
Prism Turrets Clean/Test Cold Install Wire Test Prisms
Focus Clean/Test Cold Instl Wire Test mux
Grating Clean/Test Cold Instl
Turret Wire Test optics
Camera Clean/Test Cold Instl Test Wire Test optics
Filter Wheel SD/FW Cold Test
Slit Decker
14
Quarterly ReviewJanuary 24, 2002
Work Left – Integration Plan
• Two critical areas– Radiation shields– Mechanism testing
• Need passive shields first so bulkhead can be assembled and wired
• Active shields needed for integration of bench into dewar
• Key resources– Electrical technician for wiring– M&P engineer and technician for cleaning and prep work– Scientists for testing– Mechanical engineers and designers for shields– Instrument makers for assembly/rework/testing
15
Quarterly ReviewJanuary 24, 2002
Project Status - Progress from August ’99
WBS element Mar June October January5.0 Overall project 53% 66% 80% 86%5.1 Management & Reporting 51% 61% 71% 80%5.2 Systems Engineering 100% 100% 100% 100%5.3 Mechanical 52% 70% 87% 94%5.3.1 Mechanisms 66% 84% 92% 97%5.3.2 Benches 55% 70% 100% 96%5.3.3 Fixed Assemblies 16% 36% 62% 84%5.4 Electronics 63% 59% 86% 71%5.5 Software 49% 63% 85% 86%5.6 Integration 0% 0% 2% 23%5.7 Deliverables 0% 0% 0% 45%5.8 Procurement 54% 67% 77% 86%
16
Quarterly ReviewJanuary 24, 2002
Progress Overview
• The delivery date of the instrument is now October 24, 2002– Delay radiation shield design
– Delay in mechanism testing
• The project is currently 86% complete overall
• We have completed 170 of 226 total project milestones
• Our critical path(s) are– Radiation Shields: 3D and 2D design and fabrication
– Mechanism testing
• Electronics fabrication left is mechanism and dewar wiring
• Software Component Controller code is essentially complete
17
Quarterly ReviewJanuary 24, 2002
Focus of Last Quarter of Work
• Design/fabrication activity concentrated on– Radiation shield design– Bulkhead Assembly fabrication/acceptance tests/fit checks– Fit checks and fixes– Mechanism warm tests, flexure tests, rework– Assembly cleaning and wiring, prep for integration and/or cold testing– Final fixed assembly fabrication: trusses, etc.– Telescope simulator design– General design cleanup (configuration control)
• Procurement– Mechanical – Optical
18
Quarterly ReviewJanuary 24, 2002
Progress and Schedule Comments
• Mechanical design virtually complete– Radiation Shields and the Thermal Distribution Assembly remain
• Fabrication will continue through March on shields
• Sub-assembly flexure testing complete
• Mechanism fabrication is essentially complete– Minor rework in process
• Focus mechanism
• Prism turret
– Filter wheel cleaned and wired, ready for final warm test
– Grating Turret ready for cleaning and wiring
– Camera cleaning and wiring in progress
19
Quarterly ReviewJanuary 24, 2002
Budget and Expenditures• Baseline Estimate (Jan 99 to completion)
• Labor $3,391,232• Capital $ 836,462• Total $4,227,694
• Current Forecast (Jan 99 to completion) March June October JanuaryLabor $2,866,775 $3,002,938 $2,957,389 $2,986,915Capital $1,074,798 $1,181,900 $1,138,285 $1,384,670Total $3,941,573 $4,184,838 $4,095,674 $4,371,585
• Performance ratios March June October JanuaryBCWS $1,754,979 $2,863,855 $3,085,811 $3,263,216 BCWP $1,611,542 $2,011,383 $2,526,319 $2,899,362ACWP $1,742,651 $2,113,212 $2,762,963 $3,339,222CPI 0.92 0.95 0.91 0.89
SPI 0.92 0.70 0.82 0.87
20
Quarterly ReviewJanuary 24, 2002
Problems and Concerns
• Top level integration has been delayed by 2 months until April 1st– Radiation shield design taking longer than expected– Mechanism rework required to pass flexure tests and fit checks– Focus mechanism design/fab/assembly took longer than expected
• Radiation shield fabrication will extend into March• Documentation (Manuals)
– Maintenance manual outline started; procedures documented as carried out– delayed by focus on mechanism testing and radiation shields
• OIWFS prism installation– OIWFS complete except for installing detector– prism needs to be installed and tested before benches integration into the
dewar – latest date for receipt is 3/4/2002 (with installation hardware)
• IFU– Proceeding with mass models– There is a chance for integration if it arrives in February
21
Quarterly ReviewJanuary 24, 2002
This Page Intentionally Left Blank
22
Quarterly ReviewJanuary 24, 2002
23
Quarterly ReviewJanuary 24, 2002
GNIRS Configuration
• Most design work complete• Remaining work as “punch list”
24
Quarterly ReviewJanuary 24, 2002
Priority Item Actionee Status
1 COLD STATIONING EAH 80% DESIGN COMPLETE
1 ALL ACTIVE SHIELDS EAH 60% DESIGN COMPLETE,
1 ALL PASSIVE SHIELDS GPM DESIGN 100% COMPLETE, DRAFT 55% COMPLETE ~124 DWGS
2 COLD STRAPPING ASSY'S BETWEEN MOTORS AND ACTIVE SHIELDS MED 80% DESIGN COMPLETE
2 COLD STRAPS BETWEEN CRYO COOLERS AND ACTIVE SHIELDS GPM 0% DESIGN COMPLETE
2 ADD HOLES IN FWD BHD AND AFT BHD FOR MOUNTTING PASSIVE SHIELDS STEIN READY TO ADD HOLES
3 THERMAL DISTRIBUTION CONNECTOR ASSY GPM 95% DESIGN COMPLETE
3 WOLLASTON PRISM ADAPTER J RA 0% DESIGN COMPLETE
3 NEED TO STIFFEN PRISM MASKS ON PRISM TURRET (REDESIGN) GPM 0% DESIGN COMPLETE
4 PRE AMP BOX HINGE MOUNT FOR EASY ACCESS TO CIRCUIT CARDS J RA 0% DESIGN COMPLETE
5 TELESCOPE SIMULATOR ? 0% DESIGN COMPLETE
6 LN2 PRECOOL CHECK VALVE & PRESSURE GAUGE FOR GHe PURGE GPM 0% DESIGN COMPLETE
ASSEMBLIES 197
DETAILS 763
ASSEMBLIES 65
DETAILS 101
1126
85%PERCENT OF DRAWINGS RELEASED
GNIRS TO DO LIST
TOTAL NUMBER OF MECHANICAL DRAWINGS DEFINED ON INSTRUMENT
RELEASED
UNRELEASED
DRAWING STATUS
25
Quarterly ReviewJanuary 24, 2002
Shield Status
• Passive shields (2 sets)– 3D design complete– Detailing in progress– Fabrication proceeding as design completes
• Active shields– 3D design in progress– Accurate weight estimate possible
26
Quarterly ReviewJanuary 24, 2002
Active Shield
27
Quarterly ReviewJanuary 24, 2002
Passive & Active Shields (exploded)
28
Quarterly ReviewJanuary 24, 2002
Weight Budget
• Revised Value = 4052 lb– limit = 4409 lb– increase 56 lb from last QR, -61 lb from 3/01– change mainly due to shields, hence only small c.g.
change
• Spot check hardware against models– true weights within 2% of models
29
Quarterly ReviewJanuary 24, 2002
This Page Intentionally Left Blank
30
Quarterly ReviewJanuary 24, 2002
GNIRS Subsystem tests 01/17/2002Test Status
Subsystem Test Type Warm Shop Warm Clean Cold Integrate Remarks
Environmental Cover M Partial Requires dewar shell for completion
Complete Bench O,E Cold check in assembled instrument after integration
Pre-Slit Bench M Done Fit checkOffner+Pickoff O DoneFilter Wheels (2) M DoneSlit+Decker Slides M Done IFU assumed "plug&play"
Post-Slit Bench M Done Waiting for completion of mechanism testsCollimator/Compensator M,OPrism Turret M DoneGrating Turret M DoneAcquisition Mirror M Done Clean test after integration into benchCamera Turret M,O Done Optics tests on assembly done warm after cold
mechanical testsFocus Mechanism M Partial Flexure test neededDetector Mount E Done Done In detector test dewar
OIWFS O,E Done Done Waiting for OIWFS prism & main benchGimbal Mirror M Done Done Done Mechanisms tested at IfAFilter Wheel M Done Done Mechanisms tested at IfA; no cold testing on
FWFocus Stage M Done Done Done Mechanisms tested at IfADetector Mount E Done Done Only MUX tested at IfA; detector tested at mfr.;
detector installation awaiting prism
Test Types:M: mechanical, including optomechanical and switchesO: opticalE: detector tests
Test not possible or not requiredDone Testing complete for this phase
31
Quarterly ReviewJanuary 24, 2002
Subsystem Testing
• Basic philosophy remains unchanged– All subsystems tested prior to integration– Quantify performance for mechanism motion tables,
flexure compensator
32
Quarterly ReviewJanuary 24, 2002
Subsystem Testing (2)
• All mechanisms have undergone functional testing– Some testing on focus remains (1/17)– Need to complete clean/cold tests– Turrets flexure performance determined, provides
initial input for flexure compensator settings
• Optical tests on camera, collimator remain– No alignment required– Fore-optics aligned and tested
33
Quarterly ReviewJanuary 24, 2002
Subsystem Testing (3)
• OIWFS integration nominally complete– System aligned and tested with warm MUX– Need to install science detector– Still limited time to install and check S-H prism
34
Quarterly ReviewJanuary 24, 2002
OIWFS Issues
• All OIWFS software accounted for• MUX readout working• Some setup information incomplete• Electronics documentation incomplete• Operating software is working• Mechanism status (9/20/01)
– Zero is displaced on gimbal Y-axis– Otherwise, hardware appears OK
35
Quarterly ReviewJanuary 24, 2002
Software Components
• Top Level– Instrument Sequencer
– Interfaces to detector, wavefront sensor, components controller, OCS
• Components Controller– Control (CAD, CAR, Apply)
– Status and Alarm database (SAD)
• Low Level Software– Motor control
– Temperature readback
– Pressure monitoring
36
Quarterly ReviewJanuary 24, 2002
Software Work Remaining - Design
• Alarm and Status Propagation– Complete
• WCS/DHS header information– If necessary
37
Quarterly ReviewJanuary 24, 2002
Software Work Remaining - Coding
• Low Level (Hardware Interfacing)– No remaining coding planned
• Components control– Tweak engineering user interface
• Instrument Sequencer and Interfaces– Engineering User interface (ongoing)
38
Quarterly ReviewJanuary 24, 2002
Software Work Remaining - Testing
• Low Level– Prefer fully wired system for end-to-end test– Motors
• Multiple motors simultaneously• Determine distances between limits, switches, etc• Set speeds, acceleration, backlash parameters• Actual mechanism(s) needed
– Temperature Probes• Set calibration curve and individual offsets
– Pressure Sensor• Verify operation in final configuration
39
Quarterly ReviewJanuary 24, 2002
Software Work Remaining - Testing
• Upper Level -- EPICS– Engineering screens provide next level of test
• Top Level -- OCS compliance– use OCSwish
• new tool, in use in Hawaii, verifies OCS interface
40
Quarterly ReviewJanuary 24, 2002
Software Work Remaining
• Simulation allows testing without hardware– Works only for motors.
• Additional work– Lab Support
– Conversion to GEM7 or GEM8
– powerPc on Detector controller
– Mechanism testing• Set configuration files
41
Quarterly ReviewJanuary 24, 2002
Software Work Remaining
• Software is done when – Motors, temperature readback, etc, work at command
line (low level)
– Engineering Screens provide required control and readback
– OCSwish/Acceptance test proves compliance with Gemini system
– GNIRS works on the telescope
42
Quarterly ReviewJanuary 24, 2002
Software Interface Issues
• Array Controller– Interfaced correctly to instrument sequencer?
• OCS– OCSwish will help, but it’s new to us
• OIWFS– real testing is not GNIRS concern.
43
Quarterly ReviewJanuary 24, 2002
Project Management
• Project Status• Schedule & Planning• Milestones• Budget and Expenditures• Organization• Plans for Next Review
44
Quarterly ReviewJanuary 24, 2002
Project Status – Overview
• We are still on track for 2002 delivery – current ship date Oct 3• Critical path is Radiation Shield design and fabrication• Mechanism testing and bench integration is a close second
– Mechanism-to-bench fit checks are done– Mechanism cold tests are beginning– Bench integration completes in March
• Assembly of Post-Slit bench– Bench +Prism, Grating and Camera Turrets, Acquisition Mirror and Collimator
• Assembly of Pre-Slit bench– FW, Slit/Decker, and fore-optics
• Mating of Pre-Slit, OIWFS and Post-Slit benches
• Software and electronics are working– Test and debug completed– Software checks with actual hardware in process
• OIWFS integration is complete– Detector installation remains to be done at a later date
45
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.2 Systems Engineering
• All planned tasks in this work element are complete• Activities over this quarter included
– Oversight of the top level design and interfaces– Coordination of mechanism cleaning and assembly– Mechanism warm tests– Mechanism flexure tests– Fore-optics testing– Resources
• 1.5 Scientists
46
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.3 Mechanical
Mechanism %Camera 99
Detector Focus 92
Environ Cover 99
Acquisition Mirror 89
Slit Decker 95
Filter Wheel 95
Grating Turret 98
Gratings 100
Prism Turret 95
Prisms 100
Motor Drives 100
Bench %Post-Slit 100
OIWFS 100
Collimator 95
POM/Offner 100
Fixed Assembly %Entrance Window 100Cryo-cooler 59Molecular Sieve 100Thermal Dist. 75
LN2 Pre-Cool 83Opt Bench Mount 100Environ Cover Filter 100Bulkhead 100Passive Rad Shield 68Active Rad Shield 17Front Dewar Shell 100Rear dewar Shell 100Vert Inst Frame 100Horiz Inst Frame 100Dewar Mount Truss 100TE Mount Truss 100Shipping Container 0Handling Fixture 100Ballast Weights 100
47
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.3 Mechanical
• All mechanism fabrication complete– Only activity is in rework of items found in testing
• Collimator assembly complete – waiting assembly/alignment
• Fixed assembly 3D/2D design and fabrication remaining – Radiation shields (passive and active)
– Thermal distribution assembly
– Cryo-cooler and manifold
• Resources– 2 ME’s, 3 MD, 4 IM, 1 M&P Eng, 1 Procurement
48
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.4 Electrical
• Design activities are completed
• Instrument Controller electronics thermal enclosure complete
• Work remaining– Fabricate the Thermal Enclosure to Dewar cables
– Harness the cold mechanisms and cold bench as they become available
– Support software testing
– Harness the Bulkhead Assembly
– Dewar warm-up controller fabrication
• Resources– 0.25 EE, 1 ET
49
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.5 Software
• Component Controller code complete• Code has been tested as far as possible before integration
• Testing with mechanisms is underway• Lookup tables for individual mechanisms remain
• Array controller code interface is yet to be verified
• High level (EPICS) code 99% complete
• Resources– 1 SE
50
Quarterly ReviewJanuary 24, 2002
Project Status – WBS 5.8 Procurement
• Major items remaining in procurement– Passive and Active radiation shields
– Cryo-cooler assembly
– LN2 Pre-cool assembly
• There are no major vendor fabrication contracts– Remaining work is radiation shields and small parts/components
• Resources– 1 Tech Associate, production
51
Quarterly ReviewJanuary 24, 2002
Project Status – Optics
• Instrument optics procurement complete– Optics for Telescope Simulator remain
• Filters (still an open item)– 7 filters ordered through UH consortium; 2 failed spec and
vendor may replace
• Tasks left include– Camera alignment(s)– Collimator alignment– Optics alignment tests of assembled benches
• Resources– 1 Optical Tech, 0.25 OE
52
Quarterly ReviewJanuary 24, 2002
This Page Intentionally Left Blank
53
Quarterly ReviewJanuary 24, 2002
Project Milestones by Quarter
As of 1/16/02
Calendar Year Quarter
Number of Milestones
DueRunning
Total
Number of Milestones
CompRunning
Total1999 4th 1 1 1 12000 1st 15 16 15 162000 2nd 13 29 13 292000 3rd 8 37 8 372000 4th 18 55 18 552001 1st 19 74 19 742001 2nd 34 108 34 1082001 3rd 29 137 29 1372001 4th 28 165 28 1652002 1st 47 212 5 1702002 2nd 8 220 0 1702002 3rd 2 222 0 1702002 4th 4 226 0 170
TOTAL 226 170
54
Quarterly ReviewJanuary 24, 2002
GNIRS Staffing FTE by Month
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
Month
FTE
Plan FTE Actual FTE
55
Quarterly ReviewJanuary 24, 2002
GNIRS Work by Month
0
1000
2000
3000
4000
5000
Month
Hour
s
Actual Baseline Jan'02 Plan
56
Quarterly ReviewJanuary 24, 2002
Planned FTE ProjectionJan Feb Mar Apr May Jun Jul Aug Sept Oct
FTE Type NameME Muller 1 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 1ME Hileman 0.5MD Andrew 0.75 1 1 1 1 1 1 0.5 0.25 0.25MD Downey 1 1MD Rosin 1 1MD CircleEE Penegor 0.25 0.25 0.25 0.1 0.1 0.1 0.1 0.1 0.25ET George 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 1 0.5IM Stein 1 1 1 1 1 1IM Bennett 1 1IM Harris 1 1 1 1 1 1IM Lederer 1 1
OPT Camacho 1 1P Wolff 0.1 0.1 0.1P Ruckle 1 1 1 1 1 1 1 1 1 1
OE Ming 0.25 0.25 0.25GT Pina 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
ENG Distler 0.5 0.75 0.75 0.25 0.25 0.25 0.25 0.25 0.25PA Eklund 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25AA Bowersock 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75PE Davis 0.75 1 1 1 1 1PS Elias 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
PSS Joyce 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5PM Gaughan 0.75 1 1 0.75 1 1 0.75 0.75 1 1
Total 16.35 16.6 11.6 10.35 10.6 10.6 7.35 6.85 7.25 6.5Hours 2616 2656 1856 1656 1696 1696 1176 1096 1160 1040
Spend Rate ($/mo) $99,408 $100,928 $70,528 $62,928 $64,448 $64,448 $44,688 $41,648 $44,080 $39,520
Total $ to go $632,624 16648
Jan Feb Mar Apr May Jun Jul Aug Sept Oct15.85 14.1 11.1 10.35 10.6 10.6 7.35 6.85 7.25 6.5
0
2
4
6
8
10
12
14
16
18
Jan Feb Mar Apr May Jun Jul Aug Sept
FTE
57
Quarterly ReviewJanuary 24, 2002
FTE Projection
• Table shows the resources forecast through delivery and training
• Approximately 16,600 hrs total needed to finish the project– This does not include commissioning or the impact of the pending
change order for delivery to Chile
58
Quarterly ReviewJanuary 24, 2002
GNIRS Cumulative Work
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
Month
Ho
urs
Actual Baseline Jan'02 Plan
78,766h[72,677h wo/sci.]
79,725h
63,693h
59
Quarterly ReviewJanuary 24, 2002
GNIRS Capital Spend Plan
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
$1,400,000
Month
Do
llars
Actual Baseline Jan'02 Plan
$759,192
$1,298,665
$1,260,245
60
Quarterly ReviewJanuary 24, 2002
Organization Chart
61
Quarterly ReviewJanuary 24, 2002
Director, NOAOJ. Mould
Director, NOAOJ. Mould
Gemini Projects Project Manager
N. Gaughan
Gemini Projects Project Manager
N. Gaughan
Administrative AssistantM. Bowersock
Administrative AssistantM. Bowersock
Project Scientist, Systems
Engineering J. Elias
Project Scientist, Systems
Engineering J. Elias
Mechanical EngineersG. Muller
Mechanical EngineersG. Muller
OpticalEngineerM. Liang
OpticalEngineerM. Liang
Electrical Engineer
J. Penegor
Electrical Engineer
J. Penegor
Mechanical DesignersJ. AndrewD. Rosin
E. Downey
Mechanical DesignersJ. AndrewD. Rosin
E. Downey
ProgrammerP. Ruckle
ProgrammerP. Ruckle
Project AssistantD. Eklund (.5)
Project AssistantD. Eklund (.5)
Electrical TechR. George
Electrical TechR. George
Support ScientistsD. Joyce
B. Gregory
Support ScientistsD. Joyce
B. Gregory
Procurement & Vender Liaison
A. Davis
Procurement & Vender Liaison
A. Davis
ETSL. Daggert
ETSL. Daggert
General Technician
J. Pina
General Technician
J. PinaInstrument
MakersJ. Stein
R. BennettR. HarrisJ. Irvine
Instrument MakersJ. Stein
R. BennettR. HarrisJ. Irvine
M&PB. Ditsler
M&PB. Ditsler
62
Quarterly ReviewJanuary 24, 2002
Plans for Next Review• The next Quarterly Review will be held in the April 2002 timeframe• The project will be into the Integration and Test Phase
– Flexure testing planned start in late April
• Mechanical design will be complete• Mechanical fabrication will be complete
– except for items associated with flexure testing and shipping container– Some rework items as identified in integration may remain
• Electronics fabrication and checkout completed– Some rework items as identified in integration may remain
• Component Controller Software completed and operating with the Electronics– EPICS level software will still be in work
• OIWFS integration will be completed• Manuals will have started
– Outlines will be done– Manual drafts will have started
63
Quarterly ReviewJanuary 24, 2002
Conclusions
• The current project status shows us to be over 86% complete
• We are on track to deliver in October 2002
• We are near the end of the design phase– Radiation shield design is taking longer than anticipated
– Mechanism testing and rework is taking longer than planned
• We are near the end of the fabrication phase
• All mechanisms have passed warm functional and flexure tests– Exception is focus mechanism which has yet to be fully tested
• The estimated cost of GNIRS is $ 4,371,585– January ’99 to delivery
64
Quarterly ReviewJanuary 24, 2002
Appendix A – ImagesAppendix B – Milestones,
WBS Chart
65
Quarterly ReviewJanuary 24, 2002
Appendix A
Configuration and
Fabrication Images
66
Quarterly ReviewJanuary 24, 2002
OIWFS with Assemblies
67
Quarterly ReviewJanuary 24, 2002
Complete Foreoptics Assembly
68
Quarterly ReviewJanuary 24, 2002
Short Cameras Fit-Checked on Turret
69
Quarterly ReviewJanuary 24, 2002
Four Cameras – Long Blue and Red (far left and right) and Short Blue and Red (center)
70
Quarterly ReviewJanuary 24, 2002
Detector Focus Frame Assembly
71
Quarterly ReviewJanuary 24, 2002
Grating & Prism Turrets and Cold Test Fixtures
72
Quarterly ReviewJanuary 24, 2002
Grating Turret Fit Check into Optical Bench
73
Quarterly ReviewJanuary 24, 2002
Pre-Slit Bench Fit Check
74
Quarterly ReviewJanuary 24, 2002
Prism Turret Mounted to Cold Test Fixture
75
Quarterly ReviewJanuary 24, 2002
Slit Slide Fit Check
76
Quarterly ReviewJanuary 24, 2002
Optical Bench Preliminary Fit Check
Ed Hileman
77
Quarterly ReviewJanuary 24, 2002
Optical Bench Fit Check & Team
Randy Bennett, Ed Hileman, Al Davis, John Stein, Gary Muller, Dick Joyce, John Andrew
78
Quarterly ReviewJanuary 24, 2002
View down Collimator to Optical Path
79
Quarterly ReviewJanuary 24, 2002
Assembled Bulkheads & Dewar Shells before Painting
80
Quarterly ReviewJanuary 24, 2002
Vacuum Testing of Chamber
81
Quarterly ReviewJanuary 24, 2002
Tangent Bars & Collimator Gimbal Mount Ring
82
Quarterly ReviewJanuary 24, 2002
Bulkhead after Painting
83
Quarterly ReviewJanuary 24, 2002
Bulkhead Detail
84
Quarterly ReviewJanuary 24, 2002
Bulkheads being Assembled
Al Davis, Gary Muller
85
Quarterly ReviewJanuary 24, 2002
Fully Assembled Bulkhead & Dewar Shells
Ed Hileman
86
Quarterly ReviewJanuary 24, 2002
Full Assembly on Handling Cart
87
Quarterly ReviewJanuary 24, 2002
Appendix B
Milestones
WBS Chart
88
Quarterly ReviewJanuary 24, 2002
Milestones since MFR (3/01)WBS TASK
Baseline Plan Est. Plan Act. Finish
5.8.1.1.1 RMI Optics Acceptance 6/16/00 3/1/01 3/1/01
5.2.5.5 Design Axis 2 Wiring Diagram NA 3/12/01 3/12/01
5.2.5.6 Fab/Test Axis 2 Wiring Harness NA 3/12/01 3/12/01
5.2.5.8 Mechanism Test Set Complete 9/29/00 3/12/01 3/12/01
5.3.3.1.3.5 Entrance Window Assembly Fabrication Complete 6/8/01 3/12/01 3/12/01
5.3.3.16.1.4 Dew ar Mount Truss Assembly Design Complete 1/5/01 3/13/01 3/13/01
5.4.1.2.5 Motor Drive / Cryohead Control Chassis Complete 8/29/00 4/9/01 4/9/01
5.3.1.8.2.6 Grating Turret Drafting Complete 6/7/00 4/10/01 4/10/01
5.3.3.9.1.5 Bulkhead Assembly Design Complete 9/26/00 4/10/01 4/10/01
5.3.1.2.2.2.4 Long Red Camera Drafting Complete 10/4/00 4/13/01 4/13/01
5.3.1.104.5 Motor Drive Assembly Complete 8/2/00 4/16/01 4/16/01
5.3.1.2.3.1.3 Long Blue Camera Design Complete 5/31/00 4/17/01 4/17/01
5.5.4.1 Channel Access NA 4/18/01 4/18/01
5.3.2.4.2.3.3 Offner Assembly Fabrication Complete 9/11/00 4/24/01 4/24/01
5.3.3.14.1.4 Vertical Installation Frame Assembly Design Complete 12/4/00 4/27/01 4/27/01
5.3.3.15.1.5 Horizontal Installation Frame Assembly Design Complete 12/5/00 4/27/01 4/27/01
5.3.3.17.1.5 Thermal Enclosure Mount Assembly Design Complete 1/23/01 4/30/01 4/30/01
5.3.3.19.4 Handling Fixtures Complete NA 5/18/01 5/18/01
5.3.2.3.3.2.4 Collimator Compensating Mount Design Complete NA 5/23/01 5/23/01
5.5.4.2 Instrument Coordination NA 5/24/01 5/24/01
5.3.2.3.2.1.5 Collimator Cover Box Design Complete 5/5/00 5/30/01 5/30/01
5.3.3.13.1.5 Rear Dew ar Shell Design Complete 3/29/01 5/31/01 5/31/01
5.3.3.9.2.6 Bulkhead AssemblyDrafting Complete 2/21/01 6/1/01 6/1/01
5.3.1.8.6.4 Grating Fabrication Complete 11/28/00 6/1/01 6/1/01
5.3.3.12.1.5 Front Dew ar Shell Design Complete 2/26/01 6/1/01 6/1/01
5.3.3.6.1.3 LN2 Pre-Cool Assemby Design Complete 11/16/00 6/6/01 6/6/01
5.3.1.2.3.2.4 Long Blue Camera Drafting Complete 11/27/00 6/6/01 6/6/01
5.3.3.17.2.6 Thermal Enclosure Mount Assembly Drafting Complete 3/14/01 6/8/01 6/8/01
5.3.2.3.2.2.4 Collimator Cover Box Drafting Complete 8/7/00 6/11/01 6/11/01
5.3.1.7.3.2 Filter Wheel Assembly Fabrication Complete 1/10/01 6/11/01 6/11/01
5.3.3.3.1.4 Cryo Cooler Design Complete 9/26/00 6/12/01 6/12/01
5.3.3.2.2.4 Detector Mount Assembly Drafting Complete 1/4/01 6/15/01 6/15/01
5.3.3.12.2.6 Front Dew ar Shell Drafting Complete 3/16/01 6/19/01 6/19/01
5.3.2.1.8.3.2 Bottom Camera Cover Fabrication Complete 7/21/00 6/25/01 6/25/01
5.3.2.1.8.4.4 Bottom Camera Cover Complete 7/26/00 6/28/01 6/28/01
5.3.3.13.2.6 Rear Dew ar Shell Drafting Complete NA 6/28/01 6/28/01
5.3.2.2.3.1 Receive and Inspect IFA WFS electronics 9/5/00 6/29/01 7/3/01
5.3.1.6.5.3.2 Slit/Decker Assembly Fabrication Complete 3/5/01 6/29/01 6/29/01
5.3.2.1.6.3.2 LCFMH Fabrication Complete 8/1/00 6/29/01 6/29/01
5.8.1.3.1 Flat Mirrors Acceptance 6/2/00 6/29/01 6/29/01
5.3.1.3.2.4 Detector Focus Assembly Drafting Complete 1/26/01 7/2/01 7/2/01
5.3.1.2.6.3.4 Camera Hub Fabrication Complete 12/4/00 7/5/01 7/5/01
5.3.2.1.6.4.4 LCFMH Complete 8/4/00 7/5/01 7/5/01
5.3.2.4.2.4.4 Offner Assembly Complete 9/22/00 7/16/01 7/16/01
5.3.2.3.3.3.4 Collimator Compensating Mount Drafting Complete NA 7/19/01 7/19/01
5.3.3.3.2.4 Cryo Cooler Drafting Complete 11/21/00 7/23/01 7/23/01
89
Quarterly ReviewJanuary 24, 2002
WBS - Total Project
90
Quarterly ReviewJanuary 24, 2002