Top Banner
Copyright © QinetiQ ltd 2006 CONDITIONS OF SUPPLY This document is supplied by QinetiQ for Ofcom under Contract No. C31400/008 Ofcom AMS Final report QinetiQ; PR Edmonds , B Ashforth, DI Elliner & S Madsen TRL; D Harvey, R Allan, S Clover ARUP; B Laidlaw, K Kilfedder QINETIQ/D&TS/SS/CR0600316 Publication number: QINETIQ/06/00039 July 2006 ARUP q q 'This report was commissioned by Ofcom to provide an independent view on issues relevant to its duties as regulator for the UK communication industry, for example issues of future technology or efficient use of the radio spectrum in the United Kingdom. The assumptions, conclusions and recommendations expressed in this report are entirely those of the contractors and should not be attributed to Ofcom.'
129

Qinetiq Report on Geolocation

Nov 22, 2014

Download

Documents

nicky58
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Qinetiq Report on Geolocation

Copyright © QinetiQ ltd 2006

CONDITIONS OF SUPPLY This document is supplied by QinetiQ for Ofcom under Contract No. C31400/008

Ofcom AMS Final report

QinetiQ; PR Edmonds , B Ashforth, DI Elliner & S Madsen TRL; D Harvey, R Allan, S Clover ARUP; B Laidlaw, K Kilfedder QINETIQ/D&TS/SS/CR0600316 Publication number: QINETIQ/06/00039 July 2006

ARUP

q

q

'This report was commissioned by Ofcom to provide an independent view on issues relevant to its duties as regulator for the UK communication industry, for example issues of future technology or efficient use of the radio spectrum in the United Kingdom. The assumptions, conclusions and recommendations expressed in this report are entirely those of the contractors and should not be attributed to Ofcom.'

Page 2: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 2

Administration page Customer Information

Customer reference number 830000/083

Project title OFCOM AMS System

Customer Organisation OFCOM

Customer contact Dr Christos Politis

Contract number C31400/008

Authors

QinetiQ Ltd: Paul Edmonds, David Elliner, Sue Madsen, Ben Ashforth

TRL: Donald Harvey, Roger Allen Steve Clover,

ARUP Communications: Bruce Laidlaw, Ken Kilfedder

Release Authority

Name Giles Bond

Post Research Group leader

Date of issue 07/07/2006

Record of changes

Issue Date Detail of Changes

0.1 17/01/06 First draft delivered as pdf

0.2 18/01/06 Second draft delivered as .doc

1.0 12/5/06 First issue

2.0 15/06/06 Second issue

3.0 07/07/06 Issue for publication on Ofcom website

Page 3: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 3

Executive Summary

This report has been prepared for Ofcom under contract C31400/008 by QinetiQ with contributions from its partners TRL Technology Ltd and Arup Communications through the 2005-2006 Spectrum Efficiency Scheme (SES) initiative. Introduction The radio spectrum is an increasingly important national asset, and so efficient management of it is a high priority. Good spectrum management has direct benefits in terms of improved communications, but also in indirect terms as it supports a vital part of the country’s infrastructure. To understand spectrum usage, Ofcom commissioned a study into the design of an Unattended Monitoring Station (AMS) that could be deployed in large numbers to automatically detect, identify and locate the source of interfering radio signals over a large part of the UK. Ofcom currently have two programmes which utilise unattended equipment for spectrum management and interference resolution purposes. These are a remote monitoring and direction finding system and an unattended monitoring system. Both are deployed at a limited number of sites and cover just a small proportion of the UK. A fully comprehensive network will need far more monitoring stations (original estimates were 2000 but work carried out during this study suggest that as few as 1200 could provide nationwide detection and location of handheld PMRS or 982 for location of 3G base stations). Such stations would need to be automatic in operation, have means of downloading appropriate reports and be relatively cheap to purchase and maintain. It is expected that an AMS network would have the following benefits:

• Enhanced scope of spectrum monitoring, both geographical and transmission types,

• Greater precision in identifying and locating sources of interference,

• Improved responsiveness to interference problems,

• More detailed information on spectrum usage,

• More detailed information on interference patterns.

Page 4: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 4

Project Scope The approach to the study was to begin with a literature search that built on the consortium’s existing knowledge of the state-of-the-art in spectrum monitoring. In parallel with this work, Arup Communications carried out a business case study by assessing the economic aspects of a deployed AMS system and they completed a cost-benefit analysis. Following this, the system approach was analysed using recognised propagation models and geolocation prediction tools to establish the likely performance of the system. Information from the modelling was fed back to the business case. Requirements for a final AMS system were assessed and a design specification created. Concurrently with all these activities, a ‘Proof of Principle’ prototype system was built and demonstrated. TRL led on the hardware build, and the software was developed by QinetiQ based upon previously fielded proprietary products. The purpose of the demonstrator was to de-risk the final system design, demonstrate the concept and to allow trials to take place to evaluate the efficacy of the approach for geolocation in particular.

This final report details the findings of the various work packages associated with this programme. The structure of the document is as follows:

Section 1. Introduction.

Section 2. A review of state-of the-art interference monitoring products.

Section 3. The business case study, conducted by Arup Communications. (This has also been supplied to Ofcom as a stand alone document).

Section 4. The results from applying QinetiQ modelling tools to predict the geolocation performance of the system using time-difference-of-arrival (TDOA).

Section 5. A description of the design considerations for a final deployed system.

Section 6. An overview of the design of the demonstrator units.

Section 7. Results of the trials carried out with the demonstrator units.

Section 8. Conclusions, including further requirements to improve performance for a fully deployed network. Review of current state-of-the-art automatic interf erence monitoring equipment. Work Package 1 required a literature review of automatic interference monitoring equipment with the aim of determining the current state of the art. The main search took place between February and March 2005 and a full report [1] was delivered to Ofcom. The consortium reviewed the collated evidence against the

Page 5: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 5

requirements of an automatic monitoring system that would meet Ofcom’s needs both technically and in terms of cost. A watching brief has been maintained in the interim.

The AMS would be expected to identify unauthorised radio transmissions without operator intervention with a minimum of false alarms. This will require the system to determine the form of modulation in use and to access a database of licenced users.

The requirement implicitly calls for an automatic monitoring system that is equipped with a wideband, fast tuning receiver, both to accommodate the widest bandwidth signals and to achieve the spectrum revisit time. This receiver will also ensure a high probability of intercept against fleeting or intermittent interference. The specified frequency band is 20MHz to 3GHz and there are potentially a very high number of signals simultaneously present.

Conventionally, low-cost receivers with acceptable intermodulation performance are narrowband superheterodyne types. However, both scan rate and instantaneous bandwidth could be well below what is required for this application. There are several manufacturers of wideband tuners of varying size, cost, and fidelity. Unsurprisingly the higher performance models are generally more expensive.

All of the automatic monitoring systems that were reviewed use signal location entirely based on direction finding (DF) techniques. These rely upon multi-element antenna arrays which are generally large and their profiles may not meet planning authority requirements for Ofcom’s application. No systems were found which use the Time Difference of Arrival (TDOA) location technique.

The monitoring capability of the commercially available automatic monitoring systems is generally provided by off-the-shelf spectrum analysers, rather than digitisers. While these instruments offer wide operational bandwidths, the ability of the monitoring system to intercept, analyse and classify transitory or sporadic interference is limited. These off-the-shelf instruments are also designed for laboratory use and are generally bulky and expensive assets.

The survey also revealed that the commercially available automatic monitoring systems:

• have a limited capability against modern signal types such as time and code division multiple access (TDMA and CDMA) where the signals can effectively be stacked on top of each other;

• exhibit particularly poor performance in multipath environments which limits their use in urban or metropolitan areas;

• cannot cope with co-channel signals and have limited classification capabilities in dense signal environments;

• will not support fast scan rates;

Page 6: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 6

• require high signal levels (meaning limited receiver dynamic range), which limits operational range of the system.

• are based on large, calibrated antenna arrays, laboratory spectrum analysers and add-on signal classifiers that makes the systems high cost, high value assets.

An examination of fielded systems in Australia and New Zealand was carried out as these countries have had spectrum trading arrangements in place since 1997 and 1989 respectively. However trades are not taking place regularly enough for them to have had any impact on the spectrum monitoring role performed by the regulators and many of the trades which have taken place have been as a result of mergers and acquisitions, which have not complicated monitoring requirements at all. New Zealand completed their network of Spectrum Monitoring equipment, including fixed stations and vehicles in early 2003, but the system has not yet been used to support or monitor spectrum trades.

Finally, very few of the systems that were reviewed offered any integration with existing databases of license holders and license types. This would be a useful feature as it will help operators to determine quickly whether particular transmissions are licensed or not.

The conclusion of the study was that there is a wide range of automatic monitoring systems currently available or in use on a global basis. However, there are currently no systems that are capable of fully meeting the Ofcom requirements. Identification and Analysis of System Benefits A study was carried out by Arup Communications [2] to assess the costs of introducing new equipment and an assessment of the likely benefits gained. In performing this study, Arup Communications received input from the other consortium parties and also had discussions with Ofcom to get an understanding of the current cost model.

The AMS could be deployed to cover a greater geographic area than the current spectrum monitoring system and is fully effective up to 3GHz. Thus it encompasses high-value transmissions such as GSM and UMTS mobile telephony, broadcast television, and potentially the IMS bands.

The most obvious beneficiary of the AMS system will be Ofcom itself. Additionally however, if Ofcom’s spectrum management duties can be carried out more effectively, all spectrum users will benefit. Agencies such as the Police and Coastguard will have better information with which to pursue a prosecution and some spectrum users such as broadcasters and mobile telephony operators will also benefit from certain summary information that could be made available from the system, either in the form of regular static reports, or by providing direct access to the system itself. A further tangible benefit will be help in establishing a spectrum trading mechanism, by which spectrum holders may sell or rent rights to particular bands to other organisations. With access to good information about current

Page 7: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 7

spectrum use the value of the spectrum could be more accurately determined; and underused spectrum could be easily identified by purchasers.

The costs of commissioning and operating an effective and inclusive AMS system are significant and it would represent a clear step-change from the current UMS and DF operations undertaken from Baldock. Recommendations have been put forward as to how these costs could be financed, and where potential savings can be made from partnerships with site or infrastructure owners.

However, there are huge, less easily quantified benefits of an operational and fully-featured AMS system. In principle, if a very modest efficiency gain of 1% in the use of the spectrum could be attained, that would be worth some £250 million every year. If benefits of this scale could be captured, whether by Ofcom itself or by a commercial enterprise, then a national AMS system could be deployed on a self-sustaining basis.

Modelling Study A modelling study of the proposed AMS formed Work Package 3. The aim was to determine the location accuracy of the interfering signal and the detection range of the AMS allowing a more refined estimate of the likely number of stations. Two location techniques were considered, direction finding (DF) based on multi-element arrays and Time Difference of Arrival (TDOA) – the latter method formed the greater part of the study as it was quickly shown that it provides greater accuracy and sensitivity than DF, and importantly met Ofcom’s requirement for low profile antennas.

TDOA is based on the principle that the distance a signal has travelled is related by its velocity to the time taken. If the signal is simultaneously intercepted by two sensors, the difference between the time-of-arrival of the signal at the two sensor positions can be used to estimate the relative range of the emission source to the two sensors. A line-of-position can then be generated to represent the locus of geographical points that can satisfy the measured time difference.

A model has been developed to determine the range at which a signal could be detected and the accuracy to which it could be located using a TDOA based system. The principle outputs of the modelling are a plot of geolocation error for a regular grid of points within a defined rectangular region, and an indication as to the range over which the signal can be detected.

The model was used to estimate the number of monitoring stations which would be required to provide monitoring coverage of the whole United Kingdom. The country was divided into types from ‘remote rural’ to ‘dense urban’ according to data provided by Arup and a number of exemplar transmitter types were used as test cases for calculating detection ranges. Once predicted propagation losses had been calculated it was possible to estimate the required station density for each transmitter type and area. The results of the exercise showed a significant diversity in the number of required monitoring stations to cover the country for different transmitter types ranging from 13 for pager base stations to 26,727 for GSM mobiles.

Page 8: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 8

A sensible compromise would be to use between 950 and 1200 based on the estimates for 3G base stations and personal mobile radio results.

The model was also used to show the relationship between the amount of data used in the estimation of TDOA and the achievable geolocation precision. These results were to assist in determining the requirement for communications bandwidth between the stations in order to transfer sufficient data for TDOA calculation.

Finally a comparison with DF accuracy was undertaken. Provided the three sensors used for TDOA surround an emitter, the geolocation error does not vary significantly with the distance from the emitter to the sensors. For direction finding however, there is a constant angular error so the calculated position error scales with distance from the sensor.

AMS System Design The purpose of Work Package 4 was to design an unattended monitoring system whose primary purpose is to automatically detect, identify and located the source of interfering radio signals over a large part of the UK.

The requirements called for a solution comprising of a large quantity of monitoring stations, which are networked for control, data collection, and reporting purposes. The system should be capable of fully automatic operation or manual control. It should perform routine monitoring of the spectrum to establish occupancy and locate the source of emissions potentially providing Ofcom with a means of validating a database of licensed user activity.

Based on the findings of the modelling study the system will use TDOA as the location technique.

All functionality will be accommodated in a single environmentally sealed unit that will be mounted close to the antennas in an external location. The power supply will be in a separate unit located inside a building or protective structure.

The design considers options for the various functional elements including receivers, digitisers, timing, processors and antennas and environmental constraints such as cooling and heat dissipation.

Software for spectrum monitoring and signal location has been developed by QinetiQ over the last ten years, and it is recommended that the software for the final system is based on this capability. The following functions have been identified as essential to the system:

• Determine the presence of emissions in the environment and then relate them to emitters using matched filtering techniques. This allows the production on network structure for a frequency and very advanced automation of location and modulation classification assets.

• Display sensor results,

• Log sensor results to hard disk at regular intervals,

Page 9: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 9

• Manage the transfer of the information between sensors to optimally achieve location of all emitters,

• Stream data between sensors to locate all emissions (subject to communications bandwidth available between the units),

• Calculate position fixes based on TDOA techniques based on information from multiple sensors,

• Show position fixes on a digital map,

• Report results dependent upon pre-set filters.

Communication between sensors will be achieved through use of the internet. The system will be capable of providing full control of remote sensors from either regional or national control centres. A network hierarchy for data management is essential to prevent the maximum available bandwidth from being exceeded for the control centres.

Hardware and Software development of the demonstrat or system.

A key part of AMS project was the design and build of three demonstration units to de-risk key technologies that will be required for the final deployed system and to help in identifying the benefits of novel techniques to address the AMS problem. The system is designed as a software based architecture. That is, the hardware is generic and will support a number of different functions, and the intelligence is in the software. This gives the flexibility to upgrade or enhance the capability simply by downloading a new file rather than having to change hardware.

As per the final design, a one unit design was employed. For portability and convenience the systems have been built into transit case type 19” rack units. Commercial-off-the-shelf (COTS) components have been used where possible to reduce development costs. The system consists of two main units: a rack mounted PC, and a custom “RF Tray” designed and built by TRL.

The software installed on the demonstrator system is a prototype of that proposed for the final system and has been developed at QinetiQ over approximately 6 years. Variants of this are used by a number of customers. The challenge was to create a system that would integrate with relatively low cost hardware. The basic capabilities of the application are:

• Real-Time Display – an animated real-time window displays when a connection is made to a remote sensor. This shows a real-time spectrum display along with detected emissions.

• Historical Display - Within this view each emission is represented as a line on a time versus frequency plot. The colour of the line indicates the received signal amplitude and the length of the line indicates the duration of the emission. A real-

Page 10: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 10

time and historical view can be displayed for every sensor the system is connected to.

• Maps - Maps are used both for sensor management (identifying locations of sensors, and as a means of connecting to sensors) and for displaying TDOA position fix results.

• TDOA position fixing - The AMS system supports position fixing by TDOA. When requested to locate an emission the requesting sensor and its two nearest neighbours are identified and tasked to simultaneously capture the signal. This is transferred back to a central point, correlated and mapped onto the ground to give a location.

• Filtering – By using filters it is possible for the operator to focus on signals of interest. Selection can be made on a number of criteria including signal parameters such as signal name or frequency, or geographically to select only signals coming from a selected area.

• Modulation classification – a generic blind classification algorithm is used to classify the modulation type of detected signals.

Sensor performance and trials of the AMS

Initial trials were carried out at Malvern and subsequently at Ofcom’s HQ in London to measure the sensitivity of the sensors, in particular to assess their performance in a densely populated signal environment compared with that in more rural areas. Further trials have been carried out to test the communication across a networked demonstrator system and to assess the effectiveness of the AMS in being able to pinpoint and identify RF transmission sources in real time by TDOA. The London trials showed that signal levels in urban environments can greatly exceed the expected -40dBm at the antenna. Measurements showed a number of signals at the -20dBm level with maximum levels around -10dBm. Receivers used in the system must be able to handle this power whilst maintaining sufficient sensitivity to detect low power signals.

Communication between the sensors is essential. Without a communication link the sensors can still perform spectrum monitoring individually, but they are unable to work co-operatively. To calculate locations a sensor will task its neighbours via the communications link and data will be returned back to the tasking sensor for location processing. The results from all sensors will be complied through a network hierarchy for access from the central control station. The communication link also allows access to real time or historical data from any of the sensors in the network. The demonstrator was designed to operate with 3G mobile phone data cards, but the service at the time in the Malvern area proved to be too unreliable. Instead the system was further developed to operate with a broadband connection. Whilst this introduced time delays into the project the result has been a much more flexible solution which should work with almost any type of internet connection.

Page 11: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 11

The disadvantage of using the internet to network was that it limited the number of available sensor sites available for trials. Initially, limited testing was carried out using employees’ homes but these were often not in optimal locations and the sensors were re-located to more realistic separations in Malvern, Tewkesbury and Pershore which forms a triangular configuration spaced about 17 km apart.

This enabled full testing of the TDOA capability. Multiple captures were taken against a number of signals to allow a good statistical analysis of the results. Most of the targets were FM broadcast radio stations but also pager transmitters, personal mobile radios and mobile phone base stations were used.

Results from the trials generally showed good consistency with the predictions of the modelling exercise. The choice of available targets within the “good” area enclosed within the triangle of the sensors was very limited, so many of the test emitters were in areas where an accurate location would not be expected. The emitters that were close to the triangle of sensors were located to within 150-300m and whilst the accuracy was less further away from the triangle and the geometry of the sensors in relation to the target was poor, in most cases it would still be possible to calculate an accurate direction fix.

In a full nationwide networked system it should always be possible to surround a target by three sensors so the level of accuracy will be more consistent and it should be possible to position fix most emitters of the type studied to within 100 – 200m using a bandwidth of 100kHz.

The trials were limited by the availability of transmitters in suitable locations. It is recommended that further trials be performed using transmitters under Ofcom control. Testing in alternative environments and with different sensor spacing would provide comparative data and will further enhance our understanding of the capability of the system.

Conclusions

The project therefore has concluded that whilst there are a number of automatic monitoring systems currently available they would not fulfil the full requirements of the system that Ofcom wish to implement. Modelling of the TDOA method of geolocation has confirmed that this is an appropriate approach and that it has many advantages over the more traditional DF method based on multi-element arrays. A demonstrator system has been built and trialled and the results were consistent with expectations from the modelling. This has de-risked elements of a final design and provided confidence that the design would meet the requirements that have currently been identified. Finally the cost/benefit analysis carried out by Arup has shown that whilst the cost of implementing a nationwide system are high, so too are the benefits and there are a number of options for financing both the installation and running costs of an AMS system.

Page 12: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 12

List of contents 1 Introduction 17

1.1 Background 17 1.2 An Automatic Monitoring System 18 1.3 The Consortium 19 1.4 Approach 20 1.5 Report Overview 21

2 Review of current state-of-the-art automatic interference monitoring equipment – (Work Package 1) 22 2.1 Introduction 22 2.1.1 Scope 22 2.1.2 Review of current state of the art automatic interference monitoring

systems 23 2.2 Commercially available systems 23 2.2.1 Literature search summary 24 2.2.2 Equipment summary 24 2.2.3 Internet links 29 2.3 Press Releases 29 2.3.1 Conatel Signs $10Mil TCI Spectrum Monitoring Contract 07/02/99 30 2.3.2 Dielectric receives $11 million contract 30 2.3.3 TCI International, Inc. Announces Final System Acceptance of

Spectrum Monitoring System Contract with the Government of Colombia 31

2.3.4 CTS announce systems for India 31 2.3.5 Spectrum to spend US$1-m on airwaves equipment 32 2.3.6 Vodafone Makes the First Data Call on HSDPA (3.5G Wireless) 32 2.4 Conclusions 33

3 Identification and Analysis of System Benefits – (Work Package 2) 35 3.1 Introduction 35 3.2 Benefits 38 3.2.1 More Geographically Inclusive 38 3.2.2 More Inclusive of Transmission Types 38 3.2.3 Precision in Source Identification 39 3.2.4 Responsiveness 39 3.2.5 Information On Current Use of Spectrum 39 3.3 AMS Beneficiaries 39

Page 13: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 13

3.3.1 Ofcom 39 3.3.2 Operators 40 3.3.3 End Users 41 3.3.4 Law Enforcement 41 3.3.5 Emergency Services 41 3.3.6 Research Organisations 41 3.3.7 Spectrum Traders 41 3.4 Benefits Quantification 42 3.4.1 Benefits to radio regulation 43 3.4.2 Benefits to operators 44 3.4.3 Benefits to end users 44 3.4.4 Benefits to R&D 45 3.4.5 Benefits to spectrum trading 45 3.4.6 Summary of Realisable Annual Benefits 46 3.5 Costs Quantification 47 3.5.1 Modelling Assumptions 47 3.5.2 Source Data 48 3.5.3 Build-out 52 3.5.4 Results 53 3.5.5 Sensitivity Analysis 53 3.5.6 Alternative Deployment Scenarios 56 3.6 Financing and Procurement Options 57 3.7 Conclusion 59

4 Modelling study of the proposed AMS – (Work Package 3) 60 4.1 Introduction 60 4.2 Geolocation techniques 60 4.2.1 Direction finding 60 4.2.2 Time Difference of Arrival (TDOA) 62 4.3 TDOA modelling 63 4.3.1 Overview 63 4.3.2 Calculation of propagation loss 64 4.3.3 Theory of operation 65 4.3.4 Calculation of the rms error associated with each TDOA measurement 66 4.3.5 Mapping of TDOA measurement errors to position error 66 4.3.6 Model output 68 4.3.7 Limitations of the model 69 4.4 Example applications 69 4.4.1 Required number of monitoring stations 69

Page 14: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 14

4.4.2 Practical sensor layouts 74 4.4.3 Relation between correlation sample length and geolocation precision 77 4.4.4 Results 78 4.4.5 Scaling laws 80 4.5 Graphical output 80 4.5.1 Co-channel signals 83 4.6 Comparison with DF accuracy 84

5 AMS System design – (Work Package 4) 88 5.1 Introduction 88 5.2 Requirements for the AMS 88 5.3 The proposed solution 97 5.4 Solution Architecture 97 5.4.1 ‘Two-Unit’ Architecture 98 5.4.2 ‘One-Unit’ Architecture 100 5.4.3 Outdoor Unit 102 5.4.4 Thermal Analysis: Power Dissipation 102 5.4.5 Thermal Analysis: Solar Generated Heat 104 5.4.6 Form Factor 104 5.4.7 Mounting Options 105 5.4.8 Connectors 105 5.4.9 Indicators 105 5.4.10 Materials & Construction 105 5.4.11 Environmental Specification 105 5.4.12 EMC Specification 106 5.4.13 Power Supply Unit 107 5.4.14 Summary 107 5.5 Antenna 107 5.5.1 Testing 108 5.5.2 Antenna choices 110 5.5.3 Switching 111 5.6 Functional modules 111 5.6.1 Receiver 111 5.6.2 Digitiser 114 5.6.3 Processor 115 5.6.4 GPS 116 5.6.5 ADC Clock 116 5.7 TDOA architectures 117 5.7.1 Introduction 117

Page 15: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 15

5.7.2 Sensor Selection 117 5.7.3 Timing errors 118 5.7.4 Multipath 118 5.8 Emitter Location techniques 119 5.8.1 Calculation of TDOA position loci 119 5.8.2 The extended three sensor algorithm 120 5.8.3 Maximum likelihood search 121 5.8.4 Simplex Search 122 5.9 Communication between sensors 122 5.9.1 Network control 123 5.9.2 Data storage 124 5.9.3 Data Transfer Messages 126 5.10 Software 127 5.10.1 Current QinetiQ capability 127 5.10.2 Key functionality 128

6 Hardware and software development of the demonstrator system – (Work Package 5) 130 6.1 Overview 130 6.2 Component Layout 131 6.3 Component parts 132 6.3.1 PC 132 6.3.2 Receivers 134 6.3.3 Digitiser 135 6.3.4 GPS 136 6.3.5 ADC Clock 137 6.3.6 Device Control 137 6.3.7 RS232 137 6.3.8 TTL 138 6.4 The RF tray overview 139 6.5 Demonstrator network connectivity 142 6.5.1 Wireless solution 142 6.5.2 Wired solution 143 6.6 Software 145 6.6.1 Introduction 145 6.6.2 AMS GUI 145 6.6.3 AMS GUI Displays 146

7 Sensor performance and trials of the AMS – (Work Package 6). 155 7.1 Aim 155

Page 16: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 16

7.2 MRX Receiver sensitivity 155 7.2.1 Central London trials 155 7.2.2 Possible Receiver Design enhancements 159 7.3 Communications link between sensors 160 7.3.1 Local testing 161 7.4 TDOA location testing 161 7.4.1 Sensor locations 161 7.4.2 Target frequencies 164 7.5 TDOA performance results 164 7.5.1 100kHz Bandwidth results 164 7.5.2 20 kHz Bandwidth results 169 7.5.3 Impact of sample length on accuracy 171 7.6 Comparison with simulation 173 7.7 Conclusion 179

8 Conclusions 181

9 Recommendations 188

10 References 189

11 Abbreviations 191

A Appendix A Literature study – system details 196 A.1 Codem Systems 194 A.2 TCI Spectrum monitoring and management 196 A.3 Communications Research Centre, Canada 199 A.4 SAT SigMon 208 A.5 InterConnect Communications 216 A.6 Rhode and Schwarz – Argus 218 A.7 Transportable Regional Remote Station 224 A.8 Tadiran Electronic Systems 227 A.9 Thales 232

B Appendix B Communications options available within the UK 237

Page 17: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 17

1 Introduction

1.1 Background

QinetiQ have led a consortium, with TRL Technology and Arup Communications, to carry out a research study which included the design of an unattended monitoring system that meets Ofcom’s needs, and the construction of a unit which would demonstrate elements of the whole system. This final report details the findings of the programme and is broken down into sections that cover the various work packages.

The radio spectrum is an increasingly important national asset, and so efficient management of this asset is a high priority. Spectrum management has direct benefits in terms of improved communications, but also in indirect terms as it supports a vital part of the country’s infrastructure. In the same manner that it is difficult to manage a company without management information, it is difficult to manage the spectrum well without information on its usage and quality. The design of an unattended monitoring system whose primary purpose is to automatically detect, identify and locate the source of interfering radio signals over a large part of the UK, is a key component of the Ofcom Spectrum Efficiency Scheme.

The overall net economic benefit from the use of the radio spectrum in the UK was last estimated in 2000 at about £20 billion a year. Allowing for inflation, even a 1% increase in usage brought about by more effective and efficient management would be worth £250 million a year.

Furthermore, as the spectrum, and in particular the unlicensed bands become more congested it is only a matter of time before overuse causes degradation of service. Many services operating within the unlicensed band, for example wireless LAN rely on a low occupancy within their allocated frequency band to give a reasonable chance of getting messages through. As usage increases the number of message failures increases and messages have to be resent leading to even more traffic which can lead to the whole network grinding to a halt. The only answer is to have a better monitoring capability, and to be able to act upon the results of that capability to reactively allocate bandwidth to those users most in need.

Routine monitoring of the radio spectrum by unattended sensors will provide Ofcom with the means of:

• Validating a database of licensed user activity and identifying unauthorised or “pirate” operators or other sources of interference.

• Modifying the rules governing unwanted emissions or modifying the parameters of ultra-wideband transmitters if the noise floor rises rapidly.

• Monitoring if the licence-exempt spectrum is becoming congested or whether the basis on which we have made assignments is not in line with actual usage.

Page 18: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 18

• Providing important information to make a judgement about the introduction of new technologies such as cognitive radio.

1.2 An Automatic Monitoring System

To understand spectrum usage, Ofcom commissioned a study into the design of an automatic monitoring system (AMS) that could be deployed in large numbers to monitor the radio spectrum and detect interfering radio signals with sufficient accuracy to localise and identify the source of the interference.

Ofcom currently have two programmes which utilise unattended equipment for spectrum management and interference resolution purposes.

• The remote monitoring and direction finding (RMDF) system currently consisting of 24 sites with the capabilities to detect signals and their direction of arrival from 20MHz to 3GHz.

• The Unattended Monitoring System (UMS) currently with 44 sites capable of providing occupancy information from 20MHz to 3GHz.

These systems have been deployed separately because the RMDF systems are optimally sited on high ground so that they have the highest chance of receiving an interfering signal, whereas the UMS systems are optimally mounted in city centres where they only receive local signals and so can accurately map the usage in that city.

However, a fully comprehensive network, capable of monitoring the radio spectrum and detecting interfering sources over a large part of the country will need far more monitoring stations than are currently in the network. An original estimate of the number of stations required for covering much of the urban, suburban and some of the rural area was 2000, but this has since been reduced after a business study was conducted, (see Section 3). These stations will have to be automatic in operation, have means of downloading reports of interfering sources automatically or on request and be relatively cheap to purchase and maintain to ensure the network costs are not prohibitive.

Additionally, it is expected that the AMS network would have the following benefits:

• Enhanced scope of spectrum monitoring, both geographical and transmission types,

• Greater precision in identifying and locating sources of interference,

• Improved responsiveness to interference problems,

• More detailed information on spectrum usage,

• More detailed information on interference patterns.

Page 19: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 19

1.3 The Consortium

The consortium, which has already established a track record of providing consultancy to Ofcom, comprised of three parties: QinetiQ Ltd (Prime), TRL Technology Ltd and Arup Communications. Each member brought a wide range of “world class” skills to the consortium.

The consortium members have worked successfully together in the past, and brought a proven track record of research and achievement in all aspects of electronic surveillance and technology development and production.

QinetiQ Ltd is Europe’s largest science and technology organisation. Formerly an agency of the MOD, the company has a distinguished heritage as a leading provider of technology solutions and a supplier of impartial and trusted advice.

QinetiQ has over 9,000 staff, and can supply the creative thought-power of Britain’s biggest independent team of scientists, engineers and internationally acclaimed experts.

QinetiQ’s core business is providing scientific research, test and evaluation for military and civil customers to give them leading edge competitive advantage. In many areas the problems posed by the defence environment require the creation of intellectual property well beyond the state of the art in commercial markets and a reduction in risk.

QinetiQ’s move into the commercial sector provides technology to customers from fields as diverse as transport, health, energy and telecommunications.

The Electronic Surveillance & Counter Measures Group (ES&CM Group) within QinetiQ ltd was the Prime Contractor providing the working interface with Ofcom and overall responsibility for programme delivery.

The ES&CM Group employs more than 120 scientists and engineers who work either in the research of new techniques for exploitation of the RF spectrum or in the continued development of electronic surveillance products for military and commercial customers. The expertise in the design, development and optimisation of hardware and software systems has resulted in our products being used in major procurements for the Ministry of Defence, NATO and the United States Department of Defence. The ES&CM Group has produced software and hardware units that have been sold to Thales, General Dynamics, Lockheed Martin and others, building up a track record of successful delivery.

By teaming with recognised leaders in the manufacture of state of the art technology the Group is establishing a position as one of the leading suppliers of spectrum monitoring products.

TRL Technology is a specialist supplier of surveillance, monitoring and counter measure solutions for satellite and radio communications to defence and government organisations worldwide. TRL has been delivering innovative solutions to these markets for over 20 years since its formation in 1983.

Page 20: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 20

TRL’s customer base is wide ranging and includes the UK Government including Defence Procurement Agency (DPA), Defence Science and Technology Laboratory [dstl] and Government Communications Headquarters (GCHQ). It also supplies to foreign governments of over 20 approved countries and commercial companies including QinetiQ, BAe Systems, Thales, Inmarsat and BT.

Arup Communications has over 20 years experience as IT and business consultants offering fully integrated information and communication technology solutions for the construction, government, transportation, telecoms, education, finance, research, healthcare and corporate sectors.

The core range of services offered by Arup Communications includes strategic advice, technology and business planning, and IT design and implementation. As technology specialists Arup Communications have a wide range of skills including information systems networking, wireless, audio-visual, security and control systems. The company strives to add value by looking at the best ways to use the latest technology to help the public and private sector clients reach their business objectives.

With QinetiQ’s technical and management approach, the expertise from a leading RF systems production company and the in-depth knowledge from a leading business consultancy organisation, the consortium provided Ofcom with the means to carry out an in-depth study into the design and development of an Automatic Monitoring System.

1.4 Approach

The QinetiQ approach began with a literature search that built on the team's existing knowledge of the state of the art in AMS. In parallel with this work, Arup assessed the economic aspects of a deployed AMS system. This was achieved by comparing the predicted costs of equipment options and providing first-pass cost estimates for deploying and running a real-world monitoring network. Following this, the system approach was analysed using recognised propagation models and geolocation prediction tools to establish likely performance. A prototype system was built and demonstrated, with TRL leading on the build, using their knowledge of developing and manufacturing high-technology systems, particularly RF receiver products. This lead to a final design specification for a deployable AMS system. These performance figures and costs were then fed back to further refine the business case.

QinetiQ's design objective was for an AMS unit that is capable of hosting a variety of geolocation and analysis techniques (including hybrid approaches). This enables it to adapt to evolving requirements post network deployment. The key aim has been to design and build a system that is flexible, reconfigurable and upgradeable. This has been achieved by a software based approach – by use of readily available, low cost generic hardware with the intelligence built into the software, the functionality of the system can be changed or upgraded by simply installing a new version of the software.

Page 21: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 21

The design can process emissions from a large number of emitters, encompassing analogue and digital waveforms, and can accurately locate these emitters.

1.5 Report Overview

This Final Report details the findings of the various work packages associated with this programme. Additionally a Design File has been supplied which provides a specification for the design of the final system. It summarises the outcome of the design issues considered in this report, and details the user requirements.

The structure of the document is as follows:

A review of state-of the-art interference monitoring products is given in Section 2.

The findings of the business case study, conducted by Arup Communications and considering the economics of various technical approaches, are presented in Section 3. The cost of deploying, maintaining and operating such a network in the United Kingdom are also discussed.

Section 4 presents the results from applying QinetiQ modelling tools to predict the geolocation performance of the system using Time Difference of Arrival (TDOA).

A description of the proposed solution for a final deployed system can be found in Section 5. To demonstrate the concept, three “Proof of Principle” prototype units have been built. An overview of the design of these demonstrator units can be found in Section 6.

These prototypes have since demonstrated the advantages of the TDOA location techniques as well as fast, wideband scanning and networked monitoring. Details about the trials can be found in Section 7.

Finally the conclusions, including further recommendations to improve performance for a fully deployed network, are in Section 8.

Page 22: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 22

2 Review of current state-of-the-art automatic interference monitoring equipment – (Work Package 1)

2.1 Introduction

Work Package 1 required a literature review of automatic interference monitoring equipment with the aim of determining the current state of the art.

The main search took place between February and March 2005 and a full report [1] was delivered to Ofcom.

In addition, the consortium team reviewed the collated evidence on how the current state of the art automatic monitoring systems can be used to support spectrum regulation, enforce licensing and spectrum monitoring for spectrum trading to support the Spectrum Efficiency Scheme.

A watching brief has been maintained through the remainder of the project and, although this has not identified many developments in the interim, the first data call on 3.5G, also known as HSDPA (High Speed Downlink Packet Access) that enables up to 1.5Mbps transmission speeds has been made by Vodafone and has been noted and added to section 2.3.

2.1.1 Scope

The design of an unattended monitoring system whose primary purpose is to automatically detect, identify and locate the source of interfering radio signals over a large part of the UK, is a key component of the Ofcom Spectrum Efficiency Scheme. Routine monitoring of the radio spectrum by unattended sensors will provide Ofcom with the means of validating a database of licensed user activity and identifying unauthorised or “pirate” operators or other sources of interference.

In automatic mode, the monitoring system would be expected to identify unauthorised radio transmissions without operator intervention. Since a key requirement is to minimise false alarms, the system must be able to determine with high confidence when a transmission is valid. As a minimum, this will require the system to determine the form of modulation in use, and to access a database of licensed users. However, this may be insufficient, and the system may need to progressively build up its own database of dynamic traffic activity/behaviour to identify unusual events.

The Ofcom requirement implicitly calls for an automatic monitoring system that is equipped with a wideband, fast tuning receiver, both to accommodate the widest bandwidth signals and to achieve the spectrum revisit time. This will also ensure a high probability of intercept against fleeting or intermittent interference.

Page 23: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 23

Over the specified frequency band (20MHz to 3GHz) with potentially a very high number of signals simultaneously present, maintaining high receiver fidelity will be essential for correct signal characterisation and avoidance of false alarms. Conventionally, low-cost receivers with acceptable intermodulation performance are narrowband superheterodyne types. However, both scan rate and instantaneous bandwidth are well below the requirement for this project.

There are several manufacturers of wideband tuners of varying size, cost, and fidelity. Unsurprisingly the higher performance models are generally more expensive.

An important part of this study was to focus on the affordable automatic monitoring systems that have the potential to meet (or partially meet) the Ofcom AMS requirement.

2.1.2 Review of current state of the art automatic interference monitoring systems

The consortium team has a wealth of experience in systems that provide emitter detection, location, and signal analysis and have an extensive range of contacts in relevant fields. This meant that the consortium team was ideally placed to review the state of the art in interference monitoring products, using sources and means that may not easily be available in a standard open literature search.

Multiple routes have been taken to compile information for this review. They include:

• Internet searches for relevant technical information; the ITU members web page have been reviewed for relevant information and links.

• QinetiQ ltd using its own sources of information.

• Liaison with Ofcom to compile a list of specific companies that it would wish particular attention to be paid.

The collated information has been tabulated so that Ofcom can compare the current state of the art capability of commercially available automatic spectrum monitoring systems.

In addition, the consortium team has reviewed the collated evidence on how the current state of the art automatic monitoring systems can be used to support spectrum regulation, enforce licensing and spectrum monitoring for spectrum trading to support the Spectrum Efficiency Scheme.

2.2 Commercially available systems

The consortium carried out an extensive search of current commercial and research literature of automatic monitoring systems between February and March 2005. This section describes the commercially available “off the shelf” spectrum monitoring systems that have the potential to meet (or partially meet) the current Ofcom requirement.

Page 24: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 24

A description and a specification of the automatic monitoring systems that were reviewed are given in Appendix A of this report.

2.2.1 Literature search summary

A summary of the search of current commercial and research literature of automatic monitoring systems is tabulated in Table 2.1.

The information given was acquired from numerous sources available to the QinetiQ led consortium and provides a good overview of the current capabilities of commercially available automatic monitoring systems used for spectrum management applications. The information is based on manufacturer’s data sheets and is correct to the best of the consortium’s knowledge, but has not been independently tested so the accuracy cannot be guaranteed.

The summarised data provides all of the known capabilities of all of the systems detailed in the Appendices of this report. If a box is empty then it has not been possible to find the information during the literature search or from follow-up enquiries to the companies concerned.

2.2.2 Equipment summary

The systems found during the literature search meet the requirement for large manual or automatic direction finding systems against single channel interferers such as hoaxers or pirate radio stations.

In addition they all locate signals using angle of arrival direction finding techniques. These have a constant angular error so the position error scales with distance resulting in very large probability ellipses when attempting to locate an emitter at distance.

Against modern multi-channel emitters such as GSM mobile phones or TETRA the systems may possibly work against the base channel but would not distinguish multiple mobile handsets using a single frequency as the DF technique cannot distinguish between multiple co-channel signals.

In addition the systems would not be able to locate an interfering emitter in the presence of the licensed emitter.

Page 25: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 25

Commercially available spectrum monitoring systems

Capabilities WinRadio

MS-8108SR Sat Corp

SigMon 1000 Codem

Eaglenet Aselsan TRRS

TCI TCI 715

Rohde & Schwarz

TMS 100 & 200

Thales Esmeralda

Summary

Mode of Operation

A narrowband receiver monitors a single channel

Wideband and Narrowband

Narrowband Wideband 10 MHz

Narrowband up to 500 kHz

Wideband

Spectrum Scan Yes Yes Yes Yes Yes as per ITU recommendation6 to 6000 per minute dependent upon band.

Yes Up to 750 channels/s (HF), 1000 channels/s (VHF/UHF)

Antenna Up to 6 One

Multiple Options for mobile DF, fixed DF or monitoring only

Various options dependent upon intercept or direction finding system purchased

Multiple options for fixed or mobile HF and VHF/UHF

Page 26: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 26

Capabilities WinRadio

MS-8108SR Sat Corp

SigMon 1000 Codem

Eaglenet Aselsan TRRS

TCI TCI 715

Rohde & Schwarz

TMS 100 & 200

Thales Esmeralda

Frequency Range (MHz)

0.15 to 1500 default 0.14 to 4000 extended.

Any Agilent Spectrum Analyser

20 to 2500 MHz 9 kHz to 3000 MHz

R&S EB200 10 KHz to 3000 MHz

9kHz – 30MHz (HF), 20 MHz – 3000 MHz (VHF/ UHF)

Tuning resolution (Hz)

100 10 Hz to 25 kHz 1 Hz 1Hz (HF), 10Hz (VHF/UHF)

Noise Figure 9dB (HF) 15 dB (VHF)

12 dB Typical 14dB typical (HF), 9dB typical (VHF/UHF)

Sensitivity Typically 1 uV -33 to -8 dBuv/m -124 to -100dBm (HF),

-128 to -108dBm (VHF/UHF)

Dynamic Range 85 dB

No. Narrowband Channels

6 to 8 Unspecified, cost dependent

Modulation Classification

FM, AM, Phase / ITU recommendations.

ITU-R SM 1268-1 (appendix 2), SM 328, BS412-6, chap. 4.6 of ITU-R, SMH, ed. 2002

Page 27: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 27

Capabilities WinRadio

MS-8108SR Sat Corp

SigMon 1000 Codem

Eaglenet Aselsan TRRS

TCI TCI 715

Rohde & Schwarz

TMS 100 & 200

Thales Esmeralda

Modes AM, SSB/CW, FM-N, FM-W

AM/FM/SSB AM/FM/LSB/USB/CW

AM:A2A, A2B, A3E,

CW:NON, A1A, A1B USB/LSB (SSB):J2A, J2B, J7B, H3E, J3E, R3E

ISB:B8E (2 reception channels)

FM:F3E ϕ M:G3E

FSK:F1A, F1B (HF), F1B (VHF/UHF)

TCPIP Data Communications

Yes Yes Yes Yes Yes

Location Method Direction Finding (AOA)

Direction Finding (AOA)

Direction Finding (AOA)

Direction Finding (AOA)

Direction Finding (AOA)

Triangulation (HF, UHF/VHF), option of Single Station Location (SSL) (HF)

Supports > 1 emitter on Channel

No No No No No

Page 28: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 28

Capabilities WinRadio

MS-8108SR Sat Corp

SigMon 1000 Codem

Eaglenet Aselsan TRRS

TCI TCI 715

Rohde & Schwarz

TMS 100 & 200

Thales Esmeralda

Manual Tasking Yes Yes Yes Yes Yes Yes

Licence Monitoring

No No No Licence Violation Detection – via user-defined presets

Licence Violation Detection – via user-defined presets

Can integrate with an existing national licence DB to track violations

No

Scheduled Runs Yes Yes

Client Server Operation

Yes Yes Yes Yes

Table 2.1, Commercially available spectrum monitoring systems

Page 29: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 29

2.2.3 Internet links

The following table gives the Internet URL’s of the commercially available systems covered by this report.

The links to the listed websites were valid to the date of publication of the literature study report.

System Internet URL

WinRadio http://www.winradio.com/home/ms-systems.htm

Sat Corp

http://www.sat.com/products/terrestrial/sigmon_options/sigmon_1000/

Codem http://www.codem.com/content/datasheets/sigint/eaglenet.pdf

Aselsan http://www.aselsan.com.tr/msting/trrs_eng.htm

TCI http://www.tcibr.com/PDFs/715webs.pdf

Rohde & Schwarz

http://www.spectrummonitoring.rohde-schwarz.com

Tadiran Electronic Systems

http://www.tadsys.com

Thales http://www.thalesgroup.com/land-joint/portfolio/pdf/esmeralda_ag.pdf

Table 2.2, Internet URL’s of the commercially available systems covered by this report

2.3 Press Releases

In addition to a review of the commercial and research literature for automatic monitoring systems, the consortium members have conducted a search of press releases dating back to 1999. This avenue of research has provided a good

Page 30: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 30

indication of the current use and deployment of automatic monitoring systems across the globe.

The information presented in this section has been collated from searches of international technical, business and scientific journals and publications. The reports presented in this section are informative and cover a number of systems or manufactures/suppliers listed in this report.

Other press releases were gathered, but the quality of these reports in relation to the worldwide application, technical detail and the deployment of automatic monitoring systems were judged to be less informative to Ofcom than the following examples.

2.3.1 Conatel Signs $10Mil TCI Spectrum Monitoring Contract 07/02/99

CARACAS, VENEZUELA 1999 JUL 2 (NB) -- By Staff, GNCS Business News. Venezuela's telecommunications regulator Conatel has signed a $10 million contract with TCI International (TCII) to buy a country-wide Automated Spectrum Management and Monitoring System for Venezuela.

The system consists of one national control centre, five remote monitoring stations and 10 mobile units, and is scheduled to be completed in 14 months.

Reported by Newsbytes.com, http://www.newsbytes.com

2.3.2 Dielectric receives $11 million contract

February 20, 2004 – SPX Corporation (NYSE:SPW) today announced that its Dielectric business has been awarded an $11 million contract to supply the Botswana Telecommunications Authority. The 2-phase, 13-month contract will include 18 of the company’s TCI brand Spectrum Monitoring Systems, 16 fixed and 2 mobile, along with custom RF Spectrum Management software. The Botswana Telecommunications Authority (BTA) is one of the pre-eminent agencies of its type in Africa and is at the forefront of establishing many of the spectrum monitoring techniques and standards adopted on the African continent. The BTA will use these systems to establish a nationwide network of Spectrum Monitoring Systems to monitor, control and license their wireless spectrum. Dielectric’s systems utilize the latest radio and signal processing technology and will allow the BTA systems to be controlled from a central location in the capital city of Gaborone and cover the 20-3000 MHz frequency range. Many of the Spectrum Monitoring Systems will be installed in unmanned, remote locations. John Capasso, President of Dielectric said, “BTA is leading the development of spectrum monitoring technology in Africa. As we expand our systems globally, we appreciate this vote of confidence from such an innovative partner.” Dielectric Communications is the nation's largest manufacturer of broadcast antenna systems (TV/FM/HF/MF), communication towers, lighting, and signal processing equipment. Based in Raymond, Maine, Dielectric offers complete system monitoring, maintenance, and service to the broadcast and wireless markets. SPX Corporation is a global provider of technical products and systems,

Page 31: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 31

industrial products and services, flow technology and service solutions. The Internet address for SPX Corporation’s home page is www.spx.com.

http://www.dielectric.com/broadcast/news_story.asp?ID=63

2.3.3 TCI International, Inc. Announces Final System Acceptance of Spectrum Monitoring System Contract with the Government of Colombia

Jan. 31, 2000 TCI International, Inc. announced today that on 28 January 2000, the Ministry of Communications of the Republic of Colombia formally and unconditionally accepted TCI's $18M Nationwide Automatic Spectrum Management and Monitoring System in Colombia.

The TCI Model 710 System is believed to be the first such state-of-the-art Telecommunications Infrastructure Modernization Project to be purchased and operated by an indigenous Telecommunications Authority in Latin or South America.

The Colombian Ministry of Communications and TCI are currently discussing the terms of a follow-on contract to provide technical support during the year 2000. TCI looks forward to cooperating closely with the Ministry in future years to supply System spares, maintenance, technical upgrades, and training.

2.3.4 CTS announce systems for India

PARIS, France, 6thMay, 2003 Cril Telecom Software (CTS), the leading provider of spectrum management systems and services, today announced a groundbreaking deal to provide its ELLIPSE spectrum management and monitoring solution to India’s Ministry of Communication. Selected as part of a consortium led by Thales Communications and its partner Himachal Futuristic Communications Ltd (HFCL), this multi-million Euro deal reinforces CTS’s presence in Asia. The CTS spectrum management software, ELLIPSE Spectrum, will allow the Ministry’s Wireless Planning and Coordination (WPC) Wing to securely and efficiently manage its spectrum resources in accordance with International Telecommunications Union (ITU) regulations. The project will be deployed over the next 18 months and enable the Indian Ministry of Communications to realise the following benefits: -Enhanced process automation for improved service quality to network operators; -Optimized network deployment for enhanced end-user services; -Reinforced security measures for aviation and military deployments; -Increased revenues from superior spectrum usage management; -Guaranteed data consistency and increased productivity; -Adoption and use of new telecommunications technology in India. Mr. Y.L. Agarwal, managing director at HFCL International said: “CTS’s Ellipse Spectrum software is a very scalable solution. We were confident we could rely on CTS for our nationwide deployment. The company’s customer base, wide-ranging coverage and compelling commitment to quality were significant factors in our decision to work with them.”

http://www.criltelecom.com/news_documents/023026_WPC_FINAL_gb.pdf

Page 32: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 32

2.3.5 Spectrum to spend US$1-m on airwaves equipment

Wednesday, February 09, 2005 - The technology ministry through one of its agencies, the Spectrum Management Authority (SMA), will invest upwards of US$1 million in equipment and software to improve the monitoring of Jamaica's airwaves for telecommunication firms and radio stations.

The equipment is an automated spectrum management system which can assess, co-ordinate and plan the actual assignment of frequencies.

Another instrument being secured - a remote spectrum monitoring system - will monitor the signals of users anywhere in the island.

"It will provide us with the tools we need to efficiently manage the spectrum," said Ernest Smith, the managing director of SMA.

"The remote monitoring system would be the first in the English-speaking Caribbean, to the best of my knowledge."

The project will be funded from a portion of the US$6 million that the US telecom giant AT&T Wireless, paid the Jamaican government for a cell licence last year.

This means, according to Smith, that the spectrum users would not be charged for the equipment. The SMAs budget is approximately J$60 million.

The SMA is now evaluating four firms to supply the equipment and software the agency having closed the tenders on January 17.

"We are now in the process of evaluating those tenders," he said, adding that the successful candidate would supply the equipment within a year.

"Within 12 months of placement, we expect to have those two operating systems installed and commissioned and functioning."

http://www.jamaicaobserver.com/magazines/Business/html

2.3.6 Vodafone Makes the First Data Call on HSDPA (3.5G Wireless)

14 November , 2005, Europe Portugal :Vodafone today made the first data call on 3.5G, also known as HSDPA (High Speed Downlink Packet Access) as part of the testing program of this important technology.

HSDPA is a technological evolution of the 3G network that permits a considerable increase in transmission speeds. Using this new technology, it is already possible in this initial phase to achieve higher transmission speeds of up to 1.5Mbps, approximately 4 times the speed currently available on 3G (384kbps).

With the introduction of HSDPA, it will be possible to offer new mobile data services and boost Vodafone’s current mobile broadband services such as Internet and e-mail access – the Vodafone Mobile Connect Card 3G and the Vodafone live! 3G mobile portal, along with many of the currently available

Page 33: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 33

information and entertainment services, in particular Mobile TV and video streaming and download on demand.

At the beginning of next year, Vodafone will begin to provide this technology to a limited number of users, including certain partners, customers and employees, with a view to rolling out HSDPA (3.5G) in the second half of 2006.

Through this evolution of the 3G network, Vodafone aims to maintain its leadership position in innovation and data services by ensuring that its customers enjoy high download speeds and an improved mobile experience when accessing various data services.

Vodafone has always been in the forefront of the introduction of new technologies and the development of mobile data services, having pioneered tests in Portugal of both the 2.5G (GPRS) and 3G networks, and having been the first operator to offer 3G services in Portugal with the launch of the Vodafone Mobile Connect Card 3G.

http://www.3g.co.uk/PR/Nov2005/2201.htm

2.4 Conclusions

An extensive study of commercial and research literature has been carried out. There is a wide range of automatic monitoring systems currently available or in use on a global basis. However, a closer inspection of the literature suggests that there are fewer than ten systems that come close to meeting the Ofcom requirements, and none that will fully meet them.

All of the automatic monitoring systems that were reviewed use signal location entirely based on direction finding (DF) techniques, which rely entirely upon multi-element antenna arrays. These antenna arrays are generally quite large and bulky, particularly for operation at HF and VHF and their profiles are not necessarily inconspicuous or unobtrusive.

The monitoring capability of the commercially available automatic monitoring systems is generally provided by off-the-shelf spectrum analysers, rather than digitisers. While these instruments offer wide operational bandwidths, the instantaneous bandwidth has to be reduced if signals close to thermal noise levels need to be analysed. This affects the revisit time and reduces the ability of the monitoring system to intercept, analyse and classify transitory or sporadic interference. These off-the-shelf instruments are also designed for laboratory use and are generally bulky and expensive assets.

The survey also revealed that the commercially available automatic monitoring systems:

• have a limited capability against modern signal types such as TDMA and CDMA where the signals can effectively be stacked on top of each other;

Page 34: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 34

• have limited (if any) signal analysis capabilities particularly against TDMA and CDMA or other complex methods of signal modulation;

• exhibit particularly poor performance in multipath environments which limits their use in urban or metropolitan areas;

• cannot cope with co-channel signals and have limited classification capabilities in dense signal environments;

• will not support fast scan (sample) rates;

• require high signal levels (meaning limited receiver dynamic range), which limits operational range of the system;

• are based on large, calibrated antenna arrays, laboratory spectrum analysers and add-on signal classifiers that makes the systems high cost, high value assets.

In addition, the search has found that in Australia and New Zealand, which have had spectrum trading arrangements in place since 1997 and 1989 respectively, trades are not taking place regularly enough for them to have had any impact on the spectrum monitoring role performed by the regulators. Consequently in these countries the amount of trading is sufficiently low that they do not have a requirement for sophisticated monitoring systems.

Many of the trades which have taken place have been as a result of mergers and acquisitions, which have not complicated monitoring requirements at all. New Zealand completed their network of Spectrum Monitoring equipment, including fixed stations and vehicles in early 2003, but the system has not yet been used to support or monitor spectrum trades.

Very few of the systems that were reviewed offered any integration with existing databases of license holders and license types. This is a useful feature as it will help operators to determine quickly whether particular transmissions are licensed or not. In a dynamic spectrum trading environment, it could be otherwise difficult for operators to determine the validity of unusual transmissions.

Page 35: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 35

3 Identification and Analysis of System Benefits – (Work Package 2)

3.1 Introduction

In this chapter, an outline evaluation of the potential benefits and costs from the deployment of a national network of automatic monitoring stations (AMS network) is developed. It describes the types of benefit that could be expected to arise, the likely beneficiaries and the expected scale of benefits. The capital costs of producing and installing a national AMS network have been developed, and the annual running costs estimated.

Both the benefits and costs of the AMS network have been assessed by comparison with the current methods of monitoring radio frequency use and interference in the relevant bands. Ofcom currently has deployed two systems of unattended equipment for monitoring spectrum use and resolving interference problems in the range 20MHz – 3GHz:

• 24 remote monitoring and direction finding (RMDF) sites located on hill top sites;

• 44 sites of the unattended monitoring system (UMS) located in city centres for the purpose of recording occupancy of the radio spectrum.

The number of RMDF sites may be increased. However, both systems will remain significantly less than national in scope.

The anticipated benefits of the AMS network are:

• Enhanced scope of spectrum monitoring: geographical,

• Enhanced scope of spectrum monitoring: transmission types,

• Greater precision in identifying and locating sources of interference,

• Improved responsiveness to interference problems,

• More detailed information on spectrum usage,

• More detailed information on interference patterns.

These benefits may be summarised as better information on spectrum occupancy or use, including unauthorised use, and better information to support the resolution of interference problems.

Improved information is not a benefit that can be valued directly. Information enables activities to be carried out more effectively or, by reducing uncertainty, enables other activities to be carried out that, in the absence of the information, would not be considered worthwhile.

Page 36: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 36

The potential beneficiaries are:

• Ofcom,

• End Users (citizen consumers),

• Operators – current,

• Operators – future,

• Law Enforcement,

• Emergency Services,

• Research Organisations,

• Spectrum Traders.

Note that the armed forces are excluded from this list, which concerns only civil use of the radio spectrum. The assignment of potential benefits to beneficiaries is described in Figure 3.1.

Geographical Transmission Types Precision Responsive

ness Interference

Info Usage info

Ofcom

Operators

New Operators

Users

Law

Emergency Services

Research

Traders

Figure 3.1, Benefits and Beneficiaries: Dark Green - Significant, Pale Green - Less Significant, White - Not Significant

Page 37: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 37

Economic benefit is not the same as revenue. It is not uncommon for large infrastructure deployments to be undertaken without realisable financial proceeds in excess of total costs being anticipated. The classic example is the Victoria Line on the London Underground network, the construction of which was justified on the basis of improved journey times by users, rather than increased revenues for the service provider or any other party. More recently, the construction of the Channel Tunnel Rail Link, which will replace the current rail link to Waterloo with a new high-speed line from the Tunnel to St. Pancras, has been justified because it will make a 20 minute improvement in journey times from the continent to the centre of London.

Cost-benefit calculations estimate the net effect on economic activity. So, in addition to building up the benefits assessment by looking at a series of discrete benefits and beneficiaries, it is worthwhile also making an overall assessment of the net impact. This can provide a check on the scope and scale of the assessed benefits.

Benefits can be assessed using the standard techniques of cost-benefit analysis. The standard method involves estimating how willingness-to-pay (and willingness-to-produce) varies with price, and taking into account the benefits received by users willing to pay more than the market price, and by suppliers willing to produce for less than the market price. This technique is suited to evaluating the effect of incremental change in a product or service which is already traded in a competitive market. In the case of AMS, however, existing data on spectrum usage is not charged for, so there is not a reference market price on which to base the cost-benefit calculation.

Moreover, while we have developed good information on the costs of supply, this information is not sufficient to support an analysis of potential benefits to producers (“producers’ surplus” in cost-benefit language). We are therefore limited to comparing willingness-to-pay, on the one hand, with estimated costs of supply.

The starting point for the assessment of costs and benefits of the AMS system is the assumption that Ofcom will be responsible for it and the principal beneficiary of the data it produces. We assume that AMS will replace other methods of generating data about frequency use and interference, generating some cost savings. Then, to the extent that the deployment of an AMS network makes radio regulation more efficient or the use of a particular frequency band less susceptible to interference, then the value of these changes can be valued fairly robustly – though not necessarily with precision.

On the other hand, if it is supposed that an AMS network would promote innovation or facilitate the development of a service which does not currently exist– such as spectrum trading, then the valuation of potential benefits become more speculative.

A second major issue is the limited degree to which potentially realisable benefits can be ascribed to the information provided by an AMS network as distinct from

Page 38: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 38

other relevant factors that may contribute to greater efficiency in spectrum use or the reduction in problems of interference.

In general, information that enables economic activity to be more efficient, or the value of an asset to be determined more completely or more precisely, does itself have a value (someone is willing to pay to obtain the information), but this value is limited. For example, the effort that purchasers of assets such as property or a company are willing to expend to confirm the value of their purchase (“due diligence”) may amount to 1% of the value of the asset, but is often much less and rarely more. This is because the alternative to having available good quality information is to make do with less good information. Information primarily reduces uncertainty about asset values; its worth reflects the benefit that can be obtained from the reduction in uncertainty, rather than from the intrinsic value of the asset.

3.2 Benefits

3.2.1 More Geographically Inclusive

The proposed AMS system could be deployed to cover a greater geographic area than the current spectrum monitoring system. It is assumed for the purposes of the benefits analysis that all but the most sparsely-populated areas have full coverage. Although it is possible to deploy AMS units in a more limited fashion, or to deploy them area by area fully benefits will only be realised with a near-complete deployment. We have assumed that some 83% of the UK would be covered by the system, with only regions described by the Office of National Statistics as “Remote Rural” omitted.

The currently-deployed systems are focussed on the busiest areas of the country, with other areas much harder to reach. Each of the beneficiaries listed in section 3.3 has a particular collection of benefits associated with greater geographic coverage.

3.2.2 More Inclusive of Transmission Types

The focus of the existing UMS and RMDF equipment is on frequencies below the 2GHz range. The existing systems are optimal for services such as broadcast radio and PMR. The systems are horizontally polarized, which makes detection of television and some fixed-links problematic. The AMS system is fully effective up to 3GHz, and therefore encompasses high-value transmissions such as GSM and UMTS mobile telephony and broadcast television; and potentially the IMS bands used for wireless LANs over relatively short ranges.

Page 39: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 39

3.2.3 Precision in Source Identification

The currently-deployed DF equipment can identify the location of a high-power transmitter provided there is limited co-channel interference with it, and that there are limited reflections. Even when these two criteria are met, the location precision is within about 600m or so. The AMS system is designed to operate effectively, even for lower-powered transmissions with severe co-channel and reflection effects present. The anticipated location accuracy is in the range of 100m or so.

3.2.4 Responsiveness

The AMS system should be configurable to provide pre-emptive alarms in the event that certain conditions are met. For example, if licensed spectrum were used by a source in an unexpected location, indicating a possible violation. This would enable Ofcom's officers to act in advance of receiving a compliant.

By providing greater location accuracy, the time taken to find infringing transmitters will also be reduced.

3.2.5 Information On Current Use of Spectrum

The AMS system will be able to make a record for every emission it detects and store this in a database. This emissions database will form a valuable resource, with potential applications in academia, industry and to inform Ofcom’s activities.

3.3 AMS Beneficiaries

The most obvious benefits from the AMS system will be in radio regulation. If Ofcom’s spectrum management duties can be carried out more effectively, all spectrum users will benefit.

Some spectrum users will also benefit from certain summary information that could be made available from the system, either in the form of regular static reports, or through direct access to the system itself.

3.3.1 Ofcom

Ofcom will be the key beneficiary of the system. The Communications Act 2003 outlines some specific statutory duties and regulatory principles that would be supported by the AMS network. One of Ofcom’s specific duties is to ensure the optimal use of the electromagnetic spectrum. Good information on the current usage of the spectrum is vital to discovering any inefficiencies.

Another duty is to ensure that a wide range of electronic communication services - including high speed data services - is available throughout the UK. The extent and quality of radio communication services available across the UK could be monitored by a geographically widespread AMS system.

Page 40: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 40

Although Ofcom operates with a presumption against intervention in the market, it must ensure that all such interventions are “evidence-based”. The AMS system could extend the scope of evidence collection for radio communications systems in terms of service type and geographic spread.

Ofcom is required to research markets and remain at the forefront of technological understanding. Knowledge of spectrum occupancy and other market factors and use, especially under the increasingly deregulated, spectrum trading regime could be difficult to obtain without an effective spectrum monitoring capability.

Finally, Ofcom is expected to facilitate law enforcement actions against those who misuse the spectrum, such as pirate radio broadcasters. The greater transmission location accuracy will save time and effort in tracking down misuses.

The AMS system has the potential to improve the efficiency and effectiveness of their work on these all these activities. However, significant additional resources will be required to deploy and operate the AMS system, over and above the currently-deployed systems.

3.3.2 Operators

By operators we mean organisations that operate radiocommunication services, such as broadcasters and cellular mobile telephony operators. A distinction can be made between national operators, with national network obligations and hence an interest in information that is national in scope, and operators whose infrastructure is geographically limited. Incumbent operators are likely to place a higher value on the information than new entrants, since they will be more certain to be able to realise the benefits.

Many national operators are currently working to expand and improve their services. The cellular mobile phone operators continue to install new base station sites to improve the coverage and capacity of their 2G networks, and to roll out 3G systems. Broadcasters are introducing new digital services, both for radio and television.

In both cases, improving geographic coverage is a key driver for the expansion. An AMS system covering the whole of the UK could help them to identify proactively potential coverage and capacity problems without waiting for consumer feedback or deploying survey personnel to the field.

Current operators will also be interested to discover interference sources proactively.

New operators are increasingly deploying new services and installing networks using wireless technologies. For example, there is much current interest in mobile TV, WiMAX and TD-CDMA data networks and in extending WiFi hotspot coverage in metropolitan areas. This trend is likely to accelerate in the near future, as additional frequency bands are auctioned. Spectrum trading may make it possible for frequencies already assigned to be utilised by others, for

Page 41: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 41

example frequencies used by cellular mobile operators. Incumbent and new operators would find it useful to survey the spectrum they intend to sell or acquire before engaging in spectrum transactions.

3.3.3 End Users

End users are also called citizen consumers - the users of radiocommunication services. They will benefit from any improvements to the services offered by the operators. They will also benefit from the potential of the AMS system to streamline Ofcom’s handling of complaints about interference and reception problems.

3.3.4 Law Enforcement

Law enforcement agencies can benefit from improved information on illegal uses of the spectrum. However there is also a potential benefit from the ability of the AMS system to report radio transmissions by criminals. The greater transmitter location accuracy and geographic coverage offered by the AMS system will be key to the benefits for law enforcement.

3.3.5 Emergency Services

Ofcom’s current DF equipment is occasionally used to support HM Coastguard by locating distress beacons and mayday transmissions. Improvements to the accuracy of these location services, the greater geographic coverage offered, or the ability of Coastguard Officers to use the AMS system directly could be very valuable to them on such occasions.

3.3.6 Research Organisations

Academic and commercial researchers are at work developing new radiocommunication techniques and equipment. More complete information about the actual current use of the spectrum could be made available to them to assist in their work.

For example, the database of historical transmissions could be used to inform a realistic simulation of the spectrum usage for the development of cognitive radio technology.

For these groups, the more complete and accurate the dataset, the better.

3.3.7 Spectrum Traders

A key component of the current drive towards spectrum liberalisation is the establishment of a spectrum trading mechanism, by which spectrum holders may sell or rent rights to particular bands to other organisations, without recourse to a central authority. With access to good information about current spectrum use, and how susceptible it is to interference, the value of the spectrum could be more accurately determined; and underused spectrum could be easily identified by

Page 42: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 42

purchasers. Any specialised spectrum trading agents who emerge would have a direct interest in access to accurate and comprehensive information on spectrum utilisation, in order to identify and value spectrum trading opportunities.

3.4 Benefits Quantification

It was noted in the introduction that a realistic valuation of the benefits form deployment of the AMS system would be based on an assessment of the willingness to pay of relevant parties for its output. The scope of this research has not included a rigorous investigation of commercial interest in AMS; rather benefits have been assessed analytically.

Willingness-to-pay is an important criterion because it is, in principle, an objective measure of value and because it underpins calculations of potential future revenues. The total benefits from deployment of AMS will, however, exceed potential revenues. A distinction can be made between the worth of specific information about the value of an asset and the effect of knowing that specific information is now available that was not available before. For example, if precise information can be obtained regarding the performance characteristics of second hand cars, then some purchasers will pay to obtain it, while others may not. But the fact that such information can be obtained at reasonable cost will have a generally positive effect on the value of all second hand cars. Similarly, the knowledge that frequency usage and interference can be readily measured will have a generally positive effect on the value of all frequencies.

The overall net economic benefit from the use of the radio spectrum in the UK was last estimated in 2000 at about £20 billion a year (ref: The Economic Impact of Radio, Radiocommunications Agency 2001). Updating for inflation and the overall growth of the economy would imply that the current value of spectrum use to the country is about £25 billion a year. Almost all this annual value is associated with frequency bands that would be monitored by the AMS system.

It then follows that, if a 1% improvement could be made in the value derived from use of the spectrum, this would be worth £250 million a year. The net present value of this stream of annual benefits would be of the order of £3 billion1. The AMS network may or may not be able to achieve a 1% improvement in efficiency with which frequencies are assigned and used. However, this calculation illustrates the immense potential worth of even minor improvements in spectrum usage.

Whatever their scale, it would probably be impossible to relate the improvement in frequency utilisation to a specific change in economic activity or to a specific impact on asset values. However, assuming an AMS network were able to generate good quality information regarding usage and interference across a broad range of frequencies, then the knowledge that such information was available should raise the value of rights to spectrum by at least 1%, and so will in principle produce a one-off benefit of at least this scale.

1 Based on NPV calculation with a 5% discount rate and a 20-year system lifetime.

Page 43: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 43

Public mobile communications and broadcasting activities accounted for over 75% of the overall net benefits in the 2000 report, suggesting that these two sectors should be the principal focus of attention concerning the potential overall effect of deploying an AMS network.

In public mobile communications, there would appear to be great potential for the enhanced usage of radio spectrum, which could be achieved through a variety of means:

• The assignment of additional frequencies;

• Facilitating secondary assignment;

• Spectrum trading;

• Improved engineering of networks.

The critical question is the role that the AMS network might play in enabling enhanced use of radio frequencies for public mobile communications. In general, it would appear that deployment of the AMS network, though not a necessary or sufficient condition of enhanced use of frequencies being realised, could play a major role in facilitating secondary assignment and spectrum trading (see section 3.4.5 below).

In broadcasting, the methods by which frequencies are planned and allocated means that the potential benefits are likely to be largely limited to the improved resolution of interference issues and more effective deterrence of transmissions from pirate radio stations.

At a high level, therefore, the benefits from successful deployment of a national AMS system are potentially very large in relation to the cost of the investment. In addition to this high-level approach, we have built up estimates for specific types of user of their willingness-to-pay for use of the AMS network, and to identify specific savings that the AMS system might make possible. These figures are possible sources of revenue for the an AMS operator as well as realisable components of the overall economic benefit described above.

3.4.1 Benefits to radio regulation

The first step is to consider the impact on the costs of current regulatory activities. The operation of the AMS network should enable Ofcom to reduce the numbers of its staff engaged in monitoring spectrum usage and in tracking specific cases of interference. A reasonable assumption is that staff numbers might be reduced by about 50, producing savings of the order of £4 million a year. Note that the costs, including staff costs, of operating the AMS system are accounted for in section 5 below.

Improved information should also enable improvements to be made in the conduct of radio regulation more generally. Better information would facilitate faster and more effective decision making. What might be the annual value of this effect as regards Ofcom? Quantitatively the most significant element is likely to be in more rapid detection of unauthorised use of radio frequencies, where the

Page 44: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 44

likely impact of utilising data from a national AMS system would be to produce improvements in the efficiency of detection of the order of 5-10%. Such efficiency gains might be realisable in the form of staff cost savings. The annual cost to Ofcom of detecting unauthorised frequency use is not known precisely but is estimated at about £50 million at current prices. We therefore estimate this benefit at a further £2.5 million a year.

The benefits arising from the increased value of frequencies have been estimated separately above. One consequence of such increased value would be an increase in the proceeds of spectrum auctions, which is a realisable cash benefit. The scale of future spectrum auctions can only be estimated within very wide parameters: based on recent trends, and Ofcom’s plans, we estimate average proceeds for HM Treasury from spectrum auctions of £200 million a year. Applying the 1% value improvement attributable to the AMS system described above produces an annual benefit of £2 million.

The sum of the annual estimated benefits to radio regulation of a national AMS system are therefore £8.5 million. This estimate is subject to a wide margin of error, but is likely to err on the low side. It excludes for example any estimate of the efficiency gains from improved data on spectrum use, other than in detection of unauthorised use.

3.4.2 Benefits to operators

Operators require good information of spectrum usage in order to optimise the deployment of their networks. Cellular operators, for example, can already monitor the throughput of traffic at individual base stations, but this provides limited information on the location of mobile handsets. More precise location information would enable better coverage – and hence higher revenues - or a requirement for fewer installations (lower costs).

Because of the availability of alternative sources of data, whether using alternative techniques as described above, or relying on expert opinion, or a combination of the two, operators’ willingness-to-pay for better information will be only a small fraction of the potential gains to be made from its use. One measure of the benefit of the information to operators would then be the saving in the cost of the additional expertise required to interpret and extrapolate from inferior data. The potential saving in the requirement for expertise in network planning by a national operator would be about 2-3 man years. At a total employment cost of £100,000 per expert, the worth of the improved information is about £250,000 per national operator per year. Assuming 6 national operators, (five mobile operators, plus Airwave), and allowing for a smaller benefit (saving of one man-year of expertise) to each of at least an equal number of regional and specialised operators, suggests a total annual benefit to operators of about £2 million.

3.4.3 Benefits to end users

The benefits of using radio frequencies accrue disproportionately to end users, if benefits are measured by willingness-to-pay. In relation to interference, however,

Page 45: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 45

end users appear to be relatively tolerant; Ofcom investigates just a few thousand cases each year. Even if the benefit to each user of resolving an interference problem is quite high (figures used to estimate the rectification costs of TV reception problems caused by planned tall buildings would suggest about £1-200), the total value to end users of improved efficiency in the resolution of interference problems is unlikely to exceed £1 million.

Benefits to end users arising from greater utilisation of frequency bands and improvements in the services offered by operators will be more substantial; these are considered in the relevant section.

3.4.4 Benefits to R&D

The improved flow of information relating to spectrum usage and interference that an AMS network would produce will be of interest both to academic researchers and to commercial enterprises engaged in R&D activities. While AMS information might well be made available free of charge for these purposes, in principle researchers are willing to pay for information used in their research projects.

We can distinguish between the value of the initial improvement in knowledge to which deployment of an AMS network would contribute, and the continuing flow of data that the network would generate. Valuing in advance the initial gain in knowledge is exceptionally difficult; academic researchers would probably not be willing to pay a significant amount, although an approach to funding R&D that took account of the commercial opportunities that might (or might not) arise would suggest a value of the information in the low millions of pounds.

Once there is an understanding of the type of information that can be produced on a regular basis, researchers should be able more easily to assess its worth. Research undertaken by commercial interests is likely to be the primary source of potential revenues; academic researchers may be reluctant to pay for access to data, even though they would derive significant benefit from doing so – for example, by being able to devote available research budgets to other activities.

The value of the data to researchers can be measured as the saving that would be made in having to generate equivalent information experimentally. We assume that the cost of generating equivalent information would be to employ one research assistant for one year, at a total employment cost of £50,000, including laboratory space and equipment. By surveying ongoing research projects in the radio field, we identified at least five where the type of data the AMS system will produce would be valuable. So we consider a reasonable estimate of the willingness of researchers in the UK to pay for AMS data would be about £250,000 a year.

3.4.5 Benefits to spectrum trading

Spectrum trading is a form of secondary market in rights to use radio frequencies. It should achieve a more efficient allocation of spectrum than would be possible through auction or administrative allocation methods alone. The

Page 46: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 46

precise scope and method of spectrum trading to be adopted in the UK is not yet clear.

The principal effects of an AMS network on spectrum trading are likely to be:

a) improved information regarding the usage made of specific frequency bands in specific areas, thereby enabling more frequencies to be traded;

b) improved ability to enforce property rights in regard to specific radio frequencies, thereby raising the value of tradable frequencies;

c) reducing the cost of spectrum trading transactions

The scale, timing and precise form of spectrum trading in the UK has yet to be determined. Once it is established, the annual trading turnover is likely to be significantly less than the value of frequency rights acquired at auction. It is assumed of the volume of spectrum trading will be 50% of all auction proceeds in any year2, that is about £100 million3 a year – a small fraction of the annual value of the frequencies that are tradable. The willingness of traders - buyers or sellers of spectrum - to pay for the information that an AMS network would produce to underpin their transactions is unlikely to exceed £1million (based on usual level of expense on due diligence).

This underestimates the contribution that an AMS network could make to spectrum trading. The availability of better information about usage and interference will also have a one-off positive effect on the value of spectrum property rights, increasing willingness to pay for frequencies at auction, or to pay licence fees set by an administrative process.

3.4.6 Summary of Realisable Annual Benefits

The table below summarises the annual economic benefits that have been identified and estimated in foregoing sections.

2 That is to say the annual value of spectrum trades is estimated to be about half the total

value of auctioned spectrum. 3 Currently planned auctions account for 290Mhz of spectrum in the next 12 months or so.

The most recent award (the 1781 Award in May 2006), in a perceived lower-value region, brought in around £0.6m per Mhz. Future awards in the UHF band could be very highly valued by the market; therefore an assumption of £200m auction income was made.

Page 47: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 47

Beneficiary Annual benefit

Ofcom £8.5m

Operators £2m

End users interference £1m

Researchers £0.25m

Spectrum trading £1m

Total £12.75m

Table 3.1, Estimated realisable annual benefits

While there is almost certainly a wide margin of error around these estimates, each estimate is likely to be towards the low end of the possible range of estimates. That is, we consider that in each case there are additional benefits that have not been quantified.

3.5 Costs Quantification

An economic model has been constructed which captures the chief costs of procuring, building and operating a network of AMS units to cover all but the most sparsely-populated areas of the UK.

In practise, many of these costs would not be incurred by the same organisation; the model covers the costs that be born by all involved parties. A discussion of financing and procurement options is included at section 3.6.

3.5.1 Modelling Assumptions

The UK can be modelled as regions of Remote Rural, Rural, Sub-urban, Urban and Dense Urban population. We are not interested in covering those areas with very limited transmissions, and therefore omit Remote Rural areas. The Office of National Statistics defines these regions as having fewer than 20 people per square kilometre. We have made no effort to determine where in particular any of these regions are.

The AMS units will be deployed in a set of regular grids of varying densities, with denser grids being required in more populous areas. The combination of known areas and grid densities gave a total population of 982 installed AMS units. (An alternative method, which began with a fixed number of AMS units and worked back to a set of grid densities, was used until detection range information became available).

Page 48: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 48

Each of the covered regions is modelled as having a different type of AMS installation, to account for the cost differences in installing and maintaining AMS equipment in each region. Costs that vary from region to region were site acquisition costs, mounting purchase and installation, and power and network provision. A profile of capital and operational costs was built up for each region type.

Having determined the quantity and location types of the AMS units, an outline build-out schedule was devised, based on a limited build capacity, and resulting in a four-year programme.

Maintenance costs were modelled as a programme of replacement, with a fixed percentage of AMS units being replaced in every year. Separately, a certain percentage of AMS units in each region are modelled as requiring re-location, to account for changes in the surrounding environment. This is in line with Ofcom experience in running the existing RMDF and UMS sites.

3.5.2 Source Data

3.5.2.1 Area Classification

In order to estimate the number of stations required, the anticipated densities in the various urban and rural landscapes has been developed.

The following area classifications have been defined to suit:

• Remote Rural – Remote, largely inaccessible areas of the UK where a density of zero stations will be required.

• General Rural – Sparsely populated countryside and coastal areas of the UK containing villages and towns with a population of up to 10,000.

• Suburban – Suburban areas of the UK, which make up the largely residential outlying areas of settlements with a population of 10,000 or more. Typically consists of 1-2 storey houses.

• Urban – Built-up areas of the UK consisting of settlements of 10,000 of more. Largely town and city centre areas with medium rise commercial and residential premises.

• Dense Urban – A highly developed landscape with many close-knit and high-rise, mainly commercial buildings.

It is recognised that a number of different urban / rural definitions exist and no single classification meets the needs of all users.

The Office of the Deputy Prime Minister (ODPM) recommends using a definition of Urban Settlements being those with a population of 10,000 or more [Source 1 below]. This results in an urban / rural split (by area) of 7% to 93%.

Population density statistics from the Office of National Statistics [Source 2 below] are used to separate out Remote Rural from Rural. Remote Rural areas are defined at the local authority level as those with a population density of 20 people

Page 49: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 49

per square km. This largely includes the Highlands of Scotland and the Orkney and Shetland isles.

Further data from the Office of National Statistics [Source 3 below] is used to separate out Suburban, Urban and Dense Urban areas at statistical ward level.

This results in the following profile of the UK:

Rural Urban

93% 7%

Remote Rural Rural Suburban Urban Dense Urban

17% 76% 4% 2.5% 0.5%

Table 3.2, Percentage of UK in each Region

Sources:

1. Office of the Deputy Prime Minister

Urban and Rural Definitions: A User Guide

http://www.odpm.gov.uk/stellent/groups/odpm_control/documents/contentservertemplate/odpm_index.hcst?n=3331&l=2

Accessed August 2005.

2. Office of National Statistics

Population Density, 2002

http://www.statistics.gov.uk/StatBase/ssdataset.asp?vlnk=7662&Pos=1&ColRank=1&Rank=272

Accessed August 2005.

3. Office of National Statistics

Area Classification for Statistical Wards, 2001

http://www.statistics.gov.uk/about/methodology_by_theme/area_classification/wards/cluster_summaries.asp

Accessed August 2005.

3.5.2.2 Device Detection Range- Number of Units Required

A simulation exercise was performed to determine the likely effective range of detection of the AMS devices. The simulation was based on a regular grid of AMS units at the points of equilateral triangles, placing each one in the centre of a regular hexagon. Each of the four regions was determined to require a

Page 50: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 50

different-sized grid of AMS units. Taken together with the area of each region, this leads to a total number of AMS units of 9824.

Note that the large range shown against Remote Rural is arbitrarily chosen to prevent the allocation of any units to those regions.

Range / km Area per device/ km2 (hex) Number of Devices Remote Rural 10005 2598076.2 0 Rural 15.5 624.2 295 Sub-urban 4.3 48.0 201 Urban 2.4 15.0 405 Dense Urban 2.4 15.0 81 Total 982

Table 3.3, Range, Area and Number of Devices

3.5.2.3 Site Acquisition

Time and effort will be required to locate and acquire each site required for the AMS system. This is modelled as a number of man-days effort with a cost of employment for each officer involved. A different number of days was assumed for each region-type, to include location of a suitable site, negotiations, and other administrative works. A cost of employment of £186 per day was assumed for the officers. It is assumed that sites in urban regions are more straightforward to acquire.

In each region a flat procurement cost was also assumed, to cover costs of legal fees, planning permission, etc.

Leading to the following capital costs (capex) in each area:

Rural Sub-urban Urban Dense Urban Officer Days 20 20 14 14 Site Acquisition (admin, etc) £ 3,720.9 £ 3,720.9 £ 2,604.7 £ 2,604.7 Site Procurement £ 1,000.0 £ 1,000.0 £ 1,000.0 £ 1,000.0

Table 3.4, Costs of Site Acquisition (per site)

3.5.2.4 Mounting Installation

Three different designs for mountings were considered - a steel lattice tower, a monopole tower, and installation on existing roofs. These were each modelled as the sole mounting type in the Rural, Suburban and in the two Urban regions respectively- a simplifying assumption. Tower capital costs were taken from estimates supplied by cellular operators; rooftop mounting capital costs were supplied by Ofcom.

4 This figure is based on detection of 3G base stations. 5 1000 was chosen to be sufficiently large so that the model would not allocate any AMS

devices to this region.

Page 51: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 51

Rural Sub-urban Urban Dense Urban Mounting purchase £ 15,000.0 £ 10,000.0 £ 1,500.0 £ 1,500.0 Mounting installation £ 15,000.0 £ 10,000.0 £ 1,000.0 £ 1,000.0

Table 3.5, Mounting Costs.

3.5.2.5 Site Rental

A different annual site rental cost was assumed in each region, based on discussions with Ofcom about the rental costs paid for placing the existing DF and UMS equipment, as follows:

• Rural - £2,000.0

• Suburban - £3,000.0

• Urban - £5,000.0

• Dense Urban - £10,000.0

These were treated as Operational Costs (Opex).

3.5.2.6 Churn

Experience of operating the existing DF and UMS equipment has shown that there is a significant level of Churn. Owing to various factors, new sites have to be acquired from time to time. For example, changes to building ownership or use, demolitions, proximity of new radio-sources, etc, could all lead to the need to decommission a site, and acquire a new one.

We have assumed that each re-location calls for a new expenditure of Site Acquisition Costs and Mounting costs as described in sections 3.5.2.3 and 3.5.2.4, as opex. In line with Ofcom experience, we have assumed the following levels of re-location are required annually:

• Rural - 1%

• Suburban - 5%

• Urban - 10%

• Dense Urban - 10%

3.5.2.7 Power and Network Access

Each AMS site requires a power supply and access to a reliable data network. In each region, a Capital Cost was assumed for the supply of the required infrastructure, and an Operations Cost for the services were assumed, as follows:

Page 52: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 52

Rural Sub-urban Urban Dense Urban Power Provision £ 10,000.0 £ 6,000.0 £ 3,000.0 £ 3,000.0 Network Provision £ 2,000.0 £ 1,500.0 £ 1,000.0 £ 1,000.0 Power (annual) £ 250.0 £ 250.0 £ 250.0 £ 250.0 Network (annual) £ 500.0 £ 500.0 £ 500.0 £ 500.0

Table 3.6, Power and Network Access Costs

Power provisioning and service charges are in line with Ofcom experience from the UMS equipment. Annual network costs are based on monthly charges of £40, the norm for low-rate wired access. However, this cost is likely to vary with the market trends in telecommunications costs, and according to the particular communications network architecture chosen for deployment.

3.5.2.8 Maintenance

Although it seems clear that the AMS units have few risk points with the potential for hardware failure, a regular program of maintenance has been modelled. Maintenance costs are based on the assumption that, in each region, one in twenty devices, and one in twenty mountings fail every year, and must be replaced. This is not to imply any particular lifetime for the production-spec AMS units.

3.5.2.9 Other Costs

Several costs for planning and operating the network have been included in the model, these are:

• Network Planning - £50,000

• Core HQ Equipment - £100,000

• HQ Staff Costs - £200,000

• Core Network Maintenance - £50,000

• AMS Units Hardware & Antenna (each)- £10,500

• AMS Unit Software (each)- £1,018

The total software cost is allocated amongst the individual AMS units, so that each unit has a software cost of just over £1000. It is clear that the software cost per unit does not scale linearly with the number of units. The figure quoted above is based on an enterprise-wide license of £1,000,000 divided between the 982 units required. If fewer than, 250 units were procured; a per-unit cost would probably be introduced.

3.5.3 Build-out

It is assumed that in each year of construction, 75 rural, 75 suburban, 100 urban and 25 dense urban AMS units are installed. The core network and HQ is established in the first year.

Page 53: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 53

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Core Sites 1 1 1 1 1 1 Rural Sites 75 150 225 295 295 295 Sub-urban Sites 75 150 201 201 201 201 Urban Sites 100 200 300 400 405 405 Dense Urban Sites 25 50 75 81 81 81 Total AMS Sites 275 550 801 977 982 982

Table 3.7, Installed Base of AMS Sites

3.5.4 Results

This gives a cash flow model as follows, in which for every year subsequent to Year 5, a steady state is reached, requiring no further Capital Expenditure and £6.5m in Operational Expenditure:

Capex Year 0 Year 1 Year 2 Year 3 Year 4 Year 5

Core £150,000 £- £- £- £- £- Rural £4,367,945 £4,367,945 £4,367,945 £4,076,748 £- £- Sub-urban £3,280,445 £3,280,445 £2,230,702 £- £- £- Urban £2,162,298 £2,162,298 £2,162,298 £2,162,298 £108,115 £- Dense Urban £540,575 £540,575 £540,575 £129,738 £- £-

Opex

Core £250,000 £250,000 £250,000 £250,000 £250,000 Rural £655,831 £983,747 £1,289,802 £1,289,802 £1,289,802 Sub-urban £901,657 £1,208,220 £1,208,220 £1,208,220 £1,208,220 Urban £1,392,093 £2,088,140 £2,784,186 £2,818,988 £2,818,988 Dense Urban £598,023 £897,035 £968,798 £968,798 £968,798

Total £10,501,262 £14,148,866 £14,728,661 £12,869,790 £6,643,923 £6,535,808

Table 3.8, Cash Flow Model

If the scheme extended to Year 24, the whole project would have a project net present value (NPV) of these costs, given a 5% discount rate, of about £115m. This can be considered the cost of building and operating the system as described. The total Capital Cost (the sum of the first 5 rows of this table) is £36.6 million. Once construction is complete, from Year 6 on, the assumptions above contribute to an annual operational cost of £6.5 million.

3.5.5 Sensitivity Analysis

Some charts follow indicating the relative values of each component of the overall system. They have been constructed by considering the relative contribution of each component to the NPV, total capex and opex above.

The following chart shows the relative cost of each of the modelled regions. Note that the cost levels are disproportionate to the size of the region.

Page 54: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 54

27%

21%

37%

12%3%

Rural

Sub-urban

Urban

Dense Urban

Other

Figure 3.2, Contribution of Each Region to the Project NPV

The following chart shows how each cost element contributes to the system cost. The mountings and site rental costs are the highest elements in the model. AMS units themselves form a comparatively small fraction of the total cost.

3%11%

7%

6%

9%

3%44%

10%

7%Site Aquisition

Mounting

Pow er

Netw ork

AMS Units

Other (2)

Site Rental

Maintenance

Churn

Figure 3.3, Contribution of Each Cost to NPV

Page 55: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 55

The following chart shows the contribution of each cost element to the Capital Cost. Here, the mounting costs dominate.

11%

39%

15%

4%

31%

0%

Site Aquisition

Mounting

Pow er

Netw ork

AMS Units

Other (2)

Figure 3.4, Contribution of Each Cost to the Capital Cost

As shown in the following chart, site rental costs are the highest component of the operational costs of the model.

4%8%

4%

61%

13%

10%

Pow er

Netw ork

Other (2)

Site Rental

Maintenance

Churn

Figure 3.5, Contribution of Each Cost to the Operational Cost

Page 56: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 56

3.5.6 Alternative Deployment Scenarios

The cost model seeks to account for all potential costs incurred in constructing and operating the AMS system on a national scale. It assumes that every site must be surveyed and commissioned individually as part of the deployment of the system.

It should be possible to reduce the capital or operational expenditure of an AMS system in a number of ways. For example, deployment of the system could be focussed more precisely on more populous areas, effectively taking a longer period to achieve national coverage than the four years assumed. However this is likely to reduce both the tangible and intangible benefits to many of the potential beneficiaries for reasons outlined elsewhere in this paper.

Costs could also be reduced by partnering with other organisations to provide some of the required facilities. By partnering with a major landlord, site acquisition and rental costs could be reduced. Site rental is a major component of the operational costs of the modelled AMS system at over 60%. Potential landlords would have to have a nationwide presence in rural, suburban and urban regions - examples include the supermarket chains, the Highways Agency, the Post Office or Network Rail.

Partnering with an existing operator of telecommunications infrastructure might additionally reduce the costs of provisioning mountings, power, and network infrastructure. As indicated, these costs make up about 55% of the capital costs of the AMS scheme. Churn and maintenance costs might also be reduced in this case. The UK’s cellular network operators each utilise thousands of cell sites for their equipment, which have similar infrastructure requirements. The television and radio broadcasters also have significant networks, covering the country with over one thousand transmitters.

Cellular operators typically utilise specialist agents to identify suitable sites for their equipment, negotiate with site owners and manage the installation. In addition, many transmission sites are operated by independent organisations like Arqiva and National Grid Wireless. However, a thorough assessment of the potential for cellular or broadcast equipment to interfere with the AMS units’ effectiveness would have to be undertaken before a site-sharing approach could be adopted - it is quite possible that it is technically impossible to site AMS equipment close to major spectrum users without reducing the sensitivity and therefore the usefulness of the AMS network.

Assuming that it is possible to reduce the overall site acquisition and rental costs by 50% through a partnership with a major landlord, the capital cost of the AMS network would be reduced from £39 million to £37 million. Assuming it is possible to reduce the mounting, power provision and network provision costs by 50%, through partnership with an existing infrastructure owner, a further reduction to in Capex to £27 million would be possible.

Page 57: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 57

Scenario Potential Effect Capex Opex

Self-built N/A £36,630,942 £6,535,808

Landlord Partnership

50% reduction in site acquisition an d rental

£34,584,221 £4,521,808

Infrastructure Provider Partnership

As above, plus 50% reduction in power and network provision and equipment mounting

£24,045,971 £4,521,808

Table 3.9 - Effect of partnership arrangements on Capex and Opex

3.6 Financing and Procurement Options

The analysis presented above suggests that the potential benefits of a nationwide AMS system exceed the prospective costs. The benefits are, however, distributed across a range of parties, including the public at large. The direct benefits to Ofcom itself are not likely to exceed the direct costs that Ofcom would incur in establishing and running the AMS system. That is, there would be a net cost to Ofcom of deploying an AMS system. In this section, we consider the options for financing this net cost.

First, as a regulatory authority, Ofcom does have the option of recovering the net costs of deploying an AMS system via charges to users of the radio spectrum. On reasonable assumptions, the increase in charges to spectrum users necessary to cover the net cost to Ofcom of an AMS system would be about 10%6.

It should, however, be possible to take a more commercial approach to the financing and procurement of the AMS system. We consider three options:

• A wholly commercial venture;

• A PFI-type approach to procurement;

• Outsourcing.

6 Assuming a four year deployment programme and an average life of assets of 10 years,

the annualised capital cost would be £2.4m; the annual operating cost is estimated at £6.5m; the savings on existing staff costs are estimated at £4m. So the annual net cost to Ofcom would be about £5m, which is 10% of Ofcom’s licence fee income, as reported in the Annual Report 2004-5.

Page 58: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 58

Under the commercial venture option, a private organisation establishes the AMS network with a view to selling access to it, analyses and reports generated by it. Commercial interest is likely to be stimulated by several factors:

a) Net revenue potential: the annual benefits quantified in section 4 that could in principle be captured by a commercial venture exceed the projected annual costs of the AMS system7;

b) Strategic positioning: the information generated would give the operator of the AMS system potential first-mover advantages in developing new services, including spectrum trading;

c) Export potential: successful establishment of a national AMS system might lead on to similar opportunities in other countries.

These factors suggest operation of an AMS system might be commercially attractive to equipment manufacturers, infrastructure operators and communication service providers.

It would be necessary of course to ensure that the operator of the AMS system did not secure an unfair commercial advantage through its ability to control access to the information generated.

Ofcom would act as the project sponsor and would be a principal customer, entering into a long term contract but not providing any guarantees. The transfer of commercial risk to the operator would have the consequence that the charges to Ofcom and to other users would have to exceed costs though obviously not their willingness-to-pay. If the estimates of willingness-to-pay in Section 3.4 are robust, then commercial interest would largely depend on the prospect of securing significantly lower capital or operating costs than outlined in Section 3.5.

Under a PFI-type approach, a private organisation would establish the AMS network, with a guaranteed annual revenue stream from Ofcom over its expected lifetime (15-25 years). The scale of the investment is above the minimum level at which project financing can be considered economic.

In return for the guarantee, Ofcom would expect to have a greater say in the design and deployment of the system, and in the terms on which information generated by the system was made available to third parties. While this would have advantages in maximising efficiency gains in radio regulation and non-discriminatory access to information, the result might be a solution too closely tailored to UK requirements to be successfully exported.

Under an outsourcing approach, Ofcom would own the assets comprised in the AMS system but it would be operated by a commercial organisation acting on behalf of Ofcom. Ofcom’s outsourcing partner could also be responsible for handling sales of information and other services to third party users of the system.

7 The estimated annual benefit of £1m to end users from reduction of interference probably could not be captured directly.

Page 59: Qinetiq Report on Geolocation

Ove Arup & Partners Ltd

QINETIQ/06/00039 Page 59

The merits of outsourcing in this case are that Ofcom would be able to secure reductions in staff costs and efficiencies in operating the system while avoiding giving long-term revenue guarantees to the operator. Ofcom would, however, be required to bear the capital cost and the commercial risks of deploying the system.

Which, if any, of these financing and procurement options can be taken up will depend on market-testing to establish the degree of commercial interest, and on the extent to which the conditions under which an operator would accept all or part of the commercial risk of deploying an AMS system are compatible with Ofcom’s requirements.

3.7 Conclusion

The costs of commissioning and operating an effective and inclusive AMS system are significant. With a likely capital cost of tens of millions of pounds, and an ongoing operational expenditure of millions of pounds, it would represent a clear step-change from the current UMS and DF operations undertaken from Baldock. We have shown how these costs could be financed in several ways, and outlined potential savings from partnerships with site or infrastructure owners.

However, the benefits of an operational and fully-featured AMS system are considerable, and potentially dwarf the costs. Specific benefits have been quantified above by assessing the willingness of the relevant parties to pay for the information that an AMS system would produce; these benefits amount to £12.75 million every year. The capital cost of the system is estimated at £36.6 million over four years, with an annual running cost thereafter of £6.5 million at current prices. Based on these estimates, the project has a positive net present value in excess of £42 million.

If benefits of the scale estimated could be captured as revenue, whether by Ofcom or by a commercial enterprise, then a national AMS system could be deployed on a self-sustaining basis. This may not be possible. Accordingly, a range of ways in which the AMS system could be funded and operated have been explored.

Page 60: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 60

4 Modelling study of the proposed AMS – (Work Package 3)

4.1 Introduction

A modelling study of the proposed AMS formed Work Package 3. The aim was to determine the location accuracy of the interfering signal and the detection range of the AMS allowing a more refined estimate of the likely number of stations.

Two location techniques (described briefly in Section 4.2) were considered:

• Direction finding (DF) based on multi-element arrays,

• Time Difference of Arrival (TDOA).

Most of this section concentrates on the Time Difference of Arrival technique. Direction finding was discounted at an early stage as it can be shown that both the accuracy and, more importantly the sensitivity is far greater for the TDOA system. Additionally, a DF system would require large calibrated multi element antenna arrays which do not meet Ofcom’s requirement for small inconspicuous installations

4.2 Geolocation techniques

4.2.1 Direction finding

Obtaining an emitter position estimate from a DF (Direction Find/Fix) is conceptually one of the simplest methods of geolocation (Figure 4.1). DFs can be combined most simply by using triangulation in order to estimate the position of a target. The same method can be used by multiple sensors each obtaining a DF estimate of the same targets, or a single moving sensor obtaining multiple DFs of the same targets at different positions as it moves.

Page 61: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 61

Figure 4.1, Combination of DF to give a position

This method of geolocation is versatile, in the sense that it can be used with either single or multiple-platform systems, and can be used even when there are distinct differences between the sensors involved, as long as the errors associated with each DF measurement are known.

Combination of DFs

The algorithms which combine the DF measurements have a significant influence on the performance of the technique. The Stansfield algorithm is probably the most common choice. This provides a method for statistically determining the most likely location of an emitter given at least three lines of bearing (LoB) and the associated error (if there are only two LoB, the most likely emitter location is where the two lines cross) (Figure 4.2). Stansfield (1947) provides a statistical means to determine the most likely location of an emission source, given LoB to that source and the error associated with each bearing measurement. Using this method, Stansfield shows that if there are three intersecting bearings, the most likely emitter position, may not necessarily lie in the centre of where those bearings cross. Stansfield also provides a method to calculate an area of uncertainty/probability associated with the estimated emitter location. This typically has an elliptical shape and is associated with a specified level of probability. For example a 95% probability ellipse indicates that in 95/100 times the actual emitter location will lie within that ellipse.

An alternative method of estimating an emitters location is to overlay lines of bearing on a map to determine a probability image.

Page 62: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 62

Figure 4.2, Combination of DF by Stansfield

4.2.2 Time Difference of Arrival (TDOA)

TDOA is based on the principle that distance/range is related to velocity and time (Figure 4.3). The distance between an emission/signal source and the position of a sensor can be calculated if the velocity of the signal is known (RF emissions travel at c, the speed of light), and the time taken for the signal to travel that distance

Figure 4.3, Time delay on a transmitted signal

The sensors do not have any a-priori signal information, so, although the sensors can report the time at which a signal was received, a single sensor on its own

Page 63: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 63

cannot determine the emission range, since it does not know at what time the signal was transmitted.

Alternatively, if the same signal is intercepted by two sensors, the difference between the time of arrival of the signal at the two sensor positions can be used to estimate the relative range of the emission source to the two sensors (Figure 4.4). The Time Difference of Arrival of a signal between two sensors can be used to generate an isochron. This isochron represents the locus of geographical points that can satisfy the measured time difference. (a) With two static sensors, only a single isochron can be generated. (b) Using TDOA alone, a position fix can be generated if a third sensor is available, so that TDOA curves can be generated for two additional baselines, and then combined to determine a PF.

Figure 4.4, TDOA with 2 and 3 sensors

4.3 TDOA modelling

4.3.1 Overview

A model has been developed to determine the range at which a signal could be detected, and the accuracy to which it could be located using a TDOA based system. For a comparison with a DF based system see Section 4.6.

Page 64: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 64

The modelling was restricted to the use of TDOA by three monitoring stations to estimate emitter position. One station was regarded as the ‘master’, with the TDOA with respect to the other two stations being used to determine emitter position.

The modelling assumes that TDOA values are estimated by finding the position of the “peak” in the cross-correlation of the two signals.

The principle output of the modelling is a plot of geolocation error for a regular grid of points within a defined rectangular region (Figure 4.13). The metric used for geolocation error is Circular Error Probable (CEP) which is defined as the radius of the circle centred on the true emitter position within which there is 50% probability of the estimated emitter position falling. This metric is equal to the median error distance of the position estimate.

Modelling of a particular scenario is in two stages. The first is the calculation of propagation loss as a function of distance. The second is the calculation of geolocation error based on that propagation loss profile, using a MATLAB model.

4.3.2 Calculation of propagation loss

Propagation loss as a function of range was calculated using the Microcomputer Spectrum Analysis Models Land Mobile Services application (MSAM LMS) produced by the US Dept of Commerce National Telecommunications & Information Administration.

The following is an extract from the application’s Help file, regarding the pedigree of the application:

Most of the programs were developed at National Telecommunications and Information Administration (NTIA), both at the Office of Spectrum Management (OSM) and Institute of Telecommunications Sciences (ITS). Some of the models were developed at the Joint Spectrum Center (JSC), formerly the Electromagnetic Compatibility Analysis Center (ECAC) of the Department of Defense (DOD), Annapolis, MD, and were modified to meet NTIA's requirements. The programs have been verified to be correct for many scenarios run over a number of years. NTIA assumes no responsibility for the results generated by these programs except to guarantee that the programs will run on Microsoft Windows.

Various parameters can be set including frequency (MHz), environment (‘open’, ‘suburban’, or ‘urban’), city size (if applicable), height of base station antenna (m), height of mobile antenna (m) and the percentage of time and locations for which the calculated propagation loss is not exceeded. The ‘Base Station’ is taken to be the monitoring station, and the ‘Mobile Antenna’ to be the transmitting source. ‘Height of Base Station Antenna’ is the HAAT (Height Above Average Terrain) value, This is a formally defined metric, and is

Page 65: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 65

essentially the height with respect to the average height of the terrain between 3 and 16 km from the antenna.

There are three propagation loss models available; Okumura-Hata ITU 529 [3][4], the Modified Cost 231 [5] and the Okumura-Hata Davidson [6]. The ranges of parameter values for which these are valid are shown in Table 4.1.

Model Okumura-Hata ITU 529

Modified Cost 231 Okumura-Hata Davidson

Frequency range (MHz)

150 – 1500 1500 - 2000 30 - 1500

Distance (km) 1 - 100 1 - 100 100 - 300

Base station antenna height (m)

30 - 200 30 - 200 200 – 2500

Mobile antenna height (m)

1 - 10 1 - 10 1 - 10

Table 4.1, Parameter ranges for the available propagation loss models

The maximum distance for which the propagation loss is calculated needs to be large enough to suit the scenarios that will be subsequently modelled. For larger distances than this, the MATLAB model sets the propagation loss to an arbitrary high value (300dB). The minimum distance for which the calculated propagation loss is valid is 1 km. However, the ‘Report for Distance Range’ mode allows a minimum distance of 0.1 km to be used. For distances less than the minimum available, the MATLAB model sets the propagation loss to that for the minimum available distance.

4.3.3 Theory of operation

Calculation of the geolocation error for each point of the grid has two steps. The first is the calculation of the rms error associated with each of the two TDOA measurements. The second is conversion of the TDOA measurement errors into the corresponding error in position.

There are two conditions which lead to a valid error estimate not being obtainable for a particular point. The first is poor geometry, as detailed in 2.4.4 below. The second is if the cross-correlation of the signals used to estimate TDOA does not have sufficient SNR for the correlation peak to be reliably detected. Note that the modelling does not require the signal to be detected by any of the stations prior to correlation.

Page 66: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 66

4.3.4 Calculation of the rms error associated with each TDOA measurement

The rms error associated with each TDOA measurement is modelled as having the following independent components:

1. The fundamental error in determining the position of the correlation peak due to the finite SNR of the signals being correlated. This is the Cramer-Rao lower bound (CRLB) value given by reference [7]. In computing the SNR, the presence of a co-channel interferer is accounted for by adding its received power to the computed noise power.

2. The error in synchronisation between the two stations.

3. A component to account for the shift in the signal correlation peak caused by a co-channel interferer having its correlation peak very close to that of the signal of interest. Although this is actually a deterministic bias in the estimated TDOA value, it has to be modelled as a random component.

4. A component to account for the shift in the signal correlation peak due to multi-path propagation effects.

The errors in the two TDOA measurements are also assumed to be independent.

4.3.5 Mapping of TDOA measurement errors to position error

To allow an analytic solution, geolocation using TDOA is assumed to make use of the signals from only 3 monitoring stations. It is also assumed that the 2 TDOA measurements which are used to compute the emitter position are between station 2 and station 1, and station 3 and station 1 respectively. Let the bearing and range from the emitter to the ith station be φi and Ri respectively. Here bearing is defined as the angle anti-clockwise from the x-axis. If the emitter were to be displaced from its true position by (dx dy), as shown in Figure 4.5, then dRi = -dx cos φi - dy sin φi

Equation 1

Page 67: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 67

dx

dy

R1 + dR1

R2 + dR2

R2

R3 + dR3

Φ2

Φ1

R1

R3

Φ3

Figure 4.5, Relation between TDOA errors and position error

The effect on the TDOA measurements would be: d TDOA21 = [ dx ( cos φ1 - cos φ2 ) + dy (sin φ1 - sin φ2 ) ]/c

Equation 2

Page 68: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 68

d TDOA31 = [ dx ( cos φ1 - cos φ3 ) + dy (sin φ1 - sin φ3 ) ]/c

Equation 3

This can be expressed in matrix form

=

dy

dxM

dTDOA

dTDOA

31

21

Equation 4

Suppose now that the dTDOA terms are errors in measuring TDOA. (dx dy) would be the resulting errors in the estimated position according to:

=

31

211

dTDOA

dTDOAM

dy

dx

Equation 5

If the errors in the TDOA values are independent with variance σ2

TDOA , then it can be shown that the covariance matrix for the errors (dx dy) is given by:

σ2TDOA M-1 (M-1)T

Equation 6

If M is not invertible, it indicates that the geometry for geolocation is very poor, in that one or both of the TDOA values is insensitive to the emitter position. This occurs if the two stations making the TDOA measurement have the same relative bearing with respect to the emitter. If the covariance matrix has eigenvalues e2

1 and e22 , then the median error

distance CEP is approximated by 0.59 (e1 + e2). Note that the covariance matrix is sensitive to the choice of station 1.

4.3.6 Model output

The model generates five outputs:

1. The plot of the geolocation error, over the defined rectangular region.

Page 69: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 69

2. A thresholded plot of the geolocation error. The colour map of this plot has been set to clearly indicate the points within the region for which a valid geolocation estimate could not be obtained.

3. A contour plot of the geolocation error.

4. A text file detailing various statistics of the geolocation error, distinguishing between the whole rectangular region and the triangular region defined by the 3 monitoring stations.

5. A plot showing the number of sensors which could detect the signal over a given area.

4.3.7 Limitations of the model

The main limitations are associated with the calculation of the propagation loss. For example, the effect of multi-path on geolocation accuracy is not explicitly considered. More generally, the model only predicts geolocation accuracy for a typical area of the defined type (‘Open’, ‘Suburban’ etc.). Much more detailed modelling would be required in order to predict accuracy for a specific scenario.

4.4 Example applications

4.4.1 Required number of monitoring stations

The aim of this exercise was to determine the number of monitoring stations which would be required to provide monitoring coverage of the whole United Kingdom. The exercise consisted of the following steps:

1. Divide the total area of the UK into specified percentages of different area types, corresponding to different propagation conditions.

2. Define a set of exemplar transmitter types.

3. For each combination of area and transmitter type, calculate the maximum detection range by the monitoring station.

4. For each transmitter type, determine from the maximum detection ranges the required density of monitoring stations.

The UK was divided into area types as shown in Table 4.2 below. This data was supplied by Arup as part of their investigations into usage of the system.

Page 70: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 70

Total area of the UK in km2 242,514

Area Type Proportion Area (km2)

Remote Rual 17.00% 41,227.4

Rural 76.00% 184,310.6

Sub-urban 4.00% 9,700.6

Urban 2.50% 6,062.9

Dense Urban 0.5% 1,212.6

Table 4.2, Division of the UK into area types

The area types were mapped into the Okumura Hata-Davidson (OHD) area types according to Table 4.3 below.

Area type (Arup) Area type (OHD)

Remote rural Not required

Rural Open

Sub-urban Suburban

Urban Urban-Small/medium city

Dense urban Urban – Large city

Table 4.3, Mapping of area types

The following exemplar transmitter types (Table 4.4) were used as test cases for calculating detection ranges. (The parameters were chosen in conjunction with Ofcom).

Page 71: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 71

Type Frequency(MHz)

Tx power (W)

Antenna height (m)

Required receiver bandwidth

Pirate radio station 100 10 10 150 kHz

Pager base station 153 100 10 25 kHz

Personal Mobile Radio (PMR) base

450 5 10 12.5 kHz

Personal Mobile Radio (PMR) mobile

450 0.5 2 12.5 kHz

GSM base station (Vodafone & O2)

950 1500 10 200 kHz (single channel)

GSM mobile (Vodafone & O2)

900 2 2 200 kHz (single channel)

GSM base station (T-Mobile & Orange)

1840 1500 10 200 kHz (single channel)

GSM mobile (T-Mobile & Orange)

1750 2 2 200 kHz (single channel)

3G base station 2000 20 10 5 MHz

Table 4.4, Exemplar transmitter types

Receive antenna height 20 m, 50 m for ‘Dense Urban’ area type

Receive antenna gain 0 dBi

Transmit antenna gain (to monitoring station)

0 dBi

Received SNR required for detection 10 dB

Receiver noise figure 14 dB

Table 4.5, Other modelling parameter values

Page 72: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 72

The propagation loss observed at a given range for a given area type varies with both time and location. For this exercise, the values of propagation loss used were those which would not be exceeded for 50% of times and 50% of locations.

The criterion for detection is that the ratio of signal power to noise in the signal bandwidth to exceeds 10dB. This is slightly different to how detection is carried out in the demonstration system. In this, detection is with respect to a fixed channel bandwidth of ~3kHz and there is some averaging of the noise prior to detection.

Figure 4.6 and Figure 4.7 show some sample received SNR profiles. The detection range is taken as the point at which the received SNR drops below the 10dB line.

Received SNR for several transmitter typesRural environment

-60

-40

-20

0

20

40

60

80

1 10 100

Range (km)

SN

R (

dB)

GSM Base Station

Pirate Radio Station

GSM Mobile

3G Base Station

Personal Mobile Radio

10 dB detection threshold

Figure 4.6, Received SNR for several transmitter types: Rural environment

Page 73: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 73

Received SNR for several transmitter typesUrban environment

-60

-40

-20

0

20

40

60

80

1 10 100

Range (km)

SN

R (

dB)

GSM Base Station

Pirate Radio Station

GSM Mobile

3G Base Station

Personal Mobile Radio

10 dB detection threshold

Figure 4.7, Received SNR for several transmitter types: Urban environment

The maximum detection ranges for all combinations of transmitter and area type are given in Table 4.6 below.

Rural Sub-Urban Urban Dense Urban

Pirate radio station 57 26 20 23

Pager base station 100 50.5 37.5 47.5

PMR base station 52.5 25 16.8 14.5

PMR mobile 12.5 4 2.3 3.7

GSM base station (Vodafone/O2) 81 37.5 24 19.5

GSM mobile (Vodafone/O2) 6 1.8 1 1.4

GSM base station (T-Mobile/Orange) 61 30 16.5 23.2

GSM mobile (T-Mobile/Orange) 3.4 0.95 0.4 0.5

3G base station 15.5 4.3 2 2.4

Table 4.6, Maximum detection ranges (km) for transmitter/area type combinations

Page 74: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 74

The table shows that in some cases the model predicts the detection range for “dense urban” as being greater than for “urban”. A possible explanation is that the model becomes less reliable as the distances become small, and it is starting to exaggerate the advantage of antenna elevation.

For all practical purposes the detection range can be considered to be the same for these two cases.

An approximation to the required monitoring station density for each transmitter type and area can be calculated by assuming that the percentage of the UK assigned to that area type consists of a single region, and ignoring edge effects. The monitoring stations can be assumed to be disposed on a triangular grid, the spacing of this grid being such that there is no point with a distance from at least one station exceeding the maximum detection range. Each station therefore had a notional hexagonal cell within which signals will be detected.

No coverage is required for the “Remote rural” areas of the UK.

The results of the exercise are given in Table 4.7 below.

Transmitter type Total number of monitoring stations

Pirate radio station 35

Pager base station 13

PMR base station 44

Personal mobile radio (PMR) 1,217

GSM Base station – Vodafone/O2 21

GSM Mobile – Vodafone/O2 5,923

GSM Base station – T-Mobile/Orange 35

GSM Mobile – T-Mobile/Orange 27,776

3G Base station 982

Table 4.7, Total number of monitoring stations vs transmitter type

4.4.2 Practical sensor layouts

The above approach gives sensible values for those emitter types for which the urban detection range is smaller than the size of a city. For instance, Table 4.7 states that 1166 sensors would be required in order to detect PMR mobiles

Page 75: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 75

across the whole of the UK and Figure 4.8 backs this up by showing that 851 would be sufficient to cover England and Wales.

Figure 4.8, 851 sensors providing the ability to detect PRM mobiles across England and Wales

The assumption that the urban land forms one contiguous region is however not valid for those emitter types which have significantly longer detection ranges. In a theoretical unbounded urban region, a triangular grid of sensors separated by 34.6 km, no point would be more than 20 km from the nearest sensor, enabling pirate radio stations to be detected anywhere. In such a grid, each sensor would provide urban coverage over a hexagonal cell with an area of 1039 km2, which is roughly five times the combined area of the urban regions of Norwich, Ipswich and Cambridge. In reality however, it is not possible for a single sensor to provide coverage over even these three cities because they are separated from each other by about 65 km. The quoted figure of 35 sensors may therefore not be sufficient to provide a nationwide capability against pirate radio stations.

The model used above for determining detection ranges made the assumption that a propagation path would be entirely within one land type. It was not able to predict the range over which an emitter in a rural area could be detected by an urban sensor. Initially, assume that the detection range depends on the location

Page 76: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 76

of the emitter so that any rural pirate radio station can be detected from a range of 57 km regardless of whether the sensor is in a city or not.

Figure 4.9 has three panes, which all use the same colour scale. The colour represents distance between a sensor and an emitter, as shown in the logarithmic scale at the bottom of the figure. In all three panes, the position on the map refers to the position of the emitter. The left pane shows the maximum possible range over which detection will be possible. For instance, an emitter in an urban region can only be detected if the distance to the nearest sensor is less than 20 km so the urban areas are shown in the dark blue colour which represents a range of 26 km. The rural areas appear in the orange colour which represents 57 km.

The middle pane shows what the actual distance to the nearest sensor would be from each point on the map if sensors were deployed in 51 specific locations. The colour of each point in the middle pane is at least as far to the blue end of the spectrum as the corresponding point in the left pane, showing that for any potential emitter location, the nearest sensor is closer than the maximum detection range.

If 51 sensors are able to cover England and Wales then the number required for the whole of the UK will probably be about 70 to 80.

.

Figure 4.9, Pirate radio coverage of England and Wales provided by 51 sensors

The right pane in Figure 4.9 shows, for the same arrangement of 51 sensors, the distance from each point to its third closest sensor. It can be seen that very few places are within 40 km of three sensors but that should not matter since the received SNR is allowed to be much lower at the second and third receiving station than at the first. The worst case is the city of Middlesbrough, which is

Page 77: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 77

roughly 100 km away from its third closest sensor. This is about five times the predicted detection range. Under an inverse fourth power law of propagation, increasing range by a factor of five reduces power by 28dB so it is possible that a signal originating in the city could arrive at the third sensor with a SNR of -18dB. This should still be sufficient to produce a measurable peak when cross-correlated with the signal recorded with +10dB SNR at the detecting sensor.

The assumption that any rural pirate radio emitter can be detected from 57km away regardless of the sensor location is unlikely to cause a problem since most of the cities shown in Figure 4.9 are small enough that the sensors which monitor them could themselves be situated in a rural area just outside the city. For instance, a sensor just to the east of Bristol could have the whole of the city within its 20km urban range while providing rural coverage as far as Marlborough.

4.4.3 Relation between correlation sample length and geolocation precision

The aim of this exercise was to generate modelling results which showed the relationship between the amount of data used in the estimation of TDOA and the achievable geolocation precision. These results were to assist in determining the requirement for communications bandwidth between the stations in order to cross-correlate signals and hence estimate TDOA. The following parameters were used:

Area type Open

Transmit antenna height 2 m

Receive antenna height 20 m (minimum allowed by propagation model)

Transmitter power 1W

Transmitter gain 0dBi

Receiver/signal bandwidth 20kHz

Receiver gain 0dBi

Receiver noise figure 14dB

Propagation loss not exceeded for 50% of the time and for 50% of locations.

Table 4.8, Parameters for modelling exercise

Page 78: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 78

An ideal sampling rate is assumed at twice the receiver bandwidth. In practice, a slightly higher sampling rate would be required (and hence slightly more samples).

The receiver and emitter geometry is close to the optimum for geolocation. The receivers are positioned at three corners of a square, with the emitter at the centre of that square.

The only source of error is that in estimating the position of the correlation peak due to the finite SNR of the signal. This is computed as the Cramer-Rao lower bound (CRLB) value given by reference [7]. In practice there would be additional errors due to (for example) the presence of co-channel signals, multipath effects and less than perfect synchronisation between the receivers. However, these additional errors are not sensitive to the number of data samples used. The error metric used is ‘circular error probable’ (CEP). There is a 50% probability that the estimated position will be closer to (or further away from) the true position than the CEP.

4.4.4 Results

Results of simulations based on the conditions stated in Section 3.2.1, for three receivers – emitter ranges and at 5 emitter frequencies, are given in Figure 4.10 to Figure 4.12. The number of samples refers to the number of data points captured at each sensor for correlation to calculate the TDOA.

Page 79: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 79

Geolocation error vs number of samplesRange 50 km

1

10

100

1000

10000

100 1000 10000 100000 1000000

Number of samples

Err

or (

CE

P)

met

res 30 MHz

100 MHz

300 MHz

1 GHz

2 GHz

Figure 4.10, Geolocation error vs sample length. Range 50 km

Geolocation error vs number of samplesRange 25 km

1

10

100

1000

10000

100 1000 10000 100000 1000000

Number of samples

Err

or (

CE

P)

met

res 30 MHz

100 MHz

300 MHz

1 GHz

2 GHz

Figure 4.11, Geolocation error vs sample length. Range 25 km

Page 80: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 80

Geolocation error vs number of samplesRange 10 km

1

10

100

1000

10000

100 1000 10000 100000 1000000

Number of samples

Err

or (

CE

P)

met

res 30 MHz

100 MHz

300 MHz

1 GHz

2 GHz

Figure 4.12, Geolocation error vs number of samples. Range 10 km

4.4.5 Scaling laws

The geolocation error will be inversely proportional to the square root of the signal power, so will halve for a 6dB increase in signal power.

If the receiver bandwidth (and hence the sampling rate) only increases, then for the same number of samples the geolocation error will be proportional to the square root of the receiver bandwidth.

If the receiver bandwidth matches the signal bandwidth, then (for the same number of samples) the geolocation error will be inversely proportional to the square root of the receiver bandwidth.

If the receiver bandwidth is less than the signal bandwidth, then (for the same number of samples) the geolocation error will be inversely proportional to the receiver bandwidth.

4.5 Graphical output

The figures included in this sub-section were generated using parameter values which illustrate the utility of the figures rather than values which correspond to a particular scenario.

The most important graphical output is a plot of geolocation error over the defined rectangular region of interest as shown by the scales on the two axes. An

Page 81: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 81

example of such a plot is shown in Figure 4.13. For this example, an area of 15km by 15km is being assessed and the monitoring stations are positioned just outside the top-left, bottom-left and top-right corners and are represented by black crosses. The colour at a given point represents the median error position error which there would be on a geolocation result for an emitter located at that point.

Figure 4.13, Plot of geolocation error as a function of target emitter location

Figure 4.14 refers to the same hypothetical scenario as Figure 4.13. The colour at each point represents the number of sensors which would have sufficient SNR to report that a signal was present. It is only necessary for one sensor to report the signal in order for an automatic geolocation to be tasked.

Figure 4.13 showed that geolocation would still give a result even if the emitter was in the region at the bottom right of the plot where it could not be reported by any of the sensors. However, to geolocate an emitter in this position, the sensors would have to be tasked manually.

Page 82: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 82

In a nationwide system with a large number of sensors, the sensors should be close enough together that every possible emitter position will result in a detection at at least one sensor.

Figure 4.14, Number of sensors with SNR above detection threshold

The height of the correlation peak relative to the noise in the correlation surface must be above a threshold value to ensure that the peak can be found reliably without excessive false alarms. Figure 4.15 is a plot showing how many reliable TDOA measurements would be given as a function of emitter position in the same scenario. For an emitter in the blue or green regions, it will not necessarily be possible to identify a clear peak in both correlation surfaces. However, if both peaks are identified, the error in the resulting geolocation will be that given in Figure 1.3. The geolocation errors are small even for correlation peaks which are barely detectable because the large bandwidth used in this scenario means that the correlation peaks are narrow.

Page 83: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 83

Figure 4.15, Number of reliable TDOA measurements

4.5.1 Co-channel signals

Figure 4.16 shows the potential effect of a co-channel signal on geolocation capability. For this example, the co-channel emitter is situated at the bottom-right corner. For each of the two sensor pairs, there is a green band within which the TDOA peak for the target emitter would overlap that of the co-channel emitter, resulting in an error in the determined TDOA. The width of the bands is determined by the bandwidth of the emitters. The actual geolocation error due to the presence of the co-channel emitter will depend on its power. A co-channel signal still has an effect even in the red region because it acts as noise, reducing the SNR for the target signal.

Page 84: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 84

Figure 4.16, Potential effect of a co-channel signal

4.6 Comparison with DF accuracy

Table 4.9 gives the maximum detection distances allowed from an emitter to its closest sensor for different types of signals in different environments. Provided the three sensors used for TDOA surround an emitter, the geolocation error does not vary significantly with the distance from the emitter to the sensors, only on the received SNRs and the number of points captured.

For direction finding however, there is a constant angular error so the transverse geolocation error scales with distance from the sensor. With a modern ground-based DF sensor and 10dB SNR in a clean rural environment, the DF error is typically about 2 degrees. In an urban environment, errors of about 20 degrees can be expected. The DF error does not depend on the signal bandwidth. Provided that a close to optimum antenna array size can be chosen for each signal of interest, the error is not frequency dependent.

If an emitter is geolocated by DF from two sensors at roughly equal distances from it then the expected geolocation error is roughly the product of the distance

Page 85: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 85

to one sensor and the sine of the angular DF error. The geolocation errors which result for emitters at the maximum detectable range for each of the scenarios in Table 4.6 are given in Table 4.9.

Emitter type Rural Suburban Urban Dense urban

Pirate radio station 2000 910 7000 8000

Pager base station 3500 1800 13000 17000

PMR base station 1800 870 5900 5100

PMR mobile 440 140 800 1300

GSM 900 base station

2800 1300 8400 6800

GSM 900 mobile 210 63 350 490

GSM 1800 base station

2100 1000 5800 8100

GSM 1800 mobile 120 33 140 170

3G base station 540 150 700 840

Table 4.9, Geolocation errors, in metres, expected from DF systems at the maximum detection ranges

The yellow line in Figure 4.6 shows that a 2W 1GHz emitter at a height of 2m would be received with a SNR of +1dB at a sensor which was 10km away and had a height of 20m. A 1W emitter at the same frequency would therefore be received with a SNR of roughly -2dB. Figure 4.12 shows that this 1W emitter would be geolocated with an error of about 9m if captures of 105 points were used with a receiver bandwidth of 20kHz.

Therefore, if TDOA sensors are perfectly synchronised and spaced so that they receive signals with about 10dB SNR then captures of 105 points can locate emitters with 20kHz bandwidth to about 9m. The narrowest of the example emitter types used in this report has a bandwidth of 12.5kHz so it would theoretically give a position error of about 15m. The signals with greater bandwidths should give smaller errors. However, the most likely way of synchronising the sensors is using GPS, which introduces further errors of about 50ns, resulting in 20m geolocation errors.

In previous trials, mobile phones have been located to about 40m and broadcast FM radio stations to about 100m. A TDOA system in which the distances from the emitter to the sensors was roughly the maximum detection range should be

Page 86: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 86

able to give similar accuracy whereas Table 4.9 predicts that a DF system with the same sensor spacing would give larger errors.

In a recent trial, two groups of emitters with bandwidths of the order of 10kHz were used as targets for geolocation by a pair of TDOA sensors and by a network of three DF sensors. The DF sensors were fixed and formed a 10km baseline. The errors with which they geolocated the targets depended on the distances from the sensor baseline to the targets. It was found that targets 10km from the DF baseline generally gave positional errors of about 5km while targets at 30km range gave errors of about 20km. The TDOA sensors in the trial were constantly moving and were typically each about 30km away from the emitters. The RMS TDOA errors were about 700ns against one type of emitter and 9000ns against the other. If the TDOA sensors had been stationary and surrounding the emitters, these figures would translate into positional errors of the order of 250m and 3km. In this situation, TDOA was shown to give greater accuracy than DF by roughly an order of magnitude

It has been suggested that more sensors will be required in order to provide a nationwide geolocation capability using TDOA than would be necessary using DF since for TDOA location, the signal needs to be received at three sensors whereas for DF location, it only needs to be received at two. However, there are two reasons why this is not true.

Firstly, in a regular square grid of sensors where adjacent sensors are separated by one unit of distance, the distance from an emitter to its second closest sensor is a maximum when the emitter is located close to one of the sensors, as shown in Figure 4.17. The distance to the second closest sensor is then just under one unit. The distances to the third, fourth and fifth are each also close to one unit. Similarly, in a triangular grid, the distance to the second closest sensor is again a maximum when the emitter is close to one sensor but then the seventh closest sensor is hardly any further away from it than the second. In general, any regular two-dimensional arrangement of sensors which ensures that there will always be two sensors within a given distance of an emitter regardless of the emitter’s position will inevitably provide a third sensor within the same distance.

Page 87: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 87

Figure 4.17, The maximum possible range to the third closest sensor is not significantly greater than the maximum possible range to the second closest

sensor

Secondly, for a TDOA system, only one sensor needs to be sufficiently close to the emitter to have the 10dB SNR necessary for signal detection and identification. The second and third sensors are tasked by the first and it will be possible to produce TDOA measurements by cross-correlation even if the SNRs at the second and third sensors are negative. With a DF-based system, it is still only necessary for one sensor to do the detection and identification but DF from the second sensor will not be possible unless the SNR of the signal received there is positive.

Page 88: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 88

5 AMS System design – (Work Package 4)

5.1 Introduction

The Ofcom ITT requested the design of an unattended monitoring system whose primary purpose is to automatically detect, identify and locate the source of interfering radio signals over a large part of the UK. This was carried out under Work Package 4 of the project. A requirements analysis was performed which took into account the results of Work Packages 1 and 3 and also discussions with Ofcom. This section of the report describes the outline design of the final operating system.

The solution should comprise a large quantity of monitoring stations, which are to be networked for control, data correlation, and reporting purposes and the system should be capable of fully automatic operation or manual control. Additional requirements are routine monitoring of the spectrum to establish occupancy, potentially providing Ofcom with a means of validating a database of licensed user activity.

5.2 Requirements for the AMS

The following points summarise the requirements of the system as described in the ITT. These were expanded upon in the QinetiQ proposal, and it is mainly these requirements that are listed. Some further requirements are also included which have emerged during subsequent discussions with Ofcom.

1. The units should be capable of measuring interference from 20MHz to 3GHz and should have a low noise floor, close to thermal noise, for detection.

2. Due to the numbers involved these units should be low cost and, to minimise planning permission issues, should be small and use small antennas.

3. The frequency channels and bands to be monitored should be set automatically over a communications link. It is expected that the units will have a controllable bandwidth, scan rate and dwell time.

4. They should use a reliable method of detecting the interfering signal with sufficient receiving sensitivity achieved to be usable across the entire frequency range.

5. To maximise the use of the AMS units, they need to be capable of carrying out routine spectrum monitoring tasks in measuring channel or band occupancy, as well as automated and manual interference checks.

6. The system can be used in places without dedicated communications links, hence they will be able to use existing structures such as radio or cellular networks to download recorded data and send new instructions.

More precise details of the exact requirements are beyond the scope of this document but can be found in the Design File [8].

Page 89: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 89

The following two tables summarise how these requirements have been met in the demonstrator system, and also what additional features would be included, and what changes could be made to reduce costs and improve performance for a fully deployed network of sensors. Table 5.1 details the physical characteristics and Table 5.2 the features.

Page 90: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 90

Component Requirement Demonstrator Final System Comments

Enclosure Small, light and easy to mount.

4u 19" ruggedised rack / transit case from Dragon Cases, suitable for trials. COTS 19" rack mount PC and RF trays.

Custom built sealed outdoor unit. Small enough for wall mounting, or on an antenna tower. Approx size of a desktop PC.

For cost reasons on the demonstrator (as there are only three) COTS units are being used wherever possible. With economy of scale a production run could customise components allowing a more robust, compact design. There may still be benefits to a 2 unit design.

Power Mains power. Low voltage dc with a separate indoor mains power supply unit.

For safety reasons it is more sensible to operate the final unit at a low voltage. This simplifies installation and maintenance procedures, as well as reducing the environmental requirements on the enclosure.

PC DSP processing techniques.

The philosophy is to use a software-based architecture on low cost hardware.This make the system easily upgradeable with software updates.

Intel dual 3.2 GHz XEON, COTS 19", 2u rack unit.

This provides the high level of processing power required for the intensive modulation recognition and location processing.

Probably AMD option for lower power dissipation.

PC choice is a compromise between performance, cost and power consumption. AMD processors use less power which is important for heat generation in an enclosed outdoor unit. Even so, cooling must be considered carefully.

Page 91: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 91

Component Requirement Demonstrator Final System Comments

Digitiser Reasonable probability of intercept requires a wide stare bandwidth. Following discussions with Ofcom it has become apparent that a high dynamic range will be required to work in a “noisy” environment such as London.

Echotek GC314-PCI-FS. 105 Msample per second digitiser / tuner.

Custom made digitiser with on board signal processing or FPGA to reduce workload on PC.

This is a high specification digitiser offering an increase in performance in both dynamic range and staring bandwidth over our previous systems.

Receiver 20MHz to 3GHz frequency range. Low noise figure and good sensitivity.

TRL MRX 3500 TRL MRX 3500, possibly with a low bandwidth option to give improved sensitivity in a high signal strength environment.

This is a high specification receiver which provides a wide stare bandwidth and high scan rates with a compact form and low cost

GPS TDOA location calculations require accurate position of the sensor, and precision timing to sub 100ns accuracy.

Trimble Thunderbolt.

This has a 20ns timing accuracy, to meet the precision timing of TDOA

Either GPS chips bought in direct from Motorola, or existing TRL GPS module.

For size and production cost a customised option may prove to be more suitable than a COTS item. QinetiQ will work with TRL to further develop an in-house designed board that they have.

Demodulation Discussion with Ofcom has highlighted the importance of being able to demodulate an audio signal.

Software based architecture provides upgrade path for features such as demodulation with no change to the hardware.

Software demod on IQ data, with ability to store and access across the network

Hardware demodulation has also been considered, but software is considered to offer a more flexible approach

Page 92: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 92

Component Requirement Demonstrator Final System Comments

Switching / distribution

20MHz to 3GHz frequency range.

TRL in-house circuit board - milled.

TRL printed circuit board. To cover this frequency range at least two antennas are required. Switching is needed to select the relevant one for the frequency band.

Sampling clock

Low phase noise clock to drive ADC (phase noise will reduce the sensitivity of the ADC).

TRL in-house clock module. 102.4MHz.

TRL in-house clock module. 102.4MHz..

This is the clock source that drives the ADC. Good phase noise is essential to make best use of the high quality ADC cards.

Networking Sensors to be remotely configurable.

Co-operative TDOA locations.

Data to be transferred from remote sensors for analysis.

3G phones / broadband to connect to the internet.

Broadband. Wi-fi. 3G to connect to the internet.

The internet will form the backbone of the network. It is anticipated that the final system would use whatever network medium is available to connect to the internet. This is likely to be broadband wherever possible. Real time spectrum displays may not be available, and location of weak signals could have latency across a narrow band link.

HIGH BAND: AOR-DA5000.

HIGH BAND: AOR-DA5000 .

Antennas Small antenna.

Discussion at meetings suggests that an antenna should fit into 1m3 for planning permission reasons.

LOW BAND: Scanking Royal Discone base antenna - RN40T.

LOW BAND: Robust version of demonstrator antenna.

Size of antennas is important on the final system for planning permission reasons. This makes low frequency performance more challenging. Antennas for the final system must be robust to survive outdoor conditions without degradation.

Page 93: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 93

Component Requirement Demonstrator Final System Comments

Cables Low noise figure and good sensitivity.

For both Antennas CFD400 Low loss 50 Ω coaxial cable with N type connections. Max 2.8dB loss.

Cable types and length chosen for specific installations.

The demonstrator cables need to be flexible / low bulk for packing and transport. The final system would be fixed, so cables could be more rigid to reduce cost, and give better performance.

Table 5.1, Physical characteristics

Component Requirement Demonstrator Final System Comments

Human Machine Interface (HMI)

Remote operation. Interactive software interface allowing control of local and networked sensors. Displays for spectrum monitoring, location and network (sensor) control.

As for demonstrator but with additional control for networked sensors including data management, and automatic modes for signal identification and location without operator interaction.

The software is based on QinetiQ software specifically developed over the last 7 years to manage and control multiple wideband scanning sensors in an intuitive manner.

Page 94: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 94

Component Requirement Demonstrator Final System Comments

Scan 20MHz to 3GHz frequency range. Scan control.

20 - 3000MHz in 40MHz blocks - approx 10s per scan.

20 - 3000MHz. By Default capture will be a 40MHz block, but with an option to reduce this in high signal level environments. Variable scan, down to 1s.

The proposed hardware is capable of supporting a scan rate of 40GHz a second. However, there must be a compromise between detection sensitivity and speed. The software approach allows the flexibility to optimise for different scenarios, and to upgrade as more sensitive detection algorithms are developed.

Networked monitoring operation

Sensors to be remotely configurable.

Remote monitoring of spectrum / emissions. Spectrum Occupancy. Tasking.

Full control of remote sensors. Network hierarchy for data management

The final system will be capable of providing full control of remote sensors from either regional or national control centres. Some features are bandwidth intensive (e.g. real time spectrum / emissions displays), so might only be available on higher bandwidth links.

TDOA location

Location capability.

AoA was discounted as an option after discussion at a progress meeting because of antenna size, so only TDOA is being considered as an option.

System consists of 3 sensors, each one can task the other two sensors to co-operatively perform a location.

Control of all surrounding sensors. Optimal combination of measurements to calculate location from multiple sensors.

Only three demonstrator units are being built, so the location technique is limited to intersection of two TDOA lines. Improved methods have been investigated for optimal combination of measurements from an array of sensors.

Page 95: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 95

Component Requirement Demonstrator Final System Comments

Modulation Recognition

Modulation recognition. QinetiQ signal classification software.

QinetiQ signal classification software.

The QinetiQ modulation classifier proposed for the AMS unit would have the capabilities to process the following modulation types:

Analogue: CW, AM, FM/PM, FM, SSB, DSB, USB, LSB.

Digital: ASK, MSK, FSK, PSK, QAM, ASK/PSK Hybrids

Additional Signal Type Descriptors: Voice, Tone, Morse, Radio Teletype (RTTY), CTCSS and Chirp detection is also applied to suitable signals.

Spectrum occupancy

Short term emissions history, showing all emissions against time. Long term view records average occupancy over 15min intervals. Available bandwidth locator allows identification of unoccupied bandwidth against user defined criteria.

As for demonstrator, but with the ability to work over a network connection. Occupancy data files are large so search a facility will allow only selected data to be downloaded.

Page 96: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 96

Component Requirement Demonstrator Final System Comments

Database Archiving and retrieving data.

Results of spectrum occupancy and signal recognition stored in a predefined text format allowing search or import into database packages.

Data will be stored in a format compatible with the Ofcom database. The database allows for automatic tasking of signal classifier or location on unlicensed signals.

Table 5.2, Features of the AMS

Page 97: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 97

5.3 The proposed solution

The remainder of this chapter gives an overview of a proposed system that addresses the issues listed above, and explains some of the design considerations leading to this solution. A high level system diagram is shown in Figure 5.1.

The modelling study concluded that TDOA was the preferred option (see Section 4.6). Hence this section concentrates on the design of a TDOA system.

Figure 5.1, Systems architecture of the proposed solution

5.4 Solution Architecture

The original QinetiQ proposal suggested the system would consist of antennas and two separate units, one located at the mast top next to the antennas and a second indoor mounted unit connected to the mast top unit using a single coaxial cable. During the project, a single-unit solution has been discussed for the operational equipment.

GPS UNIT

LOW BAND ANTENNA

HIGH BAND

ADC CLOCK

RECEIVER

ANTENNA SWITCH

PROCESSSOR AND

SOFTWARE

INTERNET CONNECTION

DIGITISER

ANTENNA

Page 98: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 98

The response to Ofcom’s ITT proposed a candidate system design. The design shows antennas to capture the signals, receivers for down-conversion to IF, ADC for digitising the signals and high specification computers for processing. Additionally, a GPS is included for timing and an oscillator to provide and accurate clock to ADC.

The units are arranged into two separate units. The outdoor unit contains the receivers to keep them as close as possible to the antennas to reduce RF cable losses. Signals are transferred to the indoor unit at IF where cable losses are less of a problem. By keeping the majority of the equipment indoors the environmental requirements are eased.

However, with an IF of 76.8MHz (as used by the TRL receivers) interference from in-band transmissions on long cable runs is likely to be considerable, and with the sensitivity of a correlation based location system this is not considered to be a good option. Hence, now a single-unit solution is being proposed for the operational equipment

5.4.1 ‘Two-Unit’ Architecture

In this approach, the RF functionality is placed in a unit to be mounted near the antennas – ‘outdoors’. A second unit containing the remainder of the functionality will typically be located ’indoors’ (Figure 5.2).

Figure 5.2, Two-Unit Architecture

Page 99: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 99

The outdoor unit would contain antenna inputs, antenna switching matrix, receivers, GPS, and a diplexer for sending information to the second ground mounted unit. The lower unit would contain the unit’s power supply, digitiser, and computer for signal processing, command and control and logging, and diplexer for interfacing to the other unit.

Figure 5.3 expands on the content of each unit.

Figure 5.3, Details of the two unit architecture

A variant increases the functionality in the outdoor unit by positioning the digitiser there but this is offset by the disadvantage of adding a high speed digital link between the units. The indoor unit becomes a computer processing unit and power supply for the outdoor unit.

ANTENNA SWITCH

BOTTOM UNIT

10 MHz RS232

IF

RF

NETWORK

10MHz RS 232

IF

10MHz

10 MHz, IF, RS232

HIGH BAND ANTENNA

LOW BAND ANTENNA

GPS UNIT

ADC CLOCK

PC

ANTENNA MOUNTED UNIT

1pps

RECEIVER DIGITISER

Page 100: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 100

Design Advantages

• Separate analogue and digital units simplifies the internal RFI design,

• Outdoor unit is physically smaller,

• Solar heat gain and internal power dissipation in outdoor unit will be lower. Design Drawbacks

• Inter-unit communications link requires a custom design.

• Analogue inter-unit communications link - a connection from the receiver IF (78MHz centre frequency) to the ADC is required. Losses in this cable run could be large for the potentially long distance between units. Furthermore, mobile radio transmissions and the low frequency end of band II FM broadcasting are within this IF bandwidth and are likely to result in direct signal pick up on the cable appearing at the ADC input at unacceptable levels. The use of double or triple screened coaxial cable for the IF link will increase the installation cost.

• A design variation would involve moving the digitiser to the outdoor unit. This requires a digital inter-unit communications link - the raw data rate would be 102.4Msamples/sec at 14bits and allowing a margin for synchronisation and management, a data rate of the order of 1.5Gbps results. This would require the addition of an optical fibre link to replace the existing coaxial cable link.

5.4.2 ‘One-Unit’ Architecture

An alternative architecture (Figure 5.4) with all the components located in a single unit will avoid the problems of IF interference. Although nominated a ‘one-unit’ solution, this architecture will require two units:

• Outdoor unit with all the functionality - to be mounted on the mast,

• Inside unit consisting of a power supply unit to provide low-voltage power to the outdoor unit.

Page 101: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 101

Figure 5.4, One unit architecture

Design Advantages

Apart from reducing the susceptibility to interference at IF, this design approach is simpler in that it consists of a single unit, which

• Minimises manufacturing costs,

• Simplifies installation,

• Minimal indoor accommodation for power supply,

• Reduces losses and potential signal degradation between outdoor and indoor units,

• Reduces design effort and risk by eliminating the intercommunications link between units.

GPS UNIT

LOW BAND ANTENNA

HIGH BAND ANTENNA

ADC CLOCK 102MHz

10MHz RECEIVER

ANTENNA SWITCH

PC COMMS

DIGITISER

Network

10MHz 1pps

Page 102: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 102

Design Drawbacks

This approach puts the all functionality in the outdoor unit with the following drawbacks:

• Thermal management - greater functionality in the outdoor unit produces additional heat,

• Analogue and digital processing in one unit will require careful internal RFI design,

• Greater power to be routed to mast.

On balance the one unit solution is the preferred choice, both for its improved performance and ease of installation. The architecture will still require two units – one with the functionality to be mounted outside near the antenna, and a second, a power supply unit located inside a weatherproof structure.

5.4.3 Outdoor Unit

It has been estimated that approximately 100w would be dissipated by the modules within the outdoor unit. There will be some hot spots, such as the processors. It is proposed that a fan be used to circulate the air within the unit, and heatsinks be provided on the inner and outer surfaces to maximise heat transfer into the environment.

An additional solar protection shield should be provided on the appropriate faces to minimise the effects of solar warming.

The outdoor unit should be designed to minimise the EMC risks and be environmentally sealed to avoid the need for protecting the individual modules. This unit would be of a generic design suitable for mast and wall mounting and large enough for maintenance purposes in potentially difficult access situations. Space must be available for adequate air circulation for cooling purposes.

A complementary suite of mounting brackets for the antennas will be needed.

5.4.4 Thermal Analysis: Power Dissipation

The estimated power dissipation budget for each unit is shown below in Table 5.3. Each element is described in subsequent sections.

Page 103: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 103

Item Watts

MRX Receiver 8

Clocking, RF Switching 5

Digitiser 5

GPS & reference clock 5

PC & Co-processor 50

Disk drive 5

DC to DC converter PSU 25

Total 103

Table 5.3, Estimated power dissipation budget

Forced air cooling has traditionally been considered an unattractive option due to the maintenance issues with fans. However, fans are available with a quoted life expectancy before failure of 100,000 hours at 60oC - over 11 years continuous operation. Turning it off when not required will extend this.

Ideally such a fan would operate on a cold-wall external heatsink. IP67 rated fans are available and a cowling could be arranged such that the direct impact of bad weather and ingress of foreign matter which might cause a blockage, are avoided.

Some benefit would be attained by the use of an internal fan in a sealed unit by redistributing heat from hot spots.

There are a number of alternative approaches: Finned heatsinks could be provided on external surfaces. This requires the heat generating components to be mounted on external walls to maximise thermal transfer to the external heatsink. Natural convection could provide heat dispersion. Any solar shield may impair natural convection.

Alternatively, the unit could contain louvers and internal heatsinks, which would make them more thermally efficient. However, an opening unit dictates that sealed or conformally coated component parts be used. EMC problems may be exacerbated. See further discussion on materials in Section 5.4.10.

The size of the unit is also a factor – a densely packed unit has less ability to distribute heat from hot spots by convection. A larger unit than mechanically necessary to contain the operational components may be appropriate to provide a greater degree of internal heat dispersion. However, an enlarged unit is likely to incur greater solar heating effects, as described below.

Page 104: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 104

5.4.5 Thermal Analysis: Solar Generated Heat

An outdoor mounted unit is likely to be subjected to solar gain. This effect is estimated to be:

Outside Unit

Solar gain w/m2 1000

Unit mm 500

mm 400

mm 150

Sun on largest area side only

w 200

Allowance for other sides

w 100

Total w 300

Table 5.4, Effect of solar gain on outside unit

Judicious positioning of the unit can be used to minimise the solar gain effect – positioning on north facing walls or in the shadow of other fixings.

The solar gain effects may also be reduced by the introduction of a second skin to the unit, positioned some 20 -30mm from the unit surface. This becomes the primary absorber of solar warming.

Dissipation of these levels of power will require careful thermal management design.

5.4.6 Form Factor

The proposed unit is dimensioned to contain the proposed functionality. Thermal management considerations are primary and may dictate that a larger volume be employed to allow internal air flows to assist cooling.

Maintenance considerations may also dictate a less compact configuration within the unit to ease the replacement of internal modules in the difficult working conditions that could be imposed by the units’ locations.

Page 105: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 105

5.4.7 Mounting Options

The outdoor unit will be of generic design for mast and wall mounting. It is proposed that a selection of separate fixing plates be designed for diverse mounting scenarios, e.g. wall, girder, mast etc.

A complementary suite of mounting brackets for the antennas will be needed.

5.4.8 Connectors

It is proposed to mount the connectors on the base of the unit to minimise moisture ingress. A shielding sheet will be provided give a degree of protection from direct driving rain.

Connectors will be required for:

• Low frequency antenna,

• High frequency antenna,

• GPS antenna,

• Link to LAN/WAN network,

• Link to GMS/3G antenna if no LAN/WAN,

• Power.

5.4.9 Indicators

The utility of indicators on the outdoor unit will be determined at the detailed design stage. It is not expected to be located where any such indicator will be readily visible. Any indicators could be provided inside the unit, visible to an engineer with the unit open, thereby reducing the number of piercings and potential leaks.

Basic indications, such as power and antenna selection could be provided.

5.4.10 Materials & Construction

Both polycarbonate and stainless steel units have been successfully deployed in similar applications. Both provided adequate environmental protection, with stainless steel additionally providing EMC shielding.

It is proposed stainless steel be used to exploit the EMC shielding effects.

5.4.11 Environmental Specification

The following environmental specifications have been derived by comparison with the specifications of similar in service equipment.

Page 106: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 106

Operating/Deployed

Item Limits Commentary

Temperature - high +60oC

Temperature - low -40oC

Humidity 100% Condensing

Altitude 4,500m

Vibration 0.91 g (5 to 500 Hz)

Shock 10 g 10msec duration

Driving rain 75mm/Hr Max

Table 5.5, Environmental Specification for Operating/Deployed Equipment

Storage (Un-powered)

Item Limits Commentary

Temperature - high +80oC

Temperature – low -50oC

Humidity 95% Non-condensing

Altitude 10,000m

Vibration 2.4 g (5 to 500 Hz)

Shock 40 g 10msec duration

Table 5.6, Environmental Specification for Stored Equipment

5.4.12 EMC Specification

The equipment is categorised as “IT and general equipment” and as such, the appropriate harmonised standards for EMC performance are:

EN55022 Emissions

EN55024 Immunity

Specifications under the RTTE directives may also be appropriate for the outside unit.

Page 107: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 107

5.4.13 Power Supply Unit

This power supply unit provides a safe voltage supply to the outside unit.

The indoor unit need not be environmentally sealed or protected to such a high degree as the outdoor unit. Fan cooling should not pose a problem. Solar thermal gain is not expected to be a problem.

The outside unit is predicted to dissipate about 100W. Some margin for future expansion may be allowed at minimal cost and size impact. Thus a minimum 250W at 24V supply is recommended, which may be implemented using a COTS power block enclosed in a customer case that contains appropriate terminations of cabling to the outside unit.

To cope with diverse installation requirements, wall mounted and 19 inch rack mounted options may be appropriate.

5.4.14 Summary

The original QinetiQ proposal suggested the system would consist of antennas and two small boxes, one located at the mast top next to the antennas and a second unit ground mounted connected to the mast top unit using a single coaxial cable.

During the design of the demonstration system units however it was concluded that the two box solution was likely to suffer from RF pickup on the long IF (intermediate frequency) cables, and that this would adversely effect the performance of the system. Instead it would be preferable to accommodate all of the functionality in a single unit that could be mounted close to the antennas. This avoids having long cables at IF, and complex communication between units, but does increase the size of the outdoor unit, and introduces extra complexity with weatherproofing and cooling.

Although nominated a ‘one-unit’ solution, this architecture will require two units – one with the functionality to be mounted outside, and a second, a power supply unit located inside.

5.5 Antenna

Choice of antennas is important to the performance of the system, both for detection sensitivity and location accuracy. The requirement is challenging to meet in that the system is to cover a large frequency range (20MHz to 3GHz) with ideally a flat gain of around 0dBi. Furthermore, the size of antennas is important as this could affect where the systems can be located, both for structural reasons, and to meet local planning permission rules. The smaller the antenna is the less likely it is to cause concern.

Page 108: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 108

Antennas for the final system must be robust to survive outdoor conditions without degradation, and have lightning protection circuitry to protect the rest of the AMS unit.

Testing of some candidate antennas suggests that to cover the this frequency range (20MHz – 3GHz) two separate antennas will be required, and that disc-cone antennas provide the best performance over a wide frequency range without being too large.

5.5.1 Testing

Tests were carried out using the configuration shown in Figure 5.5.

Figure 5.5, Antenna test configuration

A Rohde and Schwartz (R&S) signal generator and Minicircuits RF power amplifier were used as the transmit (TX) source. A telescopic whip was used as the receive antenna and connected to the Hewlett Packard spectrum analyser. Both antennas were mounted at a height of 2m and at approximately 50m apart outside on unobstructed ground.

The isotropic gain (dBi) of the antennas under test (AUT) was measured using the method of gain substitution. The following calibration antennas were used to accomplish this:

• AH Systems bicone (20MHz to 325MHz); • R&S 4035.8755.02 log periodic (400MHz to 3.5GHz).

The received signal level present on the spectrum analyser was recorded for each AUT over the measurement frequency range. The procedure was then carried out for the calibration antennas. The isotropic gains of the antennas under test were then calculated from the results.

Page 109: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 109

The following three plots summarise the results.

Ofcom Antenna Com parison

-60.0

-50.0

-40.0

-30.0

-20.0

-10.0

0.0

10.0

0 10 20 30 40 50 60 70 80 90 100

Frequency (MHz)

Gai

n (d

Bi)

AOR DA753 DisconeEuropean Ant. XP03V-500-1300/034Thunderpole EurostickMag MountAOR DA5000 DisconeQinetiQ Discone

Figure 5.6, Summary of results. Gain versus frequency (5MHz to 100MHz).

Ofcom Antenna Comparison

-60.0

-50.0

-40.0

-30.0

-20.0

-10.0

0.0

10.0

100 200 300 400 500 600 700 800 900 1000

Frequency (MHz)

Gai

n (d

Bi)

AOR DA753 DisconeEuropean Ant. XP03V-500-1300/034Thunderpole EurostickMag MountAOR DA5000 DisconeQinetiQ Discone

Figure 5.7, Summary of results. Gain versus frequency (100MHz to 1GHz)

Page 110: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 110

Ofcom Antenna Com parison

-60.0

-50.0

-40.0

-30.0

-20.0

-10.0

0.0

10.0

1000 1500 2000 2500 3000 3500

Frequency (MHz)

Gai

n (d

Bi)

AOR DA753 DisconeEuropean Ant. XP03V-500-1300/034Thunderpole EurostickMag MountAOR DA5000 DisconeQinetiQ Discone

Figure 5.8, Summary of results. Gain versus frequency (1GHz to 3.5GHz).

5.5.2 Antenna choices

At the higher frequencies, of the antennas tested, the AOR 5000 discone (Figure 5.9) has the best performance. This is a robust, well made, compact antenna, and is recommended as a good choice for the final system.

Figure 5.9, AOR DA5000 discone antenna

Page 111: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 111

At the lower frequencies the “QinetiQ Discone” shows the best performance. This is a QinetiQ manufactured antenna very similar in style to the Scanking Royal discone antenna (Figure 5.10) used in the demonstrator system. These antenna offer good performance, but are fairly large (1.5m high by 0.6m across), so there may be some locations where it would be more appropriate to accept a compromise on the performance in favour of a lower profile antenna.

Figure 5.10 - Scanking Royal discone antenna

5.5.3 Switching

Latest technology RF switches are required to minimise degradation to sensitivity through switching losses, and maintain linearity. Lightning protection circuitry should be utilised on the antenna inputs to protect the rest of the system.

5.6 Functional modules

5.6.1 Receiver

The requirement implicitly calls for the AMS receiver to have a wideband, fast tuning receiver, both to accommodate the widest bandwidth signals and to

Page 112: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 112

achieve the spectrum revisit time. This will also ensure a high probability of intercept against fleeting or intermittent interference.

With the proposed large number of AMS units to be deployed, the underlying requirement; mapping directly to RF performance, is its affordability, both in terms of component cost and DC power consumption.

There are many technical challenges to the design of the AMS receiver, not least the performance demanded from a low cost receiver.

An obvious limitation of the ultra wide instantaneous bandwidth solution offered is the performance in strong signal and cluttered EM environments.

To overcome the effect of multiple strong signals in the selected observation bandwidth, the AMS must engage front end gain controlling attenuators to position the available dynamic range (circa 80dB) such that the strong signals do not overdrive the maximum input voltage of the ADC.

Whilst this function is essential to prevent unwanted clipping and distortion in the ADC circuitry, and consequent severe corruption of the FFT spectra, it is undesirable from a sensitivity perspective; adding front end attenuation directly impacts the receiver noise figure and therefore the ultimate system sensitivity.

In essence, there is a finite dynamic range available in the receiving and digitising circuits and this must be positioned to accommodate the power of all the signals in the selected bandwidth. This has the effect of degrading the sensitivity of the system over the entire observation bandwidth.

This problem becomes more apparent as the selected bandwidth increases. Firstly, by nature of increased bandwidth there are there are by definition more signals to consider, each of which may in their own right be only of moderate power level but combine to overdrive the ADC.

Secondly, the subsequent degradation of system sensitivity by engaging the gain control circuits to compensate for the strong signal environment is spread across a wider bandwidth. For example, in the extreme, a single high power signal in the receive spectra will cause the degradation of an entire 40MHz of bandwidth

A more subtle and possibly worse effect can occur when strong signals are outside of the final tuned IF bandwidth but within the front end pre-selected bandwidth; under these conditions, the aggregate power at the ADC input may be within the dynamic range of the ADC. Thus the system will not select any front end attenuation. This is problematic as the troublesome high power signals have to be linearly processed in the first stages of the receiving circuits without any protective attenuation. Failure to process these, out of band signals in a linear fashion will result in the generation of numerous harmonic inter-modulation spurious terms, some of which will undoubtedly appear in the subsequent IF bandwidths following the receiver front end.

Page 113: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 113

For any receiver to operate under these conditions would require a front end, out of band dynamic range at least equal to the in-band dynamic range plus the available front end attenuation. In this case requiring a receiver front end equivalent input intercept point 40dB stronger than the equivalent in-band input intercept point; around +40dBm in this example. Such performance can be approached but comes with diminishing returns against a steeply escalating cost and power.

TRL MRX receiver suitability

The demonstration unit uses the B-Model MRX3500A receiver which will have formally entered production by the time that the Automated Monitoring System is rolled out. The formal factor, EMC and environmental specifications are not expected to change.

The MRX receiver provides an input of 40MHz bandwidth to the ADC with an instantaneous two tone in-band dynamic range of 75dB, capable of operation with a total signal power of up to -40dBm in the selected bandwidth at the antenna input. Once input signal power exceeds -40dBm, attenuators are automatically switched in to prevent overloading the ADC input. This reduces the sensitivity of the receiver by moving the available 75dB instantaneous dynamic range up to the level required to process the increased signal power.

In its MRX3500B format, it is housed in a sealed connectorised chassis, which will meet the environmental requirements.

Any relatively low cost style receiver represents a compromise between size, weight and power consumption (SWaP), cost and ultimately RF performance. The most noteworthy compromise is between cost DC power consumption and RF performance. DC power consumption, increases in line with the RF power handling capability.

Results from the central London trials (see Section 7.2.1) indicate that the signal handling performance of the RF tray may be too weak to pass on 80dB of dynamic range available in the ADC circuits to the RF environment when there are strong signals.

The situation can be partially and relatively easily improved by hardware modification to the receiver with no increase in cost or power consumption. A reduction in nominal gain of the receiver by 14dB whilst maintaining the noise figure would yield a comparable increase in dynamic range of the system under in band strong signal conditions.

Significant improvements to the strong out of band signal handling capability can only be achieved with a substantially increased out of band input intercept. This type of design change comes with steeply escalating cost both in terms of DC power consumption and money.

Realistically there are two options for achieving an increased high signal performance:

Page 114: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 114

• Instantaneous capture bandwidth reduction,

• Higher performance (and cost) receivers for urban environments.

Reducing the instantaneous capture bandwidth reduces not only the number of simultaneous signals driving the AGC but also the bandwidth over which sensitivity is lost once the AGC is engaged. The solution does however have the disadvantage of increased scan time.

A universal increase in the performance of the receiver is undesirable from a cost aspect but may still be more cost effective than maintaining different performance grade receivers depending upon the strength of the EM environment for the chosen installation.

5.6.2 Digitiser

The digitiser will capture IF signals from the receivers and convert them to a binary format for processing.

The digitiser will be required to work in two modes. It needs to have a wideband mode for rapid scanning when doing spectrum monitoring and detection, and a narrowband mode for modulation identification and location processing.

The narrow band signal can be derived from a wideband signal by digital signal processing (DSP) on the computer, but this is not considered a good option as it increases the work load on the PC, and increases the data throughput requirement across the bus onto the PC. For example, the digitiser might be capturing at 100MHz with a required narrow band capture rate (chosen to match the captured signal bandwidth) of 200kHz. This would mean that 500 times more data than is required would have to be transferred to and processed by the PC. This would not be sustainable across a PCI bus for anything other than a very short sample period.

Two options are available to provide the narrow band mode. Digitisers are available commercially with on-board digital tuners, generally based on the popular Graychip 4016 as used in the demonstrator system. This will tune and filter on a selected frequency and give a real-time IQ data stream for a wide range of bandwidths. The second, more flexible option is to use a digitiser with an on-board FPGA (field programmable gate array) or DSP capability. This would allow a similar capability to that of the Graychip to be programmed, but would also give the option of doing some of the wideband signal monitoring and signal detection processing on the digitiser. This would reduce the requirements on the PC processor considerably which would mean an overall reduction in unit power consumption and heat dissipation.

The FPGA/DSP option is recommended for the production system because of the overall reduction in power consumption and size, but the advantages must be carefully balanced against the increased development costs and more complex upgrade path. Upgrading PC based software is very straightforward; as faster processors are developed they are generally backwards compatible, so old

Page 115: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 115

software can be transferred straight onto them. Conversely, upgrading to a new DSP chip could well mean a complete re-write.

16-bit ADC devices at 100Msps are now available and would satisfy the requirements for the wideband capture mode. The number of bits is less important in the narrow band mode than in the wide band mode (TDOA processing has been shown to work with as few as 4 bits with little loss of accuracy). However, in the wideband mode the number of bits affects the dynamic range of the system, and must be matched to the dynamic range of the receiver. This is particularly important if the sensitivity to low level signals is not to be compromised when captured within the same band as a high power transmitter.

5.6.3 Processor

A PC is required to process the data acquired by the digitiser, to act as an interface and control point to the rest of the network and to provide local storage for captured data. The main requirements of the PC are sufficient processing power, and small size and power.

A modest performance PC as the host, with a DSP co-processor to carry out the signal processing functions, will be the most power efficient implementation.

The final design could use a generic processor as these are readily available at reasonable cost. The risk associated with a custom design is high and is difficult to justify. A PC104 format is proposed, being compact in format and rugged in design with ample options for connecting to external devices through various interface types.

It is recommended that the DSP processor be implemented as a co-processor to the main processor. This can be via a standard interface such as PMC or via the PCI bus. A number of standard cards are available, but a custom design may be desirable to integrate the A/D converter and signal conditioning. An FPGA could also be incorporated to soak up any other utility functions.

Porting the signal processing algorithms to a DSP co-processor involves some risk and incurs system testing and verification but this should be a relatively low risk task, as the code was originally written to operate with a co-processor of this type. The FFT transforms and averaging are well established and available ‘off-the-peg’ functionality.

The demonstration system software is written in C++ to execute under PC Windows XP. This provides a flexible upgrade path as PC processor speeds increase.

The following processing tasks are identified:

• RF tray management,

• Command & control interface,

• Network interface,

Page 116: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 116

• Signal processing,

• Spectral processing,

• Modulation classification.

These former three tasks are generic and can be efficiently carried out by the PC processor.

The signal processing task includes Fast Fourier Transform of the spectral samples into frequency spectrum followed by averaging. While this task can be carried out on the generic PC, this is not the most efficient solution. Digital Signal Processors are specifically optimised for such tasks. In terms of power consumption, a similar function can be achieved with approximately 10% of the power dissipation.

5.6.4 GPS

The key to successful TDOA processing is synchronising capture of data between the sensors. This means we need accurate timing, and an accurate frequency reference. GPS should be used to provide this as it gives superior long term stability to crystal based oscillators.

The GPS will:

• Supply a 10 MHz reference to the receiver such that all system units measure the same frequency,

• Supply the 10 MHz reference to the digitiser ADC clock generator such that all units sample at the same rate,

• Supply a 1 pulse per second (1pps) to allow all system units to perform data acquisition at the same time,

• Supply unit location for location purposes.

A timing accuracy of 20ns is achievable from a good commercial GPS unit. These units use the fact that it is stationary to allow averaging over a period of half an hour to improve the timing accuracy. This equates to a location error of approximately 10m. This is a reasonable level to aim for.

For the production quantity of systems, a custom design would be cost effective, but it must use the averaging techniques of the commercial systems if the required accuracy is to be achieved.

5.6.5 ADC Clock

A sampling clock provides the input clock frequency to the digitiser / digital receiver. This needs to have an extremely low jitter (below 0.5ps) if the full dynamic range of a 14 bit digitiser is to be achieved at a 100MHz sampling rate.

The output of the clock must be impedance matched to the input impedance of the digitiser.

Page 117: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 117

5.7 TDOA architectures

5.7.1 Introduction

Although it is possible to perform TDOA geolocation using only three sensors, the position fix produced can sometimes be ambiguous. It can be made unambiguous by using a fourth sensor. Using four or more sensors can also reduce the error in the position fix due to multipath or random measurement error.

Three sensors will give two TDOA hyperbolas which will cross at 0, 1 or 2 points. Although these points will not correspond exactly to the emitter location due to measurement errors, they will each be well-defined. However with more sensors, there will be three or more hyperbolas. If there are any errors in the TDOA measurements, these will not all intersect at a single point so, to obtain a position fix, the lines must be combined by some optimisation algorithm.

The most important performance metrics for a multi-sensor geolocation algorithm are the expected accuracy of the position fix and how well the accuracy of this fix may be estimated. Several algorithms are proposed in this report and their performance against these metrics is discussed qualitatively for a multipath co-channel environment.

5.7.2 Sensor Selection

If a very large array of sensors is available, the first decision which needs to be made is which ones should be used to perform the position fix and how the correlations should be performed?

Figure 5.11 –The master sensor should task all of its nearest neighbours

The optimum geometry for three sensors is always obtained by sensors which surround the target emitter (i.e. the emitter lies within the triangle formed by the

Page 118: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 118

sensors). However when locating a weak signal, such as a source of interference, it may only be possible to detect its presence at one of the sensors. The sensor which has the strongest SNR will be referred to as the master sensor and is marked in red in Figure 5.11. The master sensor is likely to be the one which is closest to the emitter. This master sensor and all of its ‘nearest neighbours’ should then be tasked to collect data simultaneously. This should ensure that at least one set of 3 tasked sensors surrounds the target emitter.

With a large array of sensors, not every sensor will be required to locate a transmitter, and many may be too far from the transmitter to be of any use. A decision must also be made on which sensor pairs to use in the correlation.

The signal strength is likely to be greatest at the master sensor so captures from each of the other sensors in turn should be correlated with the capture from the master sensor. Thresholding of the correlation SNR may be used to eliminate any sensors where the signal strength is too low to produce a reliable correlation.

A position fix using three sensors could be ambiguous, so ideally four or more sensors should be used.

5.7.3 Timing errors

Each TDOA measurement from a pair of sensors will be subject to a random error, ∂t. If all the errors are independent and normally distributed, then increasing the number of measurements used should improve the accuracy of the position fix. However, if a very large ∂t is included in the calculation then the error in the position found may be much worse than if it was not included. If different sensor pairs are expected to give different errors, perhaps because the sensors are of different types or because some of them are in poor multipath areas, the algorithm should give greatest weight to those measured TDOAs which are expected to have the smallest errors.

5.7.4 Multipath

A multipath environment can add echoes or delays onto a signal captured at a sensor, effecting the measured TDOAs and hence the calculated locations. Multipath is likely to be the greatest source of geolocation error.

If a sensor does not have clear line-of-sight to an emitter than the signal from the emitter must reflect off other objects on its way to the sensor. This increases the path length so it delays the time at which the signal arrives. If a correlation is being performed between sensors A and B, where A has line–of-sight to the emitter and B does not, the effect of the multipath will be to make it look as if the emitter is further from sensor B than it really is so the resulting TDOA line will not pass through the true emitter location. It is likely that several components of the signal will be received at sensor B, each with different amplitudes and different delays. Each component will produce its own peak in the correlation but the time differences between the peaks are likely to be small compared with the peak width so they combine to give a single peak whose precise TDOA value is an average of the TDOAs resulting from each multipath component.

Page 119: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 119

If the sensors are all at roughly equal distances from the emitter then it may be reasonable to expect that the signals received at each of the sensors will have been subjected to similar amounts of delay so the multipath effects will cancel out to some extent. The effects of multipath will be worst if, within each sensor pair, one sensor experiences multipath and the other does not. This could be the case in Figure 5.9 since the master sensor is significantly closer to the emitter than any of the other sensors. If the received signal levels suggest that the emitter is very close to the master sensor, it might be advantageous if the master sensor tasked its neighbours to capture and correlate signals but did not itself take part in the geolocation process.

5.8 Emitter Location techniques

The location algorithm must take information from a set of correlation surfaces and combine it to produce the positions of any emitters. It should also provide an estimate of the confidence of each position which it finds.

The AMS demonstrator system uses an algorithm which assumes that there are always three sensors available. The algorithms discussed below consider the use of four or more sensors to solve the potential ambiguities which arise when only three sensors are used. The algorithms also have the potential to improve on the accuracy by the use of more sensors.

The Exhaustive Search Algorithm and the Optimal Solution Algorithm, are designed to include information from all available sensors to reduce the random errors in the locations. Careful modelling is required to determine if there really is much advantage to be gained from this approach. It is the nature of this approach that many of the sensor pairs will have poor geometries and SNRs for locating the emitter, so are unlikely to give much improvement on the PF.

Provided the errors are truly random, a similar improvement in accuracy could be obtained from a longer capture or by repeat locations using only 3 sensors. However, if there are errors due to multipath or co-channel signals, then all the repeated measurements will be subject to the same effect so the errors will remain.

5.8.1 Calculation of TDOA position loci

Correlating data between a pair of sensors will give a single TDOA value which can be mapped onto a hyperbola on the ground. Using the TDOAs from the various sensor pairs, multiple lines of possible emitter positions can be calculated. At least two lines are required to define a position, as in the three-sensor demonstrator but, if there are more sensors, more lines can be used to refine the position. As errors are inevitable, there will not be a single point of intersection of all the lines, but a user can estimate the location of the emitter, and a measure of the confidence from how close the lines come to all intersecting. This technique is the most straightforward to implement, and is computationally efficient.

Page 120: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 120

Figure 5.12 - Each pair of sensors gives a "Line of Position"

5.8.2 The extended three sensor algorithm

A problem with using only three sensors is location ambiguities. If only one emitter is present, the two TDOA hyperbolas may intersect in two places, only one of which will be the correct location. If there are two or more signals present, then it will not be known which of the hyperbolas from one sensor pair correspond to which of the hyperbolas from the other pair, which produces more ambiguities.

Ambiguities can be removed by using four sensors, shown as green circles in Figure 5.13, and running the 3 sensor algorithm twice. First the algorithm is run on sensor set 1, giving the positions shown by the red crosses. The algorithm is then run again on sensor set 2. Another set of possible emitter locations, shown by the blue crosses, will be produced. Those position fixes which correspond to real emitters will appear in the same place in both sets, to within the size of the error ellipse, whereas the ambiguities will not.

Page 121: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 121

Set 1Set 2

Figure 5.13 - Using a fourth sensor to remove ambiguities

5.8.3 Maximum likelihood search

Rather than trying to associate peaks from different sensor pairs and calculate the point where multiple hyperbolas come closest to intersecting, it may be simpler, although more computationally expensive, to do a maximum likelihood search.

First, a search area where all the emitters are expected to lie is identified on the ground. A grid of points is then overlaid on this area. For the first point on the grid, the TDOA which would be expected for each sensor pair for an emitter at that position is calculated. The error between the calculated TDOA and the closest measured TDOA value is then found for each sensor pair and the RMS of these errors is used as a measure of the likelihood of an emitter being present at that position; the lower the RMS error, the more likely it is. The same calculation is then performed for each of the other points on the grid. The result will be an error surface which has a minimum wherever there is an emitter.

Alternatively, to eliminate the need for a set of TDOA values to be found from each correlation, for each point on the grid the expected TDOA can be calculated for each sensor pair as before, and the value of the correlation function at this TDOA value can then be looked up. The resulting correlation strengths for all of the sensor pairs can be combined to produce a likelihood value for that point on the grid.

This second method has the advantage that information about the SNR and width of each correlation peak is automatically pulled through into the likelihood surface but it is computationally intensive, and therefore slow. To ensure that the peak is not missed, the search must be performed at point spacing less than half the expected width of the correlation peak. The higher the bandwidth, the narrower the correlation peaks will be. For instance, a bandwidth of 1MHz would

Page 122: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 122

give a correlation peak width of about 1000ns so the peak on the likelihood surface would have a width of about 300m. This would restrict the grid point spacing to a maximum of 150m so a grid of 400 by 400 points would be required in order to cover a 60km square.

To speed up the search, the captured signals could initially be filtered to a reduced bandwidth so that a course grid could be used to find the approximate position. Then a finer grid over a smaller area can be searched using the full bandwidth to refine the location.

An advantage of doing a grid search is that the calculation of the expected TDOAs for each point can make use of terrain mapping data, whereas the algorithms which involve calculating the equation of each TDOA line are restricted to solutions in one plane.

The speed of a maximum likelihood algorithm may be improved by using a simplex search as an alternative to the exhaustive grid search to find the maximum of the likelihood surface.

5.8.4 Simplex Search

Rather than evaluating all points in a search area, a starting point, or seed value is used. The error gradient at this point is used to suggest the best direction to move to find the next test point. An analogy to this method could be standing on a hill side and walking in the direction of the steepest gradient as a way of finding the top. The simplex search will only give one position so it cannot be used if multiple emitters are expected to be present.

Care must be taken to ensure that the global maximum is found, rather than some local maximum which is dependent on the initial position. A simple way to avoid this problem is to run simplex searches from a few different starting points. Increasing the number of sensors tends to make the surface smoother, reducing the risk of there being local maxima.

5.9 Communication between sensors

The internet will form the backbone of the sensor network. It is anticipated that the final system will use whatever network medium is available to connect to the internet. This should be broadband wherever possible.

The final system will be capable of providing full control of remote sensors from either regional or national control centres. A network hierarchy for data management is essential to prevent the maximum available bandwidth from being exceeded for the control centres.

Some features are bandwidth intensive (e.g. real time spectrum / emissions displays), so might only be available on higher bandwidth links. Similarly location of weak signals where long sample lengths are required could have latency across a narrow band link.

Page 123: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 123

The AMS system will use the TCP/IP protocol across the Internet. This allows the use of nearly any modern communication bearer or interface and significantly lowers the communications hardware requirements as the backbone of the network is already in place. Furthermore it allows multiple systems to be controlled simultaneously from a single control centre as opposed to only a single one with a point to point link.

5.9.1 Network control

With a large network of sensors, as is proposed for the AMS system, it is essential to keep tight control over the configuration. This will be administrated by a central communications service to which all sensors and control stations have access. The sensors register their position, status and most importantly external IP address with this service. This information is then available for control stations to access information on the sensors, and for other sensors to identify their neighbours for TDOA tasking.

Figure 5.14 suggests a block diagram for the network design. Multiple sensors connect via the Internet to the primary and secondary controllers supplying their BIT (built in test) status, latitude and longitude location, TCP/IP address and port. AMS users then connect to the primary or secondary controller to determine available sensors in the correct locality for signal observation or tasking for location processing.

INTERNET

SENSOR

SENSOR

SENSOR

SENSORSENSOR

PRIMARYCONTROLLER

SECONDRYCONTROLLER

USERS

USERS

Figure 5.14, Internet connectivity

Page 124: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 124

Primary and secondary controllers will be required to provide a backup in the event of a failure. The access to the controllers can be controlled, via IP addresses or MAC addresses or usernames and passwords, and this effectively results in access to the sensor system being secured. To maximise system security all sensors should run anti-virus software and operate firewalls.

The sensors will connect to the Internet using individual modems and a user tasking the system will be able to communicate simultaneously with multiple sensors using a broadband internet connection. This Internet infrastructure usage eliminates the need for multiple modems at the users’ locations to handle the multiple simultaneous information flows.

5.9.2 Data storage

Database repositories will be required in different parts of the sensor network to record the data being collected by the sensors. The database repositories required are:

• Sensor repository,

• Regional repository,

• Regional backup repository,

• Central repository,

• Central backup repository.

Figure 5.15 shows an example part of the hierarchy of the AMS collection system. In region 1 a number of sensors are distributed in a local area. A number of similar regions will collectively cover the whole country. Emission data collected from the sensors in the region are sent to the regional servers via the internet. The secondary regional server continually mirrors the primary server so no emission data and sensor information is lost in the event of a failure. The central server collates the emission and position data from the regional servers. The sensors in all regions can be monitored to ensure they are functioning effectively. Again a secondary server will mirror the central server so no emission data and sensor information is lost if the primary server fails. All sensors can be monitored to ensure they are functioning effectively.

Page 125: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 125

RS CS TR RD TD CDTALK / DATA

TALK ADSL Modem

Regional

Database

AMS Sensor n

Primary

Regional

Server

Secondary

Regional

Server

1 2 3 4 5 6

7 8 9 101112

AB

12x

6x

8x

2x

9x

3x

10x

4x

11x

5x

7x

1x

Eth

erne

t

A

12x

6x

8x

2x

9x

3x

10x

4x

11x

5x

7x

1x

C Router/Firewall

Local datase

WWW Server

Hardware Firewall

Regional

Backup

Database

Central

server

Central

Database

Secondary

Central

Server

Secondary

Central

Database

1 2 3 4 5 6

7 8 9 101112

AB

12x

6x

8x

2x

9x

3x

10x

4x

11x

5x

7x

1x

Eth

erne

t

A

12x

6x

8x

2x

9x

3x

10x

4x

11x

5x

7x

1x

C RouterRS CS TR RD TD CD

TALK / DATATALK ADSL Modem

AMS Sensor 1

Local datase

Region 1

Internet

Figure 5.15, Example network layout

Sensor repository

The sensor repository will continually record emissions details and occupancy detected by the sensor. These emission details are:

• Emission ID,

• Frequency,

• Bandwidth,

• Amplitude,

• Start time,

• Duration,

• Modulation type.

Additionally position fix results will be stored in the database. The parameters that are recorded are:

• Task ID,

• Task time,

• Sensors tasked to obtain the position fix,

• Capture parameters returned from the sensors tasked to achieve the position fix (e.g. position, actual capture time),

Page 126: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 126

• The calculated position,

• Estimate of confidence in the position fix.

Regional repository

The regional repository will collate data recorded by individual sensors (as described in section 0). Many sensors will detect the same emissions so it is the responsibility of the regional repository to remove duplicate entries, and to form a picture of the regions spectrum usage and occupancy, and to provide a means of archiving collected data. Data transfers can take place during quiet periods to ease network congestion.

Database reporting will be available to provide statistics on spectrum usage and identifying illegal or interfering emissions.

Regional backup repository

The regional backup repository will provide a live hot swappable backup of the regional repository if it fails.

Central repository

The central repository will collate summary occupancy data from the regional repositories providing a picture of the UK spectrum usage.

Database reporting will be available to provide statistics on spectrum usage and identify illegal or interfering emissions.

The database will be accessible in a read only mode via a web server to allow access to government, educational and other institutions that have an interest in the data collected.

Central repository backup

The central backup repository will provide a live hot swappable backup of the central regional repository if it fails.

License database

Database entries are to be cross referenced against to determine if transmissions are in accordance with agreed terms in the Ofcom licensed user database.

5.9.3 Data Transfer Messages

Messages will be sent from the sensor to control centre, and control centre to sensor to describe emitters and their emissions for subsequent display as well as sensor tasking commands. A key requirement for the AMS design is that the unit be operable remotely. The summation of the data messages per unit time must not exceed the available communications bit rate. The data required to be sent over the link are:

• Service location. To allow the discovery of the unit upon the Internet.

• Data types required. This message specifies what data (spectrum plots, emissions, modulation classification results) to send to the control centre, for

Page 127: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 127

example all automatic data items can be stopped in the event of a low bandwidth ink.

• Emission detections. These messages identify a unique emitter that has gone on, off, or has timed out, its amplitude and timing parameters.

• Spectrum display. This shows in real time the radio frequency environment that the sensor is seeing.

• Modulation classification results. These are strings that describe the modulation of an emission at a specific time and frequency.

• Location request messages. These specify the time, frequency, and bandwidth of an IQ data capture for the purposes of emitter location via time difference of arrival techniques.

• Location data replies. Specifying the location request and the data to be returned.

• Data selection message. This specifies which of the available data items above are to be sent from sensor to HMI.

5.10 Software

5.10.1 Current QinetiQ capability

Over the last seven years QinetiQ have been developing high specification spectrum monitoring and modulation classifier applications capable of working analogue and digital signal types. The software will manage and control multiple wideband scanning sensors and is designed to operate in an intuitive manner with minimal operator training. It is recommended that the AMS spectrum monitoring and modulation classification functionality is based upon QinetiQ’s existing capability.

This software has the ability to:

• Display real time and historical results from multiple sensors separated geographically but connected by a network,

• Determine the presence of networks of emitters by matching of signal parameters such as frequency, modulation type and locations,

• Log sensor results to hard disk at regular intervals,

• Manage the transfer of the information between sensors to optimally achieve location of all emitters,

• Calculate position fixes based on TDOA techniques based on information from multiple sensors,

• Show position fixes on a digital map,

• Report results dependent upon pre-set filters.

Page 128: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 128

The software at each sensor logs emissions from emitters as they occur and saves these to disk after a configurable interval. Requests on emissions that have occurred are made by a designated master to the other AMS applications running on remote sensors, and these then mine their history databases to find time and frequency correlating emissions.

Narrow band captures can be tasked across multiple sensors and data returned to a single point to allow correlation and position fixing.

The QinetiQ modulation classifier proposed for the AMS unit has the capability to process the following modulation types:

Analogue signal types:

CW, AM, FM/PM, FM, SSB, DSB, USB, LSB.

Digital signal types:

ASK, MSK, FSK, PSK, QAM, ASK/PSK Hybrids.

Additional Signal Type Descriptors: Voice, Tone, Morse, Radio Teletype (RTTY), CTCSS and Chirp detection is also applied to suitable signals

5.10.2 Key functionality

Table 5.7 highlights the key components that should be included within the software for the final AMS system. Refer also to section 6.6.3 for sample display plots.

Component Description

Real time display The AMS component needs to support real time displays to show spectrum plots and detected emissions over a selected frequency range from any sensor on the network. Additionally historical displays should be viewable in the form of waterfall plots.

Mapping The mapping component allows the application to view position fixing results as well as sensor locations and tracks.

Various standard mapping formats are available commercially and should be supported.

Location Fixing The location component allows the sensors to operate co-operatively to calculate the location of an emitter. This links in with the mapping component to display location results, and will plot also show estimates of errors in the form of confidence

Page 129: Qinetiq Report on Geolocation

QINETIQ/06/00039 Page 129

Component Description

ellipses.

Spectrum Occupancy

The spectrum occupancy component allows usage as a function of time to be plotted in the form of waterfall plots. This view also allows percentage occupancy to be monitored.

Clear channel data should also be shown either graphically or in tabular form.

Filtering The filtering component sits between any data store within the application and the user displays with functionality that prevents data being displayed that does not pass the filtering criteria.

This is applicable to spectrum views to reduce the numbers of emissions being displayed and map views to only display locations from selected emitters.

Results Display The result display component displays to the user information he/she has requested. This is used to display, for example, detailed emitter perameters or location results.

Targets A target component allows identification of signals of interest for monitoring, signal classification or location.

Handoff Receiver The handoff receiver component is responsible for controlling handoff receivers, setting, frequency, mode and scanning.

Audio Streaming The audio-streamed component allows demodulated audio streams to be transferred across the network from a remote sensor to the control centre.

Table 5.7, Key software components