Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM
37

Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

May 22, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

Public Service Company of New Mexico

Open Transmission Planning Meeting November 2, 2017

Albuquerque, NM

Page 2: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

2

INTRODUCTION • Public Stakeholder Meeting

– Order 890 Objective to improve transparency and stakeholder involvement.

– Planning Process Defined in Attachment K of OATT • March Meeting Reviewed

– Planning Process – Coordination with WECC (PCC & TEPPC), WestConnect – PNM 10-Year Plan Study Scope

• November Meeting – Review 10-Year Plan Results – Input to Next Planning Cycle – Certain Other Business

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

Page 3: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

3

10-YEAR TRANSMISSION PLAN

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 4: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

4

10-YEAR TRANSMISSION PLAN

• OBJECTIVES OF STUDY EFFORT: • Support Data Base Development for PNM and

Regional Studies – 2019 (1-yr), 2022 (5-yr), 2027 (10-yr)

• Maintain Reliability • Define Transmission for Native, Network and

Point-Point Customers • Incorporate Plans Developed Through FERC

Processes, NM IRP and Regional Planning Analysis

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 5: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

5

STUDY SCOPE

• Review transmission adequacy with retail and network customer updates to designated network resources and load.

• Determine if system mitigations are needed to serve expected obligations (load forecasts and expected firm transfers) during the 10 year planning horizon without violating WECC/NERC reliability standards.

• Develop operational mitigations or system improvements to maintain system reliability and associated cost estimates and schedule.

• Incorporate assessments of economic congestion to the extent a need is identified by PNM’s or other’s involvement in the WECC process for providing this type of assessment.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 6: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

6

PROJECT DRIVERS

• Compliance with Reliability Standards • Provide Service to New Load Locations • Interconnection Projects • Recommendations for projects requiring

joint study or solutions

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 7: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

7

Project Overview

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 8: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

8

Northern New Mexico

Northern New Mexico Projects

Yah-Ta-Hey Transformer (ISD 2017)

Completed Project

Planned Project

Richmond Station (ISD 2017)

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 9: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

9

Southern New Mexico Projects

Southern New Mexico

Completed Project

Planned Project

Alamogordo Voltage support Phase 2 (ISD 2022+)

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 10: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

10

COMPLETED RELIABILITY PROJECTS

• Richmond Switching Station • 2nd Yah-Ta-Hey Transformer

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 11: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

11

RELIABILITY PROJECTS UNDER CONSTRUCTION

• None

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 12: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

12

PLANNED RELIABILITY PROJECTS

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 13: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

13

ALAMOGORDO VOLTAGE SUPPORT PHASE 2

• In-Service Date: 2012+ • Purpose – Provide adequate

voltage support and operational flexibility by increasing the transmission load serving capability.

• Project includes – Installation of an additional

switchable shunt capacitor

Holloman

Dona Ana Tularosa

Amrad

Load

Carrizo

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 14: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

14

OTHER PROJECTS

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 15: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

15

OPERATOR OR RAS SOLUTIONS

• Only Local Area Impacts • Certain N-2 overloads addressed by RAS or

Operator action. – Generation Re-dispatch – Load Shedding – Capacitor switching – Transformer Tap Adjustments

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

Page 16: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

16

Interconnection and Transmission Service Projects

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 17: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

17

Interconnection and Transmission Service Related Projects

• Generator Interconnection – El Cabo Wind Farm interconnection at Clines Corners completed

Spring 2017. • Wire-Wire Interconnections

– Blackwater Expansion for Western Interconnect Tie – completed – Cabezon Switching Station - 2018

• Transmission Service Projects – Guadalupe SVC – 2018 – Blackwater Synchronous Condenser – 2019 – Albuquerque-Clines Corners 345 kV Line – late 2020

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 18: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

18

El Cabo Wind Farm

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 19: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

19

Blackwater 345 kV Switchyard Expansion

• Expand to a 3 breaker ring bus configuration to accommodate an interconnection to Western Interconnect line.

• Western Interconnect transmission line will interconnect Broadview and planned Grady wind generation facilities.

• In-service date December 2016 (Broadview)

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

Page 20: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

20

Blackwater Station Expansion

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 21: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

21

Cabezon Switching Station • 33 miles north of Rio Puerco on the San Juan – Rio

Puerco 345 kV transmission line. • A 3 breaker ring that provides a new delivery point

Tristate G &T under the Network Transmission Service Agreement.

• Tristate will provide a 345 to 115 kV transformer which ties into the Algodones – La Jara 115 kV line segment.

• In-service spring of 2018

PNM Open Transmission Planning Meeting

November 2, 2017 Albuquerque, NM

Page 22: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

22

Wires to Wires Interconnections

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 23: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

23

Guadalupe SVC

• Size: -100 to +250 MVAR • Voltage support for transmission service

provided to Pattern and Avangrid. • Guadalupe Switching Station expanded to four

terminations to accommodate SVC. • 2018 in-service date.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 24: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

24

Guadalupe SVC

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 25: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

25

Blackwater Synchronous Condenser

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 26: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

26

Proposed Clines Corners-Albuquerque 345 kV Line

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 27: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

27

10-YEAR PLAN QUESTIONS?

Ten-Year Plan Report Available for Stakeholders completing CEII Request

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 28: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

28

2017 STUDY PLAN INPUT

• March Meeting to Review 10-Year Plan Scope

• Discussion

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 29: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

29

Large Generator Interconnection Cluster Activity

• Six Definitive Cluster closed August 10th, 2015 – Two requests of 120 MW are in LGIA negotiations. – One requests of 38 MW is in FACS study mode

• Seventh Definitive Cluster closed May 6th, 2016 – 400 MW is in LGIA negotiation.

• Eighth Definitive Cluster closed January 31, 2017 – Twelve requests of 1250 MW in SIS study mode

• Seventh Preliminary Cluster closed June 2, 2017 – One request of 50 MW in SIS study mode

• Ninth Definitive Cluster Closed October 30th – Reviewing requests, will be posted on oasis.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 30: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

30

Next Cluster Window

• Definitive Interconnection Cluster Window opens April 29th, 2018 and closes July 27, 2018

• Preliminary Interconnection Cluster Window opens November 30thth, 2017 and closes February 27, 2018

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 31: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

31

REGIONAL ACTIVITIES • SunZia

– Permitting activities Ongoing – Commercial operation date in late 2020 – www.sunzia.net

• Lucky Corridor – Project modified to single 345 kV line from Gladstone area to Ojo switching

station – Completed WECC Project Coordination Review Group report

• Mora Line Project – Lucky Corridor's Mora Line project is designed to carry 180 MW at 115 kV. – 102 miles – Working on Facilities study with PNM

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 32: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

32

REGIONAL ACTIVITIES

• Southline Project – WECC Rating Process Completed March 23, 2015 – Construction expected to begin in 2018 – In Service Date: In phase between 2018 and 2020 – August 2017 Fact Sheet Available on website:

www.southlinetransmissionproject.com

• Centennial West Clean Line Project – See project website for latest developments.

• Western Spirit Clean Line Project – Approximately 1000 MW 345 kV Project to increase access from Central New

Mexico to the Four Corners hub. – Facilities Study for interconnection to PNM completed in September 2017.

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 33: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

33

REGIONAL ACTIVITIES

• Verde Project – Interconnects to PNM’s Ojo and Norton 345 kV stations – System Impact Study completed in March 2017 – Expecting completion of Facilities Study November 2017 – 2016-2017 Permitting, Public Engagement, ROW, Engineering – 2018-2019 Construction, In Service Date 2020

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 34: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

34

Map of Regional

Transmission Projects

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 35: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

35

ORDER 1000 UPDATE • Adds planning process for identifying regional projects that are more

cost effective and efficient than projects in local plans. • Establishes cost allocation methodology for regional projects. • Full Biennial Cycle 2016-2017 mostly complete

• No regional projects identified.

• Current Activities: – Annual Stakeholder meeting – November 16th – Tempe, AZ – Start discussions for scoping 2018-2019 Biennial Planning Cycle

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 36: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

36

NEXT MEETING

March 1, 2018

PNM Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM

Page 37: Public Service Company of New Mexico · 2017-10-24 · Public Service Company of New Mexico . Open Transmission Planning Meeting . ... Load Shedding – Capacitor ... In-service date

QUESTIONS OR COMMENTS?

Tom Duane [email protected]