Top Banner
Public Meeting November 9, 2016 SRQ Media Room
21

Public Meeting November 9, 2016 SRQ Media Room

Feb 14, 2017

Download

Documents

vankhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Public Meeting November 9, 2016 SRQ Media Room

Public Meeting November 9, 2016 SRQ Media Room

Page 2: Public Meeting November 9, 2016 SRQ Media Room

Agenda

• Call Meeting to Order • Approval of Minutes • Program Schedule Review • Phase 1 MOT Plan Update • LS 87 Landscape Plan • Phase 1 Schedule Review • Outstanding Business • New Business • Public Input • Adjournment

Page 3: Public Meeting November 9, 2016 SRQ Media Room

Program Overview

PHASE 3 LS 87 Gravity

Mains

PHASE 1 LS 87 Microtunneling

PHASE 2 LS 87 Structure

PHASE 3 LS 7 Demo and

Restoration

ALTA VISTA STREET

US 41

POMELO AVE O

SPR

EY

AVE

POM

ELO

PL

ACE

Construction Sequencing – 3 Phases

Page 4: Public Meeting November 9, 2016 SRQ Media Room

Program Overview

Phase Start Finish

2015 2016 2017 2018 2019 2020

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Q 1/2

Q 3/4

Con

stru

ctio

n

Phase 1 May 2016

July 2017

Phase 2 May 2017

Oct. 2019

Phase 3 Aug. 2019

Dec. 2020

Projected Construction Timelines

Page 5: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 – Lift Station 87 Microtunneling Maintenance of Traffic Plan Update

To maintain safe traffic flow during construction by:

• Directing traffic to Mound Street/US 41 to avoid neighborhoods

• Addressing pedestrian detours and sidewalk closures

• Identifying access to businesses on Osprey Avenue

Page 6: Public Meeting November 9, 2016 SRQ Media Room

Lift Station 87 Landscape Plan

Public Participation Overview

• Series of Public Meetings Hover Arcade

Brick Façade

• Public Meeting – July 26, 2016

Page 7: Public Meeting November 9, 2016 SRQ Media Room

Red Brick Option

Page 8: Public Meeting November 9, 2016 SRQ Media Room

Sarasota High School

Page 9: Public Meeting November 9, 2016 SRQ Media Room

Landscape Architectural Renderings

• Site Plan Application

December 2014

Input from Urban Design Studio

• Landscape Architect – David W. Johnston Associates, Inc.

Phillip J. Smith, ASLA

Page 10: Public Meeting November 9, 2016 SRQ Media Room
Page 11: Public Meeting November 9, 2016 SRQ Media Room
Page 12: Public Meeting November 9, 2016 SRQ Media Room
Page 13: Public Meeting November 9, 2016 SRQ Media Room
Page 14: Public Meeting November 9, 2016 SRQ Media Room
Page 15: Public Meeting November 9, 2016 SRQ Media Room
Page 16: Public Meeting November 9, 2016 SRQ Media Room
Page 17: Public Meeting November 9, 2016 SRQ Media Room
Page 18: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 Schedule Review

• Jacking Shaft MH17 (Between Lincoln and Bridge)

October/November 2016

• Receiving Shaft MH21 (Osprey/US 41 Intersection) December 2016/January 2017

• Jacking Shaft MH24 (Luke Wood Park) December 2016/January 2017

Page 19: Public Meeting November 9, 2016 SRQ Media Room

Phase 1 Schedule Review

• MT Drive 1 (Osprey Avenue)

December/January 2017

• MT Drive 2 (Luke Wood Park) February 2017

• Demobilization July 2017

Page 20: Public Meeting November 9, 2016 SRQ Media Room

• Outstanding Business

• New Business

Page 21: Public Meeting November 9, 2016 SRQ Media Room

Public Input