Page 1: Public Hearing South Dakota Public Utility Commission ...

Public Hearing South Dakota Public Utility Commission

Groton, South Dakota

May 12, 2008

East River Electric Power Cooperative Application For Permit To Construct

Crandall 115 kV Line Tap

Page 2: Public Hearing South Dakota Public Utility Commission ...

East River Electric’s Service Area

Page 3: Public Hearing South Dakota Public Utility Commission ...

East River Electric’s Service AreaLAKE REGION ELECTRIC SERVICE AREA

NORTHERN ELECTRICLAKE REGION ELECTRIC

CODINGTON-CLARK ELECTRIC

Page 4: Public Hearing South Dakota Public Utility Commission ...

Pump Station4 large pumps

15 MW

BristolGroton

Crandall

LAKE REGION ELECTRIC SERVICE AREA

Page 5: Public Hearing South Dakota Public Utility Commission ...
Page 6: Public Hearing South Dakota Public Utility Commission ...

Pump Station4 large pumps

15 MW

BristolGroton

Crandall

LAKE REGION ELECTRIC SERVICE AREAHIGH VOLTAGE DELIVERY SYSTEM

115 KV Transmission Line

345 KV Transmission Line

Fort RandallPickstown, SD Watertown, SD

Page 7: Public Hearing South Dakota Public Utility Commission ...

Bristol

OPTIONS FOR PROJECT LINE ROUTE

Groton

Crandall

115 kV to 69 kV Transformation

Voltage DropGreater with 69 kV

69kV

69kV

115/69 kV Transformation

345/115 kV Transformation

Motor sizes for pumpsdictate need for 115 kV

voltage source

115 kV

-Stronger Delivery Point

4 large pumps15 MW

69kV

Page 8: Public Hearing South Dakota Public Utility Commission ...

Transmission Line Route

Page 9: Public Hearing South Dakota Public Utility Commission ...

Crandall Substation

Western’s Groton Substation

FERNEY

Page 10: Public Hearing South Dakota Public Utility Commission ...

Transmission Structures

Page 11: Public Hearing South Dakota Public Utility Commission ...
Page 12: Public Hearing South Dakota Public Utility Commission ...
Page 13: Public Hearing South Dakota Public Utility Commission ...

Single Pole Double Circuit 115/69 kVSingle Pole Double Circuit 115/69 kV

Page 14: Public Hearing South Dakota Public Utility Commission ...

115 Kv Line Structure with 115 Kv Post Insulators115 Kv Line Structure with 115 Kv Post Insulators

Page 15: Public Hearing South Dakota Public Utility Commission ...

Line on Private LandLine on Private Land

Page 16: Public Hearing South Dakota Public Utility Commission ...

Road ROW Private Land

Page 17: Public Hearing South Dakota Public Utility Commission ...

Road ROW Private Land

Page 18: Public Hearing South Dakota Public Utility Commission ...

Approvals Required• Six governmental agencies will have reviewed and

approved before commencement of construction– U.S. Fish and Wildlife– U.S. Army Corp of Engineers– South Dakota Department of Natural Resources– South Dakota Department of Game Fish and Parks– South Dakota State Historical Society– South Dakota Public Utility Commission

Page 19: Public Hearing South Dakota Public Utility Commission ...

County franchise obtained for both Brown and Day Counties

Page 20: Public Hearing South Dakota Public Utility Commission ...

Time frame for construction

Begin - Late 2008 Complete – Early 2009

Page 21: Public Hearing South Dakota Public Utility Commission ...

Contact Information

Dan Wall Manager Transmission/Engineering Services

Ron Golden Land Management Supervisor

Jim Edwards Assistant General Manager Operations

East River Electric Power Cooperative 605-256-4536

Page 22: Public Hearing South Dakota Public Utility Commission ...