PTT Analyst site visit Date : 8 February 2014
13

PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

May 26, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

PTT Analyst site visit

Date : 8 February 2014

Page 2: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Type Run-of-river hydropower

Capacity 1,285 MW

Location Xayaburi, Lao PDR

Offtaker 1,220 MW : 29-yr PPA with EGAT

60 MW : 29-yr PPA with EdL

Project Cost ≈THB 115 billion

YOUR SENSE OF ENERGY

1

Page 3: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Logistic to site 1) BKK - Vientiane (by plane),

Vientiane-Xayaburi (by plane)

2) BKK – Luangphabang (by plane),

Luangphabang – Xayaburi (by car~ 120 km, 3 hr)

3) BKK – Loei (by plane),

Loei – Xayaburi (by car, ~60 + 200 km, 1+3.5 hr)

XAYABURI HPP

Loei

Luang Prabang

Vientiane

Xayaburi

บ้านนาหลา บ้านตาลาน

โครงการ

เมืองไซยะบรีุ

2

Page 4: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

GPSC

EGCO NSC

XPCL

100%

25.0%

CK EdL P.T

30% 20% 5%

Laos Thai

12.5%

BECL

7.5%

• Ch. Karnchang Public Company Limited (CK) 30 % • Natee Synergy Company Limited (PTTI) 25 % • Electricity Generating Public Company Limited (EGCO) 12.5 % • Bangkok Expressway Public Company Limited (BECL) 7.5 % • P.T. Construction and Irrigation Company Limited (PT) 5 % • Electricite du Laos (EdL) 20 %

PTT

PTT

Global

Chemical

Thaioil Thaioil

Power

3

Page 5: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

XPCL EGAT

EdL

EPC

(CK-Lao)

P1 (Civil) P2 (Hydromechanical)

Whessoe

P3 (Electromechanical)

Andritz P4 (Transmission)

GoL

Lenders (KTB, BBL, SCB, KBANK,

Thailand EXIM, TISCO)

Project Developers

Lender’s Engineer

(POYRY)

Owner Engineer

(SEAN)

Lender’s legal advisor

EIA

(TEAM)

CA

PPA

PPA

SHA

CFA

GoL’s Engineer

(POYRY)

EMP & RAP

(PT & TEAM)

Designer

(Colenco & TEAM)

EMP - Environment Manage Plan

RAP - Resettlement Action Plan

4

Page 6: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Main Contractor : Ch. Karnchang (Lao) Company Limited

Type of contract : EPC Turnkey Lump Sum Contract

Comprised of main 4 packages

1) Civil Works : Ch. Karnchang (Lao) Company Limited

2) Hydro-Mechanic : Whessoe (Malaysia) [Navigation lock gate, spillway gate, etc]

3) Electro-Mechanic : Andritz (Austria) [Turbines, Generators, 500kV & 115kV

substation, Control system, etc]

4) Transmission line : Cerieco (China)

5

Page 7: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

- Project Development Agreement signed : 25 November 2008

- Tariff MOU with EGAT signed : 5 July 2010

- EPC Contract signed : 14 Oct 2011

- Concession Agreement signed : 29 Oct 2011

- EGAT PPA signed : 29 Oct 2011

- Credit Facilities Agreement signed : 31 Oct 2011

- Notice to Proceed : 15 Mar 2012

- 1st drawdown : 12 Apr 2012

- COD : 29 Oct 2019

6

Page 8: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

7

Page 9: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Vientiane

Luangphabang

0 100 200 KM

Khon Kaen 4

Loei 2 (A.Tha Li)

XAYABURI HPP

by project

by EGAT

8

Page 10: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

9

Page 11: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Environment Management Program (EMP)

– Water quality monitoring program

– Public Health Management

– Fish Biomass and Fish Migration program

Resettlement Action Plan (RAP)

– Resettlement work

– Survey on Income generation

– Livelihood Restoration Program (LRP)

– Community Development Program (CDP)

10

Page 12: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

Social Issues

- Navigation Navigation Lock

Environmental Issues

- Sediment transfer Low level outlet spillway

- Fish migration Fish passing facilities Fishery program

11

Page 13: PTT Analyst site visit Date : 8 February 2014ptt.listedcompany.com/.../20140208-PTT-analystSiteVisit.pdf2014/02/08  · PTT Analyst site visit Date : 8 February 2014 Type Run-of-river

12