PSU Building Thermal and Mechanical Systems Laboratory Environment A/E Kurt M. Shank , M.S. & Stanley A. Mumma, Ph.D., P.E. College of Engineering Department of Arch. Engineering Penn State University @ University Park, PA Selecting the Supply Air Conditions for a Dedicated OA System Working in Parallel with Distributed Sen. Cooling Equip.
23
Embed
PSU Building Thermal and Mechanical Systems Laboratory Environment A/E Kurt M. Shank, M.S. & Stanley A. Mumma, Ph.D., P.E. College of Engineering Department.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PSU
Building Thermal and Mechanical Systems Laboratory
Environment
A/E
Kurt M. Shank, M.S. & Stanley A. Mumma, Ph.D., P.E.
College of Engineering
Department of Arch. Engineering
Penn State University @ University Park, PA
Selecting the Supply Air Conditions for a Dedicated OA
System Working in Parallel with Distributed Sen. Cooling
SA-DPT, and Terminal Reheat Load, Energy, and Cost impact of SAT Load, Energy, and Cost impact of SA-
DPT Terminal Reheat and SAT Conclusions and Recommendations
Objective
Challenge the current practice of supplying air from dedicated OA systems at a neutral temperature (~70F).
Develop a methodology for selecting the proper supply air conditions.
Hypothesis 1: Load, Energy, & Cost will decrease with DBT
LCC
44F 70F
PW, 1st & Op $
PW, Op $
1st $
System Wide Impact of DBT on Load, Energy, and
Cost Assumptions– Atlanta, GA data; 12 hr/day, 6 day/wk. – 10,000 scfm of OA– Supply air DPT, 44F– 20 scfm of OA/person– Resulting space DPT, 52F– Space condition, 78F, 40% RH– No terminal reheat required, i.e. space
not overcooled with ventilation air (relaxed later)
between the DOAS and the parallel system; i.e. reduce SAT (greater sensible cooling done) and reduce the load on the parallel system (there-fore size).
– Fan Coil first cost, $6/cfm– Ceiling Radiant Panel cost, $8/sq. ft.– Sensible Wheel in DOAS, $2/scfm OA
Building LoadDOAS Parallel
Load Mix with 10,000 scfm OA in Atlanta.
SAT
F
DOASCC Load
Ton
ParallelSys. Load
Ton
Peak LoadTon
70 27 23.4 50.455 39 9 4844 47 0 47
Reason Peak Load Increased with Increasing
SAT Because of less than 100% effectiveness at the enthalpy wheel, only about 80% of the sensible cooling done on the return air (state 5-6) by the supply air (state 3-4) is able to be recovered by the enthalpy wheel (state 6-2). Consequently, the more reheat, the greater the cooling required when the parallel system is considered. Illustrated on the next slide.
Reason Peak Load Increased
with Increasing SAT, illustrated
6 56’
1
22’
Path from 6-6’ is the increase in reheat, and the path 2-2’ is the reduction in coil load. Since it is shorter than 6-6’, the cooling coil load is not reduced as much as the cooling capability of the supply air when reheated.
Energy Mix with 10,000 scfm OA in Atlanta, 3744 hoursSAT
required to meet Std. 62--Which is why so many all air VAV systems use terminal reheat
– VAV box minimums are set to meet the ventilation requirements. The minimum setting will always be at or above that required by the DOAS system since “zc “ in Eq. 6.1 will always be less than or equal to 1.
Hypothesis 3: Terminal Reheat Issues continued:
– If “zc “ = 0.4 and a space needs 200 scfm of OA, then the box minimum must be 500 scfm. “zc “ for a dedicated OA system is always 1, so it will deliver the 200 scfm.
– A room served by a VAV box with a minimum setting of 500 scfm at 55F is prone to overcool the space sooner than the dedicated OA system supplying 200 scfm of air at either 55 or 44F. (500*[78-55] >200*[78-44]) or (11,500>6,800)
Balance Point IG/ft2=QDOAS/ ft2 + Qenv/ ft2 -Qsen/ ft2
Overcooling with the DOASGraphic from the energy
bal.
IG, W/ft2
0
15
Occupancy/1000 ft2
0 90
Winter
Summer
20
4
Example: 20 people per 1000 ft2 , 4 W/ft2, If the IG less than 4 W/ft2 with an occupancy density of 20, the DOAS will overcool; if more, need parallel cooling.
Conclusion:
The 3 hypothesis verified For many building applications,
terminal reheat is seldom if ever needed with 55F or even 44F SAT from the DOAS.
Old Paradigm of supplying the air at a neutral temperature, in dedicated OA applications, should be abandoned.
Recommendation The supply air DPT should be low
enough to maintain the space RH no higher than 40%, about 44F in many cases.
The supply air dry bulb temperature should be at 55F or below.
Where Occupancy densities are very high, and terminal reheat is frequently required, use recovered heat.