Top Banner
PSM 1/PSM 2 IDP/PRB NOTICE OF IMPLEMENTATION FROM 15 APRIL UNTIL 5 JUNE 2020
13

PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

Aug 03, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

PSM 1/PSM 2 IDP/PRB

NOTICE OF IMPLEMENTATION

FROM 15 APRIL UNTIL 5 JUNE 2020

Page 2: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

Table 1 : WEEKS IN REMAINING SEMESTER 2019/2020-2

As Movement Control Order (MCO) has been extended to 14 Apri l 2020, the

implementation of PSM 1 & PSM 2 shal l fol low the new UTeM’s academic

calendar as shown at Table 1.

Week PSM 1 PSM 2

W6

15 - 17/4No any lab/worksyop activity is allowed as preparation of the lab/worksyop for the new SOP (fully controlled)

W7

20 - 24/4No any lab/worksyop activity is allowed as preparation of the lab/worksyop for the new SOP (fully controlled)

W8

27 - 30/4 Continue with the literature review/methodology progress Continue with the data collection/experimental/product

development with scope revision

W9

4 - 8/5Continue Continue

W10

11 - 15/5Continue Continue

W11

18 - 22/5Poster Presentation

Log book submission

Continue

Log book submission

W12

25 - 29/5Aidil Fitri (24 & 25 May)

Report preparation

Aidil Fitri (24 & 25 May)

Report preparation

W13

1 - 5/6Report submission Oral Presentation

Report Submission

Page 3: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN FOR PSM 1

On-line poster presentation could be taken place.

Page 4: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN FOR PSM 2

1- Students need to update his/her progress to supervisor

before 20/4/2020 via e-communication.

2- Supervisor needs to refine the scope of work accordingly.

Page 5: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN FOR PSM 2

REMARKS (as EAC latest guidelines -30/3/2020):

1- Bagi projek-projek yang terpaksa dilaksanakan secara kaedah

hardware kerana peratus kerja yang telah signif icant, maka projek-

projek ini boleh diteruskan tetapi pelajar mungkin terpaksa berstatus

Tidak Selesai kerana projek mungkin akan menjangkau tarikhtamat

semester. Pelajar akan diberikan masa semasa semester khas untuk

menyiapkan projek.

2.Projek yang masih diperingkat awal pelaksanaan amat digalakkan

untuk diubah ke bentuk simulasi komputer.

Page 6: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

Table 2 : WEEKS IN REMAINING SEMESTER 2019/2020-2

As Movement Control Order (MCO) has been extended to 14 Apri l 2020, the

implementation of IDP & PRB shal l fol low the new UTeM’s academic calendar as

shown at Table 2.

Week IDP PRB

W6

15 - 17/4No any lab/worksyop activity is allowed as preparation of the lab/worksyop for the new SOP (fully controlled)

W7

20 - 24/4No any lab/worksyop activity is allowed as preparation of the lab/worksyop for the new SOP (fully controlled)

W8

27 - 30/4

Group discussion

Development works on prototype and product analysis.

Preparation of technical report.

Group discussion

Development works on prototype and product analysis.

Preparation of technical report.

W9

4 - 8/5

Group discussion

Prototype testing and product analysis.

Poster Preparation and Preparation of technical report.

Group discussion

Prototype testing and product analysis.

Poster Preparation and Preparation of technical report.

W10

11 - 15/5

Group discussion

Prototype testing, Poster Preparation and Preparation of

technical report.

Group discussion

Prototype testing, Poster Preparation and Preparation of

technical report.

W11

18 - 22/5

e-exhibition for Poster Presentation and Prototype. e-exhibition for Poster Presentation and Prototype.

W12

25 - 29/5

Aidil Fitri (24 & 25 May)

Report preparation

Aidil Fitri (24 & 25 May)

Report preparation

W13

1 - 5/6

Submission of Final Report and log book/group folder. Submission of Final Report and log book/group folder.

Page 7: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN FOR IDP & PRB

1- Students need to update his/her progress to supervisor

before 20/4/2020 via e-communication.

2- On-line poster presentation and e-exhibition could be taken

place.

Page 8: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN FOR IDP & PRB

REMARKS (as EAC latest guidelines – 30/3/2020):

1.IDP masih perlu mengambil kira elemen complex engineering problems dan rekabentuksistem, komponen ataupun proses melalui integrasi pengetahuan umum atas keperluanyang spesifik. Penilaian kerja berpasukan masih perlu dibuat termasuk complex engineering activities characteristics.

2.Skop projek dianggap selesai dengan penghasilan prototaip rekabentuk termasuksimulasi komputer dan pembentangan penyelesaian masalah rekabentuk kritikal (critical design problem solving). Untuk kali ini tidak perlu ada hard-prototype.

Page 9: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

ACTION PLAN PRB

1. Detailed design of the product (example: CAD drawing etc.) are required.

2. The design workability such as mechanical movement etc can be displayed using

simulation software.

3. Physical prototype can be added using scale down prototype, including paper model,

plastic model, or 3d print model etc.

Page 10: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

Standard Operating Procedure for using Lab/Worksyop at FKP

Page 11: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

Standard Operating Procedure for using Lab/Worksyop at FKP

Page 12: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

REMARKS

1- A new Standard Operating Procedure for using Lab/Worksyop is applied to;

a- students (UG and PG).

b- Research Assistant (RAs).

d- Lecturers.

e- Assistant Engineer (PJs).

2- All Laboratories and Worksyop can be booked thru on-line system at FKP web-site.

3- Please kindly book the lab/worksyop before you go for health screening.

Page 13: PSM 1/PSM 2 IDP/PRB - fkp.utem.edu.myfkp.utem.edu.my/phocadownload/download/Notice for... · ACTION PLAN FOR PSM 1 On-line poster presentation could be taken place. ACTION PLAN FOR

…very much for attention, cooperation and support…