PSALM justifies uncertainty in Malaya plants operations
byMyrna VelascoOctober 15, 2014As the government has been
exhausting all excuses defensible or not so it can opt for
emergency powers on the countrys power supply next year, the Power
Sector Assets and Liabilities Management Corporation (PSALM) is
adding voice to the controversy by laying down probable precarious
operation of the 650-megawatt Malaya thermal plant next year.
The technical difficulties encountered by Malaya thermal power
plant make its availability and dependability during the Malampaya
shutdown from March to June 2015 uncertain, the state-run firm
President Emmanuel R. Ledesma Jr. has noted.
PSALM has emphasized that since the last shutdown of the
Malampaya gas production facility in November-December last year,
the plants generating unit 1 already logged more than 208.07 hours
of operations and 2,301.38 hours for generating unit 2.
It can be culled though that this is the same controversial
plant that was on open breaker status at that time, meaning it has
not been synchronized to the grid when it was supposedly expected
to help ease supply tightness on those periods.
Since March this year, a Circular issued by the Department of
Energy (DOE) has specifically lined up the Malaya plant to be just
called for dispatch as must-run unit (MRU) as may be determined or
declared by system operator National Grid Corporation of the
Philippines.
PSALM justified that the Malaya plant is an aging facility,
clocking in a life span of 40 years already. It comprises of two
units with a dependable capacity of 290-MW and 340MW each.
Malaya unit 1 has been non-operational since March 21, 2014, due
to material loss of HP (high pressure) turbine rotating parts that
led to the high turbine vibration, PSALM said.
The generating units overhaul is scheduled to commence latter
part this year and is expected for completion in the next 6 to 8
months.
PSALM averred further it is very likely that, upon actual
opening of the unit by the contractor, a more extensive damage
would be discovered.
The company qualified that even if the repair of Malayas unit 1
will turn out successful, its purported 100-percent reliable
operation cannot be guaranteed, given its age, continuous and
longer dispatch at full capacity, and fuel delivery
constraints.Rappler
Burn gov't plant if not helping consumers
Osmea says the government must decide whether or not to keep the
state-owned Malaya as a security plant or close it down
Ayee Macaraig
Published 7:36 PM, Jan 23, 2014
Updated 11:57 PM, Jan 23, 2014
DYNAMITE MALAYA.' Senators criticize government agencies for
failing to use the state-owned Malaya power plant to bring down the
prices of electricity and help consumers. Photo by Albert
Calvelo/Senate PRIB
MANILA, Philippines Why dont you burn or dynamite the plant and
sell it for scrap? Youre fooling a lot of people.
Senate Energy Committee Chairman Sergio Serge Osmea III took
energy officials to task for failing to promptly use the
state-owned Malaya thermal power plant in Rizal to help bring down
the price of electricity.
At the resumption of the Senate hearing into the power rate hike
of Manila Electric Company (Meralco) on Thursday, January 23, Osmea
said the governments decision to keep the old plant without using
it during times of emergency was a conflict of policy.
He said one such emergency was the power shortage last November
to December that led to the rate hike. The scheduled shutdown of
the Malampaya gas field and unscheduled shutdowns of other power
plants forced power distributor Meralco to buy expensive power from
the Wholesale Electricity Spot Market (WESM). (READ:INFOGRAPHIC:
How WESM affects your electricity bill)
By his calculations, Osmea said that using the Malaya plant
could have significantly brought down prices in WESM by at least
P20. As a result, the burden passed on to consumers would have been
lower.
Officials of the state-run Power Sector Assets and Liabilities
Management Corporation (PSALM) explained that they did not dispatch
power from Malaya to avoid incurring additional losses. These
losses would have been passed on to consumers through the universal
charge. Malaya is under PSALM.
Osmea told them, Thats totally irrelevant. You kept the plant in
case of emergency. An emergency occurred but you did not want to
use the plant because you dont want to add charges. It doesnt make
sense to me.
Senator Francis Escudero echoed Osmea. So anong purpose, silbi
ho sa atin ng Malaya? Wala sa ngayon kasi ayaw ninyong malugi. (So
what is Malayas purpose for us? None because you dont want to incur
losses.)
This is not the first time energy officials were under fire for
failing to tap Malaya to reduce the rate hike. The issue was also
raised during theSupreme Court oral argumentsand theHouse of
Representatives probeinto the hike earlier this week.
In the Senate hearing, PSALM department manager Abelardo
Sapalaran admitted that they bid in WESM even if Malaya is unable
to supply power only to comply with the must-offer rule in the spot
market.
Sapalaran clarified that Malaya was not on maintenance shutdown
but was on economic shutdown because of the companys financial
woes.
This prompted Escudero to ask about the purpose of Malaya,
Soirrelevant, balewala? (So its irrelevant, useless?)
Energy Secretary Jericho Petilla admitted as much. I saw that
Malaya is really a headache. Theyre perennially offering [in WESM]
but they are not considered because [the players] know they wont be
dispatched.
Petilla said he is studying issuing a circular considering
Malaya as a must-run unit.
Osmea said he was not happy with the answers of the agencies on
Malaya.
The administration has to make up its mind. Is Malaya going to
be used as a security plant or not? If not, close it down. You
cannot say it will bid in WESM and then they wont run it. It will
affect the other peoples bids, Osmea said in an interview after the
hearing.
The Senate is investigating the P4.15 per kilowatt-hour (kWh)
rate hike of Meralco, the biggest power rate hike in recent
history. Meralco was set to implement the increase in 3 tranches
starting December but the Supreme Court issued atemporary
restraining order(TRO).(READ:13 things Meralco consumers should
know about the hike)
Meralco vs PSALM, finger-pointingOsmea also castigated the
PSALM, Department of Energy (DOE), Energy Regulatory Commission
(ERC), and National Grid Corporation of the Philippines (NGCP) for
disclaiming responsibility on Malaya.
PSALM President Emmanuel Ledesma said Malaya only ran from
December 2 to 10 because NGCP never informed PSALM that there was a
shortage.
In turn, NGCP officials said they issued only one alert because
data from WESM showed there was no shortage last November.
Osmea said, You made a mistake because the market reflected
there was a shortage. That was the job of NGCP to issue warnings in
advance that we will have a tight situation on such a day, yet you
issued only one alert on November 15.
Meralco and PSALM also blamed each other for contributing to the
rate hike.
Meralco general counsel Ray Espinosa said, Why is Malaya not
synchronized with the grid? It distorts the behavior of market
participants. We need to address that.
PSALMs Ledesma shot back, pointing to Meralcos instruction to
power generator Therma Mobile to bid 100 megawatts at the WESM
ceiling price of P62 per kWh. Meralco drew criticism in the House
hearing over this move.
Why did Meralco bid P62 when there was supply? In our hearing in
Congress, I remember that was discussed. How come now, I am hearing
different things?
What happens when SC decides?Senators though were more concerned
about how the government agencies and power companies will respond
to the Supreme Courts decision on the power rate hike.
Escudero and Senators Antonio Trillanes IV, Cynthia Villar and
Pia Cayetano asked about reports of possible blackouts in summer as
a result of the TRO.
Petilla said the matter was a commercial problem that Meralco
and power generators can negotiate on. I dont want to say bite the
bullet but probably they can agree about it. Its only two
months.
In case Meralco will have to impose the rate hike on consumers,
Escudero suggested that the power distributor stagger the charges
for a longer period of time to lighten the burden on consumers.
Meralco was open to the suggestion.
Osmea said the Senate cannot wrap up its investigation because
the ERC has yet to submit its report on allegations of collusion in
the rate hike.
The ERC missed its December 30 and January 15 commitments to
submit the results.
ERC Chairperson Zenaida Ducut could not respond to Osmeas
question on when it can finish the report. The House also
criticized Ducut for the delay.
Osmea asked, Are you hiding something?
Ducut responded, Were just asking for more time.
Osmea said, How much more time? Unless youre waiting for info
from the US or Antarctica, Im sure you can give me a definite date.
For goodness sake.
Ducut said, We will commit to a period of 3 months.
Osmea exclaimed, Three months? The next problem is coming in the
April [summer months]. You keep on moving it back. ASAP is not good
enough. Give me a date. Rappler.com
Related stories:
Petilla endorses Malampaya subsidy billPetilla: Tight suply till
2016 but no power failureWHO IS TO BLAME FOR MERALCOS RATE
INCREASE?
ByDucky Paredeson February 11, 2014
THERE will be rotating brown-outs in a few months -- the kind
that we had during the Cory years.
Meralco and the Philippine Independent Power Producers
Association (PIPPA) have been hinting at this in the event that the
Supreme Court completely stops Meralco from collecting the
pass-through generation charges of independent power producers
(IPPs), estimated at P18 billion.
And, even Secretary Jericho Petilla of the Department of Energy
(DOE) admits that there could really be power disruptions this
summer because we have precariously thin reserves -- total demand
for Luzon is expected to hit 10,300 MW as against an available
combined supply of 10,500 MW. Thus, any unscheduled shutdown or
tripping of even just one IPP in the Luzon Grid would likely force
DOE to order power rationing for Metro Manila customers.
When the specter of rotating blackouts first surfaced some weeks
back, Petilla was quick to dismiss it citing the assurance of
stable supply in the years ahead, claiming that the various
committed power projects meant to augment supply were on track.
But this turns out to be no more than wishful thinking, since
only two committed projects are actually ongoing, and these are the
135-MW and 300-MW coal-fired plants of the Southern Luzon Thermal
Energy Corp. (a joint venture of Trans-Asia and Ayala Corp.) and
the Southwest Luzon Power Generation Corp. (of the Consunji
Group).
The other projects mentioned by Petilla may not take off at
all.
Petilla was candid enough to admit this blackout scenario in
revealing that the tight supply situation would puts the Luzon Grid
on yellow alert this summer, which means there will be rotating
power interruptions once a major power plant bogs down.
Kapag may plantang biglang bumagsak ay talagang hindi natin
inaasahan yan. Parang kotse yan, tumatakbo, hindi natin alam kung
kailan titirik, said Petilla.
And to boost supply, Petilla said the DOE has decided to run the
state-owned Malaya Thermal Plant in April the very same idled
government facility that senators blamed for last months upsurge in
electricity prices at the
Wholesale Electricity Spot Market (WESM) during the
November-December weeks when the Malampaya gas facility and several
IPPs were on simultaneous shutdowns.
PSALMs Ledesma subsequently admitted during the same hearing,
that the Malaya plant was not activated because it would have cost
this cash-strapped government firm as much as P1.35 billion in
operational losses were it to run this facility for a month to
augment the supply available at WESM.
The Senate energy committee chairman, Sergio Osmea III,
suggested that on the basis of such official reasoning, PSALM might
as well burn or bomb the Malaya plant and sell it for scrap
iron.
***
All these things point to the likelihood of summer blackouts and
the unconscionable idling of the governments Malaya facility bring
us to this point: What convinced Communications Secretary Herminio
Coloma to go on combat mode and attack the power industry players
by announcing that electricity consumers should not be made to pay
for the unjustified rate hike.
Coloma claimed it was the belief of President Aquino that the
Electric Power Industry Reform Act (EPIRA) provision on possible
disgorgement of profits must be enforced on industry players once
the DOE and Department of Justice (DOJ) find proof of collusion
among them, and that the rate increase was unjustified because it
was triggered by a foreseeable event for which these same players
could have prepared.
Clearly, Coloma was blaming the private sector for a mess that
was mostly the governments own makinga botched job that is likely
to get worse in the months and years ahead before it gets any
better.
It was the DOEs role to make sure that power plant maintenance
shutdowns coinciding with the Malampaya gas shutdown were
rescheduled to avoid a wide supply gap that would drive up
electricity prices.
Indeed, during the hearings at the Senate and at the House of
Representatives as well, Secretary Petilla declared that he had
called for several meetings to address the situation. In both
congressional probes, Petilla even asserted that he had instructed
officials of the Malaya plant to make necessary preparations to run
it for 15 days, but, curiously he stopped short of explaining why
Malaya had not been used during the shutdown period.
What Colomas finger-pointing suggests is that he is merely
covering up the failure of the DOE by blaming industry players for
Decembers steep rate hike.
It became very clear during the congressional hearings that had
the Malaya thermal plant, which has an available capacity of 610
MW, been operated, the spike in the WESM prices would have been
completely avoided.
In fact, a Meralco study presented during the Senate hearing
bared that had Malaya been dispatched during the Nov. 11-Dec. 10
shutdown period, WESM prices would have fallen by as much as 70%
from P21/kWh to just P5.
It has also become very clear, based on admissions by PSALMs
Ledesma that Malaya was in flagrant violation of the WESM
must-offer ruleand these violations were tolerated by the
Philippine Electricity Market Corp. (PEMC), which operates
WESM.
Remember that the Malaya thermal plant is a government- owned
and -controlled power plant under PSALM, of which Petilla is vice
chairman. Petilla also chairs PEMC.
So if Petilla was doing his job during the shutdown period, he
could have avertedas it was his duty to do sothe unusual spike in
WESM prices.
Yet Petilla did nothing. He has not even taken the PSALM
management to task for violating WESM rules in idling the facility
and for not complying with his instructions to operate and dispatch
Malaya.
As the market operator of WESM, the Petilla-chaired PEMC
actually had the first opportunity to notice and address the
unusually high prices obtaining at WESM. Yet it did not act.
In fact, PEMCI even cleared an offer price of P62 just to
satisfy a measly 0.5 MW demand. Why?
All told, Secretary Petilla could have made a big difference in
ensuring lower WESM prices. But he failed big-time.
***
But, where is Coloma coming from? Does he think that part of his
job as Palace communications secretary is to cover for the failings
of his Cabinet peers?
The Supreme Court reacted to Colomas blaming the judiciary for
the unbridled rice smuggling when he called for closer coordination
or teamwork among all agencies involved; he also asked the courts
to act faster on pending smuggling cases to complement the
Administrations drive against smugglers.
SC spokesman Theodore Te wrote: I am sure Secretary Coloma knows
the judiciary cannot act on cases that are not brought before it
and convictions cannot be secured unless the burden of proof
imposed by the Constitution is discharged by the (DOJ), which falls
under the executive and not the judicial department.
Te said the zero conviction rates in the 157 rice smuggling
cases over the past three years has to do not only with how fast
the courts resolve cases but also with the quality of the evidence
that prosecutors presented in support of their cases.
Te also said that that the secretary should know that, The
courts are not expected to have closer coordination or teamwork
with the prosecutorial arm as, on the contrary, they are expected
to be independent and, on many occasions, play the spoilers
role.
***
Readers who missed a column can
accesswww.duckyparedes.com/blogs. This is updated daily. Your
reactions are welcome [email protected] you can send me a
message through Twitter@diretsahan.
Category:
Column Of The Day- See more at:
http://www.malaya.com.ph/business-news/opinion/who-blame-meralco%E2%80%99s-rate-increase#sthash.eTgvl1As.dpufFriday,
January 24. 2014
DOE chief asked to terminate 600mw Malaya power plant
Written by Jelly F. Musico
Posted online by Jigs Nepomuceno in National News at 00:00
MANILA The Power Sector Assets and Liabilities Management Corp
(PSALM) has asked Department Energy (DOE) Secretary Carlos Jericho
Petilla to terminate the operation of the government-owned
600-megawatt Malaya thermal power plant.
Actually, when I came in I saw this Malaya is creating headache
because they are offering but would not really dispatch and they
(PSALM) requested as early as middle of last year to retire them,
Petilla told the Senate inquiry on power rate hike and bills
reviewing EPIRA (Electric Power Industry Reform Act) of 2001.
They really want to get rid of this plant because this plant is
cheaper to be burned than to actually operate in a sense, the DOF
chief added.
During the hearing, the senators learned that Malaya complied
with a must offer rule when it bidded at P45 but actually did not
dispatch power specially when Malampaya went on 30-day maintenance
shutdown late last year.
You participated in the bidding but you did not dispatch because
youre not synchronized with the national grid. So you're fooling a
lot of people, youre fooling me and youre fooling secretary, Sen.
Sergio Osmena III, chair of the Senate committee on energy, told
the PSALM officials.
PSALM department manager Abelardo Sapalaran explained that
Malaya plant has been complying with must offer rule of the
Wholesale Electricity Spot Market (WESM) but without dispatching
power for the last two years.
Actually, were losing since 2006 and we were penalized already.
The purpose of submitting bid offer is to comply with WESM rules
must-offer, Sapalaran said.
Rey Espinosa, legal counsel of MERALCO, admitted that they
offered at P62 but due to Malayas failure to dispatch, the price
hit at P62 per kilowatt hour.
If only Malaya dispatched when it offered P45, the price could
not have hit P62 because we bid at P62 so that it will not be
dispatched, Espinosa explained.
Sapalaran told the Senate panel that it takes 14 to 16 hours to
open the Malaya plant and synchronize it with NGCP.
PSALM president Emmanuel Ledesma said they did not run Malaya
when Malampaya and other power plants went to maintenance shutdown
because there was sufficient supply.
So why did we not run Malaya, personally in my understanding, is
the supply sufficient, I concluded that because NGCP (National Grid
Corporation of the Philippines) never mentioned anything to us that
there was insufficient supply, Ledesma said.
Osmena, however, believed that non-operation of Malaya has led
to the increase of prices of power.
If only Malaya dispatched at least 300mw, the prices in the WESM
could have been gone down from P62 to P12, Osmena said in media
interview after the five-hour hearing.
Osmena said the problem is PSALM tries to save money because
they admitted that running Malaya will incur for PSALM a loss of
P2.2 billion a year.
I think they have to make their mind if Malaya is going to be
used as security plan or not because if not, then close it down,
Osmena said.
Senator Cynthia Villar said she was surprised to learn that
Malaya plant cannot be used in times of emergency.
I was so surprise that there was a chance for them to help and
they did not sell their power, Villar said.
Senator Francis Chiz Escudero questioned the PSALMs action to
comply with WESMs must offer rule without dispatching power even in
time of emergency.
So whats the purpose? Why did you offer bid and would not
dispatch power? Thats irrelevant, Escudero said.
Petilla said time has not yet come for the 600mw Malaya to be
shut down despite claim by PSALM that it is no longer earning
money.
That time is not now, so do not mothball that plant at this
time. Im quite sure that there is a balance that we can do right
now, Petilla said. (PNA)
CTB/JFM
- See more at:
http://www.zambotimes.com/archives/news/84316-DOE-chief-asked-to-terminate-600mw-Malaya-power-plant.html#sthash.NuRuxwjj.dpufWHO
IS TO BLAME FOR MERALCOS RATE INCREASE?
ByDucky Paredeson February 11, 2014
THERE will be rotating brown-outs in a few months -- the kind
that we had during the Cory years.
Meralco and the Philippine Independent Power Producers
Association (PIPPA) have been hinting at this in the event that the
Supreme Court completely stops Meralco from collecting the
pass-through generation charges of independent power producers
(IPPs), estimated at P18 billion.
And, even Secretary Jericho Petilla of the Department of Energy
(DOE) admits that there could really be power disruptions this
summer because we have precariously thin reserves -- total demand
for Luzon is expected to hit 10,300 MW as against an available
combined supply of 10,500 MW. Thus, any unscheduled shutdown or
tripping of even just one IPP in the Luzon Grid would likely force
DOE to order power rationing for Metro Manila customers.
When the specter of rotating blackouts first surfaced some weeks
back, Petilla was quick to dismiss it citing the assurance of
stable supply in the years ahead, claiming that the various
committed power projects meant to augment supply were on track.
But this turns out to be no more than wishful thinking, since
only two committed projects are actually ongoing, and these are the
135-MW and 300-MW coal-fired plants of the Southern Luzon Thermal
Energy Corp. (a joint venture of Trans-Asia and Ayala Corp.) and
the Southwest Luzon Power Generation Corp. (of the Consunji
Group).
The other projects mentioned by Petilla may not take off at
all.
Petilla was candid enough to admit this blackout scenario in
revealing that the tight supply situation would puts the Luzon Grid
on yellow alert this summer, which means there will be rotating
power interruptions once a major power plant bogs down.
Kapag may plantang biglang bumagsak ay talagang hindi natin
inaasahan yan. Parang kotse yan, tumatakbo, hindi natin alam kung
kailan titirik, said Petilla.
And to boost supply, Petilla said the DOE has decided to run the
state-owned Malaya Thermal Plant in April the very same idled
government facility that senators blamed for last months upsurge in
electricity prices at the
Wholesale Electricity Spot Market (WESM) during the
November-December weeks when the Malampaya gas facility and several
IPPs were on simultaneous shutdowns.
PSALMs Ledesma subsequently admitted during the same hearing,
that the Malaya plant was not activated because it would have cost
this cash-strapped government firm as much as P1.35 billion in
operational losses were it to run this facility for a month to
augment the supply available at WESM.
The Senate energy committee chairman, Sergio Osmea III,
suggested that on the basis of such official reasoning, PSALM might
as well burn or bomb the Malaya plant and sell it for scrap
iron.
***
All these things point to the likelihood of summer blackouts and
the unconscionable idling of the governments Malaya facility bring
us to this point: What convinced Communications Secretary Herminio
Coloma to go on combat mode and attack the power industry players
by announcing that electricity consumers should not be made to pay
for the unjustified rate hike.
Coloma claimed it was the belief of President Aquino that the
Electric Power Industry Reform Act (EPIRA) provision on possible
disgorgement of profits must be enforced on industry players once
the DOE and Department of Justice (DOJ) find proof of collusion
among them, and that the rate increase was unjustified because it
was triggered by a foreseeable event for which these same players
could have prepared.
Clearly, Coloma was blaming the private sector for a mess that
was mostly the governments own makinga botched job that is likely
to get worse in the months and years ahead before it gets any
better.
It was the DOEs role to make sure that power plant maintenance
shutdowns coinciding with the Malampaya gas shutdown were
rescheduled to avoid a wide supply gap that would drive up
electricity prices.
Indeed, during the hearings at the Senate and at the House of
Representatives as well, Secretary Petilla declared that he had
called for several meetings to address the situation. In both
congressional probes, Petilla even asserted that he had instructed
officials of the Malaya plant to make necessary preparations to run
it for 15 days, but, curiously he stopped short of explaining why
Malaya had not been used during the shutdown period.
What Colomas finger-pointing suggests is that he is merely
covering up the failure of the DOE by blaming industry players for
Decembers steep rate hike.
It became very clear during the congressional hearings that had
the Malaya thermal plant, which has an available capacity of 610
MW, been operated, the spike in the WESM prices would have been
completely avoided.
In fact, a Meralco study presented during the Senate hearing
bared that had Malaya been dispatched during the Nov. 11-Dec. 10
shutdown period, WESM prices would have fallen by as much as 70%
from P21/kWh to just P5.
It has also become very clear, based on admissions by PSALMs
Ledesma that Malaya was in flagrant violation of the WESM
must-offer ruleand these violations were tolerated by the
Philippine Electricity Market Corp. (PEMC), which operates
WESM.
Remember that the Malaya thermal plant is a government- owned
and -controlled power plant under PSALM, of which Petilla is vice
chairman. Petilla also chairs PEMC.
So if Petilla was doing his job during the shutdown period, he
could have avertedas it was his duty to do sothe unusual spike in
WESM prices.
Yet Petilla did nothing. He has not even taken the PSALM
management to task for violating WESM rules in idling the facility
and for not complying with his instructions to operate and dispatch
Malaya.
As the market operator of WESM, the Petilla-chaired PEMC
actually had the first opportunity to notice and address the
unusually high prices obtaining at WESM. Yet it did not act.
In fact, PEMCI even cleared an offer price of P62 just to
satisfy a measly 0.5 MW demand. Why?
All told, Secretary Petilla could have made a big difference in
ensuring lower WESM prices. But he failed big-time.
***
But, where is Coloma coming from? Does he think that part of his
job as Palace communications secretary is to cover for the failings
of his Cabinet peers?
The Supreme Court reacted to Colomas blaming the judiciary for
the unbridled rice smuggling when he called for closer coordination
or teamwork among all agencies involved; he also asked the courts
to act faster on pending smuggling cases to complement the
Administrations drive against smugglers.
SC spokesman Theodore Te wrote: I am sure Secretary Coloma knows
the judiciary cannot act on cases that are not brought before it
and convictions cannot be secured unless the burden of proof
imposed by the Constitution is discharged by the (DOJ), which falls
under the executive and not the judicial department.
Te said the zero conviction rates in the 157 rice smuggling
cases over the past three years has to do not only with how fast
the courts resolve cases but also with the quality of the evidence
that prosecutors presented in support of their cases.
Te also said that that the secretary should know that, The
courts are not expected to have closer coordination or teamwork
with the prosecutorial arm as, on the contrary, they are expected
to be independent and, on many occasions, play the spoilers
role.
***
Readers who missed a column can
accesswww.duckyparedes.com/blogs. This is updated daily. Your
reactions are welcome [email protected] you can send me a
message through Twitter@diretsahan.
Category:
Column Of The Day- See more at:
http://www.malaya.com.ph/business-news/opinion/who-blame-meralco%E2%80%99s-rate-increase#sthash.eTgvl1As.dpufPSALM:
Malaya plant can't always run when needed
PSALM says the plant has slow start-up time and low fuel
replenishment rate
Rappler.com
Published 6:58 PM, Feb 12, 2014
Updated 7:00 PM, Feb 12, 2014
NO DISPATCH? PSALM reportedly avoided as much as P1 billion in
losses by keeping the Malaya plant offline during the Malampaya
shutdown. File Photo from AFP.
MANILA, Philippines The Power Sector Assets and Liabilities
Management Corporation (PSALM) said Wednesday, February 12 that it
should not be blamed for not dispatching the Malaya thermal power
plants energy loadwhen people needed it last year.
Emmanuel Ledesma, president of PSALM, said the power plants slow
start-up time and its low fuel replenishment rate were to blame for
their non-compliance to the must-offer rule of the Wholesale
Electricity Spot Market (WESM).
Ledesma added, "the technical limitations of Malaya make it a
sheer impossibility for Malaya to be always traded through the WESM
bidding process."
He explained further that, if the Malaya plant traded its power
at the WESM at its full, 650-megawatt (MW) capacity for 28 days, it
would take 3 months of non-operation to run again.
The power plant recently earned an exemption from WESM's
must-offer rule and instead became a must-run unit.
A must-run unit must provide needed power supply on real-time
basis or on a particular schedule deemed necessary by WESM system
operator National Grid Corporation of the Philippines (NGCP) to
ensure reliability of power supply in the grid, especially when
there's a shortfall.
The must-offer rule requires all generation companies registered
in WESM to declare and offer their maximum generating capacities to
prevent capacity withholding.
Energy Secretary Carlos Jericho Petilla said PSALMs decision not
to dispatch Malayas energy load despite bidding in the WESM
constituted a violation of WESM rules.
Petilla said Malaya was on an open breaker" status, meaning the
plant actually made an offer but didnt dispatch energy when
asked.
Ledesma countered, saying PSALMs open breaker status has since
started in August 2012, clarifiying that the illegality of this has
yet to be established in accordance with due process in the proper
forum.
PSALM explained to the Philippine Electricity Market Corporation
(PEMC) Market Surveillance Committee in June 2013 the technical and
financial reasons behind its decision to not trade Malaya in the
WESM, in response to the PEMC MSCs May 2013 letter. PEMC is the
spot market operator.
In the letter, PEMC asked PSALM to clarify Malayas status as an
open breaker plant when not run by the NGCP as a must-run unit.
Ledesma said the PEMC has, to date, not yet responded to PSALMs
letter.
Prior to the letter, PSALM emphasized that the Energy Regulatory
Commission (ERC) rather than the PEMC has the original and
exclusive jurisdiction over all cases regarding disputes between or
among members of the energy sector.
The ERC also holds jurisdiction over contesting fees, fines,
penalties, and rates.
Ledesma added that PSALM has brought this jurisdictional issue
to the Supreme Court in relation to a different case."
The ERC has requested an explanation from PSALM regarding the
open breaker status issue in January. Rappler.comPSALM approves
rehab of Malaya plant
The rehabilitation of the Malaya Unit 1 will help plug the
anticipated power supply deficiency next year
Rappler.com
Published 8:43 AM, Aug 20, 2014
Updated 8:43 AM, Aug 20, 2014
IN AID OF POWER SUPPLY. The rehabilitation of the Malaya Unit 1
will help plug the supply deficiency that is anticipated next year.
File photo by Agence France-Presse
MANILA, Philippines The Power Sector Assets and Liabilities
Management Corporation (PSALM) board has approved the
rehabilitation of Unit 1 of the Malaya Thermal Power Plant in
Rizal, the state firms president said.
The board has approved the overhauling of Malaya 1. Procurement
for the service will be handled by the Bids and Awards Committee
(BAC), said PSALM President Emmanuel Ledesma Jr. in a text message
Tuesday, August 19.
The bid schedule has yet to be finalized but industry
stakeholders are calling for the speedy rehab of the power facility
before theLuzon grid runs out of power supplyin the summer months
of 2015.
TheManila Electric Company (Meralco), for one, strongly urged
PSALM to fast-track the rehabilitation of Unit 1 so that theentire
Malaya facilitycan run at its full capacity of 650 megawatts
(MW).
PSALM and the Department of Energy (DOE) also want the
rehabilitation done before March next year.
DOE Secretary Carlos Jericho Petilla, who sits as vice chairman
of the PSALM board, said the board has been continuously meeting on
how to fast-track the rehab work.
Technically, the DOE is only one seat in the board. Any decision
will have to involve the board, he said in a separate text
message.
The PSALM board is headed by finance secretary Cesar
Purisima.
In aid of power supplyThe power facility consists of a 300-MW
unit with a once-through type boiler and a 350-MW unit fitted with
a conventional boiler. It was rehabilitated in 1995 by the Korea
Electric Power Corporation (KEPCo) under a 15-year
rehabilitate-operate-manage-maintain agreement.
According to Petilla, KEPCo has informed the agency that Unit 1
of Malaya needs to be overhauled. KEPCO is among those interested
to undertake the rehab, Petilla said.
The DOE and PSALM said the rehabilitation of the Malaya Unit 1
would help plug the supply deficiency that is anticipated next
year. (READ:Power emergency: What it means)
Ideally, Ledesma had said, the rehab of the Malaya Unit 1 should
be finished before the scheduled shutdown of the Malampaya natural
gas pipeline next year.
TheMalampaya facility will go offlinefrom March 15 to April 14,
2015 to commence Phase 3 of the installation of a platform aimed at
maintaining fuel supply to power plants providing half of Luzons
power needs.
The shutdown of the Malampaya facility, which, according to
consortium members could no longer be rescheduled, worries the DOE
and PSALM because the capacity of Malaya is crucial to the power
requirements of Luzon.
Based on DOE projections, there will be a deficit of 200 MW next
year. Energy supply will be thin by March to May 2015, the months
with the highest electricity demand for the year. To address this,
Petilla said an additional 400 MW-500 MW capacity would be needed
to act as buffer supply during the peak months. (READ:Solving the
energy crisis by empowering the people) Rappler.comFor power crisis
stories, readhere.
For related state of emergency for power crisis stories,
readhere.
Carousel image fromWikipediaPower consumers to carry burden of
P62B in settlement claims vs. PSALM?
ByDANESSA O. RIVERA, GMA NewsAugust 26, 2014 7:36pm
More from:
http://www.gmanetwork.com/news/story/376495/economy/companies/power-consumers-to-carry-burden-of-p62b-in-settlement-claims-vs-psalmConsumers
may have to carry the burden of over P60 billion in settlement
claims by disgruntled former employees of the Power Sector Assets
and Liabilities Management Corporation (PSALM) to avoid aggravating
the looming power crisis in 2015, the Energy secretary said.
Apart from having its assets garnished, a possible option is for
PSALM to get at loan to cover the settlement claims so as not to
hamper its operations, Energy Secretary Carlos Jericho Petilla told
reporters on the sidelines of the Management Association of the
Philippines (MAP) General Membership Meeting in Makati City
Tuesday.
"DOE's biggest concern is still power. The DAMA's case, whatever
liability NPC has, is part of the NPC debt," he said.
"The P62 billion, kung makakautang s'ya para hindi maapektuhan
ang operation, i-cha-charge sa tao. How much, I don't know," he
said.
Over the weekend, PSALM said it received a court order from the
Regional Trial Court (RTC)-Quezon City (QC) garnishing its funds
worth over P60 billion.
The RTC QC ordered PSALM to immediately pay P60.24 billion to
over 8,000 beneficiaries of Napocor-Drivers and Mechanics
Association (DAMA) and P1.81 billion for "lawful fees and costs for
the execution of the Supreme Court's Resolution."
The Napocor-DAMA were employees terminated by PSALM when it was
restructured in 2003 pursuant to the Electric Power Industry Reform
Act (EPIRA).
Notice of garnishment
The notice of garnishment are legally baseless and violate due
process, PSALM president and CEO Emmanuel R. Ledesma said in a
statement posted on its website Monday.
"If our funds are garnished, our long-term debts would become
immediately due and demandable... This will result in operating
cash deficit, which will lead to power shortage nationwide," he
noted.
PSALM is responsible for the fuel supply and operations budget
of state-owned power plants, namely the Malaya Thermal Power Plant
in Luzon, Power Barges (PBs) 101 and 102 and Naga Coal-fired
Thermal Power Plant in Visayas, and PB 104 in Mindanao. These
facilities produce a combined total of 430 megawatts (MW)
dependable capacity.
PSALM also provides for the fuel requirements of Independent
Power Producer (IPP) plants, namely the Ilijan Natural Gas Power
Plant in Luzon, the Zamboanga Diesel Power Plant and the General
Santos Diesel Power Plant in Mindanao.
The agency also collects and administers the Universal Charge
for Missionary Electrification, which is the source of funds of the
National Power Corporation (NPC) off-grid operations.
There's still hope as the PSALM board filed a motion for
reconsideration before the Supreme Court last Friday, Petilla
said.
"[We'll have to] wait for SC... At the expense na puwede kami
ma-contempt. Kapag sumangayon kami, baka tumigil ang planta," he
said.
"Pero ang nakikita ko lang dito na way out [ay] dagdagan ang
utang. Kung hindi magbabago si SC or i-re-reconsider ng SC na baka
mas mababa sa P62 billion, dahil malaking pabigat 'yun sa PSALM,"
he noted.
Petilla said the biggest threat to the power situation is coming
from the people who will garnish PSALM's funds.
"The interest of the public, I think, is more than the interest
of employees. I respect that they also have the rights but, in this
country, there's no absolute right. It's always what is good for
the general public," he said.
Presidential powers
During the MAP forum, Petilla reiterated the need to invoke the
Section 71 of EPIRA that gives the President the power to address
the shortage by contracting new power plants or renting modular
generators.
Last July 21, Energy Secretary Jericho Petilla saidhe
recommended that the President declare a state of national
emergency on powerto avoid rotating brownouts in Luzon due to a
power supply shortage of between 300 to 500 megawatts (MW) starting
next year.
With seven months remaining before the summer of 2015, the
government still has time to contract new power to avert an energy
crisis.
"I will take the cue of the President and those that want this
or who don't want this," he said.
Business groups urged the governmentnot to amend the EPIRA but
to implement it properlyand focus instead on implementing the law
properly.
MAP recently saidgovernment should aggressively push the demand
side to undertake energy efficiency measures, urgently implement a
voluntary Interruptible Load Program and lift the secondary price
cap in the Wholesale Electricity Spot Market.VS, GMA News
More from:
http://www.gmanetwork.com/news/story/376495/economy/companies/power-consumers-to-carry-burden-of-p62b-in-settlement-claims-vs-psalm.