PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines 1 MSK-CPECC PCH 4/28/2018 www.msk-group.org
PROVISION OF EPCC FOR FSF AROUND CPF3
HFY-CON/F&CO872-0896-01
Construction of Flow lines and Trunk lines
1
MSK-CPECC PCH
4/28/2018
www.msk-group.org
4/28/2018MSK-CPECC-PCH-CONTRACT 2
34/28/2018
1.Introduction
PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow
lines and Trunk lines Project (the “Project”) and Related System Project is carried out by JV (CPECC
&MSK )as EPC contractor for PetroChina International Iraq FZE according to letter of award dated on 31
Dec 2017. The project in handled in Halfaya Oil Field located 35 km southeast of Amarah city, Missan
Governorate, southern part of the Republic of Iraq. CPECC& MSK activities are performed based on
signed service agreement with PetroChina for the period of four years until 2021.
Project Location; The Halfaya Oil Field is situated in the Missan governorate of Iraq, 35 km southeast of
Amarah city
Client; PetroChina International Iraq FZE Iraq Branch
Contractor; CPECC& MSK
Project name; PROVISION OF EPCC FOR FSF AROUND CPF3 Construction of Flow lines and Trunk
lines
Project number; PRID-3690 HFY-CON/F&CO872-0896-01
Service order number; SO01
Project Activities;
A. Engineering
B. Procurement
C. Construction
D. Testing
E. Commissioning
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
44/28/2018
1.1 HFY OIL FIELD MAP
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
4/28/2018 5
1.2 Reference
a) PCH and HALFAYA oilfield specifications and
requirements
b) Design Bases
c) 0896 ITB Final PDF files
d) The Project documents
e) Overall Layout
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
64/28/2018
2.1 SCOPE OF WORK FOR (SO01)
a) The flowlines shall be of carbon steel API 5L-PSL2- BNS/X52NS
b) The flowline shall be buried together in common trench where they have the same
route, the minimum cover of pipeline is 1200 mm (top of pipe)
c) The estimated lengths of the flowlines will base on Location Plan of the respective
well at the relevant Site
2.Understanding the Scope of Work for the project.
The Scope of work to be performed be Contractor is only for ENGINEERING AND
CONSTRUCTION OF FLOWLINES AND TRUNKLINES for This project consist of the followings
as per section 4.0 from contract:
1. Flow lines and trunk lines
2. Civil works
3. Anticorrosion protection.
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
2.2 Scope & Quantities;
No. Description Details Unit Quantity
1 Pipeline 6" with 3PE/3PP/FBE Coating m 39300
8" with 3PE/3PP/FBE Coating m 24600
2 Road Crossing (Excavation method) 6" pipeline road crossing m 116
8" pipeline road crossing m 119
4 Road Crossing (Reserved Culvert) 6" pipeline road crossing m 80
8" pipeline road crossing m 128
5 River/Channel Crossing (with excavation) 6" Pipeline River/Channel Crossing m 107
8" Pipeline River/Channel Crossing m 66
7 Underground pipeline/cable crossing Pipeline crossing each 59
Cable crossing each 26
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
84/28/2018
2.3 Overall Layout
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
94/28/2018
4. Project Organization Chart
4.1 Project Management Organization
MSK-PRID-3680-Project Manager
Construction Manager
HSE Manager
QC Manager
Commissioning Supervisor
Planner Engineering Coordinator
Inspection Supervisor
Document Control Center (DCC)
Security Supervisor
Accountent
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
104/28/2018
4. Project Organization Chart
4.2 Project Construction ORG.Chart Construction Manager
Civil EngineerPiping
Engineer
Instruent Engineer
Quality Engineer
Testing Supervisor
Workshop Supervisor
Equipment Supervisor
Surveyors
HSE Supervisor
Coating Supervisor
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
114/28/2018
4. Project Organization Chart
4.3 Project QA/QC ORG.Chart
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
124/28/2018
5-Project Millstones.
Service Order effective date:Mar 20th 2018
Mobilization: 01-May-18
Construction-6’’ Pipeline & 8’’ Pipeline: 12-May-18
Commissioning and Demobilization: 27-Sep-18
Project Milstones.(Start Date)
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
134/28/2018
6. Construction Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
144/28/2018Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
6. Construction Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
154/28/2018Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
6. Construction Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
164/28/2018
6. Construction Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
174/28/2018Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
6. Construction Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
184/28/2018
7. Site Mobilization Plan (Man Power, Tools & Tackles, Camp, Machinery etc.)
7. 4 Man Power Schedule
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
#Project Months
1 2 3 4 5 6 7 8 9 10
A Indirect Manpower
A1 Project Manager 1 1 1 1 1 1 1
A2 Construction Manager 1 1 1 1 1 1 1
A3 HSSE Manager 1 1 1 1 1 1 1
A4 QA/QC Manager 1 1 1 1 1 1 1
A5 Engineering Manager 1 1 1 1 1 1 1
A6 Pipline Engineer 1 1 1 1 1 1 1
A7 Civil Engineer 1 1 1 1 1 1 1
A8 Document Controller 1 1 1 1 1 1 1
B Direct Manpower
B1 Construction Supervisor 0 1 1 1 1 1 1
B2 QA/QC Supervisor 0 1 1 1 1 1 1
B3 HSSE Supervisor 0 1 2 2 2 2 1
B4 Surveyor 0 2 2 1 1 1 0
B5 Surveyor Helper 0 2 3 5 5 3 2
B6 Welder 0 5 16 22 22 15 4
B7 Hydrotesting Foreman 0 0 0 1 3 3 2
B8 Strore Keeper 0 2 3 4 4 2 1
B9 NDT Supervisor 0 0 2 2 2 2 1
B10 NDT Technician 0 0 4 4 4 4 2
B11 Coating Supervisor 0 0 0 1 2 2 1
B12 Coating Techniian 0 0 0 2 4 6 3
B13 Skilled Labour 0 15 48 66 66 45 12
B14 Unskilled Labour 0 22 72 99 99 66 18
B15 Equpments operatot 4 8 16 16 16 12 6
B16 Driver 6 10 18 20 20 12 8
204/28/2018
7. Site Mobilization Plan (Man Power, Tools & Tackles, Camp, Machinery etc.)
7. 5 Equipment Schedule
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
C Equipment
C1 Crane 20 ton 0 2 3 3 2 2 1
C2 Welding machine 5 10 22 22 22 20 10
C3 Sidboom 0 6 7 7 7 6 2
C4 Boring machine 0 1 1 1 1 1 0
C5 HDD machine 0 1 1 1 1 0 0
C6 NDT equipment 0 2 2 3 3 2 2
C7 Surveying equipment 0 6 6 6 6 6 0
C8 Power generator 4 4 4 4 4 4 4
C9 Hydrotesting equipment 0 0 3 3 3 3 3
C10 Air compressor 0 1 2 2 3 3 1
C11 Welding rods oven 0 20 20 20 20 20 20
C12 12 seat bus 2 4 8 8 8 8 2
C13 Pick-up 4 5 6 6 6 5 4
#Project Months
1 2 3 4 5 6 7 8 9 10
224/28/2018
7. Site Mobilization Plan (Man Power, Tools & Tackles, Camp, Machinery etc.)
7. 6 HISTOGRAM
0
50
100
150
200
250
300
1 2 3 4 5 6 7 8 9 10
Project Week
Chart Title
Indirect Manpower Direct Manpower Equipment
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
234/28/2018
8. Project Execution activities
8.1. TOPOGRAPHIC SURVEY
8.2 PROCUREMENT
8.3 CONSTRUCTION
8.4 COMMISIONING
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
244/28/2018
8. Project Execution activities
8.4.1 TYPICAL DRAWING FOR PIPELINES CROSSING
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
25
264/28/2018
8. Project Execution activities
8.4.2 A Typical Drawing Right of Way and Working Strip Dimensions
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
27
284/28/2018
9.Project Control System
The elements of project control system shall include:
• Work Breakdown Structure (WBS) for the project
• Project Execution Schedule
• Progress Measurement/Monitoring System
• Progress ‘S’ Curve
• Manpower Histograms
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
294/28/2018
12. HSE Requirements
It is contractor’s sole responsibility to apply for Permit To Work for all operation of
the Contract
It is mandatory for contractor to provide full Personnel Protective Equipment to its
members involved in Work.
The qualified HSE supervisor capable of fluent spoken English and with similar
working experience shall be available for each working site.
It is contractor’s obligation and duty to keep a good housekeeping by segregating
and collecting waste when the operation is over.
It is contractor’s sole responsibility to get its members and vehicles issued valid
security clearance and driving pass by corresponding authorization prior to the
commencement of Contract.
The indispensable HSE signs and warning tape should be in position, as well as first
aider kit.Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
304/28/2018
12. HSE Requirements
Some critical equipment, such as cranes, shall be issued certificate by third party
authorization.
Smoking area should be appointed by contractor in working site.
No Sub-Contractor is allowed or permitted to inform or submit a report to PCH or
MOC directly without MSK authorization.
Toolbox talk is mandatory for contractor prior to commencement of daily operation.
Contractor’s members are physically and mentally fit for a variety of operations of the
Project, and with qualified certifications if necessary.
It is mandatory for Contractor to abide by the HSE procedures and regulations.
Contractor is requested to implement color-coding system for cranes, lifting tacks,
hand portable tools, equipment and so on.
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
314/28/2018
11. QAQC Requirements
At all time, QC inspector must supervise on site during construction. At the same time the
measure device should be available on site. All measure device used in this project must be
calibrated by authorized organization, including pressure recorder, Pressure gauge, holiday
tester; infrared thermometer, hardness tester, PWHT machine, and so on.
Prepare the construction record and get signature from PMC at the same time when
finishing the work;
personnel allocation:
Full-time welding inspector: CSWIP certificate.
Full-time Anti-corrosion engineer: NACE certificate.
Full-time document controller.
PQR+WPS is approved by PMC.
All the measure equipment must be qualification with calibration certificate.
Sub-contractor must submit the quality organization chart and contact information.
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
324/28/2018
11. QAQC Requirements
Marks of welding joints information including:
root welding, welder ID and date;
cap welding, welder ID and date; .
RT and date;
UT and date;
PWHT and date;
HSS and date.
Qualification of welder and coating operator;
All welder with qualification ID CARD examined by PMC can perform the welding work;
Certificate of Welding electrode.
The welding work starts after welding material is approved by PMC. The brand and type
shall be same with PQR.
The number of joint must be continuous.
ITB: Every welding joint location and elevation should be surveyed before backfilling.
The welding log/ history shall be updated and emailed to PCH every Saturday morning.
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
334/28/2018
11. QAQC Requirements
11.1 ITPs execution
CONTRACTOR will conduct inspections as per quality control requirements included in the construction procedures
and method of statements. The latter will describe as well fabrication and construction processes and key parameters
affecting quality as specified in applicable standards.
ITPs will cover as minimum the following:
- Excavation and trenching,
- Pipeline Erection and welding,
- Piping inspection and NDT,
- Hydro-testing for piping and equipment,
- Pipeline Tie-in,
- Pipeline Joint painting And coating,
- Cathode protection .
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines
344/28/2018
Thank You for Your
Attention
Project Title :PROVISION OF EPCC FOR FSF AROUND CPF3 HFY-CON/F&CO872-0896-01 Construction of Flow lines and Trunk lines