Page 1: Project Weekly Status Update 9/10/2021

Marsh Drive Bridge at Walnut Creek Replacement Project

1451 River Park Dr. Suite 220 Sacramento CA 95815 I [email protected]

Page 1 of 2

Project Weekly Status Update

9/10/2021

Figure 1 – Weekly Look-ahead Schedule

Figure 2 – Pier 2 Bent Cap Abutment 1

Page 2: Project Weekly Status Update 9/10/2021

Marsh Drive Bridge at Walnut Creek Replacement Project

1451 River Park Dr. Suite 220 Sacramento CA 95815 I [email protected]

Page 2 of 2

Figure 3 – Pier 2 Bent Cap - Falsework

Figure 4 – Abutment 6