Project Update Project Update Goat Island Park Ph. 2 Goat Island Park Ph. 2 Town of Cramerton Town of Cramerton December 19 th , 201
9

Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Dec 18, 2015

Download

Documents

Lester Watson
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Project UpdateProject UpdateGoat Island Park Ph. 2Goat Island Park Ph. 2

Town of CramertonTown of Cramerton

December 19th, 2013

Page 2: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Overall Master Plan – Phase 2

Page 3: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Master Plan – Phase 2Phase 2-Amenities Pedestrian Bridge(3) Cornhole Boards(2) Table TennisDog ParkPlaygroundObservation Platform

Phase 2-Amenities Pedestrian Bridge(3) Cornhole Boards(2) Table TennisDog ParkPlaygroundObservation Platform

Page 4: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Bridge Design

Bridge Approach80’ span

Capstone Style Prefabricated Bridge165’ Center Span, Painted Black with Decorative Lighting

Capstone Style Prefabricated Bridge165’ Center Span, Painted Black with Decorative Lighting

Bridge Approach120’ spanPrefabricated Bridge

165’ span

Page 5: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Bridge Approach Detail

Page 6: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Permitting

FERC PERMIT:

US ARMY CORP OF ENGINEERS(USACOE) PERMIT (404):

NCDENR DIVISION OF WATER RESOURCES, WATER QUALITY PERMITTING (401):

NCDENR DIVISION OF ENERGY MINERAL AND LAND RESOURCES, LAND QUALITY SECTION, EROSION AND

SEDIMENT CONTROL

COAST GUARD PERMIT

“NO-RISE” CERTIFICATION:

BUILDING PERMIT – GASTON COUNTY

Page 7: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Cost Estimate

Page 8: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

SCHEDULE

Project Team Meeting January 9, 2014

Complete Design January 31, 2014

Advertise for Construction Bids February 5, 2014

Open Construction Bids February 28, 2014

Award Construction Contract March 20, 2014

Begin Construction April 5, 2014

Complete Construction December 15, 2014

Page 9: Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Questions or Comments?

Goat Island ProjectGoat Island Project