Top Banner

of 49

Project Time Management_25 Sep 2010

Apr 03, 2018

Download

Documents

kris2tmg
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/29/2019 Project Time Management_25 Sep 2010

    1/49

    PROJECT TIME MANAGEMENT

    By

    In case you are having issues regarding audio and video please contact at

    [email protected], these training are available as recordings later ,

    please do not disturb during training.

    Please Mute your mic and mobile during training.

    Ask your question using the Q and A tab in live meeting.

    Speak one at a time so that every one is benefited.

    This training is

    sponsored bywww.itfunda.com

    supported by www.questpond.com and www.dotnetfunda.com

    Vijay Bandaru

    mailto:[email protected]://www.itfunda.com/http://www.questpond.com/http://www.dotnetfunda.com/http://www.dotnetfunda.com/http://www.questpond.com/http://www.itfunda.com/mailto:[email protected]
  • 7/29/2019 Project Time Management_25 Sep 2010

    2/49

    PROJECT TIME MANAGEMENT

    2

    Vijay BandaruMCA, MBA & PMP

    Contact:

    Email:[email protected]

    Phone: +91-984-803-2144

  • 7/29/2019 Project Time Management_25 Sep 2010

    3/49

    3

  • 7/29/2019 Project Time Management_25 Sep 2010

    4/49

    4

    What is a Project?

    What is the difference between Project &Operations?

    What is WBS?

    What are project constraints?

    What is a scope baseline?

    Why should scope to be controlled?

  • 7/29/2019 Project Time Management_25 Sep 2010

    5/49

    5

    Deliverable:Any Unique and verifiable product, Result or Capability toperform a service that must be produced to complete a process, phase orproject

    Constraint:The state, quality or sense of being restricted to a given courseof action. Eg: A date constraint assigned to complete an activity.

    Activity:A Component of work performed during the course of a project

    Activity Attributes: Include activity codes, predecessor activities, Successoractivities, Logical relationships, Leads and Lags, Resource requirements,constraints and assumptions etc

    Schedule activity:An activity that is assigned a start and end date alongwith estimated resources and cost

    Activity Duration:The time in calendar units between the start and finish ofa schedule activity

    Effort: The number of labor units required to complete a schedule activity or WBScomponent

  • 7/29/2019 Project Time Management_25 Sep 2010

    6/49

    6

    Milestone: A significant point of event in the project (Eg: Design sign off)

    Project Schedule: The planned dates for performing schedule activitiesand the planned dates for meeting schedule milestones

    Lead: Accelerating the successor (next) activity [Eg: Coding can start 5days before design is finished]

    Lag: Waiting time between two tasks [Eg: A delay of 5 days to build a wallafter foundation is laid

    Free Float [Free Slack]: Amount of time an activity may be delayedwithout delaying the early start date of any successor activity

    Total Float [Total Slack]: Amount of time an activity may be delayed from the earlystart date without delaying the project finish date

  • 7/29/2019 Project Time Management_25 Sep 2010

    7/49

    After completing this session, you will be able to:

    Understand and appreciate Time management processesof Project Management

    Understand the need for estimating activity resourcesand durations

    Appreciate the need for controlling the schedule

    Use various techniques to develop and control schedule

    7

  • 7/29/2019 Project Time Management_25 Sep 2010

    8/49

    Define Activitiesis the process of identifying the specific

    actions to be performed to produce the projectdeliverables

    Sequence Activities is the process of identifying anddocumenting relationships among project activities

    Estimate Activity Resources is the process of estimatingthe type and quantities of material, people, equipment,

    or supplies required to perform each activity

    Estimate Activity Durations is the process ofapproximating the number of work periods needed tocomplete individual activities with estimated resources

    Develop Schedule is the process of analyzing activitysequences, durations, resource requirements, and

    schedule constraints to create the project schedule

    Planning

    Control Schedule is the process of monitoring the status ofthe project to update project progress and managingchanges to the schedule baseline

    Monitor& Control

    8

    Project Time Management includes the processes required tomanage timely completion of the project.

  • 7/29/2019 Project Time Management_25 Sep 2010

    9/49

    Project Alpha: Setup ofR&D Division for Company X

    StaffEquipmentSite Bldg XXXX

    Core Staff Support Staff Staff Training

    Conduct Kickoff Meeting

    Plan for recruitment

    Advertise for Recruitment

    Conduct Interviews

    Shortlist Candidates

    Conduct Final Interviews

    Make Offer Letters

    Consolidate Offer Acceptance

    Handover to Manager and Close Project

    Conduct multiple Orientations of 1 day each

    Conduct Domain training

    Scope(Nouns)

    Time(Verbs)

    Work Packages

    Activity List

    9

  • 7/29/2019 Project Time Management_25 Sep 2010

    10/49

    0

    20

    40

    60

    80

    100

    120

    29-Sep

    8-Nov

    18-Dec

    27-Jan

    8-Mar

    17-Apr

    Planned%

    Actual %

    Activity List

    Network Diagram

    Resource requirements Activity durations

    Schedule

    Performancemeasurements

    10

  • 7/29/2019 Project Time Management_25 Sep 2010

    11/49

    InputsScope

    Baseline

    Enterpriseenvironmentalfactors

    Organizationprocess assets

    Too

    ls&

    TechniquesDecomposition

    Rolling WavePlanning

    Templates

    ExpertJudgment

    Ou

    tputsActivity List

    ActivityAttributes

    Milestone List

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Process of identifying the specific actions that need to be performedto produce the project deliverables

    11

  • 7/29/2019 Project Time Management_25 Sep 2010

    12/49

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    TOOLS & TECHNIQUES

    DECOMPOSITION Subdividing the project work packages into smallerand manageable components called Activities

    ROLLING WAVE PLANNING Near term activities planned in detail Long term activities planned at high level

    TEMPLATES Standard activity list from a previous similar project can be reused

    12

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    13/49

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    OUTPUTS

    ACTIVITY LIST Comprehensive list including all the scheduledactivities. Contains

    Activity identifier

    Scope of work description for each activity

    ACTIVITY LIST ATTRIBUTE Extend the description of activities.Contains

    Activity identifier, WBS Identifier Activity Name, Code and Description

    Relationships, Leads, Lags Constraints, Assumptions

    MILESTONE LIST Significant point or event in a project, but not anactivity itself, hence effort is zero.

    13

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    14/49

    InputsActivity list

    Activity

    AttributesMilestone list

    Project ScopeStatement

    Organizational

    Process AssetsToo

    ls&

    Techn

    iquesPrecedence

    diagrammingmethod PDM

    Dependencydetermination

    Applying leadsand lags

    ScheduleNetworktemplates

    Ou

    tputsProject

    ScheduleNetwork

    DiagramsProjectdocumentupdates

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Process of identifying and documenting relationships among theschedule activities

    14

  • 7/29/2019 Project Time Management_25 Sep 2010

    15/49

    Activity A

    Activity B

    Activity C

    Activity D

    Activity E

    Activity F

    Activity G

    Activity H

    Activities are represented on Nodes Each node has a start and a finish. There can be only 4 ways of showing dependencies between any two activitie This is done using arrows

    Finish to Start Finish to Finish

    Start to Start

    Start to Finish

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    PRECEDENCE DIAGRAM METHOD

    15

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    16/49

    Finish toStart

    Finish toFinish

    Start to Start Start toFinish

    A - DesignB - Build

    A - Review

    B - Rework

    A - Procure

    B - InspectA

    B

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    16

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    17/49

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    MANDATORYDEPENDENCIES

    DISCRETIONARYDEPENDENCIES

    EXTERNALDEPENDENCIES

    Inherent in the nature of

    the work being done.They often involvephysical limitations.

    Also, called as HardLogic

    An example: Designshould be completedbefore construction

    Based on experience,

    desire or preferences.

    Also, called as Soft,Preferred, Preferentiallogic

    For example: Plumbingwork done beforeelectric work

    Based on needs or

    dependencies outsidethe project

    Example:Environmental hearing

    before site preparationcan begin on yourproject.

    DEPENDENCY DETERMINATION

    17

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    18/49

    A (5 days)

    B (5 days)

    Lag Directs a delay in the successorevent e.g. A lag of 3 days needs to beintroduced after the pouring ofconcrete to allow for curing

    Total (10 days)

    Total (8 days)Lead (2 days)

    A (5 days)

    B (5 days)

    A (5 days)

    B (5 days)

    Lag (2 days)

    Total (12 days)

    Lead Allows acceleration of the successorevent e.g. Design can start beforerequirements gathering is completed.

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    APPLY LEADS AND LAGS

    18

    T

    OI

  • 7/29/2019 Project Time Management_25 Sep 2010

    19/49

    InputsActivity list

    Activityattributes

    Resourcecalendars

    Organizationalprocess assets

    EnterpriseEnvironmentalFactors

    To

    ols&

    Tech

    niquesExpert judgment

    Alternativesanalysis

    Publishedestimating data

    Bottom-upestimating

    Project

    managementsoftware

    O

    utputsActivity resource

    requirements

    Resource

    BreakdownStructure

    Project documentupdates

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Process of estimating the type and quantities of material, people,equipment or supplies required to perform each activity

    19

  • 7/29/2019 Project Time Management_25 Sep 2010

    20/49

    TOOLS & TECHNIQUES

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    20

    EXPERT JUDGMENT

    ALTERNATIVE ANALYSIS Identify alternate ways of estimatingresources

    Man or Machine Make or Buy

    PUBLISHED ESTIMATING DATA

    BOTTOM-UP ESTIMATING Decompose activity further

    PM SOFTWARE

  • 7/29/2019 Project Time Management_25 Sep 2010

    21/49

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    21

    Project A

    HumanResources

    Executive

    Technology Management

    Labor

    Material

    Nomination

    Equipment

    Electronic Mechanical

    RESOURCE BREAKDOWN STRUCTURE

  • 7/29/2019 Project Time Management_25 Sep 2010

    22/49

    Inputs

    Activity List

    Activity Attributes

    Activity Resource

    requirementsResourceCalendar

    Project scopestatement

    Enterprise

    environmentalfactors

    OrganizationalProcess Assets

    Tools&

    Techn

    iquesExpert judgment

    Analogousestimating

    ParametricEstimating

    Three pointestimates

    Reserve analysis

    Outputs

    Activity durationestimates

    Project document

    updates

    22

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Process of approximating the number of work periods needed tocomplete individual activities with estimated resources

  • 7/29/2019 Project Time Management_25 Sep 2010

    23/49

    23

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Expert Judgment

    AnalogousEstimates

    (Top Down)ParametricEstimation

    Three PointEstimate,

    PERT Technique

    Optimistic,More Likely,Pessimistic(O+4M+P)/6

    Reserve Analysis

    Work per unit * No.

    of units

    Leverageinformation fromprevious projects

    Reserve,Contingency

    or Buffer

  • 7/29/2019 Project Time Management_25 Sep 2010

    24/49

    24

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    ANALOGOUS PARAMETRIC THREE-POINT

    Adopts Top Downapproach

    Adopts Unitrateapproach

    Adopts O/P/ML

    approach

    Calculates based onestimates of similarprojects

    Calculates estimatesbased on Unit rate * Noof units needed

    Calculates based onOptimistic, Pessimistic& More likely estimates

    Less expensive andLess Accurate

    More AccurateNot applicable always

    PERT is more accurateDifficult when too manyactivities are to be

    estimated

    COMPARISON OF ESTIMATE MODELS

  • 7/29/2019 Project Time Management_25 Sep 2010

    25/49

    Inputs

    Activity list

    Activity Attributes

    Project ScheduleNetwork Diagrams

    Activity ResourceRequirements

    Resource Calendar

    Activity durationestimates

    Project ScopeStatement

    Enterpriseenvironmental factors

    OrganizationalProcess Assets

    To

    ols&

    Techn

    iquesSchedule NetworkAnalysis

    Critical Path Method

    Critical Chain Method

    Resource LevelingWhat-if Scenario

    Analysis

    Adjusting Leads andLags

    Schedule compression

    Scheduling tool

    O

    utputs

    Project schedule

    Schedule baseline

    Schedule data

    Project document

    updates

    25

    Process of Analyzing activity sequences, durations, resourcerequirements and schedule constraints to create Project Schedule

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

  • 7/29/2019 Project Time Management_25 Sep 2010

    26/49

    26

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Schedule NetworkAnalysis

    ResourceLeveling

    MonteCarloAnalysis

    Smoothen theresource curve

    Calculate Float

    (Slack)

    Critical PathMethod

    Calculate Early &Late Start & Finish

    SchedulingTool

    Adding Buffers

    Critical ChainMethod

    Apply Leads &Lags

    Accelerate orDelay

    What-IfScenario

    PlanningSoftwares

    ScheduleCompression

    Crashing & FastTracking

  • 7/29/2019 Project Time Management_25 Sep 2010

    27/49

    A,5

    B,7 C,6

    I, 8

    D,3

    H,4

    E,4

    F,4 G,3

    27

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Longest Path on Network Diagram Early start is same as late start. Hence, zero or negative float Delay in Critical path causes delay in project schedule More the number of critical paths, higher the negative risk

    CRITICAL PATH IN A NETWORK DIAGRAM

  • 7/29/2019 Project Time Management_25 Sep 2010

    28/49

    SCHEDULE COMPRESSION TECHNIQUES

    28

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    CRASHING Adding additional resources to the project to shorten the schedule

    Normally applied on Critical path

    Cost and Schedule tradeoffs are analyzed by monitoring risk

    FAST TRACKING Activities that are normally done in sequence are done in parallel

    May result in rework and negative risk

  • 7/29/2019 Project Time Management_25 Sep 2010

    29/49

    X = parameter under consideration e.g. Height of a Man

    Y = number of data points for each value of X

    -1s-2s-3s +3s+2s+1s

    x

    y

    29

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    NORMAL DISTRIBUTIONSD Deviance

    from Mean

    1 - 0.6827

    2 - 0.9545

    3 - 0.9973

    4 - 0.99937

    5 - 0.999994

    6 - 0.999999

  • 7/29/2019 Project Time Management_25 Sep 2010

    30/49

    PROJECT SCHEDULE

    30

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    A detailed schedule of all the project activities along with timelines,resources, dependencies . Project schedule is normally represented at 3levels

    MILESTONE SCHEDULEA Schedule chart depicting the major deliverables or keyaccomplishments of the project Eg: Completion of construction, Handover

    SUMMARY SCHEDULEA schedule chart depicting the status at Work package level Eg: Develop component 1, Test component 2

    DETAILED SCHEDULE A Schedule chart depicting the detailed activities along with the

    relationships across other activities

  • 7/29/2019 Project Time Management_25 Sep 2010

    31/49

    Inputs

    Projectmanagement plan

    Project schedule

    Work Performanceinformation

    Organizationalprocess assets

    To

    ols&

    TechniquesPerformance

    reviews

    Variance analysis

    Project

    managementsoftware

    Resource leveling

    What-if scenarioanalysis

    Adjusting leads andlags

    Schedulecompression

    Scheduling tool

    O

    utputs

    Work performancemeasurements

    OrganizationalProcess Assetsupdates

    Change requests

    Project ManagementPlan updates

    Project documentupdates

    31

    DefineActivities

    SequenceActivities

    Est. ActivityDurations

    DevelopSchedule

    ControlSchedule

    Est. ActivityResources

    Process of Monitoring the status of the project to update progress andmandating changes to the schedule baseline

  • 7/29/2019 Project Time Management_25 Sep 2010

    32/49

    32

    Define activities bydecomposingWBS further

    Sequence definedactivities using

    network diagram

    Estimate resourcesand duration for

    sequenced activities

    Build a detailedschedule usingvarious tools

    Monitor theschedule variance

    to ensure projectis on-time

  • 7/29/2019 Project Time Management_25 Sep 2010

    33/49

    FLEXERCISE

    33

  • 7/29/2019 Project Time Management_25 Sep 2010

    34/49

    Activity Duration PredecessorA 5 --

    B 7 A

    C 6 B

    D 3 C

    E 4 D,H

    F 4 A

    G 3 F

    H 4 G,I

    I 8 B

    Q : Identify the critical Path in the activity list above and its duration?

    Answer : Critical path is 5+7+8+4+4 = 28 days.

    34

  • 7/29/2019 Project Time Management_25 Sep 2010

    35/49

    Q : What is the Slack time of Activity D ?

    Q : Would crashing of task F by 2 weeks reduce the project duration?

    Q : Would crashing of task B by 2 weeks reduce the project duration?

    Q : Which tasks should the project manager look at as candidates for

    crashing?Q : Activity G has an early start time of ______ weeks and an earlyfinish time of _______ weeks

    Q : How many weeks can the activity F be allowed to slip?

    35

  • 7/29/2019 Project Time Management_25 Sep 2010

    36/49

    A,5

    B,7

    F,4

    C,6

    I, 8

    G,3

    D,3

    H,4

    E,4

    36

    Q : Calculate Critical path by calculating Early start and Late start foreach Of the activities ?

  • 7/29/2019 Project Time Management_25 Sep 2010

    37/49

    TE= 28TE= 24

    TE= 20

    TE= 12

    TE= 5TE= 0

    TE= 18

    TE= 9

    Calculate Earliest time TE at each of the nodes

    Take a forward pass and find the local Maxima at each node

    TE= 12

    TE= 21

    A,5

    B,7

    F,4

    C,6

    I, 8

    G,3

    D,3

    H,4

    E,4

    TE= 5

    TE= 5

    TE= 12

    TE= 12

    TE= 12 TE= 24

    TE= 21TE= 18

    TE= 20

    TE= 9

    37

    Step 1

  • 7/29/2019 Project Time Management_25 Sep 2010

    38/49

    TL= 28TL= 24

    TL= 20

    TL= 12

    TL= 5

    TL= 0

    TL= 21

    TL= 17

    Step 2

    Take a backward pass and find the local Minima at each node

    TL= 15

    TL= 13A,5

    B,7 C,6

    I, 8

    D,3

    H,4

    E,4

    F,4 G,3

    TL= 24

    TL= 24

    TL= 21

    TL= 20

    TL= 20

    TL= 15

    TL= 12

    TL= 17

    TL= 5

    TL= 13

    38

    Calculate Latest Finish time TL at each of thenodes

  • 7/29/2019 Project Time Management_25 Sep 2010

    39/49

    n Float / Slack time = Latest Finish time Earliest Finish time

    Step 3

    n The critical path is the Longest path, float less than orequal to specified value mostly Zero.

    n Answer : Float of D = 21-18=3

    TL= 28TL= 24

    TL= 20

    TL= 12

    TL= 5

    TL= 21

    TL= 17

    A,5

    B,7 C,6

    I, 8

    D,3

    H,4

    E,4

    F,4 G,3

    TL= 24

    TL= 24

    TL= 21

    TL= 20

    TL= 20

    TL= 15

    TL= 12

    TL= 17

    TL= 5

    TL= 13

    TL= 0

    TE= 28TE= 24

    TE= 20

    TE= 12

    TE= 5TE= 0

    TE= 18

    TE

    = 9

    TE= 5

    TE

    = 5

    TE= 12

    TE= 12

    TE

    = 12 TE= 24

    TE= 21TE= 18

    TE= 20

    TE

    = 9

    39

    Identify Critical Path

  • 7/29/2019 Project Time Management_25 Sep 2010

    40/49

    ACTIVITY NORMAL TIME CRASH TIME NORMAL $ CRASH $

    A 5 4 8000 10000

    B 7 6 8000 8500

    F 4 3 9000 15000

    H 4 3 5000 6500

    Q : Suppose the Project Manager is allocated $2500 to performcrashing. How should he spend it?

    = $2000/week

    = $500/week

    = $1500/week

    40

  • 7/29/2019 Project Time Management_25 Sep 2010

    41/49

    PERTCalculations

    Calculate1. Expected time, assuming A,B,C and D are in the critical path.2. Standard deviation.3. With 95% probability what is the Range

    Expectedtime

    (2 + 4*3 + 8)/6 = 3.7

    = 6.3

    = 7.2

    = 7.8

    ACTIVITY Optimisticestimate

    Most likelyestimate

    Pessimisticestimate

    A 2 3 8

    B 2 7 8

    C 5 7 10

    D 5 8 10

    41

    Step 1

  • 7/29/2019 Project Time Management_25 Sep 2010

    42/49

    ACTIVITY Optimisticestimate

    Most likelyestimate

    Pessimisticestimate

    PERT Time

    (OT+4*MLT+PT)/6

    Std Dev

    (PT-OT)/6

    A 2 3 8 3.7 1

    B 2 7 8 6.3 1

    C 5 7 10 7.2 0.83

    D 5 8 10 7.8 0.83

    Step 2

    Calculate1. Expected time, assuming A,B,C and D are in the critical path.2. Standard deviation.3. With 95% probability what is the Range

    PERT Calculations

    42

  • 7/29/2019 Project Time Management_25 Sep 2010

    43/49

    = 3.7+6.3+7.2+7.8 = 25

    = Sqrt(1+1+0.69+0.69)=Sqrt(3.39)=1.84 (say 2)

    = 21 to 29 weeks (2 SD)

    ACTIVITY Optimisticestimate

    Most likelyestimate

    Pessimisticestimate

    PERT Time

    (OT+4*MLT+PT)/6

    Std Dev

    (PT-OT)/6

    Variance

    Std Dev ^2

    A 2 3 8 3.7 1 1

    B 2 7 8 6.3 1 1

    C 5 7 10 7.2 0.83 0.69

    D 5 8 10 7.8 0.83 0.69

    PERT Calculations Step 3

    Calculate.1. Expected time, assuming A,B,C and D are in the critical path.

    2. Standard deviation.

    3. With 95% probability what is the Range

    43

  • 7/29/2019 Project Time Management_25 Sep 2010

    44/49

    44

  • 7/29/2019 Project Time Management_25 Sep 2010

    45/49

    45

    A project manager working on a long duration project is having atough time in planning in detail for the entire project duration.Which of the technique he should employ?

    Decomposition

    Developing PDM

    Rolling Wave Planning

    Bottom up planning

    Workbook Section 3.5

  • 7/29/2019 Project Time Management_25 Sep 2010

    46/49

    46

    A Project manager decides that he has to procure certain rawmaterial by the time the design can be approved. What type ofrelationship are we referring here?

    Finish to Finish

    Finish to Start

    Start to Finish

    Start to Start

    Workbook Section 3.5

  • 7/29/2019 Project Time Management_25 Sep 2010

    47/49

    47

    Which of the following type of estimation uses the experience ofprevious projects?

    PERT Estimates

    Analogous Estimate

    Parametric Estimate

    Bottom Up estimate

    Workbook Section 3.5

  • 7/29/2019 Project Time Management_25 Sep 2010

    48/49

    48

    Due to time constrain, a Project manager decides to add few peopleto the team and complete it on-time. What is he trying to do here?

    Fast Tracking

    Crashing

    Expert Judgment

    Network Analysis

    Workbook Section 3.5

  • 7/29/2019 Project Time Management_25 Sep 2010

    49/49