Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob
37

Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Dec 27, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

1

Project Time Management

Mohammad A. Rob

Page 2: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

2

Importance of Project Schedules

• Managers often cite delivering projects on time as one of their biggest challenges

• Average time overrun from 1995 CHAOS report was 222%

• Scope and Cost can be adjusted, but Time has the least amount of flexibility; it passes no matter what

• Schedule issues are the main reason for conflicts on projects, especially during the second half of projects

Page 3: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

3

Conflict Intensity Over the Life of a Project

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

ProjectFormation

Early Phases Middle Phases End Phases

Co

nfl

ict

Inte

nsi

ty

Schedules

Priorities

Manpower

Technical opinions

Procedures

Cost

Personality conflicts

AverageTotal Conflict

Page 4: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

4

Project Time Management Processes

• Project time management involves the processes required to ensure timely completion of a project.

• The main processes include:– Activity definition– Activity sequencing– Activity duration estimating– Schedule development– Schedule control

Page 5: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

5

Pro

ject

Tim

e M

anag

emen

t P

roce

sses

Page 6: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

6

1. Activity Definition

• Activity definition involves identifying the specific activities that the project team members and stakeholders perform to produce the project deliverables

• An activity or task is an element of work, normally found on the WBS, that has an expected duration, a cost, and resource requirements

Page 7: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

7

Activity Definition

• The main input to the Activity Definition is Work Breakdown Structure (WBS)

• Other input documents include:– Project charter that has a start and end date, and

budget information– Scope statement

• The output of this process is an activity list and/or an updated or detailed WBS and supporting explanations, so that each activity is clearly defined

Page 8: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

8

2. Activity Sequencing

• After defining project activities, the next step is activity sequencing

• Activity sequencing involves reviewing the detailed WBS, product descriptions, assumptions, and constraints to determine the relationships between activities

• A dependency or relationship shows the sequencing of project activities or tasks

• Need to answer whether a certain activity needs to be finished before starting another one, and so on

Page 9: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

9

Activity Sequencing

• There are three basic reasons for creating dependencies among project activities:

– Mandatory dependencies - inherent in the nature of the work. Testing can not be started until coding is completed

– Discretionary dependencies - defined by the project team. Example: detailed design should be done before analysis

– External dependencies - involve relationships between project and non-project activities. Example: Hardware needs to be in place before initiating software testing

• The main input to activity sequencing is activity list or detailed WBS, and the main output is network diagram

Page 10: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

10

Activity Sequencing:Project Network Diagrams

• Project network diagrams are the preferred technique for showing activity sequencing

• A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities

Page 11: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

11

Project Network Diagrams:

Arrow Diagramming Method

• One type of network diagram is called activity-

on-arrow (AOA) or arrow diagramming

method (ADM)• In this method, activities are represented by

arrows• Nodes or circles are the starting and ending points

of activities• It can only show only finish-to-start dependencies

Page 12: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

12

Project Network Diagrams: Sample Activity-on-Arrow Network Diagram

Page 13: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

13

Project Network Diagrams: Process for Creating AOA Diagrams

1. Find all of the activities that start at node 1. Draw their finish nodes and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow

2. Continue drawing the network diagram, working from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or more activities. A merge occurs when two or more nodes precede a single node

3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies

4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram

Page 14: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

14

Project Network Diagrams: Precedence Diagramming Method (PDM)

• In this method, activities are represented by boxes• Arrows show relationships between activities• More popular than ADM method and used by

project management software• It is useful in showing certain types of

dependencies• It uses four types of dependencies or relationships

between the activities

Page 15: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

15

Project Network Diagrams: Task Dependency Types in PDM

Page 16: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

16

Project Network Diagrams: Sample Precedence Diagramming Method (PDM)

Page 17: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

17

3. Activity Duration Estimating

• After defining activities and determining their

sequence, the next step in time management is

duration estimating• Duration includes the actual amount of time worked

on an activity plus elapsed time• An example of the elapsed time might be the time

needed to gather information on the activity• People doing the work should help create estimates,

and an expert should review them

Page 18: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

18

Activity Duration Estimating

• The major inputs to this process are:– activity list and activity sequencing– availability of resources, especially human resources. It

includes skills of people, number of people, and so on– identified risk, such as the probability of people leaving the

job, tools not available, and so on

• The outputs include – activity duration estimation– updated WBS, if the project team finds that certain tasks

needs to be dissected further based on their duration estimates

Page 19: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

19

4. Schedule Development

• Schedule development uses results of the other time management processes as input (e.g., project network diagram, activity duration, resource requirements) to determine the start and end date of the project and its activities

• Ultimate goal (output) is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project

• Important tools and techniques include Gantt charts, PERT analysis, and critical path analysis

Page 20: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

20

Schedule Development:Gantt Charts

• Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format

• Symbols include:– A black diamond: milestones or significant events on a

project with zero duration

– Thick black bars: summary tasks

– Lighter horizontal bars: tasks

– Arrows: dependencies between tasks

Page 21: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

21

Sample Gantt Chart

Page 22: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

22

Sample Gantt Chart for Software Launch Project

Page 23: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

23

Sample Tracking Gantt Chart

white diamond: slipped milestonetwo bars: planned and actual times

Page 24: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

24

Schedule Development: Critical Path Method (CPM)

• CPM is a project network analysis technique used to

predict total project duration

• A critical path for a project is the series of activities that determines the earliest time by which the project can be completed

• The critical path is the longest path through the network diagram and has the least amount of slack or float

Page 25: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

25

Critical Path Method (CPM): Finding the Critical Path

• First develop a good project network diagram

• Add the durations for all activities on each path through the project network diagram

• The longest path is the critical path

Page 26: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

26

Determining the Critical Path

Page 27: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

27

More on the Critical Path

• If one of more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken

• Misconceptions:– The critical path is not the one with all the critical activities;

it only accounts for time

– There can be more than one critical path if the lengths of two or more paths are the same

– The critical path can change as the project progresses

Page 28: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

28

Using Critical Path Analysis to Make Schedule Trade-offs

• Knowing the critical path helps you make schedule

trade-offs• Free slack or free float is the amount of time an

activity can be delayed without delaying the early start of any immediately following activities

• Total slack or total float is the amount of time an

activity may be delayed from its early start without

delaying the planned project finish date

Page 29: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

29

Critical Path Method (CPM): Free and Total Float or Slack

Task Start Finish Late Start Late Finish FreeSlack

TotalSlack

A Mon 8/3/98 Mon 8/3/98 Wed 8/5/98 Wed 8/5/98 0days 2daysB Mon 8/3/98 Tue 8/4/98 Mon 8/3/98 Tue 8/4/98 0days 0daysC Mon 8/3/98 Wed 8/5/98 Wed 8/5/98 Fri 8/7/98 0days 2daysD Tue 8/4/98 Fri 8/7/98 Thu 8/6/98 Tue 8/11/98 2d 2dE Wed 8/5/98 Tue 8/11/98 Wed 8/5/98 Tue 8/11/98 0d 0dF Wed 8/5/98 Mon 8/10/98 Fri 8/14/98 Wed 8/19/98 7d 7dG Thu 8/6/98 Thu 8/13/98 Mon 8/10/98 Mon 8/17/98 0d 2dH Wed 8/12/98 Wed 8/19/98 Wed 8/12/98 Wed 8/19/98 0d 0dI Fri 8/14/98 Mon 8/17/98 Tue 8/18/98 Wed 8/19/98 2d 2dJ Thu 8/20/98 Mon 8/24/98 Thu 8/20/98 Mon 8/24/98 0d 0d

Page 30: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

30

Techniques for Shortening a Project Schedule

• Shortening a project schedule requires reduction of activity duration on the critical path

• One can shorten durations of critical tasks by adding more resources or changing their scope

• Crashing is a technique that adjusts cost to reduce schedule. A part-time work activity can be finished early by allocating a full-time person

• Fast tracking means performing activities in parallel or overlapping, if possible

Page 31: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

31

Shortening Project Schedules

Overlappedtasks

Shortenedduration

Original schedule

Page 32: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

32

Importance of Updating Critical Path Data

• It is important to update project schedule information

• The critical path may change as you enter actual start and finish dates

• If you know the project completion date will slip, negotiate with the project sponsor

Page 33: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

33

Schedule Development: Program Evaluation and Review Technique (PERT)

• PERT is a network analysis technique used to

estimate project duration when there is a high

degree of uncertainty about the individual activity

duration estimates

• PERT uses probabilistic time estimates based on

using optimistic, most likely, and pessimistic

estimates of an activity duration

• PERT is based on a project network diagram

Page 34: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

34

PERT Formula and Example

• PERT uses a weighted average formula: Weighted Average Duration =

Optimistic time + 4X Most likely time + Pessimistic time

6

• Example:Weighted Average Duration =

8 workdays + 4 X 10 workdays + 24 workdays = 12 days6

where Optimistic time = 8 days, most likely time = 10 days, and Pessimistic time = 24 days.

• Thus 12 days is a better estimate than 10 days.

Page 35: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

35

5. Schedule Control

• There are many issues involved in controlling changes to project schedule– Have a realistic project schedule that can be performed by

people. Most projects fail due to people issues, not due to lack of tools & techniques such as PERT or Gantt charts

– Have the project team and other stakeholders review project charter, major delivery dates, and detailed schedule

– Don’t plan for everyone to work at 100% capacity all the time. A good level is 75 percent

– Hold progress meetings with key stakeholders and be clear and honest in communicating schedule issues

Page 36: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

36

Schedule Control: Working with People Issues

• Project managers should have leadership skills that help control schedule changes, such as:– empowerment: PM should involve team members in

creating project schedule and he/she should provide timely status information, so they feel empowered

– incentives: PM can use financial or other incentives to meet schedule expectation

– discipline: PM must have discipline to control schedule. Setting firm dates for key project milestones help minimize schedule changes

– negotiation: It is important for the PM and team members to defend their time estimates and learn to negotiate with the key stakeholders

Page 37: Project Time Management, Mohammad A. Rob @ UHCL 1 Project Time Management Mohammad A. Rob.

Project Time Management, Mohammad A. Rob @ UHCL

37

Discussion: What Went Right?

Chris Higgins used the discipline he learned in the Army to transform project management into a cultural force at Bank of America. Higgins learned that taking time on the front end of a project can save significant time and money on the back end. As a quartermaster in the Army, when Higgins' people had to pack tents, he devised a contest to find the best way to fold a tent and determine the precise spots to place the pegs and equipment for the quickest possible assembly. Higgins used the same approach when he led an interstate banking initiative to integrate incompatible check processing, checking account, and savings account platforms in various states.

Law mandated that the banks solve the problem in one year or less. Higgins' project team was pushing to get to the coding phase of the project quickly, but Higgins held them back. He made the team members analyze, plan, and document requirements for the system in such detail that it took six months just to complete that phase. But the discipline up front enabled the software developers on the team to do all of the coding in only three months, and the project was completed on time.