Top Banner
PROJECT TIME MANAGEMENT For the PMP® Exam using PMBOK® Guide 5 th Edition
123

Project Time Management Fifth Edition

Mar 13, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Time Management Fifth Edition

PROJECT TIME MANAGEMENT

For the PMP® Exam using PMBOK® Guide 5th Edition

Page 2: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PMI®, PMP®, PMBOK® Guide are registered trade marks of Project Management Institute, Inc.

Page 3: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CONTACTS

• Name: Khaled El-Nakib, PMP

• URL: http://www.khaledelnakib.com

• E-mail: [email protected]

Page 4: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

Time is a resource that when lost or misplaced, is gone forever.

HAROLD KERZNER, PHD

Page 5: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

FACTS

• We all have 24hours a day, 168 hours a week, 8760 hours a year.

• Time cannot be saved for future use

• Time has a value like currency

• Time is not elastic, we can not extend the hours

• Resource equally distributed among all human beings

Page 6: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

GLASS JAR STORY

Remember it’s you who decides what the BIG ROCKS are

Page 7: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

Exercise # 1

Sense the seconds

Page 8: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

THINGS TO REMEMBER

Same Job can take

One Week Two Weeks Three Weeks

Parkinson’s Law states that work expands to fill the time allowed

Page 9: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PROJECT TIME MANAGEMENT

Project Time Management includes the processes required to manage timely completion of the project

Page 10: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TIME MANAGEMENT PROCESSES

Project Time Management

(6.1)Plan

Schedule Management

(6.2)

Define Activity

(6.3)Sequence

Activity

(6.4)Estimate

Activity Resource

(6.5)Estimate

Activity Duration

(6.6)Develop

Schedule

(6.7)Control

Schedule

PlanningMonitoring and

Controlling

Page 11: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TIME MANAGEMENT PROCESSES

Flexible combination of planning processes:

1. In simple, low risk projects all five processes

can be seen as one big process.

2. In complex, high risk projects they can be seen

as five distinct processes

Page 12: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.1 – PLAN SCHEDULE MANAGEMENT

Plan Schedule Management is the process of

establishing the policies, procedures and

documentation for planning, developing,

managing, executing, and controlling the project

schedule.

Page 13: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-1: PROJECT MANAGEMENT PLAN

• Scope Baseline

• Other related decisions such as risk, communication or cost

Page 14: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-2: PROJECT CHARTER

• The project charter is the document that formally authorizes a projects

• It includes high-level requirements high level project description

Page 15: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-3: ENTERPRISE ENVIRONMENTAL FACTORS

• Governmental or Industry standards

• Organization infrastructure (Existing facilities, or equipment)

• Personnel skills

• Resource availability

Page 16: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-4: ORGANIZATIONAL PROCESS ASSETS

• Historical information

• Lessons learned

• Templates

• Change control procedures

• Existing formal or informal schedule control policies and procedures

Page 17: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: EXPERT JUDGMENT

• Expert judgment refers to input received from knowledge and experienced parties

Page 18: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: ANALYTICAL TECHNIQUES

• Choosing from options such as:

• Scheduling software

• Scheduling tools

• Estimating approaches

• Formats

Page 19: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: MEETINGS

• Project team may attend project meetings to develop the schedule management plan.

Page 20: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: SCHEDULE MANAGEMENT PLAN

• A document that establishes criteria and the activities for developing and controlling the project scheduleIt includes, but not limited to the following:

1. Scheduling tool

2. Level of accuracy

3. Rules of performance measurements

4. How schedule variances will be handled

5. Schedule change control procedures

6. Reporting format

Page 21: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.2- DEFINE ACTIVITY

Define activities is the process of identifying the specific actions to be performed to produce the project deliverables

Page 22: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.2- DEFINE ACTIVITY

Purpose of process

Decomposing the work package into smaller components called Schedule Activities to provide a basis for estimating

Page 23: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-1: SCHEDULE MANAGEMENT PLAN

• A document that establishes criteria and the activities for developing and controlling the project scheduleIt includes, but not limited to the following:

1. Scheduling tool

2. Level of accuracy

3. Rules of performance measurements

4. How schedule variances will be handled

5. Schedule change control procedures

6. Reporting format

Page 24: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-2: SCOPE BASELINE

� Scope Statement

� WBS

� WBS Dictionary

Page 25: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-3: ENTERPRISE ENVIRONMENTAL FACTORS

• Project Management Information System (PMIS)

• Governmental or Industry standards

• Marketplace conditions

• Stakeholders Risk Tolerance

• Infrastructure (Existing facilities, or equipments)

• Existing Human Resources (skills, knowledge)

• Personnel administration

Page 26: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-4: ORGANIZATIONAL PROCESS ASSETS

• Organization’s processes and procedures for conducting work• Standards and policies (e.g. Safety policy, project

management policy, quality policy)

• Guidelines and work instructions

• Templates

• Corporate knowledge base• Historical information and lessons learned

• Measurement database

• Projects files

Page 27: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: DECOMPOSITION

• Subdivision of work packages into smaller, more manageable components called Schedule Activities

Page 28: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: ROLLING WAVE PLANNING

• It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail

Page 29: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: EXPERT JUDGMENT

• Project team members or other experts who are experienced and skilled in developing detailed project scope statement, WBS’s, and project schedule provide expertise in defining activities.

Page 30: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: ACTIVITY LIST

• The activity list is a comprehensive list including all schedule activities that are planned to be performed on the project.

• Activity list is a component of the project management plan.

Page 31: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: ACTIVITY LIST

• Characteristics of well designed activity

• Activity is a discrete element of work.

• A single person should be responsible for performing the activity

• Activity describe the work that must be accomplished (review technical document)

• The activity work once started should be capable of proceeding to completion

Page 32: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: ACTIVITY ATTRIBUTES

• Activity attributes are an extension of the Activity attributes in the activity list and identify the multiple attributes associated with each schedule activity.

• It may include:activity code, description, predecessor, successor, logical relationship,

leads and lags, resource requirements, imposed dates, constraints, and assumptions.

Page 33: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-3: MILESTONE LIST

• A milestone is a significant event in the project, usually completion of a major deliverable

• A milestone has duration of zero and no effort

• A list of schedule milestone identifies all milestones and indicates whether the milestone is mandatory, or optional.

• Milestone list is a component of the project management plan.

Page 34: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

QUESTION

All of the following statements describe the activity list except which one?

A. The activity list is an output of the Activity Definition process.

B. The activity list includes all activities of the project.

C. The activity list is an extension of and a component of the WBS.

D. The activity list includes an identifier and description of the activity.

Page 35: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.3 - SEQUENCE ACTIVITY

• Sequence activity involves identifying and documenting the logical relationships among project activities.

Page 36: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

INPUTS

• Schedule Management Plan

• Activity List

• Activity Attributes

• Milestone List

• Project Scope Statement

• Organizational process assets

Page 37: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: DEPENDENCY DETERMINATION

• Mandatory dependencies :(i.e., hard logic): These are dependencies that cannot change

• Discretionary dependencies :(i.e., soft logic): These are dependencies that may be at the discretion of the project management team

• External dependencies:These are dependencies that may be beyond the control of the project team

• Internal dependencies:These are dependencies between project activities, and generally inside the project’s team control

Page 38: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2:APPLYING LEADS AND LAGS

• Lead

• Allows an acceleration of the successor activity

• Lag

• Directs a delay in the successor activity

Activity A

Activity B

Activity A

Activity B

Page 39: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: PRECEDING DIAGRAMMING METHOD (PDM)

• PDM is a method of constructing a project schedule network diagram used by most project management software packages

• It is also called Activity on Node (AON)

Page 40: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PRECEDING DIAGRAMMING METHOD (PDM) (CONTINUED)

• Finish Installing Windows in order to start installing Office

Activity A

Activity BFinish Activity A to Start Activity B

Finish-to-Start

Page 41: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PRECEDING DIAGRAMMING METHOD (PDM) (CONTINUED)

• Start coding (Activity B) 5 days after starting design (Activity A)

Activity A

Activity BStart Activity A to Start Activity B

Start-to-Start

Page 42: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PRECEDING DIAGRAMMING METHOD (PDM) (CONTINUED)

• Finish buying the new truck in order to end finish ending rent contract

• Finish writing last chapter to finish writing the whole book

Activity B

Activity A

Finish Activity A to Finish Activity B

Finish-to-Finish

Page 43: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PRECEDING DIAGRAMMING METHOD (PDM) (CONTINUED)

• Theoretical, rarely used

• Start night shift to finish day shift

Activity B

Activity AStart Activity B to Finish Activity A

Start-to-Finish

Page 44: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PDM EXAMPLE

Page 45: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PDM EXAMPLE (CONTINUED)

Page 46: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: PROJECT SCHEDULE NETWORK DIAGRAM

• Project schedule network diagrams are schematic display of the project’s schedule activities and the logical relationships among them.

Page 47: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: PROJECT DOCUMENTS UPDATES

• Activity List (Updates)

• Activity Attributes (Updates)

• Risk Register

Page 48: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.4 - ESTIMATE ACTIVITY RESOURCE

• Estimate activity resources is the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity

Page 49: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

COMMON INPUTS

• Schedule Management Plan

• Activity List

• Activity Attributes

• Risk Register

• Activity Cost Estimate

• Enterprise environmental factors

• Organizational process assets

Page 50: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-3: RESOURCE CALENDARS

Acquire Project Team Process

Page 51: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-3: RESOURCE CALENDARS (CONTINUED)

Conduct Procurement Process

Page 52: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

IN-3: RESOURCE CALENDARS (CONTINUED)

• Resource Calendars specify when and how long identified project resources will be available during the project

• Resource Calendar is an output of the Acquire Project Team and Conduct Procurement processes

• Both processes are performed in the Executing process group

Page 53: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: EXPERT JUDGMENT

• Any group or person with specialized knowledge in resource planning a and estimating can provide such expertise.

Page 54: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: ALTERNATIVE ANALYSIS

• You can accomplish an activity in more than one way.

• Define the combination of:

• Resource capability and skills levels

• Machine type

• Different tools

• Resource related buy or make decision

Page 55: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: PUBLISHED ESTIMATING DATA

• Some organizations publishes production rates, unit cost for labor, materials, equipments, for different countries and geographical locations within countries

Page 56: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-4: BOTTOM UP ESTIMATING

• When a scheduled activity cannot be estimated with reasonable degree of confidence, the work within the schedule activity is decomposed into more detail.

Page 57: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-5: PROJECT MANAGEMENT SOFTWARE

• Project management software has the capability to help plan, organize, and manage resource pools and develop resource estimates.

Page 58: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: ACTIVITY RESOURCE REQUIREMENTS

• Identification and description of the types and quantities of resources required for each schedule activities in a work package

• It may include:

• Basis of estimate

• Assumptions

• Availability

• Quantity

Page 59: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: RESOURCE BREAKDOWN STRUCTURE (RBS)

• A hierarchical structure of the identified resources by resource category and resource type

Page 60: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-3: PROJECT DOCUMENTS UPDATES

• Activity List (Updates)

• Activity Attributes (Updates)

• Resource Calendars

Page 61: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

WHAT DO WE HAVE NOW?

• Activity list

• Activity scope of work

• Required resource types

• Required resource quantities

• Resource calendars

Page 62: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.5 - ESTIMATE ACTIVITY DURATIONS

• Estimating activity durations process is the process of estimating the number of work periods needed to complete individual activities with estimated resources

Page 63: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

EFFORT VS DURATION

• Effort: the number of units required to complete a schedule activity or WBS component. Usually expressed as staff hours, staff days, or staff weeks.

• Duration: The total number of work periods(not including holidays or other nonworking periods) required to complete a schedule activity or WBS component.

• Elapsed Time: The amount of time that elapses between the time the task is started and the time it is completed

Page 64: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.5 - ACTIVITY DURATION ESTIMATE INPUTS1. Schedule Management Plan

2. Activity list

3. Activity attributes

4. Activity resource requirements

5. Resource calendars

6. Project scope statement

7. Risk Register

8. Work Breakdown Structure

9. Enterprise environmental factors

10. Organizational process assets

Page 65: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: EXPERT JUDGMENT

• One time estimate means one estimate per activity is received.

• Disadvantages:

• Padding (providing worst-case estimates)

• Hiding information about risks and uncertainties

• Untruthfulness when activity takes less period

• Lack of experience produce risky estimates

Page 66: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: ANALOGOUS ESTIMATE

• A.k.a. Top-down estimating

• Using actual duration of a previous similar schedule activity as the basis for estimating the duration of future schedule activity.

• Used when there is limited information

• Uses both historical data and expert judgment

• Useful when activities are really similar not just in appearance.

• Usually used in early planning phase

Page 67: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: PARAMETRIC ESTIMATING

• Multiplying the quantity of work to be performed by the productivity rate.

• Example:

• Cable installation in meters/ labor hours

Page 68: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-4: THREE-POINT ESTIMATE

• Program Evaluation and Review Technique (PERT)

• PERT uses three time estimates (optimistic, most likely, and pessimistic

• PERT is probabilistic in nature, based on a beta distribution for each activity time and a normal distribution for expected time duration

• PERT is used on those projects where percent complete is almost impossible to determine except at completed milestones (R&D)

Page 69: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PERT CALCULATIONS

• Activity Duration Estimation

• Most optimistic completion time. This time assumes that everything will go according to plan and with minimal difficulties

• Most pessimistic completion time. This time assumes that everything will not go according to plan and maximum difficulties will develop

• Most likely completion time. This is the time that, in the mind of the functional manager, would most often occur should this effort be reported over and over again

Page 70: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

PERT CALCULATIONS (CONTINUED)

Estimated activity duration

In order to calculate the probability of completing the project on time, the standard deviations of each activity must be known

Page 71: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-5: GROUP DECISION MAKING TECHNIQUES

• Unanimity (complete agreement by everyone)

• Majority (one vote more than 50% of total votes)

• Plurality (largest number of votes)

• Dictatorship (one person makes the decision)

Page 72: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-6: RESERVE ANALYSIS

• Project team can choose to incorporate additional time referred to as contingency reserve, time reserve or buffer, into the overall project schedule as recognition of schedule risk.

• The contingency reserve can be used completely or partially, reduced or eliminated

Page 73: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: ACTIVITY DURATION ESTIMATE

• Activity duration estimate are quantitative assessments of the likely number of work period that will be required to complete a schedule activity.

• 15days – 19days

• 17 days ± 2days

• 80% activity duration 17 days

Page 74: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: PROJECT DOCUMENT UPDATES

• Activity attributes are updated to include the durations for each schedule activity, the assumptions made in developing the activity duration estimates, and any contingency reserve.

Page 75: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

WHAT DO WE HAVE NOW?

• Activity list

• Activity scope of work

• Activities dependencies

• Required resource types

• Required resource quantities

• Resource calendars

• Resource availability

• Schedule activity duration

Page 76: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.6 - DEVELOP SCHEDULE

• Purpose: to determine planned start and finish dates for project activities.

• Schedule development continues throughout the project as work progresses, the project management plan changes, and anticipated risk events occur or disappear, or new risks are identified

Page 77: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

INPUTS1. Schedule Management Plan

2. Activity list

3. Activity attributes

4. Project schedule network diagram

5. Activity resource requirements

6. Resource calendars

7. Activity duration estimates

8. Project scope statement

• Schedule related Assumptions and Constraints

Page 78: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

INPUTS (CONTINUED)

9. Risk Register

10. Project staff assignments

11. Resource breakdown structure

12. Enterprise environmental factors

13. Organizational process assets

• Project calendar (working days, non working days ,shifts)

Page 79: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

ADDITIONAL INFORMATION

• Project Calendar

• Local Calendar (in case of international projects)

Page 80: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: SCHEDULE NETWORK ANALYSIS

• Schedule network analysis is a technique that generates the project schedule.

Page 81: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: CRITICAL PATH METHOD (CPM)

• The critical path method calculate theoretical early start and finish dates, and late start and finish dates for all schedule activities without regard for any resource limitations by performing a forward pass analysis an a backward pass analysis through the project schedule network.

• Purpose: determine schedule flexibility.

Page 82: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CALCULATION

• Earliest start times (forward pass)

• Earliest starting time of a successor activity is the latest of the earliest finish dates of the predecessors

Page 83: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CALCULATION (CONTINUED)

Page 84: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CALCULATION (CONTINUED)

Page 85: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CALCULATION (CONTINUED)

• Latest starting times (Backward pass)

• The latest finishing time for an activity entering a node is the earliest Late starting time of the activities exiting the node

• The latest starting time can be calculated by subtracting the activity time from the latest finishing time

Page 86: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CALCULATION (CONTINUED)

Page 87: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

CRITICAL PATH CHARACTERISTICS

• The longest path through the project

• Activities on the Critical Path have ZERO float

Page 88: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TOTAL FLOAT

• The amount of time you can delay the earliest start of a task without delaying the ending of the project

Page 89: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TOTAL FLOAT CALCULATION (CONTINUED)

(10-6) or (17-13)(6-0) or (10-4) (17-13) or (22-18)

Float = LS – ES Float = LF – EF OR

(9-6) or (14-11) (14-14) or (22-22)

Page 90: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

FREE FLOAT

• The amount of time you can delay the start of a task without delaying the earliest start of a successor task

• Free float can only occur when two or more activities share the same successor

Page 91: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

FREE FLOAT CALCULATION6-4 = 2

6-6 = 0

Free Float = ES2 – EF1

Page 92: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: CRITICAL CHAIN

• Construct the schedule network diagram using non-conservative estimates

• Define dependencies.

• Define constraints.

• Calculate critical path.

• Enter resource availability into the schedule.

• The critical chain method adds duration buffers non-work activities where needed as to help manage the planned activity durations

Page 93: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-4: RESOURCE OPTIMIZATION TECHNIQUES

• Resource Leveling

• Also called the resource-based method—is used when resources are limited or time constrained (especially those assigned to critical path activities) and when specific schedule dates need to be met

• Resource Leveling approach can cause the original critical path to change

Page 94: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-4: RESOURCE OPTIMIZATION TECHNIQUES

• Resource Smoothing

• A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed predefined resource limits.

Page 95: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-5: MODELING TECHNIQUES

• What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively on project objectives

• Simulation involves calculating multiple project durations with different set of activity assumptions.

Page 96: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-6: APPLYING LEADS AND LAGS

• Lags

• Delay successor activities and require time added either to the start date or to the finish date of the activity

• Leads

• Require time to be subtracted from the start date or the finish date of the activity

Page 97: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-7: SCHEDULE COMPRESSION

• Schedule compression shortens the project schedule without changing the project scope, to meet the schedule constraints. Imposed dates, or other schedule objectives. It includes two techniques:

1. Crashing

2. Fast tracking

Page 98: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

SCHEDULE CRASHING

• A technique in which cost and time tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost.

Page 99: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

SCHEDULE CRASHING (CONTINUED)

Time , weeks Costs Crashing cost per week, $Activity Normal Crash Normal Crash

A 4 2 10000 14000 2000B 6 5 30000 42500 12500C 2 1 8000 9500 1500D 2 1 12000 18000 6000E 7 5 40000 52000 6000F 6 3 20000 29000 3000

Page 100: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

SCHEDULE CRASHING (CONTINUED)

Page 101: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

FAST TRACKING

• Fast-tracking a project means that activities that are normally done in series are done in parallel

• Fast-tracking a job can accelerate the schedule but requires that additional risks be taken

Page 102: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-8: SCHEDULING TOOLS

• Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagram, resource and activity duration

Page 103: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: PROJECT SCHEDULEGANTT (BAR) Chart with relationships

Page 104: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: PROJECT SCHEDULE (CONTINUED)

GANTT (BAR) Chart

Page 105: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: PROJECT SCHEDULE (CONTINUED)

Network Diagram

Page 106: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: PROJECT SCHEDULE (CONTINUED)

Milestone Chart

Page 107: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: SCHEDULE BASELINE

• A schedule baseline is a specific approved version of the project schedule.

• A schedule baseline is a component of Project Management Plan, which provides the basis for measuring and reporting schedule performance.

Page 108: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-3: SCHEDULE DATA

• Supporting data for the schedule, this output includes but not limited to the milestones, schedule activities and activity attributes, resource histograms, alternative schedules, schedule contingency reserves, and the assumptions and constraints regarding the schedule

Page 109: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-4: PROJECT CALENDARS

• A project calendar identifies working days and shifts that are available for schedule activities.

Page 110: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-5: PROJECT MANAGEMENT PLAN UPDATES

• Schedule Baseline

• Schedule Management Plans

Page 111: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-6: PROJECT DOCUMENT UPDATES

• Activity Attributes update

• Activity Resource Requirements

• Calendar

• Risk Register

Page 112: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

6.7 - SCHEDULE CONTROL

• Objectives:

1. Determining the current status of the project schedule

2. Influencing the factors that create schedule changes

3. Determining that the project schedule has changed

4. Managing the actual changes as they occur

Page 113: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

INPUTS

1. Project Management Plan

2. Project Schedule

3. Work Performance Data

• Provide information on schedule performance, such as which planned dates have been met, and which have not, and alert to issues that may cause performance problems

4. Project Calendars

5. Schedule Data

6. Organizational Process Assets

Page 114: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-1: PERFORMANCE REVIEWS

• Measure, Compare and analyze schedule performance.

Page 115: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-2: PROJECT MANAGEMENT SOFTWARE

• Project management software is used to track the actual schedule dates against planned schedule dates.

Page 116: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-3: RESOURCE OPTIMIZATION TECHNIQUES

• Resource Smoothing

• A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed predefined resource limits.

Page 117: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

TT-4: MODELING TECHNIQUES

• What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively on project objectives

• Simulation involves calculating multiple project durations with different set of activity assumptions.

Page 118: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

COMMON TOOLS & TECHNIQUES

• TT-5: Adjust leads and lags

• TT-6: Schedule compression

• TT-7: Scheduling tools

Page 119: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-1: WORK PERFORMANCE INFORMATION

• The calculated schedule variance (SV) and schedule performance index (SPI) values are documented and communicated

Page 120: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-2: SCHEDULE FORECASTS

• Schedule forecast are estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time of the forecast.

Page 121: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

OUT-3: CHANGE REQUESTS

• Schedule variance analysis, along with review of progress reports may result in requested changes to the project schedule base line.

Page 122: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014

COMMON OUTPUTS

• TT-4: Project Management Plan Updates

• TT-5: Project Documents Updates

• TT-6: Organizational process asset updates

Page 123: Project Time Management Fifth Edition

© Khaled El-Nakib, PMP, PMI-RMP 2014