    CIVL 445

    Project Scheduling Using MS Project 2007

    Dr. Essam Zaneldin

    Dept. of Civil & Environmental Engineering

    n e ra m ra es n vers y

  • 8/10/2019 Project Scheduling Using MS Project 2007

    2/37

    Objectives

    Use Microsoft Project software for

    scheduling real-world projects

    Determine the total project duration

    Identify the critical path(s) in the project

    Determine activities floats (TF & FF)

    Determine activities la times

  • 8/10/2019 Project Scheduling Using MS Project 2007

    3/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    4/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    5/37

    Scheduling with MS Project

    Then Save Your Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    6/37

    Scheduling with MS Project

    Setup Projects Start Date: From the Project menu, use Project Information to

    specify the projects start date When finished click the OK button

  • 8/10/2019 Project Scheduling Using MS Project 2007

    7/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    8/37

  • 8/10/2019 Project Scheduling Using MS Project 2007

    9/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    10/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    11/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    12/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    13/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    14/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    15/37

    Scheduling with MS Project

    In ut Pro ect Activities:

    Enter activities names in theGantt Chart sheet with their

    2

    1

    A (4)

    4 9

    3

    B (6)

    E (4)

    F (10) H (8) I (6)

    shown in the figure

    87

    C (2)K (10)

    G (16)

    J (6)

  • 8/10/2019 Project Scheduling Using MS Project 2007

    16/37

  • 8/10/2019 Project Scheduling Using MS Project 2007

    17/37

    Scheduling with MS Project

    Specify Relationships: D (8)

    Once relationships are entered, a

    32-day schedule, in this example,

    will result

    1

    A (4)

    4 95 6B (6)

    E (4)

    F (10) H (8) I (6)

    ou may a so see e ura on o

    the project by using the Project

    menu, Project Information, and

    then the Statistics button

    87

    C (2)K (10)

    G (16)

    J (6)

  • 8/10/2019 Project Scheduling Using MS Project 2007

    18/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    19/37

  • 8/10/2019 Project Scheduling Using MS Project 2007

    20/37

    Scheduling with MS Project

    Creating Milestones for your Project:

    Analysis

    Report

  • 8/10/2019 Project Scheduling Using MS Project 2007

    21/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    22/37

  • 8/10/2019 Project Scheduling Using MS Project 2007

    23/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    24/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    25/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    26/37

    Scheduling with MS Project

    The Gantt chart of the project with critical activitiesshown in red color & in a different pattern:

    Critical Activities

  • 8/10/2019 Project Scheduling Using MS Project 2007

    27/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    28/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    29/37

    Scheduling with MS Project

  • 8/10/2019 Project Scheduling Using MS Project 2007

    30/37

    Scheduling with MS Project

    na ape o e ro ec s an c ar :

  • 8/10/2019 Project Scheduling Using MS Project 2007

    31/37

    Scheduling with MS Project

    View the Projects Network:

    From the View menu, select the Network Diagram option to

    view the network (precedence diagram) of the project. Notice that

    critical activities are shown in red and have bold borders

  • 8/10/2019 Project Scheduling Using MS Project 2007

    32/37

    Scheduling with MS Project

    View the Projects Network:

    To specify what data to view in the box of each task, use

    Format-Box Styles menu option

  • 8/10/2019 Project Scheduling Using MS Project 2007

    33/37

    Scheduling with MS Project

    View the Projects Network:

    To design a new box or change the

    design of the existing one,

    use Format-Box St les

    menu option

  • 8/10/2019 Project Scheduling Using MS Project 2007

    34/37

    Scheduling with MS ProjectExercise 1:

    Use MS Project for scheduling the small project shown below:

    Set up a new project file Show columns for task name, duration, predecessors, successors, ES, EF, LS,

    LF TF and FF times

    Show the critical path(s) in a different pattern

    On the Network (PDM) Diagram show the task name, duration, ES, EF, LS, LF,and TF

    Print two sheets: one for the Gantt chart showin the activit data and the barchart, and another one for the PDM network

    2

    A 4

    3D (8)

    1

    4 95 6B (6)

    F (10) H (8) I (6)

    87

    K (10)G (16)

    J (6)

  • 8/10/2019 Project Scheduling Using MS Project 2007

    35/37

    Scheduling with MS ProjectExercise 2:

    Use MS Project for scheduling the project shown below

    Set up a new project file. Show columns for task name, duration, predecessors,successors, ES, EF, LS, LF, TF, and FF times Show the critical path(s) in a different pattern

    , , , , , ,and TF

    Print two sheets: one for the Gantt chart showing the activity data and the barchart, and another one for the PDM network

    = TF = =

    =

    A (10) D (11) G (5) J (15)

    -2 1

    E (11)B (7) K (9)H (12)

    3 FS La TimeTF = TF = TF =

    I (10)F (5)C (7) L (6)

    TF =

  • 8/10/2019 Project Scheduling Using MS Project 2007

    36/37

    Exercise 3:

    Scheduling with MS Project

    Use MS Project for scheduling the project shown below

    Set up a new project file. Show columns for task name, duration,predecessors, successors, ES, EF, LS, LF, TF, and FF times

    Show the critical path(s) in a different pattern

    On the Network (PDM) Diagram show the task name, duration, ES, EF, LS, LF,and TF

    Print two sheets: one for the Gantt chart showing the activity data and the bar

    chart, and another one for the PDM network

    5 A

    910 D

    825 H

    12

    L

    1150

    15

    E

    11

    B

    8 3040

    45FC

    I

    1055

    M

    5

    60

    J7

    96K

    3

    G6

  • 8/10/2019 Project Scheduling Using MS Project 2007

    37/37

    Exercise 4:

    Scheduling with MS Project

    Use MS Project for scheduling the project shown below

    Set up a new project file. Show columns for task name, duration,predecessors, successors, ES, EF, LS, LF, TF, and FF times

    On the Network (PDM) Diagram show the task name, duration, ES, EF,

    LS, LF, and TF

    Print two sheets: one for the Gantt chart showing the activity data and

    the bar chart, and another one for the PDM network

    105A (7) C (8) G (6)

    20 35

    B (8) E (6)

    D (9) H (3)

    L (10)

    K (11)

    15 4025

    F (10) M (12)

    30