Top Banner
Project Scheduling Project Scheduling Presentation Presentation Association for the Advancement Association for the Advancement of Cost Engineering International of Cost Engineering International (AACEi) (AACEi) North Florida Section North Florida Section March 19th, 2009 Section Meeting March 19th, 2009 Section Meeting By John P. Orr, PSP By John P. Orr, PSP Scheduling and Cost Engineering on Overseas Projects: Scheduling and Cost Engineering on Overseas Projects: Earned Value and Performance Intensity Progress Measurement Earned Value and Performance Intensity Progress Measurement March 19, 2009
35

Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

Dec 14, 2015

Download

Documents

Erik Pon
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

Project Scheduling PresentationProject Scheduling Presentation

Association for the AdvancementAssociation for the Advancementof Cost Engineering International (AACEi)of Cost Engineering International (AACEi)

North Florida SectionNorth Florida Section

March 19th, 2009 Section MeetingMarch 19th, 2009 Section Meeting By John P. Orr, PSPBy John P. Orr, PSP

Scheduling and Cost Engineering on Overseas Projects: Scheduling and Cost Engineering on Overseas Projects:

Earned Value and Performance Intensity Progress MeasurementEarned Value and Performance Intensity Progress Measurement

March 19, 2009

Page 2: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

2

Scheduling & Cost EngineeringScheduling & Cost Engineeringon Overseas Projectson Overseas Projects

I. Earned Value and Performance Intensity Progress Measurement

II. Tools for Monitoring and Controlling Project Objectives:

(Cost / Quality / Time)

III. Claims Avoidance & ResolutionPresent / Refute Claims:

Sword / Shield

Page 3: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

3

Importance of SchedulingImportance of Scheduling• Convert the Work Plan into a Map – “The scheduling process forces people to quantify

their effort in discrete terms and to place activities in proper relationship to each other.”

• Establish a Baseline Against Which Progress is Measured

• Monitor and Control Projects

• Goal: To Provide Accurate Information to Decision-Makers

Page 4: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

4

Who Sets Scheduling Standards?Who Sets Scheduling Standards?

• PMBOK – Project Management InstituteBody of Knowledge

• PMI – College of Scheduling– Scheduling Excellence Initiative (SEI)

Best Practices and Guidelines (being developed)• AACE International – Recommended Practices• CMAA – Scheduling Committee Guidelines• AGC – The Associated General Contractors• US Army Corps of Engineers– Impact Evaluation Guide (Productivity)

Page 5: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

5

Who Sets the Standards?Who Sets the Standards?• No Single Body is Authoritative• Training:– Collegiate– Corporate– Software Providers– Books

• No Consistency in the Universities as to how CPM Scheduling is Taught

• Schedulers Use a Variety of Techniques• No Single Standard for Certification of

Schedulers

Page 6: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

6

US Dept of State – Overseas Building US Dept of State – Overseas Building OperationsOperations

• Provide Facilities for Diplomatic and Consular missions overseas

• As of January 2009, OBO has opened 65 new facilities with an additional 31 under design or construction

• Point position overseas in the field:The OBO Project Director (PD)

Page 7: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

7

OBO Project Director ResponsibilitiesOBO Project Director Responsibilities

• Project Controls– Project Objectives (Cost/Quality/Time)– Primary Contact with Contractor & Subs– Interface with Embassy (Post) stakeholders– Interface with Stateside stakeholders• Project Status & Completion Projections

Page 8: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

8

OBO Project Scheduling OBO Project Scheduling RequirementsRequirements

• Project Execution Schedule (PES)

• Contractor-prepared & updated– Initial PES, Baseline PES & Updates– Cost-loaded– Tied to Monthly Payment Requisition

Page 9: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

9

What does a PD Face?What does a PD Face?• His Approval Binds the USG to the Schedule• Implied Duties:– Cooperate

– Coordinate

– Not Delay, Hinder or Interfere

• Submittal Reviews (duration, stacking)• Manpower – Post Access / Clearances• Government-Furnished Material Deliveries

Page 10: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

10

What Else Does a PD Face?What Else Does a PD Face?

• Other Legal Issues– Ownership of Float

– Right to Finish Early

– Acceleration (Directed / Constructive)

– Front-end Loading

– Improper Use of Lag Factors

– No Damage for Delay Clauses

– Concurrent, Excusable, Compensable Delay

– Schedule Pacing

– Schedule Impossibility

Page 11: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

11

What What ElseElse Does a PD Face? Does a PD Face?

• Loss of Productivity– Disruptions– Delays– Overtime– Change Orders– Acceleration

• Changed Working Conditions– Loss of Productivity & Increased Labor

Costs

Page 12: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

12

What does a PD Use?What does a PD Use?• Primavera Project Planner (P3 ver 3.1)– Very Flexible Tool

– Allows for Creative Scheduling

– Allows Hidden Lag Factors and Multiple Logic Options• ADM: You saw the logic

• PDM: Less Activities, More Options for Logic

– Possibility of “Schedule Embezzlement”

• Remember:

It Only Looks Like a Gantt Chart!

Page 13: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

13

Overseas ConstructionOverseas Construction

Scaffolding:

Rome-style

Page 14: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

14

Scaffolding: Rome-styleScaffolding: Rome-style

Page 15: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

15

Scaffolding: Tbilisi-styleScaffolding: Tbilisi-style

Page 16: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

16

Formwork – African-styleFormwork – African-style

Page 17: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

17

Unfamiliar ConstructionUnfamiliar Construction

Page 18: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

18

Unfamiliar FoodUnfamiliar Food

Page 19: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

19

Unfamiliar AltitudeUnfamiliar Altitude (for Floridians) (for Floridians)

2,440M (9,700 feet above sea level)

Page 20: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

20

Unfamiliar Level of Labor IntensityUnfamiliar Level of Labor Intensity

Page 21: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

21

Overseas Issue #1: TimelinessOverseas Issue #1: TimelinessProject Execution Schedule (PES) turn-around:• Field updating process

• Focus/Emphasis on Payment Requisition

• Data sent Stateside for Primavera (P3) updating• Payment data does not include Actual Start/Finish dates

• Cycle return to field NOT timely

• Formal schedule submittal received back in field well past data date. Information no longer current

Project Director without timely information cannot provide current, accurate projections with a high degree of confidence

Page 22: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

22

Issue #2: “Schedule Embezzlement”Issue #2: “Schedule Embezzlement”

Relationship logic changes, or changes to lag factors, constraints and other “unseen” items:• Masks poor progress

• Can “stack” trades in concurrent work

• Constraints modify CPM calculations

• Date tables and bar charts do not indicate changes

Comparison to Target (prior) schedule requires P3 schedule analysis or “Digger” software, not always available in the field.

Page 23: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

23

Page 24: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

24

Slippage Masked by Logic Change(s)Slippage Masked by Logic Change(s)

Page 25: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

25

Issue #3: Out-of-Sequence WorkIssue #3: Out-of-Sequence Work• Schedule does not reflect actual sequence– Disruptions– Delivery Delays– Resource Limitations / Availability– Change Orders– Changed Working Conditions

• Inaccurate Schedule Projections – Immediate & Intermediate dates inaccurate– Limited credibility and usefulness

Page 26: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

26

Page 27: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

27

Introduction to “Momentology”Introduction to “Momentology”• A measurable rate of Performance Intensity– The Elusive “Miles-per-Hour”

– Maintaining the emphasis of the Project Schedule on the time-related aspects of project management

– Schedule performance measurement must reconcile the rate of work placement with that rate’s relationship to time-based goals• Earned Value does not accomplish this

“The concept of the critical path was all-important to the Scheduler, while it was of dubious value or interest to the Project Manager.”

Page 28: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

28

The “Duration-Day”The “Duration-Day”

• The Duration-Day = is the amount of work performance required to reduce a schedule’s remaining duration by one day.

• Also known as a “Crew-Day”

• Project Performance = Aggregate Duration-Days

Page 29: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

29

Performance IntensityPerformance Intensity

Work Performance / Time Consumption

• Add all Original Duration-Days for all (typically construction) activities in the schedule

• Divide by the number of workdays required for their performance

This is the basic formula for Performance Intensity (P.I.)

Page 30: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

30

Page 31: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

31

Page 32: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

32

P.I. equivalent to Miles per HourP.I. equivalent to Miles per Hour

• Car trip: 2,000 miles in five days. I must drive at 50 MPH for 8 hrs/day (40 hours driving) in order to travel 2,000 miles in 5 days.

• Tools: Odometer & Speedometer

• If at the end of the first hour I see I have only covered 48 miles, I can re-set the cruise control to 52 MPH to recover

Page 33: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

33

P.I. vs Total Float AnalysisP.I. vs Total Float Analysis

• Total Float analysis is subject to the Timeliness Issue (after-the-fact evaluation)– Car trip illustration: wait until the end of the

first day to learn that I have only travelled 384 miles

• Total Float is also subject to “Schedule Embezzlement” through logic changes or constraints that reserve or sequester float

Page 34: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

34

P.I. vs Earned ValueP.I. vs Earned Value

• Earned Value is also subject to the Timeliness Issue

• A resource-interpolation method, Earned Value is also performed after-the-fact.– Car trip illustration: wait for a gas fill-up in

order to check gallons of fuel consumed against miles-per-gallon estimates

Page 35: Project Scheduling Presentation Association for the Advancement of Cost Engineering International (AACEi) North Florida Section North Florida Section March.

35