JACOB ELLIS CO-OP 2015 PROJECT REVIEW 6 May, 2015
JACOB ELLISCO-OP 2015PROJECT REVIEW
6 May, 2015
MELT SHOP – MED. VOLTAGE VENTILATION
Objectives
• Assess and improve ventilation and cooling in transformer/reactor/rectifier space
Project goals:
• Reduce PM time spent cleaning/dusting equipment
• Reduce arc flash hazard from dust loading
• Reduce heat exhaustion risk to personnel
MELT SHOP – MED. VOLTAGE VENTILATION
Airflow Study/RCA Investigation
MELT SHOP – MED. VOLTAGE VENTILATION
Primary modes of failure:• Dust carry-over through evap. cooler• High moisture carry-over• Failure of secondary air circuit• Sealing of reactor vault
Airflow Study/RCA Investigation
MELT SHOP – MED. VOLTAGE VENTILATION
Improvement: Replacement of AMER-KOOL equipmentBenefits:• Increased effectiveness of filtration
• Removal of secondary air circuit – increased reliability• New canister filters to reduce PM cost – change-out, time, service life
• More efficient and reliable cooling at same airflow capacity• Replace corroded galvanized sheet metal w/ stainless to increase service life• Reduced moisture carryover
Improvement: Close off access hallway to reactor roomBenefits:• Scale-laden air no longer drawn into reactor from exterior+LMS• Air will properly change out between transformer+reactor
Improvements
MELT SHOP – MED. VOLTAGE VENTILATION
Replacement of AMER-KOOL equipment:• Currently awaiting decision on filtration design• Vendor lead time = 6-8 months• Contact: Mark Krajewski; AAF International
Arc flash/partial discharge monitoring of transformer equipment:• Evaluated by FLIR vendors during February visit• Project implementation TBD after testing equipment in ladle application
Future/Long-term work
MELT SHOP – BILLET WEIGHING SYSTEMObjectives
• Improve the use of the online billet scale in statistical process control• Use Level 2 data to investigate variation in cast billet weight• Overall goal of increasing yield in the rolling mill
MELT SHOP – BILLET WEIGHING SYSTEM
Conclusions● Data collection and measurement error prevents reliable use of SPC for
weight measurement/mill yield control● Cleanup of data highlights weaknesses in procedure, measurement, data
recording, and knowledge management in addition to steel casting defects● To reduce and control defects, a foundation for continuous PDCA
improvements must be put in place:Suggestions for immediate improvement: Revise process map to
communicate procedure, automate control systems using reliable SPC data, integrate knowledge management, and plan for new standards and procedures
● Future improvements: Use foundation of reliable measurement and interpretation to improve yield via PDCA cycle
ROLLING MILL – STAND HEAT EXCHANGERSObjectives
• Reduce total maintenance costs for heat exchanger filters• Minimize frequency of filter changeouts• Long-term: eliminate need for weekly PM schedule
ROLLING MILL – STAND HEAT EXCHANGERS
• 17 air-cooled DC slip ring motors• Slip ring brushes generate fine carbon dust• Need for continuous air cooling + dust containment• Makeup air intake• Carbon filters vs makeup filters
Process Overview
ROLLING MILL – STAND HEAT EXCHANGERS
Airflow Study
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 170
100
200
300
400
500
600
700
800
Makeup Intake Flow Volume
Pre-Down Day Post-Down Day
Stand Motor #
Airfl
ow (C
FM)
* * * * * * * *++ ++ ++ ++
ROLLING MILL – STAND HEAT EXCHANGERS
Improvement:• Redesign intake plenums to take box filtersBenefit:• Consistency in design between all heat exchangers• Stops any debris from bypassing filter – increased life for box filters• Less time cutting and installing filters
Improvement:• Intake pre-filteringBenefits:• 95-99% of debris never reaches filter• Increased filter life• Very low maintenance• Very little reduction in flow
Improvement:• Connect exchanger intakes via manifoldBenefits: • Able to preclean with fewer equipment pieces – less maintenance cost
Design Considerations
ROLLING MILL – STAND HEAT EXCHANGERS
Estimate for current maintenance cost:
Estimate for improvement cost:
Cost-Benefit Analysis
ROLLING MILL – STAND HEAT EXCHANGERS
Example: For individual precleaner option, n=17
Break even equation:
Cost-Benefit Analysis
Estimate: if the new filters only need to be changed 2x per month, the improvements will pay for themselves within 8 months
To determine λ: Install test precleaner and monitor filter condition – awaiting delivery of precleaner
SHREDDER – INFEED CONVEYOR TRACKINGObjectives
• Design method to track the life cycle of infeed conveyor chains• Collect data for mean failure time of chains to inform PM replacement• Carry over tracking system to new infeed conveyor
SHREDDER – INFEED CONVEYOR TRACKING
Problems with current process:• No way to predict infeed chain failure• Infeed breaks are extremely costly (8hrs downtime minimum)• Unable to track PM chain replacement
• Risk of repeated work
Problem approaches:• Keep track of infeed chain life cycle
• Short-term: Monitor use since last replacement• Long-term: Construct failure distribution to determine service life
Problems to solve:• How to mark and organize chain sections for long-term tracking
• Previous attempts highlight durability as major issue• High attrition of infeed flights
• Need to construct process for tracking and replacement
Project Overview
SHREDDER – INFEED CONVEYOR TRACKING
Comparison of 2 proposed solutions:
Option 1: Manual tracking of plates welded to flightsAdvantages:• Lower initial cost• No extra equipment to maintain• Ability to track life-cycle of flights as well as chainsDisadvantages:• High flight attrition – frequent marker replacements• Training and documentation required for implementation
Option 2: RFID tracking of chains:Advantages:• Direct tracking of chain – no interference from flight attrition• No extra work needed during flight replacementDisadvantages:• Higher initial cost• Reliability of RFID reader
Solution Overview
Date Section # Motor Rev Conveyor Rev12/11/2008 2-3 98,870.50 1,267.6012/18/2008 3-4 110,000.00 1,360.00
SHREDDER – INFEED CONVEYOR TRACKING
• 100’ of chain (5 sections) being replaced during outage• Flights/chains are marked for temporary identification• Cable ties attached to chain – durability test• Mock-up of flight/chain replacement form for contractors• Marker plates TBD by LCS Metal
Future Work
SHREDDER – NFRS NO.1 COOLING FANObjectives
• Make the no. 1 cooling fan in the NFRS building easily accessible for maintenance
SHREDDER – NFRS NO.1 COOLING FAN
Cooling fans 3 – 5 PM’ed by manliftCooling fan 2 accessible from building interiorCooling fan 1 is neither accessible by manlift or platform• Inability to PM fan, primarily belt changes• No way to access for repair, even in emergency• Fan has been accessible by manlift in the past (had to get it wired
somehow), but added structures now block any way in
Need solution to minimize total cost of maintenance without sacrificing function
Overview
SHREDDER – NFRS NO.1 COOLING FAN
Drawing Synthesis
SHREDDER – NFRS NO.1 COOLING FAN
Designs + Revisions
SHREDDER – NFRS NO.1 COOLING FAN
Option 1: Reverse orientation of no.1 fan• Plan: Have PCI construct scaffold to unbolt fan, hoist out from exterior• Need to consider changes in center of mass• Possible adjustments needed to girt/purlin mounting/exhaust louvre
Option 2: Build hinged frame to allow fan to swing outside
Option 3: Make a vent!
Things to consider:• Value of fans to safety, comfort• Air circulation/displacement• Plans to add additional fans
Overview of Solutions
CSI/STOREROOM – NON-STOCK WIRE REELSObjectives
• Construct permanent outdoor storage space for non-stock electric wire reels
• Compact space to allow for additional storage
• Provide easy forklift access to wire reels
• Organize reels to allow for easy identification
CSI/STOREROOM – NON-STOCK WIRE REELS
Overview
0 10 20 30 40 50 600
5
10
15
20
25
30
35
40
45
33
40
3232323031
27
31
22
272830
20
24
20
26
30
2426282627
23
30
2627262527
12
19
27
20
24
20
26
151820
26
20
16
2421
16
212225
13
17
24
2018191718
24
1613151314131613121012
141616
22
13
20
14
1011101215121112
14131210
151210121112
78697
13
7581096
10
587
4
85
10878
Flange (in)
Wid
th (i
n)
• Inventory+sizing of all reels in storage area• Design for efficient storage
CSI/STOREROOM – NON-STOCK WIRE REELS
Rack Space Design• CCC is already underway fabricating pallet
rack• Reel rack frames assembled and ready for
installation
CSI/STOREROOM – NON-STOCK WIRE REELS
Problem: Unlevel ground and pipe encountered upon removal of wire pallets• Unable to assemble reel racks on uneven ground
Contact: Ruben Peña• Ready to pour 30’x30’ slag base as soon as work space is clear• Current situation: Waiting on availability from CCC to finish clearing space• Reel racks are ready to assemble and load once storage area is level
Current Situation
OPERATIONS – OFFICE REMODELObjectives
• Remodel Danny + Linda’s offices in Operations building
• Ensure quality work to customer spec, timely scheduling, and cost savings
OPERATIONS – OFFICE REMODEL
Major elements:• New desks, cabinets, window sills, countertops, etc.• Relocate Linda’s doorframe• Replace ¼” wall paneling with sheetrock• Sheet over ext. door and window in Danny’s office• New ceiling tiles, window glass, repaint ceiling grid• Electrical work: Boxes/panels to be moved, need to run HDMI across Danny’s office to install TV
Work plans:• Remodel contracted to Koehler const.• Electrical work contracted to IES (formerly planned in-house)• All components for work are ordered• Need to relocate Danny+Linda and remove wall paneling to prep for demo work
• Demo temporarily postponed due to emergency onsite work by Koehler, lack of manpower to relocate offices during outage (demo originally planned to begin 5/11)
Current Situation
MISC. PROJECTS AND MAINTENANCE SUPPORT
Small scope/break-in projects include:- Design of AC unit stand for reheat furnace- Shop drawings of Habitat door frame holder- Created torch patterns for break-in work e.g. 4-strand chute, entry funnel weldment, broken storm
drain, drain cover on FM464 property
MISC. PROJECTS AND MAINTENANCE SUPPORT
CAD Samples
CO-OP OVERVIEW – MAIN TAKEAWAYS
• Plan and execute improvements based on clear objectives that quantifiably connect with objectives of the business as a whole
• Knowledge management: Process knowledge, previous work, documentations, lessons learned• Balance planning and action• Balance research and investigation• Be nice to engineering!• Be even nicer to your planners!• Be even more nicer to operations!
THANK YOU!