Page 1
PROJECT REPORT
TATA MOTORS LTD.
LUCKNOW
TMPS Implementation through MOST,
LINE-BALANCING & ERGONOMICS
SIX-SIGMA Submitted by
Amandeep Singh Gujral
Roll No. – 401107006
Under the Guidance of
Mr. Satish Kumar Mr.HimanshuSamolia
Faculty Coordinator Manager, PSD Dept.
Thapar University Tata Motors, Lko.
Department of Mechanical Engineering
THAPAR UNIVERSITY, PATIALA
June 2104
Page 2
DECLARATION
I hereby declare that the project work entitled 1) MOST 2) Line-Balancing 3) Ergonomics
4) Six-Sigma is an authentic record of my own work carried out at TATA MOTORS,
LUCKNOW as requirements of six months project semester for the award of degree of B.E.
(Mechanical/Industrial Engineering), Thapar University, Patiala, under the guidance of Mr.
HIMANSHU SAMOLIA and Mr. SATISH KUMAR during January to June, 2014).
Amandeep Singh Gujral
401107006
Date: ___________________
Certified that the above statement made by the student is correct to the best of our knowledge
and belief
Mr. Satish Kumar Mr. Himanshu Samolia
Faculty Coordinator Manager, PSD
Thapar University Tata Motors Ltd.
Patiala Lucknow
Page 3
ACKNOWLEDGEMENT
Firstly I would thanks the Thapar University, Patiala for providing me with the
opportunity of six months industrial training ant TATA Motors, Lucknow. These six months
were very learning and gave me a lot of knowledge regarding how industries work in real
life.
I would also thank the H.R. department of TATA Motors for assigning me to
Productivity Service Department under Mr. Himanshu Samolia, a great mentor to work with.
He gave me numerous learning opportunities during my internship period.
I would also like to thank Mr. Rishikesh Vishkarma forgiving first hand exposure of
implementing Six Sigma approach for improving quality. He also arranged tow training
programs on quality for us which increased our knowledge on how to improve quality and
become lean.
I will also thank Mr. Satish Kumar for providing us right guidance during the training
period. At last, thanks to all others who supported me during this 6 months training period.
Page 4
CONTENT
1. Summary……………………………………………………………………... 1
2. TATA Motors-Industrial Profile………………………………………………
History………………………………………………………………..........
Mission, Vision and Values………………………………………………..
Subsidiaries and Joint-Ventures…………………………………………...
Product List………………………………………………………………..
2
2
4
6
8
3. TATA Motors-Lucknow……………………………………………………... 11
4. Productivity Service Department……………………………………………….
Overview…………………………………………………………………..
Roles and Responsibilities…………………………………………………
About TMPS………………………………………….................................
12
12
12
12
5.1Project-1 Introduction (M.O.S.T)………………………………………………
What is PMTS? ...........................................................................................
M.O.S.T……………………………………………………………………
Why M.O.S.T...............................................................................................
Basic M.O.S.T……………………………………………………………..
14
14
14
15
15
5.2Project-1 Description (M.O.S.T)……………………………………………….
Objective…………………………………………………………………..
Target……………………………………………………………………....
Process Flow Diagram……………………………………………………..
TCF Line-3………………………………………………………………...
Video Making……………………………………………………………...
Sequential Input of Data…………………………………………………...
Fitment Validation…………………………………………………………
Unique Fitment Identification…………………………………………......
Output……………………………………………………………………...
Learning……………………………………………………………………
18
18
18
18
19
21
21
24
25
26
28
6.1Project-2 Introduction (Line Balancing)………………………………………. 30
6.2Project-2 Description (Line Balancing)………………………………………..
Objective ………………………………………………………………….
30
30
Page 5
Target………………………………………………………………………
Process Flow Diagram……………………………………………………..
Steps to do Line Balancing………………………………………………...
Output……………………………………………………………………...
Learning……………………………………………………………………
30
31
32
33
33
7.1Project-3 Introduction (Ergonomic Improvement at CV-CX Store)…………...
What is Ergonomics? ...................................................................................
Why is Ergonomics Important…………………………………………….
Quick Exposure Check Sheet……………………………………………...
Gemba Analysis…………………………………………………………...
NIOSH Lifting Equation…………………………………………………..
RULA & REBA…………………………………………………………...
35
35
35
36
40
43
46
7.2Project-3 Description (Ergonomic Improvement at CV-CX Store)……………
Objective…………………………………………………………………..
Target………………………………………………………………………
Process Flow Diagram……………………………………………………..
Current Condition………………………………………………………….
Study of Workplace and Improvement……………………………………
Learning……………………………………………………………………
48
48
48
49
49
50
63
8.1Project-4 Introduction (Ergonomic improvement of Bumper and FUPD
Fitment)……………………………………………………………………………
Bumper Fitment……………………………………………………………
FUPD Fitment……………………………………………………………..
65
65
66
8.2Project-4 Description (Ergonomic improvement of Bumper and FUPD
Fitment)……………………………………………………………………………
Objective…………………………………………………………………..
Target………………………………………………………………………
Process Flow Diagram……………………………………………………..
Current Condition………………………………………………………….
Improvement………………………………………………………………
Learning……………………………………………………………………
67
67
67
68
68
72
74
Page 6
9.1Project-5 Introduction (Six Sigma project on Door Lock Push Button Hard)…
What is Six-Sigma…………………………………………………………
Key Concepts of Six-Sigma……………………………………………….
Benefits of Six-Sigma……………………………………………………..
76
76
76
77
9.2Project-5 Description (Six Sigma project on Door Lock Push Button Hard)….
Objective…………………………………………………………………..
Process Flow Diagram……………………………………………………..
Define Phase……………………………………………………………….
Measure and Analysis Phase………………………………………………
Improvement Phase………………………………………………………..
Learnings…………………………………………………………………..
77
77
78
78
83
97
99
10.1References……………………………………………………………………. 100
Page 7
LIST OF FIGURES
Figure 1 THE FIRST TATA MERCEDEZ COMMERCIAL TRUCK..................................... 2
Figure 2 Mission, Vision, Culture and Values of TATA Motor ................................................ 5
Figure 3 TATA Prima ................................................................................................................ 6
Figure 4 TATA Daewoo Bus ..................................................................................................... 6
Figure 5 JLR Logo ..................................................................................................................... 7
Figure 6 Tata Marcopolo Bus .................................................................................................... 7
Figure 7 Tata Zest ...................................................................................................................... 9
Figure 8 Tata Bolt ...................................................................................................................... 9
Figure 9 Tata LPK 2518 ............................................................................................................ 9
Figure 10 Tata LPT .................................................................................................................... 9
Figure 11 Tata Defense Vehicles ............................................................................................. 10
Figure 12 Tata Defense Vehicles ............................................................................................. 10
Figure 13 Process Flow Diagram of M.O.S.T Implementation on TCF Line-3 ...................... 19
Figure 14 Layout of TCF Line-3 ............................................................................................. 20
Figure 15 MOST CARD for general move.............................................................................. 21
Figure 16 MOST CARD for control move .............................................................................. 23
Figure 17 MOST CARD for tool use ....................................................................................... 24
Figure 18 sample validation sheet ............................................................................................ 25
Figure 19 Graph showing % VA, %NVAE and % NVAN of top SMH fitments ................... 27
Figure 20 Graph showing % VA, %NVAE and % NVAN of TCF Line-3 ............................. 28
Figure 21 Process Flow for line balancing .............................................................................. 31
Figure 22 Line balancing excel sample sheet .......................................................................... 32
Figure 23 Line balancing excel sample sheet .......................................................................... 32
Figure 24 Posture Analysis Check sheet .................................................................................. 38
Figure 25 QEC Score sheet ...................................................................................................... 39
Figure 26 QEC RYG criteria .................................................................................................. 40
Figure 27 Parameters of gemba analysis ................................................................................. 41
Figure 28 Gemba analysis check sheet .................................................................................... 42
Figure 29 Side and Top view showing how to measure distances for NIOSH Lifting Equation43
Figure 30 Showing asymmetry of 90 degrees.......................................................................... 44
Figure 31 RULA MSD Risk Level .......................................................................................... 46
Page 8
Figure 32 RULA Check Sheet ................................................................................................. 47
Figure 33 REBA MSD Risk Level .......................................................................................... 48
Figure 34 REBA Check Sheet ................................................................................................. 48
Figure 35 Process Flow of Kaizen Event on Ergonomics ....................................................... 49
Figure 36 Survey Results ......................................................................................................... 49
Figure 37 Summary of Survey ................................................................................................. 50
Figure 38 screen shot of posture analysis tab in DELMIA ...................................................... 51
Figure 39 sample ergonomic summary sheet........................................................................... 52
Figure 40 Data collection table for NIOSH ............................................................................. 53
Figure 41 Screen shot of Excel File for power steering gearbox-Pickup location .................. 54
Figure 42 Screen shot of Excel File for power steering gearbox-Placement location ............. 55
Figure 43 RULA & REBA Analysis done on lifting of power steering gearbox using DELMIA
.................................................................................................................................................. 56
Figure 44 Improvement of trolley to eliminate lifting ............................................................. 57
Figure 45 Screen shot of Excel File for Clutch Pressure Plate -Pickup location ..................... 58
Figure 46 Screen shot of Excel File for Clutch Pressure Plate -Placement location ............... 59
Figure 47 Improvement suggestions for power steering gear box ........................................... 59
Figure 48 Initial situation of store layout ................................................................................. 60
Figure 49 improved situation of store layout ........................................................................... 61
Figure 50 Original layout of rack area ..................................................................................... 62
Figure 51 Suggested layout of rack area .................................................................................. 62
Figure 52 Process mapping of bumper fitment ........................................................................ 66
Figure 53 Process mapping of FUPD fitment ......................................................................... 67
Figure 54 Process flow diagram of project-4 ........................................................................... 68
Figure 55 shows RULA analysis for bumper handling ........................................................... 70
Figure 56 shows RULA analysis for FUPD handling ............................................................. 71
Figure 57 option selected for bumper fitment.......................................................................... 73
Figure 58 option selected for FUPD fitment............................................................................ 74
Figure 59 Shows DMAIC Approach for 6 sigma project ........................................................ 78
Figure 60 Problem Definitions................................................................................................. 79
Figure 61 Box Plot showing current force levels..................................................................... 80
Page 9
Figure 65 Measurement device - push pull gauge (max. 50 kgf) ............................................ 84
Figure 66 door lock part description ........................................................................................ 86
Figure 67 67 Box plot of data collected in table 26 ................................................................. 87
Figure 68 Modified Fish-Bone Diagram.................................................................................. 88
Figure 69 drawing revealing the standard distance for location of holes ................................ 89
Figure 70 Shows basic statistical calculations of distance data in table 29 ............................. 90
Figure 71 Shows basic statistical calculations of difference data in table 29 .......................... 90
Figure 72 Box plot of data in table 29 ..................................................................................... 91
Figure 73 Box plot of data in table 29 ..................................................................................... 92
Figure 74 Histogram analysis of data in table 31 .................................................................... 94
Figure 75 3- points at which gap was measured ...................................................................... 95
Figure 76 Box Plot of data in table 32 ..................................................................................... 96
Figure 77 Email sent to BIW ................................................................................................... 98
Figure 78 Email sent to ERC ................................................................................................... 98
Figure 79 Present beading design ............................................................................................ 99
Figure 80 Suggested beading design........................................................................................ 99
Page 10
LIST OF TABLES
Table 1 Brief on TATA Motors ................................................................................................. 2
Table 2 Team members of project-1 ........................................................................................ 13
Table 3 M.O.S.T standard sheet for general move .................................................................. 16
Table 4 M.O.S.T standard sheet for control move ................................................................... 17
Table 5 M.O.S.T standard sheet for tool use-for fastening and loosing operations ................ 18
Table 6 Sample of fitment list of TCF Line-3 ......................................................................... 20
Table 7 Applicability matrix used to identify unique fitments. ............................................... 26
Table 8 SMH signoff sheet showing SHM of all models of TCF Line-3 ................................ 26
Table 9 Top SMH fitments of TCF Line-3 .............................................................................. 27
Table 10Team members of project-2 ....................................................................................... 29
Table 11 Output of Line Balancing ......................................................................................... 33
Table 12 Team Members of project 3 ...................................................................................... 34
Table 13 Summary of QEC of Workers working in CV-CX Store ......................................... 51
Table 14 NIOSH Result ........................................................................................................... 60
Table 15 Data showing effect of improvement on time and productivity ............................... 61
Table 16 Data showing effect of improvement on time and productivity ............................... 63
Table 17 Team members of project 4 ...................................................................................... 64
Table 18 showing details of bumper ........................................................................................ 65
Table 19 showing details of FUPD .......................................................................................... 66
Table 20 List of Parameters ..................................................................................................... 72
Table 21 Team members of project-5 ...................................................................................... 75
Table 22 Project charter ........................................................................................................... 78
Table 23 CTQ and CTP ........................................................................................................... 80
Table 24 4W-1H table .............................................................................................................. 81
Table 25 Process walkthrough observations Chart .................................................................. 83
Table 26 First Data Collection Plan ......................................................................................... 85
Table 27 result of first data collection plan ............................................................................. 86
Table 28 Second Data Collection Plan .................................................................................... 88
Table 29 Result of second data collection ............................................................................... 89
Table 30 Third data collection plan ......................................................................................... 92
Table 31 result of third data collection plan ............................................................................ 93
Page 11
Table 32 Forth data collection plan ......................................................................................... 94
Table 33 Result of forth data collection plan ........................................................................... 96
Table 34 summary of measurement and analysis phase .......................................................... 97
Table 35 Action plan for improvement .................................................................................... 97
Page 12
1
SUMMARY
Industrial Training is the most crucial part of technical studies, in which a student is
able to synchronize his/her technical knowledge with practical knowledge. Being a Third
year Industrial Engineering Student, I had already studied in detail how an Industry works. So
when I came to TATA motors Lucknow I was pretty confident that all that knowledge would
help me during my stay at TATA Motors. I was allotted Productivity Service Department
(PSD). The main responsibilities of the department are to measure, facilitate and improve the
productivity of the plant. The major tool used is Tata Motors Production System. I was
fortunate to be a part of all the major activities of the department and learned as much as I
could in 6 months period.
The major project allotted to me was TMPS implementation at TCF line -3. Under
this my first project was to measure work content of the TCF Line-3 using Maynard
Operation Sequence Technique (MOST). This helped me in understanding how the fitments
are performed on the line and helped me to differentiate between the value added, non-value
added essential and non-value added non-essential activities performed during fitment
process.
Second project was to do the line balancing of TCF Line-3 at different capacities and
to calculate the appropriate manpower needed for to run line at these capacities.
Third project was to perform ergonomic improvements in Line-1 CV-CX Store. The
objective of this project was to identify the main problematic areas and to improve them. We
used three different tools to evaluate the store, 1.Gemba Analysis Check sheet, 2.Quick
Exposure Check sheer and 3.NIOSH Lifting Equation.
Forth project was to perform ergonomic improvements in Bumper and FUPD Fitment
Process. The objective of this project was to reduce the fatigue in workers while carrying out
fitment process. Ergonomic tools used in this project were, 1.Gemba Analysis Check sheet,
2.Quick Exposure Check sheer and 3. RULA (Rapid Upper Limb Assessment) and REBA
(Rapid Entire Body Assessment) analysis.
Fifth project was a six-sigma project on “door lock push button hard”. The objective
was to use six-sigma methodology to reduce the push button force while opening the door.
We used DMAIC approach to solve the problem.
Page 13
2
TATA MOTORS-INDUSTRIAL PROFILE Table 1 Brief on TATA Motors
Type Public
Industry Automotive
Founded 1945 by J. R. D. Tata
Headquarters Mumbai, Maharashtra, India
Area served Worldwide
Key people
Cyrus Pallonji Mistry (Chairman)
Ravi Kant (Vice Chairman)
Gross Revenue INR 1, 88,818 crores (USD 34.7 billion)
Employees
Subsidiaries Jaguar Land Rover, Tata Daewoo, Tata Hispano
Website www.tatamotors.com
History:
TATA Motors Limited is India's largest automobile company, with consolidated
revenues of INR 1, 88,818 crores (USD 34.7 billion) in 2012-13. It is the leader in
commercial vehicles in each segment, and among the top in passenger vehicles with winning
products in the compact, midsize car and utility vehicle segments. It is also the world's fourth
largest truck and bus manufacturer. The TATA Motors Group's over 55,000 employees are
guided by the mission "to be passionate in anticipating and providing the best vehicles and
experiences that excite our customers globally."
Established in 1945 in
collaboration with Daimler –
Benz AG, West Germany
(Fig.1) TATA Motors'
presence cuts across the
length and breadth of India.
Over 7.5 million Tata
vehicles ply on Indian roads,
since the first rolled out in Figure 1 THE FIRST TATA MERCEDEZ COMMERCIAL TRUCK
Page 14
3
1954. The company's manufacturing base in India is spread across Jamshedpur (Jharkhand),
Pune (Maharashtra), Lucknow (Uttar Pradesh), Pantnagar (Uttarakhand), Sanand (Gujarat)
and Dharwad (Karnataka). Following a strategic alliance with Fiat in 2005, it has set up an
industrial joint venture with Fiat Group Automobiles at Ranjangaon (Maharashtra) to produce
both Fiat and Tata cars and Fiat powertrains. The company's dealership, sales, services and
spare parts network comprises over 3,500 touch points.
TATA Motors, also listed in the New York Stock Exchange (September 2004), has
emerged as an international automobile company. Through subsidiaries and associate
companies, TATA Motors has operations in the UK, South Korea, Thailand, Spain, South
Africa and Indonesia. Among them is Jaguar Land Rover, acquired in 2008. In 2004, it
acquired the Daewoo Commercial Vehicles Company, South Korea's second largest truck
maker. The rechristened Tata Daewoo Commercial Vehicles Company has launched several
new products in the Korean market, while also exporting these products to several
international markets. Today two-thirds of heavy commercial vehicle exports out of South
Korea are from Tata Daewoo. In 2005, TATA Motors acquired a 21% stake in Hispano
Carrocera, a reputed Spanish bus and coach manufacturer, and subsequently the remaining
stake in 2009. Hispano's presence is being expanded in other markets. In 2006, TATA Motors
formed a 51:49 joint venture with the Brazil-based, Marcopolo, a global leader in body-
building for buses and coaches to manufacture fully-built buses and coaches for India - their
plants are located in Dharwad and Lucknow. In 2006, TATA Motors entered into joint
venture with Thonburi Automotive Assembly Plant Company of Thailand to manufacture and
market the company's pickup vehicles in Thailand, and entered the market in 2008. TATA
Motors (SA) (Proprietary) Ltd., TATA Motors' joint venture with Tata Africa Holding (Pty)
Ltd. set up in 2011, has an assembly plant in Rosslyn, north of Pretoria. The plant can
assemble semi knocked down (SKD) kits, light, medium and heavy commercial vehicles
ranging from 4 tonnes to 50 tonnes.
TATA Motors is also expanding its international footprint, established through
exports since 1961. The company's commercial and passenger vehicles are already being
marketed in several countries in Europe, Africa, the Middle East, South East Asia, South
Asia, South America, CIS and Russia. It has franchisee/joint venture assembly operations in
Bangladesh, Ukraine, and Senegal.
The foundation of the company's growth over the last 67 years is a deep
understanding of economic stimuli and customer needs, and the ability to translate them into
Page 15
4
customer-desired offerings through leading edge R&D. With over 4,500 engineers, scientists
and technicians the company's Engineering Research Centre, established in 1966, has enabled
pioneering technologies and products. The company today has R&D centres in Pune,
Jamshedpur, Lucknow, Dharwad in India, and in South Korea, Spain, and the UK. It was
TATA Motors, which launched the first indigenously developed Light Commercial Vehicle
in 1986. In 2005, TATA Motors created a new segment by launching the Tata Ace, India's
first indigenously developed mini-truck. In 2009, the company launched its globally
benchmarked Prima range of trucks and in 2012 the Ultra range of international standard light
commercial vehicles. In their power, speed, carrying capacity, operating economy and trims,
they will introduce new benchmarks in India and match the best in the world in performance
at a lower life-cycle cost.
TATA Motors also introduced India's first Sports Utility Vehicle in 1991 and, in
1998, the Tata Indica, India's first fully indigenous passenger car. In January 2008, TATA
Motors unveiled its People's Car, the Tata Nano. The Tata Nano has been subsequently
launched, as planned, in India in March 2009, and subsequently in 2011 in Nepal and Sri
Lanka. A development, which signifies a first for the global automobile industry, the Nano
brings the joy of a car within the reach of thousands of families.
Mission, Vision and Values:
TATA Motors is equally focussed on environment-friendly technologies in emissions
and alternative fuels. It has developed electric and hybrid vehicles both for personal and
public transportation. It has also been implementing several environment-friendly
technologies in manufacturing processes, significantly enhancing resource conservation.
Through its subsidiaries, the company is engaged in engineering and automotive solutions,
automotive vehicle components manufacturing and supply chain activities, vehicle financing,
and machine tools and factory automation solutions.
Page 16
5
Figure 2 Mission, Vision, Culture and Values of TATA Motor
TATA Motors is committed to improving the quality of life of communities by
working on four thrust areas - employability, education, health and environment. The
activities touch the lives of more than a million citizens. The company's support on education
and employability is focused on youth and women. They range from schools to technical
education institutes to actual facilitation of income generation. In health, the company's
intervention is in both preventive and curative health care. The goal of environment
protection is achieved through tree plantation, conserving water and creating new water
bodies and, last but not the least, by introducing appropriate technologies in vehicles and
Page 17
6
operations for constantly enhancing environment care. With the foundation of its rich
heritage, TATA Motors today is etching a refulgent future.
Subsidiaries and Joint-Ventures
Tata Daewoo
In 2004, TATA Motors acquired Daewoo
Commercial Vehicle Company of South Korea.
The reasons behind the acquisition were:
1. Company's global plans to reduce domestic
exposure. The domestic commercial vehicle
market is highly cyclical in nature and prone
to fluctuations in the domestic economy. TATA Motors has a high domestic exposure of
~94% in the MHCV segment and ~84% in the light commercial vehicle (LCV) segment.
Since the domestic commercial vehicle sales of the company are at the mercy of the
structural economic factors, it is increasingly looking at the international markets. The
company plans to diversify into various markets across the world in both MHCV as well
as LCV segments.
2. To expand the product portfolio TATA Motors recently introduced the 25MT GVW Tata
Novus from Daewoo’s (South Korea) (TDCV) platform. Tata plans to leverage on the
strong presence of TDCV in the heavy-tonnage range and introduce products in India at
an appropriate time. This was mainly to cater to the international market and also to cater
to the domestic market where a major improvement in the Road infrastructure was done
through the National Highway Development Project.
Tata Daewoo is the second-largest heavy commercial vehicle manufacturer in South
Korea. TATA Motors has jointly
worked with Tata Daewoo to develop
trucks such as Novus and World
Truck and buses including GloBus
and StarBus. In 2012, Tata started
developing a new line to manufacture
competitive and fuel efficient
commercial vehicles to face the
competition posed by the entry of
Figure 3 TATA Prima
Figure 4 TATA Daewoo Bus
Page 18
7
international brands like Mercedes-Benz, Volvo and Navistar into the Indian market.
Tata Hispano
Tata Hispano Motors Carrocera, S.A. is a bus and coach cabin manufacturer based in
Zaragoza, Aragon, Spain and a wholly owned subsidiary of TATA Motors. Tata Hispano has
plants in Zaragoza, Spain and Casablanca, Morocco. TATA Motors first acquired a 21%
stake in Hispano Carrocera SA in 2005, and acquired the remaining 79% for an undisclosed
sum in 2009, making it a fully owned subsidiary, subsequently renamed Tata Hispano.
Jaguar Land Rover
Jaguar Land Rover PLC is a British premium automaker headquartered in Whitley,
Coventry, United Kingdom and has been a wholly owned subsidiary of TATA Motors since
June 2008, when it was acquired
from Ford Motor Company. Its
principal activity is the
development, manufacture and sale
of Jaguar luxury and sports cars
and Land Rover premium four
wheel drive vehicles. It also owns the currently dormant Daimler, Lanchester and Rover
brands.
Jaguar Land Rover has two design centres and three assembly plants in the UK. Under Tata
ownership, Jaguar Land Rover has launched new vehicles including the Range Rover
Evoque, Jaguar F-Type and the fourth-generation Range Rover.
Tata Marcopolo
Tata Marcopolo is a bus
manufacturing joint venture between
TATA Motors (51%) and the Brazil-
based Marcopolo S.A. (49%). The joint
venture manufactures and assembles
fully built buses and coaches targeted at
developing mass rapid transportation
systems. It utilises technology and
expertise in chassis and aggregates from TATA Motors, and know-how in processes and
systems for bodybuilding and bus body design from Marcopolo. Tata Marcopolo has
launched a low-floor city bus which is widely used by Chennai, Coimbatore, Delhi,
Figure 5 JLR Logo
Figure 6 Tata Marcopolo Bus
Page 19
8
Hyderabad, Mumbai, Lucknow, Pune, Kochi, Trivandrum and Bengaluru transport
corporations. Its manufacturing facility is based in Dharwad and Lucknow.
Fiat India Automobiles
TATA Motors also formed a joint venture with Fiat and gained access to Fiat’s diesel
engine technology. TATA Motors sells Fiat cars in India through a 50/50 joint venture Fiat
Automobiles India Limited, and is looking to extend its relationship with Fiat and Iveco to
other segments.
Telcon Construction Solutions
Telcon Construction Solutions is a joint venture between TATA Motors
and Hitachi which manufactures excavators and other construction equipment.
TATA Cummins
The Company entered into an agreement with Cummins Engine Company Inc. USA
for forming a 50% - 50% joint venture to produce fuel efficient engines with low-commission
characteristics for powering the Company's range of Medium/heavy vehicles. The Company
was incorporated in October 1993. Its factory established at Jamshedpur.
TATA Technologies
Tata Technologies Limited (TTL) provides engineering and design services to the
automotive industry. Tata Motors holds 86.91% of TTL’s share capital. TTL is based in Pune
(Hinjawadi) and operates in the United States and Europe through its wholly owned
subsidiaries in Detroit and London respectively. It also has a presence in Thailand. Tata
Technologies is a software service provider in the IT services and business process
outsourcing (BPO) space. Its global client list includes Ford, General Motors, Toyota and
Honda. TTL acquired the British engineering and design services company Incat
International Plc for INR4 billion in August 2005. Incat specialises in engineering and design
services and product lifecycle management in the international automotive, aerospace and
engineering markets.
Product List
Passenger Vehicles: -
Tata Sumo
Tata Sumo Grande
Tata Safari
Tata Indica
Tata Vista
Tata Magic
Tata Nano
Tata Xenon XT
Tata Aria
Tata Venture
Page 20
9
Tata Indigo
Tata Manza
Tata Winger
Figure 7 Tata Zest
Tata Iris
Tata Zest
Tata Bolt
Figure 8 Tata Bolt
Commercial Vehicles: -
Tata Ace
Tata Ace Zip
Tata Super Ace
Tata TL/Telcoline/207 DI Pickup
Truck
Tata 407 Ex and Ex2
Tata 709 Ex
Tata 809 Ex and Ex2
Tata 909 Ex and Ex2
Tata 1109 (Intermediate truck)
Tata 1512 (Medium bus chassis)
Tata 1612/1616 (Heavy bus chassis)
Tata 1618 (Semi Low Floor bus
chassis)
Tata 1623 (Low Floor bus chassis)
Tata 1518C (Medium truck)
Figure 9 Tata LPK 2518
Tata 1613/1615 (Medium truck)
Tata 2515/2516 (Medium truck)
Tata Starbus (Branded Buses)
Tata Divo (Hispano Divo)
Tata City Ride (12 – 20 seater)
Tata 3015 (Heavy truck)
Tata 3118 (Heavy truck) (8×2)
Tata 3516 (Heavy truck)
Tata 4018 (Heavy truck)
Tata 4923 (Ultra-Heavy truck) (6×4)
Tata Novus (Heavy truck)
Tata Prima (The World Truck)
Tata Prima LX
Tata Ultra (ICV Segment)
Figure 10 Tata LPT
Page 21
10
Military Vehicles: -
Tata LSV (Light Specialist Vehicle)
Tata Mine Protected Vehicle (4×4)
Tata 2 Stretcher Ambulance
Tata 407 Troop Carrier
Tata LPTA 713 TC (4×4)
Tata LPT 709 E
Tata SD 1015 TC (4×4)
Figure 11 Tata Defense Vehicles
Tata LPTA 1615 TC (4×4)
Tata LPTA 1621 TC (6×6)
Tata LPTA 1615 TC (4×2)
Tata Winger Passenger Mini Bus
Tata Land Rover 1515 F
Tata Sumo 4*4
Figure 12 Tata Defense Vehicles
Page 22
11
TATA MOTORS-LUCKNOW
Tata Motors Lucknow (TML-Lucknow) is an important production facility of Tata
Motors Limited, which was established in 1992 to meet the growing demand for Commercial
Vehicles in the Indian market. The state of art plant is strongly backed up by an Engineering
Research Centre (ERC) & Service set-up to support with latest technology & cater to the
complexities of automobile manufacturing. Fully Built Vehicle business (FBV), which is one
of the fast growing areas of business, is also head quartered here. This plant rolls out
commercial vehicles & is specialized in the designing & manufacturing of a range of modern
buses which includes Low-floor, Semi Low-floor, and High Deck & CNG Buses. Lucknow
plant also specializes in integral bus manufacturing & has recently commissioned JV
Company, Tata Marcopolo Motors Ltd. in the premises
The major facilities at the plant comprise of:
Vehicle Factory - Assembly Plant for Trucks and Bus Chassis
Integral Bus Factory - Assembly Plant for Module Buses catering to the needs of
Tata Marcopolo Motors Limited and FBV operations
Transmission Factory - Gear Parts, Crown wheel & Pinion and Heat Treatment
facility
Production Engineering Shop catering to the tool design and manufacturing needs
A well-established Training Centre through which around 500 apprentices are trained
in various trades.
Engineering Research Centre with specific focus on buses, including a Digital
prototyping lab, use of PLM software etc.
Service Training Centre providing training to drivers and technicians of the STU's.
RECON Factory (for Reconditioning Business)
The satellite plant of TMML which caters to the Hi-end buses for the Northern
Market.
State of the art facilities like the Paint Shop, BIW Shop and the TCF factory with
automated lines have been benchmarked with the best in the world.
Page 23
12
PRPDUCTIVITY SERVICE DEPARTMENT (P.S.D)
Overview
The PSD or Productivity Service Department is one of the very important
departments in TATA MOTORS, Lucknow. This department is part of HR and is
headed by Er. Himanshu Samolia. This department is involved in two primary
tasks (1.) Work Study and manpower planning (2.) Ergonomics. This department
comprises of three Managers, 3 FTC (Fixed Term Contracts) and 3 DET
(Diploma Engineer Trainees).
Roles and Responsibilities
1. Measurement and monitoring of productivity.
2. Work system design, assessment and human resource requirement.
3. Custodianship for overall nos. For all types of personnel in the establishment (permanent,
temporary, trainees, job trainees, apprentices)
4. Measures and monitor productivity of plant, cascading of targets and facilitate
achievements of targets.
5. Based on strategy and organization structure define organizational process, systems, work
flow for attaining of plant’s objectives.
6. Based on the above defined work content and role of each position.
7. Study area wise resource requirement in line with productivity targets and work
assessment.
8. Define optimal category under with the person may be hired (contractual, temporary,
permanent, trainee)
9. Recommendation of manpower numbers along with the skill and competency requirement
for management approval.
About TMPS
TMPS stands for TATA MOTORS PRODUCTION SYSTEM, designed by
PSD department focused on increasing the productivity and good ergo nomics of
Tata Motors assembly line. It focused on calculating the SMH of all vehicles
using M.O.S.T and evaluates ergonomics of every fitment process through
Gemba analysis and Quick Exposure Check Sheet.
Page 24
13
PROJECT-1
M.O.S.T Implementation at TCF Line-3
Table 2 Team members of project-1
Team Members
1. Ashish Sinha P.S.D Team Leader
2. Lavkesh TCF Line-3 Team Member
3. Amandeep Singh Gujral P.S.D Team Member
4. Pardeep Kumar Yadav P.S.D Team Member
`
Page 25
14
INTRODUCTION
What is PMTS?
Predetermined motion time systems (PMTS) are work measurement systems based on
the analysis of work into basic human movements, classified according to the nature of each
movement and the conditions under which it is made. Each basic human movement has a
standard time and these standard times are summed to obtain standard time for a job or task.
M.O.S.T
MOST is an acronym for Maynard Operation Sequence Technique developed by
Developed by Zandin in 1970’s is a revolutionary PMTS. MOST is an activity based work
measurement system that enables you to calculate the length of time required to perform a
task i.e. a system to measure work
This technique is based on fundamental statistical principals and basic work
measurement data compiled over many years. MOST concentrates on movement of objects. It
was noticed that the movement of objects follow certain consistently repeating patterns, such
as reach, grasp, move & position of object. These patterns were identified and arranged as a
sequence events followed in moving an object. This concept provides the basis for the MOST
Sequence models. MOST makes the assumption that to move an object, a standard sequence
of events occurs.
There are four versions of M.O.S.T:
Basic M.O.S.T - General operations
Mini M.O.S.T - Repetitive operations
Maxi M.O.S.T - Non-Repetitive operations
Admin M.O.S.T - Clerical Operations
In M.O.S.T, the time is measured in TMU (Time Measurement Unit)
1 TMU = 0.00001 hour
1 TMU = 0.0006 minute
1 TMU = 0.036 second
1 hour = 100,000 TMU
1 minute = 1,667 TMU
1 second = 27.8 TMU
Page 26
15
Why M.O.S.T?
In MTM, the elements are stand alone and do not relate to the sequence of the
operation where as in M.O.S.T, the compete sequence of the operation, which consists
of smaller elements, is address.
It is much faster than traditional time study technique (e.g. Basic MOST is 40 times
faster than MTM-1)
Accuracy of up to 95% can be obtained
Less Documentation
Basic M.O.S.T
Basic M.O.S.T is used for operations that are likely to be performed more than 150 times but
less than 1500 times per week. In TATA Motors, Basic M.O.S.T is used to calculate time
standard for various fitments.
There are 3 sequence models in Basic M.O.S.T which are used to define any activity.
1. General Move Sequence:
2. Control Move Sequence: It describes the manual displacement of an object over a
“controlled” path
3. Tool Use Sequence
General Move Sequence:
This sequence model is used when an object is moved freely through space from one
location to the next (e.g., picking something up from the floor and placing it on a table).
Roughly 50% of all manual work occurs as a General Move. Figure: 3 explain how to assign
index to each sequence.
Phase Get Put Return
Parameter A, B, G A, B, P A
“A” Action Distance (mainly horizontal)
“B” Body Motion (mainly vertical)
“G” Gain Control
“P” Placement
Page 27
16
Table 3 M.O.S.T standard sheet for general move
Control Move Sequence:
It describes the movement of object over a controlled path. This sequence model is
used when an object is moved while it remains in contact with a surface (e.g., sliding the
object along the surface) or the object is attached to some other object during its movement
(e.g., moving a lever on a machine). Figure: 4 explains how to assign index to each sequence.
Phase Get Control Return
Parameter A, B, G M, X, I A
“A” Action Distance (mainly horizontal)
“B” Body Motion (mainly vertical)
“G” Gain Control
“P” Placement
“M” Move Controlled
“X” Process Times
“I” Align
Page 28
17
Table 4 M.O.S.T standard sheet for control move
Tool Use Sequence:
This sequence model applies to the use of a hand tool (e.g., a hammer). The Tool Use
Sequence is a combination of the General Move and Controlled Move activities. Tools not
listed in the tables that are similar to a tool in the table can use their time values for analysis.
Figure: 5 explains how to assign index to each sequence.
Phase Get Put Tool Use Put Return
Parameter A, B, G A, B, P T* A, B, P A
T* F, L, C, S, M, R, T
“F” Fasten
“L” Loosen
“C” Cut
“S” Surface Treat
“M” Measure
“R” Record
Page 29
18
“T” Think
DESCRIPTION
Objective:
To calculate the work Content and cycle time of all the fitments of TCF Line-3
To identify the Value added, Non-value added essential and Non-value added non-
essential activities performed during fitment Process.
Target:
To do the M.O.S.T study of the following models of TCF Line-3:
LPS 3518
LPK 2518
LPT 2518-62 Wheel Base
LPT 2518-48 Wheel Base
Process Flow Diagram:
Figure: 6 show the process flow diagram of M.O.S.T implementation process on TCF
Line-3. The process starts with getting the fitment list from the shop owner, then make video
Table 5 M.O.S.T standard sheet for tool use-for fastening and loosing operations
Page 30
19
of each fitment followed by sequential input of data (obtained from video) in most using DE
and getting the data validated for each fitment.
Figure 13 Process Flow Diagram of M.O.S.T Implementation on TCF Line-3
TCF Line-3
TCF line – 3 consists of 30 stations. These 30 stations are divided into 3 zones i.e.
Zone -1, Zone – 2 and Zone – 3 consisting of 10 stations each. After roll out from the 30th
station, it enters R1 and R2 area where inspection and testing is done. There are 2 major Sub
branches of Line –3 i.e. Engine sub assembly line and TRIM – 3. In this project we focused
on Main TCF line –3 and Engine sub assembly Line. In totality we covered around 300
fitments.
Page 31
20
Figure 14 Layout of TCF Line-3
Table 6 Sample of fitment list of TCF Line-3
1 Sub Assy. S/A OF SILENCER HANGER BKT.
2 Sub Assy. S/A OF LOAD SENCING VALVE
3 Sub Assy. S/A OF DDU
4 Sub Assy. S/A OF TRAILER CONTROL VALVE
5 Sub Assy. S/A OF SOCK ABZ. LENGTH CONVERSION
6 Sub Assy. S/A OF MODULATOR VALVE
7 Sub Assy. S/A OF A.R.B. MTG. BKT.
8 Sub Assy. S/A of propeller shaft
9 Station 01 AC Head Pipe Clamping
10 Station 01 fuel pipeline conn. With fuel filter
11 Station 01 Fuel line + Fuel Micro filter Bkt. Fitment
12 Station 01 Chassis Number Punching
13 Station 02 Front Shock Absorber Mtg. Bkt. Fitment LH/RH
14 Station 03 Anti Roll Bar Mtg. Bkt. Fitment LH/RH
15 Station 03 Power Steering Pipe Mtg. 'L' & 'Z' Bkt. Fitment
16 Station 04 AC Head Pipe Connection with DDU
17 Station 04 Bumper Mtg. Bkt. Fitment LH/RH
18 Station 04 FUPD Mtg. Bkt. Fitment LH/RH
19 Station 04 Bump stopper fitment
20 Station 04 FUPD Fitment on Long Member LH/RH
21 Station 05 Rear Shackle Fitment LH/RH
22 Station 05 Leaf Spring Fitment With Rear Live Axle LH/RH
23 Station 05 Leaf Spring Fitment With tendom Axle LH/RH
24 Station 06 Front Shackle Fitment LH/RH
25 Station 06 purge tank fitment
26 Station 06 Leaf Spring Fitment with Front Axle LH/RH
27 Station 06 RADIATOR MTG. BKT FITMENT LH/RH
28 Station 06 KITTING TROLLY INGAGEMENT
Page 32
21
29 Station 06 tail lamp fitment
30 Station 06 reverse horn fitment
31 Station 06 PTO pump fitment
32 Station 06 Ist Air Tank Fitment
41 Station 07 Rear Live Axle Dropping
Video Making:
After getting the fitment list (see table: 1) from the shop owner, the task of video
making starts. In this step, videos of all fitments performed on TCF Line-3 and Engine sub-
assembly line are prepared. The important points to be kept in mind while making video is
capture all the body motions of the worker. Any motion missed in video will generate wrong
results. Here is the list of all the fitments.
Sequential Input of Data:
Break down each fitment into activities and input these activities in the MOST CARD
(Fig.: 8, 9, 10) in delmia in the sequence which occur.
Figure 15 MOST CARD for general move
Page 33
22
1. After the MOST CARD is launched, the general move tab is selected by default.
Watch the video and enter the description of activity in the description area e.g. move
5-7 steps, bend and arise 50% occ.,grasp light object, move 5-7 steps, place the object
with adjustment. (description area is highlighted by red box in fig.: 8)
2. After entering the description, click on the parameter tab (highlighted by blue box in
fig.: 8) and select the index against the appropriate description (highlighted by orange
box in fig.: 8). If a parameter is repeated in performing an activity, increase the partial
frequency of that activity.
3. Looking at the video gather information whether the activity is performed online or
offline. If the activity is performed offline, click on the check box (highlighted by
green box in fig.: 8)
4. Gather further information on how many workers are performing the activity. E.g.
lifting and placing of bumper is done by two workers. In this case increase the
manpower to two in the box (highlighted by purple box in fig.: 8)
5. If the activity is repeated more than once during the fitment process, increase the
global frequency of the activity (highlighted in pink box in fig.: 8)
6. Decide whether the activity is value adding, essential non-value adding and non-
essential non-value adding from the drop down list (highlighted by brown box in fig.:
8)
Page 34
23
Figure 16 MOST CARD for control move
Page 35
24
Figure 17 MOST CARD for tool use
Fitment Validation
After M.O.S.T of the activities is done, the fitments validation sheet (fig.: 11)
generated by the delmia is shown to the shop owner for cross checking and rectification. The
sheet shows the activity wise break up of each fitment, global frequency of the activity,
manpower involved in performing activity and whether activity is performed on-line or off-
line.
Shop owners study each activity and if all are right, he approves it.
Page 36
25
Unique Fitment Identification
Unique fitments are those fitments which are unique to a model. By identifying
unique fitments, we will do M.O.S.T of only those fitments to reach our target of doing
M.O.S.T study of all fitments of all models assembled at TCF Line-3.
We construct an applicability matrix for every line to identify unique fitments of
every model as shown in following table:
Figure 18 sample validation sheet
Page 37
26
Table 7 Applicability matrix used to identify unique fitments.
In total we have to do M.O.S.T of 61 unique fitments to complete our M.O.S.T study
on LKP 2518 and LPT 2518 models. After finding out the unique fitment, the process of
M.O.S.T starts again, this time we need to validate only unique fitments.
Output
The following figure shows the outcome of M.O.S.T:
1. SMH of all Models
Table 8 SMH signoff sheet showing SHM of all models of TCF Line-3
2. The following table and figures show % value adding, %non-value adding
(essential) and %non-value adding (non-essential) work in fitment process
of top SMH fitments and the whole TCF Line-3.
TCF Line-3 WC
20802432000R
20802632000R
21673638000R 21670838000R 50300262000R
50302548000R
50301348000R
50301948000R
20802632000R
LPS 3518 32 TC
Ride & Comfort
Cabin
LPK 2518 38 TC
BS III CAB ERGO
W/O LB SRT
LPK 2518 38 TC
BS III CAB SRT
ERGO PACK With
LB
LPT 2518 62 TC BS
III COWL ERGO
PACK
LPT 2518 48 TC
BS III NOSE UP
ERGO
No. of
unique
fitments
A B C D E
1 Trolley Adjustment √ √ 1
2 Nylon Pipe Routing LPT √ √ √ √ 2
3 Nylon Pipe Clamping LPT √ √ √ √ 2
4 Wiring Harness Routing LPT √ √ √ √ 2
5 Wiring Harness Clamping LPT √ √ √ √ 2
6Brake Pipe Connection with Modulator Valve
(LPS) or Relay ( LPK & LPT) LH/RH√ √ √ √
1
7 Silencer Mtg. Bkt. Fitment LPT √ √ 1
8 Leaf Spring Fitment With tendom Axle LH/RH √ √ √ √ 1
9 purge air tank fitment √ √ √ √ 1
10 bump stopper Bkt. √ √ 1
11 Bump stopper fitment √ √ 1
12 Link rod fitment LH/RH √ √ √ √ 1
13 Fuel line + Fuel Micro filter Bkt. Fitment LPT √ √ 1
14 grease nipple fitment √ √ √ √ 1
15 wedge screw fitment √ √ √ √ 1
16 axle loading √ √ √ √ 1
17 dead/tendom axle dropping √ √ √ √ 1
18 dead/tendom axle U-Bolt loose fitment √ √ √ √ 1
19 dead/tendom axle U-Bolt tightning √ √ √ √ 1
V. C.
NUMB
ER -
Page 38
27
Table 9 Top SMH fitments of TCF Line-3
Figure 19 Graph showing % VA, %NVAE and % NVAN of top SMH fitments
Fitment MP SMM VA NVAE NVANNVAE+NV
AN%va
1 WIRING HARNESS ROUTING & CLAMPING 2 8.6 0.92 3.17 4.50 7.7 11%
2 MODULATOR VALVE FITMENT & CONNECTION 1 12.5 3.26 4.57 4.63 9.2 26%
3 AIR TANK MTG BKT 2 10.5 3.97 1.73 4.79 6.5 38%
4 FUPD BKT FITMENT 2 8.6 3.76 0.53 4.36 4.9 43%
5 FUPD FITMENT 2 11.0 3.15 4.54 3.33 7.9 29%
6 LEAF SPRING FITMENT FOR LIVE AXLE 2 16.5 6.50 3.46 6.56 10.0 39%
7 LEAF SPRING FITMENT FOR FRONT AXLE 2 15.1 5.37 6.75 2.96 9.7 36%
8 GREASE NIPPLE & WEDGE SCREW FITMENT 1 14.1 4.63 2.40 7.08 9.5 33%
9 FRONT AXLE FITMENT 2 11.9 0.73 9.73 1.43 11.2 6%
10 REAR AXLE FITMENT 3 18.8 3.55 9.84 5.39 15.2 19%
11 ANTI ROLL BAR SUB-ASSY 2 12.1 2.35 4.82 4.97 9.8 19%
12 PROPELLER SHAFT FITMENT 2 9.5 4.15 2.31 3.07 5.4 44%
13 break pipe connection with live axle( t joint & Break actuator ) 2 9.3 2.51 1.40 5.35 6.8 27%
14 INVERSION 2 9.0 1.30 4.34 3.31 7.7 15%
15 POWER STEERING GEAR BOX FITMENT ON FRAME 2 10.5 5.91 1.61 3.02 4.6 56%
16 SILENCER FITMENT 2 14.1 3.31 6.42 4.36 10.8 23%
17 BATTERY FITMENT 2 10.8 3.24 4.82 2.70 7.5 30%
18 SPARE WHEEL FITMENT Potential 2 8.7 6.67 1.85 0.17 2.0 77%
19 AIR LEAKAGE TESTING 1 10.7 0.82 2.04 7.84 9.9 8%
20 FRAME DROPPING 1 12.7 1.17 5.82 5.68 11.5 9%
Total SMM 234.9 67.3 82.2 85.5 167.6 29%
Total SMH 3.9 1.1 1.4 1.4 2.8Manpow
er37.0
TCF line 3 917.7 313.2 264.8 339.7 604.5 34%
15.3 5.2 4.4 5.7 10.1
Top SMH Fitment TCF 3
VA, 67.28, 29%
NVAE, 82.158, 35%
NVAN, 85.48666667, 36%
Top SMH Fitment TCF3
VA
NVAE
NVAN
Page 39
28
Figure 20 Graph showing % VA, %NVAE and % NVAN of TCF Line-3
Learnings
Learned how to implement M.O.S.T and how it is better than other PMTS.
Learned why PMTS are better than conventional time study
Learned how the assembly of various parts is done on line
Learned to differentiate between values added, non-value added (essential) and non-
value added (non-essential) activities.
This project involve lot of data gathering from other departments which helped in
development of my communication skills
How to use DELMIA Process Engineering-M.O.S.T Module.
VA, 313.19, 34%
NVAE, 264.77, 29%
NVAN, 339.7, 37%
TOTAL FITMENT OF TCF 3
VA
NVAE
NVAN
Page 40
29
PROJECT-2
Line Balancing of TCF Line-3
Table 10Team members of project-2
Team Members
1. Ashish Sinha P.S.D Team Leader
2. Lavkesh TCF Line-3 Team Member
3. Ravi Chaudhari P.S.D Team Member
4. Amandeep Singh Gujral P.S.D Team Member
Page 41
30
INTRODUCTION
Assembly line balancing can be defined as the process of optimizing an assembly line
with regard to certain factors. Configuring an assembly line is a complicated process, and
optimizing that system is an important part of many manufacturing business models.
Maintaining and operating one is often quite costly, as well. The main focus of balancing is
usually to optimize existing or planned assembly lines to minimize costs and maximize gains.
For instance, a car company might want to alter its assembly line layout in order to
speed production. The company might consider the number of work stations a manufactured
item must pass before it is complete and the time required at each point. Of course, each stage
of this process requires a certain length of time, and the allotted time to finish a process, the
number of workers, or the resource demand may also be considered, based on the specific
manufacturing requirements.
The possible results of an assembly line balancing process might be maximized
efficiency, minimized time to finish a process, or minimized number of work stations
necessary within a certain time frame. Each manufacturing process might be quite different
from another, so a company balancing unique workloads must work within the constraints
and restrictions affecting its specific assembly line
DESCRIPTION
Objective:
1. To do Line Balancing of TCF Line-3 at various capacities:-
60 vehicles/shift
55 vehicles/shift
50 vehicles/shift
45 vehicles/shift
40 vehicles/shift
30 vehicles/shift
2. To report balanced manpower needed to run TCF Line-3
Target
To balance the line-3 at maximum efficiency
Page 42
31
Process Flow Diagram:
Figure 21 Process Flow for line balancing
The inputs for line balancing are:
• Takt Time of Line
• Work Content of each fitment
• Cycle Time of each fitment
• Precedence Diagram
• Data regarding which fitment is performed at which station.
• Duration of the Shift.
After gathering the inputs, a standard sheet for line balancing is used. After the line
balancing is done, it is send to the shop owner for validation. In case of any discrepancies, the
inputs are verified and the balancing is done again. Once the balancing is validated, a trial run
is done on the basis of calculated balanced manpower. During this process, adjustments are
made in case of occurrence of variation.
Following is the screen shot of line balancing sheet. At the LHS of the sheet are the tables
in which we input data and do calculations and at the RHS side of the sheet there are station
wise LOAD CHART, which shows how much load is on each worker of the station and at
what engagement he is balanced.
Page 43
32
Figure 22 Line balancing excel sample sheet
Steps to do Line Balancing
Figure 23 Line balancing excel sample sheet
1. Enter the takt time in the cell highlighted green and volume in cell highlighted red.
2. Enter the name of the fitments in the column highlighted black and their
corresponding in column highlighted orange in ascending order starting from “0”.
3. Enter the cycle time in column highlighted in yellow, work content in column
highlighted in pink, included manpower in column highlighted in brown. The
included manpower is ideally “one” but in case there is difference between cycle time
and work content, it is “two”. The column next to the included manpower, calculates
the theoretical manpower (=work content/takt time). The sum of theoretical
Tata Motors, Lucknow
DOCUMENT
QWNER -
PSD
Department T.Time 7.3
Direct
Manpower
28463256000R DATE - 5-Jun-14 Vol- 60 60
Station Fitment NameCycle Time
(MIN)
Work
Content
(MIN)
Worker
include
(MAN)
Thr MP Bal MP MPWork
content% Eng
S/A OF SILENCER HANGER BKT. 3.2 3.2 1 0.44 A A 6.6 90%
S/A OF LOAD SENCING VALVE 1 0.00 A B 3.0 41%
S/A OF DDU 1 0.00 A 0%
S/A OF TRAILER CONTROL VALVE 1 0.00 A 0%
S/A OF SOCK ABZ. LENGTH CONVERSION 1.4 1.4 1 0.19 B 0%
S/A OF MODULATOR VALVE 3.4 3.5 1 0.48 B 0%
S/A OF A.R.B. MTG. BKT. 1.6 1.6 1 0.21 B 0%
Trolley Adjustment 1 0.00 xx 4.03 55%
Frame Dropping 5.1 6.9 2 0.94 A,B A 7.0 96%
Nylon Pipe Routing&clamping 15.5 15.5 1 2.12 C,D,W B 5.9 81%
Wiring Harness Routing&clamping 16.3 16.3 1 2.23 E,F,W C 7.3 100%
purge tank fitment 3.0 3.0 1 0.41 W D 7.3 100%
Air Dryer 4.0 4.0 0.55 W 5.5 75%
Air Tank Mtg. Bkt. Fitment LH/RH 10.5 10.5 1 1.43 G,H E 7.3 100%
Brake Pipe Connection with Modulator Valve LH/RH 3.1 3.1 1 0.43 F 7.3 100%
Breather Mtg. Bkt. S/A fitment 1.9 1.9 1 0.26 A G 7.3 100%
Link Rod Fitment 7.8 12.2 1.66 I,J H 7.1 97%
axle ( bump )stopper mtg. bkt.( with socker mtg bkt ) 4.2 4.2 1 0.57 B I 6.1 83%
Silencer Mtg. Bkt. Fitment 4.0 4.0 1 0.54 H J 6.1 83%
Fuel Line Mtg. 'I' & 'Z' Bkt. Fitment&AC head pipe mtg 4.1 4.1 1 0.56 X K 4.5 62%AC Head Pipe Connection with AC Pipe
Joint&clamping4.6 4.5 1 0.62 K X 7.3 99%
V. C.
NUMBER -
Sta
tio
n 0
Sta
tio
n 1
.0
FITMENT SUMMARY SHEET
PLANT - ASSY. LINE -
TCF 3 ECMODEL
NAME -LPK 2518
PSDPSD
Page 44
33
manpower of each station gives idea oh about how many workers should be allotted to
each station.
4. Colour the rows according to the station as shown in above figure, station 0-Pink
colour, station 1-Blue colour and so on. Now let’s focus on single station.
5. Let’s say worker “a” works at station-0. Now allot worker “a” fitment’s of station
zero till the sum of work content of fitments he is performing is nearly equal to takt
time. After that add another worker “b” and start allotting him fitments the same way.
This process continues till all the fitments of a particular station are completed. This is
done in column highlighted in purple.
6. In the column next to the column highlighted in purple, list the works allotted to each
station and in the next column highlighted in blue add the time for which that worker
is engaged and the next adjacent column gives us the % engagement of that worker.
7. After all this done, the LOAD CHART is automatically created.
8. In the manpower calculated, we add 8 workers for WCQ and 2 workers for office
work and 10% absentees.
Output
The following table shows the how much manpower is allotted to TCF Line-3 at
different volumes:
Table 11 Output of Line Balancing
Volume Manpower-Time
Study
Manpower-M.O.S.T Difference
30 vehicles/shift 124 114 10
40 vehicles/shift 143 135 8
45 vehicles/shift 173 166 8
50 vehicles/shift 188 180 8
55 vehicles/shift 198 198 0
60 vehicles/shift 204 198 6
Learning
How to do Line Balancing, Load Chart, and how to calculate efficiency of line.
How to work in excel like applying formulas, etc.
This project involve lot of data gathering from other departments which helped in
development of my communication skills
Page 45
34
PROJECT-3
Ergonomic Improvements at CV-CX Store
Table 12 Team Members of project 3
Team Members
Mr. Ashish Sinha PSD Leader
Mr. Deepak Sen Gupta CX-CV Chassis Co-leader
Mr. Ravindra Kumar TCF Assy Line-2 Member
Mr. Gaurav Agarwal TATA Tech. Member
Mr. Aamadeep Singh IT Member
Mr. Aakash Kochhar IT Member
Mr. Ravi Chaudhari PSD Member
Mr. Prasoon Mishra Lean Mfg. KPO* Coordinator
Page 46
35
INTRODUCTION
What is ergonomics?
Ergonomics can be defined simply as the study of work. More specifically,
ergonomics is the science of designing the job to fit the worker, rather than physically forcing
the worker’s body to fit the job.
Adapting tasks, work stations, tools, and equipment to fit the worker can help reduce
physical stress on a worker’s body and eliminate many potentially serious, disabling work
related musculoskeletal disorders (MSDs).
Why is ergonomics important?
Industries increasingly require higher production rates and advances in technology to
remain competitive and stay in business. As a result, jobs today can involve:
Frequent lifting, carrying, and pushing or pulling loads without help from other
workers or devices
Increasing specialization that requires the worker to perform only one function or
movement for a long period of time or day after day
Working more than 8 hours a day
Working at a quicker pace of work, such as faster assembly line speeds
Having tighter grips when using tools.
These factors—especially if coupled with poor machine design, tool, and workplace
design or the use of improper tools—create physical stress on workers’ bodies, which can
lead to injury.
If work tasks and equipment do not include ergonomic principles in their design, workers
may have exposure to undue physical stress, strain, and overexertion, including vibration,
awkward postures, forceful exertions, repetitive motion, and heavy lifting.
Recognizing ergonomic risk factors in the workplace is an essential first step in
correcting hazards and improving worker protection. Ergonomists, industrial engineers,
occupational safety and health professionals, and other trained individuals believe that
reducing physical stress in the workplace could eliminate up to half of the serious injuries
each year.
Page 47
36
The International Ergonomics Association (IEA) divides ergonomics broadly into
three domains:
Physical ergonomics - is concerned with human anatomical, anthropometric,
physiological and biomechanical characteristics as they relate to physical activity.
(Relevant topics include working postures, materials handling, repetitive movements,
work related musculoskeletal disorders, workplace layout, safety and health.)
Cognitive ergonomics - is concerned with mental processes, such as perception,
memory, reasoning, and motor response, as they affect interactions among humans
and other elements of a system.
Organizational ergonomics - is concerned with the optimization of socio technical
systems, including their organizational structures, policies, and processes.(Relevant
topics include communication, crew resource management, work design, design of
working times, teamwork, participatory design, community ergonomics, cooperative
work, new work paradigms, virtual organizations, and quality management).
Quick Exposure Check Sheet
The Quick Exposure Check (QEC) was developed to enable health and safety
practitioners to undertake assessments of the exposure of workers to musculoskeletal risk
factors (Li and Buckle, 1999). QEC focuses on exposure assessment and change in exposure,
thus allowing the benefits of workplace interventions to be assessed rapidly.
QEC has been designed to
Assess the change in exposure to musculoskeletal risk factors before and after an
ergonomics intervention,
Involve both the practitioner (observer) and the workers (who have direct experience
of performing the job) in conducting the assessment and identifying the possibilities
for change,
Encourage the improvement of workplaces and allow consideration of the
comparative impact and potential cost benefits of a number of alternative
interventions,
Educate managers, engineers, designers, health and safety practitioners and other end
users about the musculoskeletal risk factors in the workplace,
Compare exposures between two or more workers performing the same task, or
between people performing different tasks,
Page 48
37
Focus on exposure assessment and change in exposure, thus allowing benefits of
workplace interventions to be assessed rapidly.
QEC (Fig.: 14 and 15) includes the assessment of the back, shoulder/upper arm,
wrist/hand, and neck, with respect to their posture and repetitive movement. Information
about task duration, maximum weight handled, hand force exertion, exposure to vibration, the
visual demands of the task and subjective responses to the work is obtained from the worker.
The magnitude of each assessment item is classified into exposure levels, and
combined exposures between different `risk factors’ are calculated by using a score table.
Thus, the QEC Exposure Scores are based on combinations of risk factors identified by the
observer and the worker for each body part and for the worker’s subjective responses. Higher
scores result from the combination of two higher-level exposures between different risk
factors than to the combination of two lower-level exposures.
Page 49
38
POSTURE ANALYSIS SHEET
TPES Initial evaluation sheet PSD
Figure 24 Posture Analysis Check sheet
Page 50
39
TPES Initial evaluation sheet PSD
Figure 25 QEC Score sheet
Page 51
40
Gemba Analysis
Gemba means ‘Workplace’. Workplace assessment is being done on various
parameters (Fig.: 15). If any of the parameters provide a potential threat to the safety of the
operators involved in the stage then they are provided with Personal Protection Equipment
(PPEs). The gemba analysis check sheet (fig.: 16) is used for assessment.
Fall by person •Floor slippery, blocked, deteriorated etc.
•Obstacles on the ground pipes, objects etc.)
•Access to the station is too narrow or work surface is too small
•Access to heights poorly adapted (ladders, steps etc.)
•Working at heights (H>500mm)with no hand rail, no protection etc.
•Piling, stacking, unstable storage of parts etc.
•Parts difficult to grasp (sliding parts, difficult to hold in place, no handles
etc.)
Collisions •Particularly hazardous prominent fixed obstacles…
•Moving objects (hooks, swing trays, suspended tools, moving machine
elements etc.
Falling parts
Cuts, wounds •Handling of cutting tools or items with a sharp surface
(sheet metal, parts with burrs not removed, cutter etc.)
Dragging•By mechanical elements, rotations or movement of items
•Containing prominent parts, asperities or recesses, which may drag parts
of the body or clothing….
Projection of
particles •Sparks, shavings, dust etc.
Chemical
products
•Risk of contact or inhalation of dangerous substances
(solvent, mastic, glue etc.).
Figure 26 QEC RYG criteria
Page 52
41
Smoke
aerosols, dust•Considerable presence of pollutants at the work station
Burns •Possibility of contact with parts which are very hot or very cold
Contact with
live elements•Possibility of contact with live (tension) elements
•The use of a complaint electrical tool does not constitute an anomaly
Procurement,
unloading of parts
and packaging by
fork lift truck
•Check that the operations for the changing of tools and
maintenance do not present any specific risks of accidents
Operations
For changing of tools
& maintenance
•Check that the operations for the changing of tools and
maintenance do not present any specific risk of accidents
Noise•A high level(> 85 db) is a disturbance which may drawn out
audible signals used by the operators
Figure 27 Parameters of gemba analysis
Page 53
42
Area: Line:
Operation: Workforce type:
GEMBA ANALYSIS YES NO PPE REMARKSFall by persons
Falling parts
Collision against fixed or moving obstacle
Cuts, Wounds
Crushing, Shearing
Dragging by mechanical elements
Projection of particles
Use of chemical products
Considerable presence of smoke, aerosols, dust
Burns
Contact with live elementsProcurement/Unloading:
Parts & packaging by fork - lift truckOperation carried out by the section
Changing of tools
Maintenance
Noise
other
GEMBA OBSERVATION (IF ANY):
TPES ERGONOMICS SUMMARY SHEETPSD
Figure 28 Gemba analysis check sheet
Page 54
43
NIOSH Lifting Equation:
The NIOSH Lifting Equation is a tool used by occupational health and safety
professionals to assess the manual material handling risks associated with lifting and
lowering tasks in the workplace. NIOSH Lifting Equation is as follow:
RWL = LC (51) x HM x VM x DM x AM x FM x CM
Task variables needed to calculate the RWL:
•H = Horizontal location of the object relative to the body
•V = Vertical location of the object relative to the floor
•D = Distance the object is moved vertically
•A = Asymmetry angle or twisting requirement
•F = Frequency and duration of lifting activity
•C = Coupling or quality of the workers grip on the object
(M stands for Multiplier)
H- Horizontal location of the object relative to the body:
Measure and record the horizontal location of the hands at both the start (origin) and
end (destination) of the lifting task. The horizontal location is measured as the distance
(inches) between the employee’s ankles to a point projected on the floor directly below the
mid-point of the hands grasping the object as pictured below:
Figure 29 Side and Top view showing how to measure distances for NIOSH Lifting Equation
V = Vertical location of the object relative to the floor:
Measure and record the vertical location of the hands above the floor at the start
(origin) and end (destination) of the lifting task. The vertical location is measured from the
Page 55
44
floor to the vertical mid-point between the two hands as shown below. The middle knuckle
can be used to define the mid-point. (See Fig.: 17)
D = Distance the object is moved vertically:
The vertical travel distance of a lift is determined by subtracting the vertical location
(V) at the start of the lift from the vertical location (V) at the end of the lift. For a lowering
task, subtract the V location at the end from the V location at the start.
A = Asymmetry angle or twisting requirement:
Measure the degree to which the body is required to twist or turn during the lifting
task. The asymmetric angle is the amount (in degrees) of trunk and shoulder rotation required
by the lifting task.
Note: Sometimes the twisting is not caused by the physical aspects of the job design,
but rather by the employee using poor body mechanics. If this is the case, no twisting (0
degrees) is required by the job. If twisting is required by the design of the job, determine the
number of degrees the back and body trunk must twist or rotate to accomplish the lift. (i.e.
90°as pictured below)
Figure 30 Showing asymmetry of 90 degrees
F = Frequency and duration of lifting activity:
Determine the appropriate lifting frequency of lifting tasks by using the average
number of lifts per minute during an average 15 minute sampling period. For example, count
Page 56
45
the total number of lifts in a typical 15 minute period of time and divide that total number by
15.
Minimum = 0.2 lifts/minute
Maximum is 15 lifts/minute.
C = Coupling or quality of the workers grip on the object:
Determine the classification of the quality of the coupling between the worker's hands
and the object as good, fair, or poor (1, 2, or 3). A good coupling will reduce the maximum
grasp forces required and increase the acceptable weight for lifting, while a poor coupling
will generally require higher maximum grasp forces and decrease the acceptable weight for
lifting.
1. Good-Optimal design containers with handles of optimal design, or irregular
objects where the hand can be easily wrapped around the object.
2. Fair-Optimal design containers with handles of less than optimal design, optimal
design containers with no handles or cut-outs, or irregular objects where the hand can be
flexed about 90°.
3. Poor -Less than optimal design container with no handles or cut-outs, or irregular
objects that are hard to handle and/or bulky (e.g. bags that sag in the middle).
Output of NOSH Lifting Equation:
RWL: Recommended Weight Limit
Answers, “Is this weight too heavy for the task?”
LI: Lifting Index = Load ÷ RWL
Answers, “How significant is the risk?”
LI<1 ( No Risk)
1<LI<3 (Nominal Risk)
3<LI (High Risk)
L = Load:
Determine the weight of the object lifted. If necessary, use a scale to determine the
exact weight. If the weight of the load varies from lift to lift, you should record the average
and maximum weights lifted.
Page 57
46
DUR = Duration:
Determine the lifting duration as classified into one of three categories: Enter 1 for
short-duration, 2 for moderate-duration and 8 for long-duration as follows:
1 = Short-lifting ≤ 1 hour with recovery time ≥ 1.2 X work time
2 = Moderate -lifting between 1 and 2 hours with recovery time ≥ 0.3 X lifting time
8 = Long-lifting between 2 and 8 hours with standard industrial rest allowances
RULA and REBA:
RULA (Rapid Upper Limb Assessment) was developed to evaluate the exposure of
individual workers to ergonomic risk factors associated with upper extremity MSD. The
RULA ergonomic assessment tool considers biomechanical and postural load requirements of
job tasks/demands on the neck, trunk and upper extremities. A single page worksheet is used
to evaluate required body posture, force, and repetition. Based on the evaluations, scores are
entered for each body region in section A for the arm and wrist, and section B for the neck
and trunk. After the data for each region is collected and scored, tables on the form are then
used to compile the risk factor variables, generating a single score that represents the level of
MSD risk.
The RULA was designed for easy use without need for an advanced degree in
ergonomics or expensive equipment. Using the RULA worksheet, the evaluator will assign a
score for each of the following body regions: upper arm, lower arm, wrist, neck, trunk, and
legs. After the data for each region is collected and scored, tables on the form are then used to
compile the risk factor variables, generating a single score that represents the level of MSD
risk as outlined below in fig.: 19
Figure 31 RULA MSD Risk Level
Page 58
47
Figure 32 RULA Check Sheet
This ergonomic assessment tool uses a systematic process to evaluate whole body
postural MSD and risks associated with job tasks. A single page worksheet is used to evaluate
required or selected body posture, forceful exertions, type of movement or action, repetition,
and coupling.
The REBA was designed for easy use without need for an advanced degree in
ergonomics or expensive equipment. You only need the worksheet and a pen. On second
thought, you probably should finish reading and studying this guide, and I suppose a
clipboard would help as well. Using the REBA worksheet, the evaluator will assign a score
for each of the following body regions: wrists, forearms, elbows, shoulders, neck, trunk,
back, legs and knees. After the data for each region is collected and scored, tables on the form
are then used to compile the risk factor variables, generating a single score that represents the
level of MSD risk (fig.: 21)
Page 59
48
Figure 33 REBA MSD Risk Level
Figure 34 REBA Check Sheet
DESCRIPTION
Objective
Addressing of ergonomics issues & their elimination & control in Line-1 CV-CX
Store.
Target
After evaluating current condition we were able to decide our target:
Page 60
49
1. Reduction of stress in shoulder and back areas of body.
2. Reduction of motion to reduce stress in feet.
Process Flow Diagram
Figure 35 Process Flow of Kaizen Event on Ergonomics
To evaluate the current ergonomic condition we obtained the medical records from
the medical centre from July 2013 to April 2014. We also conducted a small survey among
the workers working in CV-CX Store to know about the musco-skeleton disorders. After that
we evaluated the store using Gemba analysis sheet and quick exposure check sheet and also
identified the heavy parts on which NIOSH lifting equation was applied. Then through brain
storming we decided solutions to various ergonomics issues. During the event, the main
problem encountered was in power steering gearbox lifting process on which we even
performed RULA & REBA analysis in DELMIA with the help of Mr. Gaurav.
Current Condition
From the medical records it was found
that maximum cases were of body pain and
weakness followed by pain in knees. Back
pain and shoulder pain cases were of equal
weightage.
Figure 36 Survey Results
Page 61
50
Figure 37 Summary of Survey
In the survey it was found that the body part which was under maximum strain was feet
followed by knees. The above two data helped us to narrow our focus on two things:
1. Reduce walking of the worker
2. Evaluate lifting of heavy parts
Study of Workplace and Improvement
Gemba analysis check sheet and Quick Exposure check sheet was used by the team in
evaluating the workplace. In context to safety of the worker, the gemba analysis check sheet
revealed that the worker was working in a safe environment and he was provided the
necessary personal protective equipment (PPE’S). The quick exposure check sheet revelled
that the maximum stress experienced by the worker was
Figure: 36 Summary of medical records
Page 62
51
1. Back (Moving) means stress in back during motion(E.g. during manual lifting)
2. Neck. (Refer Table: 3)
Table 13 Summary of QEC of Workers working in CV-CX Store
QEC Analysis
QEC analysis was done to study the current condition of workplace. The study starts
by collecting data. We have to fill a posture analysis check sheet shown in fig.: 14. The data
collected by the sheet is base for analysis. After collecting data, the data is punched in the
DELMIA software, and it provides us with the RYG status.
Figure 38 screen shot of posture analysis tab in DELMIA
Page 63
52
After collecting data, add the data in the sheet by selecting the check circles similar to
the sheet(see figure: 38). After the data entry, enter submit. After submission, DELMIA
generates a summary sheet revealing the ergonomic status.
Figure 39 sample ergonomic summary sheet
NIOSH Study
NIOSH Lifting Equation was applied to manual lifting process of five
heavy parts in CV-CX Store.
1. Power Steering Gearbox
2. Clutch Pressure Plate
3. Spare Wheel Carrier
4. DDU Unit
5. Spare Wheel Carrier Mgt. Bkt.
The following figure shows the table in which the data was collected of
different parameters of NIOSH Lifting Equation for these five parts:
Page 64
53
Figure 40 Data collection table for NIOSH
After data collection, the values of the parameters were input in an excel file which
automatically gave us the values of RWL and LI for all the parts for both initial and final
location.
Page 65
54
Power Steering Gearbox:
Figure 41 Screen shot of Excel File for power steering gearbox-Pickup location
Page 66
55
Figure 42 Screen shot of Excel File for power steering gearbox-Placement location
RULA & REBA Analysis
After NIOSH, RULA & REBA analysis was done in DELMIA by Mr. Gaurav for the
detailed understanding of the solutions. The following picture shows the result of RULA &
REBA analysis done on the existing situation.
inches cm
10 25.4
70 177.8
Model Inputs:
25 cm HM = 1.00
(min 25, max 64)
70 cm VM = 0.99
(min 0, max 178)
Lifting Index (LI = Load/RWL):
25 cm DM = 1.00
(min 25, max 178)
90 deg AM = 0.71
(min 0°, max 135°)
CM = 0.95
(1=good, 2=fair, 3=poor) 15.3 Kg
8 hr(s) Dur = ######
(Enter 1, 2 or 8 hrs. only)
2.312 l/m FM = 0.65
(min 0.2 lifts/min)
35.4 kg
35.4 kg
Duration
(25 is best)
(75 is best)
(25 is best)
(0 is best)
(1 is best)
NIOSH Lifting Guidelines - METRIC
Power Steering Gear Box
Enter Data
10.0 Kg
NOTE: The revised NIOSH guidelines in this Microsoft Excel Workbook are derived from a paper titled "Revised
NIOSH Equation for the Design and Evaluation of Manual Lifting Tasks" published in Ergonomics (Waters, Putz-
Anderson, Garg, and Fine, 1993).
Job Title
Multipliers: Model Outputs:
Recommendations:
Average Load Weight
Coupling
Frequency
(1 is best)
Engineering or Administrative Controls should be
implemented
Recommended Weight Limit (RWL):Horizontal Location (H)
Vertical Location (V)
Maximum Load Weight
Travel Distance (D)
2
Angle of Asymmetry (A)
3.55
Frequency Independent RWL:
Frequency Independent LI:
(0.2 is best)
DESCRIPTION
CLEAR WORKSHEET
Page 67
56
Figure 43 RULA & REBA Analysis done on lifting of power steering gearbox using DELMIA
Page 68
57
Output
Figure 44 Improvement of trolley to eliminate lifting
Trolley was modified to eliminate the lifting of the power steering gearbox. The
worker will slide the gearbox on the trolley from the table and the gearbox will slide to the
end by sliding on the rollers fitted in the trolley.
Page 69
58
Clutch Pressure Plate:
Figure 45 Screen shot of Excel File for Clutch Pressure Plate -Pickup location
Page 70
59
Figure 46 Screen shot of Excel File for Clutch Pressure Plate -Placement location
Output
Movable scissor lift is suggested for improvement in lifting
of Clutch Pressure Plate. This will eliminate vertical motion
and help in reduction of stress on shoulders and back.
Figure 47 Improvement suggestions for
power steering gear box
Page 71
60
Table 14 NIOSH Result
Part Name Initial Location Final Location
Spare wheel Carrier 2.16 1.78
DDU Unit 1.8 1.33
Spare wheel carrier Mgt. Bkt. .72 1.16
Movement Study
Next, we worked on reduction of travel distance for material procurement. Reduction
of travel distance will help in reduction of stress in feet and knees. The following figure
shows the current situation and improved situation.
Figure 48 Initial situation of store layout
Page 72
61
Figure 49 improved situation of store layout
Table 15 Data showing effect of improvement on time and productivity
Table: 15 shows that after improvement there is 50% reduction in material feeding
time for silencer hanger bkt., DDU unit and harness. The improvement has doubled the
productivity of the worker and also reduced the distance which has significantly reduce the
stress in feet and knee of the employee.
Layout of rack area was also modified. Our inspiration for modification was general
utility store. The following figure shows the change in placement of racks:
Page 73
62
Figure 50 Original layout of rack area
Figure 51 Suggested layout of rack area
The following table shows the reduction in travel distance, time saving and impact on
productivity by following this current layout.
Page 74
63
Table 16 Data showing effect of improvement on time and productivity
Learnings
Learned how to analyse GEMBA (Work Base) and on what parameters
Learned how to apply different ergonomic tools
o Quick Exposure Check
o NIOSH Lifting Equation
o RULA and REBA analysis
Inter-departmental exposure was high which helped in enhancement of
communication skills.
Learned how to work in team
How to carry out effective brain storming sessions.
Page 75
64
PROJECT-4
Ergonomic Improvements of Bumper and FUPD FITMENT
Table 17 Team members of project 4
Name Area Designation
Gurvinder Singh PTPA Leader
Parag Aneja Planning Co-Leader
Lalit Kumar TCF Assy 3 Member
Anil Sharma VFPIG Member
V S Chandel TCF Assy 3 Member
Praveen K shukla TCF Assy 2 Member
Amit Kr Singh TCF Assy 2 Member
Gaurav Srivastava TTL Member
Sanna Salim HR Member
Ashish Sinha PSD Member
Prasoon Mishra Lean Mfg Member
Page 76
65
INTRODUCTION
Bumper Fitment
A bumper is usually a metal bar or beam, attached the vehicle's front-most and rear-
most ends, designed to absorb impact in a collision. The weight of bumper varies from model
to model as shown in table below:
Table 18 showing details of bumper
The following figure shows how the bumper fitment is carried out. The bumper is
picked up by two workers from the bumper trolley and taken to the truck. The adjust the
bumper on the bracket and then fasten the bumper using nut and bolt. And the then use an
impact nut runner for tightening.
PART VARIETY WEIGHT PICTURE
Bumper 3 35 Kg ( Max)
26 Kg
13 Kg
* (Selector
switch to be
provided for
each model)
Page 77
66
Figure 52 Process mapping of bumper fitment
FUPD Fitmen
Table 19 showing details of FUPD
An FUPD (Front Underrun Protective Device) is a purpose built heavy-duty bull bar
that has been designed, manufactured, and tested to reduce fatalities in the event of a front-
end truck collision. The weight and design of FUPD remains same for all models as shown in
table below:
PART VARIETY WEIGHT PICTURE
FUPD 1 29 Kg
Page 78
67
Figure 53 Process mapping of FUPD fitment
The above figure shows how the FUPD fitment is carried out. The FUPD is picked up
from the trolley by two workers and taken to the vehicle. There they place it on the bracket
with adjustment and fasten it using nut and bolt. The tightening process is done using impact
nut runner.
DESCRIPTION
Objective
To conduct 3P kaizen for Bumper & FUPD fitment in TCF Line -2, 3 to improve the
ergonomics & safety Parameters.
Target:
To bring these fitment processes form Red category to Green category. Idea is to
reduce Musco-Skeleton Disorders.
Page 79
68
Process Flow Diagram
Figure 54 Process flow diagram of project-4
Current Condition
The gemba analysis sheet revelled that there are no safety problems in the material
handling process and proper personal protective equipment’s were for the safety of the
workers.
The QEC sheet revelled that maximum stress experienced by the worker was in the
shoulder and back areas of his body. To confirm it, further RULA analysis was done on the
current situation by Mr. Gaurav Srivastava in DELMIA. The following figure shows the
result of DELMIA:
Page 81
70
Figure 55 shows RULA analysis for bumper handling
Page 82
71
Figure 56 shows RULA analysis for FUPD handling
Page 83
72
Improvement
The following table shows the parameters on which improvement suggestions were
evaluated and their units of measurement.
Table 20 List of Parameters
Parameter Unit of Measurement
Safety Unsafe act rating 0-10 scale
Ergonomics No of ergo issues
Productivity
-Material Movement Meters
-Operator movement Meters
Muda elimination No of events
Component -Quality 0-10 scale
Complexity – operation 0-10 scale
Complexity – Structure 0-10 scale
Cost 0-10 scale
After the 1 day brain storming session, in which the team did the following tasks:
Option generation for improvement for both Bumper fitment and FUPD fitment.
Option validity. Whether the option is practically viable or not.
Option evaluation on the above listed parameters.
Option finalization.
In the brain storming session, the following options were generated. Following are the
list of options generated in brain storming session for Bumper fitment:
1. 2-Arm manipulator with LT & CT motion rails. ( Trolley location to be shifted)
2. Articulated arm with balancer and pneumatic fixture. (Bumper to be kept in vertical
stacks).
3. Hoist with tackle. (Centre flap position to be adjusted).
4. FUPD & Bumper combined fitment.
Page 84
73
5. Elbow lift with side arm (cantilever type) with vacuum cup with holding arm vertical
rotation.
6. Elbow lift with centre arm with vacuum cup without holding arm rotation.
7. Elbow lift with centre arm w/o vacuum cup (pneumatic clamping of bumper).
Following are the list of options generated in brain storming session for FUPD fitment:
1. 2 new EMS Carrier additions for FUPD.
2. Roller based transportation trolley with manual scissor lift with forks in line feeding
trolley.
3. Transportation trolley without rollers and manual scissor lift line feeding trolley.
4. Use of feeding trolley as a mini/manual forklift.
5. - Arm manipulator with LT & CT motion rails. ( Trolley location to be shifted)
6. Balancer with LT & CT Rails with magnetic tackle. (Trolley location to be shifted
and CT rails to be telescopic)
7. Articulated arm with balancer and pneumatic fixture. (FUPD to be kept in vertical
stacks).
8. Hoist with tackle (at propeller shaft fixing station).
The finalized options were ergonomically evaluated in DELMIA to confirm that these
options are free from ergonomic issues or within stress limits. The following pictures show
the finalized options:
Figure 57 option selected for bumper fitment
Page 85
74
Figure 58 option selected for FUPD fitment
Learnings
Learned how to work in team
Learned how to evaluate GEMBA and on what parameters
Learned the application of various ergonomic tools
o Quick Exposure Check Sheet
o RULA Analysis
How to conduct effective brain storming sessions.
Page 86
75
PROJECT-5
Six-Sigma Project on Door Lock Push Button Hard
Table 21 Team members of project-5
Team Members
Mr. Rishikesh CQ Champion
Mr. BN Khawas CQ Guide
Amandeep Singh Gujral PSD Leader
Shubham Chaudhary Trim-3 Leader
Page 87
76
INTRODUCTION
What is Six-Sigma?
Six Sigma's aim is to eliminate waste and inefficiency, thereby increasing customer
satisfaction by delivering what the customer is expecting.
Six-Sigma is a highly disciplined process that helps us focus on developing and
delivering near-perfect products and services.
Six-Sigma follows a structured methodology, and has defined roles for the
participants.
Six-Sigma is a data driven methodology, and requires accurate data collection for the
processes being analyse.
Six-Sigma is about putting results on Financial Statements.
Six-Sigma is a business-driven, multi-dimensional structured approach to:
1. Improving Processes
2. Lowering Defects
3. Reducing process variability
4. Reducing costs
5. Increasing customer satisfaction
6. Increased profits
The word Sigma is a statistical term that measures how far a given process deviates
from perfection.
The central idea behind Six Sigma is that if you can measure how many "defects" you
have in a process, you can systematically figure out how to eliminate them and get as close to
"zero defects" as possible and specifically it means a failure rate of 3.4 parts per million or
99.9997% perfect.
Key Concepts of Six-Sigma
At its core, Six Sigma revolves around a few key concepts.
Critical to Quality: Attributes most important to the customer.
Defect: Failing to deliver what the customer wants.
Process Capability: What your process can deliver.
Variation: What the customer sees and feels.
Page 88
77
Stable Operations: Ensuring consistent, predictable processes to improve what the
customer sees and feels.
Design for Six Sigma: Designing to meet customer needs and process capability.
Our Customers Feel the Variance, Not the Mean. So Six Sigma focuses first on reducing
process variation and then on improving the process capability.
The Benefits of Six-Sigma
There are following six major benefits of Six Sigma that attract companies.
Six-Sigma:
Generates sustained success.
Sets a performance goal for everyone.
Enhances value to customers.
Accelerates the rate of improvement.
Promotes learning and cross-pollination.
Executes strategic change.
DESCRIPTION
Objective
The objective of this project was to reduce the door lock push button force to increase
customer satisfaction.
Page 89
78
Process Flow Diagram
Figure 59 Shows DMAIC Approach for 6 sigma project
Define Phase
The problem of “Door Lock Push Button Hard” was given to us by Central Quality
department of Tata Motors, Lucknow. This problem was faced by the customers of Tata
motors from many years and was very much consistent. The following project charter will
give you detail view of the problem.
Table 22 Project charter
Page 90
79
Figure 60 Problem Definitions
Problem Definition
Page 91
80
Figure 61 Box Plot showing current force levels
The above box plot shows that the force to push the button is ranging from 140 N to
180 N which is very high.
Table 23 CTQ and CTP
Page 92
81
The above figure shows the CTQ (critical to quality) and CTP (critical to process)
parameters. It also shows how we reached CTQ and CTP by identifying voice of customer
and voice of business. This has also helped us in defining our goal for our project.
4W1H is a method of asking questions about a process or a problem taken up for
improvement. 4W1H is used to comprehend for details, analyse inferences and judgment to
get to the fundamental facts and guide statements to get to the abstraction. Methodology
includes answering a checklist of five questions, each of which comprises an interrogative
word - what, who, when, where and how.
Table 24 4W-1H table
Page 93
82
Figure 62 SIPOC Diagram for Door Lock
SIPOC is the helicopter view of the business process. It is used to capture key
information about the process. The SIPOC Diagram tells us about the various parts of the
fitment and their supplier. It also helps us identify the immediate customer who will be facing
the problem, in our case they are the testing & inspection people at TCF Line-3.
Figure 63 Top-Down Charts for Door Lock
Page 94
83
Top-Down chart is the next level detailing of SIPOC diagram. It is used to understand
the process in detail. As we can see in the figure 64, it is telling us how the different child
parts are fitted in the cab.
Table 25 Process walkthrough observations Chart
We visited the shop floor to know how the fitment process is carried out. During the
process Walk through, we have to find out that standards are being followed during the
fitment process. In our case, we find out that hammering was done on the kit lock for its
adjustment, which was due to the miss alignment of hole as shown in fig 65. This was not a
quick win and was reported to the Tata managers. This miss alignment cured by the Tata
managers and the problem was eliminated.
Measure and Analysis Phase
The measure and analysis phases go hand in hand. It started with the construction of
fish-bone diagram, in which we listed all the possible causes for the occurrence of problem.
Then we designed a data collection plan which helped us in prioritization of causes.
Page 95
84
Figure 64 Fish-Bone Diagram
Figure 65 Measurement device - push pull gauge (max. 50 kgf)
Page 96
85
First Data Collection Plan:
Table 26 First Data Collection Plan
Y's
Push Force
Door Lock
Handle
Push Force
Kit Lock
Push Force
Door Lock-
Before
Alignment
(Open)
Push Force
Door Lock-
After
Alignment
(Open)
Push Force
Door Lock
(Closed)
Performanc
e measure
Kgf Kgf Kgf Kgf Kgf
Type of
Data
(Attribute /
Variable)
Variable Variable Variable Variable Variable
Operational
definition
Push Pull
guage should
be held
perpendicular
to the button
surface
Push Pull
guage should
be held
perpendicular
to the button
surface
Push Pull
guage should
be held
perpendicular
to the button
surface
Push Pull
guage should
be held
perpendicular
to the button
surface
Push Pull
guage should
be held
perpendicular
to the button
surface
Data source
/ location
Trim Line 3 Trim Line 3 Trim Line 3 Trim Line 3 Trim Line 3
Sample size 1 1 1 1 1
Who will
collect the
data
Amandeep
and Shubham
Amandeep
and Shubham
Amandeep
and Shubham
Amandeep
and Shubham
Amandeep
and Shubham
When will
the data Be
collected
G Shift G Shift G Shift G Shift G Shift
How will the
data Be
collected
Push Pull
Guage
Push Pull
Guage
Push Pull
Guage
Push Pull
Guage
Push Pull
Guage
Other data
that should
be collected
at the same
time
Page 97
86
Figure 66 door lock part description
Table 27 result of first data collection plan
S.No. CAB No. LHS RHS LHS RHS LHS RHS LHS RHS LHS RHS
1 P344VYC02244 1.54 1.53 2.85 3.3 6.22 7.72 7.57 6.74 13.92 12
2 P344VYC02245 1.75 1.83 2.98 3.21 7.34 7.79 7.2 6.4 19.81 16.63
3 P344VYC02246 1.88 1.75 3.2 3.19 6.86 6.64 6.98 7.19 14.89 11.03
4 P344VYC02247 1.82 1.79 2.99 2.88 6.73 5.61 6.62 6.22 14.34 11.85
5 PS516VYC02249 1.98 1.89 3.14 2.99 6.55 5.9 7.48 7.09 16.97 11.09
6 PS516VYC02252 2.03 1.91 3.07 3.43 7.57 6.34 7.31 7.13 14.27 13.84
7 PS516VYC02253 1.87 1.95 3.16 3.64 6.82 6.8 6.08 6.15 13.12 12.23
8 PS516VYC02254 2.11 2.24 3.18 3.42 7.44 5.99 6.38 6.84 11.52 14.48
9 PS516VYC02264 2.18 2.37 3.57 3.33 6.79 6.81 7.19 6.02 15.99 15.22
10 PS516VYC02265 2.39 2.25 3.53 3.2 7.41 8.67 7.29 7.91 14.29 13.58
2.39 2.37 3.57 3.64 7.57 8.67 7.57 7.91 19.81 16.63
1.54 1.53 2.85 2.88 6.22 5.61 6.08 6.02 11.52 11.03
1.955 1.951 3.167 3.259 6.973 6.827 7.01 6.769 14.912 13.195
0.85 0.84 0.72 0.76 1.35 3.06 1.49 1.89 8.29 5.6Range
Initial Measurement Sheet - Door Opening Push Button Force
Date:
After Fitment
Door Handle Push Button
Force (Kgf) Force (Kgf)
Before Fitment (Part Level)
Kit Lock Before Alignment (Open)
Push Button Force (Kgf)
After Alignment (Open)
Push Button Force (Kgf)
After Alignment (Closed)
Push Button Force (Kgf)
Max
Min
Mean
Page 98
87
Figure 67 67 Box plot of data collected in table 26
A-Push Force of Door lock handle
B-Push force of Kit Lock
C-Push force of door lock (Open)-Before Alignment
D- Push force of door lock (Open)-After Alignment
E- Push force of door lock (Closed)
The graph is very revealing. In the graph we can see that the there was a sudden
increase in force in going from A, B to C and D to E. the sudden rise from A, B to C was
because the force was transmitted to Kit lock through Door lock handle as a result the
individual forces of these two components add up plus some minor losses which lead to
sudden increase in force form A, B to C. now the question arise that the why there is increase
in force from D to E because theoretically both should be same. So this became a trigger
point for our study and helped in prioritization of causes shown in red in the following fish-
bone diagram.
A B
C D E
Page 99
88
Figure 68 Modified Fish-Bone Diagram
After this we went for the reading and we identified that there was a major difference
in the push force of left door and right door. The push force of left door was significantly
higher as compared to the right door. The observation we obtained while adopting the
philosophy of Genchi Gembutsu, we designed our next data collection plan.
Table 28 Second Data Collection Plan
Kit Lock Holes(X's) in Cab Door
Performance measure mm
Type of Data (Attribute / Variable) Variable
Operational definition Distance of the holes from the
ref.(inner side of the door)
Data source / location Trim Line 3
Sample size 1
Who will collect the data Amandeep and Shubham
Page 100
89
When will the data Be collected G Shift
How will the data Be collected Vernier Calipers
Other data that should be collected at the same
time
Push Button Force (Y’s)
Figure 69 drawing revealing the standard distance for location of holes
From the drawing, we can see that the standard distance of holes 1 and 2 from the
reference are 32.5 mm and 55.5 mm. but in the actual case, the left door was far away from
standards. In both the cases, the second lock does not engage before hammering.
Table 29 Result of second data collection
Page 101
90
The following figure will help you to understand the data collected in second data
collection process in a better way.
Figure 70 Shows basic statistical calculations of distance data in table 29
From the above figure we can see that the mean of distance of hole 1 and 2 is higher
by approx. 3 mm in case of H1 and 3.5 mm in case of H2 in LHS Door.
Figure 71 Shows basic statistical calculations of difference data in table 29
Page 102
91
Difference = Distance of holes measured – Standard distance of holes.
Figure 70 is self-revealing. In case of lhs door both H1 and H2 are shifted approx. by
3mm away from the reference and in case of RHS door the difference is almost negligible.
The following box-plots will help you to see the picture more clearly.
Figure 72 Box plot of data in table 29
The above shown box-plot clearly reveals that the difference which ideally should be
zero is not coming in case of LHS door. In case of RHS door the difference is close to zero.
Page 103
92
Figure 73 Box plot of data in table 29
The above figure clearly shows that both the force and the difference are high in case
of LHS Door as compared to RHS Door. Hence this became our first validated Cause.
We designed our third data collection plan to validate our second cause:
Table 30 Third data collection plan
Push Button Force-
with beading
Push Button Force-
without beading
Performance measure Kgf Kgf
Type of Data (Attribute / Variable) Variable Variable
Operational definition Push Pull gauge
should be held
perpendicular to the
button surface
Push Pull gauge
should be held
perpendicular to the
button surface
Data source / location Trim Line 3 Trim Line 3
Sample size 1 1
Page 104
93
Who will collect the data Amandeep and
Shubham
Amandeep and
Shubham
When will the data Be collected G Shift G Shift
How will the data Be collected Push Pull Gauge Push Pull Gauge
Other data that should be collected at
the same time
The following table shows the data collected according to third data collection plan:
Table 31 result of third data collection plan
Page 105
94
Figure 74 Histogram analysis of data in table 31
Form the above histogram analysis it can be concluded that the spring force of
beading is playing and important role. This gave us our second validated cause.
Next we designed our Forth data collection plan to validate our prioritized root
causes, which are:
1. Door aperture gap very less.
2. Door closing force is high.
Table 32 Forth data collection plan
Gap Between
Door
Aperture and
Door
Push Button
Force- with
beading
Push Button
Force- without
beading
Performance measure mm Kgf Kgf
Type of Data (Attribute /
Variable)
Variable Variable Variable
Operational definition Gap Between
Door Aperture
and Door
Push Pull gauge
should be held
perpendicular to
Push Pull gauge
should be held
perpendicular to
Page 106
95
the button surface the button surface
Data source / location Trim Line 3 Trim Line 3 Trim Line 3
Sample size 1 1 1
Who will collect the data Amandeep and
Shubham
Amandeep and
Shubham
Amandeep and
Shubham
When will the data Be collected G Shift G Shift G Shift
How will the data Be collected Filler Gauge Push Pull Gauge Push Pull Gauge
Other data that should be
collected at the same time
Push Button
Force
Figure 75 3- points at which gap was measured
Page 107
96
Table 33 Result of forth data collection plan
The following box-plots will help you to pictures the data in table 15 more clearly. At
this point we have our third validated cause.
Figure 76 Box Plot of data in table 32
Page 108
97
Table 34 summary of measurement and analysis phase
Improvement Phase
The following tables show our action plan to reduce the problem. Table 35 Action plan for improvement
The action plan was implemented in following steps as follow:
Page 109
98
Step 1:
Figure 77 Email sent to BIW
Step 2:
Figure 78 Email sent to ERC
Page 110
99
Changed beading design
Figure 79 Present beading design
Figure 80 Suggested beading design
Learning
Learned about six sigma, DMAIC approach and how to apply this methodology in
real life situation
Learned about team work
Learned about importance of quality
Learned how to use MINITAB software
Learned about the various statically tools used in SIX SIGMA. E.g. hypothesis
testing, regression, etc
Page 111
100
REFRENCES
1. Source: http://www.tatamotors.com/about-us/company-profile.php
2. Source: http://www.tatamotors.com/about-us/manufacturing.php
3. Source: http://www.ergo-plus.com
4. Source: TMPS Guidelines handbook-TATA Motors
5. Source: http://www.images.google.com/dmaic/
6. Source: Zandin, Kjell B (2003). MOST Work Measurement Systems