Top Banner
PROJECT REPORT ON STUDY OF INVENTORY CONTROL AT TECHNOCRAT ENGINEERSFor TECHNOCRATS ENGINEERS By PRACHI TALEKAR Under the Guidance of PROF. VIJAY DESHMUKH Submitted to “University of Pune” In partial fulfillment of the requirement for the award of the degree of Master of Business Administration (MBA) Through Dr. Vikhe Patil Foundation’s 1
145
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Report Prachi

PROJECT REPORT

ON

“STUDY OF INVENTORY CONTROL

AT TECHNOCRAT ENGINEERS”

For

TECHNOCRATS ENGINEERS

By

PRACHI TALEKAR

Under the Guidance of

PROF. VIJAY DESHMUKH

Submitted to

“University of Pune”

In partial fulfillment of the requirement for the award of the

degree of Master of Business Administration (MBA)

Through

Dr. Vikhe Patil Foundation’s

Centre for Management Research &Development

Pune-16

1

Page 2: Project Report Prachi

ACKNOWLEDGEMENT

Planning & Motivation are the two key factors in making any activity a success. Goal

achievement is a result of effort rather than individual effort. I have been the same of this

project the co-operation &support of many individuals has made this project a success.

I have the honor to express my heartfelt gratitude to Mr.S.V.Patki for giving me the

opportunity to undergo the summer training in their esteemed organization and for his valuable

guidance and support.

I take this opportunity to extend my sincere gratitude to all the staff members for their whole

hearted cooperation and valuable help throughout the training.

I sincerely express my gratitude to Prof. Vijay Deshmukh for his support in the completion of

the project.

Sr. No. PARTICULARS PAGE NO.2

Page 3: Project Report Prachi

1 EXECUTIVE SUMMARY 4

2 COMPANY PROFILE 5

3 OBJECTIVE OF THE STUDY 7

4 RESEARCH METHODOLOGY 8

5 INTRODUCTION

INVENTORY

MATERIAL

10

6 CONCEPTS OF INVENTORY 12

7 PURCHASE

DETAILS

PROCEDURE

FORMATS

23

8 STORES ORGANISATION 34

9 CLASSIFICATION OF MATERIALS 39

10 IDENTIFICATION OF MATERIALS 43

11 CODIFICATION 44

12 TECHNIQUES OF INVENTORY MANAGEMENT

FIXATION OF LEVELS

SELECTIVE CONTROL OF INVENTORIES

JIT

ANALYSIS OF INVESTMENT IN INVENTORY

45

13 DATA ANALYSIS 55

14 RECOMMENDATIONS &SUGGESTIONS 95

15 CONCLUSION 96

16 BIBLIOGRAPHY 97

CONTENTS:

EXECUTIVE SUMMARY

3

Page 4: Project Report Prachi

Inventory is the most significant part of the company, which accounts for over 30-40% of the

company’s expenditure. This project reflects the inventory management system of

TECNOCRAT ENGINEERS. Inventory means all the materials, parts, supplies, expensive

tools and semi finished or finished products recorded on the book by an organization and kept

in its stocks, warehouse or plant for some period of time.

DEFINITION OF INVENTORY

“Inventory is a list of names, quantities and monetary values of all or any group of items”

“Inventory is a detailed list of those movable items which are necessary to manufacture a

product and to maintain the equipment and machinery in good working order.” The quantity

and value of every item is also mentioned in the list

The area of focus of this project is to reduce the overall cost associated with inventory by the

undertaking activities:-

Obtaining the list of surplus stock and finding out reasons for growing surplus.

Attempt to reduce the existing surplus.

An attempt to prevent further accumulation of surplus

Making recommendations to the currently followed purchase procedure

Suggesting more effective method for the control of inventory.

Reduction of the accumulated/surplus stock period itself reduces unnecessary amount of

money blocked in the form of inventory and hence resulting in blocking the working capital of

the company.

COMPANY PROFILE

4

Page 5: Project Report Prachi

TECHNOCRAT ENGINEERS was started in1991. Today it provides complete solution to suit

the clients welding automation requirements. The design engineers of TECHNOCRATS work

out the right level of automation for the client & make a full proof welding system, to give the

client what he dreams for these years. The company is a proven name in the welding industry

for quality ARC welding equipments & accessories reliable & quick after sales service. In any

engineering goods manufacturing activity, welding plays a very important role. "Technocrat

engineers" work in the field of welding engineering with a view to supply good quality

welding equipments, accessories and special purpose automated welding systems. Technocrat

engineers is in the field for more than 10 years today. It is known for its excellent quality

products and customer oriented service back up.

Mr. S. V. Patki and Mr. D. M. Talekar the real "technocrats" are constantly in touch

with the customers, understanding their needs developing suitable welding systems to satisfy

the customer needs. The policy of continuous improvements in the products & services keep

the customers happy and satisfied. Both the partners’ viz. Mr. Patki and Mr. Talekar are

engineers working in this field for more than last 20 years and have hands on experience in

designing, production, quality control and marketing.

PRODUCT RANGE:

Industrial Duty range.

Industrial Duty Welding Rectifiers.

CO2/MIG Welding Outfits.

Tig Welding Outfits and Control Units.

Submerged ARC Welding Machines (Carriage and Boom Mounting Type)

Self Shielded Hard Facing Welding Systems.

Automating Modules Such as Turn Tables, Welding Lathes.

Automatic/Special Purpose Welding Systems to Suit Customer’s Specific

Requirements of Productivity and quality

OTHER ACTIVITIES:

5

Page 6: Project Report Prachi

Calibration of welding equipments as per ISO 9001 requirements.

Welding improvements and automation possibilities: Advice to customers after

studying the specific needs of productivity.

OBJECTIVES OF THE STUDY

6

Page 7: Project Report Prachi

The primary objective of this project is to reduce overall expenditure or costing for the

company by lowering the cost associated with inventory.

Various other objectives pursued to fulfill the primary objective are as follows-

Reduction of existing surplus stock.

To avoid any further accumulation of surplus

To device an appropriate cost reduction technique of inventory control, which can be

used along with the existing technique to improve performance.

RESEARCH METHEDOLOGY

7

Page 8: Project Report Prachi

MEANING OF RESEARCH

Research is an active, diligent and systematic process of inquiry aimed at discovering,

interpreting and revising facts. This intellectual investigation produces a greater knowledge of

events, behaviors, theories and laws and makes practical application possible. The term

research is also used to describe an entire collection of information about a particular subject,

and is usually associated with the output of science and the specific method. The word research

derives from the French recherché, from researcher, to search closely where “chercher” means

“to search”, its literal meaning is “to investigate thoroughly’. Research is funded by the public

authorities, by the charitable organization and by private groups, including many companies. It

is defined as the “systematic and objective analysis and recording of controlled observations

that may lead to the development of generalization principles or theories, resulting in

prediction and possibly ultimate control of events.”

Research can be classified into various classes. These classes are not watertight compartments.

There is a certain amount of overlap between the various classifications. Every classification

emphasizes certain aspect of research.

RESEARCH DESIGN

A research design specifies the method and procedures for conducting a particular study. In

this case exploratory and applied type of research is used. An exploratory is generally based on

the primary data that are readily available. It does not have rigid design as researcher may have

to change his focus or direction depending on the availability of variables i.e. statistics graphs

and charting. The second type- applied research is nothing but application of sciences and

knowledge to observe variables i.e. applied theory.

DATA SOURCES

8

Page 9: Project Report Prachi

SECONDARY DATA-

As the project is based on Aligning the Inventory, hence data involved in the analysis is

basically a secondary data.

The facts and figures along with the records were taken from the executives of the company.

Records related to inventory were taken from purchase department and stores department.

METHOD OF DATA COLLECTION:

Since this scope & topic is based on theory it was imperative to use secondary data method for

data collection.

A real attempt was done to simplify the project research. The report is written in organized

appearance. Observations and recommendations are presented in this report in simple and

systematic manner.

INTRODUCTION

9

Page 10: Project Report Prachi

INVENTORY

The raw materials, work-in-progress and completely finished goods that are considered to be

the portion of a business’s assets those are ready or will be ready for selling. Inventory

represents one of the most important assets that most business possesses, because the turnover

of inventory represents one of the primary sources of revenue generation and subsequent

earnings for the companies’ shareholders/owners.

Possessing a high amount of inventory for long periods of time is not usually good for a

business, because there are inventory shortage, obsolescence and spoilage costs. However,

possessing not enough inventory isn’t good either, because the business runs the risk of losing

out potential sales and potential market share as well.

Inventory management forecasts and strategies, such as a just-in-time inventory system, can

help minimize inventory costs because goods are created or received as inventory only when

needed.

MATERIALS

Materials are the key resource in an industrial enterprise since no production is possible

without materials. Materials also form a major constituent of the cost of the product and

therefore proper control over their procurement, storage, issue, movement and consumption is

necessary.

The storage of the material is of great interest to the company, because normally substantial

amount of the company’s working capital is invested in stores. There should be a system of

proper accounting of material and supplies and it should be given same attention as is given to

accounting for money. Raw material and supplies are the equivalent of cash. They form an

important part of cost of manufacturing ad it is essential that they should be safeguarded and

accounted properly.

Material control is important managerial function, which is directed to ensure that required

quantity and quality of material is provided at the proper time with minimum amount of

capital.

10

Page 11: Project Report Prachi

Material management, according to bethel and others, is a term used to connote “controlling

the kind, location, movement and timing of the various commodities used in and produced by

the industrial enterprise.” It involves all activities concerning materials right from the time the

need for the material is established until they are to production.

Thus, the functions of material management includes:-

Material Planning

Purchasing

Inventory control

Store –keeping

Store accounting

Transportation-Internal (i.e. material handling)&

External (i.e. traffic, shipping, etc.)

Disposal of scrap, surplus and obsolete materials

Material economics

Waste Management

CONCEPTS OF INVENTORY

MEANING

11

Page 12: Project Report Prachi

The literary meaning of the word inventory is stock of goods. To the finance manager,

inventory connotes the value of raw materials, consumables, spares, work-in-progress, finished

goods and scrap in which a company’s funds have been invested. Good inventory management

is good finance management. An efficient management of inventory should ultimately result in

the maximization of the owner’s wealth. Therefore inventory is considered as locked up

capital. Inventories mean tangible property held:

a. For sale in the ordinary course of business; or

b. In the process of production for such sale or

c. For consumption in the production of goods or services for sale, including

maintenance supplies and consumables other than machinery spares.

DEFINITION

Inventory management may be defined as the sum total of those activities which are necessary

for the acquisition, storage, sale and disposal or use of material. It is a subject which merits the

attention of the top level management and influences the decisions of the planning and

executive personnel.

Decisions relating to inventories are taken primarily by executives in production, purchasing

and marketing departments. Usually, raw material policies are shaped by purchasing and

production executives, work-in-progress inventory is influenced by the decisions of production

executives and finished goods inventory policy is involved by production and marketing

executives. The financial manager has the responsibility to ensure that inventories are properly

monitored and controlled. He has to emphasize the financial point of view and initiate

programmes with the participation and involvement of others for effective management of

inventories.

The inventories which include inventories of raw materials, finished goods and work-in-

progress constitute quite a significant part of the total current assets. It has been observed that

in many cases inventories are more than 60-65% of the total current assets of the firm. This

naturally means that a very large amount is blocked in inventories & therefore management of

inventories has assumed a greater importance. If properly managed, the profitability of a firm

in the long run can be definitely improved while if neglected, the profitability is definitely

affected adversely.

12

Page 13: Project Report Prachi

DIFFERENT PERCEPTIONS OF THE “INVENTORY”

It is interesting to note different departments of the same organization hold different points of

view, which often tends to conflict with one another. It can be said as follows:-

The financial manager justifies limited inventory stocks, because for him, inventory is

money which does not earn interest and ties up capital.

The production manager, on the other hand, encourages to keeping liberal inventory

stocks to guard against stock- outs in the face of fluctuating demands and uncertain

deliveries.

The marketing executive prefers to have reserves of the finished goods inventory.

Product designers are interested in getting an inventory which makes up the products

with all possible accuracy.

Engineers, on the other hand, are often inclined to have a critical mind towards value-

analysis, value engineering and other allied problems of inventory.

Thus although the different approaches to the problems of inventory are not misleading, they

are likely to be biased by their own considerations. The top level management should,

therefore, bear such diverse expressions in mind instead of getting lost in them and take a

bird’s eye-view of the overall objective of “neither too much nor too little” inventory by

attempting a cost benefit analysis. A well-reconciled scientific approach would enable the

management to plan and control inventory effectively.

TYPES OF INVENTORY

The inventories can be classified as follows:

1) Raw Materials:

13

Page 14: Project Report Prachi

A manufacturing concern converts the raw material into the finished products. The raw

materials are the basic inputs which are required for the conservation into finished goods.

2) Work-In-Progress:

Between the raw materials and there is an intermediate stage which is known as work-in-

progress. These units are therefore neither totally raw nor totally finished and is generally a

planned activity.

3) Finished Goods:

These are completed units awaiting the sale in the market. As the production in the modern

days is in anticipation of the demand, some amount of finished goods inventory is

inevitable. The inventory should be in sufficient quantity so that marketing operations of

the firm are smooth. Thus, the stock of finished goods provides a buffer between customer

and demand and manufacturer’s supplies.

4) Flabby Inventory

It comprises finished goods, raw material and stores held because of poor working capital

management and inefficient.

5) Profit-making Inventory:

It represents the stock of raw materials and finished goods held for realizing stock profit.

6) Safety Inventory:

It provides for the failure in supplies unexpected spurt in demand, etc., although there may

be an insurance cover.

7) Normal Inventory:

It is based on a production plan, lead time of supplies and economic ordering levels.

Normal inventories fluctuate primarily with change in the production plan. Normal

inventory also includes a reasonable factor of safety.

8) Excessive Inventory:

Even an effective management may be compelled to build up excessive inventory for

reasons beyond its control, as in the case of strategic import or as a measure of government

price support of a commodity.

ASPECTS OF INVENTORY MANAGEMENT

Inventories are quite crucial for any business firm. The raw materials inventory, if kept excess

of the requirement may lead to unnecessary blocking of the funds in such inventory, while if it

14

Page 15: Project Report Prachi

is in shortage, it will lead to disrupting the flow of production. Similar things can be said about

the work in progress and finished goods inventory. The option before the management is either

to keep a very low level of inventory which is also known as hand to mouth policy or to keep a

large quantity of inventory ensuring absolute safety.

As said, above, if inventory levels are kept very low. It will lead to frequent stoppages of

production. If finished goods inventories are kept very low it will result in distributing the

delivery schedule to the customers. It may further lead to the cancellations of some of the

orders. No firm can afford to take such risks.

Alternatively, if inventory levels are kept on a very high level, carrying cost like storage,

handling, insurance, recording and inspection also increase in proportion to the inventory

volumes. At the same time, as large amount of funds are blocked in those inventories, the

liquidity of the firm is severely affected. The high levels of inventory may ensure safety but the

cost of holding such a high level of inventory may nullify their advantage.

It will also not be out of place to mention here that form holds inventories basically for three

reasons:-

a) TRANSACTION MOTIVE:

This motive implies that inventories are maintained for the facilitation of smooth

production and sales.

b) PRECAUTIONARY MOTIVE:

It suggests that the inventories are maintained to take care against the risk of unforeseen

changes in demand and supply factors.

c) SPECULATIVE MOTIVE:

It says that the inventory maintenance (high or low) decision is affected by the motive

to take advantage of price fluctuations.

The aspects of inventory management can be described as follows:-

1. To ensure hat a very high level of inventory is avoided.

15

Page 16: Project Report Prachi

2. At the same time to ensure that inventories are not so adequate that it will affect

adversely the smooth flow of production and sales.

3. Minimize the carrying cost and

4. Maintain an optimum level of inventories.

OBJECTIVES OF INVENTORY MANAGEMENT

To have stocks available as when they are required.

To minimize available storage space, but prevent stocks level from exceeding space

availability.

To meet a high percentage of demand without creating excess stock levels. In other

words, “neither to over-stock nor to run out” is the bet policy.

To maintain adequate accountability of inventory assets.

To keep all the expenditure within the budget authorization.

To decide which items to stock and which items to procure on demand.

To ensure adequate supply of materials, stores, spares, etc. minimize stock-outs and

shortages and avoid costly interruption in operations.

To keep down investment in inventories, inventory carrying cost and obsolescence

losses to minimum.

To permit a better utilization of visible stocks by facilitating inter-departmental

transfers within a company.

To provide a check against losses of material through careless of pilferage

To serve as a means for the location and disposition of inactive and obsolete items of

stores.

To provide a perpetual inventory value and a consistent and reliable basis for the

preparation of financial statements.

To contribute to the nation’s economic well-being.

To contribute to profitability and

To bring down the inventory carrying cost inventory management is considerable.

BENEFITS OF INVENTORY MANAGEMENT

16

Page 17: Project Report Prachi

Inventory control ensures an adequate supply of material and store. Minimize stock out

and shortage and avoid costly interruption in operation.

It keeps down investment in inventories.

It facilities purchasing economics through the measurement of requirement on the basis

of recorded experience.

It provides a check against the losses of material through careless or pilferage.

It serves as a means for the location and deposition of inactive and obsolete item of

store.

FACTORS INFLUENCING INVENTORY

17

Page 18: Project Report Prachi

LEAD TIME:

Lead-time is defined as the period, which elapses between the recognition of a need and its

fulfillment. There is a direct relationship between lead-time and inventory, during lead time,

there is no delivery of materials and the consuming departments are served from the existing

inventories. Both lead-time and consumption rate can be increased without notice; and

inventories are generally geared up for this contingency. As lead time increases, inventories

increase correspondingly. Lead- time is the time taken for identifying the need and placing the

order, for procuring from suppliers, for shipping, transport, receipt and inspection of items to

the delivery of finished products.

COST OF HOLDING INVENTORY:

Inventory tie up funds. They also expose a firm to a number of risks and costs. The inventory

problem is one of balancing the various costs so that the total cost is minimized. The different

costs are material cost, cost of ordering, holding or carrying the inventory, under stocking cost

and over-stocking cost.

Material Cost:

This is the cost of purchasing goods plus the transportation and handling charges.

Order Cost:

This is a cost of placing an order for goods. Every time a firm places an order; a

particular procedure has to be followed. Forms must be typed, approved and

dispatched. When goods arrive, they must be accepted, inspected and counted. The

invoice must be checked against the goods and sent to the Account department.

Arrangements for the payment to suppliers must be made. All these expenses

accumulate into a variable cost which varies with individual orders. The smaller the

number of orders, the lower is the order cos. A firm, therefore, tries to reduce the

number of orders by placing a big order each time.

Cost of Carrying Inventory:

18

Page 19: Project Report Prachi

The components of those costs are;

a. The cost of capital.

b. The cost of storage.

c. The cost of deterioration.

d. Salaries and statutory payments of stores personnel.

Cost of typing-up of funds:

An inventory may be financed by trade credit, debt financing or even by the sale of

stock. Whatever the source of funds used for the financing of the inventory, the fact

remains that cost is involved in it.

Cost of Understocking:

Excess inventories represent additional and unnecessary costs. Storages of inventory

delay the fulfillment of contractual orders, which would involve a loss of profit or some

kind of indirect cost. Understocking or out-of-stock cost is due to the non-stocking of

an inventory. This is usually measured in terms of the opportunity cost arising out of

the loss in production by the idle cost of a line. It may result in expediting orders or

giving rush orders and extra charges will have to be incurred on these orders.

Cost of Overstocking:

It is basically opportunity cost arising out of the investment in inventory for a longer

period than necessary.

RE- ORDER POINT:

The re-order point indicates when an order should be placed and depends upon the

consumption rate and the duration of lead time. The simplest method is to place an order when

the inventory is depleted to the lead time consumption level. However, an organization will

have to take care of the long time with sufficient initial stock and then follow it up regularly

with EOQ cycles.

STOCK:

19

Page 20: Project Report Prachi

In inventory control, different terms are used, such as safety stock, reserve stock, buffer stock

and so on. The buffer stock provides for normal consumption during an average lead time. The

reserve stock provides for an increased consumption rate, while safety stock for an increasing

lead time. The buffer, in fact is the multiplication of normal consumption and average lead

time. The safety stock level is the multiplication of the average demand during a period of the

maximum delay and the probability of its occurrence.

VARIETY REDUCTION:

In organization which has to stock innumerable items, it is imperative to reduce the number of

items carried in an inventory, particularly the different small items which are sparingly used. In

the case of work in progress, the increase in varieties may be due to technical bottlenecks. With

an increase in the items of raw materials, work-in-progress, output, etc. inventory control

becomes more and more cumbersome. An organization will, therefore, have to take proper

steps to ensure that variety reduction is effected as far as possible.

MATERIAL PLANNING:

Production plans have to be converted into material plans so that the quality and time schedule

of requirements may be defined. A material planning is a mechanism which perceives the

environment for inventory control. To have a successful materials planning, adoption of a

definite methodology which would take care of internal as well as external factors is a must.

SERVICE LEVEL:

The degree of service indicates a percentage of the number of replenishment orders which

arrives without difficulty and makes it possible for a firm to render an adequate service to the

customer. The service levels refer to the “probability of not running out of stock” and the

“proposition of annual demand met ex-stock.”

OBSOLETE INVENTOY AND SCRAP:

An inventory becomes obsolete because of change in the product design or because of

technological changes. Obsolescence cannot be controlled without a proper identification of

inventories which might become obsolete from time to time.

20

Page 21: Project Report Prachi

QUANTITY DISCOUNTS:

Quantity discounts are offered by the purchasers. In order to induce purchasers, suppliers often

offer a reduced price for bulk orders.

TECHNIQUES OF INVENTORY MANAGAMENT

A. FIXATION OF THE LEVELS.

B. SELSCTIVE CONTROL OF INVENTORIES.

C. JIT

D. ANALYSIS OF INVESTMENT IN INVENTORY.

McDonalds’s vs. Wendy’s: An Example

It’s easy to see how higher inventory turn than competitors translates into superior business

performance. McDonalds is unquestionably the largest and most successful fast food restaurant

in the world. Let’s compare it to one of its main competitors, Wendy’s.

McDonalds’s

2000 1999

Inventories $99,300,000 $82,700,000

Cost of revenue $8,750,100,000

Wendy’s

2000 1999

Inventories $40,086,000 $40,271,000

Cost of revenue $1,610,075,000

Use the inventory turn formula [cost of sales or cost of revenue divided by the average

inventory values] to come up with the number of inventory turns for each business. Between

1999 and 2000, McDonalds had an inventory turn of rate of 96.1549[incredible for even a

high-turn industry such as fast food]. This means that every 3.79 days, McDonald’s goes

through its inventory. Wendy’s, on the other hand, has a turn rate of 40.073 and clears its

inventory every 9.10 days.

21

Page 22: Project Report Prachi

This inventory in efficiency can make a tremendous impact on the bottom line. By tying up as

little capital as possible in inventory, McDonalds can us the cash on hand to open more stores,

increase its advertising budget, or buy back shares. It eases the strain on cash flow

considerably, allowing management much more flexibility in planning for the long term.

PURCHASE

22

Page 23: Project Report Prachi

One of the most important aspects of inventory control is to have the items in stock at the

moment they are needed. This includes going into the market to buy the goods early enough to

ensure delivery at the proper time. Thus, buying requires advance planning to determine

inventory needs for each time period and then making the commitments without

procrastination. For retailers, planning ahead is very crucial. Since they offer new items for

sale months before the actual calendar date for the beginning of the new season, it is

imperative that buying plans be formulated early enough to allow for intelligent buying

without any last minute panic purchases.

The main reason for this early offering for sale of new items is that the retailer regards

the calendar date for the beginning of the new season as the merchandise date for the end of

the old season. For example, many retailers view March 21 as the end of the spring season,

June 21 as the end of summer and December 21 as the end of winter. Part of your purchasing

plan must include accounting for the depletion of the inventory. Before a decision can be made

as to the level of inventory to order, you must determine how-long the inventory you have in

stock will last. For instance, a retail firm must formulate a plan to ensure the sale of the

greatest number of units. Likewise, a manufacturing business must formulate a plan to ensure

enough inventories are on hand for production of a finished product.

In summary, the purchasing plan details, When commitments should be placed; When

the first delivery should be received; When the inventory should be peaked; When reorders

should no longer be placed; and When the item should no longer be in stock. Well-planned

purchases affect the price, delivery and availability of products for sale.

GROWING IMPORTANCE OF PURCHASE

23

Page 24: Project Report Prachi

Traditionally, purchasing was regarded as one of the activities of the production

management. Few important reasons for the change in emphasis are:

1. Higher cost of goods and services -

Raw materials, components and services account for a significant proportion of the

company's total expenditure. Effective purchasing, therefore, can result in a

substantial saving to the company.

2. Escalating cost of stock outs -

Lack of continuity in the availability of materials seriously affects all major companies.

It can damage profitability of the company and lower employee morale. Financial loss

due to stock outs of materials, process industries and in capital-intensive units can be

enormous.

3. Higher present day cost of capital-

The capital distribution between fixed and working capital in a firm is normally

around 60:40. Further, around 80% of the working capital is locked up in inventory.

No organization can afford to invest such a big part of its capital. The bulk of these

stocks can reduce un-necessary capital lockup can be avoided if purchasing is made

efficient.

4. Purchase is not mere act of buying -

Purchasing in today's context includes a wide range of material related activities such as

market research, vendor rating, standardization and variety reduction, codification,

indent control pre-purchase value analysis, price negotiation, inventory control, surplus

disposal., purchase budget, import substitution, purchase system design etc.

5. Changing nature of purchases -

Purchasing today is no longer just commercial activity, but it is techno-

commercial activity. The activity includes technical persons from production,

design and other departments.

24

Page 25: Project Report Prachi

6. Professionalization of material function -

Like other branches of industries, purchase too has experience development of many

management concepts such as: ABC analysis, economic lot size, learning curve, critical

analysis, line of balance, variety reduction, codification, value analysis, vendor rating

etc.

7. Changing concepts of buyer- seller - relationship-

Efficient buying - continuity and availability of material with the lowest inventory -

demands a buyer to be good at business relation. Retention of good supplier, with

increasing competition, is becoming difficult and hence the buying function is

becoming challenging day by day.

OBJECTIVES OF SCIENTIFIC PURCHASING

1. To procure at competitive price the needed material, supplies, tools and services of

the right quality in the right quantity and at the right time.

2. To maintain continuity of supply to ensure production schedule at minimum

inventory investment.

3. To ensure the production of goods of better quality and the competitive price by

procuring materials, which best suits, the product and the purposes for which they are

intend.

4. To suggest better substitutes to material which are currently being used with a view to

lower cost and maintain the quality of the product.

5. To render assistance in standardization, variety reduction, value analysis and cost

reduction programmes.

6. To advice on probable prices, delivery and performance items under consideration by

design, development and estimation department.

7. To create goodwill and enhance company reputation for fairness and integrity through

dealings with the suppliers.

8. To enable company to maintain competitive position and earn a fair return on its

investment.

FUNCTIONS OF PURCHASE DEPARTMENT

25

Page 26: Project Report Prachi

1. Locating, selecting and developing qualified sources of supply.

2. Scrutinizing purchase indents and deciding suitable method of buying.

3. Floating enquires, processing quotation, conducting negotiation and releasing purchase

orders.

4. Pre- delivery follow up and shortage chasing.

5. Co-ordination with inward inspection including timely return of defective materials back

to supplier.

6. Endorsing suppliers' invoices for payment.

7. Processing suppliers request for price increase including price renegotiation.

8. Attending to supplier's representative and traveling salesman.

9. Arranging discussion meetings between supplier's representative and company's officials.

10.Disposal of surplus, obsolete and scrap material.

11.Advising management as regards to new materials, new products, forward buying etc.

12.Acting as a link between company's finance department and suppliers for timely

payments / settlement of suppliers' bill.

13.Attending to periodical activities like applying for import license, quota etc.

14.Maintaining company's image among suppliers.

PRINCIPLES OF PURCHASING (5 P’S)

Elements of scientific purchasing:

Purchasing is the most important function of material management. Scientific purchasing

however, is not mere procurement of needed materials at the lowest price but their procurement

in a way that minimizes the overall cost of the product. To ensure this, scientific purchasing is

governed by five well-known parameters called basic elements of scientific purchasing or also

called "5 R's of buying"

These 5 R's are:

~ Right Quality ~ Right Quantity

~ Right Price

~ Right Time

~ Right Source

26

Page 27: Project Report Prachi

PURCHASING CYCLE

Purchasing activity plays a vital role in all the firms in general and in the manufacturing firms in

particular. Purchasing is not merely "Buying to satisfy the indenter’s requirements" but buying

goods of right quality in the right quantities, at the right time and-at the right price"

Purchase cycle consists of following eight major activities:

1. Establishing and communicating the need for procurement.

2. Scrutiny of the purchase indents.

3. market study and selection of sources of supply

4. order preparation

5. follow up

6. receiving and inspection

7. storage and record keeping

8. Invoicing and payment.

27

Page 28: Project Report Prachi

PURCHASE PROCEDURE OF TECHNOCRAT ENGINEERS

OBJECTIVE

To ensure that adequate technical & conventional data is provided to the vendors/sub-

contractor so as to enable them to supply product/material/service to the specified

requirements & on-time.

SCOPE

This procedure covers direct materials, tools, consumables capital items which go into the

product, packaging materials & service sub-contractors.

Products & services which do not affect the finished product quality are extended.

PROCEDURE

1) PURCHASE INDENT ACCEPTANCE:

a.. Purchase action shall be taken on the basis of purchase indents received from the

concerned department or on the basis of reorder levels fixed for the stock items, as

received from PPC. Indents received from various departments are filed serially.

b. If the items are being procured for the first time, purchase department shall get the

approved drawing or the specification sheet of the items from the indenting department.

2) PROCUREMENT ACTION:

a. Details of all purchase orders released by materials department shall be entered in the

purchase order register & the purchase order number as per the register serially. Control

shall be allotted to the purchase order released.

b. Imported Material: Purchase orders for imported material shall be placed on vendors

selected based on the recommendations of Technocrats Engineers principals, or based on

the past reorder as recommended by engineering department

c. Indigenous raw material: For raw materials & bought out components procured

indigenously purchase order shall be placed on the vendor selected from the list of

approved vendors/sub- contractors. All the purchase order numbers are entered in the 28

Page 29: Project Report Prachi

purchase order register.

d. Capital items: Machine tools & other capital equipment having value more than 1 lakh

shall be procured against 'capital equipment indenting proposals' accompanied by

approved purchase indents. Machine tools & other capital equipments having value les

than 1 lakh shall be procured against approved purchase indent. The indents shall be duly

signed & approved by the Director (Operations).

e. Whenever an order is placed on a new vendor/sub-contractor that is not yet approved, the

P.O shall be typed on trial purchase order.

f. The P.O shall include applicable items from the following:

i. The type, class, grade or other precise identification.

ii. The title or other positive identification & applicable issues of specifications,

drawings, process requirements for approval or qualification of product procedures,

process equipment & personnel.

iii. The title number & issue of the quality system standard to be applied.

g. For regular procured items, an open purchase order shall be placed on the vendors.

Delivery schedule from time to time shall be sent to the vendors. If additional

quantity is required for some orders, amended schedule shall be sent.

h. For regular orders related to brackets & adaptors, the purchase order shall be released

once in a month.

i. Material movement slip shall be used whenever our material is sent outside for

machining/testing.

PURCHASE ORDER & AMENDMENT:

P.O's shall be raised on the vendor/subcontractor selected as above to

authorize the supply of direct material/items/services as per the terms of the

contract & delivery mentioned therein. Purchase orders shall be amended

whenever required & informed to vendor through P.O amendments.

REVIEW OF PURCHASE ORDER:

The P.O shall be reviewed for adequacy of the specified requirements prior

to release. All the three copies of the purchase orders shall be approved of by

the appropriate authorities before release of the P.O to the vendors/sub

29

Page 30: Project Report Prachi

contractors to the concerned department in Technocrat Engineers. The

authorize signatures are indicated.

VERIFICATION OF THE PURCHASED PRODUCT:

Whenever specified in the contract, the customer or his representative shall be allowed for

the verification of the products either at Technocrat Engineers works or at vendor's place of

work. The co-ordination for such verification activity shall be done by marketing co-

coordinator.

DISPOSAL OF NON-CONFORMING MATERIAL:

Non - conforming material shall be disposed off as per the procedure. Nonconformities

observed shall be reported in the non - conformity analysis register for initiating the

required corrective actions. Vendor/sub-contractor shall be intimated demanding corrective

action for repetitive non-conformities through supplier corrective action request.

RESPONSIBILITY AND APPROVAL:

The authorities of the respective department shall be responsible for review,

implementation, control & verification of this procedure. He shall be responsible for

providing all means & facilities for smooth working of this procedure.

30

Page 31: Project Report Prachi

FORMATS OF PURCHASE

PURCHASE ORDER

Our Older No.

M/s..

Date

YOllIRef. No.

Date

Please supply the under-mentioned goods to our works S'Ilbject to corditioim overleaf:

Sr. No. Description Quantity Per Rate Value

-

- --

Excise: MST/CST.

Octroi: Freight

Delivery:

Payment Terms:

Remarks

31

Page 32: Project Report Prachi

PRUCHASE INDENT

Purchase Indent I~o,: Date:

Please Puchase the following materials for

Sr. No. Description Code

Qty. Reqd. WhenR.eqd

.

Stock on Avg. COllSU- Previo1lS rate

hand mption & OMel'llo.

-

Route

.

Inducted By Stores Purchase

32

Page 33: Project Report Prachi

QUOTATION

BILL OF MATERIAL

STORES ORGANIZATION

Normally substantial amount of company's working capital is invested in stores. Due attention

should be given to stores routine. There should be system of proper accounting of materials and

supplies and it should be given same attention as is given to accounting for money. Raw

materials and supplies are equivalent of cash. They form an important part of manufacturing

Material Code No. A.B.C.&Co. Date

Specimen of quotations File No.

Name of Minimum qty Rate per unit Time of delivery Terms of delivery Otberterms

supplier offered

Desc.

El-O-Matic (India) Pvt. Ltd. Bill OF MATERlAL Main Assly. Pune No.

Sheet No.

Sr. Drawing Description QtyfSet Source Material Reqd. Qty. Stock Stock

No No. Code For Regd. on Short- * (Sets) * Hand * age *

ICHD.BY IDATE I APPR.BY I DATE

33

M/s. G RR NO. &. Date

D. C. NO. &. Date

P. O. NO. &.Date

The following material(s) have been received and inspected as per details below:

Sr. Part Description &. Part No. Receipts Inspection Results

No.

As Per Actually Acce- Rew- Reed Under challan received pted ork with-

out op devia- op. tion

0

- -, -

Vendor/Customer I Accounts Stores I Planning I Sub Cont.

Receipt Purchas

e ,

Page 34: Project Report Prachi

and it is essential that they should be safeguarded and accounted for properly.

TYPES OF RAW MATERIAL

a. Raw Material Stores: -

It is the store where in incoming raw material, which directly contributes to the final

product, is received, stored and issued to the production department at various stages.

b.Engineering Stores:

In this store, materials required of running of plant, which do not directly contribute as a part

of finished product, are stored. Machinery spares, consumables, stationery etc. are stored in

this and issued as per requisitions raised by various users.

c. Finished Goods Stores:

It is the place where the finished products are stored after production and are ready to

dispatch to the respective locations or warehouses.

34

Page 35: Project Report Prachi

FUNCIONS OF STORES DEPARTMENT

In the company, the duties or functions broadly cover three types - physical task of storing and

preserving material, technical job of providing storing facilities and administrative procedure

for documentation and accounting of material movements. Referring to a full - fledged

storehouse of Technocrat Engineers the following duties and function can be enlisted.

1. Classification and codification of numerous materials by using suitable method of

codification is done in the stores. Then the manual of material - codes is circulated

among store staff and other concerned department managers.

2. The stores department takes physical charge of the material forwarded by goods

receiving and inspection section and places them in the respective bin.

3. The stores department provides necessary facilities for preserving the quality of

materials as long as they are in its custody.

4. It examines that issue procedure is properly followed by confirming the materials

supplied to production department only against written formal request/demand by

authorize through document material requisition note.

5. It keeps watch on actual stock level and compares the same with pre-set stock

limits (Maximum, Minimum, Reordering etc.) so that stock moves within limits.

6. Department prepares purchase requisition note for getting replenishment of stock

when actual quantity reaches reordering level.

7. The department carryout a regular review of stock for slow and fast moving

materials, damaged and substandard materials and reports such facts to top

management.

8. It ensures that correct accounting entries are entered in stock register and records for

each transaction like receipt, issue, return to supplier return from shop floor.

9. It arranges for all type of information and data required by top management and

other concerned officers, specially keeping ready the details of stock position /

balances.

10.The stores department undertakes physical verification (stock taking) for reconciling

actual balance with the book balance and identifying discrepancies, if any, with

possible causes for the same.

Page 36: Project Report Prachi

STORES DOCUMENTS AND RECORDS

Importance of stores documents & records:-

The stores department is all the time expected to give latest information about stock

balance, movement of the materials, and condition of the material. Such reporting has to be

based on some authentic source and hence, the stores and other concerned departments -

purchase, production, costing have to record their instructions, actions, decisions by using

well designed documents and registers. The store keeper is primarily held answerable for

each and every internal movement of materials, particularly for the stock under his custody.

Proper safeguarding and identification of materials should be done by the storekeeper.

STORES ACCOUNTING RECORDS

There are two basic records of inventory control viz. Bin Cards maintained by store keeper and

store ledger accounts kept by costing department. It is the parallel accounting exercise based

on same facts, recording same transaction i.e. movements of materials. Simultaneously posting

of same entries in two independent sets of accounts offers facility of reconciliation, which in

turn acts as an effective tool of inventory control.

BIN CARDS:-A bin card is used by storekeeper to keep quantitative records for all the

items of materials and goods in his stores. This is a document maintained by store

keeper in his stores to assist him to control stock.

The format of the bin card is given below: A bin card is used for each material. Each

receipt, issue or return is recorded on the bin card in a chronological order and the latest

balance is shown after each receipt and issue. Bin card is hung up in a convenient place

outside the bin, rack or shelf. Bin cards are hung near the bins, so that they are readily

available for making entries as and when the goods are placed into the bin or taken out. All

bins racks or shelves, etc. should be numbered consequently in order to indicate their

location to the store keeper and his assistance. This numbering also serves to connect the

bin card with the bin, to which it belongs.

Page 37: Project Report Prachi

STORES LEDGER SYSTEM

It is kept in the costing department. The store ledger is generally maintained in the form of

loose leaf cards, because they can be removed and inserted easily. Each account in store

ledger represents an item of material. The format of store ledger is shown below: -

The store ledger provides a continuous record of material and stores, received, issued,

returned or transferred. It discloses the balance in hand both in quantity and value at any

point of time. It serves the management with the perpetual inventory record for necessary for

decision making. Material Receipt Report, Material Requisition, Material Return Note form

the basis for making entries in store ledger accounts. Entries made in the store ledger are

identical to those on bin cards except that money values are shown only in store ledger. It is

very important that store staff should have nothing to do with writing up of stores ledger

account, which should be written only by the staff of costing department.

Since both bin card and store ledger account are written up from the same basic document,

the quantity balance are shown by these records should agree. The reasons for discrepancies

bin balances fewer than two sets are due to such reasons as:

a. Failure to post a particular transaction

b.Wrong posting in store ledger account

c. Wrong casting

d.Theft and

e. Items placed in wrong bin.

To avoid the problem of disagreement, the two sets should be reconciled either continuously

over a period. For automatic reconciliation, store department sends the original documents to

the revised balance of bin card after its inclusion. Costing department watch that the balance of

bin card intimated with the original document is correct.

Page 38: Project Report Prachi

FORMAT OF STORE LEDGER

Store Ledger Account X.Y z. & Co

Material Maximum Stock

CadeNo: Minimum Stock

Bin No: Re-older Level

Unit: Ordering Qty

On:lered Reserved Received

Date Ref. Qty. Date Ref. Qty. Date ORNote Qty. Rate Value

Issued Stock Stock verified

SrNo. Qty. Rate Value Qty. Rate Value Date Initials Remks.

Page 39: Project Report Prachi

CLASSIFICATION OF MATERIALS

MEANING

A manufacturing or a servicing organization generally requires large number of items.

Handling of such items - planning, procurement, storage, and accounting - becomes difficult if

each one of them is handled separately. Some sort of classification, therefore, is a must since

concentration of effort according to class system is more efficient and effective compared to

diluted effort corresponding to individuals.

DEFINITION

Classification of the materials is the process of grouping of items into few categories,

according to some criteria. Since an item can be placed into more than one class depending

upon the criteria used, some sort of formal classification, therefore, is a must.

OBJECTIVE OF CLASSIFICATION

Classification of materials is required to-

Evolve procedures of planning and control of materials in a class.

Decide systems of storage and issue of materials in a class.

Devise accounting and evaluation procedures common to all materials in a class.

BASIS OF CLASSIFICATION

Materials can be classified either on the basis of-

1. Stage of conversion process

2. Nature of materials

Page 40: Project Report Prachi

3. Usability of materials

1. CLASSIFICATION ON THE BASIS OF CONVERSION PROCES:

In a manufacturing organization, store materials can be classified broadly into direct materials

and indirect materials.

2. CLASSIFICATION ON THE BASIS OF NATURE OF MATERIALS:

It can be classified into following categories:-

Raw materials-

Raw materials are the basic materials which have not undergone any conversion since their

receipt from suppliers. They are the basic materials from which company’s parts/products are

manufactured.

Raw materials are further classified into;

a. Direct materials

b. Indirect materials

Consumables -

Consumables are the materials which both cease to exist or change their shape during

the manufacturing process and as such cannot be used for the second time. Examples of

consumable items are coal, coke, lubricants, cotton waste and stationery items.

Chemicals -

Chemicals are the substances in the form of powder, liquid, tablets etc. that undergo

certain process according to a devised formula. They require be storing, preserving and

issued very cautiously after a careful scrutiny since they involve risks. Examples are

chemicals like acids.

Inflammable items -

Inflammable items are the materials which are highly susceptible to fire. Being

Page 41: Project Report Prachi

hazardous, they require being stored farther from the main store with complete fire-

fighting equipment as standby.

Furniture-

Furniture is the movable items of a house or a place. It requires large storage space,

careful handling and maintenance of proper records of their repairs, renewals and

replacements.

Perishable materials -

Perishable materials are the materials which are short lived and decay easily. Such

materials require being stored in temperature controlled rooms to prolong their life.

Packaging -

Packaging materials are the materials including wrapping materials, protective coating

and containers.

Empties-

Empties are the used packages, which have been scrapped after use. Examples are

wooden cases, metal containers and glass wares.

Supplies-

Supplies include materials used up in running of the plant or in the making of

company's products but do not themselves to into the product.

3. CLASSIFICATION ON THE BASIS OF USABILITY OF MATERIALS:

Serviceable and Unserviceable Material-

Serviceable materials are the items, which have gone temporarily out-of-order and can

be put back into use after repairs.

Unserviceable materials are the items, which have outlived their life or gone out-of-

order permanently or damaged so badly that they cannot be repaired or their repair is

economically inadvisable.

Page 42: Project Report Prachi

• Semi- Finished and Finished Materials -

Semi- Finished materials are items in the partially completed condition of manufacture

and need some further processing before they are ready for sale/shipment to the

customer. Finished materials on the contrary are the items which have been

manufactured in complete form by the production department and are ready for sale.

• Dead Stock Items -

Dead stock items also called capital equipment are the furniture, office equipment,

material handling equipment, machinery, tools and other items which have definite life

and cannot be written off before the expiry date of their life.

Obsolete Items

Obsolete items are the items, which have gone out of date because of new invention in

design, use, etc. and therefore cannot profitably be used.

Page 43: Project Report Prachi

IDENTIFICATION OF MATERIALS

MEANING

Identification is the tracing of the part description, or part number including size, material of

construction, source of supply, batch number etc.

Proper identification is necessary to

Ensure issue of correct items

Sort out mix up of materials of same size of different specifications

Track identity of the batch number through different stages of operations.

Identify source of supply for the material accepted initially but found defective

during processing.

Differentiate items manufactured/procured to current and obsolete drawings.

METHODS OF INDENTIFYING MATERIALS

• Tagging or Labeling - Identification tags, made of paper board or tin plate can be either kept

along with items or affixed on the item itself .

• Writing or Plating - Identification details can be written on the cartons or drums or items in

ink, glass making crayons, paints etc.

Engraving- Vibrating marking tools can be used to engrave identification details.

• Etching - Stamping operation may not desirable on certain components. Chemicals may etch

code number in such items.

• Colour Coding - Raw materials/rubber parts in different specifications may be identified by

Page 44: Project Report Prachi

colour codes.

CODIFICATION

MEANING

An important factor concerning indenting, purchasing and issuing activities is an accurate and

logical identification of materials. Wrong identification results in wrong purchases and/or

issuance of a different item than what is intended. Codification systems too are not perfect but

codes are shorter and as such minimize errors.

Example: LIC has a wide clientele and to identify a client by his/her name, if it is not entirely

impossible it is certainly very difficult, since there can be several persons with the same names

and perhaps with the same surnames or initials. LIC, therefore, identifies its policyholders by

policy numbers consisting of numerals.

DEFINITION

Codification in an industry is the systematic concise representation of equipment, raw

materials, tools, spares, supplies etc. in an abbreviated form employing alphabets, numerals,

colors, symbols etc.

BENEFITS OF CODEFICATION

• Accurate and logical identification -

Correct quality descriptions are necessary to ensure that items are indented, purchased, stocked

and issued correctly. Codification makes it possible since each item is assigned a unique code

after due considerations to its group, kind, size, specifications and dimensional characteristics.

• A voidance of long and unwieldy descriptions

• Prevention of duplication

Page 45: Project Report Prachi

• Product simplification (variety reduction)

• Efficient storekeeping

• Accurate and reliable recording and accounting

• Easier computerization

TECHNIQUES OF INVENTORY MANAGEMENT

[A] FIXATION OF LEVELS

[B] SELETIVE €ONTROL OF INVENTORIES

A-B-C ANALYSIS

X-Y-Z ANALYSIS, etc.

[C] JUST - IN- TIME (JIT)

.[D] ANALYSIS OF INVESTMENT IN INVENTORY

[A] FIXATION OF THE LEVELS

The basic objective behind fixation of these levels is to avoid overstocking and

understocking. In addition to this one more level of inventory takes care that orders are to

be placed only when a particular level is reached. These levels are explained below:

1. RE-ORDER LEVEL:

This level is that level of material, at which when the inventory is reached, fresh

orders are placed. While fixing the re-order level

a. Maximum consumption

b. Maximum delivery time or lead-time should be taken into consideration.

Mathematically the re-order level can be worked out as under:

2. MAXIMUM LEVEL:

This is the highest level of inventory to be maintained above which the inventory

should not rise. While fixing the maximum level, factors like minimum

consumption, minimum re-order period as well as the re-order quantity is to be

Page 46: Project Report Prachi

taken into consideration. Other factors like storage space, interest on capital blocked

in inventories is also taken into consideration. The formula for calculating

maximum level is as follows:

Maximum level = Re-order level- [Minimum usage * Minimum delivery time] +

Reorder-quantity

3. MINIMUM LEVEL:

The minimum level is the level of the inventory below which the actual inventory should

not fall. While fixing the minimum level normal consumption and normal reorder period

are taken into account. The minimum level can be calculated with the help of the

following formula:

Minimum level = Re-order level - [Minimum usage * Average delivery

time in weeks]

4. AVERAGE STOCK LEVEL:

Average stock level = Maximum level + Minimum level/2

[B] SELECTIVE CONTROL OF INVENTORIES

Selective treatment of inventories is based on the following basic philosophy of business:

"Neither one can control everything nor should one try to do so. Uniform control is rarely

effective. Effectiveness results when important aspects of a problem are pursued more

rigorously than others. A major portion of managerial time should be spent in performing

more important jobs. Less important tasks - those involving routine decisions and which

involves less risk - should be delegated to a lower level."

Selective control is a very simple approach. It is the avoidance of the "PENNY WISE &

POUND -FOOLISH POLICY".

Page 47: Project Report Prachi
Page 48: Project Report Prachi

THE ABC CLASSIFICATION:-

ABC analysis is a selective control technique which is required to be applied when we want to

control value of consumption of the item in rupees obviously when we want to control value of the

consumption of the material we must select those materials where consumption is very high. The

ABC classification system is to grouping items according to annual sales volume, in an attempt to

identify the small number of items that will account for most of the sales volume and that are the

most important ones to control for effective inventory management. ABC analysis is a system in

inventory management to minimize the cost of inventories incorporated in which are stored for long

time, these are classified into ABC groups whereas A stand for the most expensive inventories which

are purchased on customers demands so that it can be processed & then given to them on priority

basis, these items are carefully selected. B is classified for those goods which are less expensive than

A items in which can be stored for some time before it is processed and goes for those items which

are cheap in also can be abundantly used. These are items where its loss won’t cost much to the

company. ABC is class of inventory item.

A is the most important and the most expensive- under a ABC regime for minimum stock value A

should be managed by JFT since-its value makes this close management cost-effective

B are intermediate and medium expensive- .under a ABC regime for minimum stock value B

should be managed by Kanban pulling- the micromanagement by JIT is not cost effective for this

project but it should still be tracked methodically.

C are low value items- under an ABC regime for minimum stock value C should be managed by 2

bin- whereby two huge bins of (e.g. screws) item are kept and one is used at a time- when one runs

out another is ordered and the next bin is used. The low value does not justify management- and any

downtime because of running out would cost much more than the product itself.

In an analysis it is decided which products are A, B or C and exactly how they will be managed. In

any company manufacturing, there are number of items which are consumed or traded it may run

into thousands. It is found after number of studies of different companies that –

Page 49: Project Report Prachi

On the basis of above analysis these items are termed as ABC items as detailed below:

A-items- these are those items which are found hardly 5%--10% but their consumption may

amount 70%--75% of the total money spend on materials.

B-items-these are those items which are generally 100/0--15% of he total items and their

consumption amounts to 10%--15% of the money spend on the materials.

C-items-these are large number of items which are cheap and inexpensive and hence

insignificant. They are large in number s running into hardly 5%--10% of the total money

spends on materials.

Based on the above analysis decision can then be taken as to-

How to control the consumption value (rupees) and bring it down.

Value of consumption of No. of items Grade

items (value in Rs).

70% of consp. 10% of no. of items A

20% of consp. 15% of no. of items B .

10% of consp. 75% of no. of items C

Page 50: Project Report Prachi

CONTROL PEOCEDURE ARE GIVEN BELOW:-

A-items-someone at senior level must be made responsible to regularly review the consumption of

overseas items up to date and accurate records should be maintain for this items. The inventory of

these items must be minimum and the orders for these items should be staggered. So that timely

arrival of these items is insured attempt must be made to reduce internal and external lead-time of

these items. Safety stocks of these items should be minimum because frequency of ordering this

items are kept high, price discount for this items should not be avail because physical ordering is

very frequent.

B-item-this items should be kept under normal control and goods report keeping must be maintain.

Safety stock of these items can be moderate. Price discount can be avail and physical stocktaking

can also be moderate.

C-items-little control is required for c-items and the job of controlling should be left lower level

people such as those in charge of store. Large quantity or inventories can be maintain these stock

because they are cheap, so as to avoid stock out situation these items should not kept under lock and

key and must be kept at convenient places open to all for uses safety. Stock of these items can be

sufficient to avoid probability. Price discount can be avail to purchase in bulk quantity because they

are cheap. Physical checking of the stock can be done rarely once in six months.

Page 51: Project Report Prachi

HOW TO CARRY OUT ABC ANALYSIS:

It is better to go through records of the stores for number of years and find out names of all items

consumed during the year, their average yearly consumption in units and average price per unit is

also found out as shown-

NAME OF AVERAGE AVERAGE AVERAGE RANKING.

THE ITEM. ANNUAL PRICE PER VALUE OF

CONSUMPTIONUNIT (y). CONSP (x*y)

UNITS (x). RS.

A A 4000 10 40000 01

B B 600 10 6000 05

C C 2000 16 2000 03

D D 3500 01 3500 07 .

E E 50 08 400 11

F F 6000 06 36000 02

G G 2400 05 12000 04

H H 4200 01 4200 06

I 50 10 500 10

J 100 07 700 09

K K 80 40 3200 08

L L 50 08 400 11

Page 52: Project Report Prachi

Arrange the item in the order of their ranking starting with the first rank i.e. highest to lowest

consumption and calculate cumulative annual consumption and cumulative annual consumption

percentage as shown-

RANK. NAME AVERAGE CUMMULATIVE CUMMULATIVE CATEGORY.

OF CONSP ANNUAL CONSP ANNUAL CONSP

THE VALUE (RS). (%).

ITEM. (RS).

01 A 40000 40000 28.7 A

02 F 36000 76000 54.6 A

03 C 32000 108000 77.7 A

04 G 12000 120000 86.3 B

05 B 6000 126000 90.6 B

06 H 4200 130200 93.7 B

07 D 3500 133700 96.2 C

08 K 3200 136900 98.5 C

09 J 700 137600 98.8 C

10 I 500 138100 99.2 C

11 E 400 138500 99.5 C

11 L 400 138900 99.8 C

Page 53: Project Report Prachi

XYZ Analysis

X- Y -Z analysis is based on value of the stocks on hand. Items whose inventory values are high

are called X items while those whose inventory values are low are called Z items. And Y items are

those which have moderate inventory stocks. This type of analysis is carried out from the point of

view of value of balance stocks lying in the stores from time to time and classifies all the items as

given below.

‘X’ items are those items whose value of balance stock lying in the stock is very high.

'Y' items are those items whose value of balance stock is moderate.

'Z' items are those items whose value of balance stock lying in the stocks is very low.

After- knowing this type of classifications and their items can be taken to control the situation as

shown below:

1] From security point of view high value items must be stored and kept under lock and key or if

not possible they should be kept in such a way that they are always under supervision. Similarly

arrangement can be made for y and z items accordingly.

2] From inventory control point of view we must know why there is high inventory for 'X' items.

We should review inventory control procedure for each and every high item because stock should

be maintained to take care of lead-time consumption and also to provide safety stocks. For high

value items lying in stores we should review the reasons for long lead-time as well as demand

variations and see whether lead time consumption and safety stocks can be reduced. Thus proper

inventory control procedures can be developed on the basis of XYZ analysis.

XYZ analysis when combined with ABC analysis is used as under:

CLASS OF A B C

ITEMS

X Effort to be made reduce Effort to be made to Steps to be taken to

stocks to Z category convert them to Y dispose off surplus

category stocks

y Efforts to be made convert - Control may be

these to Z category. further tightened

Z - Stock levels may be -

reviewed twice a year

Page 54: Project Report Prachi

Selective control advocates control by exception. Uniform treatment of all items given diffused

effect besides being expensive. Items should be classified so that a major portion of effective

managerial time is spent on those materials which are more important than others. Thus proper

selective control methods should be selected to control the materials and prevent from facing loss,

taking advantage and knowing what exactly is to be done.

[C] JUST IN TIME (JIT)

Just in time is to produce and deliver finished goods just in time to be sold, make sub-assemblies just

in time 10 be assembled into finished goods, fabricate/purchase parts just in time to go into sub-

assemblies and procure raw materials just in tim0 to be transformed in to fabricated parts. JIT is a

complete business philosophy and the process of thinking, working and managing to eliminate

waste. TOYAT A, the originator of the JIT concept, defines waste as "anything other than minimum

amount of equipment, materials parts and working time absolutely essential to production."

OBJECTIVES:

1. Elimination of wastage in its many forms

2. Belief that ordering/holding cost can be reduced

3. Reduction in equipment lead time

4. Adjustment in the fluctuations in supply of material

5. Enhancement of quality

IMPLEMENTATION OF JIT CAN LEAD TO THE FOLLOWING BENEFITS TO THE

USER

Reduction in manufacturing lead time

Defects free production

Lower inventory investment

Greater conformance to delivery commitment

Lesser cost of production

Faster response to market needs

Improved morale of the work force.

Page 55: Project Report Prachi

TECHNIQUES OF JIT

Set up time reduction

JIT machining cells

JIT layout

The pull system (The Kanban system of production control)

Just in time purchasing

Quality at source

Employee involvement.

[D] ANALYSIS OF INVESTMENT IN INVENTORY

One of the major areas of decision - making for a finance manager is the investment decisions in

inventory. In the inventory, a large portion of the funds of a firm are invested. Therefore, whenever

a change in the inventory level is to be made, the profitability of such change should be found out.

In other words, the inventory policy of a firm will maximize the value of the firm at such point

where the incremental return from investments in inventory is either equal to or more than the

incremental cost of funds used for financing inventory.

Page 56: Project Report Prachi

DATA ANALYSIS

LIST OF PHYSICALLY CHECKED INVENTORY:

The lists of inventories in accordance with above mentioned categorization were procured from the management information system/electronic data processing department. The format is shown as below:

REVIEW OF ALL THE ITEMS AT THE STORE:

SR NO. DISCRIPTION RATE1. 1 CORE PVC CABLE 16 MM2 89.002. 1 CORE 1 MM2 BLACK 5.893. 1 CORE 1 MM2 BLUE 5.894. 1 CORE 1 MM2 GREEN 5.895. 1 CORE 1 MM2 GREY 5.896. 1 CORE 1 MM2 ORANGE 5.897. 1 CORE 1 MM2 RED 5.898. 1 CORE 1 MM2 WHITE 5.899. 1 CORE 1 MM2 YELLOW 5.8910. 10 PIN PLUG PRIYANTRONIX 30311. 10 PIN RECEPTACLE PRIYANTRONIX 29312. 2 CORE PVC CABLE 1.5 MM2 2413. 2 ROLL DRIVE WITH G BOX ( 250 RPM) 1850.0014. 2 ROLL DRIVE WITH G BOX ( IMPORTED) Geared

roller 3100.0015. 2 ROLL DRIVE WITH G BOX ( IMPORTED) Plain

roller 3100.0016. 3 CORE PVC CABLE 1.5 MM2 3117. 3 PIN PLUG & SOCKER MS TYPE 10818. 3 PIN PLUG PRIYANTRONIX ( TORCH) 5919. 3 PIN RECEPTACLE PRIYANTRONIX (WF/PS) 5520. 4 CORE PVC CABLE 1.5 MM2 4121. 4 CORE PVC CABLE 2.5 MM2 6622. 4 PIN PLUG PRIYANTRONIX 6423. 4 PIN RECEPTACLE PRIYANTRONIX 5824. 4 ROLL DRIVE UNIT WITH G BOX ( 145 RPM) 5900.0025. 4 ROLL DRIVE UNIT WITH G BOX ( 66 RPM/37

RPM)With Motor 8150.0026. 4 ROLL DRIVE WITH G BOX (IMPORTED) 4500.0027. 6 PIN PLUG & SOCKET ( MS TYPE)28. 92 TEETH 330.0029. AFCO TAG ( SOLDERING TYPE) 0.1030. ALU PLATE ( CHOKE MTG) 10.00

Page 57: Project Report Prachi

SR NO. DISCRIPTION RATE31. AMEETER 0-1500 A 33332. AMMETER 0-1000 A 33333. AMMETER 0-400 A 33334. AMMETER 0-600 A 33335. ANTI SPATTER SPRAY 500 ML 68.0036. ANTISPATTER GEL 300 GM 55.0037. BAKELITE INS PLATE 55.0038. BAKELITE STRIP ( INPUT CABLE) 1039. BEARING 6004 125.0040. BEARING 6006 185.0041. BEARING 6007 225.0042. BEARING 6009 240.0043. BEARING 6010 485.0044. BEARING 6011 552.0045. BEARING 6202 80.0046. BEARING HOUSING (MS) 100*65 1840.0047. BEARING HOUSING (MS) 125*100 2+3 1840.0048. BEARING HOUSING 100MM DIA*125 MM LONG 960.0049. BK WASHER AND BUSH ( FOR O/P TERMINAL) 1350. BK WEDGES ( FOR CHOKE) 5.0051. BOBBIN NO 13( 2 NOS/SET) 4.0052. BOBBIN NO 7 ( 12 NOS/SET) 7.0053. BRASS NIPPLE ( GAS HOSE) 12.5054. BRASS NIPPLE 3/8" * 1/8" 20.0055. BRASS NUT (GAS HOSE) 12.5056. BRUSH HOLDER ASSY WITH OUT BRUSH 20* 40 600.0057. BRUSH HOLDER ASSY Without BRUSH(8*10) V

TYPE Small 180.0058. C TYPE STRIP 18.0059. C.S.T 2.5 TERMINAL 7.0660. CAPACITOR 0.1 MFD 630V ( 6 NOS/SET) 7.0061. CARBON BRUSH 20*40 225.0062. CARBON BRUSH FOR MARTIN MOTOR 25.0063. CARBON BRUSH V 8*10 (SMALL) 75.0064. CARTRIDGE (WITH SEALING RING) 159.0065. CEBORA TIG 1565 IMPORTED 90000.0066. CERAMIC NOZZLE 2410640/WG2411 22.1067. CERAMIC NOZZLE 2411040 /WG2413 22.1068. CERAMIC NOZZLE 2461036/WG2463 22.1069. CERAMIC NOZZLE SAP 10 N 47 32.0070. CERAMIC NOZZLE SAP 10 N 48 32.0071. CHOKE BLOCK 63* 63* 180 MM (Duly drilled &

tapped) 300.0072. CHOKE CP 300 1872.00

Page 58: Project Report Prachi

SR NO. DISCRIPTION RATE73. CHOKE CP 400 3710.0074. CHOKE MTG ANGLE 10.0075. CHUCK PLATE 300* 16 MM 650.0076. CO2 WELDIN G TORCH RB 61 GD RGZ-2 3 MTR 12000.0077. CO2 WELDING TORCH 36KD 3250.0078. CO2 WELDING TORCH 40 KD (WITH 65 MM2 C/S

CABLE) 4800.0079. CO2 WELDING TORCH M/C MOUNTING NM24,0.75

mtr 1250.0080. CO2 WELDING TORCH NM24 2000.0081. CO2 WELDING WIRE 0.8 MM 15 KG SPOOLS TATA

MAKE 1020.0082. COLLET 1.6 MM SA26 10N23 27.0083. COLLET 2.0 MM SA 26 27.0084. COLLET 2.4 MM SA 26 27.0085. COLLET 3.2 MM SA26 27.0086. COLLET BODY 2.4 SA26 10N32 58.0087. COLLET BODY1.6 SA26 10N31 58.0088. COLLET GC 20 1.6 MM 26.0089. COLLET GC 20 2.0 MM 26.0090. COLLET GC 20 2.4 MM 26.0091. COLLET GC 20 3.0/3.2 MM 26.0092. CONTACT TIP 0.8 MM HD M6 10.0093. CONTACT TIP 0.8 MM LD M6 5.9094. CONTACT TIP 1.2 MM M6 LOW DUTY 5.9095. CONTACT TIP 1.2 MM M8 29.0096. CONTACT TIP 1.2 MM M6 H DUTY 10.0097. CONTACT TIP 1.6 MM M8 29.0098. CONTACT TIP 2 .0MM M8 30.0099. CONTACT TIP 2.0 MM M10 ( FOR M 750) 70.00100.

CONTACT TIP 2.8 MM M8 30.00101.

CONTACTOR 16 AMPS 42 V AC BCH 659.00102.

CONTACTOR 40 AMPS 1797.00103.

CONTACTOR 6 AMPS D 15 SERIES 3no+ 1nc 469.00104.

CONTACTOR 80 AMPS 3900.00105.

CONTACTOR AUX CONTACT BLOCK 2NO 2 NC 158.00106.

CONTACTOR AUX CONTACT BLOCK 4NO 158.00

Page 59: Project Report Prachi

107.CONTROL PANEL (SMALL) 950.00

108.CONTROL PANEL 480*620*240 WITH INSIDE TRAY 1226.00

109.CONTROL PENDENT BIG 265.00

110.CONTROL PENDENT SMALL 162.00

111.CONTROL X MER ( PS) 1750.00

112.CONTROL X MER ( SPM) 1750.00

113.CONTROL X MER ( WF) 300.00

SR NO. DISCRIPTION RATE114.

CORRUGATED BOX ( TIG) 31*15*22 7 PLY 0.00115.

CORRUGATED BOX CP 222 30"*17"*22" 62.00116.

CORRUGATED BOX CP300 33*18.5"*24" 64.00117.

CORRUGATED BOX CP400 32"*22.5"*29.5" 79.00118.

CORRUGATED BOX W F 21"*13.5"*18" 59.50119.

COTTER PIN 3/16 * 2" 1120.

D WASHER 5.00121.

DC.TIG INVERTER UNIT ( SAGAR MAKE) 42000.00122.

DIN RAIL STRIP 25.00123.

DIODE 150LF 40 RUTTONSHA 285.00124.

DIODE 16FMR 40 150+15 30.56125.

DIODE 250 RUTTONSHA 425.00126.

DIODE 351 UF 1114.00127.

DIODE CLAMP ( 6 NOS/SET) 4.00128.

DIODE D 305 ( RECTIFIER HOUSE) 515.00129. DIODE D155 A RECT HOUSE 265.00

Page 60: Project Report Prachi

130.DOOR KNOB FOR WIRE FEEDER 10.00

131.EARTHING RING ( GUN METAL) Nitin Industries 2+3 725.00

132.END CLAMP 2.75

133.END PLATE 2.00

134. EXPANSION MODULE FL1B M08B2R2 MAKE ADEC 3240.00

135.EYE BOLT 16 MM 40.00

136.FAN 15" 1650.00

137.FAN 18" 2210.00

138.FAN 24" 4200.00

139.FAN 9" 950.00

140.FAN12" 1350.00

141.FIBRE WASHER 0.30

142.FINDER SOCKET 38.00

143.FIXED JAWS (SPM FIXTURE YUTAKA) 300.00

144.FIXED WHEEL 150 * 50 193

145.FIXED WHEEL 150* 50 WITH BKT 504

146.FIXED WHEEL 300 * 50 470

147.FLOWMETER (CO2/AR) WELDCUT 420.00

148.F-R-L UNIT1/2" JENITICS MAKE 1980.00

149.FUSE HOLDER MF 20 31.00

150.FUSE HOLDER SLP 15 42.00

151.GAS DIFFUSOR 36KD 8.00

152. GAS DIFFUSOR 40 KD 18.00

Page 61: Project Report Prachi

153.GAS DIFFUSOR NM24 8.00

154.GAS HOSE RUBBER BLUE 8 MM 40.00

155.GAS PREHEATER ASSY 220V 700.00

156.GEAR 92 TEETH & 23 TEETH SET 670.00

SR NO. DISCRIPTION RATE157.

GEAR BOX (ITALLIAN) BONFIGLIOLI 3500.00158.

GEAR BOX 100 RPM 1500.00159.

GEAR BOX 145 RPM 1500.00160.

GEAR BOX 37 RPM 1500.00161.

GEAR BOX 66 RPM 1500.00162. GLASS FUSE 15 AMPS ( SLOW BLOW TYPE) 6* 32

MM 3.60163.

GLASS FUSE 4 AMPS ( SLOW BLOW TYPE) 5*20 2.40164.

HANDLE GRIP 10.00165.

HEAT SINK BIG & SMALL ( 6 NOS/SET) SET 28+36 332.76166.

HEATING ELEMENT 110 V 65.00167.

HEATING ELEMENT 230 V 65.00168.

HOSE CLIP 16 MM (GAS HOSE) 12.00169.

INLET NOZZLE 30.00170.

INNER TUBE 158.00171.

INSULATING BUSH ( MS) 2 ROLL 48.00172.

INSULATING BUSH (PC) 2 ROLL 35.00173.

INSULATING CAP ( MS) 2 ROLL 10.00174.

KNOB,POINTER,CAP FOR ABOVE 20,14,40 14.00

Page 62: Project Report Prachi

175.L BK SUPPORT ( 6 NOS/SET) 7.00

176.L TYPE PIPE 100.00

177.LED 10 MM 8.00

178.LED HOLDER 6.00

179.LED PCB ASSY 20.00

180.LED PCB BLANK 2.00

181.LINEAR BEARING LM16UU 110.00

182.LINEAR BEARING LM25UU 180.00

183.LONG CAP GC 20 WG 240 2402 ( WG2402) 73.00

184.LONG CAP SA26 57Y02 52.00

185.LUG ( SOLDERING TYPE B5 ) ( 12NOS/SET) 0.10

186.MAIN SHAFT ( 250 RPM G BOX) 75.00

187.MAIN SHAFT ( SINGLE) 2000.00

188.MAIN SHAFT ( TORCH ROTATION SYSTEM) 1900.00

189.MAIN SHAFT (DOUBLE) 90MM DIA 2300.00

190.MAIN SHAFT 2 ROLL 75.00

191.MAIN SHAFT 4 ROLL 110.00

192.MAIN SHAFT WITH BEARING( PC) 110.00

193.MAIN TRANSFORMER CP 222 10123.00

194.MAIN TRANSFORMER CP 300 11271.00

195.MAIN TRANSFORMER CP 400 22373.00

196.MALE CONNECTOR 1/8" BSP 25.00

197.MICRO SLIDE ASSY 1500.00

Page 63: Project Report Prachi

198.MOTOR MTG BKT 35.00

199.MOTOR MTG PAD SHOE 6.00

SR NO. DISCRIPTION RATE200.

MOVING JAWS (SPM FIXTURE YUTAKA) 350.00201.

N.C.ELEMENT 34.85202.

N.O. ELEMENT 34.85203.

NIPPLE ( PREHEATER) 30.00204.

NOZZLE 36 KD 75.00205.

NOZZLE 40 KD 130.00206.

NOZZLE CLEANING TOOL 5.00207.

NOZZLE FOR M750 450.00208.

NOZZLE MB25 (11) 50.00209.

NOZZLE MB25 (14) 50.00210.

NOZZLE NM24 35.00211.

NOZZLE SPRING MB25 5.50212.

NUT ( PREHEATER) 30.00213.

NYLON PAD 8.00214.

NYLON WASHER 16 MM 2.00215.

O RING SMALL 2.00216.

OUTER TUBE 84.00217.

OUTPUT BRASS BODY 70218.

OUTPUT KNOB 14219.

OUTPUT TERMINAL ASSY(WITH KNOB) 90220. PCB ASSY( SPEED CONTROL) 1550.00

Page 64: Project Report Prachi

221.PCB ASSY( WIRE FEEDER) 1700.00

222.PCB BLANK WIRE FEEDER 158.40

223.PCB BLANK( SPEED CONTROL) 111.00

224.PILOT LAMP (LED) 22.5 DIA 141.00

225.PLAIN ROLLER ( 2 ROLL) 30.00

226.PMDC MOTOR 1000 RPM 36 V DC 3200.00

227.PMDC MOTOR 120 W 36 V 5000 RPM MARTIN 1350.00

228.PMDC MOTOR 1500 RPM 36 V DC

229.PMDC MOTOR 180 W 36 V 5000 RPM MARTIN 1900.00

230.PNEUMATIC CYLINDER 63 * 50 MM 1600.00

231.PNEUMATIC CYLINDER 100 * 40 MM ( dutta) 1190.00

232.PNEUMATIC CYLINDER 100 * 40 MM(Shvo Norgen) 1425.00

233.PNEUMATIC CYLINDER PEN TYPE 25*25 750.00

234. PNEUMATIC TIMER WITH 2 BLOCK 230 V BCH MAKE 2630.00

235.PORCELAIN BEAD 0.10

236.POTENTIOMETER 5 K 3 W 38.00

237.POWER SUPPLY UNIT 24 V 2.5 AMPS 975.00

238.PREHEATER BODY 363.00

239.PRESSURE GAUGE(CYLINDER SIDE)P NO5114 210.00

240.PRESSURE GAUGE(DELIVERY SIDE)P NO5244 210.00

241. PROXIMITY REED SWITCH ( FOR CYLINDER MAGNET) 275.00

SR NO. DISCRIPTION RATE242.

PROXIMITY SWITCH NBB5 18GM 50E2 IMPORTED 585.00

Page 65: Project Report Prachi

243.PU6 TUBE 28.00

244.PULLEY CARRIER ASSY 300.00

245.PUSH BUTTON ACTUATOR BLUE 38.25

246.PUSH BUTTON ACTUATOR GREEN 38.25

247.PUSH BUTTON ACTUATOR BLACK 38.25

248.PUSH BUTTON ACTUATOR YELLOW 38.25

249.PUSH BUTTON ACTUATOR WHITE 38.25

250.PUSH BUTTON ACTUATOR MUSHRUM RED 62.00

251.PUSH BUTTON PB 800 H GREEN (INCH/OCV) 31.00

252.PVC CHANNEL 25* 25 50.00

253.PVC CHANNEL 25* 30 54.00

254.RC PCB ASSY 12.00

255.RC PCB BLANK 2.00

256.RECTFIER STACK (FOR TMIG 400) 1700.00

257.RECTIFER MTG FLAT 10.00

258.RECTIFIER MTG L BKT 10.00

259. RECTIFIER STACK ( FOR T ARC 400 RECTIFIER 400 AMPS) 1700.00

260. RECTIFIER STACK ( FOR T ARC 600 RECTIFIER 600(A) A 2400.00

261.RECTIFIER STACK ASSY( FITTED WITH DIODES) 2755.00

262.RECTIFIER STACK ASSY( WITHOUT DIODES) 1045.00

263.REED SWITCH(CURRENT SENSOR) PLA MAKE 165.00

264.REEL HOLDER AXLE 36.00

265.REEL HOLDER WITH NUT 75.00

Page 66: Project Report Prachi

266.REGULATOR WITH FLOWMETER ARGON 1810.00

267.REGULATOR WITH FLOWMETER CO2 1810.00

268.RELAY 57DP O/E/N 65.00

269.RELAY 58 DP OMRON 60.00

270.RELAY 8 PIN 24 V DC 140.00

271.RELAY BASE WITH CLIP FOR ABOVE 90.00

272.RELAY PCO 24 V DC 242.25

273.RELAY RU2 S CD24 WITH BASE & CLIP 14PIN 238.00

274. RELAY RU2 S CD24 WITH BASE & CLIP 8 PIN ADEC 190.00

275.RIVET ( 12NOS/SET) 0.50

276.ROTARY CULINDER SAS-R-32-90 SHAVO NORGEN 7102.00

277.ROTARY SWITCH 1023 104.00

278.ROTARY SWITCH 1039 F6 365.00

279.ROTARY SWITCH 40313F6 742.50

280.ROTARY SWITCH 4034 ON OFF 240.00

281.ROTARY SWITCH 60313D 726.00

282.ROTARY SWITCH 60319 F6 1215.00

SR NO. DISCRIPTION RATE283.

ROTOSEAL ATLAS 2 INPUTS 4657.00284.

ROTOSEAL SINGLE INPUT 1550.00285.

RT51 DRIVE UNIT BOX 1080.00286.

RT51 TURN TABLE WITH COVER 2380.00287.

RUBBER DIPHRAGM 58.00288. S.V. MOUNTING BUSH 2.00

Page 67: Project Report Prachi

289. S.VALVE D COIL 24 V DC SHAVO NORGENJENETICS 1200.00

290.S.VALVE D COIL 24 V DC PATCON PNEUMATICS 1200.00

291.S.VALVE D COIL 5*2 24 V DC JENETICS 1700.00

292.S.VALVE S COIL 24 V DC JENETICS 950.00

293.SELECTOR SWITCH 2 POSITION TECHNIC MAKE 119.85

294.SELECTOR SWITCH 3 POSITION TECHNIC MAKE 119.85

295.SHORT CAP GC20 42.00

296.SHUNT 1000 AMP 1260

297.SHUNT 1500 AMP 1818

298.SHUNT 400 AMP 280

299.SHUNT 600 AMP 875

300.SHUNT 800 AMP 1000

301.SILENCER FIXTURE(ELEPTICAL) JOB A YUTAKA 19320.00

302.SILENCER FIXTURE(ELEPTICAL) JOB B YUTAKA 20110.00

303.SLIDE ASSY FOR ELEPTICAL WEDING SPM 7970.00

304.SLIDE ASSY FOR REFAIR INDUTRIES SPM 13250.00

305.SMART RELAY FL1D-H12RCE MAKE ADEC 5400.00

306.SOLENOID VALVE 230 V AC 502.00

307.SOLENOID VALVE 42 V AC 502.00

308.SPANNER ( TORCH) 10.00

309.SPRING ( BRAKING) 3.00

310.SPUR GEAR 2ROLL 45.00

311. STUD 10* 415 MM ( 2NOS/SET) 35.00

Page 68: Project Report Prachi

312.SUBARC CONTROL UNIT WITH COVER 260.00

313.SWIVEL ELBOW 1/8" BSP 35.00

314.SWIVEL WHEEL 125* 50 609

315.SWIVEL WHEEL 150* 50 WITH BKT 630

316.SWIVEL WHEEL 77* 32 198

317.TERMINAL STRIP 3 WAY 10 AMPS 250 V 8.00

318.TERMINAL STRIP 4 WAY 10 AMPS 250V 10.00

319.THERMOSTAT 85/70 DEGREE 58.00

320.THYRISTOR 3935 RUTTONSHA (Rectifier house) 149.00

321.TIG TORCH GC 20 4 MTR 2815.00

322.TIG TORCH HEAD GC 20 831.30

323.TIG TORCH HEAD GC 2002 001 831.00

324.TIG TORCH HEAD SA26 SA26001 572.00

325.TIG TORCH SA26 4 MTR WITH ERGO HANDLE 2638.00

SR NO. DISCRIPTION RATE326.

TIMER 800 U 750.00327.

TIP ADAPTOR 36 KD 6 MM 8.00328.

TIP ADAPTOR 36KD 8 MM 8.00329.

TIP ADAPTOR 40 KD 8MM 48.00330.

TIP ADAPTOR MB25 8.00331.

TIP ADAPTOR NM24 4.00332.

TOGGLE SWITCH 1031 OFF -ON 48.00333.

TOGGLE SWITCH 2065 NO-OFF-NO 84.00

Page 69: Project Report Prachi

334.TOGGLE SWITCH KT 1021 ON-OFF 48.00

335.TOGGLE SWITCH KT 2061 ON-ON 84.00

336.TORCH CABLE 33.5 MM2 1 MTR NM24 525.00

337.TORCH CABLE 33.5 MM2 1.25 MTR NM24 600.00

338.TORCH CABLE 33.5 MM2 1.5 MTR NM24 700.00

339.TORCH CABLE 33.5 MM2 3 MTR NM24 1350.00

340.TORCH CABLE 50.0 MM2 1.5 MTR 36KD 925.00

341.TORCH CABLE 50.0 MM2 2.0 MTR 36KD 1250.00

342.TORCH CABLE 50.0 MM2 3 MTR 36KD 1850.00

343.TORCH HANDLE ASSY RED 133.00

344.TORCH HEAD 36 KD 650.00

345.TORCH HEAD 40 KD

346. TORCH HEAD M/C MOUNTING GOOSE NECK 36KD 750.00

347. TORCH HEAD M/C MOUNTING GOOSE NECK NM24 550.00

348. TORCH HEAD M/C MOUNTING STRAIGHT HEAD 36KD 750.00

349. TORCH HEAD M/C MOUNTING STRAIGHT HEAD NM24 550.00

350.TORCH HEAD MB25 350.00

351.TORCH HEAD NM24 300.00

352.TORCH HOLDER 28 MM 150.00

353.TORCH HOLDER 38 MM 175.00

354.TORCH KIT MB25 5.00

355.TORCH SLIDE ASSY ( PNEUMATIC) 2850.00

356.TORCH SLIDE MOUNTING BLOCK 150.00

Page 70: Project Report Prachi

357.TORCH SWITCH KIT NM 24 36.00

358. TORCH SWITCH( IMPORTED SINGLE MICRO SWITCH) 415.65

359.TRIGGER SWITCH MB25 60.00

360.TROLLEY AND COVERS CP 222 1650.00

361.TROLLEY AND COVERS CP 300 2280.00

362.TROLLEY AND COVERS CP 400/T ARC 2500.00

363.TROLLEY AND COVERS CPSA 1200 ( With Party) 11338.00

364.TUNGSTEN ELECTRODE 1.6 MM (FOR ALU welding 56.00

SR NO. DISCRIPTION RATE365.

TUNGSTEN ELECTRODE 2.4 MM 97.00366. TUNGSTEN ELECTRODE 2.4 MM (FOR ALU

WELDING) 101.00367.

TUNGSTEN ELECTRODE 3.0/3.2 MM 115.00368.

TUNGSTEN ELECTRODES 1.6 MM 56.00369.

TUNGSTEN ELECTRODES 1MM 39.00370.

TUNGSTEN ELECTRODES 2.0 MM 80.00371.

TWIN GROOVED ROLLER ( 2 ROLL) 45.00372.

VOLTMETER 0-100 V 370373.

VOLTMETER 0-60 V 370374.

WELDING CABLE 35 MM2 166.00375.

WELDING CABLE 50 MM2 235.00376.

WIRE BOOM CP 222 293.34377.

WIRE BOOM CP 300 297.23378.

WIRE BOOM CP 400 375.00379. WIRE BOOM RT 51 234.66

Page 71: Project Report Prachi

380.WIRE BOOM WIRE FEEDER 234.66

381.WIRE FEEDER BOX ,TRAY AND FRAME 450.00

382.WIRE FEEDER FRAME 100.00

383.WIRE FEEDER TRAY 100.00

384.WIRE GUIDE 20.00

385.WIRE LINER BLUE (LOW COST) 70.00

386.WIRE LINER RED 120.00

387.WIRE LINER YELLOW (1.2-1.6 MM) 110.00

388.WORM 250 RPM 100.00

389.WORM 66/37 RPM 100.00

390.WORM WHEEL 250 RPM 250.00

391.WORM WHEEL 66/37 RPM 250.00

THE ORDERING POLICY OF THE COMPANY:

The above materials are ordered on the basis of the following points:-1. Ordered on monthly basis.2. Ordered on emergency against customer order.

REVIEW OF ALL THE ITEMS WITH ITS VALUE AND QUANTITY:

STOCK AS ON:-31.03.2010

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

Page 72: Project Report Prachi

1. 1 CORE PVC CABLE 16 MM2 3 89.00 267.002. 1 CORE 1 MM2 BLACK 0 5.89 0.003. 1 CORE 1 MM2 BLUE 100 5.89 589.004. 1 CORE 1 MM2 GREEN 300 5.89 1767.005. 1 CORE 1 MM2 GREY 200 5.89 1178.006. 1 CORE 1 MM2 ORANGE 0 5.89 0.007. 1 CORE 1 MM2 RED 150 5.89 883.508. 1 CORE 1 MM2 WHITE 200 5.89 1178.009. 1 CORE 1 MM2 YELLOW 100 5.89 589.0010. 10 PIN PLUG PRIYANTRONIX 2 303 606.0011. 10 PIN RECEPTACLE

PRIYANTRONIX 3 293 879.0012. 2 CORE PVC CABLE 1.5 MM2 5 24 120.0013. 2 ROLL DRIVE WITH G BOX

( 250 RPM) 11 1850.00 20350.0014. 2 ROLL DRIVE WITH G BOX

( IMPORTED) Geared roller 1 3100.00 3100.0015. 2 ROLL DRIVE WITH G BOX

( IMPORTED) Plain roller 0 3100.00 0.0016. 3 CORE PVC CABLE 1.5 MM2 25 31 775.0017. 3 PIN PLUG & SOCKER MS TYPE 10 108 1080.0018. 3 PIN PLUG PRIYANTRONIX

( TORCH) 6 59 354.0019. 3 PIN RECEPTACLE PRIYANTRONIX

(WF/PS) 6 55 330.0020. 4 CORE PVC CABLE 1.5 MM2 116 41 4756.0021. 4 CORE PVC CABLE 2.5 MM2 30 66 1980.0022. 4 PIN PLUG PRIYANTRONIX 10 64 640.0023. 4 PIN RECEPTACLE PRIYANTRONIX 8 58 464.0024. 4 ROLL DRIVE UNIT WITH G BOX

( 145 RPM) 0 5900.00 0.0025. 4 ROLL DRIVE UNIT WITH G BOX

( 66 RPM/37 RPM)With Motor 4 8150.00 32600.0026. 4 ROLL DRIVE WITH G BOX

(IMPORTED) 2 4500.00 9000.0027. 6 PIN PLUG & SOCKET ( MS TYPE) 0  28. 92 TEETH 1 330.00 330.0029. AFCO TAG ( SOLDERING TYPE) 800 0.10 80.0030. ALU PLATE ( CHOKE MTG) 75 10.00 750.0031. AMEETER 0-1500 A 2 333 666.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL32. AMMETER 0-1000 A 3 333 999.0033. AMMETER 0-400 A 4 333 1332.0034. AMMETER 0-600 A 0 333 0.0035. ANTI SPATTER SPRAY 500 ML 0 68.00 0.00

Page 73: Project Report Prachi

36. ANTISPATTER GEL 300 GM 3 55.00 165.0037. BAKELITE INS PLATE 1 55.00 55.0038. BAKELITE STRIP ( INPUT CABLE) 2 10 20.0039. BEARING 6004 4 125.00 500.0040. BEARING 6006 5 185.00 925.0041. BEARING 6007 5 225.00 1125.0042. BEARING 6009 1 240.00 240.0043. BEARING 6010 0 485.00 0.0044. BEARING 6011 0 552.00 0.0045. BEARING 6202 8 80.00 640.0046. BEARING HOUSING (MS) 100*65 10 1840.00 18400.0047. BEARING HOUSING (MS) 125*100

2+3 5 1840.00 9200.0048. BEARING HOUSING 100MM DIA*125

MM LONG 10 960.00 9600.0049. BK WASHER AND BUSH

(FOR O/P TERMINAL) 0 13 0.0050. BK WEDGES ( FOR CHOKE) 165 5.00 825.0051. BOBBIN NO 13( 2 NOS/SET) 60 4.00 240.0052. BOBBIN NO 7 ( 12 NOS/SET) 100 7.00 700.0053. BRASS NIPPLE ( GAS HOSE) 125 12.50 1562.554. BRASS NIPPLE 3/8" * 1/8" 29 20.00 580.0055. BRASS NUT (GAS HOSE) 125 12.50 1562.556. BRUSH HOLDER ASSY WITH OUT

BRUSH 20* 40 8 600.00 4800.0057. BRUSH HOLDER ASSY Without

BRUSH(8*10) V TYPE Small 8 180.00 1440.0058. C TYPE STRIP 1 18.00 18.0059. C.S.T 2.5 TERMINAL 107 7.06 754.8960. CAPACITOR 0.1 MFD 630V

( 6 NOS/SET) 60 7.00 420.0061. CARBON BRUSH 20*40 20 225.00 4500.0062. CARBON BRUSH FOR MARTIN

MOTOR 102 25.00 2550.0063. CARBON BRUSH V 8*10 (SMALL) 10 75.00 750.0064. CARTRIDGE (WITH SEALING RING) 12 159.00 1908.0065. CEBORA TIG 1565 IMPORTED 1 90000.00 90000.0066. CERAMIC NOZZLE 2410640/WG2411 8 22.10 176.8067. CERAMIC NOZZLE 2411040 /WG2413 4 22.10 88.4068. CERAMIC NOZZLE 2461036/WG2463 10 22.10 221.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL69. CERAMIC NOZZLE SAP 10 N 47 0 32.00 0.0070. CERAMIC NOZZLE SAP 10 N 48 8 32.00 256.0071. CHOKE BLOCK 63* 63* 180 MM

(Duly drilled & tapped) 9 300.00 2700.00

Page 74: Project Report Prachi

72. CHOKE CP 300 3 1872.00 5616.0073. CHOKE CP 400 1 3710.00 3710.0074. CHOKE MTG ANGLE 14 10.00 140.0075. CHUCK PLATE 300* 16 MM 12 650.00 7800.0076. CO2 WELDIN G TORCH RB 61 GD

RGZ-2 3 MTR 2 12000.00 24000.0077. CO2 WELDING TORCH 36KD 0 3250.00 0.0078. CO2 WELDING TORCH 40 KD

(WITH 65 MM2 C/S CABLE) 1 4800.00 4800.0079. CO2 WELDING TORCH M/C

MOUNTING NM24,0.75 mtr 0 1250.00 0.0080. CO2 WELDING TORCH NM24 5 2000.00 10000.0081. CO2 WELDING WIRE 0.8 MM 15 KG

SPOOLS TATA MAKE 1 1020.00 1020.0082. COLLET 1.6 MM SA26 10N23 17 27.00 459.0083. COLLET 2.0 MM SA 26 9 27.00 243.0084. COLLET 2.4 MM SA 26 12 27.00 324.0085. COLLET 3.2 MM SA26 3 27.00 81.0086. COLLET BODY 2.4 SA26 10N32 17 58.00 986.0087. COLLET BODY1.6 SA26 10N31 2 58.00 116.0088. COLLET GC 20 1.6 MM 10 26.00 260.0089. COLLET GC 20 2.0 MM 6 26.00 156.0090. COLLET GC 20 2.4 MM 16 26.00 416.0091. COLLET GC 20 3.0/3.2 MM 0 26.00 0.0092. CONTACT TIP 0.8 MM HD M6 65 10.00 650.0093. CONTACT TIP 0.8 MM LD M6 365 5.90 2153.5094. CONTACT TIP 1.2 MM M6 LOW

DUTY 322 5.90 1899.8095. CONTACT TIP 1.2 MM M8 50 29.00 1450.0096. CONTACT TIP 1.2 MM M6 H DUTY 26 10.00 260.0097. CONTACT TIP 1.6 MM M8 50 29.00 1450.0098. CONTACT TIP 2 .0MM M8 0 30.00 0.0099. CONTACT TIP 2.0 MM M10

( FOR M 750) 19 70.00 1330.00100. CONTACT TIP 2.8 MM M8 0 30.00 0.00101. CONTACTOR 16 AMPS 42 V AC BCH 3 659.00 1977.00102. CONTACTOR 40 AMPS 0 1797.00 0.00103. CONTACTOR 6 AMPS D 15 SERIES

3no+ 1nc 3 469.00 1407.00104. CONTACTOR 80 AMPS 3 3900.00 11700.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL105. CONTACTOR AUX CONTACT BLOCK

2NO 2 NC 4 158.00 632.00106. CONTACTOR AUX CONTACT BLOCK

4NO 9 158.00 1422.00

Page 75: Project Report Prachi

107. CONTROL PANEL (SMALL) 1 950.00 950.00108. CONTROL PANEL 480*620*240 WITH

INSIDE TRAY 7 1226.00 8582.00109. CONTROL PENDENT BIG 7 265.00 1855.00110. CONTROL PENDENT SMALL 13 162.00 2106.00111. CONTROL X MER ( PS) 11 1750.00 19250.00112. CONTROL X MER ( SPM) 7 1750.00 12250.00113. CONTROL X MER ( WF) 13 300.00 3900.00114. CORRUGATED BOX ( TIG) 31*15*22

7 PLY 0 0.00 0.00115. CORRUGATED BOX CP 222

30"*17"*22" 9 62.00 558.00116. CORRUGATED BOX CP300

33*18.5"*24" 13 64.00 832.00117. CORRUGATED BOX CP400

32"*22.5"*29.5" 3 79.00 237.00118. CORRUGATED BOX W F

21"*13.5"*18" 0 59.50 0.00119. COTTER PIN 3/16 * 2" 100 1 100.00120. D WASHER 304 5.00 1520.00121. DC.TIG INVERTER UNIT

(SAGAR MAKE) 1 42000.00 42000.00122. DIN RAIL STRIP 5 25.00 125.00123. DIODE 150 A NAINA 40 265.00 10600.00124. DIODE 16FMR 40 150+15 165 30.56 5042.40125. DIODE 250 RUTTONSHA 24 425.00 10200.00126. DIODE 351 UF 12 1114.00 13368.00127. DIODE CLAMP ( 6 NOS/SET) 270 4.00 1080.00128. DIODE D 305 ( RECTIFIER HOUSE) 0 515.00 0.00129. DIODE D155 A RECT HOUSE 45 265.00 11925.00130. DOOR KNOB FOR WIRE FEEDER 4 10.00 40.00131. EARTHING RING ( GUN METAL)

Nitin industries 5 725.00 3625.00132. END CLAMP 90 2.75 247.50133. END PLATE 79 2.00 158.00134. EXPANSION MODULE FL1B

M08B2R2 MAKE ADEC 0 3240.00 0.00135. EYE BOLT 16 MM 30 40.00 1200.00136. FAN 15" 0 1650.00 0.00137. FAN 18" 1 2210.00 2210.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL138. FAN 24" 0 4200.00 0.00139. FAN 9" 4 950.00 3800.00140. FAN12" 10 1350.00 13500.00141. FIBRE WASHER 1960 0.30 588.00

Page 76: Project Report Prachi

142. FINDER SOCKET 4 38.00 152.00143. FIXEDJAWS(SPM FIXTURE YUTAKA) 1 300.00 300.00144. FIXED WHEEL 150 * 50 20 193 3860.00145. FIXED WHEEL 150* 50 WITH BKT 0 504 0.00146. FIXED WHEEL 300 * 50 4 470 1880.00147. FLOWMETER (CO2/AR) WELDCUT 0 420.00 0.00148. F-R-L UNIT1/2" JENITICS MAKE 3 1980.00 5940.00149. FUSE HOLDER MF 20 7 31.00 217.00150. FUSE HOLDER SLP 15 120 42.00 5040.00151. GAS DIFFUSOR 36KD 20 8.00 160.00152. GAS DIFFUSOR 40 KD 14 18.00 252.00153. GAS DIFFUSOR NM24 594 8.00 4752.00154. GAS HOSE RUBBER BLUE 8 MM 18 40.00 720.00155. GAS PREHEATER ASSY 220V 28 700.00 19600.00156. GEAR 92 TEETH & 23 TEETH SET 8 670.00 5360.00157. GEARBOX (ITALLIAN) BONFIGLIOLI 2 3500.00 7000.00158. GEAR BOX 100 RPM 1 1500.00 1500.00159. GEAR BOX 145 RPM 0 1500.00 0.00160. GEAR BOX 37 RPM 2 1500.00 3000.00161. GEAR BOX 66 RPM 5 1500.00 1500.00162. GLASS FUSE 15 AMPS ( SLOW BLOW

TYPE) 6* 32 MM 300 3.60 1080.00163. GLASS FUSE 4 AMPS ( SLOW BLOW

TYPE) 5*20 220 2.40 528.00164. H.V. TRANSFORMER 1 1850.00 1850.00165. HANDLE GRIP 21 10.00 210.00166. HEAT SINK BIG & SMALL

( 6 NOS/SET) SET 28+36 4 332.76 1331.04167. HEATING ELEMENT 110 V 3 65.00 195.00168. HEATING ELEMENT 230 V 6 65.00 390.00169. HOSE CLIP 16 MM (GAS HOSE) 110 12.00 1320.00170. INLET NOZZLE 7 30.00 210.00171. INNER TUBE 4 158.00 632.00172. INSULATING BUSH ( MS) 2 ROLL 20 48.00 960.00173. INSULATING BUSH (PC) 2 ROLL 5 35.00 175.00174. INSULATING CAP ( MS) 2 ROLL 17 10.00 170.00175. KNOB,POINTER,CAP FOR ABOVE

20,14,40 19 14.00 266.00176. L BK SUPPORT ( 6 NOS/SET) 279 7.00 1953.00177. L TYPE PIPE 5 100.00 500.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL178. LED 10 MM 5 8.00 40.00179. LED HOLDER 0 6.00 0.00180. LED PCB ASSY 22 20.00 440.00181. LED PCB BLANK 150 2.00 300.00

Page 77: Project Report Prachi

182. LINEAR BEARING LM16UU 16 110.00 1760.00183. LINEAR BEARING LM25UU 3 180.00 540.00184. LONG CAP GC 20 WG 240 2402

( WG2402) 1 73.00 73.00185. LONG CAP SA26 57Y02 0 52.00 0.00186. LUG ( SOLDERING TYPE B5 )

( 12NOS/SET) 1000 0.10 100.00187. MAIN SHAFT ( 250 RPM G BOX) 0 75.00 0.00188. MAIN SHAFT ( SINGLE) 2 2000.00 4000.00189. MAIN SHAFT ( TORCH ROTATION

SYSTEM) 6 1900.00 11400.00190. MAIN SHAFT (DOUBLE) 90MM DIA 0 2300.00 0.00191. MAIN SHAFT 2 ROLL 0 75.00 0.00192. MAIN SHAFT 4 ROLL 4 110.00 440.00193. MAIN SHAFT WITH BEARING( PC) 11 110.00 1210.00194. MAIN TRANSFORMER CP 222 0 10123.00 0.00195. MAIN TRANSFORMER CP 300 3 11271.00 33813.00196. MAIN TRANSFORMER CP 400 1 22373.00 22373.00197. MALE CONNECTOR 1/8" BSP 23 25.00 575.00198. MICRO SLIDE ASSY 3 1500.00 4500.00199. MOTOR MTG BKT 15 35.00 525.00200. MOTOR MTG PAD SHOE 20 6.00 120.00201. MOVING JAWS (SPM FIXTURE

YUTAKA) 1 350.00 350.00202. N.C.ELEMENT 10 34.85 348.50203. N.O. ELEMENT 39 34.85 1359.15204. NIPPLE ( PREHEATER) 27 30.00 810.00205. NOZZLE 36 KD 25 75.00 1875.00206. NOZZLE 40 KD 6 130.00 780.00207. NOZZLE CLEANING TOOL 110 5.00 550.00208. NOZZLE FOR M750 10 450.00 4500.00209. NOZZLE MB25 (11) 15 50.00 750.00210. NOZZLE MB25 (14) 29 50.00 1450.00211. NOZZLE NM24 128 35.00 4480.00212. NOZZLE SPRING MB25 100 5.50 550.00213. NUT ( PREHEATER) 42 30.00 1260.00214. NYLON PAD 13 8.00 104.00215. NYLON WASHER 16 MM 77 2.00 154.00216. O RING SMALL 425 2.00 850.00217. OUTER TUBE 4 84.00 336.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL218. OUTPUT BRASS BODY 32 70 2240.00219. OUTPUT KNOB 15 14 210.00220. OUTPUT TERMINAL ASSY

(WITH KNOB) 41 90 3690.00

Page 78: Project Report Prachi

221. PCB ASSY( SPEED CONTROL) 13 1550.00 20150.00222. PCB ASSY( WIRE FEEDER) 1 1700.00 1700.00223. PCB BLANK WIRE FEEDER 15 158.40 2376.00224. PCB BLANK( SPEED CONTROL) 17 111.00 1887.00225. PILOT LAMP (LED) 22.5 DIA 9 141.00 1269.00226. PLAIN ROLLER ( 2 ROLL) 7 30.00 210.00227. PMDC MOTOR 1000 RPM 36 V DC 2 3200.00 6400.00228. PMDC MOTOR 120 W 36 V 5000 RPM

MARTIN 7 1350.00 9450.00229. PMDC MOTOR 1500 RPM 36 V DC 0    230. PMDC MOTOR 180 W 36 V 5000 RPM

MARTIN 10 1900.00 19000.00231. PNEUMATIC CYLINDER 63 * 50 MM 3 1600.00 4800.00232. PNEUMATIC CYLINDER 100 * 40 MM

( dutta) 3 1190.00 3570.00233. PNEUMATIC CYLINDER 100 * 40

MM(Shvo Norgen) 5 1425.00 7125.00234. PNEUMATIC CYLINDER PEN TYPE

25*25 3 750.00 2250.00235. PNEUMATIC TIMER WITH 2 BLOCK

230 V BCH MAKE 1 2630.00 2630.00236. PORCELAIN BEAD 500 0.10 50.00237. POTENTIOMETER 5 K 3 W 7 38.00 266.00238. POWER SUPPLY UNIT 24 V 2.5 AMPS 8 975.00 7800.00239. PREHEATER BODY 9 363.00 3267.00240. PRESSURE GAUGE

(CYLINDER SIDE)P NO5114 6 210.00 1260.00241. PRESSURE GAUGE

(DELIVERY SIDE)P NO5244 2 210.00 420.00242. PROXIMITY REED SWITCH

(FOR CYLINDER MAGNET) 2 275.00 550.00243. PROXIMITY SWITCH NBB5 18GM

50E2 IMPORTED 19 585.00 11115.00244. PU6 TUBE 20 28.00 560.00245. PULLEY CARRIER ASSY 3 300.00 900.00246. PUSH BUTTON ACTUATOR BLUE 8 38.25 306.00247. PUSH BUTTON ACTUATOR GREEN 5 38.25 191.25248. PUSH BUTTON ACTUATOR BLACK 12 38.25 459.00249. PUSH BUTTON ACTUATOR

YELLOW 4 38.25 153.00SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

250. PUSH BUTTON ACTUATOR WHITE 13 38.25 497.25251. PUSH BUTTON ACTUATOR

MUSHRUM RED 6 62.00 372.00252. PUSH BUTTON PB 800 H GREEN 51 31.00 1581.00

Page 79: Project Report Prachi

(INCH/OCV)253. PVC CHANNEL 25* 25 6 50.00 300.00254. PVC CHANNEL 25* 30 0 54.00 0.00255. RC PCB ASSY 23 12.00 276.00256. RC PCB BLANK 108 2.00 216.00257. RECTFIER STACK (FOR TMIG 400) 0 1700.00 0.00258. RECTIFER MTG FLAT 26 10.00 260.00259. RECTIFIER MTG L BKT 25 10.00 250.00260. RECTIFIER STACK ( FOR T ARC 400

RECTIFIER 400 AMPS) 1 1700.00 1700.00261. RECTIFIER STACK ( FOR T ARC 600

RECTIFIER 600 AMPS) 1 2400.00 2400.00262. RECTIFIER STACK ASSY( FITTED

WITH DIODES) 0 2755.00 0.00263. RECTIFIER STACK ASSY( WITHOUT

DIODES) 16 1045.00 16720.00264. REED SWITCH(CURRENT SENSOR)

PLA MAKE 1 165.00 165.00265. REEL HOLDER AXLE 15 36.00 540.00266. REEL HOLDER WITH NUT 43 75.00 3225.00267. REGULATOR WITH FLOWMETER

ARGON 3 1810.00 5430.00268. REGULATOR WITH FLOWMETER

CO2 7 1810.00 12670.00269. RELAY 57DP O/E/N 18 65.00 1170.00270. RELAY 58 DP OMRON 4 60.00 240.00271. RELAY 8 PIN 24 V DC 3 140.00 420.00272. RELAY BASE WITH CLIP FOR

ABOVE 6 90.00 540.00273. RELAY PCO 24 V DC 1 242.25 242.25274. RELAY RU2 S CD24 WITH BASE &

CLIP 14PIN 11 238.00 2618.00275. RELAY RU2 S CD24 WITH BASE &

CLIP 8 PIN ADEC 11 190.00 2090.00276. RIVET ( 12NOS/SET) 300 0.50 150.00277. ROTARY CULINDER SAS-R-32-90

SHAVO NORGEN 3 7102.00 21306.00278. ROTARY SWITCH 1023 21 104.00 2184.00279. ROTARY SWITCH 1039 F6 30 365.00 10950.00280. ROTARY SWITCH 40313F6 2 742.50 1485.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL281. ROTARY SWITCH 4034 ON OFF 1 240.00 240.00282. ROTARY SWITCH 60313D 3 726.00 2178.00283. ROTARY SWITCH 60319 F6 2 1215.00 2430.00284. ROTOSEAL ATLAS 2 INPUTS 0 4657.00 0.00

Page 80: Project Report Prachi

285. ROTOSEAL SINGLE INPUT 0 1550.00 0.00286. RT51 DRIVE UNIT BOX 5 1080.00 5400.00287. RT51 TURN TABLE WITH COVER 5 2380.00 11900.00288. RUBBER DIPHRAGM 6 58.00 348.00289. S.V. MOUNTING BUSH 255 2.00 510.00290. S.VALVE D COIL 24 V DC SHAVO

NORGENJENETICS 5 1200.00 6000.00291. S.VALVE D COIL 24 V DC PATCON

PNEUMATICS 9 1200.00 10800.00292. S.VALVE D COIL 5*2 24 V DC

JENETICS 7 1700.00 11900.00293. S.VALVE S COIL 24 V DC JENETICS 2 950.00 1900.00294. SELECTOR SWITCH 2 POSITION

TECHNIC MAKE 9 119.85 1078.65295. SELECTOR SWITCH 3 POSITION

TECHNIC MAKE 3 119.85 359.55296. SHORT CAP GC20 6 42.00 252.00297. SHUNT 1000 AMP 1 1260 1260.00298. SHUNT 1500 AMP 1 1818 1818.00299. SHUNT 400 AMP 13 280 3640.00300. SHUNT 600 AMP 3 875 2625.00301. SHUNT 800 AMP 1 1000 1000.00302. SILENCER FIXTURE(ELEPTICAL)

JOB A YUTAKA 1 19320.00 19320.00303. SILENCER FIXTURE(ELEPTICAL)

JOB B YUTAKA 1 20110.00 20110.00304. SLIDE ASSY FOR ELEPTICAL

WEDING SPM 1 7970.00 7970.00305. SLIDE ASSY FOR REFAIR INDUTRIES

SPM 1 13250.00 13250.00306. SMART RELAY FL1D-H12RCE MAKE

ADEC 0 5400.00 0.00307. SOLENOID VALVE 230 V AC 3 502.00 1506.00308. SOLENOID VALVE 42 V AC 18 502.00 9036.00309. SPANNER ( TORCH) 75 10.00 750.00310. SPRING ( BRAKING) 79 3.00 237.00311. SPUR GEAR 2ROLL 70 45.00 3150.00312. STUD 10* 415 MM ( 2NOS/SET) 38 35.00 1330.00313. SUBARC CONTROL UNIT WITH

COVER 3 260.00 780.00SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

314. SWIVEL ELBOW 1/8" BSP 23 35.00 805.00315. SWIVEL WHEEL 125* 50 2 609 1218.00316. SWIVEL WHEEL 150* 50 WITH BKT 0 630 0.00317. SWIVEL WHEEL 77* 32 10 198 1980.00

Page 81: Project Report Prachi

318. TERMINAL STRIP 3 WAY 10 AMPS 250 V 3 8.00 24.00

319. TERMINAL STRIP 4 WAY 10 AMPS 250V 15 10.00 150.00

320. THERMOSTAT 85/70 DEGREE 112 58.00 6496.00321. THYRISTOR 3935 RUTTONSHA 50 149.00 7450.00322. TIG TORCH GC 20 4 MTR 0 2815.00 0.00323. TIG TORCH HEAD GC 20 0 831.30 0.00324. TIG TORCH HEAD GC 2002 001 2 831.00 1662.00325. TIG TORCH HEAD SA26 SA26001 0 572.00 0.00326. TIG TORCH SA26 4 MTR WITH

ERGO HANDLE 0 2638.00 0.00327. TIMER 800 U 3 750.00 2250.00328. TIP ADAPTOR 36 KD 6 MM 50 8.00 400.00329. TIP ADAPTOR 36KD 8 MM 12 8.00 96.00330. TIP ADAPTOR 40 KD 8MM 6 48.00 288.00331. TIP ADAPTOR MB25 12 8.00 96.00332. TIP ADAPTOR NM24 202 4.00 808.00333. TOGGLE SWITCH 1031 OFF -ON 0 48.00 0.00334. TOGGLE SWITCH 2065 NO-OFF-NO 0 84.00 0.00335. TOGGLE SWITCH KT 1021 ON-OFF 5 48.00 240.00336. TOGGLE SWITCH KT 2061 ON-ON 0 84.00 0.00337. TORCH CABLE 33.5 MM2 1 MTR

NM24 0 525.00 0.00338. TORCH CABLE 33.5 MM2 1.25 MTR

NM24 0 600.00 0.00339. TORCH CABLE 33.5 MM2 1.5 MTR

NM24 1 700.00 700.00340. TORCH CABLE 33.5 MM2 3 MTR

NM24 4 1350.00 5400.00341. TORCH CABLE 50.0 MM2 1.5 MTR

36KD 0 925.00 0.00342. TORCH CABLE 50.0 MM2 2.0 MTR

36KD 1 1250.00 1250.00343. TORCH CABLE 50.0 MM2 3 MTR

36KD 2 1850.00 3700.00344. TORCH HANDLE ASSY RED 51 133.00 6783.00345. TORCH HEAD 36 KD 8 650.00 5200.00346. TORCH HEAD 40 KD 0    347. TORCH HEAD M/C MOUNTING 0 750.00 0.00

SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL348. TORCH HEAD M/C MOUNTING

GOOSE NECK NM24 6 550.00 3300.00349. TORCH HEAD M/C MOUNTING

STRAIGHT HEAD 36KD 3 750.00 2250.00

Page 82: Project Report Prachi

350. TORCH HEAD M/C MOUNTING STRAIGHT HEAD NM24 2 550.00 1100.00

351. TORCH HEAD MB25 3 350.00 1050.00352. TORCH HEAD NM24 10 300.00 3000.00353. TORCH HOLDER 28 MM 3 150.00 450.00354. TORCH HOLDER 38 MM 15 175.00 2625.00355. TORCH KIT MB25 950 5.00 4750.00356. TORCH SLIDE ASSY ( PNEUMATIC) 11 2850.00 31350.00357. TORCH SLIDE MOUNTING BLOCK 30 150.00 4500.00358. TORCH SWITCH KIT NM 24 26 36.00 936.00359. TORCH SWITCH( IMPORTED SINGLE

MICRO SWITCH) 2 415.65 831.30360. TRIGGER SWITCH MB25 32 60.00 1920.00361. TROLLEY AND COVERS CP 222 9 1650.00 14850.00362. TROLLEY AND COVERS CP 300 4 2280.00 9120.00363. TROLLEY AND COVERS CP 400/T

ARC 3 2500.00 7500.00364. TROLLEY AND COVERS CPSA 1200

( With Party) 1 11338.00 11338.00365. TUNGSTEN ELECTRODE 1.6 MM

(FOR ALU WELDING) 10 56.00 560.00366. TUNGSTEN ELECTRODE 2.4 MM 12 97.00 1164.00367. TUNGSTEN ELECTRODE 2.4 MM

(FOR ALU WELDING) 10 101.00 1010.00368. TUNGSTEN ELECTRODE 3.0/3.2 MM 14 115.00 1610.00369. TUNGSTEN ELECTRODES 1.6 MM 7 56.00 392.00370. TUNGSTEN ELECTRODES 1MM 8 39.00 312.00371. TUNGSTEN ELECTRODES 2.0 MM 9 80.00 720.00372. TWIN GROOVED ROLLER ( 2 ROLL) 6 45.00 270.00373. VOLTMETER 0-100 V 0 370 0.00374. VOLTMETER 0-60 V 12 370 4440.00375. WELDING CABLE 35 MM2 0 166.00 0.00376. WELDING CABLE 50 MM2 30 235.00 7050.00377. WIRE BOOM CP 222 7 293.34 2053.38378. WIRE BOOM CP 300 9 297.23 2675.07379. WIRE BOOM CP 400 0 375.00 0.00380. WIRE BOOM RT 51 0 234.66 0.00381. WIRE BOOM WIRE FEEDER 4 234.66 938.64382. WIRE FEEDER BOX ,TRAY AND

FRAME 38 450.00 17100.00SR. NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

383. WIRE FEEDER FRAME 23 100.00 2300.00384. WIRE FEEDER TRAY 17 100.00 1700.00385. WIRE GUIDE 19 20.00 380.00386. WIRE LINER BLUE (LOW COST) 10 70.00 700.00

Page 83: Project Report Prachi

387. WIRE LINER RED 16 120.00 1920.00388. WIRE LINER YELLOW (1.2-1.6 MM) 17 110.00 1870.00389. WORM 250 RPM 5 100.00 500.00390. WORM 66/37 RPM 9 100.00 900.00391. WORM WHEEL 250 RPM 12 250.00 3000.00392. WORM WHEEL 66/37 RPM 8 250.00 2000.00

TOTAL VALUE OF STOCK(NET)1377154.32

REVIEW OF 13 ITEMS HAVING TOTAL VALUE BETWEEN RS 20, 000/-TO RS 1, 00, 000/-

TOTAL AMOUNT- RS 4, 36,117/-

Page 84: Project Report Prachi

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL     

1. CEBORA TIG 1565 IMPORTED 1 90000.00 90000.002. DC.TIG INVERTER UNIT ( SAGAR MAKE) 1 42000.00 42000.003. MAIN TRANSFORMER CP 400 1 22373.00 22373.004. FABRICATED TABLE 1700*1600*2114 (Yutaka SPM) 1 20315.00 20315.005. SILENCER FIXTURE(ELEPTICAL) JOB B YUTAKA 1 20110.00 20110.006. CO2 WELDIN G TORCH RB 61 GD RGZ-2 3 MTR 2 12000.00 24000.007. MAIN TRANSFORMER CP 300 3 11271.00 33813.00

8.4 ROLL DRIVE UNIT WITH G BOX ( 66 RPM/37 RPM)With Motor 4 8150.00 32600.00

9. ROTARY CULINDER SAS-R-32-90 SHAVO NORGEN 3 7102.00 21306.0010. TORCH SLIDE ASSY ( PNEUMATIC) 11 2850.00 31350.0011. 2 ROLL DRIVE WITH G BOX ( 250 RPM) 11 1850.00 20350.0012. PCB ASSY( SPEED CONTROL) 13 1550.00 20150.0013. DIODE 200 A NAINA 154 375.00 57750.00

REVIEW OF 27 ITEMS HAVING TOTAL VALUE BETWEEN RS 10,000/- TO RS 20, 000/-

TOTAL AMOUNT-Rs.379169.00/-

Page 85: Project Report Prachi

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

1.SILENCER FIXTURE(ELEPTICAL) JOB A YUTAKA 1 19320.00 19320.00

2. MAIN TRANSFORMER T ARC 400 1 13938.00 13938.00

3.SLIDE ASSY FOR REFAIR INDUTRIES SPM 1 13250.00 13250.00

4.TROLLEY AND COVERS CPSA 1200(With Party) 1 11338.00 11338.00

5.FABRICATED TABLE 600*600*750 (Yutaka SPM) RT52/RT53 2 5500.00 11000.00

6. CONTACTOR 80 AMPS 3 3900.00 11700.007. RT51 TURN TABLE WITH COVER 5 2380.00 11900.00

8.PMDC MOTOR 180 W 36 V 5000 RPM MARTIN 10 1900.00 19000.00

9.MAIN SHAFT ( TORCH ROTATION SYSTEM) 6 1900.00 11400.00

10. BEARING HOUSING (MS) 100*65 10 1840.00 18400.0011. REGULATOR WITH FLOWMETER CO2 7 1810.00 12670.0012. CONTROL X MER ( PS) 11 1750.00 19250.0013. CONTROL X MER ( SPM) 7 1750.00 12250.0014. S.VALVE D COIL 5*2 24 V DC JENETICS 7 1700.00 11900.0015. TROLLEY AND COVERS CP 222 9 1650.00 14850.0016. FAN12" 10 1350.00 13500.00

17.S.VALVE D COIL 24 V DC PATCON PNEUMATICS 9 1200.00 10800.00

18. DIODE 351 UF 12 1114.00 13368.00

19.RECTIFIER STACK ASSY(WITHOUT DIODES) 16 1045.00 16720.00

20.PROXIMITY SWITCH NBB5 18GM 50E2 IMPORTED 19 585.00 11115.00

21. WIRE FEEDER BOX ,TRAY AND FRAME 38 450.00 17100.0022. DIODE 250 RUTTONSHA 24 425.00 10200.0023. ROTARY SWITCH 1039 F6 30 365.00 10950.0024. DIODE 150LF 40 RUTTONSHA 38 285.00 10830.0025. DIODE D155 A RECT HOUSE 45 265.00 11925.0026. DIODE 150 A NAINA 40 265.00 10600.0027. THYRISTOR MELTRON 3899 71 145.00 10295.00

REVIEW OF 361 ITEMS HAVING TOTAL VALUE BETWEEN RS 0/- TO RS 10, 000/-

TOTAL AMOUNT: - RS.561868.32/-

Page 86: Project Report Prachi

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL1. MAIN TRANSFORMER CP 222 0 10123.00 0.002. SLIDE ASSY FOR ELEPTICAL WEDING SPM 1 7970.00 7970.003. 4 ROLL DRIVE UNIT WITH G BOX ( 145 RPM) 0 5900.00 0.004. SMART RELAY FL1D-H12RCE MAKE ADEC 0 5400.00 0.00

5.CO2 WELDING TORCH 40 KD (WITH 65 MM2 C/S CABLE) 1 4800.00 4800.00

6. ROTOSEAL ATLAS 2 INPUTS 0 4657.00 0.007. 4 ROLL DRIVE WITH G BOX (IMPORTED) 2 4500.00 9000.008. FAN 24" 0 4200.00 0.009. CHOKE CP 400 1 3710.00 3710.0010. GEAR BOX (ITALLIAN) BONFIGLIOLI 2 3500.00 7000.0011. CO2 WELDING TORCH 36KD 0 3250.00 0.00

12.EXPANSION MODULE FL1B M08B2R2 MAKE ADEC 0 3240.00 0.00

13. PMDC MOTOR 1000 RPM 36 V DC 2 3200.00 6400.00

14.2 ROLL DRIVE WITH G BOX ( IMPORTED) Geared roller 1 3100.00 3100.00

15.2 ROLL DRIVE WITH G BOX (IMPORTED) Plain roller 0 3100.00 0.00

16. TIG TORCH GC 20 4 MTR 0 2815.00 0.00

17.RECTIFIER STACK ASSY( FITTED WITH DIODES) 0 2755.00 0.00

18.TIG TORCH SA26 4 MTR WITH ERGO HANDLE 0 2638.00 0.00

19.PNEUMATIC TIMER WITH 2 BLOCK 230 V BCH MAKE 1 2630.00 2630.00

20. TROLLEY AND COVERS CP 400/T ARC 3 2500.00 7500.00

21.RECTIFIER STACK ( FOR T ARC 600 RECTIFIER 600 AMPS) 1 2400.00 2400.00

22. MAIN SHAFT (DOUBLE) 90MM DIA 0 2300.00 0.0023. TROLLEY AND COVERS CP 300 4 2280.00 9120.0024. FAN 18" 1 2210.00 2210.0025. CO2 WELDING TORCH NM24 5 2000.00 10000.0026. MAIN SHAFT ( SINGLE) 2 2000.00 4000.0027. F-R-L UNIT1/2" JENITICS MAKE 3 1980.00 5940.0028. CHOKE CP 300 3 1872.00 5616.0029. TORCH CABLE 50.0 MM2 3 MTR 36KD 2 1850.00 3700.0030. H.V. TRANSFORMER 1 1850.00 1850.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL31. BEARING HOUSING (MS) 125*100 2+3 5 1840.00 9200.0032. SHUNT 1500 AMP 1 1818 1818.0033. REGULATOR WITH FLOWMETER ARGON 3 1810.00 5430.0034. CONTACTOR 40 AMPS 0 1797.00 0.00

Page 87: Project Report Prachi

35.RECTIFIER STACK ( FOR T ARC 400 RECTIFIER 400 AMPS) 1 1700.00 1700.00

36. PCB ASSY( WIRE FEEDER) 1 1700.00 1700.0037. RECTFIER STACK (FOR TMIG 400) 0 1700.00 0.0038. FAN 15" 0 1650.00 0.0039. PNEUMATIC CYLINDER 63 * 50 MM 3 1600.00 4800.0040. ROTOSEAL SINGLE INPUT 0 1550.00 0.0041. MICRO SLIDE ASSY 3 1500.00 4500.0042. GEAR BOX 37 RPM 2 1500.00 3000.0043. H.F. COIL 1 1500.00 1500.0044. GEAR BOX 66 RPM 5 1500.00 1500.0045. GEAR BOX 100 RPM 1 1500.00 1500.0046. GEAR BOX 145 RPM 0 1500.00 0.00

47.PNEUMATIC CYLINDER 100 * 40 MM(Shvo Norgen) 5 1425.00 7125.00

48. PMDC MOTOR 120 W 36 V 5000 RPM MARTIN 7 1350.00 9450.0049. TORCH CABLE 33.5 MM2 3 MTR NM24 4 1350.00 5400.0050. SHUNT 1000 AMP 1 1260 1260.0051. TORCH CABLE 50.0 MM2 2.0 MTR 36KD 1 1250.00 1250.00

52.CO2 WELDING TORCH M/C MOUNTING NM24,0.75 mtr 0 1250.00 0.00

53.CONTROL PANEL 480*620*240 WITH INSIDE TRAY 7 1226.00 8582.00

54. ROTARY SWITCH 60319 F6 2 1215.00 2430.00

55.S.VALVE D COIL 24 V DC SHAVO NORGENJENETICS 5 1200.00 6000.00

56. PNEUMATIC CYLINDER 100 * 40 MM ( dutta) 3 1190.00 3570.0057. L.T TRANSFORMER 1 1100.00 1100.0058. RT51 DRIVE UNIT BOX 5 1080.00 5400.00

59.CO2 WELDING WIRE 0.8 MM 15 KG SPOOLS TATA MAKE 1 1020.00 1020.00

60. SHUNT 800 AMP 1 1000 1000.0061. POWER SUPPLY UNIT 24 V 2.5 AMPS 8 975.00 7800.00

62.BEARING HOUSING 100MM DIA*125 MM LONG 10 960.00 9600.00

63. FAN 9" 4 950.00 3800.0064. S.VALVE S COIL 24 V DC JENETICS 2 950.00 1900.0065. CONTROL PANEL (SMALL) 1 950.00 950.0066. TORCH CABLE 50.0 MM2 1.5 MTR 36KD 0 925.00 0.0067. SHUNT 600 AMP 3 875 2625.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL68. TIG TORCH HEAD GC 20 0 831.30 0.0069. TIG TORCH HEAD GC 2002 001 2 831.00 1662.0070. TIMER 800 U 3 750.00 2250.0071. TORCH HEAD M/C MOUNTING STRAIGHT 3 750.00 2250.00

Page 88: Project Report Prachi

HEAD 36KD72. PNEUMATIC CYLINDER PEN TYPE 25*25 3 750.00 2250.00

73.TORCH HEAD M/C MOUNTING GOOSE NECK 36KD 0 750.00 0.00

74. ROTARY SWITCH 40313F6 2 742.50 1485.0075. ROTARY SWITCH 60313D 3 726.00 2178.00

76.EARTHING RING ( GUN METAL) Nitin Industries 2+3 5 725.00 3625.00

77. TORCH CABLE 33.5 MM2 1.5 MTR NM24 1 700.00 700.0078. GEAR 92 TEETH & 23 TEETH SET 8 670.00 5360.0079. CONTACTOR 16 AMPS 42 V AC BCH 3 659.00 1977.0080. CHUCK PLATE 300* 16 MM 12 650.00 7800.0081. TORCH HEAD 36 KD 8 650.00 5200.0082. SWIVEL WHEEL 150* 50 WITH BKT 0 630 0.0083. CONTACTOR 16 AMPS C& S 0 625.00 0.0084. SWIVEL WHEEL 125* 50 2 609 1218.00

85.BRUSH HOLDER ASSY WITH OUT BRUSH 20* 40 8 600.00 4800.00

86.SPECIAL CONTROL X MER (PRI 230V SEC 15V, 12.0-12V 5 600.00 3000.00

87. TORCH CABLE 33.5 MM2 1.25 MTR NM24 0 600.00 0.00

88.CONTACTOR 20 AMPS 4 POLE 42 VAC C&S MAKE(D204) 10 572.75 5727.50

89. TIG TORCH HEAD SA26 SA26001 0 572.00 0.0090. BEARING 0 552.00 0.00

91.TORCH HEAD M/C MOUNTING GOOSE NECK NM24 6 550.00 3300.00

92.TORCH HEAD M/C MOUNTING STRAIGHT HEAD NM24 2 550.00 1100.00

93. TORCH CABLE 33.5 MM2 1 MTR NM24 0 525.00 0.0094. DIODE D 305 ( RECTIFIER HOUSE) 0 515.00 0.0095. FIXED WHEEL 150* 50 WITH BKT 0 504 0.0096. SOLENOID VALVE 42 V AC 18 502.0097. SOLENOID VALVE 230 V AC 3 502.00 1506.0098. BEARING 6010 0 485.00 0.0099. FIXED WHEEL 300 * 50 4 470 1880.00100. CONTACTOR 6 AMPS D 15 SERIES 3no+ 1nc 3 469.00 1407.00101. NOZZLE FOR M750 10 450.00 4500.00102. FLOWMETER (CO2/AR) WELDCUT 0 420.00 0.00103. TORCH SWITCH(IMPORTED SINGLE MICRO) 2 415.65 831.30

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL104. WIRE BOOM CP 400 0 375.00 0.00105. VOLTMETER 0-60 V 12 370 4440.00106. VOLTMETER 0-100 V 0 370 0.00107. PREHEATER BODY 9 363.00 3267.00

Page 89: Project Report Prachi

108. TORCH HEAD MB25 3 350.00 1050.00109. MOVING JAWS (SPM FIXTURE YUTAKA) 1 350.00 350.00110. AMMETER 0-400 A 4 333 1332.00111. AMMETER 0-1000 A 3 333 999.00112. AMEETER 0-1500 A 2 333 666.00113. AMMETER 0-600 A 0 333 0.00

114.HEAT SINK BIG & SMALL ( 6 NOS/SET) SET 28+36 4 332.76 1331.04

115. 92 TEETH 1 330.00 330.00116. 10 PIN PLUG PRIYANTRONIX 2 303 606.00117. CONTROL X MER ( WF) 13 300.00 3900.00118. TORCH HEAD NM24 10 300.00 3000.00

119.CHOKE BLOCK 63* 63* 180 MM (Duly drilled & tapped) 9 300.00 2700.00

120. PULLEY CARRIER ASSY 3 300.00 900.00121. FIXED JAWS (SPM FIXTURE YUTAKA) 1 300.00 300.00122. WIRE BOOM CP 300 9 297.23 2675.07123. WIRE BOOM CP 222 7 293.34 2053.38124. 10 PIN RECEPTACLE PRIYANTRONIX 3 293 879.00125. SHUNT 400 AMP 13 280 3640.00

126.PROXIMITY REED SWITCH (FOR CYLINDER MAGNET) 2 275.00 550.00

127. CONTROL PENDENT BIG 7 265.00 1855.00128. SUBARC CONTROL UNIT WITH COVER 3 260.00 780.00129. WORM WHEEL 250 RPM 12 250.00 3000.00130. WORM WHEEL 66/37 RPM 8 250.00 2000.00131. RELAY PCO 24 V DC 1 242.25 242.25132. ROTARY SWITCH 4034 ON OFF 1 240.00 240.00133. BEARING 6009 1 240.00 240.00

134.RELAY RU2 S CD24 WITH BASE & CLIP 14PIN 11 238.00 2618.00

135. WELDING CABLE 50 MM2 30 235.00 7050.00136. WIRE BOOM WIRE FEEDER 4 234.66 938.64137. WIRE BOOM RT 51 0 234.66 0.00138. CARBON BRUSH 20*40 20 225.00 4500.00139. BEARING 6007 5 225.00 1125.00

140.PRESSURE GAUGE(CYLINDER SIDE)P NO5114 6 210.00 1260.00

141.PRESSURE GAUGE(DELIVERY SIDE)P NO5244 2 210.00 420.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL142. SWIVEL WHEEL 77* 32 10 198 1980.00143. FIXED WHEEL 150 * 50 20 193 3860.00

144.RELAY RU2 S CD24 WITH BASE & CLIP 8 PIN ADEC 11 190.00 2090.00

Page 90: Project Report Prachi

145. BEARING 6006 5 185.00 925.00

146.BRUSH HOLDER ASSY Without BRUSH(8*10) V TYPE Small 8 180.00 1440.00

147. LINEAR BEARING LM25UU 3 180.00 540.00148. TORCH HOLDER 38 MM 15 175.00 2625.00149. WELDING CABLE 35 MM2 0 166.00 0.00

150.REED SWITCH(CURRENT SENSOR) PLA MAKE 1 165.00 165.00

151. CONTROL PENDENT SMALL 13 162.00 2106.00152. CARTRIDGE (WITH SEALING RING) 12 159.00 1908.00153. PCB BLANK WIRE FEEDER 15 158.40 2376.00154. CONTACTOR AUX CONTACT BLOCK 4NO 9 158.00 1422.00

155.CONTACTOR AUX CONTACT BLOCK 2NO 2 NC 4 158.00 632.00

156. INNER TUBE 4 158.00 632.00157. TORCH SLIDE MOUNTING BLOCK 30 150.00 4500.00158. TORCH HOLDER 28 MM 3 150.00 450.00

159.THYRISTOR 3935 RUTTONSHA (Rectifier house) 50 149.00 7450.00

160. PILOT LAMP (LED) 22.5 DIA 9 141.00 1269.00161. RELAY 8 PIN 24 V DC 3 140.00 420.00162. TORCH HANDLE ASSY RED 51 133.00 6783.00163. NOZZLE 40 KD 6 130.00 780.00164. BEARING 6004 4 125.00 500.00165. WIRE LINER RED 16 120.00 1920.00

166.SELECTOR SWITCH 2 POSITION TECHNIC MAKE 9 119.85 1078.65

167.SELECTOR SWITCH 3 POSITION TECHNIC MAKE 3 119.85 359.55

168. TUNGSTEN ELECTRODE 3.0/3.2 MM 14 115.00 1610.00169. PCB BLANK( SPEED CONTROL) 17 111.00 1887.00170. WIRE LINER YELLOW (1.2-1.6 MM) 17 110.00 1870.00171. LINEAR BEARING LM16UU 16 110.00 1760.00172. MAIN SHAFT WITH BEARING( PC) 11 110.00 1210.00173. MAIN SHAFT 4 ROLL 4 110.00 440.00174. 3 PIN PLUG & SOCKER MS TYPE 10 108 1080.00175. ROTARY SWITCH 1023 21 104.00 2184.00

176.TUNGSTEN ELECTRODE 2.4 MM (FOR ALU WELDING) 10 101.00 1010.00

177. THYRISTOR 25NT120 98 100.00 9800.00SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

178. WIRE FEEDER FRAME 23 100.00 2300.00179. WIRE FEEDER TRAY 17 100.00 1700.00180. WORM 66/37 RPM 9 100.00 900.00181. WORM 250 RPM 5 100.00 500.00

Page 91: Project Report Prachi

182. L TYPE PIPE 5 100.00 500.00183. TUNGSTEN ELECTRODE 2.4 MM 12 97.00 1164.00184. OUTPUT TERMINAL ASSY(WITH KNOB) 41 90 3690.00185. RELAY BASE WITH CLIP FOR ABOVE 6 90.00 540.00186. 1 CORE PVC CABLE 16 MM2 3 89.00 267.00187. OUTER TUBE 4 84.00 336.00188. TOGGLE SWITCH KT 2061 ON-ON 0 84.00 0.00189. TOGGLE SWITCH 2065 NO-OFF-NO 0 84.00 0.00190. TUNGSTEN ELECTRODES 2.0 MM 9 80.00 720.00191. BEARING 6202 8 80.00 640.00192. CORRUGATED BOX CP400 32"*22.5"*29.5" 3 79.00 237.00193. REEL HOLDER WITH NUT 43 75.00 3225.00194. NOZZLE 36 KD 25 75.00 1875.00195. CARBON BRUSH V 8*10 (SMALL) 10 75.00 750.00196. MAIN SHAFT ( 250 RPM G BOX) 0 75.00 0.00197. MAIN SHAFT 2 ROLL 0 75.00 0.00198. LONG CAP GC 20 WG 240 2402 ( WG2402) 1 73.00 73.00199. OUTPUT BRASS BODY 32 70 2240.00200. CONTACT TIP 2.0 MM M10 ( FOR M 750) 19 70.00 1330.00201. WIRE LINER BLUE (LOW COST) 10 70.00 700.00202. ANTI SPATTER SPRAY 500 ML 0 68.00 0.00203. 4 CORE PVC CABLE 2.5 MM2 30 66 1980.00204. RELAY 57DP O/E/N 18 65.00 1170.00205. HEATING ELEMENT 230 V 6 65.00 390.00206. HEATING ELEMENT 110 V 3 65.00 195.00207. CORRUGATED BOX CP300 33*18.5"*24" 13 64.00 832.00208. 4 PIN PLUG PRIYANTRONIX 10 64 640.00209. CORRUGATED BOX CP 222 30"*17"*22" 9 62.00 558.00210. PUSH BUTTON ACTUATOR MUSHRUM RED 6 62.00 372.00211. TRIGGER SWITCH MB25 32 60.00 1920.00212. RELAY 58 DP OMRON 4 60.00 240.00213. CORRUGATED BOX W F 21"*13.5"*18" 0 59.50 0.00214. 3 PIN PLUG PRIYANTRONIX ( TORCH) 6 59 354.00215. THERMOSTAT 85/70 DEGREE 112 58.00 6496.00216. COLLET BODY 2.4 SA26 10N32 17 58.00 986.00217. 4 PIN RECEPTACLE PRIYANTRONIX 8 58 464.00218. RUBBER DIPHRAGM 6 58.00 348.00219. COLLET BODY1.6 SA26 10N31 2 58.00 116.00

220.TUNGSTEN ELECTRODE 1.6 MM (FOR ALU WELDING) 10 56.00 560.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL221. TUNGSTEN ELECTRODES 1.6 MM 7 56.00 392.00222. 3 PIN RECEPTACLE PRIYANTRONIX (WF/PS) 6 55 330.00223. ANTISPATTER GEL 300 GM 3 55.00 165.00224. BAKELITE INS PLATE 1 55.00 55.00

Page 92: Project Report Prachi

225. PVC CHANNEL 25* 30 0 54.00 0.00226. LONG CAP SA26 57Y02 0 52.00 0.00227. NOZZLE MB25 (14) 29 50.00 1450.00228. NOZZLE MB25 (11) 15 50.00 750.00229. PVC CHANNEL 25* 25 6 50.00 300.00230. INSULATING BUSH ( MS) 2 ROLL 20 48.00 960.00231. TIP ADAPTOR 40 KD 8MM 6 48.00 288.00232. TOGGLE SWITCH KT 1021 ON-OFF 5 48.00 240.00233. TOGGLE SWITCH 1031 OFF -ON 0 48.00 0.00234. SPUR GEAR 2ROLL 70 45.00 3150.00235. TWIN GROOVED ROLLER ( 2 ROLL) 6 45.00 270.00236. FUSE HOLDER SLP 15 120 42.00 5040.00237. SHORT CAP GC20 6 42.00 252.00238. 4 CORE PVC CABLE 1.5 MM2 116 41 4756.00239. EYE BOLT 16 MM 30 40.00 1200.00240. GAS HOSE RUBBER BLUE 8 MM 18 40.00 720.00241. TUNGSTEN ELECTRODES 1MM 8 39.00 312.00242. PUSH BUTTON ACTUATOR WHITE 13 38.25 497.25243. PUSH BUTTON ACTUATOR BLACK 12 38.25 459.00244. PUSH BUTTON ACTUATOR BLUE 8 38.25 306.00245. PUSH BUTTON ACTUATOR GREEN 5 38.25 191.25246. PUSH BUTTON ACTUATOR YELLOW 4 38.25 153.00247. POTENTIOMETER 5 K 3 W 7 38.00 266.00248. FINDER SOCKET 4 38.00 152.00249. TORCH SWITCH KIT NM 24 26 36.00 936.00250. REEL HOLDER AXLE 15 36.00 540.00251. NOZZLE NM24 128 35.00 4480.00252. STUD 10* 415 MM ( 2NOS/SET) 38 35.00 1330.00253. SWIVEL ELBOW 1/8" BSP 23 35.00 805.00254. MOTOR MTG BKT 15 35.00 525.00255. INSULATING BUSH (PC) 2 ROLL 5 35.00 175.00256. N.O. ELEMENT 39 34.85 1359.15257. N.C.ELEMENT 10 34.85 348.50258. CERAMIC NOZZLE SAP 10 N 48 8 32.00 256.00259. CERAMIC NOZZLE SAP 10 N 47 0 32.00 0.00260. PUSH BUTTON PB 800 H GREEN (INCH/OCV) 51 31.00 1581.00261. 3 CORE PVC CABLE 1.5 MM2 25 31 775.00262. FUSE HOLDER MF 20 7 31.00 217.00263. DIODE 16FMR 40 150+15 165 30.56 5042.40264. NUT ( PREHEATER) 42 30.00 1260.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL265. NIPPLE ( PREHEATER) 27 30.00 810.00266. PLAIN ROLLER ( 2 ROLL) 7 30.00 210.00267. INLET NOZZLE 7 30.00 210.00268. CONTACT TIP 2 .0MM M8 0 30.00 0.00

Page 93: Project Report Prachi

269. CONTACT TIP 2.8 MM M8 0 30.00 0.00270. CONTACT TIP 1.2 MM M8 50 29.00 1450.00271. CONTACT TIP 1.6 MM M8 50 29.00 1450.00272. PU6 TUBE 20 28.00 560.00273. COLLET 1.6 MM SA26 10N23 17 27.00 459.00274. COLLET 2.4 MM SA 26 12 27.00 324.00275. COLLET 2.0 MM SA 26 9 27.00 243.00276. COLLET 3.2 MM SA26 3 27.00 81.00277. COLLET GC 20 2.4 MM 16 26.00 416.00278. COLLET GC 20 1.6 MM 10 26.00 260.00279. COLLET GC 20 2.0 MM 6 26.00 156.00280. COLLET GC 20 3.0/3.2 MM 0 26.00 0.00281. CARBON BRUSH FOR MARTIN MOTOR 102 25.00 2550.00282. MALE CONNECTOR 1/8" BSP 23 25.00 575.00283. DIN RAIL STRIP 5 25.00 125.00284. 2 CORE PVC CABLE 1.5 MM2 5 24 120.00285. CERAMIC NOZZLE 2461036/WG2463 10 22.10 221.00286. CERAMIC NOZZLE 2410640/WG2411 8 22.10 176.80287. CERAMIC NOZZLE 2411040 /WG2413 4 22.10 88.40288. BRASS NIPPLE 3/8" * 1/8" 29 20.00 580.00289. LED PCB ASSY 22 20.00 440.00290. WIRE GUIDE 19 20.00 380.00291. GAS DIFFUSOR 40 KD 14 18.00 252.00292. C TYPE STRIP 1 18.00 18.00293. KNOB,POINTER,CAP FOR ABOVE 20,14,40 19 14.00 266.00294. OUTPUT KNOB 15 14 210.00

295.BK WASHER AND BUSH (FOR O/P TERMINAL) 0 13 0.00

296. BRASS NUT (GAS HOSE) 125 12.50 1562.5297. BRASS NIPPLE ( GAS HOSE) 125 12.50 1562.5298. HOSE CLIP 16 MM (GAS HOSE) 110 12.00 1320.00299. RC PCB ASSY 23 12.00 276.00300. ALU PLATE ( CHOKE MTG) 75 10.00 750.00301. SPANNER ( TORCH) 75 10.00 750.00302. CONTACT TIP 0.8 MM HD M6 65 10.00 650.00303. RECTIFER MTG FLAT 26 10.00 260.00304. CONTACT TIP 1.2 MM M6 H DUTY 26 10.00 260.00305. RECTIFIER MTG L BKT 25 10.00 250.00306. HANDLE GRIP 21 10.00 210.00307. INSULATING CAP ( MS) 2 ROLL 17 10.00 170.00

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL308. TERMINAL STRIP 4 WAY 10 AMPS 250V 15 10.00 150.00309. CHOKE MTG ANGLE 14 10.00 140.00310. DOOR KNOB FOR WIRE FEEDER 4 10.00 40.00311. BAKELITE STRIP ( INPUT CABLE) 2 10 20.00

Page 94: Project Report Prachi

312. GAS DIFFUSOR NM24 594 8.00 4752.00313. TIP ADAPTOR 36 KD 6 MM 50 8.00 400.00314. GAS DIFFUSOR 36KD 20 8.00 160.00315. NYLON PAD 13 8.00 104.00316. TIP ADAPTOR MB25 12 8.00 96.00317. TIP ADAPTOR 36KD 8 MM 12 8.00 96.00318. LED 10 MM 5 8.00 40.00319. TERMINAL STRIP 3 WAY 10 AMPS 250 V 3 8.00 24.00320. C.S.T 2.5 TERMINAL 107 7.06 754.89321. L BK SUPPORT ( 6 NOS/SET) 279 7.00 1953.00322. BOBBIN NO 7 ( 12 NOS/SET) 100 7.00 700.00323. CAPACITOR 0.1 MFD 630V ( 6 NOS/SET) 60 7.00 420.00324. MOTOR MTG PAD SHOE 20 6.00 120.00325. LED HOLDER 0 6.00 0.00326. CONTACT TIP 0.8 MM LD M6 365 5.90 2153.50327. CONTACT TIP 1.2 MM M6 LOW DUTY 322 5.90 1899.80328. 1 CORE 1 MM2 GREEN 300 5.89 1767.00329. 1 CORE 1 MM2 WHITE 200 5.89 1178.00330. 1 CORE 1 MM2 GREY 200 5.89 1178.00331. 1 CORE 1 MM2 RED 150 5.89 883.50332. 1 CORE 1 MM2 YELLOW 100 5.89 589.00333. 1 CORE 1 MM2 BLUE 100 5.89 589.00334. 1 CORE 1 MM2 ORANGE 0 5.89 0.00335. 1 CORE 1 MM2 BLACK 0 5.89 0.00336. NOZZLE SPRING MB25 100 5.50 550.00337. TORCH KIT MB25 950 5.00 4750.00338. D WASHER 304 5.00 1520.00339. BK WEDGES ( FOR CHOKE) 165 5.00 825.00340. NOZZLE CLEANING TOOL 110 5.00 550.00341. DIODE CLAMP ( 6 NOS/SET) 270 4.00 1080.00342. TIP ADAPTOR NM24 202 4.00 808.00343. BOBBIN NO 13( 2 NOS/SET) 60 4.00 240.00

344.GLASS FUSE 15 AMPS ( SLOW BLOW TYPE) 6* 32 MM 300 3.60 1080.00

345. O RING BIG 182 3.00 546.00346. SPRING ( BRAKING) 79 3.00 237.00347. END CLAMP 90 2.75 247.50

348.GLASS FUSE 4 AMPS ( SLOW BLOW TYPE) 5*20 220 2.40 528.00

349. O RING SMALL 425 2.00 850.00SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL

350. S.V. MOUNTING BUSH 255 2.00 510.00351. LED PCB BLANK 150 2.00 300.00352. RC PCB BLANK 108 2.00 216.00353. END PLATE 79 2.00 158.00

Page 95: Project Report Prachi

354. NYLON WASHER 16 MM 77 2.00 154.00355. COTTER PIN 3/16 * 2" 100 1 100.00356. RIVET ( 12NOS/SET) 300 0.50 150.00357. FIBRE WASHER 1960 0.30 588.00358. LUG ( SOLDERING TYPE B5 ) ( 12NOS/SET) 1000 0.10 100.00359. AFCO TAG ( SOLDERING TYPE) 800 0.10 80.00360. PORCELAIN BEAD 500 0.10 50.00361. CORRUGATED BOX ( TIG) 31*15*22 7 PLY 0 0.00 0.00

FACTS OBSERVED DURING PHYSICAL VERIFICATION OF INVENTORY

The following points are also the points as to why the materials have become non moving and slow moving at TECHNOCRAT ENGINEERS:-

Page 96: Project Report Prachi

MISPLACEMENT OF INVENTORY: Many of the items found to be misplaced. Either the material was placed in appropriate bins &racks or the change of bin was not updated in the system.

RETURNED MATERIAL: the returned material from the shop floor is again mixed with the same stock from which it is issued. No separate treatment is given to the returned material.

CRITICAL PURCHASE: Many high value non-stocking items were found in the stores, which were yet not consumed.

OBSOLETE, SURPLUS 7 WASTE: OBSOLETE: “Those materials and equipment which are not damaged and which

have economic growth but which are no longer useful for company operation owing to many reasons such as changes in production line, process, design changes etc.

SURPLUS: “Those materials and equipment which have no immediate use, but have accumulated due the faulty planning; purchasing and forecasting but they have usage value in future.”

SCRAP: “Those materials like process wastage, such as training, boring, flashes they may have end uses, and they have no market value.”

THUS OBSOLETE & SURPLUS= SLOW MOVING ITEMS (S) ANDSCRAP=NON MOVING ITEM

LIST OF ITEMS WHICH ARE NON-MOVING (N) AND SLOW MOVING(S)

ITEMS HAVING TOTAL VALUE BETWEEN RS 20,000/- TO RS 1, 00, 000/-

Page 97: Project Report Prachi

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL TYPE1. CEBORA TIG 1565 IMPORTED 1 90000.00 90000.00 N2. DC.TIG INVERTER UNIT ( SAGAR MAKE) 1 42000.00 42000.00 N

3.SILENCER FIXTURE(ELEPTICAL) JOB B YUTAKA 1 20110.00 20110.00 N

4.CO2 WELDIN G TORCH RB 61 GD RGZ-2 3 MTR 2 12000.00 24000.00 N

5. DIODE 200 A NAINA 154 375.00 57750.00 N

1.ROTARY CULINDER SAS-R-32-90 SHAVO NORGEN 3 7102.00 21306.00 S

2.FABRICATED TABLE 1700*1600*2114 (Yutaka SPM) 1 20315.00 20315.00 S

ITEMS HAVING VALUE BETWEEM Rs.10, 000/- TO RS 20,000/-

SR.NO. MATERIAL DESCRIPTION

STOCK RATE TOTAL

TYPE

1.SILENCER FIXTURE(ELEPTICAL) JOB A YUTAKA 1 19320.00

19320.00 N

2.SLIDE ASSY FOR REFAIR INDUTRIES SPM 1 13250.00

13250.00 N

3.S.VALVE D COIL 24 V DC PATCON PNEUMATICS 9 1200.00

10800.00 N

4. DIODE 150 A NAINA 40 265.0010600.00 N

5. THYRISTOR MELTRON 3899 71 145.0010295.00 N

1. BEARING HOUSING (MS) 100*65 10 1840.00 18400.00 S2. MAIN TRANSFORMER T ARC 400 1 13938.00 13938.00 S

3.TROLLEY AND COVERS CPSA 1200 (With Party) 1 11338.00 11338.00 S

4.FABRICATED TABLE 600*600*750 (Yutaka SPM) RT52/RT53 2 5500.00 11000.00 S

5. CONTACTOR 80 AMPS 3 3900.00 11700.00 S6. RT51 TURN TABLE WITH COVER 5 2380.00 11900.00 S

7.MAIN SHAFT (TORCH ROTATION SYSTEM) 6 1900.00 11400.00 S

ITEMS HAVING TOTAL VALUE BETWEEN 0/- TO RS 20, 000/-

SR.NO MATERIAL DESCRIPTION STOC RATE TOTAL TYP

Page 98: Project Report Prachi

. K E

1.SLIDE ASSY FOR ELEPTICAL WEDING SPM 1 7970.00 7970.00 N

2.4 ROLL DRIVE WITH G BOX (IMPORTED) 2 4500.00 9000.00 N

3. H.V. TRANSFORMER 1 1850.00 1850.00 N4. PNEUMATIC CYLINDER 63 * 50 MM 3 1600.00 4800.00 N5. H.F. COIL 1 1500.00 1500.00 N6. GEAR BOX 100 RPM 1 1500.00 1500.00 N

7.PNEUMATIC CYLINDER 100 * 40 MM (Shvo Norgen) 5 1425.00 7125.00 N

8.S.VALVE D COIL 24 V DC SHAVO NORGENJENETICS 5 1200.00 6000.00 N

9. L.T TRANSFORMER 1 1100.00 1100.00 N

10.BEARING HOUSING 100MM DIA*125 MM LONG 10 960.00 9600.00 N

11. S.VALVE S COIL 24 V DC JENETICS 2 950.00 1900.00 N

12.TORCH HEAD M/C MOUNTING STRAIGHT HEAD 36KD 3 750.00 2250.00 N

13.SPECIAL CONTROL X MER(PRI 230V SEC 15V, 12.0-12V 5 600.00 3000.00 N

14.CONTACTOR 20 AMPS 4 POLE 42 VAC C&S MAKE(D204) 10 572.75 5727.50 N

15. TORCH HEAD MB25 3 350.00 1050.00 N16. FIXED JAWS (SPM FIXTURE YUTAKA) 1 300.00 300.00 N

17.TUNGSTEN ELECTRODE 2.4 MM (FOR ALU WELDING) 10 101.00 1010.00 N

18. TRIGGER SWITCH MB25 32 60.00 1920.00 N

19.TUNGSTEN ELECTRODE 1.6 MM (FOR ALU WELDING) 10 56.00 560.00 N

20. NOZZLE MB25 (14) 29 50.00 1450.00 N21. NOZZLE MB25 (11) 15 50.00 750.00 N22. PVC CHANNEL 25* 25 6 50.00 300.00 N23. 2 CORE PVC CABLE 1.5 MM2 5 24 120.00 N24. TIP ADAPTOR MB25 12 8.00 96.00 N25. NOZZLE SPRING MB25 100 5.50 550.00 N26. TORCH KIT MB25 950 5.00 4750.00 N27. O RING BIG 182 3.00 546.00 N

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL TYPE1. BEARING HOUSING (MS) 125*100 5 1840.00 9200.00 S2. GEAR BOX (ITALLIAN) BONFIGLIOLI 2 3500.00 7000.00 S

Page 99: Project Report Prachi

3. PMDC MOTOR 1000 RPM 36 V DC 2 3200.00 6400.00 S

4.2 ROLL DRIVE WITH G BOX(IMPORTED) Geared roller 1 3100.00 3100.00 S

5.PNEUMATIC TIMER WITH 2 BLOCK 230 V BCH MAKE 1 2630.00 2630.00 S

6.RECTIFIER STACK ( FOR T ARC 600 RECTIFIER 600 AMPS) 1 2400.00 2400.00 S

7. FAN 18" 1 2210.00 2210.00 S8. MAIN SHAFT ( SINGLE) 2 2000.00 4000.00 S9. SHUNT 1500 AMP 1 1818 1818.00 S

10.RECTIFIER STACK ( FOR T ARC 400 RECTIFIER 400 AMPS) 1 1700.00 1700.00 S

11. SHUNT 1000 AMP 1 1260 1260.00 S12. TORCH CABLE 50.0 MM2 2.0 MTR 36KD 1 1250.00 1250.00 S13. ROTARY SWITCH 60319 F6 2 1215.00 2430.00 S14. RT51 DRIVE UNIT BOX 5 1080.00 5400.00 S15. SHUNT 800 AMP 1 1000 1000.00 S16. CONTROL PANEL (SMALL) 1 950.00 950.00 S17. TIG TORCH HEAD GC 2002 001 2 831.00 1662.00 S

18.PNEUMATIC CYLINDER PEN TYPE 25*25 3 750.00 2250.00 S

19. ROTARY SWITCH 60313D 3 726.00 2178.00 S20. TORCH CABLE 33.5 MM2 1.5 MTR NM24 1 700.00 700.00 S21. CHUCK PLATE 300* 16 MM 12 650.00 7800.00 S

22.TORCH HEAD M/C MOUNTING STRAIGHT HEAD NM24 2 550.00 1100.00 S

23. SOLENOID VALVE 230 V AC 3 502.00 1506.00 S24. NOZZLE FOR M750 10 450.00 4500.00 S

25.TORCH SWITCH( IMPORTED SINGLE MICRO SWITCH) 2 415.65 831.30 S

26.MOVING JAWS (SPM FIXTURE YUTAKA) 1 350.00 350.00 S

27. AMMETER 0-1000 A 3 333 999.00 S28. AMEETER 0-1500 A 2 333 666.00 S29. 10 PIN PLUG PRIYANTRONIX 2 303 606.00 S30. 10 PIN RECEPTACLE PRIYANTRONIX 3 293 879.00 S31. SUBARC CONTROL UNIT WITH COVER 3 260.00 780.00 S32. ROTARY SWITCH 4034 ON OFF 1 240.00 240.00 S

33.RELAY RU2 S CD24 WITH BASE & CLIP 14PIN 11 238.00 2618.00 S

34. BEARING 6006 5 185.00 925.00 S35. BRUSH HOLDER ASSY Without BRUSH 8 180.00 1440.00 S

SR.NO. MATERIAL DESCRIPTION STOCK RATE TOTAL TYPE36. LINEAR BEARING LM25UU 3 180.00 540.00 S37. REED SWITCH(CURRENT SENSOR) PLA 1 165.00 165.00 S

Page 100: Project Report Prachi

MAKE38. CONTROL PENDENT SMALL 13 162.00 2106.00 S39. TORCH HOLDER 28 MM 3 150.00 450.00 S40. BEARING 6004 4 125.00 500.00 S

41.SELECTOR SWITCH 3 POSITION TECHNIC MAKE 3 119.85 359.55 S

42. WIRE LINER YELLOW (1.2-1.6 MM) 17 110.00 1870.00 S43. LINEAR BEARING LM16UU 16 110.00 1760.00 S44. MAIN SHAFT 4 ROLL 4 110.00 440.00 S45. 3 PIN PLUG & SOCKER MS TYPE 10 108 1080.00 S46. L TYPE PIPE 5 100.00 500.00 S47. 1 CORE PVC CABLE 16 MM2 3 89.00 267.00 S48. TUNGSTEN ELECTRODES 2.0 MM 9 80.00 720.00 S49. BEARING 6202 8 80.00 640.00 S50. CARBON BRUSH V 8*10 (SMALL) 10 75.00 750.00 S

51.CONTACT TIP 2.0 MM M10 (FOR M 750) 19 70.00 1330.00 S

52. RELAY 57DP O/E/N 18 65.00 1170.00 S53. HEATING ELEMENT 110 V 3 65.00 195.00 S54. COLLET BODY 2.4 SA26 10N32 17 58.00 986.00 S55. COLLET BODY1.6 SA26 10N31 2 58.00 116.00 S56. TUNGSTEN ELECTRODES 1.6 MM 7 56.00 392.00 S57. TOGGLE SWITCH KT 1021 ON-OFF 5 48.00 240.00 S58. SHORT CAP GC20 6 42.00 252.00 S59. TUNGSTEN ELECTRODES 1MM 8 39.00 312.00 S60. CERAMIC NOZZLE SAP 10 N 48 8 32.00 256.00 S61. 3 CORE PVC CABLE 1.5 MM2 25 31 775.00 S62. CONTACT TIP 1.6 MM M8 50 29.00 1450.00 S63. COLLET 1.6 MM SA26 10N23 17 27.00 459.00 S64. COLLET 2.4 MM SA 26 12 27.00 324.00 S65. COLLET 2.0 MM SA 26 9 27.00 243.00 S66. COLLET 3.2 MM SA26 3 27.00 81.00 S67. COLLET GC 20 2.4 MM 16 26.00 416.00 S68. COLLET GC 20 1.6 MM 10 26.00 260.00 S69. COLLET GC 20 2.0 MM 6 26.00 156.00 S70. CERAMIC NOZZLE 2461036/WG2463 10 22.10 221.00 S71. TERMINAL STRIP 3 WAY 10 AMPS 250 V 3 8.00 24.00 S72. PORCELAIN BEAD 500 0.10 50.00 S

FACTS OBSERVED DURING PHYSICAL VERIFICATION OF INVENTORY

Page 101: Project Report Prachi

The following points are also the points as to why the materials have become non moving and

slow moving at TECHNOCRAT ENGINEERS:-

MISPLACEMENT OF INVENTORY: Many of the items found to be misplaced. Either

the material was placed in appropriate bins &racks or the change of bin was not updated in

the system.

RETURNED MATERIAL: the returned material from the shop floor is again mixed with

the same stock from which it is issued. No separate treatment is given to the returned

material.

CRITICAL PURCHASE: Many high value non-stocking items were found in the stores,

which were yet not consumed.

OBSOLETE, SURPLUS 7 WASTE:

OBSOLETE: “Those materials and equipment which are not damaged and which

have economic growth but which are no longer useful for company operation owing

to many reasons such as changes in production line, process, design changes etc.

SURPLUS: “Those materials and equipment which have no immediate use, but have

accumulated due the faulty planning; purchasing and forecasting but they have usage

value in future.”

SCRAP: “Those materials like process wastage, such as training, boring, flashes they

may have end uses, and they have no market value.”

THUS

OBSOLETE & SURPLUS= SLOW MOVING ITEMS (S) AND

SCRAP=NON MOVING ITEM

Page 102: Project Report Prachi

RECOMMENDATION AND SUGGESTION

The company was recommended to adopt a locking system which is as follows:-

Security for inventory is a must for every received material.

Security for GRR(Goods receipt report) is a must

For any transaction valid and released Purchase Order is required.

For any excess received material more than Purchase order receipt requires the approval of

the Director-Operations for acceptance.

The GRR details are to be updated within 5 days in the system or the information is blocked

and manually updated in the stores.

Suppose stock is under safety level, the required quantity is to be ordered after the approval

from the Director- Operations of the company.

For critical items emergency stock is maintained in stores and recommended in the system

and used with the approval of the Director-Operations of the company.

Due to business constraint the item-springs is stored in the stores department for 2 months.

Page 103: Project Report Prachi

CONCLUSION

By the analysis done above it is sufficiently clear that the twin objectives of inventory management

are to avoid excesses stocking and ensure uninterrupted supply of materials by avoiding shortage. In

addition to the above mentioned techniques, technique of ratio analysis is also very useful. Inventory

turnover ratio, which is calculated for each type of inventory like raw materials finished goods and

work in progress, indicates the holding period of each category of inventory. The higher inventory

turnover ratio the better it is as the holding period of the inventory.

A close watch on the dormant and the slow moving items should also be kept to reduce the

investment in inventory. Similarly absolute items should be identified and eliminated so that

unnecessarily funds are not blocked in these items.

Finally it can be said that the aim should be to optimize investment in inventory by comparing

between cost of funds and rate of return from such investments, in order to maximize value of

inventory.

Page 104: Project Report Prachi

BIBILOGRAPHY

Financial Management- N.M.VECHLEKAR

Financial Management-P.K.KULKARNI

Materials and Logistics Management- L.C.JHAMB

Operational Management-CHASE & JACOB

Internet sites: WIKIPEDIA

www.technocratengineers .com