PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECT At Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5, 48/6 and 49/2, Kyalasanahalli Village, K R Puram Hobli, Bangalore East, Bangalore. Submitted By M/s. Rohan Builders #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar Bangalore – 560038 Submitted to STATE LEVEL ENVIRNOMENT IMPACT ASSESSMENT AUTHORITY (SEIAA), KARNATAKA. ENVIRONMENTAL CONSULTANTS M/s. AQUA TECH ENVIRO ENGINEERS, # 3391, 6th Main, 3rd Cross, RPC Layout, Vijayanagar II Stage, Bangalore – 560 040. Tele Phone: 080 23141679.
81
Embed
PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECT
STATE LEVEL ENVIRNOMENT IMPACT ASSESSMENT AUTHORITY (SEIAA), KARNATAKA.
ENVIRONMENTAL CONSULTANTS
M/s. AQUA TECH ENVIRO ENGINEERS, # 3391, 6th Main, 3rd Cross, RPC Layout, Vijayanagar II Stage, Bangalore – 560 040.
Tele Phone: 080 23141679.
INDEX
SL NO DESCRIPTION
1 APPLICATION IN FORM I
2 APPLICATION IN FORM I A
ANNEXURE TO APPLICATIONS
A B C
D E F
G
H I J K L
M
N 0
COMPREHENSIVE PROJECT REPORT WATER REQUIREMENT DETAILS FOR THE PROJECT SEWAGE GENERATION, UTILITY OF TREATED SEWAGE & DESIGN DETAILS OF SEWAGE TREATMENT PLANTS WATER BALANCE CHART WATER REQUIREMENT AND SEWAGE DISPOSAL DURING CONSTRUCTION PHASE SOLID WASTE GENERATION & MANAGEMENT DETAILS (CONSTRUCTION & OPERATION PHASE) ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN (EMP) FOR CONSTRUCTION AND OCCUPANCY PHASES RAIN WATER MANAGEMENT SCHEME DISASTER MANAGEMENT PLAN FOR PRE-CONSTRUCTION PHASE EMP FOR CONTROL OF DUST AND NOISE DURING CONSTRUCTION PHASE. RISK ASSESSMENT & MANAGEMENT PLAN GEO TECHNICAL INVESTIGATION REPORT TRAFFIC SURVEY AND ITS MANAGEMENT SAVINGS IN ELECTRICAL POWER CONSUMPTION PROJECT RELATED DRAWINGS/PLANS
1
APPENDIX I
(See paragraph – 6)
FORM 1
(I) Basic Information
1 Name of the Project Residential Apartment Project with 975 units.
2 S. No. in the schedule Serial No. 8 (a) of schedule
3 Proposed capacity/area/ length/tonnage to be handles/command area/lease area/number of wells to be drilled
Residential Apartment Project: Proposed units: 975 Built up area: 1,49,471 sq m Plot area: 53,494.64 sq m (13.21 Acres) Cost: Rs. 313 Crores
4 New / Expansion / Modernization New project
5 Existing capacity / Area etc., NA
6 Category of project i.e., `A` or `B` B
7 Does it attract the general condition? If yes, please specify.
NO
8 Does it attract the specific condition? If yes, please specify.
NO
9 Location Residential Apartment Project with 975 units.
16 Details of alternative Sites examined, if any. Location of these sites would be shown on a topo sheet.
Village – District – State 1. 2. No alternative sites are examined.
17 Interlined Projects NA
18 Whether separate application of interlinked project has been submitted?
NA
19 If yes, date of submission NA
20 If no, reason Proposed project is Residential Apartment with 975 Flats
21 Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given a) The Forest (Conservation) Act 1980? b) The wildlife (Protection) Act, 1972? c) The C R Z Notification, 1991?
NO NO NO
22 Whether there is any Government Order/Policy relevant/relating to the site?
None
23 Forest land involved (Hectares) None
24 Whether there is any litigation pending against the project and/or land in which the project is propose to be set up?
a) Name of the court b) Case No. c) Orders/directions of the court,
if any and its relevance with the proposed project.
None
Screening Category: The proposed project is under Item 8 B Category as per amended EIA notification September 14th 2006.
Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,)
(ii) Activity:
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.,)
Sl. No.
Information/Checklist confirmation Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)
Yes The project is designed in concurrence with the Bangalore Development Authority and therefore there will not be any permanent or temporary changes in land use, though the proposed project is likely to increase the intensity of land use.
1.2 Clearance of existing land, vegetation and buildings?
No About 200 native indigenous species are planted at site. The project site has 308 existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70 Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50 Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.
1.3 Creation of new land uses? No Creation of new land uses from the proposed project is not expected as the intended use of the plot is for the Residential Apartment.
1.4 Pre-construction investigations e.g. bore houses, soil testing?
Yes Geotechnical investigation report is enclosed as Annexure – L.
1.5 Construction works?
Yes The proposed project mainly involves construction activities. These activities are likely to have certain impact on the surrounding environment in respect of Air, Water, Land etc., The associated impact of construction activity on the above environmental attributes and the mitigation measures
4
adopted in the project is appended as Annexure – G.
1.6 Demolition works? No There is no demolition work involved in the proposed project site.
1.7 Temporary sites used for construction works or housing of construction workers? (Details of labour camps, Number of labours, Number of toilets, Bath rooms, Medical facilities for labours, safety measures for labours, Nursery for labours children)
Yes About 500 construction workers will be engaged for construction activities.
50 Sheds and 100 Toilets with bathrooms will be provided for construction workers. Sheds for construction workers will be provided within the project site. Drinking water supply and adequate storage facility will be provided for construction workers. The workers will be provided with first aid facilities apart from personal protective gadgets. Periodic health assessment camps and administration of medicines as and when required will be provided. A small class room with a teacher (crèche) to educate the children of construction worker will be provided.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations (Calculation for earth work estimation)
Yes Above ground structures are proposed. The proposed project involves Construction of Residential Apartment. Activity, Area statement and Building Configuration details of the project is detailed in the Comprehensive project report appended as Annexure - A. The proposed project is residential apartment project having basement floor and earth excavation is necessary. The layout is planned
5
keeping the natural ground profile in consideration so that minimum excavation would be required. The total quantity of excavated soil is about 50,000 cum. About 15,000 cum will be used for landscape development, about 16,000 cum will be used for backfilling and 19,000 cum will be used for formation and hardscaping activities within the project site.
1.9 Underground works including mining or tunneling?
No NA
1.10 Reclamation works? No NA
1.11 Dredging? No NA
1.12 Offshore structures? No NA
1.13 Production and manufacturing processes?
No NA
1.14 Facilities for storage of goods or materials?
Yes Temporary sheds will be constructed for storage of construction materials.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents?
Yes Liquid waste: The liquid waste from workers camps will be treated in Package STP. Water requirement for the Construction phase is appended as Annexure - E. Sewage Treatment Plant (STP) of capacity 600 KLD will be constructed to treat the wastewater generated from the project during occupancy phase. Quantity of wastewater generation and design details of STP is appended as Annexure – C. Solid Waste: Construction Phase: The domestic wastes will be segregated and collected at a common designated place and will be disposed through BBMP. Solid waste like construction debris
6
generated during construction phase of about 400 cum will be used for preparation of sub grades for Roads, pavements and pathways. Occupancy Phase: Collection and segregation at the source of generation and Organic waste will be treated in Organic Converter and the Inorganic waste will be sent for recycling. The solid waste generation detail is appended as Annexure – F.
1.16 Facilities for long term housing of operational workers?
Yes No long term housing plan for the operational worker is planned in the proposed project as the local population residing in the surrounding areas of the project site will find the employment opportunity for various maintenance needs of the project once it is occupied.
1.17 New road, rail or sea traffic during construction or operation?
No NA
1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?
No NA
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?
No NA
1.20 New or diverted transmission lines or pipelines?
No NA
1.21 Impoundment, damming, culver ting, realignment or other changes to the hydrology of watercourses or aquifers?
No NA
1.22 Stream crossings? No NA
1.23 Abstraction or transfers of water form ground or surface waters?
Yes The water supply is from BWSSB Source.
1.24 Changes in water bodies or the land surface affecting drainage or run-off?
No NA
1.25 Transport of personnel or materials for construction, operation or decommissioning?
Yes Transport facilities are not proposed as the workers will be provided with sheds to be located within the project site.
7
The impacts due to the movement of vehicle both during construction and occupancy phase is detailed in the Traffic Management studies appended as Annexure – M.
1.26 Long-term dismantling or decommissioning or restoration works?
No NA
1.27 Ongoing activity during decommissioning which could have an impact on the environment?
No NA
1.28 Influx of people to an area in either temporarily or permanently?
Yes There will be Influx of population during the construction and occupancy phase as detailed under. Temporarily during construction phase (500 numbers) and permanent during occupancy phase (4,875 numbers) are expected.
1.29 Introduction of alien species? No NA
1.30 Loss of native species or genetic diversity?
No NA
1.31 Any other actions? No NA
2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
Sl.No Information/checklist confirmation
Yes/ No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha)
Yes The proposed project site is converted for residential purposes. The net site area is 4.8 Hectares.
2.2 Water (expected source & competing users) unit: KLD
Yes The water for the proposed project will be from BWSSB Sources. Total water requirement is about 681 KLD
2.3 Minerals (MT) No NA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)
Yes Description Unit Quantity
Cement Bags 7,00,284
Steel MT 7,878
Sand Cum 64,776
Tiles sq m 1,49,633
Stone Aggregate cum 56,023
Granite/Marble sq m 39,035
8
Aluminium sq m 1,626
Wood cft 11,385
2.5 Forests and timber (source– MT) Yes Procured through local timber depots.
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)
Yes Power Requirement: Construction phase: Temporary power from BESCOM to operate construction machinery and Lighting for workers shed is 2 X 150 kVA.
DG Set of 2 X 150 kVA capacity is proposed to serve as back up power supply during power failure.
Occupancy phase:
Anticipated power requirement from BESCOM is 5,145 kVA.
1 X 250 kVA & 3 X 500 kVA capacity DG sets is proposed, which will serve as back up power supply during power failure.
Fuel Requirement: Construction phase: Low Sulphur content Diesel consumption is 30 L/hr for DG set of 2 X 150 kVA capacity respectively.
Occupancy phase: Low Sulphur content Diesel of 50 L/hr and 100 L/hr for each DG set.
2.7 Any other natural resources (use appropriate standard units)
No NA
3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.
Sl.No Information/Checklist confirmation
Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)
No NA
9
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)
No NA
3.3 Affect the welfare of people e.g. by changing living conditions?
Yes The implementation of the proposed project is beneficial both socially and economically to its local populace, as it creates both long term and short term employment opportunities.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,
No NA
3.5 Any other causes No NA
4. Production of solid wastes during construction or operation or Decommissioning (MT/Month)
Sl.No Information/Checklist confirmation
Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No NA
4.2 Municipal waste (domestic and or commercial wastes)
Yes The quantity of solid waste generation and its management during Construction and Occupancy phase is appended as Annexure – F.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules)
Yes Spent oil from DG sets category 5.1. About 300 L/Annum of spent oil is generated which is sent to authorized spent oil reprocessor with manifest as per notification of Hazardous Waste (Management and Handling Rules).
4.4 Other industrial process wastes No NA
4.5 Surplus product No NA
4.6 Sewage sludge or other sludge from effluent treatment
No The secondary dewatered STP sludge is 216 kgs/day and is taken from Plate and Frame Filter Press and used as manure.
4.7 Construction or demolition wastes Yes There is no demolition work involved in the proposed project and all efforts will be made to reduce construction waste by adopting modern construction practices such as proportioning and weigh batchers for concreting.
10
Construction debris of about 400 cum is generated which will be used as preparatory materials for road, pavement and sub grade formation within the project site.
4.8 Redundant machinery or equipment
No NA
4.9 Contaminated soils or other materials
Yes Measures adopted to control soil contamination. 1. Providing collection trays to collect oil dripping from construction machineries if any. 2. Prevention of spillage and leakage of oils if required. 3. Providing kerb stones, lined gutter and oil traps.
4.10 Agricultural wastes No NA
4.11 Other solid wastes No NA
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
Sl. No Information/Checklist confirmation
Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources
Yes There is no other source of emission from the project other than from stationary sources like DG sets to be installed during occupancy period.
5.2 Emissions from production processes
No NA
5.3 Emissions from materials handling including storage or transport
Yes Fugitive dust due to movements of vehicles carrying construction materials. Proposed measures for control of dust and noise during construction phase is appended as Annexure - J.
5.4 Emissions from construction activities including plant and equipment
Yes Fugitive dust during earthwork, concreting, construction material handling. Closed operations for mixing of construction materials will be followed.
5.5 Dust or odours from handling of materials including construction
Yes Fugitive dust due to handling of construction materials.
11
materials, sewage and waste Emission of fugitive dust will be controlled by sprinkling of water and barricading will be provided all around the project site. Details of control of Dust and Noise during construction phase is appended as Annexure – J.
5.6 Emissions from incineration of waste
No NA
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)
No NA
5.8 Emissions from any other sources No NA
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data with source of information data
6.1 From operation of equipment e.g., engines, ventilation plant, crushers
Yes Operation of DG set during occupancy phase. Appropriate and adequate noise control measures will be adopted to control noise. DG Sets are set-up in room with acoustic enclosures. Further noise attenuation by way of planting peripheral trees as noise barriers.
6.2 From industrial or similar processes
No NA
6.3 From construction or demolition No Noise generation due to construction activities will be negligible and barricades will be erected all round the site. Details of control of Noise during construction phase are appended as Annexure – J. However there is certain increase in ambient noise level during construction activities which will be reduced by under taking periodic preventive maintenance of construction materials and restricting and reducing the speed of vehicle operated for the
12
movements of construction materials. All appropriate measure as detailed for 6.1 above is applicable.
6.4 From blasting or piling No NA
6.5 From construction or operational traffic
Yes Construction phase: Vehicles carrying construction materials Occupancy phase: Vehicular movement by the occupants. The details of mitigation measure planned to reduce the noise level is appended as Annexure - G.
6.6 From lighting or cooling systems No NA
6.7 From any other sources No NA
7.Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
Sl.
No.
Information/Checklist confirmation
Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials
Yes Appropriate management measures to prevent contamination of land, water are detailed in Annexure - G under water and land environment. Disaster management plan for Pre construction phase is appended as Annexure – I
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)
Yes The total quantity of wastewater generated from the proposed project is about 528 KLD. The treated sewage from the project will be used for landscape development and toilet flushing. Water Balance Chart is appended as Annexure – D.
7.3 By deposition of pollutants emitted to air into the land or into water
No NA
7.4 From any other sources No NA
7.5 Is there a risk of long term build up of pollutants in the environment from these sources?
No NA
13
8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment
Sl.No.
Information/Checklist confirmation Yes /No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances
No NA
8.2 From any other causes No No major risk from the project is anticipated. Risk Assessment & Management Plan for the project is appended as Annexure – K
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. Floods, earthquakes, landslides, cloudburst etc)?
No NA
9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.
Sl. No
Information/Checklist confirmation Yes /No
Details thereof (with approximate quantities/rates,wherever possible) with source of information data
9.1 L Lead to development of supporting. Utilities ancillary development or development stimulated by the project which could have impact on the environment e.g.:
• Supporting infrastructure (roads, power supply, waste or wastewater treatment, etc.) • housing development • extractive industries
Yes Yes Yes No
Net Positive Impact in terms of overall development of the Area is expected from the project. Direct & Indirect Employment opportunities are also created due to development of this project. New business opportunities are expected to cater the daily needs of the residents of the project. Construction of Residential apartment project with 975 flats
14
• supply industries
• other
No No
9.2 Lead to after-use of the site, which could have an impact on the environment
No NA
9.3 Set a precedent for later developments
Yes The project development is likely to set precedence to other likely developments in the surrounding area.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects
1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value
No NA
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses other water bodies, coastal zone, biospheres, mountains, and forests.
Yes Hormavu Agara Lake at 565m (south west), Rampura lake 2 km (south east).
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
No NA
4 Inland, coastal, marine or underground waters
No NA
5 State, National boundaries No NA
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas
No NA
7 Defense installations No NA
8 Densely populated or built-up area No N
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)
No NA
10 Areas containing important, high quality or scarce resources(ground water
11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)
No NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problem (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)
No NA
16
APPENDIX II
(See paragraph 6)
FORM-1 A
(Only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring program)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted)
Attach Maps of
(i) site location (Google Image showing the project site location with surrounding details is enclosed)
(ii) surrounding features of the proposed site (within 500 meters)
(iii) The site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.
The existing land use does not get altered significantly as the project surroundings have Residential layouts, Apartments and areas with rural settings.
Surrounding Features: Google, Location map of the project site is enclosed as Annexure - O.
Land Availability & Land use Pattern: The plot area of the project is 53,494.64 sq m
Land Use Pattern: The land around the project site indicates a mixed land use pattern; there are Residential layouts, Apartments, few Commercial Establishments and surrounded by areas like Bileshivalli, Bileshivalli Colony, Kyalasanahalli, Anagalapura, Geddalahalli, Bhairali, Kotnuru, Agra, Kalkere, Kanaknagar, Chansandra.
Transportation: Project site is located on Avalahalli Main Road and located at a distance of 5 Kms from Hennur - K R puram outer ring road. The site is also accessible from Hennur Main Road and Kalkere Main Road.
17
Agricultural Land: Plantations are seen in the surrounding areas, No agriculture lands are found in the vicinity.
Forest: Bannerughatta National Park is at a distance of about 34 Km from site.
Water Bodies: Hormavu Agara Lake at 565m (south west), Rampura lake 2 km (south east).
1.2 List out all the major project requirements in terms of the Total Plot Area Built up area, Water consumption, Power requirement, connectivity, community facilities, Parking needs etc.,
53,494.64 sq m (13.21 Acres) 1,49,471 sq m 681 KLD The power required for the proposed project will be supplied by BESCOM which is about 5,145 kVA. Project site is located near NH-7 – 6.5 Kms (Bangalore - Hyderbad highway) Total parking provided: 1090 numbers Parking details & drawing is appended as Annexure – O
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site?
(Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology).
No ecological disturbance is anticipated.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability?
(Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc., may be given).
Geotechnical Investigation report of the project site is enclosed as Annexure – L.
18
1.5 Will the proposal involve alteration of natural drainage systems?
(Give details on a contour map showing the natural drainage near the proposed project site)
No
The survey/contour map of the project site is appended as Annexure – O.
1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc.
(Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.)
The proposed project is residential apartment project having basement floor and earth excavation is necessary. The total quantity of excavated soil is about 50,000 cum. About 15,000 cum will be used for landscape development, about 16,000 cum will be used for backfilling and 19,000 cum will be used for formation and hardscaping activities within the project site.
1.7 Give details regarding water supply, waste handling etc., during the construction period.
Sewage generated from construction workers camp will be treated in Package STP.
1.8 Will the low lying areas & wetlands get altered?(Provide details of how low lying and wetlands are getting modified from the proposed activity)
No
1.9 Whether construction debris & waste during construction cause health hazard?
(Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)
Construction debris 400 cum will be used for road formation activities in the project site. The details of solid wastes generated by the construction workers is appended as Annexure – F.
2. WATER ENVIRONMENT:
2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses.
How will the water requirement met?
State the sources & quantities and furnish a water balance statement.
Domestic water requirement is 681 KLD which will be sourced from BWSSB Sources. The details of source of water supply and basis of calculations is appended as Annexure - B. The water balance chart is appended as Annexure – D.
19
2.2 What is the capacity (dependable flow or yield) of the proposed source of water?
Details are applicable as above.
2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)
The expected domestic water requirement is 681 KLD and will be augmented through BWSSB sources.
2.4 How much of the water requirement can be met from the recycling of treated wastewater?
(Give the details of quantities, sources and usage)
The proposed project envisages the utility of treated sewage for recycling purposes by way of using it for flushing of toilets and gardening.
The total quantity of treated sewage available in the project is 545 KLD Toilet Flushing (Recycled): 220 KLD
Water balance chart Furnished as Annexure – D
2.5 Will there be diversion of water from other users?
(Please assess the impacts of the project on other existing uses and quantities of consumption)
No
2.6 What is the incremental pollution load from wastewater generated from the proposed activity?
(Give details of the quantities and composition of wastewater generated from the proposed activity)
The Raw sewage generated from the proposed activity will be treated to tertiary level and the residual organics in the treated wastewater will be practically nil, the treated sewage will be reused, therefore incremental pollution load is not anticipated.
Details of wastewater quality and quantity and design details of STP (600 KLD capacity) and flow chart is appended as Annexure – C.
20
2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.
Rain Water Harvesting Potential from apartment: 45 KLD
Details furnished as Annexure – H
2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis?
Would it aggravate the problems of flooding or water logging in any way?
Adequate and optimal internal storm water drains are created to handle the internal runoff and convey it to external drains.
The detailed drawing for internal storm water management is appended as Annexure – O.
2.9 What are the impacts of the proposal on the ground water?
(Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any)
As the ground water potential is likely to increase due to ground water recharging. The groundwater recharging scheme is planned in the project.
Storm water Management drawing is enclosed as Annexure – O.
2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers?
(Give details of quantities and the measures taken to avoid the adverse impacts)
Runoff contamination from the proposed project is reduced by providing lined gutter for carrying runoff from construction areas and Kerb Stones and bunds to prevent Runoff Contamination.
Preventing the mixing of storm water runoff and sewage from labour camps.
Use of leak proof containers for storage of oil to avoid contamination of runoff.
2.11 How is the storm water from within the site managed?
(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels)
The storm water is channalised through storm water drains to finally join ground water recharge pits and the excess Storm Water free from runoff Contamination will be let to External Drains.
2.12 Will the deployment of construction laborers particularly in the peak period
Sewage generated from the construction workers camp will be
21
lead to unsanitary conditions around the project site (Justify with proper explanation)
treated in package STP.
2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage?
(Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal)
Sewage Treatment Plant is proposed for treatment of domestic sewage from the project and the quantity of wastewater, design details with unit capacity and technology adopted with disposal options is appended as Annexure – C.
2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use.
Dual piping system is proposed to reduce the fresh water consumption.Dual piping system drawing is appended as Annexure – O.
3. VEGETATION
3.1 Is there any threat of the project to the biodiversity?
(Give a description of the local ecosystem with it’s unique features, if any)
No
3.2 Will the construction involve extensive clearing or modification of vegetation?
(Provide a detailed account of the trees & vegetation affected by the project)
About 200 native indigenous species are planted at site. The project site has 308 existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70 Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50 Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.
3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features
(Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)
An area of about 16,014.69 sq m is left for development of landscape. The Ground Coverage area is about 8010.71 sq m The Paved area is 23,862.75 sq m The Land use pattern scheme of the proposed project is detailed in the Comprehensive Project report appended as Annexure – A
Drawing showing the details of Landscaping and other features is appended as Annexure – O
22
4. FAUNA
4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.
No
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
No
4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna
No
5. AIR ENVIRONMENT
5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)
DG sets are the only air pollution source of the project. The DG sets will be provided with adequate stack height to disperse the emissions into the atmosphere.
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.
NA
5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.
Adequate parking facilities are proposed to be provided as per the local building by law.
The parking plan showing the entry & exit to the project site with traffic management is enclosed as Annexure - O.
Traffic management study and measures is appended as Annexure – M.
5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.
Site plan with roads, pedestrian pathways and paved areas of the project is enclosed as Annexure – O
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.
Details of noise mitigation measure proposed is appended as Annexure – G
23
5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.
The DG sets will be provided with acoustic enclosures to reduce the noise level < 55 dB
6. AESTHETICS:
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details.
Once the project is completed approximately about 4,875 people are expected in the building.
7.2 Give details of the existing social infrastructure around the proposed project.
Surrounded by Residential apartments and commercial establishments
7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?
NA
6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?
NA
6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?
The surrounding areas of the project have Residential layouts, Apartments and areas with rural settings and surrounded areas like Bileshivalli, Bileshivalli Colony, Kyalasanahalli, Anagalapura, Geddalahalli, Bhairali, Kotnuru, Agra, Kalkere, Kanaknagar, Chansandra.
6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.
The local byelaw of Bangalore Development Authority is considered in designing the project.
6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.
No
24
8. BUILDING MATERIALS
8.1 May involve the use of building materials with high-embodied energy.
Are the construction materials produced with energy efficient processes?
(Give details of energy conservation measures in the selection of building materials and their energy efficiency)
The proposed project construction materials are selected to conform the building energy efficiency norms and as well as Energy Conservation Building Code Guidelines
The following measures are taken to for conserving the energy
1. Solar powered street lighting for common areas.
2. CFL bulbs, lights and fixtures for common areas
3. Proper sizing of cables with less voltage drop so that losses in cables can be minimized
4. Optimal pumping of water using water level controllers, switching on/off of street lights with photo cell /time switch.
5. Procuring graded electrical appliances which helps in high energy conservations.
6. Timer control for external lighting
7. LED type street lighting fixtures instead of high power sodium vapor light fixture.
8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?
Details appended as Annexure – G
8.3 Are recycled materials used in roads and structures?
State the extent of savings achieved?
The construction waste and debris (400 cum) from the project will be used in road and pavement formation
8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of
The solid Wastes generated are segregated at its point of generation, collected and stored
25
the project. at a common designated place and Organic solid waste will be treated in an organic converter and product will be used as manure for Landscape or used as fuel. The inorganic solid waste is proposed to be recycled.
The details of quantity of solid waste generated is appended as
Annexure – F
9. ENERGY CONSERVATION
9.1 Give details of the power requirements, source of supply, backup source etc.
What is the energy consumption assumed per square foot of built-up area?
How have you tried to minimize energy consumption
The power required for the project is about 5145 kVA and will supply from BESCOM.
Yes, Energy conservation methods are adopted. Non Conventional Sources of Energy with Solar Street Lighting and Solar Hot Water Generation.
Terrace floor plan showing the location of solar panels and tanks is appended as Annexure – O.
9.2 What type of, and capacity of, power back-up to you plan to provide?
The proposed project will be provide with 1 X 250 kVA and 3 X 500 kVA capacity DG sets to serve as alternative source of power supply in case of break down of power from BESCOM. Occupancy phase: Low Sulphur content Diesel consumption of 50 and 100 L/hr for each DG set.
9.3 What are the characteristics of the glass you plan to use?
Provide specifications of its characteristics related to both short wave and long wave radiation?
Low emission and low solar heat gain Single glazed with aluminum frame are proposed to be used for windows etc.,
U = 5.7 W/m2 0C < 6.922W/m2 0C
SHGC = 0.4
26
9.4 What passive solar architectural features are being used in the building?
Illustrate the applications made in the proposed project.
Passive solar architectural features are considered while designing the buildings in respect of orientation of building thermal insulation aspects for wall with fenestration & roof is considered as per ECBC 2007 Guidelines viz., Balconies, Projections, Recessed window etc.,
9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.
Yes
Solar hot water facilities and Solar panels for Street lighting are proposed to be adopted.
Terrace floor plan with solar panel nos. capacity details is appended as Annexure – O.
9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?
As per ECBC Guidelines the thermal transmittance (U) value = 0.409 W/m2-0C for roofs
9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details.
Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions?
Are you using CFC and HCFC free chillers? Provide specifications.
Yes, Passive solar architectural features are considered while designing the project in respect of orientation of building with natural light and ventilation
The Low loss energy efficient transformers, CFL’s, Ballasts, variable frequency drives for motors for low power consumption are proposed.
Variable frequency drive is used for motor and pumps in order to reduce the energy consumption.
9.8 What are the likely effects of the building activity in altering the micro-climates?
Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?
None
27
9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration?
Give details of the material used and the U-values or the R values of the individual components.
For Roof
U – 0.34 W/m2-0C < 0.409 W/m2-0C
For Walls:
U-Value = 0.42 W/m2 0C < 0.431 W /m2 0C
For Vertical Fenestration
U-Value = 5.7 W /m2 0C < 6.922 W/m2 0C and Max. SHGC : 0.40
9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.
The building is designed in compliance with fire and safety norms and the NOC is obtained from Fire Fighting Department. Static Fire water tank as per the regulations is proposed, Wet risers and sprinklers provided as per the Fire Fighting Norms.
9.11 If you are using glass as wall material provides details and specifications including emissive and thermal characteristics.
Low E glasses are considered and as per the details furnished above.
9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.
NA
9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption?
Provide details of the renewable energy technologies used.
Solar hot water facilities and Solar Street lighting system are proposed.
28
10. Environment Management Plan:
10.1 The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.
Wet risers/down riser, fire alarm system, automatic sprinklers system, and portable fire extinguishers are proposed in case of fire accidents.
Details of mitigation measures to minimize adverse environmental impacts during construction and operation phase of the project is appended in Environmental Monitoring plan is enclosed as Annexure – G.
“I hereby give undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the Project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. Date: 13.10.2015 Place: Bangalore
Following approach will be adopted for Vegetation and Ground Management. It is
planned to include an ecologically knowledgeable landscape architect as an
integral member of the design team.
Preservation of existing vegetation, especially native plants, will possibly be
incorporated. Avoid fencing off property where possible to make landscape
available to community increasing project integration.
Decrease paving and monoculture lawns.
Avoid replacing mature trees with young seedlings.
Protect existing plants during construction. Delineate the "drip line"
around trees and demark or fence off areas to avoid damage.
Contain heavy equipment and stockpiling areas to predefined areas.
Design new plantings as diverse communities of species well adapted to
the site. Plant native species of varying ages. Select vegetation that
attracts wildlife.
Avoid invasive species and monocultures (same species, same age).
ROHAN BUILDERS PROJECT
67 PROJECT REPORT
4. MANAGEMENT OF SOCIO-ECONOMIC ISSUES:
1) Schools for laborer’s children
Temporary education centers (Creche) will be provided for education of the
children of the laborers.
2) Health camp for laborer’s family
Periodical health camps will be organized to monitor and facilitate the occupants
of the labor camps.
HEALTH RISK AND DISASTER MANAGEMENT:
Public health and safety:
Since all the construction related activities are confined to the project site, minimal
health related impacts are envisaged within the project influenced area during the
construction stage.
At the project site on an average of 300 no. of persons will be engaged, who face
direct exposure to dust and noise generated from the construction activity. This is
likely to cause health related affects such as asthma, bronchitis etc., and hearing
impairments respectively.
To minimize these anticipated impacts, suitable actions like
• Use of water sprinklers to prevent dust from being air borne.
• Providing suitable Personal Protective Equipments (PPE) like mouth mask with
filters, noise mask, helmets etc.,
• Periodic health check up camp for the laborers will be arranged.
• Provision of safety belts.
• In case of injury on site medical treatment and transport will be organized.
Due to operation of the proposed project, there will be enhancement in public Health
and safety.
Regular visit of resident medical officer to take care of the first aid and
primary medication in case of emergency for project occupants and laborers.
ROHAN BUILDERS PROJECT
68 PROJECT REPORT
First aid kit with primary medicines will always be available in the medical
centre.
Display of action plan and preparedness measures during emergency situations.
5. EMP IMPLEMENTATION SCHEDULE:
Phased according to the priority, the implementation schedule is presented in the
following table.
Implementation Schedule for EMP
Sl.
No.
Recommendations Requirement
1 Air pollution control measures Before commissioning of respective units
2 Water pollution control measures Before commissioning of the project
3 Noise control measures Along with the commissioning of the
Project
4 Solid waste management During commissioning of the project
5 Green belt development Stage-wise implementation
The responsibility of EMP implementation lies with the project promoter for a period
of 3 years. Once the residents' society is established, the EMP responsibility will be
properly handed over with clearly defined procedures and guidelines.
ROHAN BUILDERS PROJECT
69 PROJECT REPORT
FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS
(OCCUPANCY PHASE)
Sl.
No.
Description Financial Provision in Lakhs
Capital
Cost
Recurring
Cost
1 Operation of Sewage Treatment Plant - 5.0
2 Reclaimed Sewage Distribution Network 5.0 1.0
3 Rain water harvesting tanks and its facilities 10.0 2.0
4 Ground water recharging pits & its management 10.0 2.0
5 DG sets acoustic & Maintenance 5.0 1.0
6 Landscaping 10.0 2.0
7 Solid waste management 8.0 1.0
8 Environmental Monitoring Plan per annum (Air,
Noise, Water and Soil)
- 2.0
9 TOTAL 48.0 16.0
Contingency at 10 % 4.8 1.6
TOTAL 52.8 17.6
ROHAN BUILDERS PROJECT
70 PROJECT REPORT
6. ENVIRONMENTAL MONITORING ROUTINES:
A comprehensive monitoring program is suggested below:
Monitoring Schedule for Environmental Parameters
Sl. No
Particulars
Monitoring frequency
Duration of monitoring
Important parameters for
monitoring
I Air Quality
1. Ambient Air monitoring
Project premises Once in a month
24 hourly sample
RSPM, SPM, SO2, NOx
2. Stack monitoring
Once in a year if required
Grab SPM, SO2, NOx, HC, CO
II Water and Wastewater Quality
1. Water Quality
i. Groundwater at two locations (up-gradient and down-gradient) of treated effluent discharge area/land
Once in a month
Grab As per KSPCB requirements
2. Wastewater quality
i. Inlet into STP NA NA -
ii. Treated effluent prior to discharge
NA NA -
III Soil Quality
1. Within project premises at 1 location on effluent discharging area/land
Once in 6 month
Composite sample
As per KSPCB requirements
2. Ecological preservation and up gradation
Seasonal Visual observations
Survival rate
IV Noise monitoring
1. Project premises Once in 6 month
Day and night As per KSPCB requirements
ROHAN BUILDERS PROJECT
71 PROJECT REPORT
ANNEXURE: H
7.0 RAINWATER MANAGEMENT PLAN:
7.1 RAIN WATER HARVESTING:
The water collected from the terraces of the buildings shall be collected in the
rainwater collection sump and reused for domestic purpose after necessary
treatment.
7.2 VOLUME OF RAIN WATER HARVESTED:
The total quantity of water i.e., received in the form of rainfall over an area is called
the rain water endowment of that area, out of which the amount of water that can be
effectively harvested is called the rain water harvesting potential.
Rain Water harvesting potential = Intensity of Rainfall (m) x Roof Area x
Impermeability Factor.
The collection efficiency accounts for the fact that all the rain water falling over an
area cannot be effectively harvested due to losses on account of evaporation, spillage
or run off etc.,
According to the data available from the Indian Meteorological Department, the
Average annual rainfall around month of September = 194.80 mm
Assuming that about 90 % Rainfall can be effectively harvested.
Number of Rainy Days = 9.3
Therefore the I.R = 194.80/9.3= 20.94 mm/day or 0.02094 m/Day or 0.021 m/day
The Quantity of roof top rainwater harvested from the proposed is calculated as
under:
The 14th floor area of the proposed project is about 6,548.55 sq m
For rain water harvesting consider 75 % of this total area is 4,911 sq m
Quantity of Rain Water that can be harvested from the building is as follows.
Rain water (Q) from Roof top = 0.021 x 4,911 x 0.9
= 92.81 cum/day or say 93 cum/day
ROHAN BUILDERS PROJECT
72 PROJECT REPORT
Rain water storage sump of 100 cum (1 no) capacity is constructed to collect the rain
water and is being reused for domestic purposes.
7.3 STORM WATER MANAGEMENT:
Storm water disposal is divided into 2 Groups:
Terrace Storm water disposal: The entire rainwater from the terrace would be
disposed through suitable rain water pipes and collecting in the dedicated rain
water collection sump, which is proposed at site level. This water will be
utilized for domestic purpose
Site (Paved and landscape area) Storm water disposal: The entire storm water
from the site would be disposed off through suitable RCC Box drainage system
to the rainwater recharge pits and the excess is diverted to external storm
water drainage.
The amount of storm water that the paved area will produce can be determined by
considering the impermeability factor to be 0.9.
Q = 0.021 x 23,862.75sq m x 0.9
= 451.00 cum/day or say 451 cum/day
The amount of storm water that the landscaped area will produce can be determined
by considering the impermeability factor to be 0.3
Q = 0.021 x 16,014.69 sq m x 0.3
= 100.89 cum/day or say 101 cum/day
The Total amount of storm water = paved area + landscaped area
= 451 + 101 cum/day
= 552 cum/day
The Proponents shall also Provide Recharging Pits along the inner periphery of the
boundary wall with recharging pit of size 1.2 m dia x 2.5 m deep spaced at 20 m
centre to centre. These recharging pits are filled with graded media comprising of
Boulder at bottom and with coarse aggregates to facilitate percolation of harvested
rain water to Recharge Ground Water table.
ROHAN BUILDERS PROJECT
73 PROJECT REPORT
ANNEXURE: I
DISASTER MANAGEMENT PLANS FOR PRE CONSTRUCTION PHASE:
Risk and disaster management plan:
Disaster is an unexpected event due to sudden failure of the system, external
threats, internal disturbances, earth quakes, fire and accidents. Thus an appropriate
management plan shall be incorporated.
Precautions:
Once the likelihood of the disaster is suspected, preventive actions should be
undertaken by the project in-charge.
Conditional maintenance of equipments, materials and expertise for use during
emergency.
The electrical systems shall be provided with automatic circuit breakers
activated by over current.
Proper escape routes are planned and displayed in the public domain.
Selected representatives are given proper training to guide other inhabitants
during Fire accidents.
Periodic awareness program is conducted for the workers on their roles during
emergency situations.
Important telephone numbers like police authorities, fire department and hospitals
etc., of use during emergency situations will be made available.
ROHAN BUILDERS PROJECT
74 PROJECT REPORT
ANNEXURE: J
Environmental Management Plan for control of Dust and Noise pollution during
construction phase:
Barricades like metal sheets will be provided all round the premises of the project
to avoid fugitive dust emission in to the neighboring area and frequent water
sprinkling will also be carried out.
Environmental Impacts Mitigation Proposed
1. Leveling and Site Clearance:
Noise generation: Caused due to Excavators and Bulldozers
Most optimum no. of operation by the heavy equipment
Selection of equipment with less noise generation to be used
The earth moving equipment will be periodically checked and maintained for noise levels.
The workers will be provided with adequate PPE such as ear plugs to reduce impact of high noise levels.
Dust generation: Leveling operations results in the emission of dust.
The site cleared will be periodically watered to reduce emission of dust particles
Barricades like metal sheets will be provided all round the premises to avoid fugitive dust emission in to the neighboring area apart from water sprinkling.
The workers will be provided with PPE such as nose masks and goggles to reduce impact on health.
2. Transportation of Construction Materials:
Dust generation
Quality packaging of the construction materials
Construction materials will be covered with tarpaulin sheet to prevent from being air borne
The vehicle speed shall be regulated
Noise generation
Quality fuel will be used.
Periodic maintenance of vehicles is required.
ROHAN BUILDERS PROJECT
75 PROJECT REPORT
The workers transporting materials will be provided with PPE such as nose masks to reduce impact of air borne dust on their health
1. Construction Activities:
Noise generation
Selection of Less noise generating equipment
Personnel Protective Equipment (PPE) such as ear plugs and helmets will be provided for workers
The working hours will be imposed on the construction workers.
Dust generation PPE in the form of nose masks will be provided for construction workers
Use of water sprays to prevent dust from being air borne
Barricades like metal sheets will be provided all around the premises to avoid fugitive dust emission in to the neighboring area apart from water sprinkling
ROHAN BUILDERS PROJECT
76 PROJECT REPORT
ANNEXURE: K
RISK ASSESSMENT & MANAGEMENT PLAN
a. Construction Phase:
Sl. No.
Potential Mitigation
1 Accidental fire Fire safety gadgets.
2 Fall of objects Use of personal protection devices-helmets
3 Working at great heights Protection to prevent fall, with life safety belts and nets.
4 Accidents from machinery Personal protection gadgets
5 Electrical mishap Adopting safety measures to prevent any act of negligence and providing electrical safety measures like fire extinguishers.
b. All necessary measures will be taken to avoid accidents and mishaps during operation phase.
Precautions for Risk and Disaster Management Plan:
Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the project in-charge.
Conditional maintenance of equipments, materials, and expertise for use during emergency.
The electrical systems shall be provided with automatic circuit breakers activated by over current.
Fire extinguishers provided at pre-notified locations inside the building.
Proper escape routes will be planned and displayed in the public domain.
Selected representatives will be given proper training to guide other inhabitants during Fire accidents.
Periodic awareness program is conducted for the occupants on their roles during emergency situations.
Important telephone numbers like police authorities, fire department and hospitals
etc., of use during emergency situations are made available.
ROHAN BUILDERS PROJECT
77 PROJECT REPORT
ANNEXURE: L
SOIL INVESTIGATION REPORT
ROHAN BUILDERS PROJECT
78 PROJECT REPORT
ANNEXURE: M
TRAFFIC MANAGEMENT MEASURES
• Merging of vehicles will be performed only to left traffic from the exit gates,
this ensures safety.
• To establish smooth entry & exit of vehicles, bell mouth shape geometry is
provided at the gates. This ensures smooth transition for merging of vehicles.
• Yellow paint junction boxes are painted at the locations to create psychological
barrier for through drivers to control the speed.
• Rubber humps are introduced for the outgoing vehicles at the exit gate drive
way. All gates are manned with efficient security who can guide the entry and
exit of vehicles.
• Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress).
• Road marking, STOP lines, parking lanes, slot numbers etc, must be clearly
painted so as to guide the vehicles.
ROHAN BUILDERS PROJECT
79 PROJECT REPORT
ANNEXURE: N
ELECTRICAL ENERGY SAVINGS DETAILS
Energy Efficient motors, whose efficiency is not lower than the limits specified in section 8.2.2 of the ECBC code will be installed. b. Dry type Transformer with efficiency not lower than the limits specified in section 8.2.1 of the code shall be considered. c. Power monitoring, recording and check metering will be provided in the main LT panels on the incoming feeders and individual outgoing feeders covering all parameters such as Current, Voltage, Energy & THDI as stipulated in section 8.2.4 of the code. d. Cable sizing and design of distribution system will ensure that the total distribution loss will not exceed 1% of the total energy consumed as stipulated in section 8.2.5.1 of the code. e. Timer controls will be incorporated in the distribution board of external lighting to save energy as stipulated in section 7.4 of the code. f. Power conditioning equipment will be installed to limit THDI to 5% which shall also improve power factor to 0.95 as stipulated in section 8.2.3 of the code. g. Solar Lighting shall be provided at strategic locations in outdoor areas. h. Water cooled Chillers are used instead of air cooled chillers which provide energy savings. j. VFD drives shall be provided for secondary pumps for water cooled chillers and lifts which will result in energy savings.