Top Banner
PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECT At Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5, 48/6 and 49/2, Kyalasanahalli Village, K R Puram Hobli, Bangalore East, Bangalore. Submitted By M/s. Rohan Builders #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar Bangalore – 560038 Submitted to STATE LEVEL ENVIRNOMENT IMPACT ASSESSMENT AUTHORITY (SEIAA), KARNATAKA. ENVIRONMENTAL CONSULTANTS M/s. AQUA TECH ENVIRO ENGINEERS, # 3391, 6th Main, 3rd Cross, RPC Layout, Vijayanagar II Stage, Bangalore – 560 040. Tele Phone: 080 23141679.
81

PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

Feb 02, 2018

Download

Documents

tranhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECT

At

Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5,

48/6 and 49/2,

Kyalasanahalli Village, K R Puram Hobli,

Bangalore East, Bangalore.

Submitted By

M/s. Rohan Builders #1201, 1st floor, Divyashakti, 100 feet road,

Indiranagar Bangalore – 560038

Submitted to

STATE LEVEL ENVIRNOMENT IMPACT ASSESSMENT AUTHORITY (SEIAA), KARNATAKA.

ENVIRONMENTAL CONSULTANTS

M/s. AQUA TECH ENVIRO ENGINEERS, # 3391, 6th Main, 3rd Cross, RPC Layout, Vijayanagar II Stage, Bangalore – 560 040.

Tele Phone: 080 23141679.

Page 2: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

INDEX

SL NO DESCRIPTION

1 APPLICATION IN FORM I

2 APPLICATION IN FORM I A

ANNEXURE TO APPLICATIONS

A B C

D E F

G

H I J K L

M

N 0

COMPREHENSIVE PROJECT REPORT WATER REQUIREMENT DETAILS FOR THE PROJECT SEWAGE GENERATION, UTILITY OF TREATED SEWAGE & DESIGN DETAILS OF SEWAGE TREATMENT PLANTS WATER BALANCE CHART WATER REQUIREMENT AND SEWAGE DISPOSAL DURING CONSTRUCTION PHASE SOLID WASTE GENERATION & MANAGEMENT DETAILS (CONSTRUCTION & OPERATION PHASE) ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN (EMP) FOR CONSTRUCTION AND OCCUPANCY PHASES RAIN WATER MANAGEMENT SCHEME DISASTER MANAGEMENT PLAN FOR PRE-CONSTRUCTION PHASE EMP FOR CONTROL OF DUST AND NOISE DURING CONSTRUCTION PHASE. RISK ASSESSMENT & MANAGEMENT PLAN GEO TECHNICAL INVESTIGATION REPORT TRAFFIC SURVEY AND ITS MANAGEMENT SAVINGS IN ELECTRICAL POWER CONSUMPTION PROJECT RELATED DRAWINGS/PLANS

Page 3: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

1

APPENDIX I

(See paragraph – 6)

FORM 1

(I) Basic Information

1 Name of the Project Residential Apartment Project with 975 units.

2 S. No. in the schedule Serial No. 8 (a) of schedule

3 Proposed capacity/area/ length/tonnage to be handles/command area/lease area/number of wells to be drilled

Residential Apartment Project: Proposed units: 975 Built up area: 1,49,471 sq m Plot area: 53,494.64 sq m (13.21 Acres) Cost: Rs. 313 Crores

4 New / Expansion / Modernization New project

5 Existing capacity / Area etc., NA

6 Category of project i.e., `A` or `B` B

7 Does it attract the general condition? If yes, please specify.

NO

8 Does it attract the specific condition? If yes, please specify.

NO

9 Location Residential Apartment Project with 975 units.

Plot/Survey/Khasra No. Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5, 48/6 and 49/2,

Village kyalasanahalli

Thesil Bangalore East taluk

District Bangalore

State Karnataka

10 Nearest railway station/airport along with distance in Kms.

Bangalore city railway station and kempegowda International Airport Limited at about 25 Kms & 20 Kms respectively.

11 Nearest Town, City, District Headquarters along with distance in Kms.

Nearest town - Bangalore City & District – Bangalore

12 Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (Complete postal addresses with telephone nos. to be given)

Bruhat Bengaluru Mahanagara Palike (BBMP), N R Square, Bangalore – 560 002. Phone: 080 22975555.

13 Name of the applicant Rohan Builders

14 Registered address #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar Bangalore – 560038

Page 4: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

2

15 Address for correspondence: As above

Name SANTOSH LUNKAD

Designation (Owner/Partner/CEO) Deputy General Manager

Address #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar

Pin Code Bangalore – 560 038.

E – mail [email protected]

Telephone No. 080 25203520

Fax No. -

16 Details of alternative Sites examined, if any. Location of these sites would be shown on a topo sheet.

Village – District – State 1. 2. No alternative sites are examined.

17 Interlined Projects NA

18 Whether separate application of interlinked project has been submitted?

NA

19 If yes, date of submission NA

20 If no, reason Proposed project is Residential Apartment with 975 Flats

21 Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given a) The Forest (Conservation) Act 1980? b) The wildlife (Protection) Act, 1972? c) The C R Z Notification, 1991?

NO NO NO

22 Whether there is any Government Order/Policy relevant/relating to the site?

None

23 Forest land involved (Hectares) None

24 Whether there is any litigation pending against the project and/or land in which the project is propose to be set up?

a) Name of the court b) Case No. c) Orders/directions of the court,

if any and its relevance with the proposed project.

None

Screening Category: The proposed project is under Item 8 B Category as per amended EIA notification September 14th 2006.

Page 5: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

3

Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure, generation capacity for power generation etc.,)

(ii) Activity:

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.,)

Sl. No.

Information/Checklist confirmation Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

Yes The project is designed in concurrence with the Bangalore Development Authority and therefore there will not be any permanent or temporary changes in land use, though the proposed project is likely to increase the intensity of land use.

1.2 Clearance of existing land, vegetation and buildings?

No About 200 native indigenous species are planted at site. The project site has 308 existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70 Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50 Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.

1.3 Creation of new land uses? No Creation of new land uses from the proposed project is not expected as the intended use of the plot is for the Residential Apartment.

1.4 Pre-construction investigations e.g. bore houses, soil testing?

Yes Geotechnical investigation report is enclosed as Annexure – L.

1.5 Construction works?

Yes The proposed project mainly involves construction activities. These activities are likely to have certain impact on the surrounding environment in respect of Air, Water, Land etc., The associated impact of construction activity on the above environmental attributes and the mitigation measures

Page 6: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

4

adopted in the project is appended as Annexure – G.

1.6 Demolition works? No There is no demolition work involved in the proposed project site.

1.7 Temporary sites used for construction works or housing of construction workers? (Details of labour camps, Number of labours, Number of toilets, Bath rooms, Medical facilities for labours, safety measures for labours, Nursery for labours children)

Yes About 500 construction workers will be engaged for construction activities.

50 Sheds and 100 Toilets with bathrooms will be provided for construction workers. Sheds for construction workers will be provided within the project site. Drinking water supply and adequate storage facility will be provided for construction workers. The workers will be provided with first aid facilities apart from personal protective gadgets. Periodic health assessment camps and administration of medicines as and when required will be provided. A small class room with a teacher (crèche) to educate the children of construction worker will be provided.

1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations (Calculation for earth work estimation)

Yes Above ground structures are proposed. The proposed project involves Construction of Residential Apartment. Activity, Area statement and Building Configuration details of the project is detailed in the Comprehensive project report appended as Annexure - A. The proposed project is residential apartment project having basement floor and earth excavation is necessary. The layout is planned

Page 7: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

5

keeping the natural ground profile in consideration so that minimum excavation would be required. The total quantity of excavated soil is about 50,000 cum. About 15,000 cum will be used for landscape development, about 16,000 cum will be used for backfilling and 19,000 cum will be used for formation and hardscaping activities within the project site.

1.9 Underground works including mining or tunneling?

No NA

1.10 Reclamation works? No NA

1.11 Dredging? No NA

1.12 Offshore structures? No NA

1.13 Production and manufacturing processes?

No NA

1.14 Facilities for storage of goods or materials?

Yes Temporary sheds will be constructed for storage of construction materials.

1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

Yes Liquid waste: The liquid waste from workers camps will be treated in Package STP. Water requirement for the Construction phase is appended as Annexure - E. Sewage Treatment Plant (STP) of capacity 600 KLD will be constructed to treat the wastewater generated from the project during occupancy phase. Quantity of wastewater generation and design details of STP is appended as Annexure – C. Solid Waste: Construction Phase: The domestic wastes will be segregated and collected at a common designated place and will be disposed through BBMP. Solid waste like construction debris

Page 8: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

6

generated during construction phase of about 400 cum will be used for preparation of sub grades for Roads, pavements and pathways. Occupancy Phase: Collection and segregation at the source of generation and Organic waste will be treated in Organic Converter and the Inorganic waste will be sent for recycling. The solid waste generation detail is appended as Annexure – F.

1.16 Facilities for long term housing of operational workers?

Yes No long term housing plan for the operational worker is planned in the proposed project as the local population residing in the surrounding areas of the project site will find the employment opportunity for various maintenance needs of the project once it is occupied.

1.17 New road, rail or sea traffic during construction or operation?

No NA

1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

No NA

1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

No NA

1.20 New or diverted transmission lines or pipelines?

No NA

1.21 Impoundment, damming, culver ting, realignment or other changes to the hydrology of watercourses or aquifers?

No NA

1.22 Stream crossings? No NA

1.23 Abstraction or transfers of water form ground or surface waters?

Yes The water supply is from BWSSB Source.

1.24 Changes in water bodies or the land surface affecting drainage or run-off?

No NA

1.25 Transport of personnel or materials for construction, operation or decommissioning?

Yes Transport facilities are not proposed as the workers will be provided with sheds to be located within the project site.

Page 9: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

7

The impacts due to the movement of vehicle both during construction and occupancy phase is detailed in the Traffic Management studies appended as Annexure – M.

1.26 Long-term dismantling or decommissioning or restoration works?

No NA

1.27 Ongoing activity during decommissioning which could have an impact on the environment?

No NA

1.28 Influx of people to an area in either temporarily or permanently?

Yes There will be Influx of population during the construction and occupancy phase as detailed under. Temporarily during construction phase (500 numbers) and permanent during occupancy phase (4,875 numbers) are expected.

1.29 Introduction of alien species? No NA

1.30 Loss of native species or genetic diversity?

No NA

1.31 Any other actions? No NA

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Sl.No Information/checklist confirmation

Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha)

Yes The proposed project site is converted for residential purposes. The net site area is 4.8 Hectares.

2.2 Water (expected source & competing users) unit: KLD

Yes The water for the proposed project will be from BWSSB Sources. Total water requirement is about 681 KLD

2.3 Minerals (MT) No NA

2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)

Yes Description Unit Quantity

Cement Bags 7,00,284

Steel MT 7,878

Sand Cum 64,776

Tiles sq m 1,49,633

Stone Aggregate cum 56,023

Granite/Marble sq m 39,035

Page 10: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

8

Aluminium sq m 1,626

Wood cft 11,385

2.5 Forests and timber (source– MT) Yes Procured through local timber depots.

2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)

Yes Power Requirement: Construction phase: Temporary power from BESCOM to operate construction machinery and Lighting for workers shed is 2 X 150 kVA.

DG Set of 2 X 150 kVA capacity is proposed to serve as back up power supply during power failure.

Occupancy phase:

Anticipated power requirement from BESCOM is 5,145 kVA.

1 X 250 kVA & 3 X 500 kVA capacity DG sets is proposed, which will serve as back up power supply during power failure.

Fuel Requirement: Construction phase: Low Sulphur content Diesel consumption is 30 L/hr for DG set of 2 X 150 kVA capacity respectively.

Occupancy phase: Low Sulphur content Diesel of 50 L/hr and 100 L/hr for each DG set.

2.7 Any other natural resources (use appropriate standard units)

No NA

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Sl.No Information/Checklist confirmation

Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

No NA

Page 11: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

9

3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

No NA

3.3 Affect the welfare of people e.g. by changing living conditions?

Yes The implementation of the proposed project is beneficial both socially and economically to its local populace, as it creates both long term and short term employment opportunities.

3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

No NA

3.5 Any other causes No NA

4. Production of solid wastes during construction or operation or Decommissioning (MT/Month)

Sl.No Information/Checklist confirmation

Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes No NA

4.2 Municipal waste (domestic and or commercial wastes)

Yes The quantity of solid waste generation and its management during Construction and Occupancy phase is appended as Annexure – F.

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

Yes Spent oil from DG sets category 5.1. About 300 L/Annum of spent oil is generated which is sent to authorized spent oil reprocessor with manifest as per notification of Hazardous Waste (Management and Handling Rules).

4.4 Other industrial process wastes No NA

4.5 Surplus product No NA

4.6 Sewage sludge or other sludge from effluent treatment

No The secondary dewatered STP sludge is 216 kgs/day and is taken from Plate and Frame Filter Press and used as manure.

4.7 Construction or demolition wastes Yes There is no demolition work involved in the proposed project and all efforts will be made to reduce construction waste by adopting modern construction practices such as proportioning and weigh batchers for concreting.

Page 12: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

10

Construction debris of about 400 cum is generated which will be used as preparatory materials for road, pavement and sub grade formation within the project site.

4.8 Redundant machinery or equipment

No NA

4.9 Contaminated soils or other materials

Yes Measures adopted to control soil contamination. 1. Providing collection trays to collect oil dripping from construction machineries if any. 2. Prevention of spillage and leakage of oils if required. 3. Providing kerb stones, lined gutter and oil traps.

4.10 Agricultural wastes No NA

4.11 Other solid wastes No NA

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl. No Information/Checklist confirmation

Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

Yes There is no other source of emission from the project other than from stationary sources like DG sets to be installed during occupancy period.

5.2 Emissions from production processes

No NA

5.3 Emissions from materials handling including storage or transport

Yes Fugitive dust due to movements of vehicles carrying construction materials. Proposed measures for control of dust and noise during construction phase is appended as Annexure - J.

5.4 Emissions from construction activities including plant and equipment

Yes Fugitive dust during earthwork, concreting, construction material handling. Closed operations for mixing of construction materials will be followed.

5.5 Dust or odours from handling of materials including construction

Yes Fugitive dust due to handling of construction materials.

Page 13: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

11

materials, sewage and waste Emission of fugitive dust will be controlled by sprinkling of water and barricading will be provided all around the project site. Details of control of Dust and Noise during construction phase is appended as Annexure – J.

5.6 Emissions from incineration of waste

No NA

5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)

No NA

5.8 Emissions from any other sources No NA

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl. No.

Information/Checklist confirmation

Yes/No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data with source of information data

6.1 From operation of equipment e.g., engines, ventilation plant, crushers

Yes Operation of DG set during occupancy phase. Appropriate and adequate noise control measures will be adopted to control noise. DG Sets are set-up in room with acoustic enclosures. Further noise attenuation by way of planting peripheral trees as noise barriers.

6.2 From industrial or similar processes

No NA

6.3 From construction or demolition No Noise generation due to construction activities will be negligible and barricades will be erected all round the site. Details of control of Noise during construction phase are appended as Annexure – J. However there is certain increase in ambient noise level during construction activities which will be reduced by under taking periodic preventive maintenance of construction materials and restricting and reducing the speed of vehicle operated for the

Page 14: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

12

movements of construction materials. All appropriate measure as detailed for 6.1 above is applicable.

6.4 From blasting or piling No NA

6.5 From construction or operational traffic

Yes Construction phase: Vehicles carrying construction materials Occupancy phase: Vehicular movement by the occupants. The details of mitigation measure planned to reduce the noise level is appended as Annexure - G.

6.6 From lighting or cooling systems No NA

6.7 From any other sources No NA

7.Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sl.

No.

Information/Checklist confirmation

Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

7.1 From handling, storage, use or spillage of hazardous materials

Yes Appropriate management measures to prevent contamination of land, water are detailed in Annexure - G under water and land environment. Disaster management plan for Pre construction phase is appended as Annexure – I

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

Yes The total quantity of wastewater generated from the proposed project is about 528 KLD. The treated sewage from the project will be used for landscape development and toilet flushing. Water Balance Chart is appended as Annexure – D.

7.3 By deposition of pollutants emitted to air into the land or into water

No NA

7.4 From any other sources No NA

7.5 Is there a risk of long term build up of pollutants in the environment from these sources?

No NA

Page 15: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

13

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Sl.No.

Information/Checklist confirmation Yes /No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances

No NA

8.2 From any other causes No No major risk from the project is anticipated. Risk Assessment & Management Plan for the project is appended as Annexure – K

8.3 Could the project be affected by natural disasters causing environmental damage (e.g. Floods, earthquakes, landslides, cloudburst etc)?

No NA

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.

Sl. No

Information/Checklist confirmation Yes /No

Details thereof (with approximate quantities/rates,wherever possible) with source of information data

9.1 L Lead to development of supporting. Utilities ancillary development or development stimulated by the project which could have impact on the environment e.g.:

• Supporting infrastructure (roads, power supply, waste or wastewater treatment, etc.) • housing development • extractive industries

Yes Yes Yes No

Net Positive Impact in terms of overall development of the Area is expected from the project. Direct & Indirect Employment opportunities are also created due to development of this project. New business opportunities are expected to cater the daily needs of the residents of the project. Construction of Residential apartment project with 975 flats

Page 16: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

14

• supply industries

• other

No No

9.2 Lead to after-use of the site, which could have an impact on the environment

No NA

9.3 Set a precedent for later developments

Yes The project development is likely to set precedence to other likely developments in the surrounding area.

9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects

No NA

(II) Environmental Sensitivity:

Sl. No.

Areas Name/ Identity

Aerial distance (within 15 km.) Proposed project location boundary

1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

No NA

2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses other water bodies, coastal zone, biospheres, mountains, and forests.

Yes Hormavu Agara Lake at 565m (south west), Rampura lake 2 km (south east).

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

No NA

4 Inland, coastal, marine or underground waters

No NA

5 State, National boundaries No NA

6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas

No NA

7 Defense installations No NA

8 Densely populated or built-up area No N

9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)

No NA

10 Areas containing important, high quality or scarce resources(ground water

No NA

Page 17: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

15

resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

No NA

12 Areas susceptible to natural hazard which could cause the project to present environmental problem (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

No NA

Page 18: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

16

APPENDIX II

(See paragraph 6)

FORM-1 A

(Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring program)

1. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted)

Attach Maps of

(i) site location (Google Image showing the project site location with surrounding details is enclosed)

(ii) surrounding features of the proposed site (within 500 meters)

(iii) The site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

The existing land use does not get altered significantly as the project surroundings have Residential layouts, Apartments and areas with rural settings.

Surrounding Features: Google, Location map of the project site is enclosed as Annexure - O.

Land Availability & Land use Pattern: The plot area of the project is 53,494.64 sq m

Land Use Pattern: The land around the project site indicates a mixed land use pattern; there are Residential layouts, Apartments, few Commercial Establishments and surrounded by areas like Bileshivalli, Bileshivalli Colony, Kyalasanahalli, Anagalapura, Geddalahalli, Bhairali, Kotnuru, Agra, Kalkere, Kanaknagar, Chansandra.

Transportation: Project site is located on Avalahalli Main Road and located at a distance of 5 Kms from Hennur - K R puram outer ring road. The site is also accessible from Hennur Main Road and Kalkere Main Road.

Page 19: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

17

Agricultural Land: Plantations are seen in the surrounding areas, No agriculture lands are found in the vicinity.

Forest: Bannerughatta National Park is at a distance of about 34 Km from site.

Water Bodies: Hormavu Agara Lake at 565m (south west), Rampura lake 2 km (south east).

1.2 List out all the major project requirements in terms of the Total Plot Area Built up area, Water consumption, Power requirement, connectivity, community facilities, Parking needs etc.,

53,494.64 sq m (13.21 Acres) 1,49,471 sq m 681 KLD The power required for the proposed project will be supplied by BESCOM which is about 5,145 kVA. Project site is located near NH-7 – 6.5 Kms (Bangalore - Hyderbad highway) Total parking provided: 1090 numbers Parking details & drawing is appended as Annexure – O

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site?

(Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology).

No ecological disturbance is anticipated.

1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability?

(Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc., may be given).

Geotechnical Investigation report of the project site is enclosed as Annexure – L.

Page 20: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

18

1.5 Will the proposal involve alteration of natural drainage systems?

(Give details on a contour map showing the natural drainage near the proposed project site)

No

The survey/contour map of the project site is appended as Annexure – O.

1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc.

(Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.)

The proposed project is residential apartment project having basement floor and earth excavation is necessary. The total quantity of excavated soil is about 50,000 cum. About 15,000 cum will be used for landscape development, about 16,000 cum will be used for backfilling and 19,000 cum will be used for formation and hardscaping activities within the project site.

1.7 Give details regarding water supply, waste handling etc., during the construction period.

Sewage generated from construction workers camp will be treated in Package STP.

1.8 Will the low lying areas & wetlands get altered?(Provide details of how low lying and wetlands are getting modified from the proposed activity)

No

1.9 Whether construction debris & waste during construction cause health hazard?

(Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

Construction debris 400 cum will be used for road formation activities in the project site. The details of solid wastes generated by the construction workers is appended as Annexure – F.

2. WATER ENVIRONMENT:

2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses.

How will the water requirement met?

State the sources & quantities and furnish a water balance statement.

Domestic water requirement is 681 KLD which will be sourced from BWSSB Sources. The details of source of water supply and basis of calculations is appended as Annexure - B. The water balance chart is appended as Annexure – D.

Page 21: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

19

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

Details are applicable as above.

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

The expected domestic water requirement is 681 KLD and will be augmented through BWSSB sources.

2.4 How much of the water requirement can be met from the recycling of treated wastewater?

(Give the details of quantities, sources and usage)

The proposed project envisages the utility of treated sewage for recycling purposes by way of using it for flushing of toilets and gardening.

The total quantity of treated sewage available in the project is 545 KLD Toilet Flushing (Recycled): 220 KLD

Water balance chart Furnished as Annexure – D

2.5 Will there be diversion of water from other users?

(Please assess the impacts of the project on other existing uses and quantities of consumption)

No

2.6 What is the incremental pollution load from wastewater generated from the proposed activity?

(Give details of the quantities and composition of wastewater generated from the proposed activity)

The Raw sewage generated from the proposed activity will be treated to tertiary level and the residual organics in the treated wastewater will be practically nil, the treated sewage will be reused, therefore incremental pollution load is not anticipated.

Details of wastewater quality and quantity and design details of STP (600 KLD capacity) and flow chart is appended as Annexure – C.

Page 22: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

20

2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Rain Water Harvesting Potential from apartment: 45 KLD

Details furnished as Annexure – H

2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis?

Would it aggravate the problems of flooding or water logging in any way?

Adequate and optimal internal storm water drains are created to handle the internal runoff and convey it to external drains.

The detailed drawing for internal storm water management is appended as Annexure – O.

2.9 What are the impacts of the proposal on the ground water?

(Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any)

As the ground water potential is likely to increase due to ground water recharging. The groundwater recharging scheme is planned in the project.

Storm water Management drawing is enclosed as Annexure – O.

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers?

(Give details of quantities and the measures taken to avoid the adverse impacts)

Runoff contamination from the proposed project is reduced by providing lined gutter for carrying runoff from construction areas and Kerb Stones and bunds to prevent Runoff Contamination.

Preventing the mixing of storm water runoff and sewage from labour camps.

Use of leak proof containers for storage of oil to avoid contamination of runoff.

2.11 How is the storm water from within the site managed?

(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels)

The storm water is channalised through storm water drains to finally join ground water recharge pits and the excess Storm Water free from runoff Contamination will be let to External Drains.

2.12 Will the deployment of construction laborers particularly in the peak period

Sewage generated from the construction workers camp will be

Page 23: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

21

lead to unsanitary conditions around the project site (Justify with proper explanation)

treated in package STP.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage?

(Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal)

Sewage Treatment Plant is proposed for treatment of domestic sewage from the project and the quantity of wastewater, design details with unit capacity and technology adopted with disposal options is appended as Annexure – C.

2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use.

Dual piping system is proposed to reduce the fresh water consumption.Dual piping system drawing is appended as Annexure – O.

3. VEGETATION

3.1 Is there any threat of the project to the biodiversity?

(Give a description of the local ecosystem with it’s unique features, if any)

No

3.2 Will the construction involve extensive clearing or modification of vegetation?

(Provide a detailed account of the trees & vegetation affected by the project)

About 200 native indigenous species are planted at site. The project site has 308 existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70 Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50 Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features

(Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)

An area of about 16,014.69 sq m is left for development of landscape. The Ground Coverage area is about 8010.71 sq m The Paved area is 23,862.75 sq m The Land use pattern scheme of the proposed project is detailed in the Comprehensive Project report appended as Annexure – A

Drawing showing the details of Landscaping and other features is appended as Annexure – O

Page 24: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

22

4. FAUNA

4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.

No

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

No

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna

No

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)

DG sets are the only air pollution source of the project. The DG sets will be provided with adequate stack height to disperse the emissions into the atmosphere.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

NA

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

Adequate parking facilities are proposed to be provided as per the local building by law.

The parking plan showing the entry & exit to the project site with traffic management is enclosed as Annexure - O.

Traffic management study and measures is appended as Annexure – M.

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

Site plan with roads, pedestrian pathways and paved areas of the project is enclosed as Annexure – O

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.

Details of noise mitigation measure proposed is appended as Annexure – G

Page 25: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

23

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

The DG sets will be provided with acoustic enclosures to reduce the noise level < 55 dB

6. AESTHETICS:

7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details.

Once the project is completed approximately about 4,875 people are expected in the building.

7.2 Give details of the existing social infrastructure around the proposed project.

Surrounded by Residential apartments and commercial establishments

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?

NA

6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

NA

6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

The surrounding areas of the project have Residential layouts, Apartments and areas with rural settings and surrounded areas like Bileshivalli, Bileshivalli Colony, Kyalasanahalli, Anagalapura, Geddalahalli, Bhairali, Kotnuru, Agra, Kalkere, Kanaknagar, Chansandra.

6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

The local byelaw of Bangalore Development Authority is considered in designing the project.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

No

Page 26: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

24

8. BUILDING MATERIALS

8.1 May involve the use of building materials with high-embodied energy.

Are the construction materials produced with energy efficient processes?

(Give details of energy conservation measures in the selection of building materials and their energy efficiency)

The proposed project construction materials are selected to conform the building energy efficiency norms and as well as Energy Conservation Building Code Guidelines

The following measures are taken to for conserving the energy

1. Solar powered street lighting for common areas.

2. CFL bulbs, lights and fixtures for common areas

3. Proper sizing of cables with less voltage drop so that losses in cables can be minimized

4. Optimal pumping of water using water level controllers, switching on/off of street lights with photo cell /time switch.

5. Procuring graded electrical appliances which helps in high energy conservations.

6. Timer control for external lighting

7. LED type street lighting fixtures instead of high power sodium vapor light fixture.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Details appended as Annexure – G

8.3 Are recycled materials used in roads and structures?

State the extent of savings achieved?

The construction waste and debris (400 cum) from the project will be used in road and pavement formation

8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of

The solid Wastes generated are segregated at its point of generation, collected and stored

Page 27: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

25

the project. at a common designated place and Organic solid waste will be treated in an organic converter and product will be used as manure for Landscape or used as fuel. The inorganic solid waste is proposed to be recycled.

The details of quantity of solid waste generated is appended as

Annexure – F

9. ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc.

What is the energy consumption assumed per square foot of built-up area?

How have you tried to minimize energy consumption

The power required for the project is about 5145 kVA and will supply from BESCOM.

Yes, Energy conservation methods are adopted. Non Conventional Sources of Energy with Solar Street Lighting and Solar Hot Water Generation.

Terrace floor plan showing the location of solar panels and tanks is appended as Annexure – O.

9.2 What type of, and capacity of, power back-up to you plan to provide?

The proposed project will be provide with 1 X 250 kVA and 3 X 500 kVA capacity DG sets to serve as alternative source of power supply in case of break down of power from BESCOM. Occupancy phase: Low Sulphur content Diesel consumption of 50 and 100 L/hr for each DG set.

9.3 What are the characteristics of the glass you plan to use?

Provide specifications of its characteristics related to both short wave and long wave radiation?

Low emission and low solar heat gain Single glazed with aluminum frame are proposed to be used for windows etc.,

U = 5.7 W/m2 0C < 6.922W/m2 0C

SHGC = 0.4

Page 28: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

26

9.4 What passive solar architectural features are being used in the building?

Illustrate the applications made in the proposed project.

Passive solar architectural features are considered while designing the buildings in respect of orientation of building thermal insulation aspects for wall with fenestration & roof is considered as per ECBC 2007 Guidelines viz., Balconies, Projections, Recessed window etc.,

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

Yes

Solar hot water facilities and Solar panels for Street lighting are proposed to be adopted.

Terrace floor plan with solar panel nos. capacity details is appended as Annexure – O.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

As per ECBC Guidelines the thermal transmittance (U) value = 0.409 W/m2-0C for roofs

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details.

Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions?

Are you using CFC and HCFC free chillers? Provide specifications.

Yes, Passive solar architectural features are considered while designing the project in respect of orientation of building with natural light and ventilation

The Low loss energy efficient transformers, CFL’s, Ballasts, variable frequency drives for motors for low power consumption are proposed.

Variable frequency drive is used for motor and pumps in order to reduce the energy consumption.

9.8 What are the likely effects of the building activity in altering the micro-climates?

Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

None

Page 29: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

27

9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration?

Give details of the material used and the U-values or the R values of the individual components.

For Roof

U – 0.34 W/m2-0C < 0.409 W/m2-0C

For Walls:

U-Value = 0.42 W/m2 0C < 0.431 W /m2 0C

For Vertical Fenestration

U-Value = 5.7 W /m2 0C < 6.922 W/m2 0C and Max. SHGC : 0.40

9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.

The building is designed in compliance with fire and safety norms and the NOC is obtained from Fire Fighting Department. Static Fire water tank as per the regulations is proposed, Wet risers and sprinklers provided as per the Fire Fighting Norms.

9.11 If you are using glass as wall material provides details and specifications including emissive and thermal characteristics.

Low E glasses are considered and as per the details furnished above.

9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.

NA

9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption?

Provide details of the renewable energy technologies used.

Solar hot water facilities and Solar Street lighting system are proposed.

Page 30: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

28

10. Environment Management Plan:

10.1 The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

Wet risers/down riser, fire alarm system, automatic sprinklers system, and portable fire extinguishers are proposed in case of fire accidents.

Details of mitigation measures to minimize adverse environmental impacts during construction and operation phase of the project is appended in Environmental Monitoring plan is enclosed as Annexure – G.

“I hereby give undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the Project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. Date: 13.10.2015 Place: Bangalore

SANTOSH LUNKAD,

Deputy General Manager, #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar Bangalore – 560038

Signature of the applicant

With Name and Full address (Project Proponent / Authorized Signatory)

Page 31: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

30 PROJECT REPORT

Annexure & Details to Application in

Form 1 and Form 1A

Page 32: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

31 PROJECT REPORT

ANNEXURE – A

COMPREHENSIVE PROJECT REPORT

PROJECT AT GLANCE

PROPOSED PROJECT Residential Apartment Project with 975 Flats

LOCATION Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5, 48/6

and 49/2, Kyalasanahalli Village, K R Puram Hobli,

Bangalore East, Bangalore.

TOTAL PLOT AREA 53,494.64 sq m (13.21 Acres)

TOTAL BUILT UP AREA 1,49,471 sq m

TOTAL COST OF PROJECT Rs. 313,00,00,000/-

(Rupees Three Hundred and thirteen Crores Only)

NO. OF FLOORS PROPOSED The proposed Residential Apartment Project

consists of 5 blocks with 2 Basement, Ground and

14 Upper Floors.

CAR PARKING DETAILS Total No. of parking space proposed is 1,090 Cars

WATER SUPPLY The water supply is from BWSSB source.

PROPOSED SANITATION Under Ground Sanitary System Facility for

conveying the wastewater to the Proposed

Sewage Treatment Plant.

SOLID WASTE MANAGEMENT Collection and Segregation at source of

generation and the Organic waste will be treated

in Organic Converter and the Inorganic Waste will

be sent for recycling.

AIR POLLUTION/ NOISE

GENERATION SOURCE

1 x 250 kVA & 3 x 500 kVA capacity DG sets with

acoustics are proposed to be provided with

adequate stack height.

Page 33: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

32 PROJECT REPORT

BACKGROUND OF THE PROPOSED APARTMENT PROJECT:

M/s. Rohan Builders #1201, 1st floor, Divyashakti, 100 feet road, Indiranagar

Bangalore – 560038 intend to establish Residential Apartment project with 975

flats at Survey Nos. 48/1, 48/3, 48/4A, 48/4B, 48/5, 48/6 and 49/2,

Kyalasanahalli Village, K R Puram Hobli, Bangalore East, Bangalore.

LAND USE PATTERN FOR THE PROPOSED PROJECT:

Sl. No

Particulars Area Percentage

Sq.mt Acres (%)

1 Total Plot area 53,494.64 13.21 NA

2 Civic Amenities including kharab land

4060.65 1.00 NA

3 Net Plot Area 49,433.99 12.21 100

4 Ground Coverage area 8,010.71 2 16.20

5 Paved area 23,862.75 4.84 48.27

7

Landscape area

a) On natural earth 16,014.69 3.95 32.39

b) On Podium 1,545.84 0.38 -

Page 34: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

33 PROJECT REPORT

AREA STATEMENT FOR THE PROPOSED PROJECT:

SL.NO FLOORS BUILT-UP AREA IN SQ M (blocks

1 -5) ACTIVITIES

1 Upper Basement 25121.71 PARKING

2 Lower Basement 16655.45 PARKING

3 Ground floor 6763.82 63 Flats

4 Ist floor 6759.41 63 Flats

5 2nd floor 7377.83 70 Flats

6 3rd floor 7401.55 70 Flats

7 4th floor 7574.72 70 Flats

8 5th floor 7495.08 70 Flats

9 6th floor 7657.30 65 Flats

10 7th floor 7085.05 65 Flats

11 8th floor 7567.18 70 Flats

12 9th floor 7428.30 70 Flats

13 10th floor 7392.59 70 Flats

14 11th floor 7544.32 70 Flats

15 12th floor 7762.08 70 Flats

16 13th floor 6548.55 58 Flats

17 14th floor 3463.03 31 Flats

18 Clubhouse 1873.05 -

Total area 1,49,471.01 975

CAR PARKING STATEMENT:

SL.NO FLOORS CARS

1 Upper Basement 631

2 Lower Basement 409

3 Surface parking 50

Total parking spaces 1,090

Page 35: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

34 PROJECT REPORT

AIR POLLUTION SOURCES & ITS MANAGEMENT: The anticipated power required for the project (about 5,145 kVA) will be

supplied from BESCOM. The primary sources of air pollution from the

establishment are from the operation of diesel generator sets. The project will

be provided with DG set of following capacity and is installed to serve as an

alternative back up source of power supply in the event of breakdown of power

supply BESCOM. The details of capacities & fuel consumption for the DG sets are

given below.

Air Pollution Sources for the Proposed Project:

Sl.

No

Stack Details Stack Attached to

Physical Details D.G Set

1 Capacity 1 X 250 kVA & 3 x 500 kVA DG sets

capacity.

2 Fuel quantity 50 & 100 L/hr Respectively

3 Fuel used Ultra Pure Low Sulphur Content Diesel

4 Stack height Chimneys (Above roof level) of 3 m and

5 m for each DG set.

5 Stack diameter 80 mm

Emission Details

1 Sulphur dioxide 0.0166g/s & 0.0333 g/s for each DG sets

respectively.

2 Suspended Particulate

Matter (SPM)

0.0166g/s & 0.0333 g/s for each DG sets

respectively.

3 Oxides of Nitrogen 0.5111g/s & 1.022 g/s for each DG sets

respectively.

Page 36: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

35 PROJECT REPORT

NOISE GENERATION SOURCES:

Major noise producing sources of the residential apartment is expected to be

from DG set, Vehicular movements from and to the proposed project. The DG

sets are provided with acoustic enclosures to control the noise levels in such a

way that the noise levels are within the permissible limits specified for ambient

noise levels. More over the DG sets are operated only during the emergencies

when there is power failure.

PROJECTED COST OF THE PROJECT:

The total projected cost of the proposed project is presented as below.

Sl.

No.

Particulars Cost in Rupees.

1. Land Cost Rs. 87,06,00,000/-

2. Construction Cost @ rate of

Rs. 1,400/Sft of built up area

Rs. 2,25,16,31,295/-

TOTAL

Rs. 3,12,22,31,295/-

Or say

Rs. 3,13,00,00,000/-

Rupees Three Hundred and thirteen Crores Only

Page 37: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

36 PROJECT REPORT

ANNEXURE: B

SOURCE OF WATER FOR THE PROPOSED PROJECT:

The most important aspect under the water supply scheme is the selection of

source of Water, which should be reliable and potable. The water required for

the project will be drawn from BWSSB source.

DETAILS OF WATER CONSUMPTION OF THE PROJECT: The apartment being a residential one, water demand is for domestic purpose,

public uses and fire fighting purposes. It includes the quantity of water required

in the houses for drinking, bathing, cooking, washing etc., The quantity of water

required for domestic purposes depends on the habits, social status, climatic

conditions and customs of the people. In India on an average the domestic water

consumption under normal conditions is about 135 litres/capita/day as per NBC,

the details of domestic consumption is as follows.

Sl. No.

Utility Consumption in Litres per Capita per day

1 Drinking 5

2 Bathing 40

3 Cooking 5

4 Washing of clothes 20

5 Utensils washing 10

6 Washing of floor 10

7 Flushing of Toilets 45

Total 135

The anticipated water demand is worked out by taking into consideration that

the project is fully developed and the residents have fully occupied their

respective flats.

Page 38: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

37 PROJECT REPORT

WATER CONSUMPTION OF THE PROPOSED PROJECT:

No. Water requirement

1 No. of units 975

Total contributing population considering 5

person per flats

975 X 5 = 4,875

2 Total number of occupants in the project 4,875 persons

3 Water requirement for the Residential

Apartment by considering water demand of

135 LPCD

4,875 X 135 =

6,58,125 Litres/day or

say 659 KLD ----A

4 Considering 10% extra for club house 4,875 x 0.10 = 488 488 x 45 =21,960L/day Or say 22 KLD ---- B

TOTAL WATER REQUIRED FOR PROPOSED PROJECT(A+B) = 659 +22

= 681 KLD

WATER DISTRIBUTION SYSTEM:

The proposed water supply scheme to cater to the public and domestic water

requirement of the proposed project consists of sourcing pre-treated potable

water from Public supply into a common collection facility known as the Raw

Water Sump. The Raw Water Sump will be constructed in RCC. The water from

the UG sump will be pumped to overhead tank. The OHTs are staged on terrace

depending on the contour of its distribution network.

Page 39: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

38 PROJECT REPORT

ANNEXURE: C

1. SEWAGE GENERATION AND DISPOSAL SYSTEM:

Wastes of different type such as spent water from bath rooms, water

closets/pans, house and street washings, semi liquid waste of human excreta,

dry refuse of house and street sweepings, broken furniture, crockery etc., are

produced daily. If proper arrangement for collection treatment and disposal of

all the wastes produced are not made, unsanitary conditions will develop and it

will become impossible for the public to live. Therefore, it is most essential to

collect, treat and dispose all the sanitary waste produced. Generally, it has been

observed that about 80 % of the water supplied comes out as sewage. Therefore,

the total quantity of wastewater generated from the proposed Residential

Apartment Project is worked out as below.

Water required for the project = 681 KLD

Wastewater generation : 681 X 0.80 = 544.8 or say 545 KLD

(Assuming 80 % of the water

Supplied comes out as wastewater)

Domestic wastewater generated from the proposed project will be conveyed to

Sewage Treatment Plant of capacity 600 KLD for treatment and disposal.

TREATED SEWAGE DISPOSAL:

a. Toilet Flushing:

Total contribution population from the proposed project is 4,875 Persons.

Toilet flushing water requirement at the rate of 45 LPCD

= 4,875 X 45 = 219,375 L/day or say 220 KLD ----A

Page 40: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

39 PROJECT REPORT

b. Gardening water requirement:

Total area available for landscape development on natural earth and podium

within the project = 17,092.46 sq m

Treated water used for gardening @ rate of 7 L/sq m/day for landscape on

natural earth and podium landscape are = 17,560.53 X 7

= 1,22,923.71 L/day or say 125 KLD

Total water reused for landscape development: 125 KLD

c. Excess quantity of 200 KLD will be given to construction projects, used for

water avenue plantations.

Page 41: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

40 PROJECT REPORT

TECHNICAL PROPOSAL FOR SEWAGE TREATMENT PLANT (STP)

I GENERAL DETAILS

Total Occupancy 4875

Water required for the project 681 KLD

Sewage generated 545 KLD for which STP designed for 600 KLD.

II DESIGN OF BAR SCREEN CHAMBER

A Design flow rate 600 cum/day

B Assume working period of 12 to 14 hrs/day,

C Average flow rate/hr 42.872143 cum/h

D Peak factor 5.00

E Peak flow 214.36071 cum/h

F Desired vel 0.8 m/s

G Net screen area = (e / (f * 3600)) 0.074 sqm

H Adopting screen with flats of 5mm tk & 8 mm openings,

Gross area of the screen 0.121 sqm

I Inclination of screen to horizontal is 60°,

Gross area of the screen = h/sin60° 0.140 sqm

J Hence size of screen 0.37 x 0.37 mtr

Hence provide a smallest bar screen of size 500.00 X 1000 mm

III DESIGN OF EQUALISATION TANK

A Design flow rate 600 cum/day

B Retention time 6.00 hrs

C Vol of tank = (a/24)*b 150.00 cum

D Assume depth of tank 2.00 m

E Size of tank 8.66 x 8.66 x 2.00

Page 42: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

41 PROJECT REPORT

IV DESIGN OF EFFLUENT TRANSFER PUMP (1W+1S)

A Design flow rate 600 cum/day

B Working period 20.00 hrs/day

C Average flow 30.00 cum/h

D Total head required 12.00 mtr

E Hence provide 2 nos (1W + 1S), Horizontal submersible non

Clog pump of capacity 30.00 cum/hr 12.00 M head

V DESIGN OF AERATION TANK

A Design flow rate 600 cum/day

B BOD IN = 200 - 300 mg/lit

C BOD OUT = 20 - 30 mg/lit

D BOD removal efficiency =95%

E F/M = ratio for < 20 mg/sqm of BOD (i.e. 0.12 to 0.13)

F MLSS = 3000 to 3500

G Vol of Tank = (Q x BOD IN)/ (F/M) x MLSS 500.18 cum

H Size of tank 14.20 X 14.20 X 2.50

VI DESIGN OF AIR BLOWERS

A Design flow rate 600 cum/day

B Working period 20.00 h/day

C Average flow 30.00 cum/hr @ 400 mg/lit BOD

D Total BOD = 12.00 Kg/hr

A Quantity of air required for Aeration tank:

For extended aeration system,

Oxygen qty reqd = 1.8 Kg of O2/ Kg of BOD removed 21.6 Kg of O2/hr

Density of air 1.2

% age of O2 in air by wt. 0.232

Page 43: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

42 PROJECT REPORT

Alpha 0.65

Beta 0.95

O2 transfer efficiency at the respective aeration tank depth 0.2

Air required = O2 required

(Density of air x % of O2 in air by wt. x Alpha x Beta x O2 transfer efficiency

at the respective aeration tank depth)

= 628.23 cum/h

For mixing we need approx. 0.75 cum of air/ hr/ cum of tank volume

B for Equilisation tank,

Vol of air required = 112.50 cum/h

C for Semi Treated effluent collection sump,

Vol of air required = 84.38 cum/h

Total Volume of air required (1 + 2 + 3) = 825.10 cum/h

Add 10 % extra for losses 82.51 cum/h

Hence provide (1W + 1S) air blower of capacity 907.61 cum/hr @ 0.5 ksc

VII DESIGN OF SETTLING TANK

A Design flow rate 600 cum/day

B Working period 20.00 h/day

C Average flow rate 30.00 cum/h

D Recommended flow rate = 0.6 to 0.75 cum/sqm/hr

E Area required = 50.00 sqm

F Size of tank 7.07 x 7.07 m

G Recommended HRT for settling tank is between 2 to 2.5 hrs

Volume of tank = area reqd x HRT 125.00 cum

H With size of tank as above,

Depth of tank = 2.50 mtr

I Therefore size of tank is 7.07 x 7.07 x 2.50

Note: Depth of tank not to be greater than 2.5m.

Page 44: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

43 PROJECT REPORT

VIII DESIGN OF SEMI-TREATED & TREATED EFFLUENT COLLECTION SUMP

A Design flow rate 600 cum/day

B Flow rate to sump = design flow rate x 0.9 = 540.189 cum/day

SWD + FB = 0.3m

Last modified: 28/10/2015 Page 2 of 5 PSI Consulting

C Providing 10 hrs storage,

Capacity of sump = 225.00 cum

D Capacity of semi treated effluent sump 112.5 cum

With a depth of 2.5m,

E Size of semi treated effluent tank = 7.00 x 7.00 x 2.50

F Size of treated effluent tank = 7.00 x 7.00 x 2.50

IX DESIGN OF SEMI TREATED EFFLUENT TRANSFER PUMP

A Design flow rate 600 cum/day

B Working period 20.00 h/day

C Average flow rate 30.00 cum/h

D Head loss through PSF 1.00 kg/cm2

E Head loss through ACF 1.00 kg/cm2

F Head loss through pipes 0.30 kg/cm2

G Therefore the total head required is,

Suction head 3.00 m

+ Head loss through PSF, ACF & pipes 23.00 m

+ Residual head 3.50 m

H Total = 30.00 m

I Therefore pump required is (1W + 1S) 30.00 cum/hr 30 m head

Page 45: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

44 PROJECT REPORT

X DESIGN OF ACF/PSF

A Design flow rate 540.189 cum/day

B Working period 16.00 h/day

C Average flow rate 33.76 cum/hr

D Velocity of flow 1.50 m/s

E Considering backwash @ 50% of Avg. flow,

F Total Flow = 16.88 cum/hr

G C/s area of PSF/ ACF = 1.33 sqm

H Therefore Dia of PSF/ACF = 1.30 m

XI DESIGN OF DIFFUSER MEMBRANE QUANTIY

COARSE BUBBLE DIFFUSERS

1 For Equalisation Tank

A Size of tank SWD 8.66 x 8.66 x 2.00

B Max. Horizontal spacing of diffusers is 1.3 to 1.47m

C Max. Vertical spacing of diffusers is 2.6m

D No. of columns of diffusers 7.00 Nos.

E Actual spacing of diffusers 1.24 within the range 1.3 to 1.47 hence OK.

F No. of rows of diffusers 3.00 Nos.

G Actual spacing of diffusers 2.89 which is < 2.6 m. Hence OK.

H Total No. of coarse bubble diffusers 21.00 Nos.

I Air flux rate ( AFR ) = capacity of EQ. Tank/ No. of diffusers

= 7.14 m3/no/hr < 40 m3/no/hr. Hence OK.

FINE PORE DIFFUSERS

A Max. Horizontal spacing of diffusers < 1.5m -- (d)

B Max. Vertical spacing of diffusers is (2.5 - 3.0) x d

1.3 to 1.47

Max 1000

Max 2600

Page 46: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

45 PROJECT REPORT

Last modified:28/10/2015 Page 3 of 5 PSI Consulting

1 For Aeration Tank

A Size of Tank SWD 14.20 x 14.20 x 2.50

B No. of columns of diffusers 9.00 Nos.

C Actual spacing of diffusers 1.58 which is < 1.5 m. Hence OK.

D Proposed horizontal spacing of diffusers = 2.5 x 1.5 = 3.75 m

E No. of rows of diffusers 4.00 Nos.

F Actual spacing of diffusers 3.55 m which is < 3.75m. Hence OK.

G Total No. of coarse bubble diffusers 72.00 Nos.

H Air flux rate (AFR ) = capacity of AE. Tank/ No. of diffusers

= 6.95 m3/m/hr which is < 14 m3/m/hr.Hence OK.

I Ratio = AT/ AD

= Area of Aeration Tank/ Eff. Area of diffusers

Where Eff area of diffusers = No. of diffusers x const (0.236)

= 11.87 which is with the range 5 to 20.

Hence OK.

2 For Semi Treated Effluent Sump

A Size of Tank SWD 7.0 x 7.00 x 2.50

B No. of columns of diffusers 5 Nos.

C Actual spacing of diffusers 1.4 which is < 1.5 m. Hence OK.

D Proposed horizontal spacing of diffusers = 2.5 x 1.5 = 3.75 m

E No. of rows of diffusers 2.00 Nos.

F Actual spacing of diffusers 3.50 m which is < 3.75m. Hence OK.

G Total No. of coarse bubble diffusers 20.00 Nos.

H Air flux rate (AFR ) = capacity of STES. Tank/ No. of diffusers

= 5.625 m3/m/hr which is < 14 m3/m/hr.Hence OK.

I Therefore,

Total No. of Coarse Bubble diffusers 23.00 Nos.

Total No. of Fine pore diffusers 101.00 Nos.

Page 47: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

46 PROJECT REPORT

XII DESIGN OF FILTER PRESS

A Design flow rate 600 cum/day

B Daily BOD = Design flow rate x 0.4 240.084 kg/day

C In extended aeration activated sludge plant, the %age of waste

Activated sludge = 0.2 -0.3 times the daily BOD

D Therefore Waste activated sludge = 55.2 kg/day on Dry wt. Basis

E %age of moisture reduction possible in a good filter press = 15%

F Therefore wet cake capacity = 368.13 lit

G No. of batches/ day = 2.00

H Wet cake / batch = 184.06 lit

I Therefore provide filter press with Hydraulic closing device &

motorised pack with a wet cake holding capacity of 92.03 Lit » 100 Lit ---2 no.

XIII DESIGN OF SLUDGE DRYING BEDS

A Excess sludge to be wasted/day = ( V x X )/( Oc x Xr )

B V = Vol of aeration tank = 500.18 cum

C X = MLVSS = 3500 mg/lit

D Oc = Sludge age = 25.00 days

E Xr = MLVSS in recirculation line = 8000.00

= 8.75 m3/day @ 0.8% concentration

F Desired depth of sludge in SDB = 0.3 to 0.4m

G Area of bed = 29.2 sqm

H Hence size of bed = 5.40 x 5.40

I since it takes 5-6 days for complete dewatering & drying of the

Sludge, provide = 175.06125 sqm

J Sludge holding tank = 3.00 nos.

K Hence provide Sludge holding tank = 5.40 x 5.40 m --- 3.00

Page 48: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

47 PROJECT REPORT

XIV DESIGN OF CHLORINE DOZING SYSTEM

Quantity of chlorine reqd = 10.00 mg/lit = 10 gms/cum

Last modified:28/10/2015 Page 4 of 5 PSI Consulting

Design flow rate = 600.21 cum/day

= 6002.1 gms/cum @100% solution

= 6.0021 kg/cum @100% solution

But available concentration of solution = 10%.

Therefore quantity of chlorine reqd/day @ 10% conc = 60.021 lit/day

Assuming that the dozing is reqd in 8hrs/day, capacity of

Chlorine dozing pump required = 8 lit/h @ 0.5 ksc

Therefore provide Chemical Dozing pump of capacity = 2.67 lit/h @ 0.5 ksc ---- 3

nos.

XV DESIGN OF SLUDGE TRANSFER PUMP (1W + 1S)

1 For Sludge Drying Beds

A Design flow rate 600.21 cum/day

B Working period 20.00 hrs/day

C Average flow rate 30.00 cum/h

D Therefore the pump required is(avg. flow rate x 20%) 6.00 cum/h 10 m head

2 For Filter Press

A Design flow rate 600.21 cum/day

B Working period 20.00 h/day

C Average flow rate 30.00 cum/h

D Min. inlet pressure required at the Filter press = 5 kg/cm2

E Therefore the pump required is = 3.00 cum/h 60 m head

Page 49: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

48 PROJECT REPORT

ABSTRACT:

I DESIGN FLOW RATE 600 cum/day

II BAR SCREEN CHAMBER 500 X 1000 mm

III EQUILISATION TANK 8.66 X 8.66 X 2.00

IV EFFLUENT TRANSFER PUMP (1W+1S) 30.00 cum/h 12.00 m head

V AERATION TANK 14.20 X 14.20 X 2.50

VI AIR BLOWERS (1W+1S ) 907.61 cum/h

VII SETTLING TANK 7.07 X 7.07 X 2.50

VIII A. SEMI TREATED EFFLUENT COLLECTION SUMP 7.00 X 7.00 X 2.50

IX SEMI TREATED EFFLUENT TRANSFER PUMP (1W+1S) 30.00 cum/h 30 m

head

X A. PSF - 1No AND ACF 1No flow rare cum/h 1.30 34.00

B. ACF - 1 no. flow rate cum/h 1.30 34.00

XI A. COARSE BUBBLE DIFFUSERS 23.00 nos

B. FINE PORE DIFFUSERS 101.00 nos

XII FILTER PRESS 100.00 0 nos

XIII SLUDGE HOLDING TANKS 5.40 X 5.40 m --- 3.00

XIV CHLORINE DOZING SYSTEM 2.67 lit/h @ 0.5 ksc ---- 3 nos.

XV SLUDGE TRANSFER PUMP (1W+1S)

A. FOR SLUDGE DRYING BEDS 6.00 cum/h 10.00 m head

B. FOR FILTER PRESS 3.00 cum/h 60.00 m head

Page 50: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

49 PROJECT REPORT

TREATMENT FLOW CHART FOR 600 KLD CAPACITY

Raw Sewage

Recycle Pumps Sludge

Excess Sludge

Pressure Sand Filter

Activated Carbon Filter Sludge for disposal Chlorine doser

Reuse for flushing, landscaping etc.,

Bar Screen Chamber

Equalization Tank

Aeration Tank

Settling Tank

Final Holding Sump

Mechanical Filter Press

Alum Doser

Sludge

Holding Tank

Page 51: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

50 PROJECT REPORT

ANNEXURE: D

WATER BALANCE CHART

Recycle for Toilet Flushing Wastewater generated 545 KLD

Daily water Requirement

461 KLD

Total Raw Water demand (Start Up)

681 KLD

Toilet Flushing 220 KLD

STP Designed for 600 KLD

Landscape Development

125 KLD

Excess quantity of 200 KLD will be discharged to UGD facilities / used

for Watering Avenue Plantation.

Page 52: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

51 PROJECT REPORT

ANNEXURE: E

WATER REQUIREMENT & SEWAGE DISPOSAL DURING CONSTRUCTION PHASE

Domestic water requirements during construction phase.

Total number of manpower required : 500

Water requirements @ of 100 LPCD : 500 x 100 = 50,000 L/day

Total domestic water requirements : 50 KLD

Wastewater discharge (Considering 80% of water consumed comes out as

wastewater)

= 50,000 X 0.80 = 40,000 L/day or say 40 KLD

The wastewater generated will be treated in Package Sewage Treatment Plant of

50 KLD Capacity.

Page 53: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

52 PROJECT REPORT

ANNEXURE: F

SOLID WASTE GENERATION & ITS MANAGEMENT - CONSTRUCTION PHASE:

The total manpower : 500

Considering solid waste generation @ 0.25 kg/capita/day

Total solid waste generation : 500 x 0.25 = 125 Kgs/day

The domestic wastes will be disposed through BBMP.

OCCUPANCY PHASE:

The wastes that are generated from the day to day activities which are in solid

form are categorized as solid wastes. Solid Wastes include dry refuse of house

and street sweepings, crockery, Kitchen Wastes, and also electronic wastes. The

quantity of solid waste generated from the proposed project is calculated as

follows.

Total Contributing population from the Apartment 4,875 Persons

Assuming solid waste generation rate as 0.4 kg/person/day for Residential

Apartment

Quantity of solid waste generated from the project 1,950 Kgs/day

Organic solid waste: 60 % of the total waste 1,170 kgs/day

Inorganic solid waste: 40 % of the total waste 780 kgs/day

The solid Wastes generated will be segregated at its point of generation and

collected separately in different color coded Synthetic Bins depending upon the

basis of its Bio Degradability at a common designated point. Organic solid waste

from the project will be treated in an organic converter and is used as manure

for Landscape or used as fuel. The inorganic solid waste is proposed to be

recycled.

Page 54: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

53 PROJECT REPORT

Page 55: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

54 PROJECT REPORT

The compost formed by this method will have a pH value of 6.5 – 7.5 C: N ratio

of 15:1 and organic matter of 40 – 50%. There will not be any pathogens and the

pellets manufactured will have a calorific value of 3500 to 4000 Kcal/Kg.

Page 56: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

55 PROJECT REPORT

SECONDARY SLUDGE FROM STPs: The solid waste generated from the STP’s of secondary settling is in the form of

stabilized secondary sludge. Then is passed through the Plate & Frame filter

press, the solids obtained as semi solid cakes are used as organic manure for the

development of plantations within the premises. The quantity of secondary

sludge from the secondary settling units of the treatment

* Rate: 600 m3/day and Sludge - 216 Kgs/Day

HAZARDOUS WASTE:

The Hazardous waste generated from the project is waste oil of about 200 – 300

Litres/annum which will be stored in closed barrels and disposed to KSPCB

approved and CPCB register waste oil re-processors. Authorization will be

obtained from KSPCB as per Hazardous waste (Management & Handling)

Amendment Rules, 2008.

BIO MEDICAL WASTE:

The Bio Medical Waste generated from the project will be collected and

segregated at source based on their categorization as per the Biomedical Waste

(Management and Handling) Rules in containers and will be disposed as per the

guidelines. Common designated place will be earmarked for the storage of bio

medical waste and will be disposed scientifically.

e - WASTE:

The Electronic Waste (e-waste) such as CD’s, Pendrives, computer and its

components, used batteries, etc., from the project will be segregated, collected

and stored at a designated place and will be handed over to authorized

recyclers.

Page 57: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

56 PROJECT REPORT

ANNEXURE – G

ENVIRONMENTAL MANAGEMENT PLAN:

1. INTRODUCTION:

The Environmental Management Plan (EMP) is aimed at mitigating the possible

adverse impact of a project and ensuring the existing environmental quality. The

EMP converse all aspects of planning, construction and operation of the project

relevant to environment. It is essential to implement the EMP right from the

planning stage continuing throughout the construction and operation stage.

Therefore the main purpose of the Environmental Management Plan (EMP) is to

identify the project specific activities that would have to be considered for the

significant adverse impacts and the mitigation measures required.

The construction phase impacts are mostly short term, restricted to the

plot area and not envisaged on the larger scale. In the operational phase the

environmental impacts are due to continuous operation of the project, hence,

the emphasis in the Environment Management Plan (EMP) is to minimize such

impacts. The following mitigation measures are recommended in order to

synchronize the economic development of the project area with the

environmental protection of the region.

The emphasis on the EMP development is on the following;

Mitigation measures for each of the activities causing the environmental

Impact.

Monitoring plans for checking activities and environmental parameters and

monitoring responsibilities.

Role responsibilities and resource allocation for monitoring; and

Implementation of the Scheduled plan.

Page 58: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

57 PROJECT REPORT

2. EMP DURING CONSTRUCTION PHASE:

During Construction phase, the activities which need to be monitored and

managed from the point of pollution are detailed in the subsequent sections.

2.1 LEVELLING AND SITE CLEARANCE:

The proposed project is residential apartment project having basement floor and

earth excavation is necessary. The layout is planned keeping the natural ground

profile in consideration with buildings at different levels so that minimum

excavation would be required. The total quantity of excavated soil is about

50,000 cum. About 15,000 cum will be used for landscape development, about

16,000 cum will be used for backfilling and 19,000 cum will be used for

formation and hardscaping activities within the project site.

Environmental Management Plan during Leveling and Site Clearance:

Environmental

Impacts

Mitigation Proposed Remarks

Noise generation:

Caused due to

Excavators and

Bulldozers

Most optimum no. of

operation by the heavy equipment

Selection of equipment with

less noise generation.

The earth moving equipment

shall be periodically checked

and maintained for noise levels.

The workers will be provided

with PPE such as ear plugs

To reduce noise

level, Equipment

provided with

noise control

devices is only

used.

Dust generation:

Leveling operations

results in the

The site cleared will be

periodically watered to reduce

dust emissions

Tertiary treated

water to be used.

Page 59: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

58 PROJECT REPORT

emission of dust. Barricades like metal sheets

will be provided all round the

premises to avoid fugitive dust

emission in to the neighboring

area apart from water

sprinkling.

The workers will be provided

with PPE such as nose masks

and goggles to reduce impact.

2.2 TRANSPORTATION OF CONSTRUCTION MATERIALS:

During the Transportation of construction materials, minimum no. of vehicles

will be used. Most optimum route is planned to reduce the impact of

transportation activity on the environment.

Environmental Management during Transportation

Environmental Impacts Mitigation Proposed

Noise generation

Quality fuel will be used.

Periodic maintenance of vehicles is required.

Dust generation

Quality packaging of the construction materials

Construction materials will be covered with tarpaulin

sheet to prevent from being air borne

The vehicle speed shall be regulated

The workers transporting materials will be provided

with PPE such as nose masks to reduce impact of air

borne dust on their health

Vehicular emissions Periodic emission check for vehicles will be done

Clean fuel will be used for vehicles

Page 60: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

59 PROJECT REPORT

2.3 CONSTRUCTION ACTIVITIES:

During the construction work, the following impacts are identified to monitor

and mitigate the level of impact.

Environmental Management during Construction

Environmental

Impacts

Mitigation Proposed Remarks

Noise generation

Less noise generating equipment

Personnel Protective Equipment (PPE)

such as ear plugs and helmets will be

provided for workers

The working hours to be imposed on the

construction workers.

Implementation

responsibility:

Contractor - Civil

Works

Dust generation PPE in the form of nose masks will be

provided for construction workers.

Use of water sprays to prevent dust

from being air borne.

Barricades like metal sheets will be

provided all around the premises to

avoid fugitive dust emission into the

neighboring area apart from water

sprinkling.

Implementation

responsibility:

Contractor

Water discharge

(Construction

works)

Sewage generated will be treated in

Package STP.

Implementation

responsibility:

Contractor

Air Emissions from

Construction

machinery

Periodic check and regular

maintenance of construction machinery

for emissions.

Clean fuel are used in equipments

Implementation

responsibility:

Contractor

Page 61: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

60 PROJECT REPORT

2.4 WASTEWATER DISCHARGE:

The sewage generated from the labors during construction is estimated to be

about 50 KLD will be treated in Package STP.

2.4.1 LABOUR CAMPS:

Environmental Management for Labor Camp:

Environmental

Impacts

Mitigation Proposed Remarks

Wastewater

generation

Provision of adequate sanitation

facilities.

Responsibility:

Contractor

Usage of water Water for labor camps will be supplied in

required quantities.

Responsibility:

Contractor

Solid waste

generation

Segregation of Dry Waste and Wet

Waste. Adequate facilities to handle

solid wastes shall be provided and will

be disposed through BBMP.

Implementation

responsibility:

Contractor –

maintenance.

2.5 DISPOSAL OF EXCAVATED EARTH:

The proposed project is residential apartment project having basement floor and

earth excavation is necessary. The total quantity of excavated soil is about

50,000 cum. About 15,000 cum will be used for landscape development, about

16,000 cum will be used for backfilling and 19,000 cum will be used for

formation and hardscaping activities within the project site.

2.6 PERSONNEL SAFETY SYSTEM:

It is planned to adopt the safe working practices which shall govern all

construction works undertaken throughout the project. Following Safety Aids to

all laborers will be provided:

Page 62: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

61 PROJECT REPORT

Safety Helmets, Safety Belts, Safety Shoes, Hand gloves

Gumboots while concreting

Safety Goggles while welding/ Stone dressing etc.

Facemasks and full body kit while Pest control

Implementation of Safety procedures such as:

• Using proper lifting techniques

• Using Safe Scaffolds

• Hot work permits for Fabrication and Welding

FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP

ASPECTS (CONSTRUCTION ASPECTS)

Sl. No.

Description Financial Provision in Lakhs

Capital Cost

Recurring Cost

1 Environmental Management Plan during construction phase: Using tertiary treated water for

• Sprinkling to control fugitive dusts

Construction & curing purposes

Flushing

1.0 1.0 1.0

0.5 0.5 0.5

2 Sewage Treatment Plant for Operation Phase 100 -

3 Potable water requirement for the construction workers 2.0 0.5

4 Maintenance of Vehicles and equipments - 5.0

5 Top Soil Conservation 2.0 -

6 Temporary Storm Water Drains 5.0 1.0

7 Personal protection safety gadgets and health care. 2.0 0.5

8 First aid facilities for workers 2.0 0.5

9 Plantation of Saplings 10.0 -

10 Environmental Monitoring Plan (Air, Noise, Water and Soil).

- 2.0

11

TOTAL 126.00 11

Contingency at 10 % 12.6 1.1

TOTAL 138.6 12.1

Page 63: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

62 PROJECT REPORT

3. EMP DURING OPERATION PHASE:

Following are the identified operational phase activities in the impact

assessment, which may have impact on the environment.

1. Air quality

2. Water quality

3. Noise quality

4. Solid waste disposal

5. Green belt development

6. Storm water Management

3.1 AIR QUALITY MANAGEMENT:

The pollutants envisaged from the proposed project are SPM, SO2, NOx, HC and

CO mainly due to burning of liquid fuel (HSD) in DG sets.

Exhaust from DG set will be emitted from stack of adequate height for

dispersion of gaseous pollutants. The following Table presents the EMP for air

quality management during operation phase.

Air Quality Management during Operation Phase

Environmental Impacts Mitigation Proposed

DG set Equipment selected will ensure the exhaust

emission standard as prescribed as per the

latest amendments from the MoEF.

DG will be used as stand-by unit

Periodic check and maintenance

Ambient air quality Ambient air quality monitoring as per the

prescribed norms at regular interval.

Page 64: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

63 PROJECT REPORT

3.2 WATER QUALITY MANAGEMENT:

Water requirement of project will be augmented through BWSSB sources. Details

of water requirement and Water balance is presented in Annexure B & D

respectively.

The sewage generated from the proposed project will be treated in the

proposed STP. The treatment scheme for domestic sewage generated from

project is discussed in Annexure - C. Treated water will be reused for flushing,

gardening etc., and the following Table presents the EMP for water quality.

Water Quality Management during Operation Phase

Environmental impacts Mitigation Proposed

Wastewater Treated with proposed Sewage Treatment

Plant to produce tertiary treated water which is

reused for secondary purposes such as flushing

landscaping development etc.,

Water conservation measures will be encouraged

3.3 NOISE MANAGEMENT:

High noise generating units such as DG set will be provided with acoustic

enclosures. Green belt on the project boundary will further act as noise barrier

and helps in attenuation of noise. The Table presents the EMP for noise level.

Noise Management during Operation Phase

Environmental Impacts Mitigation Proposed

Noise from DG set area Acoustic enclosures will be provided for DG set

DG set will be installed in an area (utility

section) where the access will be restricted

The use of PPE (ear plugs) will be mandatory in

this area.

Selection of equipment to ensure that the

Page 65: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

64 PROJECT REPORT

residual noise level of <55 dB(A)

Noise levels will be checked periodically using

a noise pressure level meter

3.4 SOLID WASTE MANAGEMENT:

The solid wastes generated during operation phase can be categorized under

Three types: Domestic/Residential Waste

Wet Garbage: Food waste, Lawn mowing wastes etc.

Dry Garbage: Paper, Plastic, Bottles, etc.

Sludge from Sewage Treatment Plant (STP)

The solid waste generated and its management is detailed in Annexure – F.

The various mitigation measures to be adopted during collection and disposal of

wastes are as follows:

It is preferable that the container and bins used for collection of waste

should be of closed type and waste is not exposed thus possibility of

spreading of disease through flies and mosquitoes is minimized.

Collection system should be properly supervised so that quick and regular

removal of waste from the dustbin is practiced.

Door to door collection shall be done in each building to collect the solid

wastes.

3.5 STORM WATER MANAGEMENT:

As the project location is blessed with fairly good rainfall, it is planned to

collect the storm water at different gradients of the location. There will be

rainfall runoff from building roof-tops, roads and pavements and greenbelt area.

Necessary provision will be made to collect the quantity of rainfall runoff during

the most rainy day of season. Necessary rain harvesting pit/recharge pit at every

30 m centre to centre have been envisaged. A storm water drain with 600mm

wide with RCC precast perforated cover and 1800 mm dia RCC precast Ring soak

Page 66: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

65 PROJECT REPORT

pit will be provided around the periphery of property and designed as per

building by-law (schedule 12).

3.6 LANDSCAPE DEVELOPMENT:

Vegetation is the natural extension of the soil ecosystem on a site. It can

provide summer shade, wind protection and a low-maintenance landscape that is

adapted to the local environment. The layout masterplan is planned in such a

way that the maximum natural vegetation can be retained as is without much

disturbance. It will be further enhanced by planting additional trees as proposed

below:

List of plant species proposed:

Sl. No. Scientific name Common name

1 Michelia champaca Champaca

2 Polyalthia fragarans False Ashok, Devdar, Nettilingam

3 Thespesia populnea Indian Tulip tree, Aden Apple

4 Bombax ceiba Cotton tree, Red Cotton tree

5 Pterospermum acerifolium

Kanak Champa, Karnikara tree, Bayur Tree, Maple-Leafed Bayur Tree

6 Aegle marmelos Stone apple, Beli fruit, Wood apple

7 Murraya koenigii Curry leaf, Mahanimba, Curry patta, Nimbapatra

8 Azadirachta indica Margosa tree, Neem

9 Sapindus emarginatus Soapnut tree, Kookatakayi, Soapberry

10 Butea monosperma Parrot tree, Palash, Dhak, Tesu , Bastard Teak

11 Pongamia pinnata Honge, Indian Beech tree

12 Bauhinia malabarica Lilac Bauhinia; Malabar Bauhinia

13 Bauhinia purpurea Devakanchan, Purple Butterfly tree, Purple Orchid tree

14 Cassia fistula Golden shower tree, Indian Laburnum

Page 67: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

M/s. ROHAN BUILDERS

66 PROJECT REPORT

15 Cassia roxburghii Pink Lady, Red Indian Laburnum

16 Saraca asoca Ashoka tree

17 Madhuca indica Butter tree, Hippe

18 Mimusops elengi Sapanish cherry, Bullet-wood tree, Indian Medaller, Bakula

19 Alstonia scholaris Indian devil tree, Pala tree, Dita bark

20 Phyllanthus acidus Star Gooseberry, Malay gooseberry

21 Hibiscus spp Hibiscus

22 Mallotus philippensis Kamala tree, Monkey face tree, Scarlet croton

About 200 native indigenous species are planted at site. The project site has 308

existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70

Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50

Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.

Following approach will be adopted for Vegetation and Ground Management. It is

planned to include an ecologically knowledgeable landscape architect as an

integral member of the design team.

Preservation of existing vegetation, especially native plants, will possibly be

incorporated. Avoid fencing off property where possible to make landscape

available to community increasing project integration.

Decrease paving and monoculture lawns.

Avoid replacing mature trees with young seedlings.

Protect existing plants during construction. Delineate the "drip line"

around trees and demark or fence off areas to avoid damage.

Contain heavy equipment and stockpiling areas to predefined areas.

Design new plantings as diverse communities of species well adapted to

the site. Plant native species of varying ages. Select vegetation that

attracts wildlife.

Avoid invasive species and monocultures (same species, same age).

Page 68: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

67 PROJECT REPORT

4. MANAGEMENT OF SOCIO-ECONOMIC ISSUES:

1) Schools for laborer’s children

Temporary education centers (Creche) will be provided for education of the

children of the laborers.

2) Health camp for laborer’s family

Periodical health camps will be organized to monitor and facilitate the occupants

of the labor camps.

HEALTH RISK AND DISASTER MANAGEMENT:

Public health and safety:

Since all the construction related activities are confined to the project site, minimal

health related impacts are envisaged within the project influenced area during the

construction stage.

At the project site on an average of 300 no. of persons will be engaged, who face

direct exposure to dust and noise generated from the construction activity. This is

likely to cause health related affects such as asthma, bronchitis etc., and hearing

impairments respectively.

To minimize these anticipated impacts, suitable actions like

• Use of water sprinklers to prevent dust from being air borne.

• Providing suitable Personal Protective Equipments (PPE) like mouth mask with

filters, noise mask, helmets etc.,

• Periodic health check up camp for the laborers will be arranged.

• Provision of safety belts.

• In case of injury on site medical treatment and transport will be organized.

Due to operation of the proposed project, there will be enhancement in public Health

and safety.

Regular visit of resident medical officer to take care of the first aid and

primary medication in case of emergency for project occupants and laborers.

Page 69: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

68 PROJECT REPORT

First aid kit with primary medicines will always be available in the medical

centre.

Display of action plan and preparedness measures during emergency situations.

5. EMP IMPLEMENTATION SCHEDULE:

Phased according to the priority, the implementation schedule is presented in the

following table.

Implementation Schedule for EMP

Sl.

No.

Recommendations Requirement

1 Air pollution control measures Before commissioning of respective units

2 Water pollution control measures Before commissioning of the project

3 Noise control measures Along with the commissioning of the

Project

4 Solid waste management During commissioning of the project

5 Green belt development Stage-wise implementation

The responsibility of EMP implementation lies with the project promoter for a period

of 3 years. Once the residents' society is established, the EMP responsibility will be

properly handed over with clearly defined procedures and guidelines.

Page 70: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

69 PROJECT REPORT

FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS

(OCCUPANCY PHASE)

Sl.

No.

Description Financial Provision in Lakhs

Capital

Cost

Recurring

Cost

1 Operation of Sewage Treatment Plant - 5.0

2 Reclaimed Sewage Distribution Network 5.0 1.0

3 Rain water harvesting tanks and its facilities 10.0 2.0

4 Ground water recharging pits & its management 10.0 2.0

5 DG sets acoustic & Maintenance 5.0 1.0

6 Landscaping 10.0 2.0

7 Solid waste management 8.0 1.0

8 Environmental Monitoring Plan per annum (Air,

Noise, Water and Soil)

- 2.0

9 TOTAL 48.0 16.0

Contingency at 10 % 4.8 1.6

TOTAL 52.8 17.6

Page 71: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

70 PROJECT REPORT

6. ENVIRONMENTAL MONITORING ROUTINES:

A comprehensive monitoring program is suggested below:

Monitoring Schedule for Environmental Parameters

Sl. No

Particulars

Monitoring frequency

Duration of monitoring

Important parameters for

monitoring

I Air Quality

1. Ambient Air monitoring

Project premises Once in a month

24 hourly sample

RSPM, SPM, SO2, NOx

2. Stack monitoring

Once in a year if required

Grab SPM, SO2, NOx, HC, CO

II Water and Wastewater Quality

1. Water Quality

i. Groundwater at two locations (up-gradient and down-gradient) of treated effluent discharge area/land

Once in a month

Grab As per KSPCB requirements

2. Wastewater quality

i. Inlet into STP NA NA -

ii. Treated effluent prior to discharge

NA NA -

III Soil Quality

1. Within project premises at 1 location on effluent discharging area/land

Once in 6 month

Composite sample

As per KSPCB requirements

2. Ecological preservation and up gradation

Seasonal Visual observations

Survival rate

IV Noise monitoring

1. Project premises Once in 6 month

Day and night As per KSPCB requirements

Page 72: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

71 PROJECT REPORT

ANNEXURE: H

7.0 RAINWATER MANAGEMENT PLAN:

7.1 RAIN WATER HARVESTING:

The water collected from the terraces of the buildings shall be collected in the

rainwater collection sump and reused for domestic purpose after necessary

treatment.

7.2 VOLUME OF RAIN WATER HARVESTED:

The total quantity of water i.e., received in the form of rainfall over an area is called

the rain water endowment of that area, out of which the amount of water that can be

effectively harvested is called the rain water harvesting potential.

Rain Water harvesting potential = Intensity of Rainfall (m) x Roof Area x

Impermeability Factor.

The collection efficiency accounts for the fact that all the rain water falling over an

area cannot be effectively harvested due to losses on account of evaporation, spillage

or run off etc.,

According to the data available from the Indian Meteorological Department, the

Average annual rainfall around month of September = 194.80 mm

Assuming that about 90 % Rainfall can be effectively harvested.

Number of Rainy Days = 9.3

Therefore the I.R = 194.80/9.3= 20.94 mm/day or 0.02094 m/Day or 0.021 m/day

The Quantity of roof top rainwater harvested from the proposed is calculated as

under:

The 14th floor area of the proposed project is about 6,548.55 sq m

For rain water harvesting consider 75 % of this total area is 4,911 sq m

Quantity of Rain Water that can be harvested from the building is as follows.

Rain water (Q) from Roof top = 0.021 x 4,911 x 0.9

= 92.81 cum/day or say 93 cum/day

Page 73: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

72 PROJECT REPORT

Rain water storage sump of 100 cum (1 no) capacity is constructed to collect the rain

water and is being reused for domestic purposes.

7.3 STORM WATER MANAGEMENT:

Storm water disposal is divided into 2 Groups:

Terrace Storm water disposal: The entire rainwater from the terrace would be

disposed through suitable rain water pipes and collecting in the dedicated rain

water collection sump, which is proposed at site level. This water will be

utilized for domestic purpose

Site (Paved and landscape area) Storm water disposal: The entire storm water

from the site would be disposed off through suitable RCC Box drainage system

to the rainwater recharge pits and the excess is diverted to external storm

water drainage.

The amount of storm water that the paved area will produce can be determined by

considering the impermeability factor to be 0.9.

Q = 0.021 x 23,862.75sq m x 0.9

= 451.00 cum/day or say 451 cum/day

The amount of storm water that the landscaped area will produce can be determined

by considering the impermeability factor to be 0.3

Q = 0.021 x 16,014.69 sq m x 0.3

= 100.89 cum/day or say 101 cum/day

The Total amount of storm water = paved area + landscaped area

= 451 + 101 cum/day

= 552 cum/day

The Proponents shall also Provide Recharging Pits along the inner periphery of the

boundary wall with recharging pit of size 1.2 m dia x 2.5 m deep spaced at 20 m

centre to centre. These recharging pits are filled with graded media comprising of

Boulder at bottom and with coarse aggregates to facilitate percolation of harvested

rain water to Recharge Ground Water table.

Page 74: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

73 PROJECT REPORT

ANNEXURE: I

DISASTER MANAGEMENT PLANS FOR PRE CONSTRUCTION PHASE:

Risk and disaster management plan:

Disaster is an unexpected event due to sudden failure of the system, external

threats, internal disturbances, earth quakes, fire and accidents. Thus an appropriate

management plan shall be incorporated.

Precautions:

Once the likelihood of the disaster is suspected, preventive actions should be

undertaken by the project in-charge.

Conditional maintenance of equipments, materials and expertise for use during

emergency.

The electrical systems shall be provided with automatic circuit breakers

activated by over current.

Proper escape routes are planned and displayed in the public domain.

Selected representatives are given proper training to guide other inhabitants

during Fire accidents.

Periodic awareness program is conducted for the workers on their roles during

emergency situations.

Important telephone numbers like police authorities, fire department and hospitals

etc., of use during emergency situations will be made available.

Page 75: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

74 PROJECT REPORT

ANNEXURE: J

Environmental Management Plan for control of Dust and Noise pollution during

construction phase:

Barricades like metal sheets will be provided all round the premises of the project

to avoid fugitive dust emission in to the neighboring area and frequent water

sprinkling will also be carried out.

Environmental Impacts Mitigation Proposed

1. Leveling and Site Clearance:

Noise generation: Caused due to Excavators and Bulldozers

Most optimum no. of operation by the heavy equipment

Selection of equipment with less noise generation to be used

The earth moving equipment will be periodically checked and maintained for noise levels.

The workers will be provided with adequate PPE such as ear plugs to reduce impact of high noise levels.

Dust generation: Leveling operations results in the emission of dust.

The site cleared will be periodically watered to reduce emission of dust particles

Barricades like metal sheets will be provided all round the premises to avoid fugitive dust emission in to the neighboring area apart from water sprinkling.

The workers will be provided with PPE such as nose masks and goggles to reduce impact on health.

2. Transportation of Construction Materials:

Dust generation

Quality packaging of the construction materials

Construction materials will be covered with tarpaulin sheet to prevent from being air borne

The vehicle speed shall be regulated

Noise generation

Quality fuel will be used.

Periodic maintenance of vehicles is required.

Page 76: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

75 PROJECT REPORT

The workers transporting materials will be provided with PPE such as nose masks to reduce impact of air borne dust on their health

1. Construction Activities:

Noise generation

Selection of Less noise generating equipment

Personnel Protective Equipment (PPE) such as ear plugs and helmets will be provided for workers

The working hours will be imposed on the construction workers.

Dust generation PPE in the form of nose masks will be provided for construction workers

Use of water sprays to prevent dust from being air borne

Barricades like metal sheets will be provided all around the premises to avoid fugitive dust emission in to the neighboring area apart from water sprinkling

Page 77: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

76 PROJECT REPORT

ANNEXURE: K

RISK ASSESSMENT & MANAGEMENT PLAN

a. Construction Phase:

Sl. No.

Potential Mitigation

1 Accidental fire Fire safety gadgets.

2 Fall of objects Use of personal protection devices-helmets

3 Working at great heights Protection to prevent fall, with life safety belts and nets.

4 Accidents from machinery Personal protection gadgets

5 Electrical mishap Adopting safety measures to prevent any act of negligence and providing electrical safety measures like fire extinguishers.

b. All necessary measures will be taken to avoid accidents and mishaps during operation phase.

Precautions for Risk and Disaster Management Plan:

Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the project in-charge.

Conditional maintenance of equipments, materials, and expertise for use during emergency.

The electrical systems shall be provided with automatic circuit breakers activated by over current.

Fire extinguishers provided at pre-notified locations inside the building.

Proper escape routes will be planned and displayed in the public domain.

Selected representatives will be given proper training to guide other inhabitants during Fire accidents.

Periodic awareness program is conducted for the occupants on their roles during emergency situations.

Important telephone numbers like police authorities, fire department and hospitals

etc., of use during emergency situations are made available.

Page 78: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

77 PROJECT REPORT

ANNEXURE: L

SOIL INVESTIGATION REPORT

Page 79: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

78 PROJECT REPORT

ANNEXURE: M

TRAFFIC MANAGEMENT MEASURES

• Merging of vehicles will be performed only to left traffic from the exit gates,

this ensures safety.

• To establish smooth entry & exit of vehicles, bell mouth shape geometry is

provided at the gates. This ensures smooth transition for merging of vehicles.

• Yellow paint junction boxes are painted at the locations to create psychological

barrier for through drivers to control the speed.

• Rubber humps are introduced for the outgoing vehicles at the exit gate drive

way. All gates are manned with efficient security who can guide the entry and

exit of vehicles.

• Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress).

• Road marking, STOP lines, parking lanes, slot numbers etc, must be clearly

painted so as to guide the vehicles.

Page 80: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

79 PROJECT REPORT

ANNEXURE: N

ELECTRICAL ENERGY SAVINGS DETAILS

Energy Efficient motors, whose efficiency is not lower than the limits specified in section 8.2.2 of the ECBC code will be installed. b. Dry type Transformer with efficiency not lower than the limits specified in section 8.2.1 of the code shall be considered. c. Power monitoring, recording and check metering will be provided in the main LT panels on the incoming feeders and individual outgoing feeders covering all parameters such as Current, Voltage, Energy & THDI as stipulated in section 8.2.4 of the code. d. Cable sizing and design of distribution system will ensure that the total distribution loss will not exceed 1% of the total energy consumed as stipulated in section 8.2.5.1 of the code. e. Timer controls will be incorporated in the distribution board of external lighting to save energy as stipulated in section 7.4 of the code. f. Power conditioning equipment will be installed to limit THDI to 5% which shall also improve power factor to 0.95 as stipulated in section 8.2.3 of the code. g. Solar Lighting shall be provided at strategic locations in outdoor areas. h. Water cooled Chillers are used instead of air cooled chillers which provide energy savings. j. VFD drives shall be provided for secondary pumps for water cooled chillers and lifts which will result in energy savings.

Page 81: PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT PROJECTenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/07_Nov... · PROJECT REPORT FOR THE PROPOSED RESIDENTIAL APARTMENT

ROHAN BUILDERS PROJECT

80 PROJECT REPORT

ANNEXURE – 0

PROJECT RELEATED DRAWINGS & PLANS