Celanese Methanol Plant Clear Lake, Texas $160,000,000 Contract Value Worley Parsons 15 Month Duration 1,860,300 Workhours 148,000 LF of Piping –Spools 11,126 Pipe Welds -187,383 Weld Dia. Inches 1,022 Hydrostatic Test Packages • Greenfield Project • Turner Increased craft manpower from 300 to 900 over a 7-week period • 110 pipe welders on the project • Turner fabricated all piping with pipe sizes ranging up to 72” diameter • Turner provided commissioning and start-up assistance Zero Lost Time Accidents Project Quick Facts