32 Market Avenue SW, Suite 200 Grand Rapids, MI 49503 Ph: 616. 464. 1740 Fx: 616. 464. 1742 www.OrionBuilt.com Project Progress Report Report No: 17 Report Period: June 20 th thru June 24 th , 2016 Fulton Square Distribution: Roger Rehkopf, John Wheeler, Gary Postma, Ryan Wheeler, John Boonstra, Corey Bixby, Deb Filipiak Project Manager: DuWayne Johnson Superintendent: Kyle Marchand Report Date: June 24 th , 2016
12

Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Jul 18, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

32 Market Avenue SW, Suite 200 ♦ Grand Rapids, MI 49503

Ph: 616. 464. 1740 ♦ Fx: 616. 464. 1742 ♦ www.OrionBuilt.com

Project Progress Report

Report No: 17

Report Period: June 20th thru June 24th, 2016

Fulton Square

Distribution:

Roger Rehkopf, John Wheeler,

Gary Postma, Ryan Wheeler,

John Boonstra, Corey Bixby,

Deb Filipiak

Project Manager: DuWayne Johnson

Superintendent: Kyle Marchand

Report Date: June 24th, 2016

Page 2: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

Contents

1.0 Executive Summary .......................................................................................................... 2

2.0 Summary of Work ........................................................................................................... 2-3

2.0 Work Completed & Two Week Look-Ahead ....................................................... 2

2.1 Schedule Impacts ................................................................................................ 3

2.2 Issues/Potential Delays/Potential Change Orders .............................................. 3

3.0 Health & Safety Report .................................................................................................... 3

4.0 Resources & Labor Report .............................................................................................. 4

5.0 Weather .......................................................................................................................... 4

6.0 Open RFI Log ................................................................................................................... 4

7.0 On Schedule? .................................................................................................................. 5

Notes ..................................................................................................................................... 5

Project Photos ....................................................................................................................... 6-7

Appendix

Page 3: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

1.0 Executive Summary

With two rain days this week, progress was a bit slower than normal. However, trades were

able to stay on schedule and continue significant work on Building A. Consumers Energy was

onsite to run primary power and set transformer for Building A.

2.0 Summary of Work The following work has been completed since the last report:

• Fair & Square Carpentry

o Completed roof truss installation and roof sheathing

o Completed wood top plate for all Steel Building B

o Completed South stairs in Building A

o Started floor truss hanger installation on Building B.

o Started Stair #3 for Building B

• Consolidated Electric

o Continued Electrical Box out for Building A 2nd and 3rd Level Units.

• Tekton Masonry

o Completed masonry work above Mailroom Building A.

• Custom Steel

o Completed installation of structural steel for Building B.

o Completed installation fo brick relief angle on perimeter of Building B.

o Steel inspection performed and passed.

• J Stevens Roofing

o Started installation of Building A Roof

• MPH Plumbing

o Continued plumbing rough-in for Building A 2nd Floor.

Two Week Look-Ahead:

• J Stevens Roofing

o Complete Building A Roof

• Custom Steel

o Deliver and install brick relief angle/tube steel for Masonry stair towers

• Fair & Square

o Complete installation of floor truss hangers Building B.

o 2nd Floor trusses and sheathing Building B.

o Delivery and installation of 2nd Floor wall panels Building B.

• Consolidated Electric

o Continue electrical Rough-In Building A 3rd Floor due 7/8/16

• MPH Plumbing

o Continue plumbing rough-In Building A 3rd Floor due 7/8/16

• Progressive HVAC

o Start Building A mechanical rough-in 3rd Floor due 7/8/16

• Brigade Fire Protection

o Start Building A FP rough-in 3rd Floor due 7/8/16

Page 4: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

2.1 Schedule Impacts

The Project has lost # days since last report.

Item Description/Activity

Schedule

Start

Actual

Start

Delay

Days

1

2

3

4

5

6

7

8

Total lost days this report 0.00

Total lost days last report 0.00

Total lost days to date 0.00

2.2 Issues / Potential Delays / Potential Change Orders

Item Description Category

1 Bulletin #5 Issued for pricing from subcontractors Change Orders

2

3

4

5

6

7

8

3.0 Health & Safety Report / OSHA Visit

Item Accident / Incident Date Time Lost

1

2

3

4

5

Page 5: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

4.0 Resources & Labor Report

Item Trade / Designation

1 Orion Construction 40 hours

2 ThornApple Excavation 0 hours

3 B & B Concrete 0 hours

4 Custom Steel 19 hours

5 Tekton Masonry 72 hours

6 M.P.H. Plumbing 42 hours

7 Fair & Square 522 hours

8 Consolidated Electric 72 hours

9 Progressive HVAC 0 hours

10 J Stevens Roofing 50 hours

11 Brigade Fire Protection 3 hours

12

hours

Total hours this report 748 hours

Total hours last report 7,070.0 hours

TOTAL HOURS 7,818.0 hours

5.0 Weather

Day Date Description of Weather Event Low Temp Hi Temp Precipitation

Mon 6/20 Sunny-Humid 72 90

Tue 6/21 Overcast 62 86

Wed 6/22 Overcast 56 89

Thu 6/23 Overcast 59 85

Fri 6/24 Sunny 57 86

Sat

6.0 Open RFI

Item Description

1 RFI #21- Kitchen Electrical (In Progress)

2 RFI #22- Balcony Electrical Boxes (In Progress)

3

4

5

6

Page 6: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

7.0 On Schedule?

Anticipated Completion Date: December 22, 2016

Item Milestone Description Due Date

1 Building Permit Received 2/17/16

2 Project Actual Start Date 2/18/16

3 Project Date of Substantial Completion

4 Date of Occupancy

5 Weekly Subcontractor Meeting (date & time) Tues 11am

6 Bi-Weekly Owner/Architect/Contractor Meeting (date & time) Tues 11:30

7

8

9

10

11

12

13

14

15

NOTES:

Page 7: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

Project Photographs

Stairs in Building A Framing

Building A Framing above Water Room

West Elevation Framing Tyvek Completed

Stairs in Building B Framing

South Elevation Framing Completed

East Elevation Framing Tyvek Completed

Page 8: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Fulton Square Report No. Report #17 June 24, 2016

Project Photographs

MEP rough-ins Continue

Steel Relief angled welded in place

Roof Sheathing Completed

Wood top plate for steel completed

Building B Floor Truss Hanger installation

Roofing Installation Progress

Page 9: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

Updated On: June 24, 2016

REQUEST FOR INFORMATION LOGID Current

Status

Priority Request Description Requested By Approval Authority Date Requested Date Response

Required

Date Response

Received

Notes

001 In Progress High Location of storm water leads Orion/ Thornapple Civil Engineer 03/08/16 03/10/16

No storm leads located along Carlton Ave as indicated on

drawings.

002 Closed Critical Foundation Dimension Issues Orion/ B&B Concrete Architect 03/14/16 03/14/16 03/17/16 USE ARCH DRAWING DIMENSIONS

003 Closed Medium First Floor Demising Wall Columns Orion/Standale Lumber Architect 03/15/16 03/21/16 03/25/16 Use Collumns Spec'd. Collumns will stick out in closets

004 Closed Medium Connection Details Orion/Standale Lumber Structural Engineer 03/15/16 03/21/16 03/25/16 See attached Sketchs within response

005 Closed Medium Multiple Framing Questions- Standale Panalization Pacakage Orion/Standale Lumber Structural Engineer 03/25/16 04/06/16 03/28/15 See RFI response for multiple answers

006 Closed Medium Foundation Details for Building A East walls Orion/ B&B Concrete Architect 03/30/16 04/06/16 03/31/16 Reissued Changed in Bulletin #1 Porch Sizes Reduced

007 Closed Medium Misc. Structural Steel Detail Questions Orion/Ludtke Architect 04/13/16 04/19/16 04/13/16

008 Closed Low Selection of Electrical cover plate colors Orion/ Consolidated Architect 04/29/16 05/16/16 04/29/16

009 Closed Medium Footing Schedule does not include F5.5 Footing Orion/B&B Concrete Structural Engineer 05/03/16 05/10/16 05/03/16 Updated Footing Schedule

010 Closed High Stair S2 wall schedule and MECH Room Wall Schedule Orion/ Tekton Masonry Architect 05/06/16 05/10/16 05/12/16

011 Closed Medium Brick Relief Angle Steel Exterior Fastening Orion/ Tekton Masonry Architect 05/06/16 05/13/16 05/12/16

012 Closed Medium Building A Interior Footing Details Orion/ B&B Concrete Structural Engineer 05/09/16 05/16/16 05/09/16 Updated Footing Detail w/ sketch

013 Closed Medium CMU Block Damproofing and Insulation Alternative Orion/ Tekton Masonry Architect 05/19/16 05/27/16 05/19/16 Approved Alternate CMU Block Insulation

014 Closed Medium Electronic strike on storefront doors Orion/Double O Architect 05/25/16 05/30/16 05/31/16 Provided door to place electric strike

015 Closed High Building A Framing Fastening Requirements Orion/ Fair & Square Structural Engineer 05/31/16 06/03/16 06/02/16 Provided fastening requirements and clarification

016 Closed Medium Patio Door Alternate Orion/ Double O Architect 06/06/16 06/13/16 06/06/16 Patio Door Alternate from Jeld-Wen Approved

017 Closed High Building B 2nd Floor Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Cut Down header and fasten as directed in RFI Response

018 Closed Medium Unit Type G Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Adjusted From H4 to H1 Header

019 Closed Medium Reflected Ceiling Plan 1st Floor Building A Orion Architect 06/08/16 06/15/16 06/15/16 Changed Framing in Bulletin #5

020 Closed Medium Kitchen Cabinets & Appliance Conflict Orion/ Lumbermans Architect 06/10/16 06/17/16 06/15/16 Changed Kitchen Layouts in Bulletin #5

021 In Progress Medium Kitchen Island Electrical Orion/ Consolidated Architect 06/20/16 06/24/16 Working on Potential Solutions

022 In Progress Medium Balcony Electrical and Framing Conflict Orion/ Consolidated Architect 06/20/16 06/24/16 Potential solution provided, Electrican confirming

Concept Design

Orion Construction

Fulton Square

General Contractor:

Project Name:

Architect:

32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503

(616) 464-1740 Office | (616) 464-1742 Fax Page 1 of 1

Page 10: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

SUBMITTAL LOG UPDATED: June 24, 2016

0004 Concrete B&B Concrete 03 3000 Steel Reinforcement Drawings 3/4/2016 3/1/2016 3/3/2016 3/9/2016 3/10/2016 3/11/2016 REVIEWED W/COMMENTS NONE CLOSED

0008 Concrete B&B Concrete 03 3000 Mix Designs 03/07/16 3/5/2016 3/7/2016 3/11/2016 3/7/2016 3/7/2016 REVIEWED NONE CLOSED

0032 Masonry Tekton 04 20 00 Unit Block Masonry 4/15/16 4/26/2016 4/26/2016 5/4/2016 4/27/2016 4/28/2016 APPROVED NONE CLOSED

0015 Steel Ludtke Steel 05 Structural Steel Shop Drawings 03/22/16 3/23/2016 3/24/2016 4/4/2016 4/4/2016 4/4/2016 APPROVED AS NOTED NONE CLOSED

0015 Steel Ludtke Steel 05 Misc Steel Shop Drawings 03/22/16 3/23/2016 3/24/2016 4/4/2016 4/4/2016 4/4/2016 APPROVED AS NOTED MAKE CORRECTIONS NOTED CLOSED

0024 Carpentry Standale Lumber 06 17 53 Fabricated Wood Trusses Bld B 4/1/16 4/11/2016 4/11/2016 4/25/2016 4/13/2016 4/13/2016 RETURNED NONE CLOSED

0025 Carpentry Standale Lumber 06 17 53 Fabricated Roof Trusses Bld B 4/1/16 4/12/2016 4/12/2016 4/25/2016 4/13/2016 4/13/2016 RETURNED NONE CLOSED

0031 Carpentry Standale Lumber 06 17 53 Fabricated Roof Trusses Bld A 04/25/16 4/25/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS NONE CLOSED

0033 Carpentry Standale Lumber 06 10 00 Wall Panels Bld A 4/6/16 4/6/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED

0034 Carpentry Standale Lumber 06 10 00 Wall Panels Bld B 4/6/16 4/6/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED

0016 Caulking Custom Caulking 07 90 00 Joint Protection 03/15/16 3/24/2016 3/25/2016 4/4/2016 4/1/2016 4/1/2016 RETURNED NONE CLOSED

0022 Concrete B&B Concrete 07 00 00 Elevator Pit Waterproofing 04/01/16 4/6/2016 4/6/2016 4/7/2016 4/7/2016 4/7/2016 APPROVED NONE CLOSED

0030 Insulation Randl Interiors 07 21 00 Thermal Insultation 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED NONE CLOSED

0028 Fireproofing Randl Interiors 07 81 00 Applied Fireproofing 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED AS NOTED NONE CLOSED

0027 EIFS Randl Interiors 07 24 00 Direct Exterior Finish System 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED AS NOTED NONE CLOSED

0002 Carpentry Double O Supply 088000 Insulated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED

0002 Carpentry Double O Supply Tubelite Entrances 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED

0002 Carpentry Double O Supply 087100 Aluminum Door Hardware 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED

0002 Carpentry Double O Supply Fire Rated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED

0019 Carpentry Double O Supply 084113 Vinyl Windows and Patio Doors 2/23/16 3/8/2016 3/30/2016 4/8/2016 4/4/2016 4/4/2016 APPROVED AS NOTED MAKE CORRECTIONS NOTED CLOSED

0021 Carpentry Double O Supply 083100 Aluminum Doors & Storefront Windows 03/15/16 3/29/2016 3/30/2016 4/12/2016 4/5/2016 4/12/2016 REVIEWED W/COMMENTS NONE CLOSED

0021 Carpentry Double O Supply 083100 Aluminum Doors & Storefront Windows UPDATED COMMENTS 4/26/2016 NONE CLOSED

0026 Carpentry AOA 08113 1400 Hollow Metal and Wood Doors 4/1/16 4/18/2016 4/18/2016 4/25/2016 4/22/2016 5/11/2016 APPROVED AS NOTED NONE CLOSED

Division 05 Metals

Division 06 Wood, Plastics & Composites

Division 07 Thermal & Moisture Protection

Division 08 Openings

Fulton Sqaure

Division 03 Concrete

Division 02 Existing Conditions

Item No.Due From

A/E/ORequired Action

Due From

SubStatus

Ball in

Court Company

Rec'd From

Sub

Sent to

A/E/O

Revision

No.Spec #

Division 04 Masonry

Returned to

SubTrade Required Submittal Item

Rec'd from

A/E/O

32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503

(616) 464-1740 Office | (616) 464-1742 Fax

www.OrionBuilt.com

Page 11: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

0038 Metal Panel Reliable Sheet 08 00 00 ACM Panels and Metal Coping 5/1/16 5/11/2016 5/11/2016 5/25/2016 5/26/2016 5/26/2016 REVIEWED W/COMMENTS APPROVAL CLOSED

0020 Painting DeMaat Bros. 099000 Paint 03/15/16 3/29/2016 3/30/2016 4/12/2016 4/4/2016 4/4/2016 APPROVED NONE CLOSED

0029 Gypboard Randl Interiors 09 2116-5113 Gypsum Board and ACT Ceiling 04/18/16 4/18/2016 4/22/2016 5/3/2016 5/26/2016 5/27/2016 REVIEWED W/COMMENTS NONE CLOSED

Carpet DeGraaf Interiors 09 68 00 Carpeting 06/01/16 6/15/2016 ORION

Interiors DeGraaf Interiors 09 72 00 Wall Coverings 06/01/16 6/15/2016 ORION

0007 Mailboxes Klosterman 10 55 00 Postal Specialties 03/10/16 3/4/2016 3/4/2016 3/16/2016 3/7/2016 3/31/2016 REVIEWED W/COMMENTS NONE CLOSED

0009 Bath Acessories Product Resources 10 28 00 Toilet Room Accessories 3/15/16 3/9/2016 3/9/2016 3/18/2016 3/21/2016 3/22/2016 APPROVED AS NOTED NONE CLOSED

0010 Bike Racks Product Resources 10 00 00 Bike Racks 3/15/16 3/9/2016 3/9/2016 3/18/2016 3/11/2016 3/11/2016 REVIEWED W/COMMENTS NONE CLOSED

0014 Signage Handicap Signs 10 00 00 Parking Lot Signage 03/15/16 3/16/2016 3/18/2016 3/25/2016 3/23/2016 3/31/2016 APPROVED AS NOTED NONE CLOSED

0006 Appliances General Electric 11 31 00 Residential Appliances 03/01/16 03/01/16 03/04/16 03/14/16 03/11/16 03/29/16 REVIEWED W/COMMENTS REVIEW CLOSED

0012 Casework Lumbermans 12 35 30 Casework Shop Drawings 03/15/16 3/16/2016 3/18/2016 3/23/2016 3/29/2016 3/29/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED

0013 Casework Lumbermans 12 35 30- 2.5 Countertop Shop Drawing 03/15/16 3/16/2016 3/18/2016 3/23/2016 3/29/2016 3/29/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED

0023 Elevator Kone 14 21 00 Electric Traction Elevator 04/01/16 4/6/2016 4/7/2016 4/18/2016 4/15/2016 4/15/2016 REVIEWED W/COMMENTS NONE CLOSED

042 Fire Protection Brigade 21 13 11 Building A Wet Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED

042 Fire Protection Brigade 21 13 11 Building B Wet Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED

042 Fire Protection Brigade 21 13 16 Building A Dry Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED

042 Fire Protection Brigade 21 13 16 Building B Dry Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED

0003 Plumbing M.P.H. 22 4000 WC-1 and WC-2 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 4000 Lav-1, Lav-2, and Lav-3 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 01 Plumbing M.P.H. 22 4000 Tub-1 and Tub-2 2/23/16 2/23/16 03/15/16 3/22/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 01 Plumbing M.P.H. 22 4000 SH-1, SH-2, and SH-3 2/23/16 2/23/16 03/15/16 3/22/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 4000 S-1, S-2, S-3 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 4000 SS-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 3300 EWC-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 0000 WB-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 0000 IM-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 3300 EWH-1 and EWH-2 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 0000 Expansion Tank 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 0000 SP-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 1119 TS-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

0003 Plumbing M.P.H. 22 0000 OI- 1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED

043 Plumbing M.P.H. 22 00 00 Submeters 2/23/16 6/20/2016 06/22/16 6/26/2016 FORWARDED TO A/E APPROVAL A/E

0037 Mechanical Progressive 23 00 00 Multiple (HVAC Package) 4/10/2016 4/21/2016 5/11/2016 5/25/2016 5/26/2016 5/26/2016 APPROVED AS NOTED NONE NONE

Division 09 Finishes

Division 10 Specialties

Division 22 Plumbing

Division 12 Furnishings

Division 14 Conveying Equipment

Division 11 Equipment

Division 23 HVAC

Division 21 Fire Protection

32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503

(616) 464-1740 Office | (616) 464-1742 Fax

www.OrionBuilt.com

Page 12: Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades

0011 Electrician Consolidated 26 00 00Electrical Distribution (panelboards,

Meters, Load Centers)3/10/16 3/15/2016 3/16/2016 3/23/2016 4/15/2016 4/15/2016 REVIEWED W/COMMENTS NONE CLOSED

0017 Electrician Consolidated 26 09 26 Lighting Controls 3/10/16 3/29/2016 3/29/2016 4/8/2016 4/4/2016 4/4/2016 APPROVED AS NOTED NONE CLOSED

0018 Electrician Consolidated 26 29 51 Lighting Fixtures 3/10/16 3/29/2016 3/29/2016 4/8/2016 4/4/2016 4/4/2016 REVIEWED W/COMMENTS NONE CLOSED

0018 01 Electrician Consolidated 26 29 51 Missing Lighting Fixture 04/07/16 4/11/2016 4/11/2016 4/15/2016 4/12/2016 4/12/2016 REVIEWED NONE CLOSED

0039 Electrician Consolidated 27 05 28 Building A Tele-Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED

0040 Electrician Consolidated 27 05 28 Building B Tele- Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED

0035 Electrician Consolidated 28 31 00 Building A Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED

0035 R01 Electrician Consolidated 28 31 00 Building A Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED

0035 R02 Electrician Consolidated 28 31 00 Building A Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED

0036 Electrician Consolidated 28 31 00 Building B Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED

0036 R01 Electrician Consolidated 28 31 00 Building B Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED

0036 R02 Electrician Consolidated 28 31 00 Building B Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED

0001 Excavation Thornapple 310000 WCU, Geotextile, IB Pipe, etc.. 1/28/16 2/1/2016 2/1/2016 2/4/2016 2/5/2016 2/18/2016 APPROVED AS NOTED NONE CLOSED

0041 Fencing Fence Consultant 31 00 00 Wood Privacy Fence 06/09/16 6/9/2016 6/6/2016 6/14/2016 FORWARDED TO A/E APPROVAL A/E

Division 31 Site Improvements

Division 28 Electronic Safety and Security

Division 26 Electrical

Division 27 Communications

32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503

(616) 464-1740 Office | (616) 464-1742 Fax

www.OrionBuilt.com