32 Market Avenue SW, Suite 200 ♦ Grand Rapids, MI 49503 Ph: 616. 464. 1740 ♦ Fx: 616. 464. 1742 ♦ www.OrionBuilt.com Project Progress Report Report No: 17 Report Period: June 20 th thru June 24 th , 2016 Fulton Square Distribution: Roger Rehkopf, John Wheeler, Gary Postma, Ryan Wheeler, John Boonstra, Corey Bixby, Deb Filipiak Project Manager: DuWayne Johnson Superintendent: Kyle Marchand Report Date: June 24 th , 2016
12
Embed
Project Progress Report...Fulton Square Report No. Report #17 June 24, 2016 1.0 Executive Summary With two rain days this week, progress was a bit slower than normal. However, trades
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
32 Market Avenue SW, Suite 200 ♦ Grand Rapids, MI 49503
Priority Request Description Requested By Approval Authority Date Requested Date Response
Required
Date Response
Received
Notes
001 In Progress High Location of storm water leads Orion/ Thornapple Civil Engineer 03/08/16 03/10/16
No storm leads located along Carlton Ave as indicated on
drawings.
002 Closed Critical Foundation Dimension Issues Orion/ B&B Concrete Architect 03/14/16 03/14/16 03/17/16 USE ARCH DRAWING DIMENSIONS
003 Closed Medium First Floor Demising Wall Columns Orion/Standale Lumber Architect 03/15/16 03/21/16 03/25/16 Use Collumns Spec'd. Collumns will stick out in closets
004 Closed Medium Connection Details Orion/Standale Lumber Structural Engineer 03/15/16 03/21/16 03/25/16 See attached Sketchs within response
005 Closed Medium Multiple Framing Questions- Standale Panalization Pacakage Orion/Standale Lumber Structural Engineer 03/25/16 04/06/16 03/28/15 See RFI response for multiple answers
006 Closed Medium Foundation Details for Building A East walls Orion/ B&B Concrete Architect 03/30/16 04/06/16 03/31/16 Reissued Changed in Bulletin #1 Porch Sizes Reduced
009 Closed Medium Footing Schedule does not include F5.5 Footing Orion/B&B Concrete Structural Engineer 05/03/16 05/10/16 05/03/16 Updated Footing Schedule
010 Closed High Stair S2 wall schedule and MECH Room Wall Schedule Orion/ Tekton Masonry Architect 05/06/16 05/10/16 05/12/16
012 Closed Medium Building A Interior Footing Details Orion/ B&B Concrete Structural Engineer 05/09/16 05/16/16 05/09/16 Updated Footing Detail w/ sketch
013 Closed Medium CMU Block Damproofing and Insulation Alternative Orion/ Tekton Masonry Architect 05/19/16 05/27/16 05/19/16 Approved Alternate CMU Block Insulation
014 Closed Medium Electronic strike on storefront doors Orion/Double O Architect 05/25/16 05/30/16 05/31/16 Provided door to place electric strike
015 Closed High Building A Framing Fastening Requirements Orion/ Fair & Square Structural Engineer 05/31/16 06/03/16 06/02/16 Provided fastening requirements and clarification
016 Closed Medium Patio Door Alternate Orion/ Double O Architect 06/06/16 06/13/16 06/06/16 Patio Door Alternate from Jeld-Wen Approved
017 Closed High Building B 2nd Floor Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Cut Down header and fasten as directed in RFI Response
018 Closed Medium Unit Type G Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Adjusted From H4 to H1 Header
019 Closed Medium Reflected Ceiling Plan 1st Floor Building A Orion Architect 06/08/16 06/15/16 06/15/16 Changed Framing in Bulletin #5
020 Closed Medium Kitchen Cabinets & Appliance Conflict Orion/ Lumbermans Architect 06/10/16 06/17/16 06/15/16 Changed Kitchen Layouts in Bulletin #5
021 In Progress Medium Kitchen Island Electrical Orion/ Consolidated Architect 06/20/16 06/24/16 Working on Potential Solutions
022 In Progress Medium Balcony Electrical and Framing Conflict Orion/ Consolidated Architect 06/20/16 06/24/16 Potential solution provided, Electrican confirming
Concept Design
Orion Construction
Fulton Square
General Contractor:
Project Name:
Architect:
32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503
0027 EIFS Randl Interiors 07 24 00 Direct Exterior Finish System 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED AS NOTED NONE CLOSED
0002 Carpentry Double O Supply 088000 Insulated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply Tubelite Entrances 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply 087100 Aluminum Door Hardware 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply Fire Rated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0019 Carpentry Double O Supply 084113 Vinyl Windows and Patio Doors 2/23/16 3/8/2016 3/30/2016 4/8/2016 4/4/2016 4/4/2016 APPROVED AS NOTED MAKE CORRECTIONS NOTED CLOSED
0039 Electrician Consolidated 27 05 28 Building A Tele-Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED
0040 Electrician Consolidated 27 05 28 Building B Tele- Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED
0035 Electrician Consolidated 28 31 00 Building A Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED
0035 R01 Electrician Consolidated 28 31 00 Building A Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED
0035 R02 Electrician Consolidated 28 31 00 Building A Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED
0036 Electrician Consolidated 28 31 00 Building B Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED
0036 R01 Electrician Consolidated 28 31 00 Building B Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED
0036 R02 Electrician Consolidated 28 31 00 Building B Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED