Snowmass Town Park Master Plan August 17, 2020 | PROJECT PROCESS PROJECT PROCESS PROJECT STARTUP DESIGN ALTERNATIVES FINAL MASTER PLAN • TOWN & STAKEHOLDER INTERVIEWS • PROGRAM ASSESSMENT • CONCEPT GENERATION AND EVALUATION • FINAL PLAN • PHASING PLAN • BUDGET 08-17-20 TC Packet Page 198 of 207
9
Embed
PROJECT PROCESS...More efficiently utilize the used and unused park space to create a beautiful and engaging destination for all ages. PRIORITY USER GROUP Town of Snowmass Village
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Snowmass Town Park Master PlanAugust 17, 2020 | P R O J E C T P R O C E S S
PROJECT PROCESSPROJECT STARTUP
DESIGN ALTERNATIVES
FINAL MASTER PLAN
• TOWN & STAKEHOLDER INTERVIEWS• PROGRAM ASSESSMENT
• CONCEPT GENERATION AND EVALUATION
• FINAL PLAN• PHASING PLAN• BUDGET
08-17-20 TC Packet Page 198 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | P R O J E C T G O A L S
PRIMARY MASTER PLAN GOALMore efficiently utilize the used and unused park space to create a
beautiful and engaging destination for all ages.
PRIORITY USER GROUPTown of Snowmass Village residents
08-17-20 TC Packet Page 199 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | P R O J E C T G O A L S
SECONDARY MASTER PLAN GOALS
• Beautify the entry to Snowmass• Reduce conflict between events and rec
users• Incorporate centralized storage and
maintenance facility• Provide additional opportunities for field
sports programming • Provide additional parking• Enhance recreation opportunities
• Minimize pedestrian/bike/vehicular conflict
• Maintain space for rec/pool expansion• Maintain existing improvements• Maintain a quality rodeo facility
08-17-20 TC Packet Page 200 of 207
BLACK SADDLE PARKING
0' 80' 160'
SCALE: 1"=80' NORTH
240’
Snowmass Town Park Master PlanAugust 17, 2020 | S P A C E U S A G E D I A G R A M
rodeo / parkingparking
grass fields
grass fields
grass fields
parking
active recreation
active recreationpassive / wetlandspassive / wetlands
active recreation
08-17-20 TC Packet Page 201 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | P R O G R A M S U M M A R Y
• Wetland recreation area with diverse access experiences• Improved recreation pond with beach, wading/swimming, fishing,
and gathering areas• Additional programmable field space• Stream-side play/exploration• Bike skills trail• Additional restroom facilities• Additional rentable events space• Additional summer and winter parking• Indoor, consolidated parks maintenance facility
IMPROVEMENTS SUMMARY
08-17-20 TC Packet Page 202 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | T O W N P A R K M A S T E R P L A N
overlook/lounge deck/fishing pier/event space with overhead element for shade/visibility
lawn area with trees
crusher fine path
flagstone and decorative aggregate water play feature
sand beach
dredge pond of cattails and fill lower “finger”
bike/pedestrian boardwalk
Scandinavian plank path + mini-ropes course
decomposed granite and boardwalk trail network
picnic table(s), typ.
Key Considerations:• Maintain/promote creek and wetland health• Transition from active to passive uses as you move away from the pond to
the eastern end of wetlands• Emphasize visual access from the road to the pond and wetlands• Capitalize on existing shade; create shade with proposed vegetation as
design develops• Create a variety of trail types for a multitude of users: ADA, paved bike,
mountain bike, passive ped trails, active ped/ ‘adventure’ trails• Provide easy access to important amenities: paddle board drop off, beach
access, bathrooms etc.• Create a variety of active and passive ways to experience the wetland,
including educational and interactive opportunities• Capitalize on existing views and strategically place elements so that their
view-shed is not compromised by development. Focus on the natural world and specific details
• Enhance and create connection to “wildness” • Capitalize on existing topography such as the existing bench on the
southern side of the wetlands and abundant flat space• Be mindful of maintenance requirements for all proposed design
elements• A very light construction footprint to preserve the wetlands to the
greatest extent possible while constructing paths and elements.
brus
h cre
ek ro
ad
1
1
2
2
4
4
6
6
9
9
33
55
8
8
7
7
1010
1413
13
11
15
12
16
11
12
08-17-20 TC Packet Page 204 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | W I N T E R U S A G E
day skier parking at rodeo grounds (~197 spaces)
arena fencing and event fencing storage area
collapsible stands in storage modemerchandise booths stored
tent storage in maintenance building
nordic ski/snowshoe trail
ice rink
winter trails parking access
flush curb & blocked spaces for winter parking access
transit center
existing day skier overflow parking
08-17-20 TC Packet Page 205 of 207
Snowmass Town Park Master PlanAugust 17, 2020 | P R O G R A M S U M M A R Y
BY THE NUMBERS
Field Space:• 272,700 SF of playable field space (approx. 64,000 SF gain)• 2 possible simultaneous U-18 soccer fields (no change)• 2 possible simultaneous full-sized softball fields (1 additional field) • 6 possible simultaneous U-10 soccer fields (2 additional fields)
Park Structures:• 2 large gazebos with water and power (1 additional)• NEW 2 covered picnic structures• NEW 2 plumbed restroom facilities with 5 unisex “stalls” total (incl. 2
accessible).• NEW indoor parks maintenance facility (approx. 2,600 SF)