Top Banner
Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3 2 nd Semester 2008/2009 UP Copyrights 2009 Project Planning & Control Eng: Eyad Haddad
31

Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Dec 26, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control1

ECCS5209

Project Planning & Control

Faculty of Applied Engineering and Urban Planning

Civil Engineering Department

Lect. 2+3

2nd Semester 2008/2009

UP Copyrights 2009

Pro

ject

Pla

nnin

g &

Contr

ol

Eng: Eyad Haddad

Page 2: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control2

‘A unique set of co-ordinated activities,

with definite starting and finishing points,

undertaken by an individual or organization

to meet specific objectives within defined

schedule, cost and performance parameters.’

Project definition

Page 3: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control3

As stated in the definition,

a project has a definite starting and finishing point and must

meet certain specified objectives.

These objectives, must meet three fundamental criteria:

1 The project must be completed on time;

2 The project must be accomplished within the budgeted cost;

3 The project must meet the prescribed quality requirements.

Project definition

Page 4: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control4

These criteria can be graphically represented by the well-known project triangle (Figure 1.1). .

Some organizations like to substitute the word ‘quality’

with ‘performance’, but the principle is the same – the operational requirements of the project must be met, and met safely.

Page 5: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control5

In certain industries like airlines, railways and mining etc. the fourth

Criterion معيار, safety, is considered to be equally, if not more important.

In these organizations, the triangle can be replaced by a diamond now showing the four important criteria (Figure 1.2).

Page 6: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control6

Time bound project

cost and performance may have to be sacrificed to meet the unalterable

starting date of the tournament.

(In practice, the increased cost may well be a matter of further

negotiation

and the temporarily delayed display can usually be added later during

the non-playing hours.)

Cost bound project

The project cost cannot be exceeded, because the housing grant

allocated by central government for this type of development has been

frozen at a fixed sum.

Another solution to this problem would be to reduce the specification

of the internal fittings instead of reducing the number of units

Page 7: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control7

Performance (quality) bound project

An armaments manufacturer has been contracted to design and

manufacture a new type of rocket launcher to meet the client’s

performance specification in terms of range, accuracy and rate of fire.

Even if the delivery has to be delayed to carry out more tests and the

cost has increased, the specification must be met. Again if the weapons

were required during a war, the specification might be relaxed to get the

equipment into the field as quickly as possible.

Page 8: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control8

Business case

1. Why is the project required?

2. What are we trying to achieve?

3. What are the deliverables?

4. What is the anticipated cost?

5. How long will it take to complete?

6. What quality standards must be achieved?

7. What are the performance criteria?

8. What are Key Performance Indicators (KPI)?

9.What are the main risks?

10.What are success criteria?

11.Who are the main stakeholders?

Page 9: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 9

A construction project, or any project, is defined by the following

- A defined goal or objective.

- Specific tasks to be performed.

- A defined beginning and end.

- Resources being consumed (manpower+ materials).

The goal of construction project is to build something.

The differentiation between construction industry and other industries

is that its projects are large, built on-site, and generally unique.

Time, money, labor, equipment, and, materials are all examples of

the kinds of resources that are consumed by the project.

The Construction Project

Page 10: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 10

The construction industry is the largest industry in the world.

Growth in this industry in fact is an indicator of the economic

conditions of a country. This is because the construction industry

consumes a wide employment circle of labor

The manufacturing industry exhibit high-quality products, timelines of

service delivery, reasonable cost of service, and low failure rates,

the construction industry, on the other hand, is generally the opposite.

Most projects exhibit cost overruns, time extensions, and conflicts

among parties.

The Need for Project Management (for many Reasons)?

Page 11: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 11Example of a complicated project

Page 12: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 12

In general, the construction industry is more challenging than

other industries due to :

its unique nature;

every project is one-of a kind;

many conflicting parties are involved;

projects are constrained by time,

money and quality;

and high risk.

Construction industry challenging:

Page 13: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 13

The acquisition of a constructed facility usually represents a major capital

investment, whether its owner happens to be an individual, a private

corporation or a public agency.

The commitment of resources for such an investment is motivated by

market demands.

or perceived needs.

The project life cycle for a constructed facility may be illustrated in

Figure 1.2.

The Project Life Cycle:

Page 14: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 14

Page 15: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 15

A) Preconstruction Phase

B) Procurement Phase(bidding & award)

C) Construction Phase

D) Closeout Phase

A-1 Conceptual Design

A-2 Schematic Design

A-3 Design Development

A-4 Contract Documents

The Project Life Cycle

Page 16: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 16

A. Preconstruction phase

It can be broken into

conceptual planning,

schematic design,

design development,

and contract document

1. Conceptual design:

-Very important for the owner.

- During this stage the owner hires key consultants including the designer and project manager, selects the project site, and establish a conceptual estimate, schedule, and program.

-The owner must gather as much reliable information as possible about the project.

- The most important decision is to proceed with the project or not.

The Project Life Cycle

Page 17: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 17

2. Schematic design: During this phase,

-the project team investigates alternate design solutions, materials and systems.

-Completion of this stage represents about 30% of the design completion for the project.

3. Design development:

-Designing the main systems and components of the project.

-Good communication between owner, designer, and construction manager is critical during this stage because selections during this design stage affect project appearance, construction and cost.

- This stage takes the project from 30% design to 60% design.

The Project Life Cycle (Cont.)

Page 18: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 18

4. Contract documents:

-Final preparation of the documents necessary for the bid package such

as the drawings, specifications, general conditions, and bill of

quantities.

-All documents need to be closely reviewed by the construction manager

and appropriate owner personnel to decrease conflicts, and changes.

- With the contract documents are almost complete; a detailed and

complete cost estimate for the project can be done

The Project Life Cycle (Cont.)

Page 19: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 19

B. Procurement phase (Bidding and award phase)

-The project formally transits from design into construction.

-This stage begins with a public advertisement for all interested bidders .

-In fast-track projects, this phase overlaps with the design phase.

-If the project is phased, each work package will be advertised and bid out

individually.

- It is very important stage to select highly qualified contractors.

The Project Life Cycle (Cont.)

Page 20: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 20

C. Construction phase

-The actual physical construction of the project stage.

-This stage takes the project from procurement through the final

completion.

-It is the time where the bulk of the owner’s funds will be spent.

-It is the outcome of all previous stages (i.e., good preparation means

smooth construction).

- The consultant will be deployed for contract administration and

construction supervision.

- Changes during construction may hinder the progress of the project.

The Project Life Cycle (Cont.)

Page 21: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 21

D. Closeout phase

- Transition from design and construction to the actual use of the

constructed facility.

- The management team must provide documentation, shop drawings, as

built drawings, and operation manuals to the owner organization.

- Assessment of the project team’s performance is crucial in this stage

for avoiding mistakes in the future.

- Actual activity costs and durations should be recorded and compared

with that was planned.

The Project Life Cycle (Cont.)

Page 22: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 22

Page 23: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 23

Major Types of Construction Projects

1 .Residential Housing Construction:

Residential housing construction includes houses and high-rise apartments.

2. Institutional and Commercial Building Construction

such as schools and universities, medical centers and hospitals, sports

facilities, shopping centers, warehouses and light manufacturing plants,

and skyscrapers for offices and hotels.

3. Specialized Industrial Construction:Specialized industrial construction usually involves very large scale

projects with a high degree of technological complexity, such as

oil refineries, steel mills, chemical processing plants and coal-fired or

nuclear power plants.

4. Infrastructure and Heavy Construction:such as highways, tunnels, bridges, pipelines, drainage systems and

sewage treatment plants.

Page 24: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 24

Job Supervisors Subs

Owners

Corporate Managemen

t

Field Labor

DesignCenter

Sales & Marketing

Accounting

Scheduling

Purchasing Estimating

Local Municipalities

Banks & Mortgage Lendors

Manufacturers

Suppliers

RE Agents

Too Many Participants

Construction Project Participants

Page 25: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 25

Construction Project Participants

1. The Owner (The Client)

He is the individual or organization for whom a project is to be built under

a contract.

He owns and finances the project. Depending on the owners’ capabilities,

they may handle all or portions of planning, project management, design,

engineering, procurement, and construction.

Public owners Private owners

2. The Design Professionals

Architects, engineers, and design consultants.

The major role of the design professional is to interpret or assist the owner

in developing the project’s scope, budget, and schedule and to prepare

construction documents. Depending on the size and sophistication of the

owner.

Page 26: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 26

3. The Construction Professionals

They are the parties that responsible for constructing the project.

In traditional management where the owner, design professional, and contractors are separate companies, the contractor would be termed a prime contractor.

The prime contractor is responsible for delivering a complete project in accordance with the contract documents. In most

cases, the prime contractor divides the work among many specialty contractors called subcontractors as shown in Figure 1.4.

Construction Project Participants (Cont.)

Page 27: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 27

4. The Project Manager

Is the individual charged with the overall coordination of the entire

construction program for the owner.

These include planning, design, procurement, and construction. Among

his/her duties:

- Clear definitions of the goals of the project.

- Investigate alternative solutions for the problems.

- Develop a detailed plan to make the selected program reality.

-Implement the plan and control the project.

Construction Project Participants (Cont.)

Page 28: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 28

5. Construction Manager:

is a specialized firm or organization which administrates the on-site

erection activities and the consulting services required by the owner from

planning through design and construction to commissioning.

The construction manager is responsible for design coordination, proper

selection of materials and methods of construction, contracts preparation

for award, cost and scheduling information and control.

Construction Project Participants (Cont.)

Page 29: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 29

CONSTRUCTION INDUSTRY

Page 30: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 30

The Construction Team

The principal participants/key players in any construction project include:

The Owner

The Design Professional (Architect & Engineers)

The Contractor

Page 31: Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 2+3.

Project Planning & Control 31

The Construction Team

ARCHITECT CONTRACTOR

CONTRACT CONTRACT