Top Banner
Project Planning Class 7
24

Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Dec 26, 2015

Download

Documents

Aldous Morris
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Project Planning

Class 7

Page 2: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

SDLCProject Identification

& Selection

Project Initiation& Planning

***

Analysis

Logical Design

Physical Design

Implementation

Maintenance

Page 3: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Class today Project Planning in more depth

Define the problem Define the objectives Project Feasibility Produce the Project Schedule

Page 4: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Defining the Problem Concentrate on current system Provide enough information to

make it specific to your application.

Page 5: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Define Objectives Should match to most, if not all,

problems Why might objectives not cover all

problems?

Can be both quantitative and qualitative

Page 6: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Assessing Project Feasibility Economic Organizational and Cultural (or

Political) Technical Schedule Resource Operational Legal/contractual

Page 7: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Economic feasibility Identifying the financial benefits

and costs associated with the project (CBA)

At this point, probably do not know enough to complete in detail.

What can be done: list tangible and intangible costs and benefits.

Page 8: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Tangible benefits Can be measured in dollars and

with certainty. 1. 2. 3. 4.

Page 9: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Tangible Benefit Example Time spent finding invoices,

receipts, and orders… Assume person spends 10% of time

doing this Assume your new system will reduce

the time to 1% This represents a 9% reduction in time If person’s salary is $25,000/yr, then

savings is $2,250 ($25000 * .09)

Page 10: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.
Page 11: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Intangible benefits Difficult to assign dollar amount Customer-related, societal

1. 2. 3.

Page 12: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Costs Tangible

One-time costs Recurring costs

Intangible

Page 13: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.
Page 14: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.
Page 15: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.
Page 16: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Other Feasibility Analyses Organizational & Cultural (Political)

Technical

Page 17: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Other feasibility analyses Schedule

Resource

Page 18: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Other feasibility analyses Operational

Legal / Contractual

Page 19: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Staff the Project Covered in earlier class

Page 20: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Representing and Scheduling Project Plans Gantt Chart: graphical representation of

a project that shows each task activity as a horizontal bar.

Pert chart: A diagram that depicts project activities and their inter-relationships.

Critical path scheduling: a scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project.

Page 21: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Steps in Project Scheduling Identify phases/activities/tasks in

project (use SDLC as guide) Estimate the size of the task Determine sequence for identified

tasks Schedule tasks

Page 22: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Class Activity

A project has been defined to contain the following list of activities and tasks along with their required times for completion:

Page 23: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

ACTIVITY/task Time (weeks) Predecessors

ANALYSIS: 1 – collect requirements 2 - 2 – analyze processes 3 1 3 – analyze data 3 2DESIGN: 4 – design processes 7 2 5 – design data 6 2 6 – design screens 1 3,4 7 – design reports 5 4,5IMPLEMENTATION: 8 – program 4 6,7 9 – test and document 8 7 10 – install 2 8,9

Page 24: Project Planning Class 7. SDLC Project Identification & Selection Project Initiation & Planning *** Analysis Logical Design Physical Design Implementation.

Lab Using Microsoft PM to create a

project schedule (Gantt and PERT)