Jul 15, 2015
Progress Review
EV
PV
AC
SV
CV
ΔT
Cu
mu
lati
ve V
alu
es
Time
CV -ve indicates over-budget
+ve indicates under-budget
SV -ve indicates behind schedule
+ve indicates ahead of schedule
CPI Indicates INR_ worth of work has been
done for each Rupee spent.
SPI Indicates that the project is progressing
at _% of the rate originally planned.
Cost Variance (CV) Formula: CV= EV –AC
Schedule Variance (SV)
Formula: SV = EV – PV
Cost Performance Index (CPI)
Formula: CPI = EV/AC
Schedule Performance Index (SPI)
Formula: SPI = EV/PV
Item Formula Remark
Cost Variance (CV) EV –AC Negative value indicates over budget and positive
value indicates under budget
Schedule Variance (SV) EV – PV Negative value indicates behind schedule and positive
value indicates ahead of schedule
Cost Performance Index (CPI) EV / AC Lesser than one indicates over budget and greater
than one indicates under budget
Schedule Performance Index (SPI) EV / PV Lesser than one indicates behind schedule and greater
than one indicates ahead of schedule
Estimate at Completion (EAC) BAC / CPI Considering that the rate of spending remains the
same
AC + ETC Considering that the current estimate is fundamentally
flawed
AC + (BAC – EV) Considering atypical variances
AC + [(BAC – EV) / CPI] Considering typical variances
Estimate to Complete (ETC) EAC –AC Considering that the current estimate is fundamentally
flawed
BAC – EV Considering atypical variances
(BAC – EV) / CPI Considering typical variances
Variance at Completion (VAC) BAC – EAC Considering the status of the budget expected at the
end of the project
Financial Term Definition
Benefit Cost Ratio
(BCR)
Compares the benefits (revenues) to the costs of different options
Chart of Accounts Any numbering system used to monitor project costs by category (for example, labor, supplies, and materials)
Depreciation Reduced price of an asset over time attributable to deterioration, obsolescence, and impending retirement
Applies particularly to physical assets such as equipment and structures
Straight Line depreciation: Standard amount depreciating every year
Accelerated depreciation: Value depreciating at a faster rate, for example, Double Declining method and Sum of the
Years Digits
Internal Rate of Return
(IRR)
Rate at which the project inflows and project outflows are equal
Project with greatest IRR is generally selected
Net Present Value
(NPV)
Present value of the total benefits minus costs over many time periods
Investment is profitable for positive NPV
Project with greatest NPV is selected
Opportunity Cost Opportunity given up by selecting one project over another
Payback Period Time period it takes to recover the investment made in the project before the profits start accumulating
Present Value The current value of future cash flows.
Sunk Cost Expended costs, to be avoided when deciding whether to continue with a troubled project
THANKS